CN111709614A - Seven-step quality management method for pile foundation based on BIM model - Google Patents

Seven-step quality management method for pile foundation based on BIM model Download PDF

Info

Publication number
CN111709614A
CN111709614A CN202010460712.7A CN202010460712A CN111709614A CN 111709614 A CN111709614 A CN 111709614A CN 202010460712 A CN202010460712 A CN 202010460712A CN 111709614 A CN111709614 A CN 111709614A
Authority
CN
China
Prior art keywords
pile foundation
acceptance
quality
bim model
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010460712.7A
Other languages
Chinese (zh)
Inventor
贺新武
杨彪
葛建军
李通拉嘎
陈文龙
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
PowerChina Huadong Engineering Corp Ltd
Original Assignee
PowerChina Huadong Engineering Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by PowerChina Huadong Engineering Corp Ltd filed Critical PowerChina Huadong Engineering Corp Ltd
Priority to CN202010460712.7A priority Critical patent/CN111709614A/en
Publication of CN111709614A publication Critical patent/CN111709614A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • G06Q10/06395Quality analysis or management
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Health & Medical Sciences (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a seven-step quality management method of a pile foundation based on a BIM model, which comprises the following steps of: a construction manager logs in a pile foundation quality management APP to initiate a pile foundation quality acceptance flow form, fills the serial number of the pile foundation quality acceptance flow form, and transmits a pile foundation acceptance qualified photo to a corresponding acceptance stage and correspondingly notes; after the completion of filling in the acceptance stage in the pile foundation quality acceptance flow form, sequentially sending the pile foundation quality acceptance flow form to each unit auditor for auditing; if the auditor finds errors in the auditing process, the auditor can return, and the construction unit field quality manager modifies the errors and submits the audits again; and after the last auditor agrees, the pile foundation quality acceptance flow sheet is automatically associated to the pile foundation corresponding to the lightweight BIM model in the pile foundation quality management APP. The invention relates the quality acceptance process and the pile foundation BIM model, and realizes the dynamic management and visualization of pile foundation quality acceptance.

Description

Seven-step quality management method for pile foundation based on BIM model
Technical Field
The invention relates to a BIM model-based pile foundation engineering construction quality management method, which is mainly used for controlling pile foundation construction quality process in industries such as industrial and civil construction, railways, roads and the like and a system thereof.
Background
In the field of engineering construction, the management of pile foundation construction quality mainly adopts engineering field management personnel of supervision, construction units, owners, design units and other units to check and accept each link of pile foundation construction and form paper checking and accepting or rectification data, and later-stage arrangement and formation of filing data. Because the pile foundation quality control has more steps, each step needs to participate in each party for acceptance, paper data is formed for storage, the time and cost are increased, and the paper data are easily disordered and lost in the later storage process. Meanwhile, if a problem occurs in the project operation stage, the quality tracing difficulty is very high.
Although information technology is also used in the field of engineering construction in recent years, the depth and the width of the information technology in pile foundation engineering application are still limited, and the energy efficiency of pile foundation construction quality management cannot be effectively improved.
Disclosure of Invention
The invention aims to provide a seven-step quality management method for a pile foundation based on a BIM (building information modeling) model, aiming at the defects in the prior art.
For this reason, the above object of the present invention is achieved by the following technical solutions:
a seven-step quality management method of a pile foundation based on a BIM model is characterized by comprising the following steps of: the seven-step quality management method of the pile foundation based on the BIM model comprises the following steps of: construction manager logs in pile foundation quality control APP and initiates pile foundation quality acceptance flow form to fill in the serial number of pile foundation quality acceptance flow form, construction manager transmits pile foundation acceptance qualified photo to corresponding acceptance stage, and corresponding remark, and the acceptance stage includes: centering, rock entering, final hole forming, reinforcement cage manufacturing, reinforcement cage welding, secondary cleaning and primary irrigation; after the completion of filling in the acceptance stage in the pile foundation quality acceptance flow form, the pile foundation quality acceptance flow form is sequentially sent to auditors of all units for auditing, wherein: auditing personnel of each unit log in pile foundation quality management APP to fill in by default or a construction manager modifies the APP as required; if the auditor finds errors in the auditing process, the auditor can return, and the construction unit field quality manager modifies the errors and submits the audits again; after the approval of the final auditor, the pile foundation quality acceptance flow sheet is automatically associated to the corresponding pile foundation of the lightweight BIM model in the pile foundation quality management APP, and the pile number of the pile foundation and the serial number of the pile foundation quality acceptance flow sheet share the same serial number; the pile foundation quality management APP is a WeChat applet or APP software which is authorized to log in by WeChat.
While adopting the technical scheme, the invention can also adopt or combine the following technical scheme:
as a preferred technical scheme of the invention: the pile foundation quality acceptance flow form further comprises acceptance dates, task notification modes, filling persons, auditing units, responsible persons and processing opinions of the examination and approval links.
As a preferred technical scheme of the invention: the pile foundation quality management APP comprises a pile foundation quality acceptance flow form, a pile foundation BIM model, form data updated in real time and rectification data; the rectification data is provided after being audited by auditors of all units, and if errors are found in the auditing process, rectification and rectification are sent to form rectification data; the construction manager can change the pile foundation quality acceptance flow form in real time, the examination opinions proposed by an auditor before and after the change are form data updated in real time, and the pile foundation BIM model and the pile foundation quality acceptance flow form are in one-to-one correspondence, namely, after each pile foundation quality acceptance flow form is finished, when corresponding pile foundations in the BIM model are consulted, the examination acceptance and correction information attached to the pile foundations can be automatically inquired.
As a preferred technical scheme of the invention: the construction progress condition of a single pile or all pile foundations can be inquired and counted by an acceptance person or a person to be accepted through pile foundation quality management APP.
As a preferred technical scheme of the invention: pile foundation quality management APP is provided with a personnel management module for setting personnel permission, and the permission mainly comprises checking, task initiating, task forwarding, task modifying, task sending, counting and summarizing.
The invention provides a seven-step quality management method for a pile foundation based on a BIM model, which is characterized in that by means of BIM modeling software and an informatization technology, the quality of the pile foundation is inspected, developed and formed into a standard fixed form, APP is developed and formed and embedded into a WeChat platform, and management units such as construction units, owners, supervision, EPC general packages and the like can inspect and accept the pile foundation process through the APP embedded with WeChats, the inspection and acceptance process can be automatically notified through WeChats or mobile phone short messages, and the construction progress of the pile foundation can be inquired through a mobile platform. The method can realize remote supervision and management on the construction quality of the pile foundation engineering, the problems occurring in acceptance check of the pile foundation quality are rectified and closed through the WeChat mobile cloud platform, and dynamic supervision is realized on acceptance check or rectification of each stage of the pile foundation through virtual visualization. The method can realize the informatization management and control of the construction quality of the pile foundation engineering, the pile foundation quality has traceability, and the pressure of a data worker and the redundancy of the acceptance data are greatly reduced; the quality of the pile foundation is checked and accepted through the WeChat mobile cloud platform, so that the method is convenient, rapid and efficient; the quality acceptance process is associated with the pile foundation BIM model through the method, and the dynamic management and visualization of pile foundation quality acceptance are realized.
Drawings
Fig. 1 is a system schematic diagram of a seven-step quality management method for a pile foundation of a wechat mobile cloud platform based on a BIM model.
FIG. 2 is a diagram of an APP system framework for seven-step quality acceptance of pile foundations.
Fig. 3 is a schematic diagram of a seven-step quality acceptance form of a pile foundation.
Detailed Description
Specific examples of the invention are described in detail below, with systems and interfaces as shown in the figures. The present invention is intended to be illustrative, and not to be construed as being limited thereto.
As shown in fig. 1-3, in this example, the adopted pile foundation seven-step quality management APP utilizes an information technology and a lightweight BIM model, and by embedding a wechat mobile cloud platform, is simple in operation, convenient in communication, high in acceptance check efficiency, time-saving and labor-saving, and has obvious advantages.
In the embodiment, when a login person logs in for the first time, the pile foundation quality management APP is opened through the WeChat mobile cloud platform, the APP software needs to be logged in by using WeChat authorization, and a system management person can check and file according to the role of the login person. After the administrator authorizes the system, the system can log in. Because the login is authorized by using the WeChat and the backstage manager can check, the login caliber is relatively unique.
In this example, the pile foundation seven-step quality acceptance form flow is as follows:
the construction site can inform all parties of checking and accepting through the WeChat group and the telephone after the three-level inspection is finished;
1) the method comprises the steps that all parties participate in field acceptance and acceptance of organization, an administrator logs in a pile foundation quality management APP to initiate a pile foundation quality acceptance flow form and fills in a serial number, acceptance time, an auditor, filling time and the like can be automatically generated, the administrator only needs to transmit a pile foundation acceptance picture to a corresponding stage, for example, a pile foundation centering stage, the acceptance picture in pile foundation centering is transmitted, the picture is stored after transmission is completed, a remark column is arranged on the left side of each picture column, for example, the conditions of quality problems, pouring disconnection and the like exist, but the conditions of acceptance after final rectification and the like can be filled in.
2) After the filling is completed, a filler clicks to store, the operations are repeated in seven acceptance steps of centering, rock entering, final hole, reinforcement cage manufacturing, reinforcement cage welding, secondary cleaning and primary filling in sequence, after the filling of a final primary filling form is completed, the form can be automatically changed from the original storage into a button for submitting, storing and canceling, and an EPC general packet unit auditor, a supervision unit auditor, a design unit auditor and an owner unit auditor appear in sequence on the auditor, a system can automatically fill a default auditor, and if modification is needed, only clicking in is needed, and a corresponding person is selected; if a unit is considered not to be checked, the unit may not be selected.
3) After the acceptance examiner submits, the acceptance examiner submits the information according to the auditors of the units filled in the form in sequence, the informing mode in the form can select WeChat informing and short message informing, the auditor reviews the submitted pictures and character records after receiving the informing, if agreeing, the form can be automatically submitted to the next auditor, and the paper auditing is completed. Or if the auditor finds errors in the auditing process, the auditor can return to the operation, and the construction unit can submit the errors again after the quality manager on site modifies the errors.
4) And after the last auditor agrees, the form approval process is finished, the form can be automatically associated to the corresponding pile foundation of the lightweight BIM model in the APP software, the form and the lightweight BIM model are associated through the pile number, the pile number is set according to the design drawing number, and the process is finished when the lightweight BIM model is built.
The inspection person or the inspected person can inquire and count the construction progress of a single pile or all pile foundations;
the pile foundation seven-step quality acceptance list and the pile foundation summary list can respectively generate acceptance data in PDF and word formats.
The personnel permission in the pile foundation quality acceptance APP mainly comprises checking, task initiating, task forwarding, task modifying, task sending, counting, summarizing and the like.
Data uploading and updating can be safely stored in the cloud server, data query is conducted through the safety interface, and the whole process is conducted in a safe and controllable range. The cloud server can store, receive, send, modify and the like data.
The method can realize the informatization management and control of the construction quality of the pile foundation engineering, the pile foundation quality has traceability, and the pressure of a data worker and the redundancy of the acceptance data are greatly reduced; the quality of the pile foundation is checked and accepted through the WeChat mobile cloud platform, so that the method is convenient, rapid and efficient; the quality acceptance process is associated with the pile foundation BIM model through the method, and the dynamic management and visualization of pile foundation quality acceptance are realized.
Although the above embodiments describe the present invention in detail, it is only a part of the embodiments of the present invention, not all embodiments, and one can also obtain other embodiments without inventive step according to the present embodiment, and these embodiments all belong to the protection scope of the present invention.

Claims (5)

1. A seven-step quality management method of a pile foundation based on a BIM model is characterized by comprising the following steps of: the seven-step quality management method of the pile foundation based on the BIM model comprises the following steps of: construction manager logs in pile foundation quality control APP and initiates pile foundation quality acceptance flow form to fill in the serial number of pile foundation quality acceptance flow form, construction manager transmits pile foundation acceptance qualified photo to corresponding acceptance stage, and corresponding remark, and the acceptance stage includes: centering, rock entering, final hole forming, reinforcement cage manufacturing, reinforcement cage welding, secondary cleaning and primary irrigation; after the completion of filling in the acceptance stage in the pile foundation quality acceptance flow form, the pile foundation quality acceptance flow form is sequentially sent to auditors of all units for auditing, wherein: auditing personnel of each unit log in pile foundation quality management APP to fill in by default or a construction manager modifies the APP as required; if the auditor finds errors in the auditing process, the auditor can return, and the construction unit field quality manager modifies the errors and submits the audits again; after the approval of the final auditor, the pile foundation quality acceptance flow sheet is automatically associated to the corresponding pile foundation of the lightweight BIM model in the pile foundation quality management APP, and the pile number of the pile foundation and the serial number of the pile foundation quality acceptance flow sheet share the same serial number; the pile foundation quality management APP is a WeChat applet or APP software which is authorized to log in by WeChat.
2. The seven-step quality management method for the pile foundation based on the BIM model according to claim 1, characterized in that: the pile foundation quality acceptance flow form further comprises acceptance dates, task notification modes, filling persons, auditing units, responsible persons and processing opinions of the examination and approval links.
3. The seven-step quality management method for the pile foundation based on the BIM model according to claim 1, characterized in that: pile foundation quality control APP includes pile foundation quality acceptance flow form, pile foundation BIM model, real-time update's form data, rectification data, and pile foundation BIM model and pile foundation quality acceptance flow form are the one-to-one, and when each pile foundation quality acceptance flow form was accomplished, when looking up the corresponding pile foundation in the BIM model, can inquire the acceptance, rectification information of attaching this pile foundation automatically.
4. The seven-step quality management method for the pile foundation based on the BIM model according to claim 1, characterized in that: the construction progress condition of a single pile or all pile foundations can be inquired and counted by an acceptance person or a person to be accepted through pile foundation quality management APP.
5. The seven-step quality management method for the pile foundation based on the BIM model according to claim 1, characterized in that: pile foundation quality management APP is provided with a personnel management module for setting personnel permission, and the permission mainly comprises checking, task initiating, task forwarding, task modifying, task sending, counting and summarizing.
CN202010460712.7A 2020-05-27 2020-05-27 Seven-step quality management method for pile foundation based on BIM model Pending CN111709614A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010460712.7A CN111709614A (en) 2020-05-27 2020-05-27 Seven-step quality management method for pile foundation based on BIM model

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010460712.7A CN111709614A (en) 2020-05-27 2020-05-27 Seven-step quality management method for pile foundation based on BIM model

Publications (1)

Publication Number Publication Date
CN111709614A true CN111709614A (en) 2020-09-25

Family

ID=72538375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010460712.7A Pending CN111709614A (en) 2020-05-27 2020-05-27 Seven-step quality management method for pile foundation based on BIM model

Country Status (1)

Country Link
CN (1) CN111709614A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113159248A (en) * 2021-04-28 2021-07-23 温州开晨科技有限公司 Pile foundation construction management method and system based on two-dimensional code
CN113469840A (en) * 2021-06-16 2021-10-01 浙江华东建设工程有限公司 Intelligent management system for pile foundation construction

Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106096851A (en) * 2016-06-21 2016-11-09 浙江精工钢结构集团有限公司 A kind of structural steelwork based on BIM technology visualization acceptance method
CN109555116A (en) * 2018-11-08 2019-04-02 广东省第建筑工程有限公司 A kind of high density karst intense development area fully-sleeved filled pile construction method

Patent Citations (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106096851A (en) * 2016-06-21 2016-11-09 浙江精工钢结构集团有限公司 A kind of structural steelwork based on BIM technology visualization acceptance method
CN109555116A (en) * 2018-11-08 2019-04-02 广东省第建筑工程有限公司 A kind of high density karst intense development area fully-sleeved filled pile construction method

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113159248A (en) * 2021-04-28 2021-07-23 温州开晨科技有限公司 Pile foundation construction management method and system based on two-dimensional code
CN113469840A (en) * 2021-06-16 2021-10-01 浙江华东建设工程有限公司 Intelligent management system for pile foundation construction

Similar Documents

Publication Publication Date Title
CN111709614A (en) Seven-step quality management method for pile foundation based on BIM model
US9384231B2 (en) Data lineage management operation procedures
CN106330575A (en) Safety service platform and safety service deployment method
CN108322475A (en) A kind of equipment remote collaboration method for maintaining and system based on MR live streamings
CN105868369A (en) Data model verification system and method based on Merkle tree structure
CN104951524B (en) A kind of mobile platform and its application method for database O&M
CN109345195A (en) A kind of project supervision monitoring and managing method and system based on BIM
CN103761598A (en) Enterprise information centralized collection processing method and system
CN111126530A (en) Ann lamp control system based on WeChat
CN103426041A (en) Radiation source real-time monitoring and managing system and method based on Internet of things
CN115860410A (en) WeChat-based large civil engineering construction potential safety hazard management system
CN103543709A (en) Environmental pollution monitoring and managing system of construction site
CN202421839U (en) Monitoring center for engineering machinery remote monitoring system
CN102480383B (en) A kind of log information message processing method and device
CN113763207A (en) Mobile data acquisition system based on Internet
CN105718602B (en) Standard cloud system for safe production of rural hydropower station
CN108153621B (en) Cloud disaster backup emergency switching management system
KR102411460B1 (en) System and Method for verifying vessel design drawings
CN108647905A (en) A kind of highway electromechanics operation management system and management method
CN110929331A (en) Block chain-based distributed building information modeling management system
CN110889763B (en) Financial management system based on big data
JP2007279993A (en) Quality management method by construction inspection
CN112184068B (en) Highway engineering project information collaboration method based on ERP
CN109886528A (en) A method of management control is executed for manufacturing
CN204873310U (en) Elevator safety inspection intelligent terminal system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination