CN111709070A - 基于Autodesk Revit软件的BIM模型快速变更方法 - Google Patents
基于Autodesk Revit软件的BIM模型快速变更方法 Download PDFInfo
- Publication number
- CN111709070A CN111709070A CN202010452356.4A CN202010452356A CN111709070A CN 111709070 A CN111709070 A CN 111709070A CN 202010452356 A CN202010452356 A CN 202010452356A CN 111709070 A CN111709070 A CN 111709070A
- Authority
- CN
- China
- Prior art keywords
- model
- change
- bim
- engineering
- revit software
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/10—Geometric CAD
- G06F30/13—Architectural design, e.g. computer-aided architectural design [CAAD] related to design of buildings, bridges, landscapes, production plants or roads
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06F—ELECTRIC DIGITAL DATA PROCESSING
- G06F30/00—Computer-aided design [CAD]
- G06F30/20—Design optimisation, verification or simulation
-
- G—PHYSICS
- G06—COMPUTING; CALCULATING OR COUNTING
- G06T—IMAGE DATA PROCESSING OR GENERATION, IN GENERAL
- G06T19/00—Manipulating 3D models or images for computer graphics
- G06T19/20—Editing of 3D images, e.g. changing shapes or colours, aligning objects or positioning parts
Landscapes
- Engineering & Computer Science (AREA)
- Physics & Mathematics (AREA)
- Theoretical Computer Science (AREA)
- Geometry (AREA)
- Computer Hardware Design (AREA)
- General Physics & Mathematics (AREA)
- General Engineering & Computer Science (AREA)
- Architecture (AREA)
- Evolutionary Computation (AREA)
- Software Systems (AREA)
- Computer Graphics (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Computational Mathematics (AREA)
- Mathematical Analysis (AREA)
- Mathematical Optimization (AREA)
- Pure & Applied Mathematics (AREA)
- Stored Programmes (AREA)
Abstract
本发明公开了一种基于Autodesk Revit软件的BIM模型快速变更方法,针对变电站工程基于Autodesk Revit软件的BIM模型,通过建立项目样板、企业族库、企业实施标准,实现工程变更信息的半自动化处理;即在模型上进行变更内容的体现的同时,直接基于Revit平台得出变更所产生的工程量、成本、进度的变化。本发明方法简便、效果好。
Description
技术领域
本发明涉及一种BIM模型快速变更方法。
背景技术
2017年全国基建行业已有超过90%的项目应用BIM技术,民建项目有超过80%应用BIM技术;BIM技术在国内的迅速发展使得项目各方的迅速反应显得刻不容缓。
对于项目变更的传统处理方式是通过手动变更BIM模型及相关参数设置来计算及处理变更的影响结果,这样的变更更新方式仅能在模型中体现出设计方案样式、外观的改变,无法体现出方案变更所带来的成本、进度等各方面的影响。
对于项目变更的传统处理方式是通过手动变更BIM模型及相关参数设置来计算及处理变更的影响结果,这样的变更更新方式仅能在模型中体现出设计方案样式、外观的改变,无法体现出方案变更所带来的成本、进度等各方面的影响。
发明内容
本发明的目的在于提供一种方法简便、效果好的基于Autodesk Revit软件的BIM模型快速变更方法。
本发明的技术解决方案是:
一种基于Autodesk Revit软件的BIM模型快速变更方法,其特征是:针对变电站工程基于Autodesk Revit软件的BIM模型,通过建立项目样板、企业族库、企业实施标准,实现工程变更信息的半自动化处理;即在模型上进行变更内容的体现的同时,直接基于Revit平台得出变更所产生的工程量、成本、进度的变化。
具体流程:对设计模型依次进行拓扑解析、补充信息误差校正、造体、相似图元合并处理,在通过BIM模型进行三角化处理,并进一步经渲染数据、场景组织空间索引、遮挡剔除、渲染队列排序、批量绘制处理。
本发明方法简便、效果好。
附图说明
下面结合附图和实施例对本发明作进一步说明。
图1是本发明一个实施例的工作流程示意图。
具体实施方式
一种基于Autodesk Revit软件的BIM模型快速变更方法,针对变电站工程基于Autodesk Revit软件的BIM模型,通过建立项目样板、企业族库、企业实施标准,实现工程变更信息的半自动化处理;即在模型上进行变更内容的体现的同时,直接基于Revit平台得出变更所产生的工程量、成本、进度的变化。
具体流程:对设计模型依次进行拓扑解析、补充信息误差校正、造体、相似图元合并处理,在通过BIM模型进行三角化处理,并进一步经渲染数据、场景组织空间索引、遮挡剔除、渲染队列排序、批量绘制处理。
Claims (2)
1. 一种基于Autodesk Revit软件的BIM模型快速变更方法,其特征是:针对变电站工程基于Autodesk Revit软件的BIM模型,通过建立项目样板、企业族库、企业实施标准,实现工程变更信息的半自动化处理;即在模型上进行变更内容的体现的同时,直接基于Revit平台得出变更所产生的工程量、成本、进度的变化。
2. 根据权利要求1所述的基于Autodesk Revit软件的BIM模型快速变更方法,其特征是:具体流程:对设计模型依次进行拓扑解析、补充信息误差校正、造体、相似图元合并处理,在通过BIM模型进行三角化处理,并进一步经渲染数据、场景组织空间索引、遮挡剔除、渲染队列排序、批量绘制处理。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010452356.4A CN111709070A (zh) | 2020-05-26 | 2020-05-26 | 基于Autodesk Revit软件的BIM模型快速变更方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010452356.4A CN111709070A (zh) | 2020-05-26 | 2020-05-26 | 基于Autodesk Revit软件的BIM模型快速变更方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111709070A true CN111709070A (zh) | 2020-09-25 |
Family
ID=72537732
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010452356.4A Pending CN111709070A (zh) | 2020-05-26 | 2020-05-26 | 基于Autodesk Revit软件的BIM模型快速变更方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111709070A (zh) |
Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107038603A (zh) * | 2017-03-17 | 2017-08-11 | 东易日盛家居装饰集团股份有限公司 | 一种基于bim软件的工程报价生成方法及系统 |
CN107194824A (zh) * | 2017-05-08 | 2017-09-22 | 中车青岛四方机车车辆股份有限公司 | 工程数据的变更方法和装置 |
CN107958357A (zh) * | 2018-01-22 | 2018-04-24 | 东华理工大学 | 一种bim项目的成本管理系统 |
CN109447481A (zh) * | 2018-10-31 | 2019-03-08 | 广西路桥工程集团有限公司 | 一种基于三维模型的现场成本监控系统及方法 |
CN110705853A (zh) * | 2019-09-20 | 2020-01-17 | 国网上海市电力公司 | 一种基于bim模型的变电站成本动态管控系统及方法 |
-
2020
- 2020-05-26 CN CN202010452356.4A patent/CN111709070A/zh active Pending
Patent Citations (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN107038603A (zh) * | 2017-03-17 | 2017-08-11 | 东易日盛家居装饰集团股份有限公司 | 一种基于bim软件的工程报价生成方法及系统 |
CN107194824A (zh) * | 2017-05-08 | 2017-09-22 | 中车青岛四方机车车辆股份有限公司 | 工程数据的变更方法和装置 |
CN107958357A (zh) * | 2018-01-22 | 2018-04-24 | 东华理工大学 | 一种bim项目的成本管理系统 |
CN109447481A (zh) * | 2018-10-31 | 2019-03-08 | 广西路桥工程集团有限公司 | 一种基于三维模型的现场成本监控系统及方法 |
CN110705853A (zh) * | 2019-09-20 | 2020-01-17 | 国网上海市电力公司 | 一种基于bim模型的变电站成本动态管控系统及方法 |
Non-Patent Citations (4)
Title |
---|
么远: ""基于BIM的变电工程造价快速估算方法研究"", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
刘睿 等: ""BIM在变电站项目工程造价中的应用"", 《工程造价管理》 * |
刘素琴: ""BIM技术在工程变更管理中设计阶段的应用研究"", 《中国优秀硕士学位论文全文数据库 工程科技Ⅱ辑》 * |
王志伟 等: ""基于轻量化BIM、RFID技术与ERP系统的预制装配式隧道结构智能建造系统 "", 《中国铁路》 * |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN106600700B (zh) | 一种三维模型数据处理系统 | |
CN107229790B (zh) | 生成三维、二维图形的桥梁结构信息模型系统及使用方法 | |
CN110362887A (zh) | 一种基于Revit的快速建模方法 | |
CN110765510A (zh) | 一种基于bim技术的建筑设计制图系统及其制图方法 | |
CN111310278A (zh) | 一种基于仿真的船舶自动化建模方法 | |
CN109086495A (zh) | Bim出精装施工图的方法 | |
WO2024045615A1 (zh) | 一种管道三维建筑信息模型的自动化标注方法及系统 | |
KR20030073424A (ko) | 렌더링시스템, 렌더링방법 및 그 기록매체 | |
CN112163264B (zh) | 基于bim的假山模块化施工方法、装置及存储介质 | |
CN109388812B (zh) | 一种基于云计算的模块化自动出图方法及系统 | |
CN111709070A (zh) | 基于Autodesk Revit软件的BIM模型快速变更方法 | |
CN112396681A (zh) | 一种动画生成方法、装置和存储介质 | |
CN105956346A (zh) | 一种铝合金模板设计系统和方法 | |
CN115115787A (zh) | 一种基于DirectVR的二维图纸转3D模型方法 | |
CN111177866B (zh) | 一种基于smooth t和matlab的涡轮特性处理方法 | |
CN113971302A (zh) | 一种钢结构桥梁验证方法及演示方法 | |
CN111179420B (zh) | 一种三维城市模型优化方法及系统 | |
CN112966058A (zh) | 一种基于构件级管理的bim模型lod加载与应用方法 | |
CN107633543B (zh) | 考虑局部拓扑结构的线条形状对应方法 | |
JP2008287300A (ja) | 設計支援装置 | |
CN111179422A (zh) | 一种模型构建方法、装置及终端设备 | |
JP2012128609A (ja) | 図面作成支援方法及び装置 | |
CN103645899A (zh) | 一种将cad中设计数据集成到erp系统的方法 | |
CN117371094A (zh) | 一种基于bim的空间钢结构建模方法 | |
CN115393546A (zh) | 一种bim模型分拆展示的方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200925 |