CN111653955A - A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations - Google Patents

A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations Download PDF

Info

Publication number
CN111653955A
CN111653955A CN202010434859.9A CN202010434859A CN111653955A CN 111653955 A CN111653955 A CN 111653955A CN 202010434859 A CN202010434859 A CN 202010434859A CN 111653955 A CN111653955 A CN 111653955A
Authority
CN
China
Prior art keywords
base
substation
realizing
construction method
installation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010434859.9A
Other languages
Chinese (zh)
Other versions
CN111653955B (en
Inventor
黄正丹
严祥武
吴建新
申腾
陈敏捷
曾峥
丁傲
赵渐进
喻祥喜
彭川
杨乘
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xiaogan Kexian Electric Power Co ltd
Original Assignee
Xiaogan Kexian Electric Power Engineering Consulting Design Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xiaogan Kexian Electric Power Engineering Consulting Design Co ltd filed Critical Xiaogan Kexian Electric Power Engineering Consulting Design Co ltd
Priority to CN202010434859.9A priority Critical patent/CN111653955B/en
Publication of CN111653955A publication Critical patent/CN111653955A/en
Application granted granted Critical
Publication of CN111653955B publication Critical patent/CN111653955B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/26Casings; Parts thereof or accessories therefor
    • H02B1/50Pedestal- or pad-mounted casings; Parts thereof or accessories therefor
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02BBOARDS, SUBSTATIONS OR SWITCHING ARRANGEMENTS FOR THE SUPPLY OR DISTRIBUTION OF ELECTRIC POWER
    • H02B1/00Frameworks, boards, panels, desks, casings; Details of substations or switching arrangements
    • H02B1/26Casings; Parts thereof or accessories therefor
    • H02B1/30Cabinet-type casings; Parts thereof or accessories therefor
    • H02B1/303Bases or feet

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Foundations (AREA)

Abstract

本发明涉及电力设备技术领域,具体地说,涉及一种实现变电站二次屏柜安装基础的快速施工方法,具体包括如下步骤:S1开槽→S2制备混凝土→S3浇注混凝土→组装底座→S5安装底座→S6安装变电站二次屏柜。本发明中通过开挖0.4m深的底座固定槽以及在槽内安装用于固定变电站二次屏柜的底部,不仅加快土建施工的进度和降低施工难度,还达到了节约成本的目标,提高二次屏柜底座安装施工效率,降低工作强度,缩短土建施工时间施工成本,节约资源,增加电网运行的可靠性,通过调节微调螺栓的相对位置,改变螺帽的相对高度,从而实现可调高度的功能,可以将底座的各个水平高度进行统一,使得结构更加稳定。

Figure 202010434859

The invention relates to the technical field of electric power equipment, in particular to a rapid construction method for realizing the installation foundation of secondary screen cabinets in substations, which specifically includes the following steps: S1 grooving → S2 preparing concrete → S3 pouring concrete → assembling base → S5 installation Base → S6 to install the secondary panel cabinet of the substation. In the present invention, by excavating a 0.4m deep base fixing groove and installing the bottom of the substation secondary screen cabinet in the groove, it not only speeds up the progress of civil construction and reduces the difficulty of construction, but also achieves the goal of saving costs and improves the two The installation and construction efficiency of the base of the secondary screen cabinet reduces the work intensity, shortens the civil construction time and construction cost, saves resources, and increases the reliability of the power grid operation. Function, can unify the various levels of the base, making the structure more stable.

Figure 202010434859

Description

一种实现变电站二次屏柜安装基础的快速施工方法A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations

技术领域technical field

本发明涉及电力设备技术领域,具体为一种实现变电站二次屏柜安装基础的快速施工方法。The invention relates to the technical field of electric power equipment, in particular to a rapid construction method for realizing the installation foundation of a secondary screen cabinet of a substation.

背景技术Background technique

安装二次控制屏(柜)采用预留基坑的方法需开挖原有地基,并预留足够的空间,以便电气设备通过电缆可以安全互相连接,同时对原有安装基础不产生影响。然而,在主控室有限的空间内开挖1.2m深的基坑,并且在不影响原有设备基础稳定性的前提下,采用现有制作底座基础的方法其施工难度较大,从而导致施工进度较慢。地基开挖过程中,土方的开挖量较大,产生的弃土外运工作较难展开。To install the secondary control panel (cabinet), the method of reserving the foundation pit requires excavating the original foundation and reserving enough space so that the electrical equipment can be safely connected to each other through cables, and at the same time, the original installation foundation will not be affected. However, excavating a foundation pit with a depth of 1.2m in the limited space of the main control room, and on the premise of not affecting the stability of the original equipment foundation, the existing method of making the base foundation is difficult to construct, resulting in construction Progress is slow. In the process of foundation excavation, the amount of earthwork excavation is large, and it is difficult to carry out the transport of the generated spoil.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于提供一种实现变电站二次屏柜安装基础的快速施工方法,以解决上述背景技术中提出现如今安装二次控制屏的工作量大,施工速度慢的问题。The purpose of the present invention is to provide a fast construction method for realizing the installation foundation of the secondary panel cabinet of the substation, so as to solve the problems of the heavy workload and slow construction speed of the installation of the secondary control panel in the above-mentioned background art.

为实现上述目的,本发明提供如下技术方案:To achieve the above object, the present invention provides the following technical solutions:

一种实现变电站二次屏柜安装基础的快速施工方法,具体包括如下步骤:A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations, specifically comprising the following steps:

S1开槽:选取变电站二次屏柜的安装位置,在选定位置开挖用于安装变电站二次屏柜底座的基坑,并对边角处进行修正;S1 Slotting: Select the installation position of the secondary screen cabinet of the substation, excavate the foundation pit for installing the base of the secondary screen cabinet of the substation at the selected position, and correct the corners;

S2制备混凝土:现场制作C20混凝土,每100g原料需拌水12g,人工振捣约10min,直至混凝土具有流动性;S2 Preparation of concrete: C20 concrete is produced on site, 12g of water should be mixed with every 100g of raw materials, and it should be vibrated manually for about 10min until the concrete has fluidity;

S3浇注混凝土:在挖取的基坑内浇注混凝土浆料,且混凝土的强度为35-50%;S3 pouring concrete: pouring concrete slurry in the excavated foundation pit, and the strength of the concrete is 35-50%;

S4组装底座:将用于安装变电站二次屏柜底座对各种原料进行拼接,并对其表面进行镀锌处理;S4 assembly base: the base used to install the secondary panel cabinet of the substation will be spliced with various raw materials, and the surface will be galvanized;

S5安装底座:待混凝土凝固成型后,将拼接后的底座安装于浇注混凝土顶部,并通过底座上的可升降支撑机构对底座的各个边角的位置进行调整,使得底座的顶面为水平;S5 installation base: After the concrete is solidified and formed, the spliced base is installed on the top of the poured concrete, and the position of each corner of the base is adjusted through the liftable support mechanism on the base, so that the top surface of the base is horizontal;

S6安装变电站二次屏柜:将变电站二次屏柜移动至底座上进行固定。S6 Install the secondary screen cabinet of the substation: Move the secondary screen cabinet of the substation to the base for fixing.

作为优选,所述基坑的深度为0.4m,且基坑的底面积与底座的占地面积相同。Preferably, the depth of the foundation pit is 0.4m, and the bottom area of the foundation pit is the same as the footprint of the base.

作为优选,所述底座包括两组平行设置的横梁和两组平行设置的纵梁,两组横梁与两组纵梁组成长方形结构,两组所述横梁的底部均安装有两个平行设置的可升降支撑机构,所述可升降支撑机构包括支撑腿,所述支撑腿上安装有螺栓固定片,所述螺栓固定片的中心处开设有安装螺孔,所述安装螺孔内螺纹连接有微调螺栓,所述微调螺栓上螺纹连接有第一螺母和第二螺母,所述第一螺母和第二螺母分别设置于螺栓固定片的上下两侧。Preferably, the base includes two sets of parallel beams and two sets of parallel beams, the two sets of beams and the two sets of longitudinal beams form a rectangular structure, and the bottoms of the two sets of beams are installed with two parallel adjustable beams. Lifting support mechanism, the liftable support mechanism includes a support leg, a bolt fixing sheet is installed on the support leg, a mounting screw hole is opened at the center of the bolt fixing sheet, and the inner thread of the mounting screw hole is connected with a fine-tuning bolt A first nut and a second nut are threaded on the fine adjustment bolt, and the first nut and the second nut are respectively arranged on the upper and lower sides of the bolt fixing plate.

作为优选,所述支撑腿的顶部安装有顶座,所述顶座的两端边缘部开设有安装孔,所述横梁的底面开设有与所述安装孔尺寸相适配、位置相对应且数量相同的连接螺孔。Preferably, a top seat is installed on the top of the support leg, mounting holes are provided on the edges of both ends of the top seat, and the bottom surface of the beam is provided with a size, corresponding position and number of the mounting holes. The same connection screw holes.

作为优选,所述支撑腿通过固定螺栓依次穿过安装孔和连接螺孔螺纹连接于所述横梁底部。Preferably, the support legs are threadedly connected to the bottom of the beam by fixing bolts through the mounting holes and the connecting screw holes in sequence.

作为优选,所述横梁、纵梁以及支撑腿均采用角钢制成,且角钢的厚度为5mm。Preferably, the beams, the longitudinal beams and the supporting legs are all made of angle steel, and the thickness of the angle steel is 5 mm.

作为优选,所述横梁的长度为800mm,所述纵梁的长度为400mm,所述支撑腿的长度为150mm。Preferably, the length of the cross beam is 800mm, the length of the longitudinal beam is 400mm, and the length of the support leg is 150mm.

作为优选,所述微调螺栓的长度为90mm,第一螺母和第二螺母的厚度为15mm,螺帽的厚度为15mm。Preferably, the length of the fine adjustment bolt is 90mm, the thickness of the first nut and the second nut is 15mm, and the thickness of the nut is 15mm.

作为优选,所述微调螺栓的底端为光螺杆,其长度为10mm。Preferably, the bottom end of the fine adjustment bolt is a light screw, and its length is 10mm.

与现有技术相比,本发明的有益效果是:Compared with the prior art, the beneficial effects of the present invention are:

1、本实现变电站二次屏柜安装基础的快速施工方法中通过开挖0.4m深的底座固定槽以及在槽内安装用于固定变电站二次屏柜的底部,不仅加快土建施工的进度和降低施工难度,还达到了节约成本的目标,提高二次屏柜底座安装施工效率,降低工作强度,缩短土建施工时间施工成本,节约资源,增加电网运行的可靠性。1. In this fast construction method for realizing the installation foundation of the secondary screen cabinet of the substation, by excavating a base fixing groove with a depth of 0.4m and installing the bottom of the secondary screen cabinet in the substation to fix the bottom of the substation, it not only speeds up the progress of civil construction and reduces the The difficulty of construction has also achieved the goal of saving costs, improving the construction efficiency of the installation of the base of the secondary screen cabinet, reducing the work intensity, shortening the construction cost of civil construction, saving resources and increasing the reliability of power grid operation.

2、本实现变电站二次屏柜安装基础的快速施工方法中通过设置的可升降支撑机构,结构简单,设计合理,通过调节微调螺栓的相对位置,改变螺帽的相对高度,从而实现可调高度的功能,可以将底座的各个水平高度进行统一,焊接在槽钢底部的螺母具有固定作用,减小螺杆与底座支撑的移动,使得结构更加稳定。2. The lifting and lowering support mechanism provided in the rapid construction method for realizing the installation foundation of the secondary screen cabinet of the substation has a simple structure and a reasonable design. By adjusting the relative position of the fine-tuning bolt, the relative height of the nut is changed, so as to realize the adjustable height It can unify the various levels of the base, and the nut welded on the bottom of the channel steel has a fixed function, reducing the movement of the screw and the base support, making the structure more stable.

附图说明Description of drawings

图1是本发明底座的结构示意图;Fig. 1 is the structural representation of the base of the present invention;

图2是本发明横梁的分解结构示意图;Fig. 2 is the exploded structure schematic diagram of the beam of the present invention;

图中各标号的定义为:The definitions of the symbols in the figure are:

100、横梁;101、安装螺孔;100. Beam; 101. Mounting screw holes;

200、纵梁;200, longitudinal beam;

300、可升降支撑机构;301、支撑腿;302、连接顶座;303、安装孔;304、螺栓固定片;305、安装螺孔;306、微调螺栓;307、第一螺母;308、第二螺母。300, liftable support mechanism; 301, support leg; 302, connecting top seat; 303, mounting hole; 304, bolt fixing plate; 305, mounting screw hole; 306, fine adjustment bolt; 307, first nut; 308, second nut.

具体实施方式Detailed ways

下面将结合本发明实施例,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其他实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, rather than all the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.

在本发明的描述中,需要理解的是,术语“中心”、“纵向”、“横向”、“长度”、“宽度”、“厚度”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”、“顺时针”、“逆时针”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的设备或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", " rear, left, right, vertical, horizontal, top, bottom, inside, outside, clockwise, counterclockwise, etc., or The positional relationship is based on the orientation or positional relationship shown in the drawings, which is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying that the referred device or element must have a specific orientation, be constructed and operated in a specific orientation, Therefore, it should not be construed as a limitation of the present invention.

实施例1Example 1

一种实现变电站二次屏柜安装基础的快速施工方法,具体包括如下步骤:A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations, specifically comprising the following steps:

S1开槽:选取变电站二次屏柜的安装位置,在选定位置开挖用于安装变电站二次屏柜底座的基坑,并对边角处进行修正;S1 Slotting: Select the installation position of the secondary screen cabinet of the substation, excavate the foundation pit for installing the base of the secondary screen cabinet of the substation at the selected position, and correct the corners;

S2制备混凝土:现场制作C20混凝土,每100g原料需拌水12g,人工振捣约10min,直至混凝土具有流动性;S2 Preparation of concrete: C20 concrete is produced on site, 12g of water should be mixed with every 100g of raw materials, and it should be vibrated manually for about 10min until the concrete has fluidity;

S3浇注混凝土:在挖取的基坑内浇注混凝土浆料,且混凝土的强度为35-50%;S3 pouring concrete: pouring concrete slurry in the excavated foundation pit, and the strength of the concrete is 35-50%;

S4组装底座:将用于安装变电站二次屏柜底座对各种原料进行拼接,并对其表面进行镀锌处理;S4 assembly base: the base used to install the secondary panel cabinet of the substation will be spliced with various raw materials, and the surface will be galvanized;

S5安装底座:待混凝土凝固成型后,将拼接后的底座安装于浇注混凝土顶部,并通过底座上的可升降支撑机构对底座的各个边角的位置进行调整,使得底座的顶面为水平;S5 installation base: After the concrete is solidified and formed, the spliced base is installed on the top of the poured concrete, and the position of each corner of the base is adjusted through the liftable support mechanism on the base, so that the top surface of the base is horizontal;

S6安装变电站二次屏柜:将变电站二次屏柜移动至底座上进行固定。S6 Install the secondary screen cabinet of the substation: Move the secondary screen cabinet of the substation to the base for fixing.

进一步的,基坑的深度为0.4m,且基坑的底面积与底座的占地面积相同。Further, the depth of the foundation pit is 0.4m, and the bottom area of the foundation pit is the same as that of the base.

本实施例的实现变电站二次屏柜安装基础的快速施工方法通过开挖0.4m深的底座固定槽以及在槽内安装用于固定变电站二次屏柜的底部,不仅加快土建施工的进度和降低施工难度,还达到了节约成本的目标,提高二次屏柜底座安装施工效率,降低工作强度,缩短土建施工时间施工成本,节约资源,增加电网运行的可靠性。The rapid construction method for realizing the installation foundation of the secondary screen cabinet of the substation in this embodiment not only accelerates the progress of civil construction and reduces the The difficulty of construction has also achieved the goal of saving costs, improving the construction efficiency of the installation of the base of the secondary screen cabinet, reducing the work intensity, shortening the construction cost of civil construction, saving resources and increasing the reliability of power grid operation.

实施例2Example 2

作为本发明的第二种实施例,如图1和图2所示,底座包括两组平行设置的横梁100和两组平行设置的纵梁200,两组横梁100与两组纵梁200组成长方形结构,两组横梁100的底部均安装有两个平行设置的可升降支撑机构300,可升降支撑机构300包括支撑腿301,支撑腿301上安装有螺栓固定片304,螺栓固定片304的中心处开设有安装螺孔305,安装螺孔305内螺纹连接有微调螺栓306,微调螺栓306上螺纹连接有第一螺母307和第二螺母308,第一螺母307和第二螺母308分别设置于螺栓固定片304的上下两侧。As the second embodiment of the present invention, as shown in FIG. 1 and FIG. 2 , the base includes two sets of parallel beams 100 and two sets of parallel beams 200 , and the two sets of beams 100 and the two sets of longitudinal beams 200 form a rectangle. Structure, the bottoms of the two sets of beams 100 are installed with two parallelly arranged liftable support mechanisms 300. The liftable support mechanism 300 includes a support leg 301, and a bolt fixing piece 304 is installed on the support leg 301. The center of the bolt fixing piece 304 A mounting screw hole 305 is provided, and a fine-tuning bolt 306 is threadedly connected to the mounting screw hole 305. The fine-tuning bolt 306 is threadedly connected with a first nut 307 and a second nut 308. The upper and lower sides of the sheet 304.

进一步的,支撑腿301的顶部安装有顶座302,顶座302的两端边缘部开设有安装孔303,横梁100的底面开设有与安装孔303尺寸相适配、位置相对应且数量相同的连接螺孔101,支撑腿301通过固定螺栓400依次穿过安装孔303和连接螺孔101螺纹连接于横梁100底部,便于将支撑腿301进行安装或拆卸,在长期使用后,若发现其中一个或多个支撑腿301损坏,可单独进行更换,节约维修成本。Further, a top seat 302 is installed on the top of the support leg 301 , and mounting holes 303 are formed on the edges of both ends of the top seat 302 . The connecting screw holes 101, the support legs 301 are screwed to the bottom of the beam 100 through the mounting holes 303 and the connecting screw holes 101 in turn through the fixing bolts 400, so that the support legs 301 can be easily installed or removed. If a plurality of supporting legs 301 are damaged, they can be replaced individually, which saves maintenance costs.

具体的,横梁100、纵梁200以及支撑腿301均采用角钢制成,且角钢的厚度为5mm,横梁100的长度为800mm,纵梁200的长度为400mm,支撑腿301的长度为150mm,微调螺栓306的长度为90mm,第一螺母307和第二螺母308的厚度为15mm,螺帽的厚度为15mm,微调螺栓306的底端为光螺杆,其长度为10mm,微调螺栓306的剩余长度即为可调的最大长度,其可调最大长度为90-2×15-15-10-5=30mm。Specifically, the beam 100, the longitudinal beam 200 and the support legs 301 are all made of angle steel, and the thickness of the angle steel is 5 mm, the length of the beam 100 is 800 mm, the length of the longitudinal beam 200 is 400 mm, and the length of the supporting legs 301 is 150 mm. The length of the bolt 306 is 90mm, the thickness of the first nut 307 and the second nut 308 is 15mm, and the thickness of the nut is 15mm. The adjustable maximum length is 90-2×15-15-10-5=30mm.

本实施例的实现变电站二次屏柜安装基础的快速施工方法中通过设置的可升降支撑机构300,结构简单,设计合理,通过调节微调螺栓306的相对位置,改变螺帽的相对高度,从而实现可调高度的功能,可以将底座的各个水平高度进行统一,焊接在槽钢底部的螺母具有固定作用,减小螺杆与底座支撑的移动,使得结构更加稳定。The lifting and lowering support mechanism 300 provided in the rapid construction method for realizing the installation foundation of the secondary panel cabinet of the substation in this embodiment has a simple structure and a reasonable design. The height-adjustable function can unify the various levels of the base, and the nut welded on the bottom of the channel steel has a fixed function, reducing the movement of the screw and the base support, making the structure more stable.

以上显示和描述了本发明的基本原理、主要特征和本发明的优点。本行业的技术人员应该了解,本发明不受上述实施例的限制,上述实施例和说明书中描述的仅为本发明的优选例,并不用来限制本发明,在不脱离本发明精神和范围的前提下,本发明还会有各种变化和改进,这些变化和改进都落入要求保护的本发明范围内。本发明要求保护范围由所附的权利要求书及其等效物界定。The foregoing has shown and described the basic principles, main features and advantages of the present invention. Those skilled in the art should understand that the present invention is not limited by the above-mentioned embodiments, and the above-mentioned embodiments and descriptions are only preferred examples of the present invention, and are not intended to limit the present invention, without departing from the spirit and scope of the present invention. Under the premise, the present invention will also have various changes and improvements, and these changes and improvements all fall within the scope of the claimed invention. The claimed scope of the present invention is defined by the appended claims and their equivalents.

Claims (9)

1.一种实现变电站二次屏柜安装基础的快速施工方法,其特征在于:具体包括如下步骤:1. a kind of quick construction method that realizes the installation foundation of secondary screen cabinet of substation, it is characterized in that: specifically comprise the steps: S1开槽:选取变电站二次屏柜的安装位置,在选定位置开挖用于安装变电站二次屏柜底座的基坑,并对边角处进行修正;S1 Slotting: Select the installation position of the secondary screen cabinet of the substation, excavate the foundation pit for installing the base of the secondary screen cabinet of the substation at the selected position, and correct the corners; S2制备混凝土:现场制作C20混凝土,每100g原料需拌水12g,人工振捣约10min,直至混凝土具有流动性;S2 Preparation of concrete: C20 concrete is produced on site, 12g of water should be mixed with every 100g of raw materials, and it should be vibrated manually for about 10min until the concrete has fluidity; S3浇注混凝土:在挖取的基坑内浇注混凝土浆料,且混凝土的强度为35-50%;S3 pouring concrete: pouring concrete slurry in the excavated foundation pit, and the strength of the concrete is 35-50%; S4组装底座:将用于安装变电站二次屏柜底座对各种原料进行拼接,并对其表面进行镀锌处理;S4 assembly base: the base used to install the secondary panel cabinet of the substation will be spliced with various raw materials, and the surface will be galvanized; S5安装底座:待混凝土凝固成型后,将拼接后的底座安装于浇注混凝土顶部,并通过底座上的可升降支撑机构对底座的各个边角的位置进行调整,使得底座的顶面为水平;S5 installation base: After the concrete is solidified and formed, the spliced base is installed on the top of the poured concrete, and the position of each corner of the base is adjusted through the liftable support mechanism on the base, so that the top surface of the base is horizontal; S6安装变电站二次屏柜:将变电站二次屏柜移动至底座上进行固定。S6 Install the secondary screen cabinet of the substation: Move the secondary screen cabinet of the substation to the base for fixing. 2.根据权利要求1所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述基坑的深度为0.4m,且基坑的底面积与底座的占地面积相同。2 . The rapid construction method for realizing the installation foundation of the secondary panel cabinet of the substation according to claim 1 , wherein the depth of the foundation pit is 0.4m, and the bottom area of the foundation pit is the same as that of the base. 3 . 3.根据权利要求1所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述底座包括两组平行设置的横梁(100)和两组平行设置的纵梁(200),两组横梁(100)与两组纵梁(200)组成长方形结构,两组所述横梁(100)的底部均安装有两个平行设置的可升降支撑机构(300),所述可升降支撑机构(300)包括支撑腿(301),所述支撑腿(301)上安装有螺栓固定片(304),所述螺栓固定片(304)的中心处开设有安装螺孔(305),所述安装螺孔(305)内螺纹连接有微调螺栓(306),所述微调螺栓(306)上螺纹连接有第一螺母(307)和第二螺母(308),所述第一螺母(307)和第二螺母(308)分别设置于螺栓固定片(304)的上下两侧。3. The rapid construction method for realizing the installation foundation of the secondary panel cabinet of a substation according to claim 1, wherein the base comprises two groups of parallel beams (100) and two groups of parallel beams (200) , the two sets of beams (100) and the two sets of longitudinal beams (200) form a rectangular structure, and the bottoms of the two sets of beams (100) are installed with two parallelly arranged liftable support mechanisms (300), the liftable supports The mechanism (300) includes a support leg (301) on which a bolt fixing sheet (304) is installed, and a mounting screw hole (305) is opened at the center of the bolt fixing sheet (304), and the A fine-tuning bolt (306) is threadedly connected to the mounting screw hole (305), and a first nut (307) and a second nut (308) are threadedly connected to the fine-tuning bolt (306), and the first nut (307) and the The second nuts (308) are respectively disposed on the upper and lower sides of the bolt fixing plate (304). 4.根据权利要求3所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述支撑腿(301)的顶部安装有连接顶座(302),所述连接顶座(302)的两端边缘部开设有安装孔(303),所述横梁(100)的底面开设有与所述安装孔(303)尺寸相适配、位置相对应且数量相同的连接螺孔(101)。4. The rapid construction method for realizing the installation foundation of the secondary panel cabinet of the substation according to claim 3, characterized in that: the top of the support leg (301) is provided with a connecting top seat (302), and the connecting top seat ( 302) are provided with mounting holes (303) at the edges of both ends, and the bottom surface of the beam (100) is provided with connecting screw holes (101) which are of the same size, corresponding positions and the same number as the mounting holes (303). ). 5.根据权利要求4所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述支撑腿(301)通过固定螺栓(400)依次穿过安装孔(303)和连接螺孔(101)螺纹连接于所述横梁(100)底部。5. The rapid construction method for realizing the installation foundation of the secondary panel cabinet of a substation according to claim 4, wherein the support legs (301) pass through the installation holes (303) and the connection bolts in turn through the fixing bolts (400). The hole (101) is screwed to the bottom of the beam (100). 6.根据权利要求3所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述横梁(100)、纵梁(200)以及支撑腿(301)均采用角钢制成,且角钢的厚度为5mm。6. The rapid construction method for realizing the installation foundation of the secondary panel cabinet of a substation according to claim 3, wherein the beam (100), the longitudinal beam (200) and the supporting legs (301) are all made of angle steel, And the thickness of the angle steel is 5mm. 7.根据权利要求6所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述横梁(100)的长度为800mm,所述纵梁(200)的长度为400mm,所述支撑腿(301)的长度为150mm。7. The rapid construction method for realizing the installation foundation of the secondary panel cabinet of a substation according to claim 6, wherein the length of the beam (100) is 800mm, the length of the longitudinal beam (200) is 400mm, and the The length of the support leg (301) is 150mm. 8.根据权利要求6所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述微调螺栓(306)的长度为90mm,第一螺母(307)和第二螺母(308)的厚度为15mm,螺帽的厚度为15mm。8. The rapid construction method for realizing the installation foundation of the secondary panel cabinet of a substation according to claim 6, characterized in that: the length of the fine-tuning bolt (306) is 90mm, and the first nut (307) and the second nut (308) ) is 15mm thick and the nut is 15mm thick. 9.根据权利要求6所述的实现变电站二次屏柜安装基础的快速施工方法,其特征在于:所述微调螺栓(306)的底端为光螺杆,其长度为10mm。9. The rapid construction method for realizing the installation foundation of the secondary panel cabinet of the substation according to claim 6, wherein the bottom end of the fine adjustment bolt (306) is a light screw, and its length is 10mm.
CN202010434859.9A 2020-05-21 2020-05-21 A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations Active CN111653955B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010434859.9A CN111653955B (en) 2020-05-21 2020-05-21 A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010434859.9A CN111653955B (en) 2020-05-21 2020-05-21 A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations

Publications (2)

Publication Number Publication Date
CN111653955A true CN111653955A (en) 2020-09-11
CN111653955B CN111653955B (en) 2021-12-21

Family

ID=72349580

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010434859.9A Active CN111653955B (en) 2020-05-21 2020-05-21 A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations

Country Status (1)

Country Link
CN (1) CN111653955B (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112081134A (en) * 2020-09-18 2020-12-15 广东电网有限责任公司佛山供电局 Power transformer base rapid conversion device and use method thereof
CN112739089A (en) * 2020-12-08 2021-04-30 南京迪港科技有限责任公司 Novel rack base convenient to installation
CN112850479A (en) * 2021-01-04 2021-05-28 中国十七冶集团有限公司 Track type installation method for electric box, disc and cabinet
CN118572533A (en) * 2024-07-29 2024-08-30 国网山东省电力公司滨州市沾化区供电公司 Assembled power supply unit support basis

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0964551A (en) * 1995-08-23 1997-03-07 Oki Electric Ind Co Ltd Fixing structure for adjuster foot
KR100746286B1 (en) * 2007-06-18 2007-08-13 유환홍 Process distribution box for extra high pressure
US20100290175A1 (en) * 2009-05-15 2010-11-18 Jacobsen Mark W Adjustable electrical switching apparatus mounting apparatus and switchgear apparatus including the same
CN202396106U (en) * 2011-11-18 2012-08-22 河南辉煌科技股份有限公司 Adjustable cabinet base
CN203194052U (en) * 2013-03-14 2013-09-11 中兴通讯股份有限公司 Adaptive installation part of communication cabinet pedestal
CN205298819U (en) * 2015-12-18 2016-06-08 金华电力设计院有限公司 Regulation prestressing mechanism of self -supporting cable support
CN105909006A (en) * 2016-05-06 2016-08-31 上海南华兰陵电气有限公司 Prefabricated splicing-combined transformer substation
CN107039897A (en) * 2017-06-20 2017-08-11 四川电力设计咨询有限责任公司 The mounting structure and installation method of electrical cubicle
CN107165288A (en) * 2017-06-05 2017-09-15 浙江省送变电工程公司 The lower margin reinforced liner of construction in a kind of steel reinforced concrete structure cushion cap
CN208674718U (en) * 2018-09-20 2019-03-29 华仪电气股份有限公司 A kind of adjustable mounting plate of box-type substation
CN110158627A (en) * 2019-04-30 2019-08-23 国网浙江省电力有限公司金华供电公司 A kind of basis in prefabricated transformer substation power distribution unit building and construction method
CN210482359U (en) * 2019-06-26 2020-05-08 国网吉林省电力有限公司松原供电公司 Special-shaped foundation structure of 10kV switch cabinet

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH0964551A (en) * 1995-08-23 1997-03-07 Oki Electric Ind Co Ltd Fixing structure for adjuster foot
KR100746286B1 (en) * 2007-06-18 2007-08-13 유환홍 Process distribution box for extra high pressure
US20100290175A1 (en) * 2009-05-15 2010-11-18 Jacobsen Mark W Adjustable electrical switching apparatus mounting apparatus and switchgear apparatus including the same
CN202396106U (en) * 2011-11-18 2012-08-22 河南辉煌科技股份有限公司 Adjustable cabinet base
CN203194052U (en) * 2013-03-14 2013-09-11 中兴通讯股份有限公司 Adaptive installation part of communication cabinet pedestal
CN205298819U (en) * 2015-12-18 2016-06-08 金华电力设计院有限公司 Regulation prestressing mechanism of self -supporting cable support
CN105909006A (en) * 2016-05-06 2016-08-31 上海南华兰陵电气有限公司 Prefabricated splicing-combined transformer substation
CN107165288A (en) * 2017-06-05 2017-09-15 浙江省送变电工程公司 The lower margin reinforced liner of construction in a kind of steel reinforced concrete structure cushion cap
CN107039897A (en) * 2017-06-20 2017-08-11 四川电力设计咨询有限责任公司 The mounting structure and installation method of electrical cubicle
CN208674718U (en) * 2018-09-20 2019-03-29 华仪电气股份有限公司 A kind of adjustable mounting plate of box-type substation
CN110158627A (en) * 2019-04-30 2019-08-23 国网浙江省电力有限公司金华供电公司 A kind of basis in prefabricated transformer substation power distribution unit building and construction method
CN210482359U (en) * 2019-06-26 2020-05-08 国网吉林省电力有限公司松原供电公司 Special-shaped foundation structure of 10kV switch cabinet

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
牟思浦: "《电气二次回路接线及施工》", 31 October 1999, 中国电力出版社 *

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112081134A (en) * 2020-09-18 2020-12-15 广东电网有限责任公司佛山供电局 Power transformer base rapid conversion device and use method thereof
CN112739089A (en) * 2020-12-08 2021-04-30 南京迪港科技有限责任公司 Novel rack base convenient to installation
CN112850479A (en) * 2021-01-04 2021-05-28 中国十七冶集团有限公司 Track type installation method for electric box, disc and cabinet
CN118572533A (en) * 2024-07-29 2024-08-30 国网山东省电力公司滨州市沾化区供电公司 Assembled power supply unit support basis
CN118572533B (en) * 2024-07-29 2024-10-18 国网山东省电力公司滨州市沾化区供电公司 Assembled power supply unit support basis

Also Published As

Publication number Publication date
CN111653955B (en) 2021-12-21

Similar Documents

Publication Publication Date Title
CN111653955A (en) A rapid construction method for realizing the installation foundation of secondary screen cabinets in substations
CN211113707U (en) Embedded positioning device for foundation bolt
CN103711142A (en) GIS foundation for 220kv transformer substation
CN103031892A (en) Steel truss brace and manufacturing method for steel truss platform
CN102425188A (en) Height-adjustable tower foundation and adjusting method thereof
CN209353366U (en) Tower Crane Foundation Conversion Parts
CN117200658A (en) Leveling method for cross rod of photovoltaic bracket
CN203684265U (en) GIS foundation for 220 kv transformer substation
CN203008232U (en) Steel truss strut
CN209760786U (en) instrumentization support system for controlling precision of two-dimensional component
CN218438009U (en) Fast assembly elevator shaft
CN208361753U (en) A kind of tower crane supporting leg anchoring pre-buried structure and tower crane
CN211037753U (en) Novel scaffold for constructional engineering
CN206873303U (en) A pin-connected panel high position falls boom support
CN222781911U (en) A simple lime spreading device for lime soil roadbed construction
CN221119306U (en) Beam reinforcing structure for construction design
CN219034224U (en) A main transformer oil pool grid support structure
CN210002437U (en) prefabricated elevator foundation
CN223074777U (en) An iron tower foundation that is easy to install
CN216038315U (en) Tower body device of tower crane
CN211959124U (en) Power equipment with adjustable height
CN213629587U (en) Novel extra-high voltage converter transformer fireproof wall equipment support connecting structure
CN215733094U (en) Mounting tool suitable for concealed installation of electronic box on masonry structure
CN216075191U (en) A pit-in-pit prefabricated cofferdam
CN217106227U (en) Cup mouth bearing-inserting type steel frame column leveling structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
CP03 Change of name, title or address

Address after: No. 543, Huancheng Road, Xiaogan City, Hubei Province, 432000

Patentee after: Xiaogan Kexian Electric Power Co.,Ltd.

Country or region after: China

Address before: No. 543, Huancheng Road, Xiaogan City, Hubei Province, 432000

Patentee before: XIAOGAN KEXIAN ELECTRIC POWER ENGINEERING CONSULTING DESIGN CO.,LTD.

Country or region before: China

CP03 Change of name, title or address