CN111636683A - Complete method for embedding indoor electric box - Google Patents

Complete method for embedding indoor electric box Download PDF

Info

Publication number
CN111636683A
CN111636683A CN202010484477.7A CN202010484477A CN111636683A CN 111636683 A CN111636683 A CN 111636683A CN 202010484477 A CN202010484477 A CN 202010484477A CN 111636683 A CN111636683 A CN 111636683A
Authority
CN
China
Prior art keywords
electric box
supporting
frame
box
angle iron
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010484477.7A
Other languages
Chinese (zh)
Inventor
纪学灵
何军伟
彭建良
吉登松
陈志军
尹伟贤
张涛
张闯
卢帅
姜华
王少军
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongtian Huanan Construction Investment Group Co ltd
Zhongtian Construction Group Co Ltd
Original Assignee
Zhongtian Huanan Construction Investment Group Co ltd
Zhongtian Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongtian Huanan Construction Investment Group Co ltd, Zhongtian Construction Group Co Ltd filed Critical Zhongtian Huanan Construction Investment Group Co ltd
Priority to CN202010484477.7A priority Critical patent/CN111636683A/en
Publication of CN111636683A publication Critical patent/CN111636683A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/08Distribution boxes; Connection or junction boxes
    • H02G3/12Distribution boxes; Connection or junction boxes for flush mounting
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02GINSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
    • H02G3/00Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
    • H02G3/02Details
    • H02G3/08Distribution boxes; Connection or junction boxes
    • H02G3/12Distribution boxes; Connection or junction boxes for flush mounting
    • H02G3/121Distribution boxes; Connection or junction boxes for flush mounting in plain walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Mechanical Engineering (AREA)
  • Connection Or Junction Boxes (AREA)

Abstract

The invention discloses a complete method for embedding an indoor electric box, which is characterized by comprising the following steps: the method comprises the following steps: the method comprises the steps of preparing an electric box needing to be embedded, measuring the specific size of the electric box, designing and setting a fixing mechanism outside the electric box according to the size and the characteristics of the electric box, designing and setting a frame and a shaping supporting mechanism inside the electric box, and taking down the frame and the shaping supporting mechanism for repeated recycling after the electric box is embedded. The pre-embedding method can not only avoid the displacement of the electric box during pouring, but also avoid the problem that the electric box is easy to deform during concrete pouring due to the thin wall of the electric box during pre-embedding, and the shaping support mechanism can be recycled, is convenient to use and is very practical.

Description

Complete method for embedding indoor electric box
Technical Field
The invention relates to the field of building construction, in particular to a complete method for embedding an indoor electric box.
Background
The indoor electric box is constructed by adopting a rear cutting method in a traditional method on a concrete wall, foam is embedded firstly in the construction stage of a main body structure, foam and peripheral concrete are cut before the electric box is installed in the later stage, and the electric box is installed.
Disclosure of Invention
The invention provides a complete method for embedding an indoor electric box, which solves the problem that the electric box is easy to deform during concrete pouring due to thin electric box wall when the electric box is embedded, and further strengthens the stability of the electric box on a wall body.
In order to achieve the purpose, the invention adopts the following technical scheme:
a complete set of method for embedding an indoor electric box is characterized in that: the method comprises the following steps:
s1, preparing an electric box to be embedded, measuring the specific size of the electric box, designing and arranging a fixing mechanism outside the electric box according to the size and the characteristics of the electric box, and designing and arranging a frame and a shaping supporting mechanism inside the electric box;
s2, designing and fixing mechanism materials including supporting angle irons, countersunk screws, angle iron fixing ribs and vertical ribs;
s3, designing a shaping support mechanism material comprising a support square tube, a fixing nut, a guide nut and an adjusting bolt;
s4, placing the frame and the shaping supporting mechanism in the electric box, specifically as follows:
the frame is arranged at the center position inside the electric box, the supporting square tube is positioned outside the frame, the fixing nut is welded on one side of the frame far away from the supporting square tube, the guide nut is welded on one side of the frame close to the supporting square tube, the guide nut is matched with the fixing nut, the adjusting bolt is in threaded connection with the fixing nut and the guide nut, one end of the adjusting bolt penetrates through the side wall of the frame and extends to the inside of the supporting square tube, and the adjusting bolt penetrates through the side wall of the frame and extends to the inside of the supporting square tube and is connected with the supporting square tube in a rotating mode;
the adjusting bolt moves to drive the supporting square pipe to move, and when the supporting square pipe moves to be attached and tightly propped against the side wall of the electric box, the installation of the forming supporting mechanism of the electric box is completed;
s5, after the frame and the shaping supporting mechanism in the electric box are completed, sealing the electric box by using a transparent adhesive tape for protection;
s6, according to the position in the drawing electric box, one end of a supporting angle iron is fixed to the four corners of the electric box through countersunk screws, one end of an angle iron fixing rib and one side of the supporting angle iron are fixed in a welding mode through spot welding, and the other end of the angle iron fixing rib and a vertical rib of a wall body are fixed in a welding mode through spot welding (the vertical rib is of an original structure in the wall body), so that the two ends of the supporting angle iron are fixed, and the complete stability of the electric box in the wall body is achieved;
the adjusting bolt moves to drive the supporting square pipe to move, and when the supporting square pipe moves to be attached to the side wall of the electric box, the installation of the forming supporting mechanism of the electric box is completed;
s7, sealing the pre-embedded electric box and pouring concrete;
s8, after the concrete is demoulded, the electric box sealing protective adhesive tape is disassembled, the adjusting bolt is rotated, the frame and the shaping supporting mechanism can be taken down, the pre-embedding of the electric box is completed, and the frame and the shaping supporting mechanism which are taken down are repeatedly recycled.
And in the operation of the step S6, one end of the support angle iron, which is far away from the electric box, is respectively welded with the vertical rib and the support angle iron to form a rectangle.
Step S4 in the operation time guarantee that support side 'S pipe is moderate in the electronic box, do not influence adjusting bolt switching, guarantee simultaneously that support side' S pipe and the accessory of electronic box do not conflict, support side 'S pipe is the setting of rectangle post, just the width and the electronic box lateral wall of support side' S pipe match.
The invention has the beneficial effects that:
1. there is the support angle bar through electronic box four corners fixed mounting, and supports the vertical muscle welding of angle bar through the fixed muscle of angle bar and wall body for the more stable pre-buried in the wall body of electronic box makes the electronic box take place the displacement when having avoided concreting, leads to the electronic box position and the inconsistent condition in drawing position.
2. Through rotating the adjusting bolt in the design supporting mechanism, promote support side's pipe and remove to the electronic box lateral wall for support side's pipe plays the supporting role for the electronic box lateral wall, has avoided the condition that makes the electronic box lateral wall take place to warp when concrete placement smashes, and simultaneously after the pre-buried shaping of electronic box, the accessible rotates adjusting bolt and drives support side's pipe and the separation of electronic box lateral wall and remove to the frame, makes the design supporting mechanism can take out from the electronic box and has enough to meet the need the recycling.
In conclusion, the method for embedding the electric box can not only avoid the electric box from displacing during pouring, but also avoid the deformation of the electric box during pouring and tamping, and the shaping supporting mechanism can be used in a circulating way, so that the problem that the electric box is easy to deform during concrete pouring and tamping due to the thin electric box wall when the electric box is embedded is solved.
Drawings
FIG. 1 is a schematic structural diagram of the present invention.
FIG. 2 is a schematic side view of the present invention.
Fig. 3 is a schematic top view of the present invention.
Reference numbers in the figures: 1. an electric box; 3. a frame; 4. a shaping support mechanism; 5. supporting angle iron; 6. countersunk screws; 7. angle iron fixing ribs; 8. vertical ribs; 10. fixing a nut; 11. a guide nut; 12. adjusting the bolt; 13. and supporting the square pipe.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-3, a method for embedding an indoor electric box in a whole set is characterized in that: the method comprises the following steps:
s1, preparing an electric box 1 to be embedded, measuring the specific size of the electric box, designing and arranging a fixing mechanism outside the electric box 1 according to the size and the characteristics of the electric box 1, and designing and arranging a frame 3 and a shaping supporting mechanism 4 inside the electric box 1;
s2, designing and fixing mechanism materials including supporting angle iron 5, countersunk head screws 6 and angle iron fixing ribs 7;
s3, designing a shaping support mechanism 4, wherein the material comprises a support square pipe 13, a fixing nut 10, a guide nut 11 and an adjusting bolt 12;
s4, firstly, placing the frame 3 and the shaping supporting mechanism 4 in the electric box 1, specifically, arranging the frame 3 in the center position in the electric box 1, wherein the supporting square tube 13 is positioned outside the frame 3, the fixing nut 10 is welded on one side of the frame 3 far away from the supporting square tube 13, the guide nut 11 is welded on one side of the frame 3 close to the supporting square tube 13, the guide nut 11 is matched with the fixing nut 10, the adjusting bolt 12 is in threaded connection with the fixing nut 10 and the guide nut 11, one end of the adjusting bolt 12 penetrates through the side wall of the frame 3 and extends into the supporting square tube 13, and the end of the adjusting bolt 12 penetrating through the side wall of the frame 3 and extending into the supporting square tube 13 is rotatably connected with the supporting square tube 13;
the adjusting bolt 12 moves to drive the supporting square pipe 13 to move, and when the supporting square pipe 13 moves to be attached and tightly propped against the side wall of the electric box 1, the installation of the shaping supporting mechanism 4 forming the electric box 1 is completed;
s5, after the frame 3 and the shaping supporting mechanism 4 in the electric box 1 are completed, sealing and protecting the electric box by using a transparent adhesive tape;
s6, according to the position in the electrical box of the drawing, one end of a supporting angle iron 5 is fixed at four corners of the electrical box 1 through countersunk screws 6, one end of an angle iron fixing rib 7 and one side of the supporting angle iron 5 are fixed through spot welding, and then the other end of the angle iron fixing rib 7 and a vertical rib 8 of a wall body are fixed through spot welding (the vertical rib is of an original structure in the wall body), so that two ends of the supporting angle iron 5 are fixed, and the complete stability of the electrical box 1 in the wall body is completed;
s7, sealing the pre-buried electric box 1 and pouring concrete;
s8, after the concrete is demoulded, the electric box sealing protective adhesive tape is disassembled, the adjusting bolt 12 is rotated, the frame 3 and the shaping supporting mechanism 4 can be taken down, the pre-embedding of the electric box 1 is completed, and the frame 3 and the shaping supporting mechanism 4 which are taken down are repeatedly recycled.
And in the operation of the step S6, one end of the support angle iron, which is far away from the electric box, is respectively welded with the vertical rib and the support angle iron to form a rectangle.
When the operation is performed in the step S4, the square tube is guaranteed to be moderate in the electric box, the opening and closing of the adjusting bolt are not affected, meanwhile, the square tube is guaranteed not to conflict with accessories in the electric box, the square tube is arranged in a rectangular column, and the width of the square tube is matched with the side wall of the electric box.
There is a support angle bar through electronic box four corners fixed mounting, and supports the vertical muscle of angle bar and wall body and support the angle bar welding for the more stable pre-buried in the wall body of electronic box makes the electronic box take place the displacement when having avoided concreting, leads to the electronic box position and the inconsistent condition in drawing position.
Through rotating the adjusting bolt in the design supporting mechanism, promote support side's pipe and remove to the electronic box lateral wall for support side's pipe plays the supporting role for the electronic box lateral wall, has avoided the condition that makes the electronic box lateral wall take place to warp when concrete placement smashes, and simultaneously after the pre-buried shaping of electronic box, the accessible rotates adjusting bolt and drives support side's pipe and the separation of electronic box lateral wall and remove to the frame, makes the design supporting mechanism can take out from the electronic box and has enough to meet the need the recycling.
In conclusion, the method for embedding the electric box can not only avoid the electric box from displacing during pouring, but also avoid the deformation of the electric box during pouring and tamping, and the shaping supporting mechanism can be used in a circulating way, so that the problem that the electric box is easy to deform during concrete pouring and tamping due to the thin electric box wall when the electric box is embedded is solved.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (3)

1. A complete set of method for embedding an indoor electric box is characterized in that: the method comprises the following steps:
s1, preparing an electric box (1) to be embedded, measuring the specific size of the electric box, designing and arranging a fixing mechanism outside the electric box (1) according to the size and the characteristics of the electric box (1), and designing and arranging a frame (3) and a shaping supporting mechanism (4) inside the electric box (1);
s2, designing and fixing mechanism materials including supporting angle iron (5), countersunk head screws (6) and angle iron fixing ribs (7);
s3, designing a shaping supporting mechanism (4) and making the shaping supporting mechanism comprise a supporting square pipe (13), a fixing nut (10), a guide nut (11) and an adjusting bolt (12);
s4, placing the frame (3) and the shaping supporting mechanism (4) in the electric box (1) firstly, and concretely comprising the following steps: the frame (3) is arranged at the center position in the electric box (1), the supporting square tube (13) is positioned on the outer side of the frame (3), the fixing nut (10) is welded on one side of the frame (3) far away from the supporting square tube (13), the guide nut (11) is welded on one side of the frame (3) close to the support square pipe (13), the guide nut (11) is matched with the fixed nut (10), the adjusting bolt (12) is in threaded connection with the fixed nut (10) and the guide nut (11), one end of the adjusting bolt (12) penetrates through the side wall of the frame (3) and extends into the supporting square pipe (13), the adjusting bolt (12) penetrates through the side wall of the frame (3) and extends to one end inside the supporting square pipe (13), and the end of the adjusting bolt is rotatably connected with the supporting square pipe (13);
the adjusting bolt (12) moves to drive the supporting square pipe (13) to move, and when the supporting square pipe (13) moves to be attached and tightly propped against the side wall of the electric box (1), the forming supporting mechanism (4) of the electric box (1) is formed and installed;
s5, after the frame (3) and the shaping supporting mechanism (4) in the electric box (1) are completed, sealing the electric box by using a transparent adhesive tape for protection;
s6, according to the position in the electrical box on the drawing, one end of a supporting angle iron (5) is fixed at four corners of the electrical box (1) through countersunk screws (6), one end of an angle iron fixing rib (7) and one side of the supporting angle iron (5) are fixed in a welding mode through spot welding, and then the other end of the angle iron fixing rib (7) and a vertical rib (8) of a wall body are fixed in a welding mode through spot welding, so that the two ends of the supporting angle iron (5) are fixed, and complete stability of the electrical box (1) in the wall body is achieved;
s7, performing mold sealing and concrete pouring on the pre-embedded electric box (1);
s8, after the concrete is demoulded, the electric box sealing protective adhesive tape is disassembled, the adjusting bolt (12) is rotated, the frame (3) and the shaping supporting mechanism (4) can be taken down, the pre-embedding of the electric box (1) is completed, and the frame (3) and the shaping supporting mechanism (4) which are taken down are recycled.
2. The method for embedding the indoor electric box in a whole set according to claim 1, wherein the method comprises the following steps: and in the operation of the step S6, one end of the supporting angle iron (5) far away from the electric box (1) is respectively welded with the vertical rib (8) and the supporting angle iron (5) to form a rectangle.
3. The method for embedding the indoor electric box in a whole set according to claim 1, wherein the method comprises the following steps: step S4 in the operation time guarantee support side 'S pipe (13) moderate in electronic box (1), do not influence adjusting bolt (12) switching, guarantee simultaneously that support side' S pipe (13) and the accessory in electronic box (1) do not conflict, support side 'S pipe (13) is the setting of rectangle post, just the width of support side' S pipe (13) matches with electronic box (1) lateral wall.
CN202010484477.7A 2020-06-01 2020-06-01 Complete method for embedding indoor electric box Pending CN111636683A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010484477.7A CN111636683A (en) 2020-06-01 2020-06-01 Complete method for embedding indoor electric box

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010484477.7A CN111636683A (en) 2020-06-01 2020-06-01 Complete method for embedding indoor electric box

Publications (1)

Publication Number Publication Date
CN111636683A true CN111636683A (en) 2020-09-08

Family

ID=72329574

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010484477.7A Pending CN111636683A (en) 2020-06-01 2020-06-01 Complete method for embedding indoor electric box

Country Status (1)

Country Link
CN (1) CN111636683A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113131365A (en) * 2021-03-22 2021-07-16 中国五冶集团有限公司 Method for strengthening internal support of indoor finished product electric box

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3009733A1 (en) * 2013-08-13 2015-02-20 Imepsa Soc HINGED BOX BOX FOR CONCRETE SLAB
CN106121232A (en) * 2016-08-24 2016-11-16 中天建设集团有限公司天津分公司 The installation method of distribution box in a kind of secondary structure
CN106911110A (en) * 2017-02-14 2017-06-30 山西省工业设备安装有限公司 A kind of distribution box support component and the utilization direct pre-embedded construction method of the component
EP3219873A1 (en) * 2016-03-18 2017-09-20 Ain Corporation Reservation box for incorporating pipelines suitable for being positioned on a frame
CN208777708U (en) * 2018-09-03 2019-04-23 云南建投第六建设有限公司 Support mode inside concealed distribution box body
CN210273410U (en) * 2019-08-21 2020-04-07 广州市璟宏工程管理有限公司 Pre-buried fixing device of block terminal

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
FR3009733A1 (en) * 2013-08-13 2015-02-20 Imepsa Soc HINGED BOX BOX FOR CONCRETE SLAB
EP3219873A1 (en) * 2016-03-18 2017-09-20 Ain Corporation Reservation box for incorporating pipelines suitable for being positioned on a frame
CN106121232A (en) * 2016-08-24 2016-11-16 中天建设集团有限公司天津分公司 The installation method of distribution box in a kind of secondary structure
CN106911110A (en) * 2017-02-14 2017-06-30 山西省工业设备安装有限公司 A kind of distribution box support component and the utilization direct pre-embedded construction method of the component
CN208777708U (en) * 2018-09-03 2019-04-23 云南建投第六建设有限公司 Support mode inside concealed distribution box body
CN210273410U (en) * 2019-08-21 2020-04-07 广州市璟宏工程管理有限公司 Pre-buried fixing device of block terminal

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113131365A (en) * 2021-03-22 2021-07-16 中国五冶集团有限公司 Method for strengthening internal support of indoor finished product electric box

Similar Documents

Publication Publication Date Title
CN111636683A (en) Complete method for embedding indoor electric box
CN211028699U (en) Building curtain built-in fitting combination welding system
CN212784347U (en) Internal support bracket structure of embedded indoor electrical box wire box
CN114197877A (en) Wall and column concrete junction position separation device and construction method
CN113513142B (en) Prefabricated convex window correction device and correction method adopting same
KR101523360B1 (en) Coil inserting machine
CN205668836U (en) A kind of cable reclaimer
CN214062373U (en) Vibrating device for civil construction
KR20100119687A (en) A supporting device for a yoke the mold
CN218864354U (en) Fixing structure for mounting air conditioner external unit
CN210450457U (en) Arch door frame forming device
CN111343523A (en) Dismounting device for sound box mesh enclosure
CN217268817U (en) Aluminum formwork convenient to construct and install
CN206758847U (en) A kind of metal-air switch enclosure
KR20090118506A (en) Concrete form
CN215150186U (en) Supporting device for assembled building board die
CN213005798U (en) Prefabricated part with embedded door frame or window frame
CN210930007U (en) Box is deposited to interactive model of 3D scene
CN218843847U (en) Post-cast strip end constructional column supporting structure
CN214925328U (en) Building constructional column forming device
CN216474704U (en) Portable wave form guardrail installation device
CN216598397U (en) Vortex-induced vibration structure for restraining lightning rod of transformer substation framework
CN219753265U (en) Slope protection reinforcing structure
CN211319570U (en) Economic management is with simulation sand table structure
CN218467246U (en) Pavilion convenient to installation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200908