CN111594229A - 一种浅埋富水地质条件下连拱隧道进洞的施工方法 - Google Patents

一种浅埋富水地质条件下连拱隧道进洞的施工方法 Download PDF

Info

Publication number
CN111594229A
CN111594229A CN202010465066.3A CN202010465066A CN111594229A CN 111594229 A CN111594229 A CN 111594229A CN 202010465066 A CN202010465066 A CN 202010465066A CN 111594229 A CN111594229 A CN 111594229A
Authority
CN
China
Prior art keywords
grouting
hole
drilling
tunnel
pipe
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010465066.3A
Other languages
English (en)
Other versions
CN111594229B (zh
Inventor
陈小羊
金阳
黄琪
姚兵
杨作杰
高晓波
邓庭彦
施洺
白海亮
王迎东
李延志
丁冲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Construction Seventh Engineering Division Corp Ltd
Transportation Construction Co Ltd of China Construction Seventh Engineering Division Corp Ltd
Original Assignee
China Construction Seventh Engineering Division Corp Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Construction Seventh Engineering Division Corp Ltd filed Critical China Construction Seventh Engineering Division Corp Ltd
Priority to CN202010465066.3A priority Critical patent/CN111594229B/zh
Publication of CN111594229A publication Critical patent/CN111594229A/zh
Priority to US17/331,637 priority patent/US20220106879A1/en
Application granted granted Critical
Publication of CN111594229B publication Critical patent/CN111594229B/zh
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/15Plate linings; Laggings, i.e. linings designed for holding back formation material or for transmitting the load to main supporting members
    • E21D11/152Laggings made of grids or nettings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • E21D11/18Arch members ; Network made of arch members ; Ring elements; Polygon elements; Polygon elements inside arches
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

本发明涉及一种浅埋富水地质条件下连拱隧道进洞的施工方法;其解决的技术方案包括清理注浆地表,标注注浆加固范围,根据设计图纸洞口段洞内径向锚杆的位置间距100×60cm(环向×纵向),在洞顶地表对应位置测量放样,按比例绘制断面图,计算出所需打设锚杆点的坐标及角度,标出钻孔位置,在各钻孔处钉设小木桩进行标识,并根据地面标高确定锚杆打设的深度,钻孔,扫孔,注浆,施工准备,洞口及明洞土石方开挖至隧道起拱线平后,进行洞口长管棚施工,施工时采用潜孔钻钻孔,长管棚注浆按固结管棚周围有限范围内土体设计,来实现浅埋富水地质条件下连拱隧道进洞施工。

Description

一种浅埋富水地质条件下连拱隧道进洞的施工方法
技术领域
本发明涉及隧道工程技术领域,特别是一种浅埋富水地质条件下连拱隧道进洞的施工方法。
背景技术
浅埋隧道是一种特定条件下的隧道工程,埋深不足隧道洞径的2倍,其施工不仅受覆盖层地质因素的制约,而且还受地面环境的影响,隧道浅埋并非单纯指洞顶地层厚度小,还应结合上覆地层的工程地质条件综合判定,包括围岩结构构造特征,风化、破碎、断层影响的程度,结构强度,松散状况以及地下水等因素。
某隧道隧址区属于低山丘陵地貌,构造行迹主要表现为节理裂隙发育,地质条件较差,其中进出口洞口全风化混合花岗岩围岩级别为Ⅴ级,隧道进洞口全风化混合花岗岩厚度大、结构松散,易坍塌,使得进洞口仰坡岩土体的稳定性极差,施工开挖极易产生浅层工程滑坡或大的坍塌,出洞口上部第四系残坡积层厚度较大、结构松散;强风化岩体受节理、裂隙和风化影响,岩体破碎,遇水极易软化导致强度迅速降低,施工开挖极易产生浅层工程大坍塌,隧道施工时需清除地表残坡积物,对强风化岩层表面采取喷浆和砌石护坡措施,因此,对施工方法提出了更高的要求。
浅埋隧道进洞一直是隧道施工中至关重要的环节,在隧道进洞时,一般都是采用超前大管棚注浆来控制隧道开挖后地表的沉降和洞内的围岩稳定,但当隧道洞口处地质条件复杂,围岩风化严重,洞口受到浅埋、富水等不利因素作用时,只采用管棚支护很难有效地控制地表沉降和洞内围岩稳定,这时就需要结合其它有效措施来解决浅埋富水条件下隧道的进洞问题。
发明内容
针对上述情况,为克服现有技术之缺陷,本发明提供一种浅埋富水地质条件下连拱隧道进洞的施工方法,有效的解决了现有隧道洞口处地质条件复杂,围岩风化严重,洞口受到浅埋、富水等不利因素作用时,采用管棚支护很难有效地控制地表沉降和洞内围岩稳定的问题。
其解决问题的技术方案是,一种浅埋富水地质条件下连拱隧道进洞的施工方法,施工步骤包括:
步骤一:清理注浆地表,清除注浆坡面上的妨碍注浆的杂物,清理中尽量不破坏地表植被,保持山体的自然风貌;
步骤二:标注注浆加固范围,通过分析计算,对隧道出口注浆布置范围为: 纵向长度18m,其中管棚长度16m,宽度为自隧道左右主洞中心线向两侧各5m,即环向10m;深度为至距隧道拱顶部 0.5m 左右处;
步骤三:根据设计图纸洞口段洞内径向锚杆的位置间距100×60cm(环向×纵向),在洞顶地表对应位置测量放样,按比例绘制断面图,计算出所需打设锚杆点的坐标及角度,标出钻孔位置,在各钻孔处钉设小木桩进行标识,并根据地面标高确定锚杆打设的深度;
步骤四:钻孔:钻孔采用工程钻机干钻,钻孔采用潜孔钻在注浆点位钻孔,钻进设前调整好钻入角度,钻孔过程中经常检查钻入角度;
步骤五:扫孔:为保证注浆效果,地表注浆采用两次扫孔分段注浆的方式,钻孔后,采用后退式方式扫孔一遍,清孔完毕后,再将钻杆插入孔底,重复扫孔一次即可;
步骤六:注浆:为了选择适合该隧道地表注浆的最佳浆液配合比,对各配合比的浆液性能作了几组有代表性的现场试验,重点比较其凝结时间、抗拉强度及抗折强度;
步骤七:施工准备:地表注浆结束后,施作洞口截水沟等排水系统,坡顶截水沟设于边、仰坡顶以外不小于5m,其坡度根据地形设置,排水坡度不应小于3%,以免淤积;
步骤八:洞口及明洞土石方开挖至隧道起拱线平后,进行洞口长管棚施工,管棚定向采用2m长的C25混凝土套拱,套拱基础必须落在稳定的基础上,套拱混凝土导向墙在明洞外轮廓线以外施作,导向墙内设4组I16工字钢,工字钢分段按设计尺寸弯制成弧形,段与段之间采有螺栓连接成半圆形,在洞口架立固定后,在钢架上安装并固定φ114孔口管,立内、外模浇筑混凝土,混凝土套拱厚60cm;
步骤九:施工时采用潜孔钻钻孔,钢管沿隧道周边以纵坡角度大1°外插角打入围岩,环向间距为40cm,钻机立轴方向必须准确控制,以保证孔口的孔向正确,每钻完一孔便顶进一根钢管;
步骤十:长管棚注浆按固结管棚周围有限范围内土体设计,浆液扩散半径不小于0.5m,注浆采用分段注浆,注浆采用单液注浆,注浆前均应进行单液注浆试验,注浆按单管达到设计注浆量作为注浆结束的标准,当注浆压力达到设计终压10分钟后,进浆量仍达不到设计注浆量时,也可结束注浆。
本发明构思新颖,结构巧妙,实用性强,有效的解决了现有隧道洞口处地质条件复杂,围岩风化严重,洞口受到浅埋、富水等不利因素作用时,采用管棚支护很难有效地控制地表沉降和洞内围岩稳定的问题。
附图说明
图1为本发明钢花管横断面布置图。
图2为本发明锚杆打设位置图。
图3为本发明经向锚杆地表外做带压注浆技术流程图。
图4为本发明长管棚施工流程图。
具体实施方式
以下结合附图对本发明的具体实施方式做出进一步详细说明。
本发明的施工步骤包括:
步骤一:清理注浆地表,清除注浆坡面上的妨碍注浆的杂物,清理中尽量不破坏地表植被,保持山体的自然风貌;
步骤二:标注注浆加固范围,通过分析计算,对隧道出口注浆布置范围为: 纵向长度18m,其中管棚长度16m,宽度为自隧道左右主洞中心线向两侧各5m,即环向10m;深度为至距隧道拱顶部 0.5m 左右处;
步骤三:根据设计图纸洞口段洞内径向锚杆的位置间距100×60cm(环向×纵向),在洞顶地表对应位置测量放样,按比例绘制断面图,计算出所需打设锚杆点的坐标及角度,标出钻孔位置,在各钻孔处钉设小木桩进行标识,并根据地面标高确定锚杆打设的深度;
步骤四:钻孔:钻孔采用工程钻机干钻,钻孔采用潜孔钻在注浆点位钻孔,钻进设前调整好钻入角度,钻孔过程中经常检查钻入角度,以防偏孔;
步骤五:扫孔:为保证注浆效果,地表注浆采用两次扫孔分段注浆的方式,钻孔后,采用后退式方式扫孔一遍,清孔完毕后,再将钻杆插入孔底,重复扫孔一次即可;
步骤六:注浆:为了选择适合该隧道地表注浆的最佳浆液配合比,对各配合比的浆液性能作了几组有代表性的现场试验,重点比较其凝结时间、抗拉强度及抗折强度;
步骤七:施工准备:地表注浆结束后,施作洞口截水沟等排水系统,坡顶截水沟设于边、仰坡顶以外不小于5m,其坡度根据地形设置,排水坡度不应小于3%,以免淤积;
步骤八:洞口及明洞土石方开挖至隧道起拱线平后,进行洞口长管棚施工,管棚定向采用2m长的C25混凝土套拱,套拱基础必须落在稳定的基础上,套拱混凝土导向墙在明洞外轮廓线以外施作,导向墙内设4组I16工字钢,工字钢分段按设计尺寸弯制成弧形,段与段之间采有螺栓连接成半圆形,在洞口架立固定后,在钢架上安装并固定φ114孔口管,立内、外模浇筑混凝土,混凝土套拱厚60cm;
步骤九:施工时采用潜孔钻钻孔,钢管沿隧道周边以纵坡角度大1°外插角打入围岩,环向间距为40cm,钻机立轴方向必须准确控制,以保证孔口的孔向正确,每钻完一孔便顶进一根钢管。钻进中随时检查偏斜度,发现偏差及时纠正;
步骤十:长管棚注浆按固结管棚周围有限范围内土体设计,浆液扩散半径不小于0.5m,注浆采用分段注浆,注浆采用单液注浆,不仅可简化工艺,降低造价,而且固结强度高,因此注浆前均应进行单液注浆试验,注浆按单管达到设计注浆量作为注浆结束的标准,当注浆压力达到设计终压10分钟后,进浆量仍达不到设计注浆量时,也可结束注浆,注浆作业应认真记录,随时分析和改进作业,并注意观察初期支护和工作面状态,保证安全。
在步骤二中,进行材料准备:洞内锚杆为Ф25中空注浆锚杆;洞外锚杆用注浆管进行替代,注浆管为φ50mm壁厚3.5mm热压无缝钢管,管身按间距15cm,梅花形钻孔,孔径为8mm,纵向间距1m,环向间距0.6m梅花形布置,钢管尾部焊上φ6钢筋劲箍,导管长根据现场实际情况确定,前端加工成锥形,加固范围内注浆管四周钻四排φ8mm的注浆孔,加固范围以外管段不钻孔,作为注浆用导浆管。
在步骤六中,注浆材料采用水泥单液浆,水泥采用活性高,出厂日期不超过3个月的42.5R以上普通硅酸盐水泥,为了保证注浆不停顿地进行,注浆前应认真检查:注浆泵的状况是否良好,配件是否备齐;检查制浆的原材料是否备齐,质量是否合格,水灰比采用0.5,并根据实际情况进行适当调整。
在步骤六中,注浆顺序:横向按照先两边、后中间的施工顺序,纵向按照由低至高的顺序进行钻孔和注浆,在同一排为防止相临施工孔之间窜浆,采用间隔施工法。
在步骤八中,管棚钢管规格:管棚采用外径φ108mm,壁厚6mm的热轧无缝钢管制作,钢管前端呈尖锥状,尾部焊接φ10加劲箍,管壁四周钻4排φ12mm压浆孔,钻孔间距为15cm,呈梅花形布置,施工时钢管沿隧道周边以1°外插角,钢花管总长为18m尾端留4.5m不钻孔,尖锥段长10cm,每节节长为3m、6m,每节钢管两端均预加工成外丝扣,同一断面内接头数量不超过总钢管数的50%,编号为奇数管的第一节采用3m钢花管,偶数管第一节采用6m钢管,以后每一节都采用6m长,最后打入的一节钢管结合套拱长度截取,钢管入土长度为设计长度16m。
与现有技术相比,本发明的有益效果在于:
施工人员通过该保护方法进行施工作业后,因步骤三浇筑的操作,混凝土浇筑完成后为使浇筑更为密实,通过刮板将混凝土进行铺平的同时少量灌注混凝土,使得混凝土填实中隔墙内部模板中,使中隔墙混凝土在浇筑过程中灌注到最高位,使得后期主洞开挖后从侧面观察,中隔墙顶部回填密实,沉降观测数据显示拱顶无明显下沉;且通过步骤四、步骤五,使用喷射混凝土对中隔墙肩部与拱顶为结合的部位进行喷护密封,防止注浆过程中漏浆,压浆从低位往高位压,压浆前打开注浆管排气阀门,直到冒出浓浆后再逐一关闭,持续加压,且将中隔墙中模板注满混凝土,从而使得隧道进洞口结实可靠,其结构不易松散,防止出现坍塌现象,同理,在隧道出口上部结构依旧稳定密实,使得强风化岩体不易受节理、裂隙和风化影响,在开挖的过程中还不易产生坍塌、崩塌和掉块现象,而且爆破所产生的飞石冲击在中隔墙时不易对其造成较大的伤害,提高中隔墙的刚性强度不会影响隧道的承重性能,即可有效的对连拱隧道中隔墙进行保护,进一步提高了连拱隧道的稳定性。

Claims (5)

1.一种浅埋富水地质条件下连拱隧道进洞的施工方法,其特征在于,包括以下施工步骤:
步骤一:清理注浆地表,清除注浆坡面上的妨碍注浆的杂物,清理中尽量不破坏地表植被,保持山体的自然风貌;
步骤二:标注注浆加固范围,通过分析计算,对隧道出口注浆布置范围为: 纵向长度18m,其中管棚长度16m,宽度为自隧道左右主洞中心线向两侧各5m,即环向10m;深度为至距隧道拱顶部 0.5m 左右处;
步骤三:根据设计图纸洞口段洞内径向锚杆的位置间距100×60cm(环向×纵向),在洞顶地表对应位置测量放样,按比例绘制断面图,计算出所需打设锚杆点的坐标及角度,标出钻孔位置,在各钻孔处钉设小木桩进行标识,并根据地面标高确定锚杆打设的深度;
步骤四:钻孔:钻孔采用工程钻机干钻,钻孔采用潜孔钻在注浆点位钻孔,钻进设前调整好钻入角度,钻孔过程中经常检查钻入角度;
步骤五:扫孔:为保证注浆效果,地表注浆采用两次扫孔分段注浆的方式,钻孔后,采用后退式方式扫孔一遍,清孔完毕后,再将钻杆插入孔底,重复扫孔一次即可;
步骤六:注浆:为了选择适合该隧道地表注浆的最佳浆液配合比,对各配合比的浆液性能作了几组有代表性的现场试验,重点比较其凝结时间、抗拉强度及抗折强度;
步骤七:施工准备:地表注浆结束后,施作洞口截水沟等排水系统,坡顶截水沟设于边、仰坡顶以外不小于5m,其坡度根据地形设置,排水坡度不应小于3%,以免淤积;
步骤八:洞口及明洞土石方开挖至隧道起拱线平后,进行洞口长管棚施工,管棚定向采用2m长的C25混凝土套拱,套拱基础必须落在稳定的基础上,套拱混凝土导向墙在明洞外轮廓线以外施作,导向墙内设4组I16工字钢,工字钢分段按设计尺寸弯制成弧形,段与段之间采有螺栓连接成半圆形,在洞口架立固定后,在钢架上安装并固定φ114孔口管,立内、外模浇筑混凝土,混凝土套拱厚60cm;
步骤九:施工时采用潜孔钻钻孔,钢管沿隧道周边以纵坡角度大1°外插角打入围岩,环向间距为40cm,钻机立轴方向必须准确控制,以保证孔口的孔向正确,每钻完一孔便顶进一根钢管;
步骤十:长管棚注浆按固结管棚周围有限范围内土体设计,浆液扩散半径不小于0.5m,注浆采用分段注浆,注浆采用单液注浆,注浆前均应进行单液注浆试验,注浆按单管达到设计注浆量作为注浆结束的标准,当注浆压力达到设计终压10分钟后,进浆量仍达不到设计注浆量时,也可结束注浆。
2.根据权利要求1所述的一种浅埋富水地质条件下连拱隧道进洞的施工方法,其特征在于,在步骤二中,进行材料准备:洞内锚杆为Ф25中空注浆锚杆;洞外锚杆用注浆管进行替代,注浆管为φ50mm壁厚3.5mm热压无缝钢管,管身按间距15cm,梅花形钻孔,孔径为8mm,纵向间距1m,环向间距0.6m梅花形布置,钢管尾部焊上φ6钢筋劲箍,导管长根据现场实际情况确定,前端加工成锥形,加固范围内注浆管四周钻四排φ8mm的注浆孔,加固范围以外管段不钻孔,作为注浆用导浆管。
3.根据权利要求1所述的一种浅埋富水地质条件下连拱隧道进洞的施工方法,其特征在于,在步骤六中,注浆材料采用水泥单液浆,水泥采用活性高,出厂日期不超过3个月的42.5R以上普通硅酸盐水泥,为了保证注浆不停顿地进行,注浆前应认真检查:注浆泵的状况是否良好,配件是否备齐;检查制浆的原材料是否备齐,质量是否合格,水灰比采用0.5,并根据实际情况进行适当调整。
4.根据权利要求1所述的一种浅埋富水地质条件下连拱隧道进洞的施工方法,其特征在于,在步骤六中,注浆顺序:横向按照先两边、后中间的施工顺序,纵向按照由低至高的顺序进行钻孔和注浆,在同一排为防止相临施工孔之间窜浆,采用间隔施工法。
5.根据权利要求1所述的一种浅埋富水地质条件下连拱隧道进洞的施工方法,其特征在于,在步骤八中,管棚钢管规格:管棚采用外径φ108mm,壁厚6mm的热轧无缝钢管制作,钢管前端呈尖锥状,尾部焊接φ10加劲箍,管壁四周钻4排φ12mm压浆孔,钻孔间距为15cm,呈梅花形布置,施工时钢管沿隧道周边以1°外插角,钢花管总长为18m尾端留4.5m不钻孔,尖锥段长10cm,每节节长为3m、6m,每节钢管两端均预加工成外丝扣,同一断面内接头数量不超过总钢管数的50%,编号为奇数管的第一节采用3m钢花管,偶数管第一节采用6m钢管,以后每一节都采用6m长,最后打入的一节钢管结合套拱长度截取,钢管入土长度为设计长度16m。
CN202010465066.3A 2020-05-28 2020-05-28 一种浅埋富水地质条件下连拱隧道进洞的施工方法 Active CN111594229B (zh)

Priority Applications (2)

Application Number Priority Date Filing Date Title
CN202010465066.3A CN111594229B (zh) 2020-05-28 2020-05-28 一种浅埋富水地质条件下连拱隧道进洞的施工方法
US17/331,637 US20220106879A1 (en) 2020-05-28 2021-05-27 Construction method for entering shallow-buried multi-arch tunnel under water-rich geological conditions

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010465066.3A CN111594229B (zh) 2020-05-28 2020-05-28 一种浅埋富水地质条件下连拱隧道进洞的施工方法

Publications (2)

Publication Number Publication Date
CN111594229A true CN111594229A (zh) 2020-08-28
CN111594229B CN111594229B (zh) 2021-08-20

Family

ID=72184079

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010465066.3A Active CN111594229B (zh) 2020-05-28 2020-05-28 一种浅埋富水地质条件下连拱隧道进洞的施工方法

Country Status (2)

Country Link
US (1) US20220106879A1 (zh)
CN (1) CN111594229B (zh)

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302039A (zh) * 2020-10-26 2021-02-02 中交路桥建设有限公司 隧道洞口浅埋崩坡积体处理施工方法
CN113107539A (zh) * 2021-05-11 2021-07-13 青岛理工大学 一种管棚加固区最优厚度计算方法
CN113982603A (zh) * 2021-11-05 2022-01-28 广西路桥工程集团有限公司 一种隧道出口浅埋段崩坡积体处治方法
CN114718582A (zh) * 2022-06-08 2022-07-08 中铁九局集团第七工程有限公司 一种小净距水平节理页岩地质隧道洞口段的施工方法
CN115030165A (zh) * 2022-05-13 2022-09-09 中交一公局第四工程有限公司 一种用于超浅埋进洞下穿公路结构及施工方法
CN117780362A (zh) * 2024-02-27 2024-03-29 中铁十七局集团第五工程有限公司 一种超小净距隧道中岩柱置换与加固结构及其施工方法

Families Citing this family (17)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111537166A (zh) * 2020-05-09 2020-08-14 烟台华正仪器仪表有限公司 便携式汽车发动机汽缸泄漏率测试仪
CN114753401B (zh) * 2022-04-08 2023-05-26 中铁十九局集团第五工程有限公司 隧道底部溶洞处理的施工方法
CN115142854B (zh) * 2022-04-29 2023-03-24 北京城建设计发展集团股份有限公司 矿山法隧道单层衬砌结构体系及施工方法
CN114809698B (zh) * 2022-05-05 2022-10-25 兰州理工大学 一种基于实时监测的土遗址裂隙注浆方法
CN114992385A (zh) * 2022-05-30 2022-09-02 中建一局集团建设发展有限公司 一种大直径长距离钢制输水管道多接一拖拉施工方法
CN114922658A (zh) * 2022-06-14 2022-08-19 上海宝冶集团有限公司 一种山岭隧道车行横通道塌方处置加固方法
CN115324108B (zh) * 2022-07-19 2024-09-03 中建五局土木工程有限公司 明暗连拱偏压隧道的施工方法
CN114991811B (zh) * 2022-08-03 2022-10-28 交通运输部公路科学研究所 一种岩溶隧道穿越暗河区段的结构设计与防排水方法
CN115404845B (zh) * 2022-08-08 2024-01-30 中国建筑第七工程局有限公司 溶土洞处理施工方法
CN115859430B (zh) * 2022-12-01 2024-05-07 中铁二十三局集团有限公司 一种适用于富水软岩单线铁路隧道加固设计及施工方法
CN116104502B (zh) * 2023-01-09 2023-06-27 北京城建设计发展集团股份有限公司 用于加固穿越煤矿采空区山岭隧道的方法
CN116220740B (zh) * 2023-03-02 2023-10-27 云南省交通规划设计研究院有限公司 一种无中导连拱隧道后行洞的横向超前支护设计方法
CN116044455B (zh) * 2023-04-03 2023-06-23 湖南大学 一种用于隧道定向加固的注浆系统
CN116606108B (zh) * 2023-05-17 2024-05-24 江河安澜工程咨询有限公司 一种富水洞段tbm施工用高性能回填灌浆材料及其制备方法
CN117569271B (zh) * 2023-11-23 2024-08-20 水利部交通运输部国家能源局南京水利科学研究院 一种直线水工隧洞内的钢管内衬施工方法
CN117779841B (zh) * 2023-12-29 2024-09-13 中交城乡建设规划设计研究院有限公司 一种抗滑移管棚支护路基防护方法
CN118278211B (zh) * 2024-05-20 2024-08-16 长江勘测规划设计研究有限责任公司 一种确定水下灌浆孔口管镶铸长度的计算方法

Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02171497A (ja) * 1988-12-23 1990-07-03 Toko Tekko Kk 隧道掘削岩盤の内壁に対する一次吹付コンクリート施工法
JPH02308095A (ja) * 1989-05-24 1990-12-21 Ohbayashi Corp 岩盤の補強方法
CN202300445U (zh) * 2011-10-26 2012-07-04 中铁二十四局集团福建铁路建设有限公司 超浅埋下穿公路长管棚隧道支护结构
CN202544866U (zh) * 2011-12-23 2012-11-21 中铁十九局集团第五工程有限公司 大跨度地铁进洞门管棚超前支护装置
CN203756182U (zh) * 2014-04-04 2014-08-06 湖南省高速公路建设开发总公司 一种应用于软弱岩质区域浅埋公路隧道的支护结构
CN104389618A (zh) * 2014-10-13 2015-03-04 中铁二院重庆勘察设计研究院有限责任公司 一种连拱隧道洞身无室大管棚支护施工方法
CN104612713A (zh) * 2014-12-12 2015-05-13 中铁十九局集团有限公司 超浅埋地段隧道施工方法
CN204419195U (zh) * 2014-12-29 2015-06-24 山西省交通科学研究院 一种适用于隧道洞口段的支护结构型式
CN104818991A (zh) * 2015-03-30 2015-08-05 中铁二十四局集团福建铁路建设有限公司 一种浅埋偏压残坡积土隧道的施工方法
CN105156121A (zh) * 2015-10-08 2015-12-16 中铁二十五局集团第五工程有限公司 一种大断面黄土隧道进洞浅埋段的施工方法
CN208330411U (zh) * 2018-06-12 2019-01-04 云南省交通规划设计研究院 一种套拱离壁的隧道洞口管棚支护结构
CN109707399A (zh) * 2019-02-21 2019-05-03 中铁二院工程集团有限责任公司 隧道出洞支护构造及其施工方法
CN110056369A (zh) * 2019-05-05 2019-07-26 中交第三航务工程局有限公司 一种隧道进出口洞口的施工方法
CN110159308A (zh) * 2019-05-27 2019-08-23 中国五冶集团有限公司 一种隧道长管棚定位方法

Patent Citations (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH02171497A (ja) * 1988-12-23 1990-07-03 Toko Tekko Kk 隧道掘削岩盤の内壁に対する一次吹付コンクリート施工法
JPH02308095A (ja) * 1989-05-24 1990-12-21 Ohbayashi Corp 岩盤の補強方法
CN202300445U (zh) * 2011-10-26 2012-07-04 中铁二十四局集团福建铁路建设有限公司 超浅埋下穿公路长管棚隧道支护结构
CN202544866U (zh) * 2011-12-23 2012-11-21 中铁十九局集团第五工程有限公司 大跨度地铁进洞门管棚超前支护装置
CN203756182U (zh) * 2014-04-04 2014-08-06 湖南省高速公路建设开发总公司 一种应用于软弱岩质区域浅埋公路隧道的支护结构
CN104389618A (zh) * 2014-10-13 2015-03-04 中铁二院重庆勘察设计研究院有限责任公司 一种连拱隧道洞身无室大管棚支护施工方法
CN104612713A (zh) * 2014-12-12 2015-05-13 中铁十九局集团有限公司 超浅埋地段隧道施工方法
CN204419195U (zh) * 2014-12-29 2015-06-24 山西省交通科学研究院 一种适用于隧道洞口段的支护结构型式
CN104818991A (zh) * 2015-03-30 2015-08-05 中铁二十四局集团福建铁路建设有限公司 一种浅埋偏压残坡积土隧道的施工方法
CN105156121A (zh) * 2015-10-08 2015-12-16 中铁二十五局集团第五工程有限公司 一种大断面黄土隧道进洞浅埋段的施工方法
CN208330411U (zh) * 2018-06-12 2019-01-04 云南省交通规划设计研究院 一种套拱离壁的隧道洞口管棚支护结构
CN109707399A (zh) * 2019-02-21 2019-05-03 中铁二院工程集团有限责任公司 隧道出洞支护构造及其施工方法
CN110056369A (zh) * 2019-05-05 2019-07-26 中交第三航务工程局有限公司 一种隧道进出口洞口的施工方法
CN110159308A (zh) * 2019-05-27 2019-08-23 中国五冶集团有限公司 一种隧道长管棚定位方法

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
宋志荣: "《公路隧道穿越浅埋偏压大范围松散堆积体进洞施工技术》", 《铁道建筑技术》 *

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112302039A (zh) * 2020-10-26 2021-02-02 中交路桥建设有限公司 隧道洞口浅埋崩坡积体处理施工方法
CN113107539A (zh) * 2021-05-11 2021-07-13 青岛理工大学 一种管棚加固区最优厚度计算方法
CN113982603A (zh) * 2021-11-05 2022-01-28 广西路桥工程集团有限公司 一种隧道出口浅埋段崩坡积体处治方法
CN115030165A (zh) * 2022-05-13 2022-09-09 中交一公局第四工程有限公司 一种用于超浅埋进洞下穿公路结构及施工方法
CN115030165B (zh) * 2022-05-13 2024-01-19 中交一公局第四工程有限公司 一种用于超浅埋进洞下穿公路结构及施工方法
CN114718582A (zh) * 2022-06-08 2022-07-08 中铁九局集团第七工程有限公司 一种小净距水平节理页岩地质隧道洞口段的施工方法
CN114718582B (zh) * 2022-06-08 2022-09-06 中铁九局集团第七工程有限公司 一种小净距水平节理页岩地质隧道洞口段的施工方法
CN117780362A (zh) * 2024-02-27 2024-03-29 中铁十七局集团第五工程有限公司 一种超小净距隧道中岩柱置换与加固结构及其施工方法
CN117780362B (zh) * 2024-02-27 2024-04-30 中铁十七局集团第五工程有限公司 一种超小净距隧道中岩柱置换与加固结构及其施工方法

Also Published As

Publication number Publication date
US20220106879A1 (en) 2022-04-07
CN111594229B (zh) 2021-08-20

Similar Documents

Publication Publication Date Title
CN111594229B (zh) 一种浅埋富水地质条件下连拱隧道进洞的施工方法
CN110056369B (zh) 一种隧道进出口洞口的施工方法
CN110130927B (zh) 一种炭质板岩隧道大变形控制施工方法
CN104564128B (zh) 一种浅埋暗挖隧道施工用变形监测方法
CN104500077B (zh) 一种浅埋暗挖隧道穿越平房区施工方法
CN110374633B (zh) 隧道穿越松散体的洞口段施工方法
CN109723443B (zh) 隧道施工方法
CN111997624A (zh) 一种浅埋大断面暗挖矩形隧道施工方法
CN111852515A (zh) 一种隧道地层预加固综合注浆方法
CN105569051A (zh) 一种砂卵石漂石地质层基坑支护体系及施工方法
CN115539048A (zh) 一种用于浅埋偏压隧道洞口施工方法
CN110735436A (zh) 一种路堑岩质边坡加固结构
CN114411761B (zh) 新建筑施工时对拟建地铁隧道超前预支护体系及支护方法
CN112377208A (zh) 一种用于浅埋偏压隧道洞口施工方法
CN115324591A (zh) 一种饱和软黄土隧道分部降水-支护综合施工方法
CN116537794A (zh) 一种浅埋暗挖三洞大断面隧道下穿既有铁路组合施工方法
CN113309526B (zh) 一种地铁站扣拱开挖及支护的施工方法
CN114278313A (zh) 一种基于区间不同开挖工法转换的支护体系及施工方法
CN111622234B (zh) 一种斜竖向组合钢管桩承托的卸荷式薄壁箱型挡墙及施工工艺
CN110905529B (zh) 穿越滑坡体黄土隧道施工方法
CN115012955B (zh) 一种连拱隧道进口大管棚施工方法
CN105840209B (zh) 锚桩在隧道洞身段控制变形施工工法
CN114622574B (zh) 一种富水抛填土深基坑截水开挖支护方法、支护装置
CN115404885A (zh) 适于多台阶高陡边坡渐变式支挡施工方法
CN114086968B (zh) 一种下穿既有建筑暗挖隧道施工方法

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Address before: 450000 No. 116 Chengdong Road, Jinshui District, Henan, Zhengzhou

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

CB03 Change of inventor or designer information
CB03 Change of inventor or designer information

Inventor after: Tian Zhijie

Inventor after: Shi Ming

Inventor after: Bai Hailiang

Inventor after: Wang Yingdong

Inventor after: Li Yanzhi

Inventor after: Ding Chong

Inventor after: Yue Meng

Inventor after: Fang Yucheng

Inventor after: Zhang Yong

Inventor after: No grain left

Inventor after: Chen Xiaoyang

Inventor after: Jin Yang

Inventor after: Huang Qi

Inventor after: Yao Bing

Inventor after: Yang Zuojie

Inventor after: Gao Xiaobo

Inventor after: Deng Tingyan

Inventor before: Chen Xiaoyang

Inventor before: Wang Yingdong

Inventor before: Li Yanzhi

Inventor before: Ding Chong

Inventor before: Jin Yang

Inventor before: Huang Qi

Inventor before: Yao Bing

Inventor before: Yang Zuojie

Inventor before: Gao Xiaobo

Inventor before: Deng Tingyan

Inventor before: Shi Ming

Inventor before: Bai Hailiang

TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210723

Address after: 5-7 / F, Zhongjian building, 108 Chengdong Road, Jinshui District, Zhengzhou City, Henan Province, 450000

Applicant after: China Construction Seventh Bureau Transportation Construction Co.,Ltd.

Applicant after: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

Address before: No.267, 15th Street, Jingkai, Zhengzhou, Henan Province, 450000

Applicant before: CHINA CONSTRUCTION SEVENTH ENGINEERING DIVISION Corp.,Ltd.

GR01 Patent grant
GR01 Patent grant