CN111519666A - Pile-row filling type vibration isolation trench and construction method thereof - Google Patents

Pile-row filling type vibration isolation trench and construction method thereof Download PDF

Info

Publication number
CN111519666A
CN111519666A CN202010466853.XA CN202010466853A CN111519666A CN 111519666 A CN111519666 A CN 111519666A CN 202010466853 A CN202010466853 A CN 202010466853A CN 111519666 A CN111519666 A CN 111519666A
Authority
CN
China
Prior art keywords
vibration isolation
concrete
reinforced concrete
vibration
pile
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010466853.XA
Other languages
Chinese (zh)
Inventor
张延年
张于于
海洪
康楠
王铁源
闫明程
于洋
李志军
陈志燕
杜松岩
董宁
李琦琦
陈昊
刘柏男
张文洁
崔长青
王亭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010466853.XA priority Critical patent/CN111519666A/en
Publication of CN111519666A publication Critical patent/CN111519666A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D31/00Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution
    • E02D31/08Protective arrangements for foundations or foundation structures; Ground foundation measures for protecting the soil or the subsoil water, e.g. preventing or counteracting oil pollution against transmission of vibrations or movements in the foundation soil
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/62Insulation or other protection; Elements or use of specified material therefor
    • E04B1/92Protection against other undesired influences or dangers
    • E04B1/98Protection against other undesired influences or dangers against vibrations or shocks; against mechanical destruction, e.g. by air-raids
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H9/00Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate
    • E04H9/02Buildings, groups of buildings or shelters adapted to withstand or provide protection against abnormal external influences, e.g. war-like action, earthquake or extreme climate withstanding earthquake or sinking of ground
    • E04H9/021Bearing, supporting or connecting constructions specially adapted for such buildings

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • General Engineering & Computer Science (AREA)
  • Paleontology (AREA)
  • Business, Economics & Management (AREA)
  • Emergency Management (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Hydrology & Water Resources (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Bulkheads Adapted To Foundation Construction (AREA)

Abstract

The utility model provides a campshed filled vibration isolation ditch and construction method thereof, belongs to building vibration isolation field, including setting up slot, prefabricated reinforced concrete campshed, closing cap board, flexible filler material, concrete dado, cement mortar basement, rectangle recess, backfill, the former soil in place between building and the vibration source, both sides are equipped with two rows of prefabricated reinforced concrete campsheds and insert the underground in the slot, the prefabricated reinforced concrete campshed is arranged in the concrete dado lower part and is exposed, packs in the regional intussuseption of concrete dado and cement mortar basement wall enclosure and is filled with flexible filler material, prefabricated reinforced concrete campshed top is equipped with the closing cap board, the top of closing cap board is the backfill. The invention is mainly used for solving the problems of unstable structure and fatigue failure caused by the vibration of the important building structure due to the vibration source around the important building such as building or road construction, traffic vibration and the like. The invention has obvious vibration isolation effect and obvious protection effect on buildings.

Description

Pile-row filling type vibration isolation trench and construction method thereof
Technical Field
The invention belongs to the field of building vibration isolation, and particularly relates to a construction method of a row pile filling type vibration isolation trench.
Background
Along with the continuous development and progress of human society, the problems caused by vibration are more and more extensive, the quantity of the vibration generated in production and living of people is increased day by day, the life of people is influenced constantly, and a plurality of buildings with extremely high cultural historical value and great humanistic significance in China are threatened. Particularly, vibration caused by building or road construction and traffic vibration is vibration which is propagated from a vibration source to four places, and is elastic wave radiated to the periphery from the vibration source. The wave propagation method can be divided into three types, namely longitudinal waves (P waves), transverse waves (S waves) (both the longitudinal waves and the transverse waves belong to body waves) and surface waves (L waves).
The damage of the vibration to the building is found in the following three points: the transverse wave causes the horizontal swing of the building, which causes the damage of the building and has great destructive power. The method is equivalent to applying repeated action force in the horizontal direction to a house building, and when the magnitude and the caused deformation exceed the limit of the vibration resistance of a building beam structure, the whole building can be inclined or toppled to cause damage; the longitudinal wave makes the building produce jolt from top to bottom, because some buildings are long in the past, its vertical stability is relatively poor, when the vibration is great, can make the bottom increase very big dynamic load as load-carrying members' post in the twinkling of an eye, the dead weight on stack upper portion, when surpassing bottom post bearing capacity, thereby the bottom post can collapse and lead to destroying. 3. The buildings are affected by foundation soil disturbance generated by surrounding vibration sources and low-frequency and micro-vibration actions for a long time, and the buildings can generate permanent and irreversible fatigue damage, so that the safety of the buildings is obviously reduced, and various diseases occur.
The vibration isolation measure of the vibration isolation trench is that a vibration isolation barrier is arranged on a propagation path of vibration waves to damage the propagation path of the vibration waves, so that the loss of the energy of the vibration waves is caused, and the purpose of reducing or even eliminating the influence of the vibration waves on a protected building is achieved.
Current barrier vibration isolation is largely divided into two broad categories, namely continuous vibration isolation barriers and discontinuous barriers. The continuous vibration isolation barrier is typically represented by a vibration isolation trench, when an artificial vibration source with higher vibration frequency and earthquake vibration are performed, the properly designed vibration isolation trench can play a good vibration isolation effect, but part of vibration sources with lower vibration frequency have generally longer wavelength, if the hollow trench is selected as the vibration isolation barrier, the hollow trench is required to have great depth, the requirement has great operation difficulty in actual construction, if a continuous wall is selected as the vibration isolation barrier, a very large engineering quantity can be generated, the construction cost is greatly improved, and particularly, when the geological conditions of a construction site are very poor, the construction difficulty and the construction cost can be greatly improved.
The flexible filling material can effectively prevent waves from transmitting and diffracting and consuming vibration wave energy, the flexible filling material has an attenuation filtering effect on short-period vibration, such as waste foamed plastic, waste foamed concrete or sawdust, the rigid concrete plate has an attenuation filtering effect on long-period vibration, the long-period vibration waves are attenuated by layer consumption in a mode that the rigid concrete plate and the flexible filling material are alternately arranged in layers, so that the vibration response of a building is reduced, and the purpose of vibration isolation protection of the building is achieved.
Therefore, the method for constructing the vibration isolation trench by the prefabricated reinforced concrete row piles and the flexible filling materials to reduce the influence of the surrounding vibration on the building is discussed, and the method has important economic significance and environmental protection significance.
Disclosure of Invention
In order to solve the technical problems, the invention provides a method for constructing a row pile filling type vibration isolation trench, and mainly aims to develop a method for constructing a vibration isolation trench which has the advantages of obvious vibration isolation effect, simple structure, safety, reliability, convenience in transportation and construction, and can effectively reduce the influence of surrounding vibration on a building.
The technical scheme adopted by the invention is as follows:
a pile-filling type vibration isolation ditch comprises a groove, prefabricated reinforced concrete piles, sealing cover plates, flexible filling materials, concrete retaining walls, cement mortar bases, rectangular grooves, backfill soil and site original soil which are arranged between a building and a vibration source, wherein two rows of prefabricated reinforced concrete piles are arranged on two sides in the groove and inserted into the ground, the prefabricated reinforced concrete piles are prefabricated reinforced concrete members, the prefabricated reinforced concrete piles are arranged in the concrete retaining walls, the lower parts of the prefabricated reinforced concrete piles are exposed, the cement mortar bases are arranged at the bottoms of the concrete retaining walls, the flexible filling materials are filled in areas where the concrete retaining walls and the cement mortar bases enclose, the sealing cover plates are arranged above the prefabricated reinforced concrete piles and are prefabricated reinforced concrete members, the width of each sealing cover plate is larger than the distance between the prefabricated reinforced concrete piles on two sides, and rectangular bulges bent downwards by 90 degrees are arranged on two sides of each sealing cover plate, the upper part of the outer side of the precast reinforced concrete row pile is provided with a rectangular groove matched with the rectangular protrusion above the sealing cover plate, and backfill is arranged above the sealing cover plate.
Further, the cross section of the precast reinforced concrete row pile is circular, the diameter of the cross section is 10-20cm, the height is determined by the depth of the vibration isolation trench, specifically 3-5m, the depth of the vibration isolation trench is deeper as the vibration source is closer to the building, and the bottom end of the precast reinforced concrete row pile is a conical round end.
Furthermore, rectangular bulges at two sides of the sealing cover plate are 10cm in height, and the plate thickness is 100 mm.
Further, the flexible filling material is one or more of waste foam plastic, waste foam concrete or sawdust.
Furthermore, the vibration isolation trench is provided with a rectangular groove for positioning and installing the cover plate, the rectangular groove is arranged outside the precast reinforced concrete row pile, the width and the height of the rectangular groove are 10cm, and the bottom and two side walls of the rectangular groove are leveled by cement mortar.
A construction method of a row pile filling type vibration isolation trench comprises the following steps: firstly, selecting a position of a vibration isolation ditch, wherein the vibration isolation ditch is arranged on a foundation between a building and a main vibration source and is close to one side of the building, digging a vibration isolation groove between the building and the vibration source after the position of the vibration isolation ditch is selected, digging soil to be stacked beside the groove and used as backfill soil, wherein the digging mode of the vibration isolation ditch adopts a mode of digging twice and two layers, the first layer is dug for the first time, the digging is started from the ground, the depth of the first layer is one third of the whole height of the vibration isolation ditch, the second layer is dug for the second time, the digging width of the second layer is started from the bottom of the first layer, the digging width of the first layer is smaller than the width of the bottom of the first layer, the digging depth is reached from the bottom of the first layer, the digging whole depth is determined by the depth of the building foundation; after the groove is dug, pile sinking is carried out on two sides in the groove by a static pressure pile sinking method, the precast reinforced concrete row pile extends into the ground, the extending depth is not less than one third of the height of the pile, then concrete retaining walls are poured on two sides of the groove, a template is erected firstly, a 3-5cm gap is arranged between the template and the concrete row pile when the template is erected, then pouring concrete in situ behind the template to combine the concrete retaining wall and the concrete row pile into a whole, removing the template after the poured concrete reaches 70% of the design strength, forming a rigid side wall combining the row pile and the concrete into a whole on two sides in the groove, leveling the trench bottom, using cement mortar as a leveling substrate, after the cement mortar of the substrate is hardened to the designed strength, and filling flexible materials in the grooves, installing the sealing cover plates after the flexible materials are filled in the grooves, and backfilling to the ground and tamping after the whole vibration isolation ditch is constructed.
The invention has the beneficial effects that:
1. the vibration isolation structure has the advantages that the vibration waves are consumed and attenuated when the vibration waves meet the structure in a mode of combined vibration isolation of the rigid side wall formed by the precast reinforced concrete row piles and the concrete retaining wall and the flexible filling material, so that the vibration response of the building is reduced, the purpose of vibration isolation protection of the building is achieved, and the vibration isolation effect is obvious.
2. The prefabricated reinforced concrete row pile and the capping plate are prefabricated components, and the prefabricated reinforced concrete row pile and the capping plate are convenient to construct, high in construction speed and convenient to transport.
3. The filling materials used in the invention are common waste materials, so that the common waste materials are reused, and the cost and the resource can be saved.
Drawings
FIG. 1 is a schematic longitudinal sectional view of the vibration isolation trench according to the present invention;
fig. 2 is a cross-sectional view of the vibration isolation groove B-B of fig. 1.
In the figure: 1, precast reinforced concrete row piles; 2 is a sealing cover plate; 3 is a flexible filling material; 4 is a concrete retaining wall; 5 is a cement mortar base; 6 is a rectangular groove; 7 is backfill soil; 8 is the original soil of the field.
Detailed Description
The invention is described in detail below with reference to the figures and examples.
The utility model provides a campshed filling type vibration isolation ditch and construction method thereof, the vibration isolation ditch include the ditch of digging out, the prefabricated reinforced concrete campshed 1 of both sides in the ditch, flexible filling material 3 and the apron 2 in the ditch of arranging between building and vibration source. The precast reinforced concrete row piles 1 and the cover plates 2 are all reinforced concrete members precast in factories. The flexible filling material 3 includes waste foamed plastic, waste foamed concrete, sawdust, or the like. The assembled vibration isolation trench is a rigid body with hard outside and soft inside, the reinforced concrete rigid body can block the transmission of vibration waves from the outside, and the internal flexible filling material 3 for absorbing the vibration waves can effectively prevent the waves from transmitting and diffracting and consuming the energy of the vibration waves, so that the vibration isolation trench has a good vibration isolation effect. The invention is arranged on the foundation between the building and the main vibration source, and should be close to one side of the building as much as possible, the trench excavation depth is determined by the building foundation depth, 2-5m can be selected, if the building foundation is deeper, the vibration isolation trench depth can be increased for preventing excessive vibration waves from bypassing the vibration isolation trench.
The prefabricated reinforced concrete campshed 1 is a prefabricated reinforced concrete member and is arranged on two sides of the groove, the section is circular, the diameter of the section can be 10-20cm, the height is determined by the depth of the vibration isolation groove and can be 3-5m, the depth of the vibration isolation groove is deeper as the vibration source is closer to the building, and the bottom end of the prefabricated reinforced concrete campshed 1 is a conical round end; the cover plate 2 is a prefabricated reinforced concrete member, is arranged at the top of the groove and is responsible for covering the groove, rectangular bulges are arranged on two sides of the cover plate 2, the height of each bulge can be 10cm, and the thickness of the plate can be 100 mm.
The vibration isolation ditch is provided with a rectangular groove 6 for positioning and installing the cover sealing plate 2, the rectangular groove 6 is arranged outside the precast reinforced concrete row pile 1, the width and the height of the rectangular groove 6 can be set to be 10cm, and the bottom and two side walls of the rectangular groove 6 are trowelled by cement mortar.
The flexible filling material 3 is a material which mainly consumes vibration energy in the vibration isolation trench, the flexible filling material 3, such as waste foamed plastic, waste foamed concrete or sawdust, has low elastic modulus, has good attenuation and filtration effects on vibration, has good absorption and dispersion effects on vibration impact load, and can greatly consume the energy of vibration waves in the vibration propagation process, and the flexible filling material 3 used in the invention is a common waste material, so that the waste material can be recycled.
A row pile filling type vibration isolation ditch construction method comprises the steps of firstly selecting a position of a vibration isolation ditch, arranging the vibration isolation ditch on a foundation between an ancient building and a main vibration source, approaching one side of the ancient building as much as possible, digging a vibration isolation groove between the building and the vibration source after selecting the position of the vibration isolation ditch, piling soil beside the groove to be used as backfill soil, digging the vibration isolation ditch in a mode of digging twice and two layers, digging a first layer for the first time, starting to dig from the ground to reach a first elevation, taking one third of the whole height of the vibration isolation ditch as the depth of the first layer, digging a second layer for the second time, starting to dig the second layer at the bottom of the first layer, wherein the width of the dug ditch is smaller than the width of the bottom of the first layer, starting to dig from the first elevation to reach a second elevation, the whole depth of the dug is determined by the depth of the building foundation, and taking 2-5m as the whole depth if the building, the depth of the vibration isolation trench can be increased to prevent excessive vibration waves from bypassing the vibration isolation trench, and the width of the trench is 1-1.2m to ensure the vibration isolation effect. After a groove is excavated, pile sinking is carried out on two sides in the groove by a static pressure pile sinking method, a precast reinforced concrete row pile 1 extends into the ground to the third elevation, the extending depth is not less than one third of the height of the pile, then a concrete retaining wall 4 is poured on two sides of the groove, firstly a template is erected, a 3-5cm gap is arranged between the template and the concrete row pile when the template is erected, then concrete is poured behind the template, the concrete retaining wall 4 and the concrete row pile 1 are combined into a whole, the template is removed when the poured concrete reaches 70% of the designed strength, the row pile and the concrete are combined into a whole rigid side wall on two sides in the groove, then the groove bottom is leveled, cement mortar is used as a leveling base 5, after the cement mortar of the base 5 is hardened to the designed strength, a flexible material 3 is filled in the groove, a sealing cover plate 2 is installed after the flexible material is filled in the groove, and backfilling soil to the ground and tamping after the whole vibration isolation ditch is constructed.
Example 1:
as shown in fig. 1-2, fig. 1 is a sectional view a-a of fig. 2, and fig. 2 is a sectional view B-B of fig. 1, the present invention is installed on the ground between the building and the main vibration source, and should be as close to one side of the building as possible. When the vibration waves meet the vibration isolation protection device, the vibration waves are consumed and attenuated when the vibration waves meet the vibration isolation protection device in a mode of combining the rigid concrete side wall and the flexible filling material for vibration isolation, so that the vibration response of a building is reduced, and the purpose of vibration isolation protection of the building is achieved.
When the construction is carried out, firstly, selecting the position of a vibration isolation ditch, arranging the vibration isolation ditch on a foundation between an ancient building and a main vibration source, enabling the vibration isolation ditch to be close to one side of the ancient building as much as possible, digging a vibration isolation groove between the building and the vibration source after the position of the vibration isolation ditch is selected, piling soil dug beside the groove to be used as backfill soil, adopting a mode of digging twice and digging two layers, digging a first layer for the first time, digging from the ground to reach a first elevation, wherein the depth of the first layer can be one third of the whole height of the vibration isolation ditch, digging a second layer for the second time, digging the second layer at the bottom of the first layer, wherein the width of the dug ditch is smaller than the width of the bottom of the first layer, digging from the first elevation to a second elevation, the whole digging depth is determined by the depth of the building foundation, can be 2-5m, and if the building foundation is deeper, the depth of, the width of the groove is 1-1.2m to ensure the vibration isolation effect. After a groove is excavated, pile sinking is carried out on two sides in the groove by a static pressure pile sinking method, prefabricated reinforced concrete row piles extend into the ground to the third elevation, the depth of the prefabricated reinforced concrete row piles is not less than one third of the height of the pile, then concrete retaining walls are poured on two sides of the groove, a template is firstly erected, a 3-5cm gap is arranged between the template and the concrete row piles when the template is erected, then concrete is poured behind the template to combine the concrete retaining walls and the concrete row piles into a whole, the template is removed when the poured concrete reaches 70% of the designed strength, rigid side walls formed by combining the row piles and the concrete into a whole are formed on two sides in the groove, then the groove bottom is leveled, cement mortar is used as a leveling base, after the cement mortar of the base is hardened to the designed strength, then flexible materials are filled in the groove, a sealing cover plate is installed after the flexible materials are filled in the groove, and backfilling soil to the ground and tamping after the whole vibration isolation ditch is constructed.
The foregoing is only a preferred embodiment of the present invention, and it should be noted that, for those skilled in the art, various modifications and decorations can be made without departing from the principle of the present invention, and these modifications and decorations should also be regarded as the protection scope of the present invention.

Claims (6)

1. The utility model provides a row's stake filled type vibration isolation ditch which characterized in that: the concrete pile comprises a groove, prefabricated reinforced concrete piles (1), a cover sealing plate (2), flexible filling materials (3), a concrete retaining wall (4), a cement mortar base (5), a rectangular groove (6), backfill soil (7) and site original soil (8) which are arranged between a building and a vibration source, wherein two rows of prefabricated reinforced concrete piles (1) are arranged on two sides in the groove and inserted into the ground, the prefabricated reinforced concrete piles (1) are prefabricated reinforced concrete members, the prefabricated reinforced concrete piles (1) are arranged in the concrete retaining wall (4) and exposed from the lower part, the cement mortar base (5) is arranged at the bottom of the concrete retaining wall (4), the flexible filling materials (3) are filled in an area defined by the concrete retaining wall (4) and the cement mortar base (5), the cover sealing plate (2) is arranged above the prefabricated reinforced concrete piles (1), the sealing cover plate (2) is a prefabricated reinforced concrete component, the width of the sealing cover plate (2) is larger than the distance between prefabricated reinforced concrete row piles (1) on two sides, rectangular protrusions bent downwards by 90 degrees are arranged on two sides of the sealing cover plate (2), rectangular grooves (6) matched with the rectangular protrusions on the sealing cover plate are arranged on the upper portion of the outer side of the prefabricated reinforced concrete row piles (1), and backfill soil (7) is arranged above the sealing cover plate (2).
2. The pile-packed vibration isolation trench according to claim 1, wherein: the cross section of the precast reinforced concrete row pile (1) is circular, the diameter of the cross section is 10-20cm, the height is determined by the depth of the vibration isolation trench, specifically 3-5m, the closer the vibration source is to the building, the deeper the depth of the vibration isolation trench is, and the bottom end of the precast reinforced concrete row pile (1) is a conical round end.
3. The pile-packed vibration isolation trench according to claim 1, wherein: rectangular bulges are arranged on two sides of the sealing cover plate (2), the height of each bulge is 10cm, and the thickness of the plate is 100 mm.
4. The pile-packed vibration isolation trench according to claim 1, wherein: the flexible filling material (3) is one or more of waste foam plastic, waste foam concrete or sawdust.
5. The pile-packed vibration isolation trench according to claim 1, wherein: the vibration isolation ditch is provided with a rectangular groove (6) for positioning and installing the sealing cover plate (2), the rectangular groove (6) is arranged on the outer side of the precast reinforced concrete row pile (1), the width and height of the rectangular groove (6) are 10cm, and the bottom and two side walls of the rectangular groove (6) are leveled through cement mortar.
6. A construction method of a row pile filling type vibration isolation trench is characterized in that: the method comprises the following steps: firstly, selecting a position of a vibration isolation ditch, wherein the vibration isolation ditch is arranged on a foundation between a building and a main vibration source and is close to one side of the building, digging a vibration isolation groove between the building and the vibration source after the position of the vibration isolation ditch is selected, digging soil to be stacked beside the groove and used as backfill soil, wherein the digging mode of the vibration isolation ditch adopts a mode of digging twice and two layers, the first layer is dug for the first time, the digging is started from the ground, the depth of the first layer is one third of the whole height of the vibration isolation ditch, the second layer is dug for the second time, the digging width of the second layer is started from the bottom of the first layer, the digging width of the first layer is smaller than the width of the bottom of the first layer, the digging depth is reached from the bottom of the first layer, the digging whole depth is determined by the depth of the building foundation; after a groove is excavated, pile sinking is carried out on two sides in the groove by a static pressure pile sinking method, a precast reinforced concrete row pile (1) extends into the ground, the depth of the precast reinforced concrete row pile is not less than one third of the height of the pile, then a concrete retaining wall (4) is poured on two sides of the groove, a template is firstly erected, a 3-5cm gap is arranged between the template and the concrete row pile (1) when the template is erected, then concrete is poured behind the template, the concrete retaining wall (4) and the concrete row pile (1) are combined into a whole, the template is removed after the poured concrete reaches 70% of the designed strength, a rigid side wall formed by combining the row pile and the concrete into a whole is formed on two sides in the groove, then leveling is carried out on the bottom of the groove, cement mortar is used as a leveling base (5), and after the cement mortar of the base (5) is hardened to the designed strength, the groove is filled with a flexible material, and after the flexible material is filled, the sealing cover plate (2) is installed, and after the whole vibration isolation ditch is constructed, soil is backfilled to the ground and tamped.
CN202010466853.XA 2020-05-28 2020-05-28 Pile-row filling type vibration isolation trench and construction method thereof Pending CN111519666A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010466853.XA CN111519666A (en) 2020-05-28 2020-05-28 Pile-row filling type vibration isolation trench and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010466853.XA CN111519666A (en) 2020-05-28 2020-05-28 Pile-row filling type vibration isolation trench and construction method thereof

Publications (1)

Publication Number Publication Date
CN111519666A true CN111519666A (en) 2020-08-11

Family

ID=71907788

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010466853.XA Pending CN111519666A (en) 2020-05-28 2020-05-28 Pile-row filling type vibration isolation trench and construction method thereof

Country Status (1)

Country Link
CN (1) CN111519666A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111980074A (en) * 2020-08-27 2020-11-24 兰州理工大学 Empty trench pile-arranging combined vibration isolation system and construction method
CN111997100A (en) * 2020-09-16 2020-11-27 张延年 Waterproof anti-seepage vibration isolation empty trench and construction method thereof
CN113107021A (en) * 2021-04-20 2021-07-13 辽宁工程技术大学 Vibration isolation dike for preventing vibration rebound increase of high-speed rail and arrangement method thereof
CN113605268A (en) * 2021-08-17 2021-11-05 张静 Dust fall noise insulation device for road construction
CN113668417A (en) * 2021-09-27 2021-11-19 北京市科学技术研究院城市安全与环境科学研究所 Prefabricated assembled composite vibration isolation barrier and construction method thereof
CN113818495A (en) * 2021-09-16 2021-12-21 中南大学 Periodic pile-wall structure aiming at low-frequency surface wave vibration isolation and construction method
CN114808861A (en) * 2022-05-20 2022-07-29 四川省水利电力工程局有限公司 Gate dam building prefabricated member structure and construction method thereof
CN115961650A (en) * 2022-11-02 2023-04-14 兰州理工大学 Vibration control device for reducing earthquake response of adjacent liquid storage tanks and vibration control method thereof
CN116065633A (en) * 2023-02-17 2023-05-05 山东建大工程鉴定加固设计有限公司 Combined isolation protection method for subway station support pile construction close to electric power pipe ditch

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2069891U (en) * 1987-06-10 1991-01-23 浙江大学 Shock-isolating pile made of fine coal ash
CN101338590A (en) * 2008-08-13 2009-01-07 湖南大学 Composite shock insulation layer
CN104695292A (en) * 2015-03-26 2015-06-10 南京工业大学 Discontinuous vibration reduction and isolation device and forming method
CN205636829U (en) * 2016-01-27 2016-10-12 宁波易通建设有限公司 Take support system's damping trench
CN111042211A (en) * 2019-12-25 2020-04-21 东南大学 Vibration isolation ditch with viscoelastic vibration isolation and absorption device and vibration isolation method thereof
CN212427245U (en) * 2020-05-28 2021-01-29 张延年 Row pile filling type vibration isolation ditch

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN2069891U (en) * 1987-06-10 1991-01-23 浙江大学 Shock-isolating pile made of fine coal ash
CN101338590A (en) * 2008-08-13 2009-01-07 湖南大学 Composite shock insulation layer
CN104695292A (en) * 2015-03-26 2015-06-10 南京工业大学 Discontinuous vibration reduction and isolation device and forming method
CN205636829U (en) * 2016-01-27 2016-10-12 宁波易通建设有限公司 Take support system's damping trench
CN111042211A (en) * 2019-12-25 2020-04-21 东南大学 Vibration isolation ditch with viscoelastic vibration isolation and absorption device and vibration isolation method thereof
CN212427245U (en) * 2020-05-28 2021-01-29 张延年 Row pile filling type vibration isolation ditch

Cited By (14)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111980074A (en) * 2020-08-27 2020-11-24 兰州理工大学 Empty trench pile-arranging combined vibration isolation system and construction method
CN111997100A (en) * 2020-09-16 2020-11-27 张延年 Waterproof anti-seepage vibration isolation empty trench and construction method thereof
CN113107021A (en) * 2021-04-20 2021-07-13 辽宁工程技术大学 Vibration isolation dike for preventing vibration rebound increase of high-speed rail and arrangement method thereof
CN113605268B (en) * 2021-08-17 2024-04-02 张静 Noise isolation device for road construction
CN113605268A (en) * 2021-08-17 2021-11-05 张静 Dust fall noise insulation device for road construction
CN113818495A (en) * 2021-09-16 2021-12-21 中南大学 Periodic pile-wall structure aiming at low-frequency surface wave vibration isolation and construction method
CN113668417A (en) * 2021-09-27 2021-11-19 北京市科学技术研究院城市安全与环境科学研究所 Prefabricated assembled composite vibration isolation barrier and construction method thereof
CN113668417B (en) * 2021-09-27 2023-01-10 北京市科学技术研究院城市安全与环境科学研究所 Prefabricated assembled composite vibration isolation barrier and construction method thereof
CN114808861A (en) * 2022-05-20 2022-07-29 四川省水利电力工程局有限公司 Gate dam building prefabricated member structure and construction method thereof
CN114808861B (en) * 2022-05-20 2024-01-26 四川水发建设有限公司 Gate dam building prefabricated member structure and construction method thereof
CN115961650B (en) * 2022-11-02 2024-03-01 兰州理工大学 Vibration control device for reducing earthquake response of adjacent liquid storage tanks and vibration control method thereof
CN115961650A (en) * 2022-11-02 2023-04-14 兰州理工大学 Vibration control device for reducing earthquake response of adjacent liquid storage tanks and vibration control method thereof
CN116065633A (en) * 2023-02-17 2023-05-05 山东建大工程鉴定加固设计有限公司 Combined isolation protection method for subway station support pile construction close to electric power pipe ditch
CN116065633B (en) * 2023-02-17 2023-09-15 山东建大工程鉴定加固设计有限公司 Combined isolation protection method for subway station support pile construction close to electric power pipe ditch

Similar Documents

Publication Publication Date Title
CN111519666A (en) Pile-row filling type vibration isolation trench and construction method thereof
CN212427245U (en) Row pile filling type vibration isolation ditch
CN111519667A (en) Composite filling material assembled vibration isolation ditch
CN101250886B (en) Method for reinforcing masonry structure building base
CN110004919B (en) Foundation pit enclosure construction method used in pipeline influence range
CN111379282A (en) Assembled vibration isolation trench and construction method thereof
CN111519668A (en) Sandwich multilayer assembled vibration isolation trench
CN212582756U (en) Composite filling material assembled vibration isolation ditch
CN212582754U (en) Variable-depth modular anti-seepage vibration isolation ditch
CN212427247U (en) Sandwich multilayer assembled vibration isolation trench
CN111379279A (en) Variable-depth modular anti-seepage vibration isolation ditch and construction method thereof
CN111379281A (en) Cylindrical unit type vibration isolation trench and construction method thereof
CN212582753U (en) Assembled vibration isolation trench with wave block
JP6760529B1 (en) How to build a waterproof wall and a waterproof wall
CN212427249U (en) Assembled vibration isolation empty ditch
KR100360462B1 (en) Method to construct a structure on soft soil and the structure thereof
CN212427250U (en) Waterproof anti-seepage vibration isolation empty ditch
CN111379278A (en) Variable-depth assembled vibration isolation trench
CN113323030B (en) Vibration isolation structure for strengthening soil layer rigidity
CN215715515U (en) Municipal pipe network construction supporting integrated structure under unfavorable geological conditions
CN212427244U (en) Cylindrical unit type vibration isolation ditch
CN111997100A (en) Waterproof anti-seepage vibration isolation empty trench and construction method thereof
JP4410572B2 (en) Construction method of revetment for landfill
CN212801683U (en) Variable-depth assembled vibration isolation trench
CN111005410B (en) Building anti-floating structure and green construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination