CN111508461B - Information centralization management system and method for multi-sound masking system - Google Patents

Information centralization management system and method for multi-sound masking system Download PDF

Info

Publication number
CN111508461B
CN111508461B CN202010284793.XA CN202010284793A CN111508461B CN 111508461 B CN111508461 B CN 111508461B CN 202010284793 A CN202010284793 A CN 202010284793A CN 111508461 B CN111508461 B CN 111508461B
Authority
CN
China
Prior art keywords
sound masking
information
masking system
list
controller
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010284793.XA
Other languages
Chinese (zh)
Other versions
CN111508461A (en
Inventor
张建强
吴晓明
汪付强
张鹏
刘宏
王帅
刘祥志
马晓凤
郝秋赟
梁艳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shandong Computer Science Center National Super Computing Center in Jinan
Original Assignee
Shandong Computer Science Center National Super Computing Center in Jinan
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shandong Computer Science Center National Super Computing Center in Jinan filed Critical Shandong Computer Science Center National Super Computing Center in Jinan
Priority to CN202010284793.XA priority Critical patent/CN111508461B/en
Publication of CN111508461A publication Critical patent/CN111508461A/en
Application granted granted Critical
Publication of CN111508461B publication Critical patent/CN111508461B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G10MUSICAL INSTRUMENTS; ACOUSTICS
    • G10KSOUND-PRODUCING DEVICES; METHODS OR DEVICES FOR PROTECTING AGAINST, OR FOR DAMPING, NOISE OR OTHER ACOUSTIC WAVES IN GENERAL; ACOUSTICS NOT OTHERWISE PROVIDED FOR
    • G10K11/00Methods or devices for transmitting, conducting or directing sound in general; Methods or devices for protecting against, or for damping, noise or other acoustic waves in general
    • G10K11/16Methods or devices for protecting against, or for damping, noise or other acoustic waves in general
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02PCLIMATE CHANGE MITIGATION TECHNOLOGIES IN THE PRODUCTION OR PROCESSING OF GOODS
    • Y02P90/00Enabling technologies with a potential contribution to greenhouse gas [GHG] emissions mitigation
    • Y02P90/02Total factory control, e.g. smart factories, flexible manufacturing systems [FMS] or integrated manufacturing systems [IMS]

Abstract

The application discloses a multi-sound masking system information centralization management system and method, comprising the following steps: the system comprises a controller, an information centralization management device and at least two sound masking systems respectively connected with the information centralization management device, wherein each sound masking system comprises a sound masking system controller and at least one sound masking system load connected with the sound masking system controller; the information centralization management equipment is configured to carry out parameter configuration on each sound masking system; and receiving the working state data uploaded by each sound masking system, classifying the working state data, and sending the working state data to the controller according to the priority level of each data classification. The application can flexibly expand according to the size of the protection area, and realize the collaborative protection of the multi-sound masking system; the method can conveniently acquire the protection parameters of the area to be protected and flexibly configure the number and the positions of the sound masking systems.

Description

Information centralization management system and method for multi-sound masking system
Technical Field
The application relates to the technical field of sound masking systems, in particular to an information centralization management system and method for a multi-sound masking system.
Background
The statements in this section merely provide background information related to the present disclosure and may not necessarily constitute prior art.
The language sound is used as an important carrier for people to exchange and transfer information, and the carried information is abundant and has more occasions. When people talk, a large amount of sound information is generated. Because the indoor facility conditions and the safety conditions are changeable, sensitive sound information can leak to different degrees, and the security of speaking content is directly related.
With the development of information technology, eavesdropping means are increasingly advanced, and serious challenges are brought to sound information security. In order to improve the sound information security, sound information leakage protection is required. In particular, it relates to a confidential place of confidential information such as national policy, military, business, science and technology, etc., and its facility condition and security status are directly related to the smooth progress of confidential activity and the security of speaking content. Currently, in order to ensure sound information security, two approaches are mainly adopted: firstly, by changing the building structure, the leakage of sound information is reduced as much as possible; secondly, by installing an acoustic masking system, the leaked acoustic information is not easy to acquire.
The sound masking system achieves the purpose of preventing eavesdropping by additionally arranging an interference device at a position where sound information leakage is likely to occur, signals generated by the existing sound masking system are converted into masking signals such as sound signals and vibration signals through devices such as a sound generator and a vibration generator, and sound information protection is carried out on a certain area.
However, the inventor finds that the current sound masking system is greatly influenced by hardware design and specific environment system layout, and effective protection can not be carried out by infinitely increasing the protection terminals, so that the protection area of the single sound masking system is limited. As the number of the sound masking systems increases, the multiple sound masking systems are required to work simultaneously for protection, but as the sound masking systems work independently of each other and have no data interaction, the maintenance difficulty and the management cost increase along with the increase of the number of the sound masking systems.
Aiming at the problem of information centralization management when the existing common multi-sound masking system works cooperatively, no effective solution is proposed at present.
Disclosure of Invention
In view of this, the application provides a system and a method for information centralization management of a multi-sound masking system, which classifies the data information of all the sound masking systems and classifies the data information in a class, thereby greatly reducing the maintenance difficulty and the management cost when the sound masking systems are operated.
According to a first aspect of an embodiment of the present application, there is provided a multi-sound masking system information centralization management system including: the system comprises a controller, an information centralization management device and at least two sound masking systems respectively connected with the information centralization management device, wherein each sound masking system comprises a sound masking system controller and at least one sound masking system load connected with the sound masking system controller;
the information centralization management equipment carries out parameter configuration on each sound masking system by receiving a controller instruction;
and receiving the working state data uploaded by each sound masking system, classifying the working state data, and sending the working state data to the controller according to the priority level of each data classification.
According to a second aspect of the embodiment of the present application, there is provided a method for centrally managing information of a multi-sound masking system, including:
generating an initial equipment list, an initial theoretical configuration information list, a corresponding protection area diagram and a protection parameter description according to the arrangement condition of each sound masking system;
acquiring identifier information of each current sound masking system to form a current equipment list, and updating an initial equipment list according to the current equipment list;
parameter configuration is carried out on each sound masking system;
and receiving the working state data uploaded by each sound masking system, classifying the working state data, and uploading the data according to the priority level of each data classification.
Compared with the prior art, the application has the beneficial effects that:
(1) The application can flexibly expand according to the size of the protection area, and realizes the collaborative protection of the multi-sound masking system. Because the protection area of a single sound masking system is limited, when the protection area is increased and two or more sound masking systems are required to be protected, infinite expansion of the protection area of the system can be realized through the star-shaped expansion structure. The method can conveniently acquire the protection parameters of the area to be protected and flexibly configure the number and the positions of the sound masking systems.
(2) The multi-sound masking system is more convenient to maintain during collaborative protection, simpler to manage and lower in management cost. The parameter configuration and terminal data centralized management and monitoring during multi-system protection can be realized through the information centralized management method, and the effective supervision of the running states of each sound masking system and the working states of the vibration masking device and the sound masking device which are correspondingly installed are realized. The fastest, most efficient and most accurate equipment maintenance and management is realized.
Additional aspects of the application will be set forth in part in the description which follows and, in part, will be obvious from the description, or may be learned by practice of the application.
Drawings
FIG. 1 is a schematic diagram of a multi-sound masking system information centric management system according to an embodiment of the present application;
FIG. 2 is a schematic diagram of a method for centralized management of information of a multi-sound masking system according to an embodiment of the present application;
FIG. 3 is a schematic diagram of another multi-sound masking system information centric management system according to an embodiment of the present application;
fig. 4 is a schematic diagram of another method for centering information of a multi-sound masking system according to an embodiment of the present application.
Detailed Description
It should be noted that the following detailed description is exemplary and is intended to provide further explanation of the application. Unless defined otherwise, all technical and scientific terms used herein have the same meaning as commonly understood by one of ordinary skill in the art to which this application belongs.
It is noted that the terminology used herein is for the purpose of describing particular embodiments only and is not intended to be limiting of exemplary embodiments according to the present application. As used herein, unless the context clearly indicates otherwise, the singular forms also are intended to include the plural forms, and furthermore, it is to be understood that the terms "comprises" and "comprising" and any variations thereof are intended to cover non-exclusive inclusions, such as, for example, processes, methods, systems, products or devices that comprise a series of steps or units, are not necessarily limited to those steps or units that are expressly listed, but may include other steps or units that are not expressly listed or inherent to such processes, methods, products or devices.
Embodiments of the application and features of the embodiments may be combined with each other without conflict.
Example 1
According to an embodiment of the present application, there is provided an embodiment of a multi-sound masking system information centralization management system, referring to fig. 1, including: a controller, an information center management device, a 3-1-3-n sound masking system controller and a 4-1-4-n sound masking system load (vibration masker and sound masker).
The deployment mode of the sound masking system controller can be designed into a sound masking system controller centralization scheme according to the actual condition of the protection area. The controller, the information centralized management equipment and the sound masking system controller are centralized in a fixed area for centralized management, and the load of the sound masking system is fixed according to the actual protection area and position information is recorded.
Specifically, the sound masking system carries out sound information safety protection for the designated area, the controllers and the loads of the sound masking system can work independently without mutual influence, and information interaction is carried out between the controllers through the information management equipment.
The controller is used for storing default configuration parameters of the system, working state information and identification information of all sound masking systems in the system, a plan view of a protection area corresponding to each sound masking system and description and explanation of the protection parameters, and each sound masking system carries out parameter adjustment according to the structure of the protection area and the protection parameters and records the configuration parameters.
The information management equipment integrates and classifies the data issued by the controller and uploaded by each sound masking system and manages the data according to the data grade and the instruction grade.
Each sound masking system is installed and requires recording its corresponding protection area, corresponding protection parameters, system identifier, type of terminal carried by the system and its corresponding number.
And after the sound masking systems are required to be laid, generating an initial equipment list, a protection area plan corresponding to each sound masking system and a protection parameter description.
When the system is started, the controller sends a calling sound masking system identifier instruction to the information management equipment, the information management equipment acquires the sound masking systems and sends the acquired system identifiers, the acquired system identifiers are uploaded to the controller, all online sound masking system equipment lists are generated, and the online sound masking system equipment lists are compared with the local lists and updated.
If the controller call sound masking system identifier instruction request fails, automatically sending a second call instruction; if the controller local device list is consistent with the newly acquired device list, the local device list does not need to be updated;
if the controller local device list is inconsistent with the newly acquired device list, adding a new sound masking system to the local device list if all local list devices are contained; if the local whole device list is not contained, whether the device inconsistent with the newly acquired device list and the local device list belongs to the fault device or the removed device is confirmed, and the local device list is updated.
After the equipment list is updated, the configuration process of the multi-sound masking system information centralization management system is as follows:
when the system works, the sound masking system in the system can be configured in a mode of loading default parameters or in a mode of carrying out fine adjustment on certain parameters after loading the default parameters, and the current configuration information is stored in a local controller;
after receiving the configuration information through the information management device, the sound masking system executes updating the configuration information and stores the current configuration information.
The information management device maintains data interaction between the controller and the sound masking system.
The sound masking system stores configuration information and transmits real-time working state information to the controller through the information management device, and records the information to the controller locally.
After the parameter configuration of each sound masking system is completed, the working state information interaction process of the system is as follows:
the sound masking system classifies the sound masking system into three levels according to the alarm information, the state information and the configuration information, wherein the levels are the configuration information, the alarm information and the state information in sequence from high to low. When alarm information exists, the alarm information is sent preferentially; and preferentially sending state information when no alarm information exists. When a certain configuration parameter of a certain or all sound masking systems needs to be finely tuned in the working process of the system, the configuration information is sent preferentially.
Normally, parameter configuration work is not needed in the normal working process of the whole system.
The communication between the sound masking system and the information management device adopts an arbitration mechanism, and the communication between the information management device and the controller adopts an information priority mechanism.
The information management device receives the sound masking system information, classifies and sorts the sound masking system information according to the device identifier and the information level, and sends the sound masking system information to the controller, and the controller visualizes and records the system data after receiving the information of the information management device. When the information management equipment receives that the information of any sound masking system contains alarm information, the data containing the alarm information is packed and sent to the controller in priority, and the alarm information is prompted at the sound masking system end and simultaneously visualized and audible alarm prompt is performed at the controller end.
According to an embodiment of the present application, there is further provided an embodiment of a method for centrally managing information of a multi-sound masking system, referring to fig. 2, including the following processes:
the preparation process comprises the following steps:
step 1-1: and recording the spatial position of each sound masking system load, the protection area of the load and the corresponding theoretical protection parameters of the area.
Step 1-2: and connecting the load to the sound masking system controller, and recording the corresponding relation.
Step 1-3: and (3) generating a corresponding initial theoretical configuration information table and equipment list and a corresponding protection area image after the sound masking system controllers are connected with loads according to the text description and the data formed in the step (1).
The configuration process comprises the following steps:
step 2-1: the controller sends a calling device instruction to the information centralization management device;
step 2-2: the information centralization management equipment receives the instruction of the controller and replies confirmation information to the controller;
step 2-3: the information centralization management equipment receives the instructions of each sound masking system and analyzes the equipment identifier;
there are two cases at this time:
case 1: the sound masking system works for the first time, and the configuration information and the state information are zero data except the identifier information.
Case 2: the sound masking system does not operate for the first time, and the configuration information and the state information are actual data except the identifier information.
Step 2-4: the information centralization management device sends the analysis device list to the controller. And comparing the newly acquired list information with the equipment list formed in the preparation process by the controller, and checking whether the newly acquired list information is consistent with the equipment list.
In the system operation process, when a certain sound masking system needs to be replaced, the configuration process steps 1 to 4 are repeated, after the equipment list is confirmed, the new equipment list is covered with the equipment list generated in the preparation process, and the new equipment list is stored.
When a certain sound masking system is needed to be added to the whole system, checking whether all devices in the original device list are contained in the new list, and if the difference between the number of the new device list and the number of the original device list is the number of the newly added sound masking system, covering the original device list by the new device list and storing the new device list.
When the whole system needs to reduce a certain sound masking system, checking whether the new list is contained by all devices in the original device list, and if so, covering the new device list by the original device list and saving the new device list, wherein the difference value between the number of the original device list and the number of the new device list is the number of the sound masking system subtracted.
Step 2-5: the controller sends a calling configuration instruction to the information centralization management equipment;
step 2-6: the information centralization management equipment receives the instruction of the controller and replies confirmation information to the controller;
step 2-7: the information center management equipment receives the instructions of each sound masking system and analyzes the configuration information of each equipment
Extinguishing; there are two cases at this time:
case 1: the sound masking system works for the first time, and the configuration information and the state information are zero data except the identifier information.
Case 2: the sound masking system does not operate for the first time, and the configuration information and the state information are actual data except the identifier information.
Step 2-8: the information centralization management device transmits the analyzed configuration information of each device to the controller. The controller newly acquires whether the configuration information of each device is zero data.
When the configuration information is zero data, an initial theoretical configuration information list generated in the preparation process is extracted, the controller sends the configuration information in the initial configuration list to the information centralization management equipment, and the information centralization management equipment sends the information to the target equipment for configuration and stores the configuration information locally in the sound masking system controller.
When the acquired configuration information is non-zero data, the controller records the configuration information and goes to step 2-10;
when a certain sound masking system is needed to be added to the whole system, the preparation process information of the part with the added area to be protected is required to be re-acquired, and the corresponding initial theoretical configuration information table and the protection area image of each sound masking system are updated.
Because the newly added sound masking system has no configuration information, the controller acquires zero data of the configuration information, extracts a corresponding initial theoretical configuration information list regenerated in the preparation process, sends the configuration information in the initial configuration list to the information centralized management equipment, and the information centralized management equipment encrypts and sends the information to the newly added equipment for configuration and locally stores the configuration information in the sound masking system controller.
When the whole system needs to reduce a certain sound masking system, the preparation process information of the part of the protection area corresponding to the rest sound masking system needs to be re-acquired, and the corresponding initial theoretical configuration information table and the protection area image of each sound masking system are updated. And reconfiguring each sound masking system according to the new initial theoretical configuration information table.
Step 2-9: and checking the protection effect of the whole system after the configuration according to the generated initial theoretical configuration parameters, and fine-tuning the configuration parameters of each sound masking system according to the protection effect. After the protection effect is confirmed, the configuration parameters of each sound masking system are saved again at the controller end, and a new configuration information table is generated and saved.
Step 2-10: in the process of step 2-8, when the acquired configuration information is non-zero data, the configuration information recorded by the controller is compared with the trimmed configuration information stored by the controller in step 2-9, and if the configuration information is inconsistent with the configuration information stored in step 2-9, the configuration information needs to be reconfigured into the configuration information stored in step 2-9.
If the controller part or a certain load of any sound masking system needs to be replaced, when the load position is unchanged, when the steps 2-8 are executed, the preparation process and the initial theoretical configuration information table generated in the preparation process and the protection area image of each sound masking system do not need to be updated again, and only the configuration information stored in the steps 2-9 need to be reconfigured. The updating of the device list is carried out according to the steps 2-1 to 2-4.
The monitoring process comprises the following steps:
after the equipment list is updated and the configuration information of each sound masking system is confirmed, the information centralization management equipment acquires the monitoring information of each sound masking system, performs classified management according to alarm information and state information and sends the classified management to the controller for visualization.
Example two
According to an embodiment of the present application, there is provided an embodiment of a multi-sound masking system information centralization management system, referring to fig. 3, including: a controller, an information center management device, a 3-1-3-n sound masking system controller and a 4-1-4-n sound masking system load (vibration masker and sound masker).
The deployment mode of the sound masking system controller can be designed into a sound masking system controller localization scheme according to the actual situation of the protection area. The controller and the information centralized management equipment are centralized in a fixed area for centralized management, and the sound masking system is fixed according to the actual protection area and records position information.
The functions and implementation manners of the controller, the information-centric managing device, the sound masking system controller and the sound masking system load are the same as those in the first embodiment, and will not be described again.
According to an embodiment of the present application, there is further provided an embodiment of a method for centrally managing information of a multi-sound masking system, referring to fig. 4, including the following processes:
the preparation process comprises the following steps:
step 1-1: and recording the spatial position of the load of each sound masking system, the protection area of the system and the corresponding theoretical protection parameters of the area.
Step 1-2: and (3) generating a corresponding initial theoretical configuration information table, a corresponding equipment list and a corresponding sound masking system protection area image from the text description and the data formed in the step (1).
The configuration process comprises the following steps:
step 2-1: and the controller sends a calling device instruction to the information centralization management device.
Step 2-2: the information centralization management equipment receives the instruction of the controller and replies confirmation information to the controller.
Step 2-3: the information centric management device receives each sound masking system instruction and parses the device identifier.
There are two cases at this time:
case 1: the sound masking system works for the first time, and the configuration information and the state information are zero data except the identifier information.
Case 2: the sound masking system does not operate for the first time, and the configuration information and the state information are actual data except the identifier information.
Step 2-4: the information centralization management device sends the analysis device list to the controller. And comparing the newly acquired list information with the equipment list formed in the preparation process by the controller, and checking whether the newly acquired list information is consistent with the equipment list.
And (3) in the whole system operation process, when a certain sound masking system needs to be replaced, repeating the configuration process steps 1 to 4, and after confirming the equipment list, covering the equipment list generated in the preparation process with a new equipment list and storing the new equipment list.
When a certain sound masking system is needed to be added to the whole system, checking whether all devices in the original device list are contained in the new list, and if the difference between the number of the new device list and the number of the original device list is the number of the newly added sound masking system, covering the original device list by the new device list and storing the new device list.
When the whole system needs to reduce a certain sound masking system, checking whether the new list is contained by all devices in the original device list, and if so, covering the new device list by the original device list and saving the new device list, wherein the difference value between the number of the original device list and the number of the new device list is the number of the sound masking system subtracted.
Step 2-5: and the controller sends a calling configuration instruction to the information centralization management equipment.
Step 2-6: the information centralization management equipment receives the instruction of the controller and replies confirmation information to the controller.
Step 2-7: the information centralization management equipment receives the instructions of each sound masking system and analyzes the configuration information of each equipment. There are two cases at this time:
case 1: the sound masking system works for the first time, and the configuration information and the state information are zero data except the identifier information.
Case 2: the sound masking system does not operate for the first time, and the configuration information and the state information are actual data except the identifier information.
Step 2-8: the information centralization management device transmits the analyzed configuration information of each device to the controller. The controller newly acquires whether the configuration information of each device is zero data.
When the configuration information is zero data, an initial theoretical configuration information list generated in the preparation process is extracted, the controller sends the configuration information in the initial configuration list to the information centralization management equipment, and the information centralization management equipment sends the information to the target equipment for configuration and stores the configuration information locally in the sound masking system controller.
When the acquired configuration information is non-zero data, the controller records the configuration information and goes to the step 2-10;
when a certain sound masking system is needed to be added to the whole system, the preparation process information of the part with the added area to be protected is required to be re-acquired, and the corresponding initial theoretical configuration information table and the protection area image of each sound masking system are updated.
Because the newly added sound masking system has no configuration information, the controller acquires zero data of the configuration information, extracts a corresponding initial theoretical configuration information list regenerated in the preparation process, sends the configuration information in the initial configuration list to the information centralized management equipment, and the information centralized management equipment encrypts and sends the information to the newly added equipment for configuration and locally stores the configuration information in the sound masking system controller.
When the whole system needs to reduce a certain sound masking system, the preparation process information of the part of the protection area corresponding to the rest sound masking system needs to be re-acquired, and the corresponding initial theoretical configuration information table and the protection area image of each sound masking system are updated.
And reconfiguring each sound masking system according to the new initial theoretical configuration information table.
Step 2-9: and checking the protection effect of the whole system after the configuration according to the generated initial theoretical configuration parameters, and fine-tuning the configuration parameters of each sound masking system according to the protection effect. After the protection effect is confirmed, the configuration parameters of each sound masking system are saved again at the controller end, and a new configuration information table is generated and saved.
Step 2-10: in the process of step 2-8, when the acquired configuration information is non-zero data, the configuration information recorded by the controller is compared with the trimmed configuration information stored by the controller in step 2-9, and if the configuration information is inconsistent with the configuration information stored in step 2-9, the configuration information needs to be reconfigured into the configuration information stored in step 2-9. If the controller part or a certain load of any sound masking system needs to be replaced, when the load position is unchanged, when the steps 2-8 are executed, the preparation process and the initial theoretical configuration information table generated in the preparation process and the protection area image of each sound masking system do not need to be updated again, and only the configuration information stored in the steps 2-9 need to be reconfigured. The updating of the device list is carried out according to the steps 2-1 to 2-4.
The monitoring process comprises the following steps:
after the equipment list is updated and the configuration information of each sound masking system is confirmed, the information centralization management equipment acquires the monitoring information of each sound masking system, performs classified management according to alarm information and state information and sends the classified management to the controller for visualization.
While the foregoing description of the embodiments of the present application has been presented in conjunction with the drawings, it should be understood that it is not intended to limit the scope of the application, but rather, it is intended to cover all modifications or variations within the scope of the application as defined by the claims of the present application.

Claims (6)

1. A multi-sound masking system information centralization management system, comprising: the system comprises a controller, an information centralization management device and at least two sound masking systems respectively connected with the information centralization management device, wherein each sound masking system comprises a sound masking system controller and at least one sound masking system load connected with the sound masking system controller;
the information centralization management equipment carries out parameter configuration on each sound masking system by receiving a controller instruction;
the working state data uploaded by each sound masking system is received, classified and sent to the controller according to the priority level of each data classification;
the information centralization management equipment generates an initial equipment list, an initial protection area plan corresponding to each sound masking system and a protection parameter description according to the layout parameters of each sound masking system;
the information centralization management equipment receives a calling sound masking system identifier instruction issued by the controller, acquires the system identifier of each sound masking system in real time, and uploads the system identifier to the controller;
the controller generates an online sound masking system equipment list according to the received system identifiers of the sound masking systems;
comparing the list with a list of devices stored locally by the controller; if the list is inconsistent with the device list stored locally by the controller, updating the device list stored locally by the controller according to the newly acquired list;
classifying the working state data, and transmitting the working state data to a controller according to the priority level of each data classification, wherein the process comprises the following steps: dividing the working state data of the sound masking system into: alarm information, state information and configuration information; and the priority order of the data is set as follows from high to low in sequence: configuration information, alarm information, and status information.
2. The multi-sound masking system information centralization management system of claim 1 wherein the controller is configured to obtain and store device list information, configuration information, operating status information, and device identification information for each sound masking system.
3. The multi-sound masking system information centralization management system according to claim 1, wherein the process of parameter configuration of each sound masking system by the information centralization management equipment comprises:
when the equipment list is unchanged, the information centralization management equipment acquires the current configuration information of each sound masking system and uploads the current configuration information to the controller;
if the configuration information received by the controller is zero, the configuration information in the initial theoretical configuration information list is sent to the information centralization management equipment, and the information centralization management equipment sends the received configuration information to the target equipment for parameter configuration;
if the configuration information received by the controller is not zero, comparing the configuration information with the configuration information in the initial theoretical configuration information list, and if the configuration information is inconsistent, sending the configuration information in the initial theoretical configuration information list to the information center management equipment to update the configuration information of each sound masking system.
4. The multi-sound masking system information centralization management system according to claim 1, wherein the process of parameter configuration of each sound masking system by the information centralization management equipment comprises:
when the equipment list is increased or decreased, regenerating an initial theoretical configuration information table and each sound masking system protection area image according to the changed equipment list; and re-configuring parameters of each sound masking system according to the changed initial theoretical configuration information table.
5. A method for centrally managing information of a multi-sound masking system, comprising:
generating an initial equipment list, an initial theoretical configuration information list, a corresponding protection area diagram and a protection parameter description according to the arrangement condition of each sound masking system;
acquiring identifier information of each current sound masking system to form a current equipment list, and updating an initial equipment list according to the current equipment list;
parameter configuration is carried out on each sound masking system;
receiving the working state data uploaded by each sound masking system, classifying the working state data, and uploading the data according to the priority level of each data classification;
the information centralization management equipment generates an initial equipment list, an initial protection area plan corresponding to each sound masking system and a protection parameter description according to the layout parameters of each sound masking system;
the information centralization management equipment receives a calling sound masking system identifier instruction issued by the controller, acquires the system identifier of each sound masking system in real time, and uploads the system identifier to the controller;
the controller generates an online sound masking system equipment list according to the received system identifiers of the sound masking systems;
comparing the list with a list of devices stored locally by the controller; if the list is inconsistent with the device list stored locally by the controller, updating the device list stored locally by the controller according to the newly acquired list;
classifying the working state data, and transmitting the working state data to a controller according to the priority level of each data classification, wherein the process comprises the following steps: dividing the working state data of the sound masking system into: alarm information, state information and configuration information; and the priority order of the data is set as follows from high to low in sequence: configuration information, alarm information, and status information.
6. The method for centrally managing information of a multiple sound masking system according to claim 5, wherein the process of parameter configuration for each sound masking system when the list of devices is unchanged comprises:
if the current configuration parameters of the sound masking system are zero, carrying out parameter configuration on the target equipment according to the parameters in the initial theoretical configuration information list;
if the current configuration parameters of the sound masking system are not zero, comparing the current configuration information with the configuration information in an initial theoretical configuration information list, and if the current configuration information is inconsistent with the configuration information in the initial theoretical configuration information list, updating the configuration information in the initial theoretical configuration information list;
when the equipment list is increased or decreased, the process of parameter configuration for each sound masking system comprises the following steps:
regenerating an initial theoretical configuration information table and each sound masking system protection area image according to the changed equipment list; and re-configuring parameters of each sound masking system according to the changed initial theoretical configuration information table.
CN202010284793.XA 2020-04-13 2020-04-13 Information centralization management system and method for multi-sound masking system Active CN111508461B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010284793.XA CN111508461B (en) 2020-04-13 2020-04-13 Information centralization management system and method for multi-sound masking system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010284793.XA CN111508461B (en) 2020-04-13 2020-04-13 Information centralization management system and method for multi-sound masking system

Publications (2)

Publication Number Publication Date
CN111508461A CN111508461A (en) 2020-08-07
CN111508461B true CN111508461B (en) 2023-11-03

Family

ID=71877513

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010284793.XA Active CN111508461B (en) 2020-04-13 2020-04-13 Information centralization management system and method for multi-sound masking system

Country Status (1)

Country Link
CN (1) CN111508461B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6188771B1 (en) * 1998-03-11 2001-02-13 Acentech, Inc. Personal sound masking system
CN1505811A (en) * 2001-02-26 2004-06-16 777388安大略有限公司 Networked sound masking and paging system
JP2012073411A (en) * 2010-09-29 2012-04-12 Yamaha Corp Masker sound output control device
JP2012226348A (en) * 2011-04-04 2012-11-15 Yamaha Corp Masking system, masking environment control device, masker sound generation device, and information terminal
EP3070709A1 (en) * 2015-03-20 2016-09-21 Yamaha Corporation Sound masking apparatus and sound masking method
CN106873553A (en) * 2017-02-09 2017-06-20 北京东土科技股份有限公司 Field apparatus control management method and device based on industry internet operating system
CN206849492U (en) * 2017-06-27 2018-01-05 山东省计算中心(国家超级计算济南中心) Sound masking system based on auditory localization
CN109343500A (en) * 2018-11-28 2019-02-15 上海风语筑展示股份有限公司 A kind of centralization shows monitoring nodes management system and method
KR20190029397A (en) * 2017-09-11 2019-03-20 삼성전자주식회사 Apparatus and method for transmitting control information in wireless communication system
CN110568290A (en) * 2019-09-18 2019-12-13 山东省计算中心(国家超级计算济南中心) Real-time monitoring device for load working state of sound masking system under multi-load condition

Family Cites Families (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2003037035A1 (en) * 2001-10-24 2003-05-01 Acentech, Inc. Sound masking system
US8107639B2 (en) * 2006-06-29 2012-01-31 777388 Ontario Limited System and method for a sound masking system for networked workstations or offices
JP4245060B2 (en) * 2007-03-22 2009-03-25 ヤマハ株式会社 Sound masking system, masking sound generation method and program
US9579499B2 (en) * 2012-09-17 2017-02-28 Cochlear Limited Sound processing using a masking model
US10497354B2 (en) * 2016-06-07 2019-12-03 Bose Corporation Spectral optimization of audio masking waveforms
GB2562507B (en) * 2017-05-17 2020-01-29 Jaguar Land Rover Ltd Apparatus and method for privacy enhancement
CN113015989A (en) * 2018-06-08 2021-06-22 通信安全集团公司 Block chain supervision

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6188771B1 (en) * 1998-03-11 2001-02-13 Acentech, Inc. Personal sound masking system
CN1505811A (en) * 2001-02-26 2004-06-16 777388安大略有限公司 Networked sound masking and paging system
JP2012073411A (en) * 2010-09-29 2012-04-12 Yamaha Corp Masker sound output control device
JP2012226348A (en) * 2011-04-04 2012-11-15 Yamaha Corp Masking system, masking environment control device, masker sound generation device, and information terminal
EP3070709A1 (en) * 2015-03-20 2016-09-21 Yamaha Corporation Sound masking apparatus and sound masking method
CN106873553A (en) * 2017-02-09 2017-06-20 北京东土科技股份有限公司 Field apparatus control management method and device based on industry internet operating system
CN206849492U (en) * 2017-06-27 2018-01-05 山东省计算中心(国家超级计算济南中心) Sound masking system based on auditory localization
KR20190029397A (en) * 2017-09-11 2019-03-20 삼성전자주식회사 Apparatus and method for transmitting control information in wireless communication system
CN109343500A (en) * 2018-11-28 2019-02-15 上海风语筑展示股份有限公司 A kind of centralization shows monitoring nodes management system and method
CN110568290A (en) * 2019-09-18 2019-12-13 山东省计算中心(国家超级计算济南中心) Real-time monitoring device for load working state of sound masking system under multi-load condition

Also Published As

Publication number Publication date
CN111508461A (en) 2020-08-07

Similar Documents

Publication Publication Date Title
CN110221567B (en) Intelligent management and control system based on 5G internet of things technology
CN102224470B (en) For providing the system and method for control and automation services
JPH02100528A (en) Reorganization of dynamic group in trunk-type radio communication system
JP2001522180A (en) "Plug and Play" operation and maintenance architecture for wireless base stations
CN108011770B (en) Multistage distributed monitoring system of very high frequency ground-to-air communication sharing system
CN102710436B (en) A kind of network device management method, device, relevant device and system
DE102006033503A1 (en) Wireless power transmission systems and methods
WO2010108339A1 (en) A shield system for seamless graded management and use controlling method thereof
CN110798459B (en) Multi-safety-node linkage defense method based on safety function virtualization
CN101022367A (en) Network management method and system
CN107092243B (en) Power supply control intelligent safety monitoring system based on Internet of things
WO2019228400A1 (en) Data processing system and method
CN110854725B (en) Service linkage system and method between multiple power substations
CN110633085B (en) Relay protection setting calculation method and device based on micro-service architecture
CN111508461B (en) Information centralization management system and method for multi-sound masking system
CN102238571B (en) Apparatus of Internet of Things machine to machine/man (M2M) business processing, system and method thereof
US8619625B2 (en) Network and method for the computer-assisted operation of an autonomous network comprising a plurality of autonomous terminals
CN110932905B (en) Outdoor cabinet environment monitoring method and system
CN111654470B (en) Robot system state monitoring method, equipment and storage medium
CN108755502A (en) A kind of intelligent barrier gate and its control method
JPH0865759A (en) Building managing device
CN110830327A (en) Method for realizing process layer network full link monitoring and alarming
JPH04213246A (en) Fault information transmission suppression system
CN113656092B (en) Plug-in-based SCADA system driving protocol efficient management method
CN214755725U (en) Patch virus library management system and power system for transformer substation

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant