CN111501813A - High bearing platform building pile foundation - Google Patents

High bearing platform building pile foundation Download PDF

Info

Publication number
CN111501813A
CN111501813A CN202010284889.6A CN202010284889A CN111501813A CN 111501813 A CN111501813 A CN 111501813A CN 202010284889 A CN202010284889 A CN 202010284889A CN 111501813 A CN111501813 A CN 111501813A
Authority
CN
China
Prior art keywords
sleeve
precast tubular
tubular pile
bolt
pile foundation
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010284889.6A
Other languages
Chinese (zh)
Inventor
许灵杰
夏建新
叶益环
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Xiamen Foundation Engineering Co ltd
Original Assignee
Zhejiang Xiamen Foundation Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Xiamen Foundation Engineering Co ltd filed Critical Zhejiang Xiamen Foundation Engineering Co ltd
Priority to CN202010284889.6A priority Critical patent/CN111501813A/en
Publication of CN111501813A publication Critical patent/CN111501813A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/60Piles with protecting cases
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention discloses a high bearing platform building pile foundation, which is characterized in that: locate the sleeve at precast tubular pile top including precast tubular pile and cover, be equipped with grout hole, exhaust hole and many anchor muscle on the sleeve, the sleeve can be dismantled and locate on the precast tubular pile. The high-bearing-platform building pile foundation injects concrete slurry into the precast tubular pile at high pressure through the grouting hole, so that the precast tubular pile, the sleeve, the inner sleeve, the bolt, the reinforcing rib and the diagonal rod are integrated, and the integrity, reliability and shearing resistance of the pile foundation are improved; after the bearing platform is connected through the anchoring ribs, the structural stability of the pile foundation and the bearing platform is improved due to the arrangement of the sleeve, the inner sleeve, the bolt and the reinforcing ribs, and the bending resistance and the shearing resistance of the connecting position of the pile foundation and the bearing platform are also improved.

Description

High bearing platform building pile foundation
Technical Field
The invention relates to a high bearing platform building pile foundation.
Background
At present, the precast tubular pile of the building pile foundation mostly adopts a concrete cast-in-place mode, the connection between the precast tubular pile and a bearing platform is realized by arranging an anchoring rib at the top of the precast tubular pile, the reliability and the shearing resistance of the pile body of the building pile foundation are poor, and the structural stability of the connection position of the pile body and the bearing platform is poor, and the bending resistance and the shearing resistance are also poor.
Disclosure of Invention
In view of the defects of the background art, the invention aims to provide a high-bearing-platform building pile foundation with better integrity, reliability and structural stability.
Therefore, the invention is realized by adopting the following technical scheme:
high cushion cap building pile foundation, characterized by: locate the sleeve at precast tubular pile top including precast tubular pile and cover, be equipped with grout hole, exhaust hole and many anchor muscle on the sleeve, the sleeve can be dismantled and locate on the precast tubular pile.
Furthermore, many slant poles are worn to be equipped with in precast tubular pile middle part.
Further, be equipped with the interior sleeve pipe of laminating with the precast tubular pile inner wall in the sleeve, be equipped with the relative bolt hole of multilayer on the precast tubular pile, be equipped with the mounting hole that can aim at the bolt hole on sleeve and the interior sleeve pipe.
Further, precast tubular pile middle part is equipped with the slant through-hole, and slant through-hole inner wall is equipped with the slant spout, and the slant spout end is equipped with communicating lock groove of buckling with it, the slant pole middle part is equipped with can be at the slant spout, buckle the lug of lock inslot activity.
Furthermore, the inner wall of the inner sleeve is provided with a plurality of layers of reinforcing parts, and each layer of reinforcing part comprises a plurality of reinforcing ribs which are obliquely arranged downwards.
Furthermore, every layer is relative bolt hole spiro union has worn out precast tubular pile's bolt, and the bolt passes sleeve and interior sheathed tube mounting hole, and the nut fastening is passed through at the both ends of bolt and becomes sleeve, precast tubular pile and interior bushing connection as an organic whole.
Furthermore, a polygonal locking groove is formed in the upper end face of the inclined rod.
After the technical scheme is adopted, the precast tubular pile is firstly sunk into the foundation; then, a plurality of inclined rods penetrate through the precast tubular pile through the inclined through holes and are inserted into the foundation, meanwhile, the convex blocks slide into the bottoms of the inclined sliding grooves, and then, a key with a polygonal convex block is inserted into the polygonal locking groove and is rotated, so that the convex blocks enter the bent locking groove to complete the locking of the inclined rods; sleeving a sleeve with an inner sleeve on the top of the precast tubular pile, aligning mounting holes of the sleeve and the inner sleeve with bolt holes of the precast tubular pile, and fastening the precast tubular pile, the sleeve and the inner sleeve through bolts and nuts; finally, concrete grout is injected into the precast tubular pile at high pressure through the grouting holes, so that the precast tubular pile, the sleeve, the inner sleeve, the bolt, the reinforcing rib and the diagonal rod are integrated, and the integrity, reliability and shearing resistance of the pile foundation are improved; after the bearing platform is connected through the anchoring ribs, the structural stability of the pile foundation and the bearing platform is improved due to the arrangement of the sleeve, the inner sleeve, the bolt and the reinforcing ribs, and the bending resistance and the shearing resistance of the connecting position of the pile foundation and the bearing platform are also improved.
Drawings
The invention has the following drawings:
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a schematic structural diagram of a local precast tubular pile in the invention;
FIG. 3 is a schematic view of the structure of the diagonal member of the present invention;
fig. 4 is a top view of the diagonal member of the present invention.
Detailed Description
Referring to the attached drawings, the high-bearing-platform building pile foundation provided by the invention comprises a precast tubular pile 1 and a sleeve 2 sleeved on the top of the precast tubular pile 1, wherein a grouting hole 3, an exhaust hole 4 and a plurality of anchoring ribs 5 are arranged on the sleeve 2, the sleeve 2 is detachably arranged on the precast tubular pile 1, a plurality of inclined rods 6 penetrate through the middle part of the precast tubular pile 1, an inner sleeve 7 attached to the inner wall of the precast tubular pile 1 is arranged in the sleeve 2, a plurality of layers of opposite bolt holes 8 are arranged on the precast tubular pile 1, mounting holes 9 capable of aligning with the bolt holes 8 are arranged on the sleeve 2 and the inner sleeve 7, an inclined through hole 10 is arranged in the middle part of the precast tubular pile 1, an inclined chute 11 is arranged on the inner wall of the inclined through hole 10, a bent locking groove 12 communicated with the inclined chute 11 is arranged at the tail end of the inclined chute 11, each layer of reinforcing component comprises a plurality of reinforcing ribs 14 which are arranged obliquely downwards, a bolt 15 penetrating through the precast tubular pile 1 is screwed in each layer of opposite bolt holes 8, the bolt 15 penetrates through the mounting hole 9 of the sleeve 2 and the inner sleeve 7, two ends of the bolt 15 are fastened through nuts 16 to connect the sleeve 2, the precast tubular pile 1 and the inner sleeve 7 into a whole, and the upper end face of the inclined rod 6 is provided with a polygonal locking groove 17.
In this embodiment, the precast tubular pile 1 is first sunk into the foundation 18; then, a plurality of inclined rods 6 penetrate through the precast tubular pile 1 through the inclined through holes 10 and are inserted into the foundation 18, meanwhile, the convex blocks 13 slide into the bottoms of the inclined sliding grooves 11, and then, a key with polygonal convex blocks is inserted into the polygonal locking grooves 17 and is rotated, so that the convex blocks enter the bent locking grooves 12 to complete the locking of the inclined rods 6; sleeving the sleeve 2 with the inner sleeve 7 on the top of the precast tubular pile 1, aligning the mounting holes 9 of the sleeve 2 and the inner sleeve 7 with the bolt holes 8 of the precast tubular pile 1, and fastening the precast tubular pile 1, the sleeve 2 and the inner sleeve 7 through bolts 15 and nuts 16; finally, concrete grout is injected into the precast tubular pile 1 through the grouting holes 3 at high pressure, so that the precast tubular pile 1, the sleeve 2, the inner sleeve 7, the bolts 15, the reinforcing ribs 14 and the inclined rods 6 are integrated, and the integrity, reliability and shearing resistance of a pile foundation are improved; after the bearing platform is connected through the anchoring ribs 5, the sleeve 2, the inner sleeve 7, the bolt 15 and the reinforcing ribs 13 are arranged, so that the structural stability of the pile foundation and the bearing platform is improved, and the bending resistance and the shearing resistance of the connecting position of the pile foundation and the bearing platform are also improved.

Claims (8)

1. High cushion cap building pile foundation, characterized by: locate the sleeve at precast tubular pile top including precast tubular pile and cover, be equipped with grout hole, exhaust hole and many anchor muscle on the sleeve, the sleeve can be dismantled and locate on the precast tubular pile.
2. A high cap building pile foundation as claimed in claim 1, wherein: many slant poles wear to be equipped with in the middle part of precast tubular pile.
3. A high cap building pile foundation according to claim 1 or 2, wherein: be equipped with the interior sleeve pipe of laminating with the precast tubular pile inner wall in the sleeve, be equipped with the relative bolt hole of multilayer on the precast tubular pile, be equipped with the mounting hole that can aim at the bolt hole on sleeve and the interior sleeve pipe.
4. A high cap building pile foundation as claimed in claim 2, wherein: the precast tubular pile middle part is equipped with the slant through-hole, and slant through-hole inner wall is equipped with the slant spout, and the slant spout end is equipped with communicating lock groove of buckling with it, slant pole middle part is equipped with can be at the slant spout, buckle the lug of lock inslot activity.
5. A high cap building pile foundation as claimed in claim 3, wherein: the inner sleeve inner wall is provided with a plurality of layers of reinforcing parts, and each layer of reinforcing part comprises a plurality of reinforcing ribs which are obliquely arranged downwards.
6. A high cap building pile foundation as claimed in claim 3, wherein: every layer is relative bolt hole spiro union has worn out precast tubular pile's bolt, and the bolt passes sleeve and interior sheathed tube mounting hole, and the nut fastening is passed through at the both ends of bolt and becomes sleeve, precast tubular pile and interior bushing connection as an organic whole.
7. A high cap building pile foundation according to claim 5, wherein: every layer is relative bolt hole spiro union has worn out precast tubular pile's bolt, and the bolt passes sleeve and interior sheathed tube mounting hole, and the nut fastening is passed through at the both ends of bolt and becomes sleeve, precast tubular pile and interior bushing connection as an organic whole.
8. A high cap building pile foundation according to claim 5, wherein: the upper end face of the oblique rod is provided with a polygonal locking groove.
CN202010284889.6A 2020-04-13 2020-04-13 High bearing platform building pile foundation Withdrawn CN111501813A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010284889.6A CN111501813A (en) 2020-04-13 2020-04-13 High bearing platform building pile foundation

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010284889.6A CN111501813A (en) 2020-04-13 2020-04-13 High bearing platform building pile foundation

Publications (1)

Publication Number Publication Date
CN111501813A true CN111501813A (en) 2020-08-07

Family

ID=71867542

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010284889.6A Withdrawn CN111501813A (en) 2020-04-13 2020-04-13 High bearing platform building pile foundation

Country Status (1)

Country Link
CN (1) CN111501813A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114277789A (en) * 2021-12-16 2022-04-05 深圳市工勘岩土集团有限公司 Pile-in-pile structure formed based on construction of defective cast-in-place piles
CN114277798A (en) * 2021-12-16 2022-04-05 深圳市工勘岩土集团有限公司 Method for binding new reinforcement cage in hole of defected cast-in-place pile

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114277789A (en) * 2021-12-16 2022-04-05 深圳市工勘岩土集团有限公司 Pile-in-pile structure formed based on construction of defective cast-in-place piles
CN114277798A (en) * 2021-12-16 2022-04-05 深圳市工勘岩土集团有限公司 Method for binding new reinforcement cage in hole of defected cast-in-place pile

Similar Documents

Publication Publication Date Title
CN101487355B (en) Telegraph pole and its mounting and fixing method
CN105134269B (en) Control method for roadway surrounding rock achieving cooperative load bearing by enabling anchor cables to penetrate through sheds
CN109184733B (en) Soft rock chamber bottom heave treatment supporting structure and method based on prefabricated bottom arc plate
CN103015414B (en) A kind of precast concrete post grouting pile and grouting process
CN111501813A (en) High bearing platform building pile foundation
CN211773698U (en) Pile anchor supporting construction
CN104727318A (en) Foundation ditch composite concrete nail supporting structure and method
CN103603379A (en) Anti-floating system combining anti-floating cement soil pile and anti-floating anchor rod and construction process of anti-floating system
CN110616740A (en) Structure for expanding subway section in subway mine method construction interval and construction method thereof
CN111364494A (en) Offshore high-pile bearing platform foundation supported by anchor cables and inclined straight piles and construction method thereof
US20100247245A1 (en) Foundation structure using micro pile and method for forming the same
CN203613568U (en) Anti-floating cement soil pile and anti-floating anchor rod combined anti-floating system
CN213038413U (en) Improved high bearing platform building pile foundation
CN205576957U (en) Stake end pilework
JP4017766B2 (en) Hollow cylindrical body and its construction method
CN202989911U (en) Post-grouting pile of precast concrete
CN109706927A (en) A kind of preparation method of Prestressed Rock soil anchor bolt and its free segment
CN115821972A (en) Assembled rock anchor rod foundation of power transmission line and construction method
CN110761192B (en) Caisson pile foundation and construction method thereof
CN212506362U (en) Offshore high-rise pile cap foundation supported by anchor cables and inclined straight piles
CN208039240U (en) A kind of built pile
CN219491492U (en) Reinforced concrete anchor connection structure
CN218291978U (en) Soil nailing wall structure
CN102080376B (en) Built-in composite anchor rod construction method and composite anchor rod drilling tool used by same
CN105297760B (en) Drill bit anchor pile composite foundation stabilization structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20200807

WW01 Invention patent application withdrawn after publication