CN111476425A - Engineering project cost progress supervision system and method - Google Patents

Engineering project cost progress supervision system and method Download PDF

Info

Publication number
CN111476425A
CN111476425A CN202010296188.4A CN202010296188A CN111476425A CN 111476425 A CN111476425 A CN 111476425A CN 202010296188 A CN202010296188 A CN 202010296188A CN 111476425 A CN111476425 A CN 111476425A
Authority
CN
China
Prior art keywords
project
construction
progress
cost
module
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010296188.4A
Other languages
Chinese (zh)
Inventor
胡江昊
李兵
贾登泽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhongdao Minghua Construction Project Consulting Co ltd
Original Assignee
Zhongdao Minghua Construction Project Consulting Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhongdao Minghua Construction Project Consulting Co ltd filed Critical Zhongdao Minghua Construction Project Consulting Co ltd
Priority to CN202010296188.4A priority Critical patent/CN111476425A/en
Publication of CN111476425A publication Critical patent/CN111476425A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/27Replication, distribution or synchronisation of data between databases or within a distributed database system; Distributed database system architectures therefor
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F21/00Security arrangements for protecting computers, components thereof, programs or data against unauthorised activity
    • G06F21/60Protecting data
    • G06F21/64Protecting data integrity, e.g. using checksums, certificates or signatures
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06313Resource planning in a project environment
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Computer Security & Cryptography (AREA)
  • Databases & Information Systems (AREA)
  • Data Mining & Analysis (AREA)
  • General Engineering & Computer Science (AREA)
  • Computing Systems (AREA)
  • Health & Medical Sciences (AREA)
  • Bioethics (AREA)
  • General Health & Medical Sciences (AREA)
  • Computer Hardware Design (AREA)
  • Software Systems (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Biodiversity & Conservation Biology (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a project cost progress supervision system and a project cost progress supervision method, which comprise a cloud server and a project terminal: the project terminal is in communication connection with the cloud server and is used for sending construction photos of a construction site to the cloud server; the cloud server comprises a project plan module, a block chain building module and a project progress module: the project planning module is used for acquiring a construction cost file related to construction cost, planning the construction cost according to a construction cost flow and obtaining a planning progress data table; the block chain building module is used for obtaining corresponding processing nodes in the schedule data table and forming the processing nodes into a project cost block chain according to the project cost flow; and the project progress module obtains the construction progress of the current processing node according to the acquired construction photo, generates a three-dimensional model graph by using a BIM (building information modeling) system when the construction progress is abnormal with the progress of the schedule data sheet, and predicts the time and construction cost for completing the current processing node according to the information of the project list.

Description

Engineering project cost progress supervision system and method
Technical Field
The invention relates to the technical field of engineering management, in particular to a system and a method for supervising construction project cost progress.
Background
The information technology is rapidly developed, and new technologies represented by mobile internet, internet of things, cloud computing and the like are widely applied to various social industries, so that the production and living modes of people are continuously changed, and the huge progress of the society is promoted. The enterprise in charge of bid inviting can make project cost for the accepted project before bid inviting, and the existing cost process is the work of cost calculation for the accepted project according to the information provided by the working personnel and the information obtained by the self-to-site survey.
At present, a chinese patent with publication number CN107392568A discloses a project cost management system, which comprises a project collection module, a project contract module, a project registration module, a project implementation module and a project filing module, and realizes paperless network office and reasonable and balanced task scheduling, relatively reasonable performance distribution results and resource sharing in companies through a series of processes such as project collection, contract management, project registration, project implementation opinion data filing and the like.
However, the work of the cost workers needs to be supervised due to the complexity of the cost work, the cost work of the cost workers can only be supervised by related personnel at present, the requirement of automatic office is not met, and meanwhile, additional workers are needed, so that the waste of human resources is caused.
Disclosure of Invention
Aiming at the defects in the prior art, the invention aims to provide the project cost progress monitoring system which has the advantages of monitoring the progress cost information of each processing node of the project, high efficiency and high accuracy.
The above object of the present invention is achieved by the following technical solutions:
a project cost progress supervision system comprises a cloud server and a project terminal:
the project terminal is in communication connection with the cloud server and is used for sending construction photos of a construction site to the cloud server;
the cloud server comprises a project plan module, a block chain building module and a project progress module:
the project planning module is used for acquiring project bidding documents, project lists and construction cost documents related to construction cost in construction drawings, planning and arranging the construction cost according to a construction cost flow and acquiring a planning progress data table;
the block chain building module is used for acquiring corresponding processing nodes in the schedule data table and forming the processing nodes into a project cost block chain according to the project cost flow;
and the project progress module is used for performing big data integration and analysis on the construction information in the acquired construction photo, obtaining the construction progress of the current processing node, generating a three-dimensional model graph of the current processing node by using the BIM system when the construction progress is abnormal to the progress of the plan data table, and predicting the time and construction cost of the current processing node according to the information of the project list.
By adopting the technical scheme, the three-dimensional model graph of the construction project is established according to the construction drawing, the engineering quantity of each processing node can be intuitively calculated, and the construction cost of the whole construction project is quickly calculated by referring to the engineering price; processing nodes corresponding to each flow step of the construction cost are built into a construction cost block chain through a block chain technology, and the time of progress management can be shortened and the efficiency of progress management can be improved by utilizing the function of rapid processing provided by the block chain; meanwhile, each process node is formed into a corresponding node subchain based on a block chain technology, and each process is developed all the time according to a time sequence, so that the characteristics of irreversible time and non-falsification in the block chain are well utilized, and the accuracy of each process is ensured.
The present invention in a preferred example may be further configured to: the cloud server further comprises a risk evaluation module, and the risk evaluation module is used for carrying out automatic risk evaluation on the found abnormity and reasons, automatically issuing early warning and intelligently adjusting the schedule data sheet.
By adopting the technical scheme, the risk evaluation module intelligently adjusts the completion time of each processing node, so that each processing node is compactly connected, and the engineering efficiency of a construction project is improved.
The present invention in a preferred example may be further configured to: the cloud server further comprises a reminding module, and the reminding module is used for sending the schedule progress data table to the project terminal for real-time display and reminding project responsible persons when the schedule progress data table is updated.
By adopting the technical scheme, the reminding module reminds the project responsible person when the schedule data sheet is updated, so that the project responsible person of the next processing node can reasonably arrange the follow-up time of the project.
The present invention in a preferred example may be further configured to: the cloud server is used for sending the engineering cost files of the processing nodes to the corresponding cost member terminals when the processing nodes are finished.
By adopting the technical scheme, a constructor can calculate the construction cost of each processing node according to the project cost file when each processing node is finished, and then the construction costs of all the processing nodes are added to obtain the construction cost of the whole construction project, so that the construction cost of the whole construction project can be calculated more quickly.
The present invention in a preferred example may be further configured to: the block chain building module comprises:
the progress acquiring unit is used for acquiring the processing progress content and the corresponding processing time of each processing node;
the calculating unit is used for calculating a hash value corresponding to the processing progress content of each processing node according to a hash algorithm;
and the block chain building unit is used for forming the project cost block chain according to the hash value corresponding to each processing progress content and the corresponding processing time.
By adopting the technical scheme, each processing node is combined into the block chain by using the mode of forming the block chain, a reliable framework is provided for the project cost progress management, and when a new process is built each time, the processing nodes are directly added into the corresponding processing nodes in the block chain, so that the efficiency of the progress management is improved.
The second aim of the invention is realized by the following technical scheme:
a method for supervising construction project cost progress is characterized by comprising the following steps:
s1, planning and arranging the construction cost according to the acquired project bidding documents, project lists and construction cost documents related to the construction cost in the construction drawings by combining the construction cost flow to obtain a planning progress data table;
s2, acquiring corresponding processing nodes through the schedule data sheet, and combining the processing nodes with the project cost flow to form a project cost block chain;
s3, according to the schedule data sheet, taking construction pictures of a construction site, performing big data integration and analysis on construction information in the obtained construction pictures, obtaining the construction progress of the current processing node, when the construction progress and the schedule data sheet progress are abnormal, generating a three-dimensional model diagram of the current processing node by using a BIM system, and predicting the time and construction cost of the current processing node according to the information of the project list.
By adopting the technical scheme, the three-dimensional model graph of the construction project is established according to the construction drawing, the engineering quantity of each processing node can be intuitively calculated, and the construction cost of the whole construction project is quickly calculated by referring to the engineering price; processing nodes corresponding to each flow step of the construction cost are built into a construction cost block chain through a block chain technology, and the time of progress management can be shortened and the efficiency of progress management can be improved by utilizing the function of rapid processing provided by the block chain; meanwhile, each process node is formed into a corresponding node subchain based on a block chain technology, and each process is developed all the time according to a time sequence, so that the characteristics of irreversible time and non-falsification in the block chain are well utilized, and the accuracy of each process is ensured.
The present invention in a preferred example may be further configured to: in step S3, automatically evaluating the risk of the detected abnormality and cause, and automatically issuing an early warning; meanwhile, the schedule is intelligently adjusted, and a project responsible person is reminded.
By adopting the technical scheme, the completion time of each processing node is intelligently adjusted, so that each processing node is compactly connected, and the engineering efficiency of a construction project is improved.
The present invention in a preferred example may be further configured to: and sending the project cost file of each processing node to the corresponding cost member when each processing node is finished.
By adopting the technical scheme, a constructor can calculate the construction cost of each processing node according to the project cost file when each processing node is finished.
In summary, the invention includes at least one of the following beneficial technical effects:
1. establishing a three-dimensional model diagram of a construction project according to a construction drawing, calculating the engineering quantity of each processing node very intuitively, and quickly calculating the construction cost of the whole construction project by referring to the engineering price; processing nodes corresponding to each flow step of the construction cost are built into a construction cost block chain through a block chain technology, and the time of progress management can be shortened and the efficiency of progress management can be improved by utilizing the function of rapid processing provided by the block chain; meanwhile, each process node is formed into a corresponding node subchain based on a block chain technology, and as each process is developed all the time according to a time sequence, the characteristics of irreversible time and non-falsification in the block chain are well utilized, and the accuracy of each process is ensured;
2. the risk assessment module intelligently adjusts the completion time of each processing node, so that the processing nodes are compactly connected, and the engineering efficiency of a construction project is improved.
Drawings
FIG. 1 is a system block diagram of an embodiment of the invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
A project cost progress supervision system, refer to FIG. 1, includes cloud server and project terminal: the project terminal is in communication connection with the cloud server and is used for sending construction photos of a construction site to the cloud server; the cloud server comprises a project plan module, a block chain building module and a project progress module: the project planning module is used for acquiring project bidding documents, project lists and construction cost documents related to construction cost in the construction drawings, planning the construction cost according to the construction cost flow and acquiring a planning progress data table; the block chain building module is used for obtaining corresponding processing nodes in the schedule data table and forming the processing nodes into a project cost block chain according to the project cost flow; and the project progress module is used for performing big data integration and analysis on the construction information in the acquired construction photo, obtaining the construction progress of the current processing node, generating a three-dimensional model graph of the current processing node by using the BIM system when the construction progress is abnormal to the progress of the plan data table, and predicting the time and construction cost of the current processing node according to the information of the project list.
Establishing a three-dimensional model diagram of a construction project according to a construction drawing, calculating the engineering quantity of each processing node very intuitively, and quickly calculating the construction cost of the whole construction project by referring to the engineering price; processing nodes corresponding to each flow step of the construction cost are built into a construction cost block chain through a block chain technology, and the time of progress management can be shortened and the efficiency of progress management can be improved by utilizing the function of rapid processing provided by the block chain; meanwhile, each process node is formed into a corresponding node subchain based on a block chain technology, and each process is developed all the time according to a time sequence, so that the characteristics of irreversible time and non-falsification in the block chain are well utilized, and the accuracy of each process is ensured.
After the construction photo is received, the corresponding building in the construction photo can be extracted by adopting relatively mature image processing software in the prior art, the proportion of the building is adjusted to be consistent with the three-dimensional model graph, then the building is compared with the three-dimensional model graph, and the processing node can be known to be approximately completed by a few percent through comparison due to the fact that the engineering quantity of the whole construction project is known, so that the construction progress of the current processing node can be rapidly calculated.
The cloud server also comprises a risk evaluation module, wherein the risk evaluation module is used for carrying out automatic risk evaluation on the found abnormity and reasons, automatically issuing early warning and intelligently adjusting a schedule data table; the risk assessment module intelligently adjusts the completion time of each processing node, so that the processing nodes are compactly connected, and the engineering efficiency of a construction project is improved. The cloud server also comprises a reminding module, wherein the reminding module is used for sending the schedule progress data table to the project terminal for real-time display and reminding a project responsible person when the schedule progress data table is updated; and the reminding module reminds the project responsible person when the schedule data sheet is updated, so that the project responsible person of the next processing node can reasonably arrange the follow-up time of the project.
The cloud server is used for sending the project cost files of the processing nodes to the corresponding cost worker terminals when the processing nodes are finished; when each processing node is finished, a constructor can calculate the construction cost of each processing node according to the project cost file, and then the construction costs of all the processing nodes are added to obtain the construction cost of the whole construction project, so that the construction cost of the whole construction project can be calculated more quickly.
The block chain building module comprises: the progress acquiring unit is used for acquiring the processing progress content and the corresponding processing time of each processing node; the calculating unit is used for calculating a hash value corresponding to the processing progress content of each processing node according to a hash algorithm; and the block chain building unit is used for forming the project cost block chain according to the hash value corresponding to each processing progress content and the corresponding processing time. And when a new process is established every time, the processing nodes are directly added into the corresponding processing nodes in the block chain, so that the efficiency of progress management is improved. The hash algorithm in the present invention maps a binary value of any length to a binary value of a shorter fixed length, and this small binary value is called a hash value. Hash values are a unique and extremely compact representation of a piece of data as a value. If a piece of plaintext is hashed and even if only one letter of the piece is altered, the subsequent hash will produce a different value. It is computationally infeasible to find two different inputs whose hash is the same value, so the hash value of the data can verify the integrity of the data.
A method for supervising construction project cost progress is characterized by comprising the following steps:
s1, planning and arranging the construction cost according to the acquired project bidding documents, project lists and construction cost documents related to the construction cost in the construction drawings by combining the construction cost flow to obtain a planning progress data table;
s2, acquiring corresponding processing nodes through the schedule data sheet, and combining the processing nodes with the project cost flow to form a project cost block chain;
s3, according to the schedule data sheet, taking construction pictures of a construction site, performing big data integration and analysis on construction information in the obtained construction pictures, obtaining the construction progress of the current processing node, when the construction progress and the schedule data sheet progress are abnormal, generating a three-dimensional model diagram of the current processing node by using a BIM system, and predicting the time and construction cost of the current processing node according to the information of the project list.
In step S3, automatically evaluating the risk of the detected abnormality and cause, and automatically issuing an early warning; meanwhile, the schedule is intelligently adjusted, and a project responsible person is reminded. The completion time of each processing node is intelligently adjusted, so that the processing nodes are compactly connected, and the engineering efficiency of a construction project is improved. When each processing node finishes, the engineering cost file of the processing node is sent to a corresponding cost member; the construction cost staff can calculate the construction cost of each processing node according to the project cost file when each processing node is finished.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.

Claims (8)

1. The utility model provides an engineering project cost progress supervisory systems which characterized in that, includes cloud ware and project terminal:
the project terminal is in communication connection with the cloud server and is used for sending construction photos of a construction site to the cloud server;
the cloud server comprises a project plan module, a block chain building module and a project progress module:
the project planning module is used for acquiring project bidding documents, project lists and construction cost documents related to construction cost in construction drawings, planning and arranging the construction cost according to a construction cost flow and acquiring a planning progress data table;
the block chain building module is used for acquiring corresponding processing nodes in the schedule data table and forming the processing nodes into a project cost block chain according to the project cost flow;
and the project progress module is used for performing big data integration and analysis on the construction information in the acquired construction photo, obtaining the construction progress of the current processing node, generating a three-dimensional model graph of the current processing node by using the BIM system when the construction progress is abnormal to the progress of the plan data table, and predicting the time and construction cost of the current processing node according to the information of the project list.
2. The project cost progress supervision system according to claim 1, wherein the cloud server further comprises a risk assessment module, the risk assessment module is used for carrying out automatic risk assessment on the found abnormality and reason, automatically issuing early warning, and intelligently adjusting a schedule progress data sheet.
3. The project cost progress supervision system according to claim 2, characterized in that the cloud server further comprises a reminding module, and the reminding module is used for sending the schedule progress data sheet to the project terminal for real-time display and reminding project responsible persons when the schedule progress data sheet is updated.
4. The project cost progress supervision system according to claim 3, characterized by further comprising a cost terminal, wherein the cost terminal is in communication connection with the cloud server, and the cloud server is used for sending the project cost file of each processing node to the corresponding cost terminal when the processing node is finished.
5. A project cost progress supervision system according to claim 1 characterised in that the block chain building module comprises:
the progress acquiring unit is used for acquiring the processing progress content and the corresponding processing time of each processing node;
the calculating unit is used for calculating a hash value corresponding to the processing progress content of each processing node according to a hash algorithm;
and the block chain building unit is used for forming the project cost block chain according to the hash value corresponding to each processing progress content and the corresponding processing time.
6. A method for supervising construction project cost progress is characterized by comprising the following steps:
s1, planning and arranging the construction cost according to the acquired project bidding documents, project lists and construction cost documents related to the construction cost in the construction drawings by combining the construction cost flow to obtain a planning progress data table;
s2, acquiring corresponding processing nodes through the schedule data sheet, and combining the processing nodes with the project cost flow to form a project cost block chain;
s3, according to the schedule data sheet, taking construction pictures of a construction site, performing big data integration and analysis on construction information in the obtained construction pictures, obtaining the construction progress of the current processing node, when the construction progress and the schedule data sheet progress are abnormal, generating a three-dimensional model diagram of the current processing node by using a BIM system, and predicting the time and construction cost of the current processing node according to the information of the project list.
7. The method as claimed in claim 6, wherein in step S3, the method carries out automatic risk assessment for the detected abnormality and reason, and automatically issues an early warning; meanwhile, the schedule is intelligently adjusted, and a project responsible person is reminded.
8. The method as claimed in claim 7, wherein the method is used for sending the project cost file of each processing node to the corresponding cost member when the processing node is finished.
CN202010296188.4A 2020-04-15 2020-04-15 Engineering project cost progress supervision system and method Pending CN111476425A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010296188.4A CN111476425A (en) 2020-04-15 2020-04-15 Engineering project cost progress supervision system and method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010296188.4A CN111476425A (en) 2020-04-15 2020-04-15 Engineering project cost progress supervision system and method

Publications (1)

Publication Number Publication Date
CN111476425A true CN111476425A (en) 2020-07-31

Family

ID=71753431

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010296188.4A Pending CN111476425A (en) 2020-04-15 2020-04-15 Engineering project cost progress supervision system and method

Country Status (1)

Country Link
CN (1) CN111476425A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112529446A (en) * 2020-12-18 2021-03-19 北京求实工程管理有限公司 Engineering project cost risk management system
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113344552A (en) * 2021-07-08 2021-09-03 中宬建设管理有限公司 Multi-project joint management method and system based on engineering cost
CN114240376A (en) * 2021-12-17 2022-03-25 杭州正大装饰有限公司 Project progress tracking method, system, device and computer readable medium
CN115392808A (en) * 2022-10-31 2022-11-25 长春龙佳网络科技有限公司 Building construction prediction progress and allocation system based on deep learning
CN115601000A (en) * 2022-10-13 2023-01-13 中宬建设管理有限公司(Cn) BIM5D model engineering cost method and system in complex environment
CN116228175A (en) * 2023-05-09 2023-06-06 南京煌泰慧筑科技有限公司 Real-time management system based on enterprise-level engineering construction cost
CN116305797A (en) * 2023-02-07 2023-06-23 广东电网有限责任公司广州供电局 Construction risk assessment system based on BIM and multisource quality information fusion

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108629564A (en) * 2018-04-28 2018-10-09 中国船舶重工集团公司第七〇九研究所 A kind of Management in Large Scale Project system and method based on block chain technology
CN109657927A (en) * 2018-11-27 2019-04-19 建经投资咨询有限公司 A kind of Whole Process Cost progress supervision system and method
CN109697188A (en) * 2018-11-30 2019-04-30 广州菲达建筑咨询有限公司 Cost Data management method and system
CN110322147A (en) * 2019-07-04 2019-10-11 四川元丰建设项目管理有限公司 A kind of Project Supervision approaches to IM and system
CN110991990A (en) * 2019-11-25 2020-04-10 四川华通建设工程造价管理有限责任公司 Engineering project cost management system

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN108629564A (en) * 2018-04-28 2018-10-09 中国船舶重工集团公司第七〇九研究所 A kind of Management in Large Scale Project system and method based on block chain technology
CN109657927A (en) * 2018-11-27 2019-04-19 建经投资咨询有限公司 A kind of Whole Process Cost progress supervision system and method
CN109697188A (en) * 2018-11-30 2019-04-30 广州菲达建筑咨询有限公司 Cost Data management method and system
CN110322147A (en) * 2019-07-04 2019-10-11 四川元丰建设项目管理有限公司 A kind of Project Supervision approaches to IM and system
CN110991990A (en) * 2019-11-25 2020-04-10 四川华通建设工程造价管理有限责任公司 Engineering project cost management system

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112529446A (en) * 2020-12-18 2021-03-19 北京求实工程管理有限公司 Engineering project cost risk management system
CN113256131A (en) * 2021-06-01 2021-08-13 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of prefabricated building
CN113256131B (en) * 2021-06-01 2024-02-02 安徽鑫洋信息工程有限公司 Intelligent coordination construction system of assembled building
CN113344552A (en) * 2021-07-08 2021-09-03 中宬建设管理有限公司 Multi-project joint management method and system based on engineering cost
CN114240376A (en) * 2021-12-17 2022-03-25 杭州正大装饰有限公司 Project progress tracking method, system, device and computer readable medium
CN115601000A (en) * 2022-10-13 2023-01-13 中宬建设管理有限公司(Cn) BIM5D model engineering cost method and system in complex environment
CN115601000B (en) * 2022-10-13 2023-10-20 中宬建设管理有限公司 BIM5D model engineering construction cost method and system under complex environment
CN115392808A (en) * 2022-10-31 2022-11-25 长春龙佳网络科技有限公司 Building construction prediction progress and allocation system based on deep learning
CN116305797A (en) * 2023-02-07 2023-06-23 广东电网有限责任公司广州供电局 Construction risk assessment system based on BIM and multisource quality information fusion
CN116305797B (en) * 2023-02-07 2023-11-14 广东电网有限责任公司广州供电局 Construction risk assessment system based on BIM and multisource quality information fusion
CN116228175A (en) * 2023-05-09 2023-06-06 南京煌泰慧筑科技有限公司 Real-time management system based on enterprise-level engineering construction cost

Similar Documents

Publication Publication Date Title
CN111476425A (en) Engineering project cost progress supervision system and method
CN108009758B (en) BIM-based intelligent management method for field construction materials
CN109559069B (en) Production management method and device based on assembly type building platform and terminal equipment
CN110991990A (en) Engineering project cost management system
CN109557934B (en) Unmanned aerial vehicle cruise control method and device based on fabricated building platform
CN110750650A (en) Construction method and device of enterprise knowledge graph
CN110599007A (en) Project progress management system
CN101808351B (en) Method and system for business impact analysis
CN111915143B (en) Complex product assembly management and control system based on intelligent contract
CN113656864B (en) Building construction method, system, computer device and storage medium based on BIM
CN103345235A (en) Method and module for establishing data acquisition rule of statistical process control system
CN117035691B (en) Engineering construction digital project management method and system based on BIM technology
CN113487084A (en) Method and device for predicting service life of equipment, computer equipment and computer-readable storage medium
CN113010595A (en) Electric power energy data analysis and monitoring method and system
CN110069826B (en) Project management method, system and storage medium based on BIM
CN116756832A (en) BIM technology-based engineering cost management and control system and method
CN105574678A (en) Employee performance assessment data automation system based on executive force indexes
CN110674534A (en) Remote quality detection technology based on Internet of things electronic evidence chain
CN110909129A (en) Abnormal complaint event identification method and device
CN110110949A (en) Construction work subcontracting price assessment system and method based on big data
CN116894639A (en) Multi-information fusion plan management system and method for Internet of things
CN115967730A (en) Data acquisition method and system based on Internet of things
CN115660619A (en) Production management system and server based on BIM information management
CN114493262A (en) System, method and device for processing electric power big data and computer equipment
CN113807599A (en) Intelligent construction informatization integrated management cloud platform

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200731

WD01 Invention patent application deemed withdrawn after publication