CN111472346A - 灌注桩桩身周围土体加固施工方法 - Google Patents
灌注桩桩身周围土体加固施工方法 Download PDFInfo
- Publication number
- CN111472346A CN111472346A CN202010367065.5A CN202010367065A CN111472346A CN 111472346 A CN111472346 A CN 111472346A CN 202010367065 A CN202010367065 A CN 202010367065A CN 111472346 A CN111472346 A CN 111472346A
- Authority
- CN
- China
- Prior art keywords
- grouting
- pile
- hole
- cast
- holes
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D3/00—Improving or preserving soil or rock, e.g. preserving permafrost soil
- E02D3/12—Consolidating by placing solidifying or pore-filling substances in the soil
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D15/00—Handling building or like materials for hydraulic engineering or foundations
- E02D15/02—Handling of bulk concrete specially for foundation or hydraulic engineering purposes
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D2250/00—Production methods
- E02D2250/003—Injection of material
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D5/00—Bulkheads, piles, or other structural elements specially adapted to foundation engineering
- E02D5/22—Piles
- E02D5/34—Concrete or concrete-like piles cast in position ; Apparatus for making same
Abstract
本发明涉及建筑施工领域,尤其是一种灌注桩桩身周围土体加固施工方法,加工无缝注浆管,由注浆管上加工有溢浆孔;利用履带式液压潜孔钻机在灌注桩桩身周围进行孔位钻进,使注浆孔均匀布置在灌注桩桩身外侧周围;高压注浆机由下向上进行注浆,直到所有的注浆孔完成注浆为止;所有注浆孔完成注浆后,拔出注浆管并对注浆孔进行封孔固定;注浆区域土体固化后,利用旋挖钻机进行钻孔灌注桩施工。本发明有效增强了土体间的强度,保证了成孔质量,防止塌孔现象的发生,减少了沉渣现象。
Description
技术领域
本发明涉及建筑施工领域,尤其是一种灌注桩桩身周围土体加固施工方法。
背景技术
传统的灌注桩成孔工艺方法有正、反循环钻孔、冲击成孔、干作业挖孔、旋挖钻孔等,不同地层选用不同成孔设备。当遇到回填尾矿砂、碎石区域,经过现场试桩,该地质条件下钻孔时塌孔明显,无法成桩。尾矿砂与碎石间孔隙率较大,且无粘聚力,地层相对水位较高等;由于土体稳定性极差,用水量明显,当机械成孔时,需制备泥浆比重较高的泥浆液;当人工挖孔时,需随挖随浇筑护壁混凝土,且存在较大的安全危险性。由于碎石层孔隙率较大,无粘性,无法使用泥浆护壁技术。
发明内容
为解决上述技术问题,本发明提出一种有效增强土体间的强度,保证成孔质量,防止塌孔的灌注桩桩身周围土体加固施工方法。
本发明采用如下技术方案:
一种灌注桩桩身周围土体加固施工方法,按照如下步骤进行:
A、加工无缝注浆管,由注浆管底部向上300mm处开始加工溢浆孔,溢浆孔以及注浆管的底部分别用透明胶带密封;
B、根据浆液扩散半径以及灌注桩的桩径,确定注浆孔的位置与个数,利用履带式液压潜孔钻机在灌注桩桩身周围进行孔位钻进,使注浆孔均匀布置在灌注桩桩身外侧周围;
C、将注浆管插入注浆孔内,通过高压注浆机由下向上进行注浆,一个注浆孔注浆完成后跳注到另一个注浆管对其对应的注浆孔开始注浆,根据浆液的扩散速度对每个注浆孔进行分阶段多次注浆,直到所有的注浆孔完成注浆为止;
D、所有注浆孔完成注浆后,拔出注浆管并对注浆孔进行封孔固定;
E、注浆区域土体固化后,利用旋挖钻机进行钻孔灌注桩施工。
与现有技术相比,本发明的有益效果是:
通过在灌注桩桩身周围注浆加固的施工方法,有效增强了土体间的强度,保证了成孔质量,防止塌孔现象的发生,减少了沉渣现象,避免因地基不均匀沉降及桩体质量造成质量事故的发生。
进一步的,本发明采用的优选方案是:
步骤A中的注浆管环形对称设置有两排溢浆孔,每排溢浆孔设置有三个,同排溢浆孔的间距为200mm,每个溢浆孔的孔径为3~5mm。
步骤B中注浆孔设置有8个,每个注浆孔分别距灌注桩桩身200mm,8个注浆孔在灌注桩桩身外侧均匀布置。
步骤C中的注浆压力为0.2~0.3Mpa,注浆流量为7~10L/min。
步骤B中潜孔钻机进行孔位钻进时,当遇到碎石层与风化岩层时,潜孔钻机进行加压回旋冲击,直到达到孔深的设计要求,注浆孔底进入强风化花岗片麻岩1000mm。
附图说明
图1为本发明的结构示意图;
图2为注浆管的结构示意图;
图3为图2的A-A断面图;
图4为灌注桩桩身周围注浆管的排布示意图;
图5为钻孔灌注桩施工的示意图;
图中:注浆管1;潜孔钻机2;潜孔钻杆3;钻孔马达4;冲击器5;溢浆孔6;旋挖钻机7;主卷扬8;旋挖钻杆9;旋挖钻头10;尾矿砂11;碎石层12;风化岩13。
具体实施方式
以下结合附图和具体实施例对本发明进一步说明。
一种灌注桩桩身周围土体加固施工方法,按照如下步骤进行:
A、加工无缝注浆管11,由注浆管1底部向上300mm处开始加工溢浆孔6,注浆管1环形对称设置有两排溢浆孔6,每排溢浆孔6竖向设置有三个,同排溢浆孔6的间距为200mm,每个溢浆孔6的孔径为5mm。所有溢浆孔6以及注浆管1的底部分别用透明胶带密封。
B、根据浆液扩散半径以及灌注桩的桩径,确定注浆孔的位置与个数,注浆孔在灌注桩桩身周围均匀设置有8个,每个注浆孔的中心距离灌注桩桩身均为200mm。利用履带式液压潜孔钻机2在灌注桩桩身周围进行孔位钻进,使注浆孔均匀布置在灌注桩桩身外侧周围,履带式液压潜孔钻机2(三一重工SR205,钻孔直径为600~1800mm,最大钻孔深度为6400mm,最大压力165N)进行液压驱动,钻机马达带动潜孔钻杆3通过冲击器5进入地面以下地层。当遇到碎石层12与风化岩13层时,潜孔钻机2进行加压回旋冲击,直到达到孔深的设计要求,注浆孔底进入强风化花岗片麻岩1000mm。
C、将注浆管1的底端插入任意一个注浆孔中,通过高压注浆机对注浆孔进由下向上进行注浆,注浆压力为0.2~0.3Mpa,注浆流量为7~10L/min,该注浆孔注浆完成后马上跳注到另一根灌注桩桩身周围的任意一个注浆孔。注浆孔注浆时,根据浆液的扩散速度,对每个注浆孔分阶段多次注浆,直到所有的注浆孔都注浆完成。
D、所有注浆孔完成注浆后,拔出注浆管1,并用专用封孔材料聚氨酯封堵剂进行孔口封堵,该物质具有遇水后发生化学反应,形成弹性胶状固结体,从而达到封浆作用。
E、当注浆区域土体固化后,灌注桩周围尾矿砂11及碎石层12形成环向整体,固化完成后,利用旋挖钻机77进行钻孔灌注桩施工,将旋挖钻机77的钻机钻杆与钻机钻头(钻机钻头为双边进土斗齿捞沙钻头)连接,接口用连接销固定,防止钻机钻头掉落,然后旋挖钻机77驱动旋挖钻机77主卷扬8带动钻机钻杆与钻机钻头进行旋挖钻进,钻进过程中应注意孔内地下水位,并用专用泥浆化合物进行泥浆护壁施工;护筒内泥浆面应高于地下水位1000~1500mm,且泥浆面不低于护筒底部500mm以上。
通过潜孔钻机2将注浆管1打入土体内,浆液在注浆管1内均匀的注入地层中,浆液以渗透方式,填充缝隙间的水分和空气后占据其位置,经控制一端时间后,浆液将碎石和尾矿砂11间隙凝结成一个整体,从而是灌注桩桩身周围的土体加固,减少地基沉降量,土体加固达到设计强度后,即可进行旋挖钻孔灌注桩施工。
以上仅为本发明的具体实施方式,但对本发明的保护并不局限于此,所有涉及本技术领域技术人员所能想到的对本技术方案技术特征提出的等效变化或替换,都包含在本发明的保护范围之内。
Claims (5)
1.一种灌注桩桩身周围土体加固施工方法,其特征在于,按照如下步骤进行:
A、加工无缝注浆管,由注浆管底部向上300mm处开始加工溢浆孔,溢浆孔以及注浆管的底部分别用透明胶带密封;
B、根据浆液扩散半径以及灌注桩的桩径,确定注浆孔的位置与个数,利用履带式液压潜孔钻机在灌注桩桩身周围进行孔位钻进,使注浆孔均匀布置在灌注桩桩身外侧周围;
C、将注浆管插入注浆孔内,通过高压注浆机由下向上进行注浆,一个注浆孔注浆完成后跳注到另一个注浆管对其对应的注浆孔开始注浆,根据浆液的扩散速度对每个注浆孔进行分阶段多次注浆,直到所有的注浆孔完成注浆为止;
D、所有注浆孔完成注浆后,拔出注浆管并对注浆孔进行封孔固定;
E、注浆区域土体固化后,利用旋挖钻机进行钻孔灌注桩施工。
2.根据权利要求1所述的灌注桩桩身周围土体加固施工方法,其特征在于:步骤A中的注浆管环形对称设置有两排溢浆孔,每排溢浆孔设置有三个,同排溢浆孔的间距为200mm,每个溢浆孔的孔径为3~5mm。
3.根据权利要求1所述的灌注桩桩身周围土体加固施工方法,其特征在于:步骤B中注浆孔设置有8个,每个注浆孔分别距灌注桩桩身200mm,8个注浆孔在灌注桩桩身外侧均匀布置。
4.根据权利要求1所述的灌注桩桩身周围土体加固施工方法,其特征在于:步骤C中的注浆压力为0.2~0.3Mpa,注浆流量为7~10L/min。
5.根据权利要求1所述的灌注桩桩身周围土体加固施工方法,其特征在于:步骤B中潜孔钻机进行孔位钻进时,当遇到碎石层与风化岩层时,潜孔钻机进行加压回旋冲击,直到达到孔深的设计要求,注浆孔底进入强风化花岗片麻岩1000mm。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010367065.5A CN111472346A (zh) | 2020-04-30 | 2020-04-30 | 灌注桩桩身周围土体加固施工方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010367065.5A CN111472346A (zh) | 2020-04-30 | 2020-04-30 | 灌注桩桩身周围土体加固施工方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111472346A true CN111472346A (zh) | 2020-07-31 |
Family
ID=71757076
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010367065.5A Withdrawn CN111472346A (zh) | 2020-04-30 | 2020-04-30 | 灌注桩桩身周围土体加固施工方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111472346A (zh) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113802552A (zh) * | 2021-10-27 | 2021-12-17 | 浙江工业职业技术学院 | 一种桩周土体加固方法 |
CN114319327A (zh) * | 2021-12-07 | 2022-04-12 | 上海二十冶建设有限公司 | 一种高填方区超长挖孔免护筒式加固方法及其注浆装置 |
CN114837607A (zh) * | 2022-04-27 | 2022-08-02 | 中煤科工开采研究院有限公司 | 注浆加固施工工艺 |
CN114837166A (zh) * | 2022-05-18 | 2022-08-02 | 中铁六局集团有限公司 | 山区复杂地形地质桩基施工工法 |
CN115030187A (zh) * | 2022-07-20 | 2022-09-09 | 中建八局第二建设有限公司 | 一种石硝区钢管桩跟管施工的基坑支护方法 |
Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02112517A (ja) * | 1988-10-21 | 1990-04-25 | Nippon Sogo Bosui Kk | 二重管を用いた複合注入工法 |
CN101768959A (zh) * | 2010-01-18 | 2010-07-07 | 魏勇 | 一种灌注桩土体的止水加固设备及施工技术 |
CN206971225U (zh) * | 2017-06-30 | 2018-02-06 | 中国建筑第七工程局有限公司 | 灌注桩后压浆装置 |
-
2020
- 2020-04-30 CN CN202010367065.5A patent/CN111472346A/zh not_active Withdrawn
Patent Citations (3)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
JPH02112517A (ja) * | 1988-10-21 | 1990-04-25 | Nippon Sogo Bosui Kk | 二重管を用いた複合注入工法 |
CN101768959A (zh) * | 2010-01-18 | 2010-07-07 | 魏勇 | 一种灌注桩土体的止水加固设备及施工技术 |
CN206971225U (zh) * | 2017-06-30 | 2018-02-06 | 中国建筑第七工程局有限公司 | 灌注桩后压浆装置 |
Non-Patent Citations (1)
Title |
---|
水利部建设与管理司 中国水利工程协会: "《2014年度水利水电工程 建设工法汇编》", 30 November 2014, 黄河水利出版社 * |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113802552A (zh) * | 2021-10-27 | 2021-12-17 | 浙江工业职业技术学院 | 一种桩周土体加固方法 |
CN114319327A (zh) * | 2021-12-07 | 2022-04-12 | 上海二十冶建设有限公司 | 一种高填方区超长挖孔免护筒式加固方法及其注浆装置 |
CN114837607A (zh) * | 2022-04-27 | 2022-08-02 | 中煤科工开采研究院有限公司 | 注浆加固施工工艺 |
CN114837607B (zh) * | 2022-04-27 | 2024-04-05 | 中煤科工开采研究院有限公司 | 注浆加固施工工艺 |
CN114837166A (zh) * | 2022-05-18 | 2022-08-02 | 中铁六局集团有限公司 | 山区复杂地形地质桩基施工工法 |
CN115030187A (zh) * | 2022-07-20 | 2022-09-09 | 中建八局第二建设有限公司 | 一种石硝区钢管桩跟管施工的基坑支护方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111472346A (zh) | 灌注桩桩身周围土体加固施工方法 | |
CN105464074B (zh) | 一种人工挖孔桩高聚物注浆防护结构及其施工方法 | |
CN110778328B (zh) | 穿越滑坡体的黄土隧道进洞口段施工方法 | |
CN113463670A (zh) | 一种深基坑基坑底板施工的抽排水方法及抽排水结构 | |
CN113431490B (zh) | 一种用于岩溶地区的大直径管桩施工设备及方法 | |
CN113186903A (zh) | 组合式桩型结构及采用组合式桩型结构处理深基坑施工桩承载力不足的施工方法 | |
CN112761076A (zh) | 一种应用于水位变化条件下的锁扣钢管桩围堰及施工方法 | |
CN110735432A (zh) | 盾构过侵限隧道范围内桩基清除及参数控制方法 | |
Brown | Practical considerations in the selection and use of continuous flight auger and drilled displacement piles | |
CN110952528A (zh) | 复杂地质条件水泥土地下连续墙施工方法 | |
CN111501781A (zh) | 一种杂填土超深基坑固结注浆结合双排钢管桩支护方法及结构 | |
CN112761166A (zh) | Smw工法桩结合前置注浆钢管组合支护浅基坑施工方法 | |
US4496268A (en) | Method and apparatus for constructing reinforced concrete walls in the earth | |
CN109208594B (zh) | 钢护筒下沉遇孤石的处理方法、钢护筒结构及钻孔桩 | |
CN111287173A (zh) | 一种装配式载芯桩与施工方法 | |
CN106049467A (zh) | 复杂地质下冲击钻钻孔灌注桩漏浆处理方法 | |
CN113482028B (zh) | 一种沉井卡桩破除的施工方法 | |
Spagnoli et al. | Support for offshore monopile installation through the trench cutter technology | |
CN109653193B (zh) | 逆作地下连续墙施工方法 | |
JP3224008B2 (ja) | 水深下地盤改良工法 | |
CN103074887B (zh) | 钻喷一体化地基处理方法及专用钻具组件 | |
CN111549794A (zh) | 一种适用于软基处理的微型支护方法及微型桩支护结构 | |
JP2004218378A (ja) | 既設杭の撤去方法 | |
CN110685292A (zh) | 一种基坑排水系统及其施工方法 | |
CN212983829U (zh) | 一种适用于软基处理的微型桩支护结构 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20200731 |
|
WW01 | Invention patent application withdrawn after publication |