CN111456754A - Auxiliary tunnel structure for left-right separation tunnel and construction method thereof - Google Patents

Auxiliary tunnel structure for left-right separation tunnel and construction method thereof Download PDF

Info

Publication number
CN111456754A
CN111456754A CN202010262620.8A CN202010262620A CN111456754A CN 111456754 A CN111456754 A CN 111456754A CN 202010262620 A CN202010262620 A CN 202010262620A CN 111456754 A CN111456754 A CN 111456754A
Authority
CN
China
Prior art keywords
tunnel
auxiliary
reinforced concrete
vertical partition
partition wall
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010262620.8A
Other languages
Chinese (zh)
Inventor
王若晨
邸成
周跃峰
林本涛
朱勇
喻渝
陈锡武
黄华
张磊
郑伟
朱宏
殷召念
熊国兴
姜波
范磊
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN202010262620.8A priority Critical patent/CN111456754A/en
Publication of CN111456754A publication Critical patent/CN111456754A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/14Layout of tunnels or galleries; Constructional features of tunnels or galleries, not otherwise provided for, e.g. portals, day-light attenuation at tunnel openings
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • E21D11/385Sealing means positioned between adjacent lining members
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • E21F17/103Dams, e.g. for ventilation

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

A left-right partition tunnel auxiliary tunnel structure and a construction method thereof are provided, which are used for improving the utilization rate of a single auxiliary tunnel during operation and reducing the number of auxiliary tunnels of a rescue station section, thereby solving the problem of difficult site selection of the auxiliary tunnels in a complex and dangerous mountain area, reducing the engineering scale and lowering the engineering cost. The lining structure of the tunnel auxiliary gallery is composed of an arch wall primary supporting structure, an arch wall molded lining structure and a bottom plate structure, a reinforced concrete vertical partition wall for dividing the section of the tunnel auxiliary gallery into a personnel evacuation channel and a smoke exhaust channel is arranged in the tunnel auxiliary gallery, the upper end of the reinforced concrete vertical partition wall is fixedly connected with the arch crown part of the arch wall molded lining structure, and the lower end of the reinforced concrete vertical partition wall is fixedly connected with the bottom plate structure. The buried rubber waterstop is buried in the longitudinal construction joint of the reinforced concrete vertical partition wall.

Description

Auxiliary tunnel structure for left-right separation tunnel and construction method thereof
Technical Field
The invention relates to the technical field of auxiliary tunnel construction of railway tunnels and highway tunnels, in particular to an auxiliary tunnel structure for disaster prevention and rescue during operation and a construction method thereof.
Background
Since twenty-first century, along with the high-speed development of railway construction in China, high-standard double-track railways with the speed of 200km per hour are increasingly constructed, particularly in mountainous areas in the middle and western regions, line extension is limited by various factors such as large curve radius, complex terrain and geological conditions and the like, the scale of the tunnel is rapidly increased, the number of long and large mountain tunnels is increased, and meanwhile, the requirements of the long tunnel on auxiliary tunnels are increased by considering factors such as construction period, operational maintenance, disaster prevention, evacuation and rescue and the like.
In a conventional disaster prevention evacuation rescue project, particularly a repair-combined emergency rescue station in a tunnel, the evacuation requirement of people after a train on fire stops is met, and an independent people evacuation channel and a smoke evacuation channel are required to be arranged according to the principle of separating people from smoke, as shown in fig. 1 and 2. The personnel evacuation channel is connected with the evacuation flat guide and used for evacuating personnel outside the tunnel, and the smoke exhaust channel is connected with the smoke exhaust channel and used for exhausting fire smoke generated by the fire train, namely at least two auxiliary tunnels connected outside the tunnel need to be arranged on the tunnel body rescue station section. Due to the restrictions of terrain and geological conditions and environmental protection, the selection conditions and difficulties of the auxiliary tunnel with proper length and good entrance conditions are difficult to find on the key lines affecting the construction period of a newly built project, especially in the complicated and hard mountainous areas, so that the arrangement of the auxiliary tunnel at the rescue station is very necessary to be simplified.
Disclosure of Invention
The invention aims to solve the technical problem of providing an auxiliary tunnel structure of a left-right separation tunnel, so that the utilization rate of a single auxiliary tunnel in the operation period is improved, and the number of auxiliary tunnels of a rescue station section is reduced, thereby solving the problem of difficult site selection of the auxiliary tunnels in a complex and dangerous mountain area, reducing the engineering scale and reducing the engineering cost.
The technical scheme adopted by the invention for solving the technical problems is as follows:
the invention relates to a left-right separation tunnel auxiliary tunnel structure, wherein a lining structure of the tunnel auxiliary tunnel comprises an arch wall primary supporting structure, an arch wall molded lining structure and a bottom plate structure, and is characterized in that: a reinforced concrete vertical partition wall for dividing the section of the tunnel auxiliary gallery into a personnel evacuation channel and a smoke exhaust channel is arranged in the tunnel auxiliary gallery, the upper end of the reinforced concrete vertical partition wall is fixedly connected with the vault part of the arch wall molded lining structure, and the lower end of the reinforced concrete vertical partition wall is fixedly connected with the bottom plate structure; and a buried rubber waterstop is buried in the longitudinal construction joint of the reinforced concrete vertical partition wall.
Another technical problem to be solved by the present invention is to provide a method for constructing the auxiliary tunnel structure for the left-right separation tunnel, which includes the following steps:
①, according to the normal process, completing tunnel auxiliary gallery excavation and constructing an arch wall primary supporting structure;
② constructing a bottom plate structure;
③ binding the steel bars of the reinforced concrete vertical partition wall, pouring concrete in sections, and burying a buried rubber waterstop at the longitudinal construction joint;
④ constructing arch wall mold lining structure;
⑤ construction of drainage cover plate ditch and leveling layer in the evacuation channel, and drainage ditch in the smoke evacuation channel.
The invention has the advantages that the left and right partition tunnel auxiliary tunnel structure replaces the traditional auxiliary tunnel structure, on one hand, the principle of separating the human smoke in disaster prevention evacuation rescue is met, the human evacuation and the smoke pumping are both in independent space, and the utilization rate of a single auxiliary tunnel during operation is improved; on the other hand, additional auxiliary tunnels are avoided, and the problem that the auxiliary tunnels are difficult to select addresses is effectively solved. Meanwhile, the scale of the auxiliary tunnel project is reduced, and the construction cost is reduced.
Drawings
The specification includes the following five figures:
fig. 1 is a plan view of a personnel evacuation passageway and a smoke evacuation passageway of a conventional rescue station;
fig. 2 is a sectional view of a conventional tunnel auxiliary gallery structure;
fig. 3 is a plan view of a rescue station employing an auxiliary tunnel structure of a left-right divided tunnel according to the present invention;
fig. 4 is a sectional view of an auxiliary tunnel structure of a left-right divided tunnel according to the present invention;
FIG. 5 is an enlarged view of portion A of FIG. 4;
the figure shows the components, the part names and the corresponding marks: the system comprises a personnel evacuation channel 1, a smoke evacuation channel 2, a tunnel auxiliary gallery 3, an arch wall primary supporting structure 11, an arch wall mold lining structure 12, a bottom plate structure 13, a reinforced concrete vertical partition wall 14, partition wall reinforcing steel bars 14a, partition wall embedded rubber water stops 14b, partition wall concrete 14c, a leveling layer 15, a drainage cover plate ditch 16 and a drainage ditch 17.
Detailed Description
The invention is further illustrated with reference to the following figures and examples.
Referring to fig. 3 and 5, the lining structure of the tunnel auxiliary gallery 3 comprises an arch wall primary supporting structure 11, an arch wall mold lining structure 12 and a bottom plate structure 13, a reinforced concrete vertical partition wall 14 for dividing the section of the tunnel auxiliary gallery 3 into a personnel evacuation channel 1 and a smoke exhaust channel 2 is arranged in the tunnel auxiliary gallery 3, the upper end of the reinforced concrete vertical partition wall 14 is fixedly connected with the arch crown part of the arch wall mold lining structure 12, and the lower end of the reinforced concrete vertical partition wall is fixedly connected with the bottom plate structure 13; and a buried rubber water stop 14b is buried in the longitudinal construction joint of the reinforced concrete vertical partition wall 14.
According to the invention, through reasonably optimizing the structure of the tunnel auxiliary gallery, the separation of people and smoke is realized by using one auxiliary gallery, and the left side and the right side of the auxiliary gallery are divided into a personnel evacuation channel and a smoke exhaust channel through the vertical partition walls. The utilization rate of a single auxiliary tunnel in the operation period is improved, the number of auxiliary tunnels of a rescue station section is reduced, the problem of difficulty in site selection of the auxiliary tunnels is effectively solved, the project scale is reduced, and the project cost is reduced.
Referring to fig. 4, in the people evacuation channel 1, a drain cover gutter 16 is provided laterally outside the floor structure 13, and a screed 15 is laid on the floor structure 13. In the flue gas channel 2, a drain 17 is arranged laterally outside the floor structure 13.
Referring to fig. 4, the construction method of the auxiliary tunnel structure for the left-right separation tunnel of the present invention includes the steps of:
①, finishing the excavation of the tunnel auxiliary gallery 3 according to the normal working procedures and constructing an arch wall primary supporting structure 11;
②, constructing the floor structure 13;
③ binding the steel bars 14a of the reinforced concrete vertical partition wall 14, pouring concrete 14c in sections, and burying a buried rubber water stop 14b at the longitudinal construction joint;
④ constructing arch wall mold lining structure 12;
⑤ drainage cover plate ditch 16 and leveling layer 15 are constructed in the people evacuation channel 1, and drainage ditch 17 is constructed in the smoke evacuation channel 2.
The foregoing is only illustrative of some of the principles of the left and right divided tunnel auxiliary gallery structure and method of construction of the present invention, and is not intended to limit the invention to the specific structure and application shown and described, and accordingly all modifications and equivalents that may be employed fall within the scope of the claims of the invention.

Claims (4)

1. The utility model provides a control supplementary gallery structure of partition tunnel, the lining structure of supplementary gallery of tunnel (3) is by hunch wall preliminary bracing structure (11), hunch wall mould lining structure (12) and floor structure (13), characterized by: a reinforced concrete vertical partition wall (14) for dividing the section of the tunnel auxiliary gallery (3) into a personnel evacuation channel (1) and a smoke exhaust channel (2) is arranged in the tunnel auxiliary gallery, the upper end of the reinforced concrete vertical partition wall (14) is fixedly connected with the arch crown part of an arch wall mold lining structure (12), and the lower end of the reinforced concrete vertical partition wall is fixedly connected with a bottom plate structure (13); and a buried rubber water stop (14b) is buried at the longitudinal construction joint of the reinforced concrete vertical partition wall (14).
2. The auxiliary tunnel structure of the left and right divided tunnels according to claim 1, wherein: in the people evacuation channel (1), a drainage cover plate ditch (16) is arranged on the transverse outer side of the bottom plate structure (13), and a leveling layer (15) is laid on the bottom plate structure (13).
3. The auxiliary tunnel structure of the left and right divided tunnels according to claim 1, wherein: in the smoke exhaust channel (2), a drainage ditch (17) is arranged on the transverse outer side of the bottom plate structure (13).
4. A construction method of an auxiliary tunnel structure for a tunnel divided left and right as claimed in any one of claims 1 to 3, comprising the steps of:
①, finishing the excavation of the tunnel auxiliary gallery (3) and constructing an arch wall primary supporting structure (11) according to the normal procedures;
②, constructing a floor structure (13);
③ binding the steel bars (14a) of the reinforced concrete vertical partition wall (14), pouring concrete (14c) in sections, and burying a buried rubber water stop (14b) at the longitudinal construction joint;
④ constructing arch wall mould lining structure (12);
⑤ A drainage cover plate ditch (16) and a leveling layer (15) are constructed in the personnel evacuation channel (1), and a drainage ditch (17) is constructed in the smoke evacuation channel (2).
CN202010262620.8A 2020-04-05 2020-04-05 Auxiliary tunnel structure for left-right separation tunnel and construction method thereof Pending CN111456754A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010262620.8A CN111456754A (en) 2020-04-05 2020-04-05 Auxiliary tunnel structure for left-right separation tunnel and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010262620.8A CN111456754A (en) 2020-04-05 2020-04-05 Auxiliary tunnel structure for left-right separation tunnel and construction method thereof

Publications (1)

Publication Number Publication Date
CN111456754A true CN111456754A (en) 2020-07-28

Family

ID=71683628

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010262620.8A Pending CN111456754A (en) 2020-04-05 2020-04-05 Auxiliary tunnel structure for left-right separation tunnel and construction method thereof

Country Status (1)

Country Link
CN (1) CN111456754A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282841A (en) * 2020-12-03 2021-01-29 中铁建大桥工程局集团第五工程有限公司 Rapid drainage and slag discharge system for full-section tunnel and construction method
CN114215598A (en) * 2021-12-24 2022-03-22 中铁二院工程集团有限责任公司 Single-hole double-track railway tunnel and method for reducing influence of train derailment on adjacent track operation

Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003314200A (en) * 2002-04-24 2003-11-06 Kajima Corp Tunnel ventilating system and tunnel ventilating method
JP2004270345A (en) * 2003-03-10 2004-09-30 Railway Technical Res Inst Pressure wave damping structure for fixed construction
JP2004324188A (en) * 2003-04-24 2004-11-18 Okumura Corp Dust collecting method in tunnel and apparatus constructing method
JP2005282085A (en) * 2004-03-29 2005-10-13 Sekisui Chem Co Ltd Movably partitioning method and movable partition panel metal fixture
CN104314601A (en) * 2014-11-19 2015-01-28 上海市城市建设设计研究总院 Natural ventilation tunnel structure
CN204126663U (en) * 2014-10-08 2015-01-28 西南交通大学 A kind of single hole big cross section Extra Long Tunnel Construction ventilation system
KR20150024119A (en) * 2013-08-26 2015-03-06 윤세모 Structure and manufacture method for barrier rib of wind duct
KR20160013387A (en) * 2014-07-25 2016-02-04 한국도로공사 Inclined shaft structure to convert air direction
KR20170104790A (en) * 2016-03-08 2017-09-18 청암건업 주식회사 Division structure for horizontal hall and construction method thereof
JP2018096161A (en) * 2016-12-15 2018-06-21 清水建設株式会社 Duct for air ventilation in pit
CN108425700A (en) * 2018-03-14 2018-08-21 中冶京诚工程技术有限公司 A kind of shield method pipe gallery
CN109139040A (en) * 2018-10-25 2019-01-04 中冶京诚工程技术有限公司 A kind of comprehensive pipe gallery structure of comprehensive utilization of energy
CN209704616U (en) * 2018-08-21 2019-11-29 中铁二院工程集团有限责任公司 Take into account the High aititude railway tunnel service gallery liner structure of construction, ventilation of taking precautions against natural calamities
CN110700851A (en) * 2019-10-14 2020-01-17 中铁第四勘察设计院集团有限公司 Single-hole double-line jet fan tunnel section based on urban D-type vehicle clearance design
CN212225230U (en) * 2020-04-05 2020-12-25 中铁二院工程集团有限责任公司 Left-right separation tunnel auxiliary tunnel structure

Patent Citations (15)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2003314200A (en) * 2002-04-24 2003-11-06 Kajima Corp Tunnel ventilating system and tunnel ventilating method
JP2004270345A (en) * 2003-03-10 2004-09-30 Railway Technical Res Inst Pressure wave damping structure for fixed construction
JP2004324188A (en) * 2003-04-24 2004-11-18 Okumura Corp Dust collecting method in tunnel and apparatus constructing method
JP2005282085A (en) * 2004-03-29 2005-10-13 Sekisui Chem Co Ltd Movably partitioning method and movable partition panel metal fixture
KR20150024119A (en) * 2013-08-26 2015-03-06 윤세모 Structure and manufacture method for barrier rib of wind duct
KR20160013387A (en) * 2014-07-25 2016-02-04 한국도로공사 Inclined shaft structure to convert air direction
CN204126663U (en) * 2014-10-08 2015-01-28 西南交通大学 A kind of single hole big cross section Extra Long Tunnel Construction ventilation system
CN104314601A (en) * 2014-11-19 2015-01-28 上海市城市建设设计研究总院 Natural ventilation tunnel structure
KR20170104790A (en) * 2016-03-08 2017-09-18 청암건업 주식회사 Division structure for horizontal hall and construction method thereof
JP2018096161A (en) * 2016-12-15 2018-06-21 清水建設株式会社 Duct for air ventilation in pit
CN108425700A (en) * 2018-03-14 2018-08-21 中冶京诚工程技术有限公司 A kind of shield method pipe gallery
CN209704616U (en) * 2018-08-21 2019-11-29 中铁二院工程集团有限责任公司 Take into account the High aititude railway tunnel service gallery liner structure of construction, ventilation of taking precautions against natural calamities
CN109139040A (en) * 2018-10-25 2019-01-04 中冶京诚工程技术有限公司 A kind of comprehensive pipe gallery structure of comprehensive utilization of energy
CN110700851A (en) * 2019-10-14 2020-01-17 中铁第四勘察设计院集团有限公司 Single-hole double-line jet fan tunnel section based on urban D-type vehicle clearance design
CN212225230U (en) * 2020-04-05 2020-12-25 中铁二院工程集团有限责任公司 Left-right separation tunnel auxiliary tunnel structure

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112282841A (en) * 2020-12-03 2021-01-29 中铁建大桥工程局集团第五工程有限公司 Rapid drainage and slag discharge system for full-section tunnel and construction method
CN114215598A (en) * 2021-12-24 2022-03-22 中铁二院工程集团有限责任公司 Single-hole double-track railway tunnel and method for reducing influence of train derailment on adjacent track operation
CN114215598B (en) * 2021-12-24 2023-10-03 中铁二院工程集团有限责任公司 Single-hole double-line railway tunnel and method for reducing influence of train derailment on adjacent line operation

Similar Documents

Publication Publication Date Title
CN103256052B (en) Construction method for integral straight middle wall type double-arch tunnel
CN111456754A (en) Auxiliary tunnel structure for left-right separation tunnel and construction method thereof
CN105240024A (en) Parallel shield tunneling method for extended construction of subway station
CN113847040B (en) Large-span non-column underground station underground excavation construction method
CN213088012U (en) Tunnel auxiliary gallery structure with upper and lower partitions
CN107401413A (en) Tunnel structure for expansive stratum
CN108843380A (en) Precast construction under a kind of Railway Tunnel three-piece type rail
CN208073481U (en) Mountainous City Underground Subway Station vented construction
CN115182737A (en) Vertical orthogonal ejection type air duct structure of deep-buried subway station and construction method
CN212225230U (en) Left-right separation tunnel auxiliary tunnel structure
CN207568626U (en) A kind of tunnel structure for expansive stratum
CN111502689A (en) Upper and lower partition tunnel auxiliary tunnel structure and construction method thereof
CN111794782A (en) Tunnel track ballast bed water-drainage preventing structure and construction method thereof
CN112922646A (en) Building method of underground excavation station excavated by large-section single-span support through superposed arch-wall integrated type
CN112282788A (en) Railway TBM construction tunnel section structure
CN105156130B (en) A kind of constructing tunnel exempts from supporting safe construction method
CN111719344A (en) Ballast bed water-proof and drainage structure
CN115142854B (en) Mine method tunnel single-layer lining structure system and construction method
CN111794757B (en) Underground water treatment method for composite stratum subsurface excavation construction under existing building
RU101054U1 (en) TRANSPORT TUNNEL FOR ROAD AND / OR RAILWAY
CN112253172B (en) Tunnel bottom lining structure provided with tie beam and construction method thereof
CN210509196U (en) Large-section tunnel structure of hard rock stratum underground excavation single-layer lining subway parking line
CN214221203U (en) Tunnel bottom lining structure provided with tie beam
CN208718721U (en) A kind of railway large diameter shield tunnel rail flowering structure of rapid construction
CN112900493A (en) From waterproof uncovered piping lane

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination