CN111441526A - Method for installing upper fixed node of clean ceiling of electronic factory building - Google Patents
Method for installing upper fixed node of clean ceiling of electronic factory building Download PDFInfo
- Publication number
- CN111441526A CN111441526A CN201910043903.0A CN201910043903A CN111441526A CN 111441526 A CN111441526 A CN 111441526A CN 201910043903 A CN201910043903 A CN 201910043903A CN 111441526 A CN111441526 A CN 111441526A
- Authority
- CN
- China
- Prior art keywords
- ceiling
- shaped steel
- suspended ceiling
- installing
- factory building
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
-
- E—FIXED CONSTRUCTIONS
- E04—BUILDING
- E04B—GENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
- E04B9/00—Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
- E04B9/18—Means for suspending the supporting construction
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G3/00—Installations of electric cables or lines or protective tubing therefor in or on buildings, equivalent structures or vehicles
- H02G3/36—Installations of cables or lines in walls, floors or ceilings
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Physics & Mathematics (AREA)
- Electromagnetism (AREA)
- Supports For Pipes And Cables (AREA)
Abstract
The invention discloses a method for installing a fixed node at the upper part of a clean suspended ceiling of an electronic factory building, and aims to provide a method which is convenient, quick, flexible, bidirectionally adjustable, pre-buried once and shared for multiple times for field installation. The fixed furred ceiling that does not need each specialty to punch alone to and the vexation of cross operation. When the clean room ceiling is constructed, after the C-shaped steel is pre-embedded for one time, the MEP electromechanical pipeline support is hung on the clean room ceiling and is shared with the ceiling. The method reduces the complexity of working procedures in the aspect of construction, can not be well connected in order, and simultaneously reduces the work of cleaning for a plurality of times due to multiple pollution.
Description
Technical Field
The invention belongs to the field of ceiling installation, and particularly relates to an installation method of an upper fixed node of a clean ceiling of an electronic factory building.
Background
The ceiling of the clean room is connected with the structural floor slab, and the expansion anchor bolt single-point fixing is adopted in the conventional method.
At present, chinese patent with publication number CN105507478A discloses a furred ceiling installation component, including lead screw, main joist, connection hanger, triangle fossil fragments, the lead screw passes through expansion bolts to be fixed to the building top surface, it uses the nut to pass through to connect hanger the screw with lead screw swing joint, the main joist cup joints in the connection hanger, still includes bilateral hanging piece, bilateral hanging piece carries on the main joist, the part of the suspension clasp at bilateral hanging piece both ends is do not the straining triangle fossil fragments reach the atress and spread out smoothly, the direction of triangle fossil fragments with the direction of main joist is perpendicular.
The prior art comprises the following contents: typesetting according to the size of the ceiling board of the clean room, firstly carrying out construction setting in the X-axis direction and the Y-axis direction, mechanically punching and installing an expansion anchor bolt lower hanging suspender at a cross point, and then installing a hanging part and a keel.
The existing installation process has the following defects: if the construction paying-off and punching positions are inaccurate, construction deviation exists, and accumulated deviation exists, the installation cannot be carried out, secondary punching and hole patching are carried out, and the installation is relocated; even small deviations can affect the verticality of the lower suspension system.
Disclosure of Invention
The invention aims to provide a method for installing a fixed node at the upper part of a clean ceiling of an electronic factory building. The device has the advantages of convenient, quick, flexible and bidirectional adjustment in field installation, one-time pre-embedding and multiple sharing.
The purpose of the invention can be realized by the following technical scheme:
a method for installing a fixed node at the upper part of a clean ceiling of an electronic factory building comprises the following installation steps:
s01, paying off at the bottom of the structural floor slab, and installing C-shaped steel by using anchor bolts;
s02, mounting a screw rod of the suspended ceiling through a spring nut at the lower notch of the C-shaped steel;
s03, adjusting the position of the suspender in the X direction of the lower notch of the C-shaped steel according to the arrangement of the ceiling tiles;
s04, installing a connecting piece at the lower part of the suspender, and fixing the connecting piece with the ceiling keel to realize Y-direction adjustment;
s05, mounting an MEP electromechanical pipeline support in the suspended ceiling, and fixing the suspended ceiling with the C-shaped steel through a spring nut;
and S06, checking and accepting, finally installing the ceiling board, adjusting the levelness and the verticality, and finishing the installation.
Adopt rearmounted pre-buried C shaped steel mode, fix C shaped steel in the structure bottom with the crab-bolt earlier, then hang substructure through C shaped steel notch, satisfy toilet's suspension system problem promptly, also solved MEP electromechanical pipeline support hanging point problem simultaneously. The fixed furred ceiling that does not need each specialty to punch alone to and the vexation of cross operation.
When the clean room ceiling is constructed, after the C-shaped steel is pre-embedded for one time, the MEP electromechanical pipeline support is hung on the clean room ceiling and is shared with the ceiling. The method reduces the complexity of working procedures in the aspect of construction, can not be well connected in order, and simultaneously reduces the work of cleaning for a plurality of times due to multiple pollution.
The invention has the beneficial effects that:
(1) the traditional single-point fixing method is changed by adopting a post-embedded C-shaped steel mode;
(2) the ceiling of the clean room is convenient to install, and meanwhile, the ceiling problem of the MEP electromechanical pipeline support can be solved;
(3) in the aspect of construction process, the construction method is used for multiple times through one-time pre-embedding;
(4) avoid punching and pre-burying for many times, dust pollution for many times brings the vexation for cleaning work.
Drawings
FIG. 1 is a schematic view of the X-direction structure;
fig. 2 is a schematic view of the structure in the Y direction.
In the figure, the position of the upper end of the main shaft,
1. an anchor bolt; 2. c-shaped steel; 3. a spring nut; 5. a suspended ceiling; 6. a boom; 7. a connecting member; 8. a ceiling keel; 9. MEP electromechanical pipeline support.
Detailed Description
Example 1: a method for installing a fixed node at the upper part of a clean ceiling 5 of an electronic factory building, as shown in figures 1 and 2, comprises the following installation steps:
s01, constructing and paying off at the bottom of the structural floor slab, and installing C-shaped steel 2 by using anchor bolts 1;
s02, mounting a screw rod of the suspended ceiling 5 on the lower notch of the C-shaped steel 2 through a spring nut 3;
s03, adjusting the position of the suspender 6 in the X direction of the lower notch of the C-shaped steel 2 according to the arrangement of the ceiling 5 plates;
s04, installing a connecting piece 7 at the lower part of the suspender 6, and fixing the connecting piece 7 with a keel of the suspended ceiling 5 to realize Y-direction adjustment;
s05, mounting an MEP electromechanical pipeline support 9 in the suspended ceiling 5, and fixing the suspended ceiling 5 and the C-shaped steel 2 through the spring nut 3;
and S06, checking and accepting, finally installing the suspended ceiling 5 plate, adjusting the levelness and the verticality, and finishing the installation.
Adopt rearmounted pre-buried C shaped steel 2 mode, fix C shaped steel 2 in the structure bottom with crab-bolt 1 earlier, then hang substructure through C shaped steel 2 notches, satisfy toilet's suspension system problem promptly, also solved MEP electromechanical pipeline support 9 simultaneously and hung a little problem. The fixed suspended ceiling 5 does not need to be punched independently by each specialty to and the trouble of cross operation is avoided.
When the clean room suspended ceiling 5 is constructed, after the C-shaped steel 2 is pre-embedded for one time, the MEP electromechanical pipeline support 9 is hung on the top and is shared with the suspended ceiling 5. The method reduces the complexity of working procedures in the aspect of construction, can not be well connected in order, and simultaneously reduces the work of cleaning for a plurality of times due to multiple pollution.
(1) The traditional single-point fixing method is changed by adopting a mode of rear pre-embedding C-shaped steel 2;
(2) the clean room ceiling 5 is convenient to install, and meanwhile, the problem of the MEP electromechanical pipeline support 9 ceiling 5 can be solved;
(3) in the aspect of construction process, the construction method is used for multiple times through one-time pre-embedding;
(4) avoid punching and pre-burying for many times, dust pollution for many times brings the vexation for cleaning work.
Finally, it should be noted that: although the present invention has been described in detail with reference to the above embodiments, it should be understood by those skilled in the art that: modifications and equivalents may be made thereto without departing from the spirit and scope of the invention, and the appended claims are intended to cover such modifications and equivalents as fall within the true spirit and scope of the invention.
Claims (1)
1. The utility model provides an installation method of upper fixed node of clean suspended ceiling of electronic factory building, which is characterized in that: the method comprises the following installation steps:
s01, paying off at the bottom of the structural floor slab, and installing C-shaped steel (2) by using an anchor bolt (1);
s02, mounting a screw rod of the suspended ceiling (5) through a spring nut (3) at the lower notch of the C-shaped steel (2);
s03, adjusting the position of the suspender (6) in the X direction of the lower notch of the C-shaped steel (2) according to the arrangement of the ceiling (5) plates;
s04, a connecting piece (7) is arranged at the lower part of the suspender (6) and is fixed with a keel of the suspended ceiling (5) through the connecting piece (7), so that Y-direction adjustment is realized;
s05, mounting an MEP electromechanical pipeline support (9) in the suspended ceiling (5), and fixing the suspended ceiling (5) with the C-shaped steel (2) through a spring nut (3);
and S06, checking and accepting, finally installing a ceiling (5) plate, adjusting the levelness and the verticality, and finishing the installation.
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910043903.0A CN111441526A (en) | 2019-01-17 | 2019-01-17 | Method for installing upper fixed node of clean ceiling of electronic factory building |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201910043903.0A CN111441526A (en) | 2019-01-17 | 2019-01-17 | Method for installing upper fixed node of clean ceiling of electronic factory building |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111441526A true CN111441526A (en) | 2020-07-24 |
Family
ID=71626982
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201910043903.0A Pending CN111441526A (en) | 2019-01-17 | 2019-01-17 | Method for installing upper fixed node of clean ceiling of electronic factory building |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111441526A (en) |
Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3769774A (en) * | 1972-06-26 | 1973-11-06 | W Barnes | Steel deck insert |
JPH03181606A (en) * | 1989-12-11 | 1991-08-07 | Chem Seiko:Kk | Receiving tool for suspension bolt on ceiling and the like |
CN201258548Y (en) * | 2008-08-18 | 2009-06-17 | 上海德瑞金属制品有限公司 | Steel frame fixer |
CN202157448U (en) * | 2011-06-29 | 2012-03-07 | 中国电子系统工程第四建设有限公司 | Hanging device without destroying roof structure |
CN203383383U (en) * | 2013-06-14 | 2014-01-08 | 厦门特房建设工程集团有限公司 | Adjustable type ceiling device |
CN203756700U (en) * | 2013-10-28 | 2014-08-06 | 上海舒雨建筑材料有限公司 | Spring nut for C-shaped steel |
CN203927373U (en) * | 2014-07-02 | 2014-11-05 | 上海新奇五金有限公司 | Shaped steel reinforcer |
CN204358256U (en) * | 2014-11-22 | 2015-05-27 | 苏州耀洲金属制品有限公司 | Groove top formula pipeline elevator |
CN105645256A (en) * | 2014-11-22 | 2016-06-08 | 苏州耀洲金属制品有限公司 | Span beam type pipeline hanger |
CN205475953U (en) * | 2016-04-01 | 2016-08-17 | 柏诚工程股份有限公司 | Clean laminar flow hood's of large -scale pharmacy mounting structure |
CN106284815A (en) * | 2016-08-12 | 2017-01-04 | 中国航天建设集团有限公司 | Furred ceiling clean board construction technique |
CN106481014A (en) * | 2016-12-21 | 2017-03-08 | 北京市第三建筑工程有限公司 | Using the mineral wool abatvoix furred ceiling nothing suspension rod keel installation and its construction method |
CN207260404U (en) * | 2017-06-06 | 2018-04-20 | 深圳瑞和建筑装饰股份有限公司 | Furred ceiling bulk and furred ceiling |
US20180347615A1 (en) * | 2017-06-06 | 2018-12-06 | Michael A. Martin | Fastener system for use in securing an object to a channel beam |
CN109025028A (en) * | 2018-07-13 | 2018-12-18 | 中国十七冶集团有限公司 | People's furred ceiling and construction method in a kind of toilet |
-
2019
- 2019-01-17 CN CN201910043903.0A patent/CN111441526A/en active Pending
Patent Citations (15)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US3769774A (en) * | 1972-06-26 | 1973-11-06 | W Barnes | Steel deck insert |
JPH03181606A (en) * | 1989-12-11 | 1991-08-07 | Chem Seiko:Kk | Receiving tool for suspension bolt on ceiling and the like |
CN201258548Y (en) * | 2008-08-18 | 2009-06-17 | 上海德瑞金属制品有限公司 | Steel frame fixer |
CN202157448U (en) * | 2011-06-29 | 2012-03-07 | 中国电子系统工程第四建设有限公司 | Hanging device without destroying roof structure |
CN203383383U (en) * | 2013-06-14 | 2014-01-08 | 厦门特房建设工程集团有限公司 | Adjustable type ceiling device |
CN203756700U (en) * | 2013-10-28 | 2014-08-06 | 上海舒雨建筑材料有限公司 | Spring nut for C-shaped steel |
CN203927373U (en) * | 2014-07-02 | 2014-11-05 | 上海新奇五金有限公司 | Shaped steel reinforcer |
CN204358256U (en) * | 2014-11-22 | 2015-05-27 | 苏州耀洲金属制品有限公司 | Groove top formula pipeline elevator |
CN105645256A (en) * | 2014-11-22 | 2016-06-08 | 苏州耀洲金属制品有限公司 | Span beam type pipeline hanger |
CN205475953U (en) * | 2016-04-01 | 2016-08-17 | 柏诚工程股份有限公司 | Clean laminar flow hood's of large -scale pharmacy mounting structure |
CN106284815A (en) * | 2016-08-12 | 2017-01-04 | 中国航天建设集团有限公司 | Furred ceiling clean board construction technique |
CN106481014A (en) * | 2016-12-21 | 2017-03-08 | 北京市第三建筑工程有限公司 | Using the mineral wool abatvoix furred ceiling nothing suspension rod keel installation and its construction method |
CN207260404U (en) * | 2017-06-06 | 2018-04-20 | 深圳瑞和建筑装饰股份有限公司 | Furred ceiling bulk and furred ceiling |
US20180347615A1 (en) * | 2017-06-06 | 2018-12-06 | Michael A. Martin | Fastener system for use in securing an object to a channel beam |
CN109025028A (en) * | 2018-07-13 | 2018-12-18 | 中国十七冶集团有限公司 | People's furred ceiling and construction method in a kind of toilet |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN111441526A (en) | Method for installing upper fixed node of clean ceiling of electronic factory building | |
CN204534892U (en) | A kind of Bidirectional adjustable air conditioner support | |
EP3033461A1 (en) | Primary and intermediate horizontal leveler | |
CN204230807U (en) | A kind of power cable crane span structure supporting structure being easy to regulate | |
JP4646679B2 (en) | Frame material support structure | |
CN214614939U (en) | Metal wall plate connecting and supporting system | |
CN108824689B (en) | Hyperboloid furred ceiling installation component | |
JP6135912B2 (en) | Ceiling foundation hardware and ceiling structure | |
CN220516711U (en) | Simple top plate bolt mounting tool | |
CN213806092U (en) | Ceiling connecting piece | |
CN105804307A (en) | Ceiling device | |
CN101718138B (en) | Large metal veneer suspending assembly | |
CN214785176U (en) | Concrete curtain wall plate dry hanging device | |
CN205504207U (en) | Pipeline hanger | |
CN215519436U (en) | Suspended ceiling connecting structure for movable vacation house | |
CN220172776U (en) | Bridge mounting bracket structure | |
CN211250703U (en) | Hoisting tool for concrete prefabricated part | |
CN217680228U (en) | Wall surface three-dimensional adjustable keel system | |
CN219909557U (en) | Suspended ceiling construction device free of reverse support of suspender | |
CN220080466U (en) | Light steel joist furred ceiling | |
CN214364634U (en) | Adjustable hanging piece for mounting assembly type building envelope structural slab | |
CN217128835U (en) | Convenient side fascia installed part | |
CN203645236U (en) | Bus duct angle iron hanging bracket | |
JP7202849B2 (en) | Mounting structure for unit room | |
CN214739068U (en) | Construction structure of component for fixing lower supporting plate of stone curtain wall |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200724 |
|