Prior art keywords
sunpender
mariages
furred ceiling
toilet
people
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810769912.3A
Other languages
Chinese (zh)
Inventor
王芝保
尹万云
唐世敏
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China MCC17 Group Co Ltd
Original Assignee
China MCC17 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China MCC17 Group Co Ltd filed Critical China MCC17 Group Co Ltd
Priority to CN201810769912.3A priority Critical patent/CN109025028A/en
Publication of CN109025028A publication Critical patent/CN109025028A/en
Pending legal-status Critical Current

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/06Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation characterised by constructional features of the supporting construction, e.g. cross section or material of framework members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B9/00Ceilings; Construction of ceilings, e.g. false ceilings; Ceiling construction with regard to insulation
    • E04B9/18Means for suspending the supporting construction
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Mechanical Engineering (AREA)
  • Residential Or Office Buildings (AREA)

Abstract

The present invention provides people's furred ceiling and construction method in a kind of toilet, including furred ceiling cleaning board finish, aluminium mariages sunpender, girt, mariages sunpender is multiple groups, top is provided with fixing piece and connect with floor, its underpart is connect by rectangular regulating part with aluminium alloy main joist, and clean board finish is mounted between adjacent aluminium alloy main joist, and adjacent mariages sunpender is within clean board furred ceiling surface layer height 1.5m, using girt by connector drawknot, it is whole to form space.Structure of the invention is simple, it is easy to operate, reduce construction cost, simplify processing step, the space of toilet's technology interlayer is widened, simultaneously by setting mariages sunpender and girt, phenomena such as overload deforms, falls off can be overhauled to avoid people on toilet's furred ceiling, improve construction quality.Solves existing toilet's furred ceiling there are consumptive materials the defects of more, higher cost, complex process, and congestion can't bear in interlayer, it is difficult to the problem of meeting each profession operation and maintenance function.

Description

People's furred ceiling and construction method in a kind of toilet
Technical field
The present invention relates to technical field of building construction, people's furred ceiling and construction method in specially a kind of toilet.
Background technique
Currently, toilet has been widely used the region that purity requirements are high in the fields such as electronics, medical treatment, food, it is clean The sealing system that room generally uses clean board to go along with sb. to guard him is provided with interlayer in toilet's furred ceiling, is to install various equipment systems Water pipe, cable, air hose, combustion gas, steam and other auxiliary devices of system and the building storey specially built, at the same it is also each to meet The installation of class pipeline, operation, maintenance requirement.Therefore the height in toilet's furred ceiling is often beyond 1.5m or more, to be formed Sunpender slenderness ratio is excessive, and easy stress is unbalance and furred ceiling is caused to deform, therefore reversed support should be arranged in related specification requirement, or Furred ceiling conversion layer, and maintenance riding track are further arranged using steelframe, prevent furred ceiling from deforming, falling off and meet inspection in furred ceiling Build the function of people.
The reversed support of setting, conversion layer or the method for overhauling riding track in existing toilet's furred ceiling, that there are consumptive materials is more, at The defects of this is higher, complex process, and can't bear more congestion in originally compact interlayer, it is difficult to meet each profession Operation and maintenance function.
Therefore, in toilet's engineering ceiling construction, should be avoided setup cost it is higher, it is complex process it is reversed support, turn Layer or maintenance riding track are changed, while reducing furred ceiling and the unfavorable factors such as deforming and dropping off, is further increased in toilet's technology interlayer Each profession operation and maintenance convenience, accelerating construction progress with quality management is solved the problems, such as required for toilet's construction.
Summary of the invention
To achieve the above object, the present invention provides people's furred ceiling and construction method in a kind of toilet:
People's furred ceiling in a kind of toilet, including building floor and clean board, which is characterized in that the lower end of the building floor Surface is fixedly connected with setscrew, and the lower end of the setscrew is fixedly connected with fixing piece, the fixing piece upper and lower extremities back Bolt hole is offered, is connected with mariages sunpender in the bolt hole of the fixing piece lower limb back;Up and down the two of the mariages sunpender End and middle part are threaded with nut, and the upper end of the mariages sunpender is fixedly connected by nut with fixing piece, described double The middle part of silk sunpender is fixedly connected with connector by nut, and the lower end of the mariages sunpender is fixedly connected with rectangular by nut Regulating part;The web of the connector and the junction of mariages sunpender offer opening U-type groove, two side wing edges of the connector Place offers bolt hole, and girt, level described in two sides are respectively connected in the bolt hole of two side wing edge of the connector The junction of pull rod and connector is threaded with nut, and girt described in two sides connects by the way that nut and connector are fixed It connects;The upper and lower ends of the rectangular regulating part are opened up there are two bolt hole, are connected in the bolt hole of the rectangular regulating part lower end It is connected to fastening bolt, described that aluminium alloy main joist is fixedly connected with by rectangular regulating part fastening bolt, the described aluminium alloy master The two sidewalls lower end of keel is fixedly connected to aluminum corner brace, and the aluminum corner brace both wings are equipped with self-tapping screw, and the aluminum corner brace passes through self tapping Clean board is fixedly connected at the lower end both wings of aluminium alloy main joist by screw.
Preferably, the junction of the aluminium alloy main joist and fastening bolt offers T-slot.
Preferably, filled with fire proofings such as rock wools in the clean board.
Preferably, the mariages sunpender is two zinc-plated sunpenders of full wire, and the girt is the zinc-plated sunpender of single full wire.
Preferably, the fixing piece is made of galvanizing bath steel, and the connector has zinc-plated C-type steel to be made, the rectangular tune Section part is made of galvanized steel plain sheet, and the aluminium alloy main joist is the hanging beam with T-slot, and the clean board is two-sided color coated steel sheet.
The construction method of people's furred ceiling in a kind of toilet, comprising the following steps:
In toilet before people's ceiling construction, the horizontal line for setting toilet's furred ceiling is surveyed using five line laser levels for step 1 With the position of aluminium alloy main joist, hole is taken on building floor along aluminium alloy main joist, is pacified fixing piece with two setscrews It on building floor, is hung on fixing piece under mariages sunpender double nut, each group mariages is set using the survey of five line laser levels The height of sunpender, extra sunpender are cut off using electric angle grinder and are flushed, and its underpart is connected by rectangular regulating part with double nut;
Step 2 penetrates the bolt head of fastening bolt in the T-slot of aluminium alloy main joist, and is mounted on rectangular regulating part On, then clean board sequence is mounted between two adjacent aluminium alloy main joists, is fixed with aluminum corner brace and self-tapping screw;
Step 3 adjusts the levelness of furred ceiling by the double nut at the rectangular regulating part of mariages downrod lower end, then will even Fitting opening U-lag is mounted among mariages sunpender, is fixed with double nut, adjacent double by connector drawknot using girt Silk sunpender, it is whole to form space.
Preferably, in step 3, the adjacent mariages sunpender is apart from clean board furred ceiling surface layer height within 1.5m.
It is compared with prior art, the present invention having the following advantages and benefits:
1) people's furred ceiling in the toilet carries self weight and maintenance load of clean board furred ceiling etc. by setting mariages sunpender, Bearing capacity is not only increased, and when upper people maintenance overloads, wherein a sunpender falls off, another sunpender can also continue Carrying, mariages sunpender ensure each other;
2) people's furred ceiling in the toilet, by being provided with girt between adjacent mariages sunpender, even if one group of mariages is hung Bar falls off, and girt can also play the role of drawknot furred ceiling.
Structure of the invention is simple, easy to operate, reduces construction cost, simplifies processing step, has widened toilet The space of interlayer, while by setting mariages sunpender and girt, overload can be overhauled to avoid people on toilet's furred ceiling Phenomena such as deforming, falling off, improves construction quality.It solves existing toilet mentioned above in the background art to hang The defects of top there are consumptive materials more, higher cost, complex process, and congestion can't bear in interlayer, it is difficult to meet each profession fortune The problem of row and maintenance function.
Detailed description of the invention
Fig. 1 is structural schematic diagram of the invention;
Fig. 2 is A-A cross-sectional view of the invention;
In figure: 1 building floor, 2 setscrews, 3 fixing pieces, 4 nuts, 5 mariages sunpenders, 6 connectors, 7 girts, 8 Rectangular regulating part, 9 fastening bolts, 10 aluminium alloy main joists, 11 clean boards, 12 aluminum corner braces, 13 self-tapping screws.
Specific embodiment
In order to make the objectives, technical solutions, and advantages of the present invention clearer, with reference to embodiments, to the present invention It is further elaborated.It should be appreciated that the specific embodiments described herein are merely illustrative of the present invention, it is not used to Limit the present invention.
With reference to the accompanying drawing and specific embodiment is further described application principle of the invention.
Embodiment one
People's furred ceiling in a kind of toilet as shown in Figure 1 to Figure 2, including building floor 1 and clean board 11, building floor 1 Rear surface be fixedly connected with setscrew 2, the lower end of setscrew 2 is fixedly connected with fixing piece 3,3 upper and lower extremities of fixing piece Back offers bolt hole, is connected with mariages sunpender 5 in the bolt hole of 3 lower limb of fixing piece back;The upper and lower ends of mariages sunpender 5 and Middle part is threaded with nut 4, and the upper end of mariages sunpender 5 is fixedly connected by nut 4 with fixing piece 3, mariages sunpender 5 Middle part is fixedly connected with connector 6 by nut 4, and the lower end of mariages sunpender 5 is fixedly connected with rectangular regulating part 8 by nut 4; The web of connector 6 and the junction of mariages sunpender 5 offer opening U-type groove, offer spiral shell at two side wing edges of connector 6 Keyhole, and girt 7, the company of two sides girt 7 and connector 6 are respectively connected in the bolt hole of 6 liang of side wing edges of connector The place of connecing is threaded with nut 4, and two sides girt 7 is fixedly connected by nut 4 with connector 6;Rectangular regulating part 8 it is upper Lower both ends are opened up there are two bolt hole, are connected with fastening bolt 9 in the bolt hole of rectangular 8 lower end of regulating part, are passed through rectangular tune Section part 8 fastening bolt 9 is fixedly connected with aluminium alloy main joist 10, and the two sidewalls lower end of aluminium alloy main joist 10 is fixedly connected with There is aluminum corner brace 12,12 both wings of aluminum corner brace are equipped with self-tapping screw 13, and clean board 11 is fixedly connected on by aluminum corner brace 12 by self-tapping screw 13 At the lower end both wings of aluminium alloy main joist 10.
Wherein, the junction of aluminium alloy main joist 10 and fastening bolt 9 offers T-slot, is filled with rock in clean board 11 The fire proofings such as cotton, mariages sunpender 5 are two zinc-plated sunpenders of full wire, and girt 7 is the zinc-plated sunpender of single full wire, fixing piece 3 It is made of galvanizing bath steel, connector 6 has zinc-plated C-type steel to be made, and rectangular regulating part 8 is made of galvanized steel plain sheet, aluminium alloy main joist 10 be the hanging beam with T-slot, and clean board 11 is two-sided color coated steel sheet.
The construction method of people's furred ceiling in a kind of toilet, comprising the following steps:
In toilet before people's ceiling construction, the horizontal line for setting toilet's furred ceiling is surveyed using five line laser levels for step 1 With the position of aluminium alloy main joist 10, hole is taken on building floor 1 along aluminium alloy main joist 10, will be consolidated with two setscrews 2 Determine part 3 to be mounted on building floor 1, mariages sunpender 5 is hung on fixing piece 3 under double nut 4, is surveyed using five line laser levels If the height of each group mariages sunpender 5, extra sunpender is cut off using electric angle grinder and is flushed, and its underpart is used by rectangular regulating part 8 Double nut 4 connects;
Step 2 penetrates the bolt head of fastening bolt 9 in the T-slot of aluminium alloy main joist 10, and is mounted on rectangular tune It saves on part 8, then 11 sequence of clean board is mounted between two adjacent aluminium alloy main joists 10, with aluminum corner brace 12 and self-tapping screw 13 is fixed;
Step 3 adjusts the levelness of furred ceiling by the double nut 4 at the rectangular regulating part 8 in 5 lower end of mariages sunpender, then will The opening U-lag of connector 6 is mounted among mariages sunpender 5, fixed with double nut 4, is drawn using girt 7 by connector 6 Adjacent mariages sunpender 5 is tied, it is whole to form space.
In step 3, adjacent mariages sunpender 5 is apart from 11 furred ceiling surface layer height of clean board within 1.5m.
It should be noted that, in this document, the terms "include", "comprise" or its any other variant are intended to non-row His property includes, so that the process, method, article or equipment for including a series of elements not only includes those elements, and And further include other elements that are not explicitly listed, or further include for this process, method, article or equipment institute it is intrinsic Element.In the absence of more restrictions, the element limited by sentence "including a ...", it is not excluded that including institute State in the process, method, article or equipment of element that there is also other identical elements.
The above is made skilled artisans appreciate that or realizing this hair in specific embodiment party of the invention It is bright.Various modifications to these embodiments will be apparent to one skilled in the art, as defined herein General Principle can be realized in other embodiments without departing from the spirit or scope of the present invention.Therefore, of the invention It is not intended to be limited to the embodiments shown herein, and is to fit to and the principles and novel features disclosed herein phase one The widest scope of cause.

Claims (7)

1. people's furred ceiling in a kind of toilet, including building floor (1) and clean board (11), which is characterized in that the building floor (1) rear surface is fixedly connected with setscrew (2), and the lower end of the setscrew (2) is fixedly connected with fixing piece (3), Fixing piece (3) the upper and lower extremities back offers bolt hole, is connected with mariages in the bolt hole of fixing piece (3) the lower limb back and hangs Bar (5);The upper and lower ends of the mariages sunpender (5) and middle part are threaded with nut (4), and the mariages sunpender (5) Upper end is fixedly connected by nut (4) with fixing piece (3), and the middle part of the mariages sunpender (5) is fixedly connected with by nut (4) The lower end of connector (6), the mariages sunpender (5) is fixedly connected with rectangular regulating part (8) by nut (4);The connector (6) junction of web and mariages sunpender (5) offers opening U-type groove, opens up at two side wing edges of the connector (6) There is bolt hole, and be respectively connected with girt (7) in the bolt hole of (6) two side wing edge of the connector, level described in two sides is drawn The junction of bar (7) and connector (6) is threaded with nut (4), girt (7) described in two sides by nut (4) with Connector (6) is fixedly connected;The upper and lower ends of the rectangular regulating part (8) open up the rectangular adjusting there are two bolt hole It is connected with fastening bolt (9) in the bolt hole of part (8) lower end, it is described to be fixedly connected by rectangular regulating part (8) fastening bolt (9) Have aluminium alloy main joist (10), the two sidewalls lower end of described aluminium alloy main joist (10) is fixedly connected to aluminum corner brace (12), institute It states aluminum corner brace (12) both wings to be equipped with self-tapping screw (13), the aluminum corner brace (12) is fixed by clean board (11) by self-tapping screw (13) It is connected at the lower end both wings of aluminium alloy main joist (10).
2. people's furred ceiling in a kind of toilet according to claim 1, which is characterized in that the aluminium alloy main joist (10) with The junction of fastening bolt (9) offers T-slot.
3. people's furred ceiling in a kind of toilet according to claim 1, which is characterized in that be filled in the clean board (11) The fire proofings such as rock wool.
4. people's furred ceiling in a kind of toilet according to claim 1, which is characterized in that the mariages sunpender (5) is two The zinc-plated sunpender of full wire, the girt (7) are the zinc-plated sunpender of single full wire.
5. people's furred ceiling in a kind of toilet according to claim 1, which is characterized in that the fixing piece (3) is by galvanizing bath Steel is made, and the connector (6) has zinc-plated C-type steel to be made, and the rectangular regulating part (8) is made of galvanized steel plain sheet, and the aluminium closes Golden main joist (10) is the hanging beam with T-slot, and the clean board (11) is two-sided color coated steel sheet.
6. according to claim 1 to the construction method of people's furred ceiling in a kind of toilet described in 5 any one, which is characterized in that The following steps are included:
In toilet before people's ceiling construction, the horizontal line and aluminium for setting toilet's furred ceiling are surveyed using five line laser levels for step 1 The position of alloy main joist (10) takes hole on building floor (1) along aluminium alloy main joist (10), with two setscrews (2) Fixing piece (3) is mounted on building floor (1), mariages sunpender (5) is hung on fixing piece (3) under double nut (4), using five Line laser level surveys the height for setting each group mariages sunpender (5), and extra sunpender is cut off using electric angle grinder and flushed, and its underpart is logical Rectangular regulating part (8) are crossed to be connected with double nut (4);
The bolt head of fastening bolt (9) is penetrated in the T-slot of aluminium alloy main joist (10), and is mounted on rectangular tune by step 2 Save on part (8), then clean board (11) be sequentially mounted between two adjacent aluminium alloy main joists (10), with aluminum corner brace (12) and Self-tapping screw (13) is fixed;
Step 3 adjusts the levelness of furred ceiling by the double nut (4) at the rectangular regulating part in mariages sunpender (5) lower end (8), then Connector (6) opening U-lag is mounted among mariages sunpender (5), it is fixed with double nut (4), passed through using girt (7) It is whole to form space for the adjacent mariages sunpender (5) of connector (6) drawknot.
7. the construction method of people's furred ceiling in a kind of toilet according to claim 6, which is characterized in that in step 3, The adjacent mariages sunpender (5) is apart from clean board (11) furred ceiling surface layer height within 1.5m.
CN201810769912.3A 2018-07-13 2018-07-13 People's furred ceiling and construction method in a kind of toilet Pending CN109025028A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810769912.3A CN109025028A (en) 2018-07-13 2018-07-13 People's furred ceiling and construction method in a kind of toilet

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810769912.3A CN109025028A (en) 2018-07-13 2018-07-13 People's furred ceiling and construction method in a kind of toilet

Publications (1)

Publication Number Publication Date
CN109025028A true CN109025028A (en) 2018-12-18

Family

ID=64642508

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810769912.3A Pending CN109025028A (en) 2018-07-13 2018-07-13 People's furred ceiling and construction method in a kind of toilet

Country Status (1)

Country Link
CN (1) CN109025028A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN110130605A (en) * 2019-06-04 2019-08-16 上海建工一建集团有限公司 A kind of the edge sealing fixing component and application method of ceiling decoration glass
CN110173068A (en) * 2019-06-04 2019-08-27 上海建工一建集团有限公司 A kind of Lift-on/Lift-off System and construction method of ceiling decoration glass
CN111441526A (en) * 2019-01-17 2020-07-24 柏诚工程股份有限公司 Method for installing upper fixed node of clean ceiling of electronic factory building
CN111456313A (en) * 2020-03-25 2020-07-28 中国五冶集团有限公司 Method for quickly installing color steel ceiling plate in purification area
CN117306769A (en) * 2023-11-12 2023-12-29 江苏省华建建设股份有限公司 Steel plate suspended ceiling method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200961312Y (en) * 2006-10-16 2007-10-17 张永新 Vermiculite fire-proof color-steel ceiling and partition board
CN201751478U (en) * 2009-12-07 2011-02-23 中国电子系统工程第二建设有限公司 Modified installation structure for suspended ceiling of sandwiched color steel composite board
CN105672546A (en) * 2016-01-21 2016-06-15 苏州凯奥净化科技有限公司 Ceiling for clean room
WO2017144046A1 (en) * 2016-02-24 2017-08-31 Wilhelm Layher Verwaltungs-Gmbh Supporting device of metal for suspending a hanging scaffold or another hanging structure
CN207453242U (en) * 2017-11-06 2018-06-05 谢莹 A kind of clean operating room subsiding crack constructing structure

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN200961312Y (en) * 2006-10-16 2007-10-17 张永新 Vermiculite fire-proof color-steel ceiling and partition board
CN201751478U (en) * 2009-12-07 2011-02-23 中国电子系统工程第二建设有限公司 Modified installation structure for suspended ceiling of sandwiched color steel composite board
CN105672546A (en) * 2016-01-21 2016-06-15 苏州凯奥净化科技有限公司 Ceiling for clean room
WO2017144046A1 (en) * 2016-02-24 2017-08-31 Wilhelm Layher Verwaltungs-Gmbh Supporting device of metal for suspending a hanging scaffold or another hanging structure
CN207453242U (en) * 2017-11-06 2018-06-05 谢莹 A kind of clean operating room subsiding crack constructing structure

Cited By (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111441526A (en) * 2019-01-17 2020-07-24 柏诚工程股份有限公司 Method for installing upper fixed node of clean ceiling of electronic factory building
CN110130605A (en) * 2019-06-04 2019-08-16 上海建工一建集团有限公司 A kind of the edge sealing fixing component and application method of ceiling decoration glass
CN110173068A (en) * 2019-06-04 2019-08-27 上海建工一建集团有限公司 A kind of Lift-on/Lift-off System and construction method of ceiling decoration glass
CN110173068B (en) * 2019-06-04 2024-05-28 上海建工一建集团有限公司 Hoisting system and construction method for ceiling decorative glass
CN110130605B (en) * 2019-06-04 2024-05-28 上海建工一建集团有限公司 Edge sealing fixing member for ceiling decorative glass and use method
CN111456313A (en) * 2020-03-25 2020-07-28 中国五冶集团有限公司 Method for quickly installing color steel ceiling plate in purification area
CN117306769A (en) * 2023-11-12 2023-12-29 江苏省华建建设股份有限公司 Steel plate suspended ceiling method

Similar Documents

Publication Publication Date Title
CN109025028A (en) People's furred ceiling and construction method in a kind of toilet
US9938733B2 (en) Wire rope tension grid improvements
CN108868139A (en) A kind of method of furred ceiling
CN215442646U (en) High-space long-span steel frame conversion layer mounting structure
CN205777020U (en) A kind of large span space furred ceiling reversely and changes support means
CN207405853U (en) Kitchen and toilet ceiling structure
CN211200882U (en) Steel construction conversion layer furred ceiling
CN207892092U (en) A kind of curtain wall support structure
CN215484010U (en) Aluminum square tube assembled design mounting structure who subsides of preapring for an unfavorable turn of events shape
CN212670973U (en) Building light steel grid suspended ceiling
CN214169619U (en) Reverse installation aluminum honeycomb panel furred ceiling system
CN114412046A (en) Anti-deformation anti-falling assembled buckle suspended ceiling
CN217299430U (en) Furred ceiling structure of C shaped steel conversion
CN219992857U (en) Assembled furred ceiling structure
CN219654049U (en) Hoisting device for ceiling access opening at narrow part
CN219118530U (en) Assembled light indoor ceiling structure
CN217400071U (en) Gypsum board plane furred ceiling mounting structure
CN214500286U (en) Suspension rack for multilayer pipeline
CN220599114U (en) Multilayer bearing structure is encorbelmented outward in high altitude
CN211421559U (en) Suspended ceiling structure
CN220318927U (en) Integrated furred ceiling antidetonation construction structures
CN212248860U (en) Mineral wool board convenient to dismantle
CN103225390A (en) Hollow facade pulley guide attached-type lifting scaffold
CN213572596U (en) Steel structure suspended ceiling
CN210316246U (en) Ancient building roof heat preservation back up coat

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20181218