CN111441251A - Construction method for folding steel box girder striding over existing steel girder - Google Patents

Construction method for folding steel box girder striding over existing steel girder Download PDF

Info

Publication number
CN111441251A
CN111441251A CN202010258170.5A CN202010258170A CN111441251A CN 111441251 A CN111441251 A CN 111441251A CN 202010258170 A CN202010258170 A CN 202010258170A CN 111441251 A CN111441251 A CN 111441251A
Authority
CN
China
Prior art keywords
steel box
box girder
closure section
section steel
girder
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010258170.5A
Other languages
Chinese (zh)
Inventor
李江
王晓敏
孙凤祥
叶绍其
吕新阳
李磊
刘静
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
5th Engineering Co Ltd of MBEC
Original Assignee
5th Engineering Co Ltd of MBEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 5th Engineering Co Ltd of MBEC filed Critical 5th Engineering Co Ltd of MBEC
Priority to CN202010258170.5A priority Critical patent/CN111441251A/en
Publication of CN111441251A publication Critical patent/CN111441251A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D2/00Bridges characterised by the cross-section of their bearing spanning structure
    • E01D2/04Bridges characterised by the cross-section of their bearing spanning structure of the box-girder type

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction method of a closure section steel box girder striding over an existing bridge, which is characterized in that a pad seat and a vertical jack are installed on the top surface of a cantilever end of the side span steel box girder striding over two sides of the existing bridge, a lifting lug and a counter-force seat are welded on the top surface of two sides of the closure section steel box girder, and the closure section steel box girder is lifted to the pad seat by using lifting equipment until the vertical jack props up a lifting frame; a longitudinal jack is arranged by utilizing a counter-force seat welded on the steel box girder at the closure section in advance to support the cushion seat; and lifting the lifting frame by a vertical jack on one side of the side span steel box girder to adjust the vertical displacement of the closure section steel box girder, pushing a cushion seat by a longitudinal jack to adjust the longitudinal displacement, and adjusting the closure section steel box girder until the adjustment is finished. And welding the closure section steel box girder and the side span steel box girder of the adjacent section, completing system conversion, and finally dismantling the vertical jack, the longitudinal jack, the hanging bracket, the counter-force seat and the cushion seat. The invention has the advantages that: the construction auxiliary device has a simple structure and high positioning precision, and effectively accelerates the construction progress.

Description

Construction method for folding steel box girder striding over existing steel girder
Technical Field
The invention relates to the field of municipal bridge construction, in particular to a construction method of a closure section steel box girder striding over an existing bridge.
Background
With the continuous development of municipal bridge construction technology, in order to reduce the congestion of the existing municipal traffic to the maximum extent, the construction of municipal elevated frames becomes the inevitable choice for the development of the urban traffic. When the viaduct is designed, the viaduct inevitably intersects with the existing bridge, and when the steel box girder striding the existing bridge is installed, how to install the steel box girder quickly avoids influencing the traffic and the structure safety of the existing bridge, which is a difficult problem in construction. The conventional construction method mostly adopts a support method to carry out the installation and construction of the steel box girder, and has the defects that a support needs to be erected on the existing bridge, the structural safety and the traffic of the existing bridge are influenced, and the construction is not facilitated.
Disclosure of Invention
The invention aims to provide a construction method of a closure section steel box girder striding over an existing bridge, which has the advantages of simple structure, convenience in operation, high positioning precision and capability of effectively accelerating the construction progress.
The object of the invention is achieved in that:
a construction method of a closure section steel box girder of an existing overpass is characterized by comprising the following steps: the method comprises the following specific steps:
A. firstly, constructing the side-span steel box girders of each section in the two side areas of the existing viaduct girder by using a support method, and connecting the side-span steel box girders into a whole by welding so that the side-span steel box girders of two adjacent piers of the existing viaduct girder are suspended above the existing viaduct girder;
b: installing a cushion seat and a vertical jack on the top surface of the cantilever end of the side span steel box girder on two sides of the existing viaduct girder;
c: welding lifting lugs and counter-force seats on the top surfaces of two sides of the middle closure section steel box girder, mounting a lifting frame on the lifting lugs, hanging the lifting lugs on the top surfaces of two sides of the closure section steel box girder by using a hoisting device to hoist the closure section steel box girder to a pad seat, and hooking after the closure section steel box girder is aligned with the bridge axis of the side span steel box girder until a vertical jack jacks the lifting frame;
d: a longitudinal jack is arranged at the counter-force seat on the steel box girder at the closure section to support the cushion seat;
e: lifting a hanging bracket by a vertical jack on one side of the existing viaduct beam to adjust the vertical displacement of the closure section steel box beam, adjusting the longitudinal displacement of the closure section steel box beam by a longitudinal jack pushing seat, adjusting the closure section steel box beam, temporarily fixing one side of the closure section steel box beam and the side span steel box beam of the adjacent section after the adjustment is in place, and adjusting the other side of the closure section steel box beam until the adjustment is finished;
f: and welding the closure section steel box girder and the side span steel box girder of the adjacent section to complete system conversion, and finally removing the vertical jack, the longitudinal jack, the hanging bracket, the counter-force seat and the cushion seat to complete construction of the closure section steel box girder.
When the steel box girder construction spanning the existing viaduct is carried out, the side-span steel box girders of each section in the two side areas of the existing viaduct are constructed by utilizing a support method, the side-span steel box girders are connected into a whole by welding, and only the steel box girders of the closure section are left; installing a pad seat and a vertical jack on the top surface of the cantilever end of the side span steel box girder which spans two sides of the existing bridge, welding a lifting lug and a counter-force seat on the top surface of two sides of the closure section steel box girder, installing a hanging bracket, hoisting the closure section steel box girder to the pad seat by using hoisting equipment, and hooking after the closure section steel box girder is aligned with the bridge axis of the side span steel box girder until the vertical jack jacks the hanging bracket; a longitudinal jack is arranged by utilizing a counter-force seat welded on the steel box girder at the closure section in advance to support the cushion seat; and lifting the lifting frame by a vertical jack on one side of the side-span steel box girder to adjust the vertical displacement of the closure section steel box girder, pushing the cushion seat by a longitudinal jack to adjust the longitudinal displacement, adjusting the closure section steel box girder, temporarily fixing one side of the closure section steel box girder and the side-span steel box girder of the adjacent side-span steel box girder after the adjustment is in place, and adjusting the other side of the closure section steel box girder until the adjustment is finished. And welding the closure section steel box girder and the side span steel box girder of the adjacent section to complete system conversion, and finally removing the vertical jack, the longitudinal jack, the hanging bracket, the counter-force seat and the cushion seat to complete construction of the closure section steel box girder.
The invention fully considers traffic jam of municipal works, quickly finishes the adjustment of the closure section steel box girder by arranging the hanging bracket and the fine adjustment device consisting of the longitudinal jack and the vertical jack on the side span steel box girder, ensures the installation quality of the closure section steel box girder and solves the problem that the existing elevated bridge cannot be provided with the bracket. The invention has the advantages that: the construction auxiliary device is simple in structure, convenient to operate, high in positioning accuracy and capable of effectively accelerating construction progress.
Drawings
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a right side view of FIG. 1;
reference numerals: 1-existing elevated bridge, 2-bridge pier, 3-side span steel box girder, 4-closure section steel box girder, 5-pad seat, 6-vertical jack, 7-lifting lug, 8-hanging bracket, 9-counterforce seat, 10-longitudinal jack, and 11-hoisting equipment.
Detailed Description
The present invention will be described in further detail with reference to the following examples and drawings.
A construction method of a closure section steel box girder of an existing overpass comprises the following specific steps:
A. firstly, constructing the side-span steel box girders 3 of each section in the two side areas of the existing elevated bridge 1 by using a support method, and connecting the side-span steel box girders 3 into a whole by welding, so that the side-span steel box girders 3 of the two adjacent piers 2 of the existing elevated bridge 1 are cantilevered above the existing elevated bridge 1;
b: installing a cushion 5 and a vertical jack 6 on the top surface of the cantilever end of the side span steel box girder 3 which spans two sides of the existing viaduct girder 1;
c: welding lifting lugs 7 and counter-force seats 9 on the top surfaces of two sides of the middle closure section steel box girder 4, mounting a lifting frame 8 on the lifting lugs 7, hanging the closure section steel box girder 4 to a pad seat 5 by using a hoisting device 11 to hang the lifting lugs 7 on the top surfaces of two sides of the closure section steel box girder 4, and hooking after the closure section steel box girder 4 is aligned with the bridge axis of the side span steel box girder 3 until a vertical jack 6 props against the lifting frame 8;
d: a longitudinal jack 10 is arranged at a counter-force seat 9 on the closure section steel box girder 4 and props against the pad seat 5;
e: lifting a hanger 11 by a vertical jack 6 at one side of the existing elevated bridge 1 to adjust the vertical displacement of a closure section steel box girder 4, lifting a cushion seat 5 by a longitudinal jack 10 to adjust the longitudinal displacement of the closure section steel box girder 4, adjusting the closure section steel box girder 4, temporarily fixing one side of the closure section steel box girder 4 and an adjacent section side span steel box girder 3 after the adjustment is in place, and adjusting the other side of the closure section steel box girder 4 until the adjustment is finished;
f: and welding the closure section steel box girder 4 and the side span steel box girder 3 of the adjacent section to complete system conversion, and finally removing the vertical jack 6, the longitudinal jack 10, the hanger 8, the counter-force seat 9 and the cushion seat 5 to complete construction of the closure section steel box girder 4.
In the steps B-E, the closure section steel box 4 beam is adjusted through the vertical jack 6 and the longitudinal jack 10, the precision of the large-scale steel box beam during fine adjustment can be well guaranteed, and meanwhile, the operation is convenient and fast, and the safety risk is low.

Claims (1)

1. A construction method of a closure section steel box girder of an existing overpass is characterized by comprising the following steps: the method comprises the following specific steps:
A. firstly, constructing the side-span steel box girders of each section in the two side areas of the existing viaduct girder by using a support method, and connecting the side-span steel box girders into a whole by welding so that the side-span steel box girders of two adjacent piers of the existing viaduct girder are suspended above the existing viaduct girder;
b: installing a cushion seat and a vertical jack on the top surface of the cantilever end of the side span steel box girder on two sides of the existing viaduct girder;
c: welding lifting lugs and counter-force seats on the top surfaces of two sides of the middle closure section steel box girder, mounting a lifting frame on the lifting lugs, hanging the lifting lugs on the top surfaces of two sides of the closure section steel box girder by using a hoisting device to hoist the closure section steel box girder to a pad seat, and hooking after the closure section steel box girder is aligned with the bridge axis of the side span steel box girder until a vertical jack jacks the lifting frame;
d: a longitudinal jack is arranged at the counter-force seat on the steel box girder at the closure section to support the cushion seat;
e: lifting a hanging bracket by a vertical jack on one side of the existing viaduct beam to adjust the vertical displacement of the closure section steel box beam, adjusting the longitudinal displacement of the closure section steel box beam by a longitudinal jack pushing seat, adjusting the closure section steel box beam, temporarily fixing one side of the closure section steel box beam and the side span steel box beam of the adjacent section after the adjustment is in place, and adjusting the other side of the closure section steel box beam until the adjustment is finished;
f: and welding the closure section steel box girder and the side span steel box girder of the adjacent section to complete system conversion, and finally removing the vertical jack, the longitudinal jack, the hanging bracket, the counter-force seat and the cushion seat to complete construction of the closure section steel box girder.
CN202010258170.5A 2020-04-03 2020-04-03 Construction method for folding steel box girder striding over existing steel girder Pending CN111441251A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010258170.5A CN111441251A (en) 2020-04-03 2020-04-03 Construction method for folding steel box girder striding over existing steel girder

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010258170.5A CN111441251A (en) 2020-04-03 2020-04-03 Construction method for folding steel box girder striding over existing steel girder

Publications (1)

Publication Number Publication Date
CN111441251A true CN111441251A (en) 2020-07-24

Family

ID=71652782

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010258170.5A Pending CN111441251A (en) 2020-04-03 2020-04-03 Construction method for folding steel box girder striding over existing steel girder

Country Status (1)

Country Link
CN (1) CN111441251A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112726412A (en) * 2020-12-28 2021-04-30 山东大学 Precise three-dimensional positioning device and method for steel box girder hoisting closure
CN113944103A (en) * 2021-10-22 2022-01-18 中交路桥建设有限公司 Assembled support device applied to installation of steel box girder road-crossing bridge and construction method

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060200920A1 (en) * 2005-03-11 2006-09-14 Sang-Hyo Kim Method of constructing partially earth-anchored cable-stayed bridge using thermal prestressing technique
CN202414957U (en) * 2011-12-27 2012-09-05 广东省长大公路工程有限公司 Soft connecting device suitable for rapidly hoisting water large-sized members
CN202466414U (en) * 2011-12-27 2012-10-03 中交第二航务工程局有限公司 Large-segment steel box girder matching bracket structure
CN106087747A (en) * 2016-06-17 2016-11-09 柳州黔桥工程材料有限公司 Stride incremental launching construction method for correcting error
CN206143637U (en) * 2016-10-14 2017-05-03 中交一公局第五工程有限公司 Steel longeron moves adjusting device with great ease
CN108547223A (en) * 2018-03-12 2018-09-18 中交第二航务工程局有限公司 The hybrid beam bridge construction method of steel reinforced concrete overlapping
JP2019138123A (en) * 2018-02-15 2019-08-22 株式会社富士ピー・エス Movable work vehicle with retractable roof
CN110182682A (en) * 2019-06-03 2019-08-30 中铁大桥局集团有限公司 A kind of suspender for the lifting of big segment steel truss girder
CN110820579A (en) * 2019-11-15 2020-02-21 广州市市政集团有限公司 Construction method based on movable steel box girder road-crossing construction working platform

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060200920A1 (en) * 2005-03-11 2006-09-14 Sang-Hyo Kim Method of constructing partially earth-anchored cable-stayed bridge using thermal prestressing technique
CN202414957U (en) * 2011-12-27 2012-09-05 广东省长大公路工程有限公司 Soft connecting device suitable for rapidly hoisting water large-sized members
CN202466414U (en) * 2011-12-27 2012-10-03 中交第二航务工程局有限公司 Large-segment steel box girder matching bracket structure
CN106087747A (en) * 2016-06-17 2016-11-09 柳州黔桥工程材料有限公司 Stride incremental launching construction method for correcting error
CN206143637U (en) * 2016-10-14 2017-05-03 中交一公局第五工程有限公司 Steel longeron moves adjusting device with great ease
JP2019138123A (en) * 2018-02-15 2019-08-22 株式会社富士ピー・エス Movable work vehicle with retractable roof
CN108547223A (en) * 2018-03-12 2018-09-18 中交第二航务工程局有限公司 The hybrid beam bridge construction method of steel reinforced concrete overlapping
CN110182682A (en) * 2019-06-03 2019-08-30 中铁大桥局集团有限公司 A kind of suspender for the lifting of big segment steel truss girder
CN110820579A (en) * 2019-11-15 2020-02-21 广州市市政集团有限公司 Construction method based on movable steel box girder road-crossing construction working platform

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
万成钢: "城市市政桥梁多层跨线互通立交施工技术", 《城市建设理论研究(电子版)》 *
孙婷: "BIM虚拟建造技术在既有城市公路立交枢纽更新改建施工中的应用", 《建筑施工》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112726412A (en) * 2020-12-28 2021-04-30 山东大学 Precise three-dimensional positioning device and method for steel box girder hoisting closure
CN113944103A (en) * 2021-10-22 2022-01-18 中交路桥建设有限公司 Assembled support device applied to installation of steel box girder road-crossing bridge and construction method

Similar Documents

Publication Publication Date Title
CN110042769B (en) Auxiliary span full-cantilever assembling construction method for composite beam cable-stayed bridge
CN111441251A (en) Construction method for folding steel box girder striding over existing steel girder
CN102330414A (en) Hanging basket cantilever method construction method of large-span continuous rigid beam sidespan cast-in-place beam section
CN110644371A (en) Prefabricated capping beam installation method and system
CN102134832B (en) Movable support and movable support assisted method for erecting steel box beams through non-variable amplitude frame beam crane
CN112227232A (en) Pier upright post underpinning method of pier-beam consolidation continuous beam bridge
CN213328682U (en) Mounting structure suitable for heavy scattered cable saddle
CN211472207U (en) Suspension beam system for hoisting prefabricated section box girder
CN111962402A (en) Lateral sliding installation method for steel box girder
CN100497834C (en) Construction equipment for integral roof-holding highway bridge top structure
CN111005324B (en) Support-free suspension and locking construction method for assembled type segmental box girder
CN113073555B (en) Pier top block positioning system and construction method thereof
KR101028869B1 (en) Temporary structure apparatus precast end segment for bridge
CN112323647B (en) Rigid frame bridge hanging basket suspension casting system and construction method thereof
KR100487574B1 (en) Method and apparatus for lifting upper structure using girder type bracket supported by steel stranded wires and saddles
CN209923780U (en) Suspended support of segment prefabricated bent cap
CN210013135U (en) Cast-in-place bent cap combined type formwork system of encorbelmenting
CN209276999U (en) A kind of urban viaduct cantilever is set a roof beam in place support system
CN220166687U (en) Cast-in-situ construction arch frame for upper beam of cable tower
CN219637723U (en) Municipal administration overpass quick construction system
CN216405153U (en) Attached type cast-in-place concrete overline bridge column type support dismantling device
KR200283142Y1 (en) Apparatus for lifting upper structure using girder type bracket supported by steel stranded wires and saddles
CN217629466U (en) Corrugated steel web plate lifting system for bridge
CN214993124U (en) Lifting mechanism of through tied arch bridge
CN220638385U (en) Movable tensioning device suitable for precast T beam edge and midspan hogging moment

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200724