CN111424697A - Construction method for prefabricating deep and large open caisson by slicing - Google Patents

Construction method for prefabricating deep and large open caisson by slicing Download PDF

Info

Publication number
CN111424697A
CN111424697A CN202010309113.5A CN202010309113A CN111424697A CN 111424697 A CN111424697 A CN 111424697A CN 202010309113 A CN202010309113 A CN 202010309113A CN 111424697 A CN111424697 A CN 111424697A
Authority
CN
China
Prior art keywords
arc
open caisson
shaped
anchor rod
pipe pieces
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Withdrawn
Application number
CN202010309113.5A
Other languages
Chinese (zh)
Inventor
左回刚
张久昌
周洪光
户少勇
罗佳宁
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Civil Engineering Co Ltd of CREC
Sixth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Original Assignee
Shanghai Civil Engineering Co Ltd of CREC
Sixth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Civil Engineering Co Ltd of CREC, Sixth Engineering Co Ltd of Shanghai Civil Engineering Co Ltd of CREC filed Critical Shanghai Civil Engineering Co Ltd of CREC
Priority to CN202010309113.5A priority Critical patent/CN111424697A/en
Publication of CN111424697A publication Critical patent/CN111424697A/en
Withdrawn legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D23/00Caissons; Construction or placing of caissons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D17/00Excavations; Bordering of excavations; Making embankments
    • E02D17/02Foundation pits
    • E02D17/04Bordering surfacing or stiffening the sides of foundation pits
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D19/00Keeping dry foundation sites or other areas in the ground
    • E02D19/06Restraining of underground water
    • E02D19/12Restraining of underground water by damming or interrupting the passage of underground water
    • E02D19/18Restraining of underground water by damming or interrupting the passage of underground water by making use of sealing aprons, e.g. diaphragms made from bituminous or clay material
    • E02D19/185Joints between sheets constituting the sealing aprons
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/74Means for anchoring structural elements or bulkheads
    • E02D5/76Anchorings for bulkheads or sections thereof in as much as specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2200/00Geometrical or physical properties
    • E02D2200/16Shapes
    • E02D2200/1607Shapes round, e.g. circle
    • E02D2200/1621Shapes round, e.g. circle made from multiple elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0004Synthetics
    • E02D2300/0018Cement used as binder
    • E02D2300/002Concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/20Miscellaneous comprising details of connection between elements
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2600/00Miscellaneous
    • E02D2600/30Miscellaneous comprising anchoring details

Landscapes

  • Engineering & Computer Science (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • Structural Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Hydrology & Water Resources (AREA)
  • Foundations (AREA)

Abstract

The invention belongs to municipal water supply and drainage engineering construction, and relates to a construction method for prefabricating a deep and large open caisson by segments, which comprises the following steps: (1) uniformly decomposing the open caisson into a plurality of arc sections in the horizontal direction, decomposing the open caisson into a rectangular block design in the vertical direction, and pouring concrete to form an arc-shaped duct piece; (2) arc bolt holes are reserved at the upper end, the lower end, the left side wall and the right side wall of the arc tube sheet respectively; (3) an anchor rod hole is formed in the middle of the arc-shaped duct piece; (4) arc splicing is carried out in the foundation pit in the horizontal direction through a plurality of arc-shaped pipe pieces, then the arc-shaped pipe pieces are spliced layer by layer from bottom to top, water stop strips are arranged at seams, and the arc-shaped pipe pieces are connected with each other through arc-shaped bolts to form an open caisson; (5) the arc-shaped duct piece is fixed on the wall of the foundation pit by the anchor rod penetrating through the anchor rod hole. The invention is suitable for manufacturing the open caisson in a gravel area with limited construction clearance, large underground water consumption, soft geology and reduced construction cost and improved construction quality.

Description

Construction method for prefabricating deep and large open caisson by slicing
Technical Field
The invention belongs to municipal water supply and drainage engineering construction, and relates to a construction method for prefabricating a deep and large open caisson in a segmented manner.
Background
Along with the need of urban development and the maturity of pipe jacking technology, pipe jacking construction is increasing day by day, and open caisson construction is adopted for a working well and a receiving well more commonly. The existing water supply and drainage open caisson structure adopts a template to cast a concrete structure in situ, and is poured step by step in a ring mode, the locking phenomenon is easy to occur when the conventional open caisson is adopted for construction, the drainage and collapse quantity is large, the construction period is difficult to control, and the construction cost is high.
Disclosure of Invention
In order to solve the technical problem, the invention provides a construction method for prefabricating a deep and large open caisson in a slicing manner, which can realize the rapid forming of the open caisson.
The specific technical scheme is as follows: a construction method for prefabricating a deep and large open caisson by segments comprises the following steps: (1) uniformly decomposing the wall of the open caisson into a plurality of arc sections around the round shape of the open caisson in the horizontal direction, decomposing the wall of the open caisson into a rectangular block design in the vertical direction, and pouring concrete to form an arc-shaped duct piece; (2) arc bolt holes are reserved at the upper end, the lower end, the left side wall and the right side wall of each arc pipe piece respectively, and the bolt holes on two adjacent arc pipe pieces can be communicated; (3) an anchor rod hole is formed in the middle of the arc-shaped duct piece; (4) arc splicing is carried out in the foundation pit in the horizontal direction through a plurality of arc-shaped pipe pieces, then the arc-shaped pipe pieces are spliced layer by layer from bottom to top, water stop strips are arranged at seams, and the arc-shaped pipe pieces are connected with each other through arc-shaped bolts to form an open caisson; (5) the arc-shaped duct piece is fixed on the wall of the foundation pit by the anchor rod penetrating through the anchor rod hole.
Has the advantages that: by adopting the device, the construction process of the prior open caisson operation is changed from cast-in-place to prefabricated structure construction by casting and then sinking, the device is particularly suitable for manufacturing the open caisson in a gravel area with limited construction clearance, large underground water consumption and soft geology, and reduces the construction cost and improves the construction quality.
Drawings
FIG. 1 is a top view of an open caisson formed by arcuate segments in accordance with the present invention;
FIG. 2 is an enlarged view of a portion A of FIG. 1;
FIG. 3 is a plan view of a segment of a curved duct of the present invention;
FIG. 4 is an elevational view of a segment of the present invention;
wherein, 1, an arc-shaped duct piece; 2, arranging bolt holes; 3, arranging a bolt hole; 4 side bolt holes; 5, anchoring the bolt; 6, lining the open caisson two; 7 water stop strip.
Detailed Description
The segmented prefabrication structure of the deep and large open caisson shown in the figures 1-4 comprises a plurality of arc-shaped pipe pieces 1 which are rectangular and uniform, wherein after the arc-shaped pipe pieces 1 are mutually connected, a circular ring can be formed on a horizontal surface in a surrounding manner, and the open caisson is formed in the vertical direction; arc bolt holes are reserved at the upper end, the lower end, the left side wall and the right side wall of each arc-shaped duct piece 1 respectively, and two adjacent bolt holes can be connected in a through mode; two adjacent arc-shaped pipe pieces 1 are connected through an arc-shaped bolt; an anchor rod hole is formed in the front surface of the arc-shaped duct piece 1, an anchor rod 5 is arranged on the anchor rod hole, and the arc-shaped duct piece 1 is fixed on the pit wall of the foundation pit through the anchor rod 5; the arc-shaped duct piece is of a concrete structure.
And furthermore, 7 water stopping strips are arranged between every two adjacent arc-shaped pipe pieces and used for stopping water.
The construction method comprises the following steps: (1) uniformly decomposing the wall of the open caisson into a plurality of arc sections around the round shape of the open caisson in the horizontal direction, decomposing the wall of the open caisson into a rectangular block design in the vertical direction, and pouring concrete to form an arc-shaped duct piece 1; (2) arc bolt holes are reserved at the upper end, the lower end, the left side wall and the right side wall of each arc-shaped duct piece 1 respectively, and the bolt holes on two adjacent arc-shaped duct pieces 1 can be communicated; (3) an anchor rod hole is arranged in the middle of the arc-shaped duct piece 1; (4) arc splicing is carried out in the foundation pit in the horizontal direction through a plurality of arc-shaped pipe pieces, then the arc-shaped pipe pieces are spliced layer by layer from bottom to top, a water stop strip 7 is arranged at a joint, and the arc-shaped pipe pieces 1 are connected with each other through arc-shaped bolts to form an open caisson; (5) the arc-shaped duct piece is fixed on the wall of the foundation pit by the anchor rod penetrating through the anchor rod hole.
The working principle is as follows:
horizontal direction evenly decomposes into a plurality of segmental arcs around the open caisson is circular to the open caisson wall of a well, vertical direction decomposes into the rectangular block to the open caisson wall of a well, form the prefabricated construction method of dark big open caisson burst, the device appearance rectangle is the arc section of jurisdiction, from top to bottom during the prefabricated arc section of jurisdiction, the arc bolt hole is reserved respectively to both sides, be used for fixed adjacent arc section of jurisdiction 1, adopt arc bolted connection in the middle of the arc section of jurisdiction 1, the centre sets up stagnant water 7 stagnant water, the anchor rod hole is reserved in the setting of arc section of jurisdiction simultaneously, adopt stock 5 to fix the arc section of jurisdiction on the foundation ditch, each arc section of jurisdiction assembles into an open.
Prefabricated arc section of jurisdiction is concrete structure, and prefabricated section of jurisdiction size can be confirmed according to open caisson construction drawing, and the arc bolt hole is reserved from top to bottom to the side for place the arc bolt, it is fixed with bolted connection between the section of jurisdiction, set up sealing rod 7 between the section of jurisdiction and be used for the stagnant water, the section of jurisdiction openly sets up the stock hole, adopts the stock to fix the section of jurisdiction at foundation ditch hole wall.

Claims (1)

1. The construction method for prefabricating the deep and large open caisson by segments is characterized by comprising the following steps of: (1) uniformly decomposing the wall of the open caisson into a plurality of arc sections around the round shape of the open caisson in the horizontal direction, decomposing the wall of the open caisson into a rectangular block design in the vertical direction, and pouring concrete to form an arc-shaped duct piece; (2) arc bolt holes are reserved at the upper end, the lower end, the left side wall and the right side wall of each arc pipe piece respectively, and the bolt holes on two adjacent arc pipe pieces can be communicated; (3) an anchor rod hole is formed in the middle of the arc-shaped duct piece; (4) arc splicing is carried out in the foundation pit in the horizontal direction through a plurality of arc-shaped pipe pieces, then the arc-shaped pipe pieces are spliced layer by layer from bottom to top, water stop strips are arranged at seams, and the arc-shaped pipe pieces are connected with each other through arc-shaped bolts to form an open caisson; (5) the arc-shaped duct piece is fixed on the wall of the foundation pit by the anchor rod penetrating through the anchor rod hole.
CN202010309113.5A 2020-04-19 2020-04-19 Construction method for prefabricating deep and large open caisson by slicing Withdrawn CN111424697A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010309113.5A CN111424697A (en) 2020-04-19 2020-04-19 Construction method for prefabricating deep and large open caisson by slicing

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010309113.5A CN111424697A (en) 2020-04-19 2020-04-19 Construction method for prefabricating deep and large open caisson by slicing

Publications (1)

Publication Number Publication Date
CN111424697A true CN111424697A (en) 2020-07-17

Family

ID=71557094

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010309113.5A Withdrawn CN111424697A (en) 2020-04-19 2020-04-19 Construction method for prefabricating deep and large open caisson by slicing

Country Status (1)

Country Link
CN (1) CN111424697A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021213094A1 (en) * 2020-04-19 2021-10-28 中铁上海工程局集团有限公司 Fragmented prefabricated structure of deep and large open caisson
CN114232665A (en) * 2021-11-29 2022-03-25 中国一冶集团有限公司 Prefabricated assembled open caisson structure and construction method thereof

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204552747U (en) * 2015-04-21 2015-08-12 西安科技大学 A kind of coal mine shaft lining shaft wall structure
CN204551486U (en) * 2015-03-25 2015-08-12 中国建筑西南勘察设计研究院有限公司 Anchor rod type advanced tubule and injection steel bar concrete cylindrical thin wall foundation pit supporting construction
CN106014420A (en) * 2016-05-17 2016-10-12 上海市城市建设设计研究总院 Assembled shaft duct piece structure
CN107893665A (en) * 2017-11-06 2018-04-10 山东建筑大学 A kind of prefabricated assembled composite supporting construction mounting process based on shaped steel
KR20180084411A (en) * 2017-01-17 2018-07-25 이신원 Construction method of lower pier casion footing using PCC structure
CN108360543A (en) * 2018-05-03 2018-08-03 中铁上海工程局集团有限公司 A kind of big pre-cast sink well structure of depth and its installation method
CN109519174A (en) * 2019-01-09 2019-03-26 东北大学 A kind of shaft wall supporting construction
CN109898535A (en) * 2019-01-10 2019-06-18 刘建华 Prefabricated assembled upper pipe working well prestressing force open caisson and assembling method
CN110185053A (en) * 2019-04-22 2019-08-30 温州大学 A kind of construction method of assembled circular open caisson
CN212452715U (en) * 2020-04-19 2021-02-02 中铁上海工程局集团有限公司 Burst prefabricated construction of dark heavy open caisson

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN204551486U (en) * 2015-03-25 2015-08-12 中国建筑西南勘察设计研究院有限公司 Anchor rod type advanced tubule and injection steel bar concrete cylindrical thin wall foundation pit supporting construction
CN204552747U (en) * 2015-04-21 2015-08-12 西安科技大学 A kind of coal mine shaft lining shaft wall structure
CN106014420A (en) * 2016-05-17 2016-10-12 上海市城市建设设计研究总院 Assembled shaft duct piece structure
KR20180084411A (en) * 2017-01-17 2018-07-25 이신원 Construction method of lower pier casion footing using PCC structure
CN107893665A (en) * 2017-11-06 2018-04-10 山东建筑大学 A kind of prefabricated assembled composite supporting construction mounting process based on shaped steel
CN108360543A (en) * 2018-05-03 2018-08-03 中铁上海工程局集团有限公司 A kind of big pre-cast sink well structure of depth and its installation method
CN109519174A (en) * 2019-01-09 2019-03-26 东北大学 A kind of shaft wall supporting construction
CN109898535A (en) * 2019-01-10 2019-06-18 刘建华 Prefabricated assembled upper pipe working well prestressing force open caisson and assembling method
CN110185053A (en) * 2019-04-22 2019-08-30 温州大学 A kind of construction method of assembled circular open caisson
CN212452715U (en) * 2020-04-19 2021-02-02 中铁上海工程局集团有限公司 Burst prefabricated construction of dark heavy open caisson

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2021213094A1 (en) * 2020-04-19 2021-10-28 中铁上海工程局集团有限公司 Fragmented prefabricated structure of deep and large open caisson
CN114232665A (en) * 2021-11-29 2022-03-25 中国一冶集团有限公司 Prefabricated assembled open caisson structure and construction method thereof

Similar Documents

Publication Publication Date Title
CN212452715U (en) Burst prefabricated construction of dark heavy open caisson
CN111424697A (en) Construction method for prefabricating deep and large open caisson by slicing
CN215105880U (en) Concrete inverted well suitable for connecting new and old water supply and drainage pipelines
CN106088758B (en) A kind of bilayer assembled underground granary
CN111733878A (en) Full-prefabricated assembled superposed comprehensive pipe gallery supporting construction structure and process
CN116856932A (en) Large-diameter prestress assembly vertical shaft structure containing glass fiber rib part and construction method
CN111173033A (en) Prefabricated pipe gallery structure and pipe jacking method construction method thereof
CN107401142B (en) Bank revetment heightening construction method is refuted in active service
CN205591210U (en) Formula cast member and construction assembly are spliced to underground
CN108547286A (en) A kind of prefabricated guide groove structure of concrete cut and guide groove installation method
CN109184734B (en) Assembled protective shell lining structure for rectangular underground space and construction method
CN106088762A (en) The prefabricated assembled circular underground granary of a kind of insertion slot type encased steel plate
CN112726784A (en) Fully-prefabricated PC sewer inspection well component assembly type structure and construction method
CN102322065B (en) Bottom channel inner support of foundation pit supporting structure
CN205858358U (en) Prestressing combination formula well tunnel modular structure
CN213926110U (en) River course transformation engineering underground continuous wall of intercepting water and preventing seepage
CN214090251U (en) Modular drainage inspection shaft
CN211898551U (en) Prefabricated pipe gallery structure
CN212388601U (en) Full-prefabricated assembled superposed comprehensive pipe gallery supporting and constructing structure
CN217712488U (en) Be used for quick shut-in well device of trouble no sand pipe well
CN216475060U (en) Occlusive pile structure with reinforcing function
CN213926359U (en) Inspection well structure for rapid construction
CN216788363U (en) Well head block structure of deep tube well
CN219298271U (en) Open cut pipe group structure
CN219364628U (en) Mounting structure is built together with draining inspection shaft to fixed pier

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WW01 Invention patent application withdrawn after publication

Application publication date: 20200717