CN111383127B - Main network operation plan management system and method for power system - Google Patents

Main network operation plan management system and method for power system Download PDF

Info

Publication number
CN111383127B
CN111383127B CN202010154590.9A CN202010154590A CN111383127B CN 111383127 B CN111383127 B CN 111383127B CN 202010154590 A CN202010154590 A CN 202010154590A CN 111383127 B CN111383127 B CN 111383127B
Authority
CN
China
Prior art keywords
plan
operation plan
module
human resource
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010154590.9A
Other languages
Chinese (zh)
Other versions
CN111383127A (en
Inventor
李芳洲
马力
薛博水
陈德凯
孙若峰
刘国建
徐肖庆
李骞
王新
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Yunnan Power Grid Co Ltd
Original Assignee
Yunnan Power Grid Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Yunnan Power Grid Co Ltd filed Critical Yunnan Power Grid Co Ltd
Priority to CN202010154590.9A priority Critical patent/CN111383127B/en
Publication of CN111383127A publication Critical patent/CN111383127A/en
Application granted granted Critical
Publication of CN111383127B publication Critical patent/CN111383127B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06311Scheduling, planning or task assignment for a person or group
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • Theoretical Computer Science (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Health & Medical Sciences (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Data Mining & Analysis (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Game Theory and Decision Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention relates to a system and a method for managing a power system main network operation plan, belonging to the field of management of a power system main network. The system comprises a human resource management module, a power failure operation plan management module and a power failure operation plan management module; the human resource management module is used for inputting the human resource condition in a specified time by matching with the basic team or importing the human resource condition according to a specified template; the power failure operation plan management module is used for filling the power failure operation plan, determining whether the operation plan can be executed or not, checking an initial version plan, inquiring operation plan data to be issued, initiating an operation plan modification application, and performing operation plan modification operation after the operation plan is passed through; the uninterrupted operation plan management module is used for carrying out plan addition, accountability examination, operation plan starting, coordination unit examination, plan modification and formal plan query. The invention can improve the scientific reasonability and the management level of the plan.

Description

Main network operation plan management system and method for power system
Technical Field
The invention relates to a power system main network operation plan management system and a method, and belongs to the technical field of management of power system main networks.
Background
The major network operation plan is an important ring in lean management of the power system, the importance of the major network operation plan in the whole production management process is higher and higher, and the major network operation plan is characterized by comprising the following steps:
the task sources are multiple: various types are involved, including capital construction engineering, technical improvement engineering, major repair engineering, defect elimination, pre-test and the like;
the involved departments are many: the method comprises the steps of birth counting, marketing, capital construction, dispatching stations, power transformation work areas, construction departments and the like;
the constraint conditions are multiple: including warranty power constraints (time warranty power, important and dual power user warranty power), time constraints, manpower constraints, and equipment resource constraints;
uncertain factors: such as weather factors, coordination of the levels, etc.
Meanwhile, with the increasing expansion of the scale of the power grid, the topological structure of the power grid is more and more complex. In the face of complex power grids, in the face of multitasking, multiple departments, multiple constraint conditions and various uncertain factors, the process of making a main network operation plan is more and more complex. The automation degree of the traditional operation planning, adjusting and other processes is low and depends on manual communication and coordination, the established plan cannot guarantee effective cooperation of multiple tasks, effective cooperation of multiple departments and full utilization of manpower and equipment resources, repeated adjustment is often required during plan execution, the safety production risk is increased, repeated power failure of equipment is caused, and the requirement of lean management is difficult to meet. Therefore, it is urgently needed to adopt an automatic optimization model and flow support to realize optimization and smooth operation of the production operation plan.
Disclosure of Invention
In view of the above problems, the present invention is directed to solving the above-described problems. It is an object of the present invention to provide a power system main network operation plan management system and method that solves the above problems. Specifically, the invention can realize the optimization of the production operation plan and improve the scientific reasonability and the management level of the plan.
In order to solve at least one of the above-mentioned defects in the prior art, the present invention provides a system for managing a primary grid operation plan of an electric power system, which has the following specific scheme:
a major network operation plan management system of an electric power system comprises a human resource management module, a power failure operation plan management module and a power failure operation plan management module;
the human resource management module is used for providing a reference for entering and adjusting a plan for an operation basic level planner, a basic level planner and a local dispatching mode by matching with the basic level team and entering the human resource condition in a specified time or according to a specified template;
the power failure operation plan management module is used for filling a power failure operation plan, determining whether the operation plan can be executed or not, checking an initial version plan, inquiring operation plan data to be issued, initiating an operation plan modification application, and performing operation plan modification operation after the operation plan is passed through;
the uninterrupted operation plan management module is used for carrying out plan addition, special responsibility examination, operation plan starting, coordination unit examination, plan modification and formal plan query.
Furthermore, the human resource management module comprises a human resource list module and a human resource adding module;
the human resource list module is used for providing a list display function after human resources are input, and the information list is used for displaying the units and groups of input human resources and the human resource distribution condition of each day in the current month in a default mode;
the human resource newly-increased module is used for realizing newly-increased, modification, viewing, crosswalk graph, setting as a human resource template and exporting functions, and specifically comprises the following steps:
newly adding: the method comprises the steps of recording human resource information of each day once according to the actual human resource arrangement condition of the current month of the team;
modifying: according to the actual change condition of the human resources, the current monthly human resource information is changed;
and (6) viewing: checking the human resource input condition of the current month in the form of a calendar;
cross-road drawing: checking the occupation condition of the human resources in the current month by combining the operation plan;
setting as a human resource template: selecting one condition of the manpower resources input into the system as a template, and automatically inputting the manpower resources according to the template when the system automatically adds the manpower resources;
and (3) derivation: and exporting the human resource information of the current month.
Furthermore, the power failure operation plan management module comprises a power failure operation plan filling stage module, a pre-meeting and post-meeting stage module, an initial version plan checking stage module and a formal plan stage module;
the power failure operation plan reporting module is used for carrying out operation plan addition, special responsibility audit, operation plan starting and key marking; the operation plan is newly added by a team and then submitted to a special responsibility audit, the operation plan is submitted to a department planner after the special responsibility audit is passed, and the operation plan is started by the department planner in a unified way;
the pre-meeting and post-meeting stage module is used for determining whether the operation plan can be executed or not according to the paper application data submitted by the offline operation unit through the coordination unit, and directly returning the operation plan to an operation planner of an operation plan reporting department if the operation plan is not approved to be executed; secondly, the cooperation unit planner adjusts the operation time of the executable operation plan and fills in the cooperation unit opinions;
the initial plan checking stage module is used for secondary checking or countersigning by an operation plan reporting unit and an operation plan adjusted after the coordination unit meets, and the module mainly checks whether the adjusted operation plan can meet the requirements of each unit;
the formal plan stage module is used for inquiring the operation plan data to be issued and also initiating an operation plan modification application, and the operation plan modification operation can be carried out after the approval is passed.
Furthermore, the uninterrupted operation plan management module comprises a plan adding module, a special responsibility auditing module, an operation plan starting module, a matching unit auditing module, a plan modifying module and a formal plan inquiring module;
the plan adding module is used for carrying out plan input by an operation basic level planner;
the special responsibility auditing module is used for planning special responsibility and combining with the actual situation to carry out plan approval, and after approval is passed, the operation plan is transferred to the hands of department planners to carry out the next process;
the operation plan starting module is used for starting a plan after the department planner passes the responsibility audit;
the cooperation unit auditing module is used for auditing the operation plan time by the cooperation unit, clicking an auditing passing description plan to be normally executed to directly generate a formal plan, and submitting again the auditing after the auditing does not pass the requirement that the operation filling department modifies the operation plan time according to the failure reason;
the plan modification module is used for modifying the operation plan data which cannot be verified according to the reason that the verification cannot be passed after the operation plan data is verified by the cooperation unit for the operation plan filing department;
the formal plan query module is used for displaying all the operation plans which do not need to be matched with the unit and are approved by the matched unit and submitted by the operation plan filing department in the list, and each unit can query the operation plan data of the unit in the module and export the plans according to the format of the import 4A.
A power system main network operation plan management method comprises the following steps:
A. providing a reference for entering and adjusting a plan for an operation basic level planner, a basic level planner and a local dispatching mode by matching with the basic level team and entering the human resource condition in a specified time or importing the human resource condition according to a specified template;
B. filling the power failure operation plan, determining whether the operation plan can be executed, checking an initial version plan, inquiring operation plan data to be issued, initiating an operation plan modification application, and performing operation plan modification operation after the operation plan passes the verification;
C. and performing plan addition, accountability audit, operation plan starting, coordination unit audit, plan modification and formal plan query.
Further, the A comprises:
(1) list of human resources: providing a list display function after human resources are input, and displaying the units and groups of the input human resources and the human resource distribution condition of each day in the current month by default in an information list;
(2) newly adding human resources: the method realizes the functions of newly adding, modifying, checking, setting a crosswalk graph as a human resource template and exporting, and specifically comprises the following steps:
newly adding: the method comprises the steps of recording human resource information of each day once according to the actual human resource arrangement condition of the current month of the team;
modifying: according to the actual change condition of the human resources, the current monthly human resource information is changed;
and (6) viewing: checking the human resource input condition of the current month in the form of a calendar;
cross-road drawing: checking the occupation condition of the current month human resources by combining the operation plan;
setting as a human resource template: selecting one condition of the manpower resources input into the system as a template, and automatically inputting the manpower resources according to the template when the system automatically adds the manpower resources;
and (3) deriving: and exporting the human resource information of the current month.
Further, the B includes:
(1) and (3) an operation plan filling stage:
performing operation plan addition, accountability audit, operation plan starting and key marking; the operation plan is newly added by a team and then submitted to a special responsibility audit, the operation plan is submitted to a department planner after the special responsibility audit is passed, and the operation plan is started by the department planner in a unified way;
in the aspect of flow time nodes, the work plan filling and the special responsibility examination have no time node limitation, the work plan filling can be carried out in any time period, only the time limitation is that a department planner starts the work plan of each month, and within the specified time nodes, the work planner can start the walking plan after the special responsibility examination as a main plan and add a supplementary plan;
(2) before meeting and after meeting:
in the pre-meeting and post-meeting stage, the operation plan data marked as key points in the key marking process is submitted to the process; determining whether the operation plan can be executed or not by a matching unit according to paper application data submitted by an offline operation unit, and if the operation plan is not approved to be executed, directly returning the operation plan to an operation planner of an operation plan filing department; secondly, the cooperation unit planner adjusts the operation time of the executable operation plan, fills in cooperation unit opinions and the like;
(3) checking stage of original edition plan
In the initial edition plan checking stage, the operation plan reporting unit and the operation plan adjusted after the matching unit perform secondary checking or countersigning, and the module mainly checks whether the adjusted operation plan can meet the requirements of each unit;
(4) stage of official planning
After the operation plan is checked, all the operation plan data are gathered to the process, in the process of the method, all people can inquire the operation plan data to be issued and can also initiate an operation plan modification application, and after the operation plan is checked, the operation plan modification operation can be carried out.
Further, the method C includes a method for managing the uninterruptible operation plan, specifically:
(1) plan for new addition
Plan addition is carried out by plan entry of a job base planner;
(2) accountability audit
The special responsibility auditing mainly refers to submitting a plan to a special responsibility auditing interface after a team planner enters the plan, and after a related plan is specially responsible for logging in a system, the operation plan data submitted by the team under the jurisdiction of the team can be seen on the interface, in the interface, the plan special responsibility is combined with the actual situation to carry out plan approval, and after the approval is passed, the operation plan is transferred to the hands of a department planner to carry out the next process;
(3) job plan enablement
The operation plan starting mainly refers to starting the plan after the department planner passes the responsibility audit in the module;
the main data source in the process is mainly a plan which is subject to plan responsibility and passes audit, and a department planner can inquire operation plan data of which the plan state is a non-starting state, a closed loop state and the like in the process interface.
The functions of the department plan capable of operating in the flow interface are mainly as follows: enabling the plan to be a formal plan, modifying the plan which is not enabled and is returned in an abnormal state, and returning the plan to the functions of accountability, inquiry and import of the plan;
(4) auditing by cooperating with unit
On a matching unit auditing interface, a data source is mainly started by a department planner and needs a matching unit plan;
the cooperation unit audits the operation plan time, the cooperation unit can audit the operation plan time by clicking the audit specification plan, normal execution can be directly carried out to generate a formal plan, the audit does not pass, the operation filling department needs to modify the operation plan time according to the failure reason, and the audit is submitted again;
(5) plan modification
In plan modification, the data source is mainly the operation plan data which cannot be audited by the coordination unit, and after the operation plan data is audited by the coordination unit, the operation plan data which cannot be audited is modified according to the reason of the non-audit by the operation plan filing department;
(6) official plan query
In the formal plan query, all the operation plans which do not need to be matched with the unit are displayed in the list after the matched unit is checked and passed and submitted by the operation plan filing department, and each unit can query the operation plan data of the unit in the module and carry out plan export according to the format of import 4A.
The invention has the beneficial effects that:
the method establishes an operation plan intelligent system by means of a computer intelligent process and an informatization technology, realizes the functions of reminding production resources and constraint conditions of main network operation by the system, transmitting the operation by the system in a matching way, analyzing the operation by the system, showing operation indexes in real time, tracing the operation plan root and source and the like, and further improves the scientific reasonability and the management level of the plan.
Drawings
FIG. 1 is a flow chart of the present invention for managing a blackout operation plan;
FIG. 2 is a flow chart of the management of a non-stop operation plan according to the present invention.
Detailed Description
Example 1: as shown in fig. 1-2, a major network operation plan management system for an electric power system includes a human resource management module, a power failure operation plan management module, and a power outage operation plan management module; the human resource management module is used for providing a reference for entering and adjusting a plan for an operation basic level planner, a basic level planner and a local dispatching mode by matching with the basic level team to enter in a specified time or importing human resource conditions according to a specified template;
the human resource management module comprises a human resource list module and a human resource adding module;
the human resource list module is used for providing a list display function after human resources are input, and the information list is used for displaying the units and groups of input human resources and the human resource distribution condition of each day in the current month in a default mode;
the human resource newly-increased module is used for realizing newly-increased, modification, viewing, crosswalk graph, setting as a human resource template and exporting functions, and specifically comprises the following steps:
newly adding: the method comprises the steps of recording human resource information of each day once according to the actual human resource arrangement condition of the current month of the team;
modification: according to the actual change condition of the human resources, the human resource information of the current month is changed;
and (6) viewing: checking the human resource input condition of the current month in a calendar mode;
a cross-road map: checking the occupation condition of the current month human resources by combining the operation plan;
setting as a human resource template: selecting one condition of manpower resources of the input system as a template, and automatically inputting the manpower resources according to the template when the system automatically adds the manpower resources;
and (3) deriving: and exporting the human resource information of the current month.
The power failure operation plan management module is used for filling a power failure operation plan, determining whether the operation plan can be executed or not, checking an initial version plan, inquiring operation plan data to be issued, initiating an operation plan modification application, and performing operation plan modification operation after the operation plan is passed through;
furthermore, the power failure operation plan management module comprises a power failure operation plan filling stage module, a pre-meeting and post-meeting stage module, an initial version plan checking stage module and a formal plan stage module;
the power failure operation plan reporting module is used for carrying out operation plan addition, special responsibility audit, operation plan starting and key marking; the operation plan is newly added by a team and then submitted to a special responsibility audit, the operation plan is submitted to a department planner after the special responsibility audit is passed, and the operation plan is started by the department planner in a unified way;
in the aspect of flow time nodes, the work plan filling and the special responsibility examination have no time node limitation, the work plan filling can be carried out in any time period, only the time limitation is that a department planner starts the work plan in each month, and within the specified time nodes, the work planner can start the walking plan after the special responsibility examination as a main plan and add a supplementary plan.
The pre-meeting and post-meeting stage module is used for determining whether the operation plan can be executed or not according to the paper application data submitted by the offline operation unit through the coordination unit, and directly returning the operation plan to an operation planner of an operation plan reporting department if the operation plan is not approved to be executed; secondly, the cooperation unit planner adjusts the operation time of the executable operation plan and fills in cooperation unit opinions;
the initial plan checking stage module is used for secondary checking or countersigning by an operation plan reporting unit and an operation plan adjusted after the coordination unit meets, and the module mainly checks whether the adjusted operation plan can meet the requirements of each unit;
the formal plan stage module is used for inquiring the operation plan data to be issued and also initiating an operation plan modification application, and the operation plan modification operation can be carried out after the approval is passed.
The uninterrupted operation plan management module is used for carrying out plan addition, special responsibility examination, operation plan starting, coordination unit examination, plan modification and formal plan query.
Furthermore, the uninterrupted operation plan management module comprises a plan adding module, a special responsibility auditing module, an operation plan starting module, a coordination unit auditing module, a plan modifying module and a formal plan inquiring module;
the plan adding module is used for plan input by a job base planner;
the special responsibility auditing module is used for planning special responsibility and combining with the actual situation to carry out plan approval, and after approval is passed, the operation plan is transferred to the hands of department planners to carry out the next process;
the operation plan starting module is used for starting a plan after the department planner passes the accountability examination in the module;
the cooperation unit auditing module is used for auditing the operation plan time by the cooperation unit, clicking an auditing passing description plan to be normally executed to directly generate a formal plan, and submitting again the auditing after the auditing does not pass the requirement that the operation filling department modifies the operation plan time according to the failure reason;
the plan modification module is used for modifying the operation plan data which cannot be verified according to the reason that the verification cannot be passed after the operation plan data is verified by the cooperation unit for the operation plan filing department;
the formal plan query module is used for displaying all the operation plans which do not need the cooperation units and are checked by the cooperation units and submitted by the operation plan filing department in the list, and each unit can query the operation plan data of the unit in the module and export the plans according to the format of import 4A.
A power system main network operation plan management method comprises the following steps:
A. providing a reference for entering and adjusting a plan for an operation basic level planner, a basic level planner and a local dispatching mode by matching with the basic level team and entering the human resource condition in a specified time or importing the human resource condition according to a specified template;
B. filling the power failure operation plan, determining whether the operation plan can be executed, checking an initial version plan, inquiring operation plan data to be issued, initiating an operation plan modification application, and performing operation plan modification after the operation plan passes the verification;
C. and performing plan addition, accountability audit, operation plan starting, coordination unit audit, plan modification and formal plan query.
Further, the A comprises:
(1) list of human resources: providing a list display function after human resources are input, and displaying the units and groups of the input human resources and the human resource distribution condition of each day in the current month by default in an information list;
(2) newly adding human resources: the method realizes the functions of newly adding, modifying, checking, setting a crosswalk graph as a human resource template and exporting, and specifically comprises the following steps:
newly adding: the method comprises the steps of recording human resource information of each day once according to the actual human resource arrangement condition of the current month of the team;
modification: according to the actual change condition of the human resources, the human resource information of the current month is changed;
and (6) viewing: checking the human resource input condition of the current month in the form of a calendar;
cross-road drawing: checking the occupation condition of the current month human resources by combining the operation plan;
setting as a human resource template: selecting one condition of manpower resources of the input system as a template, and automatically inputting the manpower resources according to the template when the system automatically adds the manpower resources;
and (3) deriving: and exporting the human resource information of the current month.
Further, the B includes:
(1) and (3) an operation plan filling stage:
performing operation plan addition, accountability audit, operation plan starting and key marking; the operation plan is newly added by a team and then submitted to a special responsibility audit, the operation plan is submitted to a department planner after the special responsibility audit is passed, and the operation plan is started by the department planner in a unified way;
in the aspect of flow time nodes, the work plan reporting and the special responsibility auditing have no time node limitation, the work plan can be carried out in any time period, only the time limitation exists when a department planner starts the work plan in each month, and within the specified time nodes, the work planner can start the walking plan after the special responsibility auditing as a main plan and add a supplementary plan;
(2) stage before meeting and stage after meeting:
in the pre-meeting and post-meeting stage, the operation plan data marked as the key in the key marking process is submitted to the process; determining whether the operation plan can be executed or not by a matching unit according to paper application data submitted by an offline operation unit, and if the operation plan is not agreed to be executed, directly returning the operation plan to an operation planner of an operation plan filling department; secondly, the cooperation unit planner adjusts the operation time of the executable operation plan, fills in cooperation unit opinions and the like;
(3) checking stage of original edition plan
In the initial edition plan checking stage, the operation plan reporting unit and the operation plan adjusted after the matching unit perform secondary checking or countersigning, and the module mainly checks whether the adjusted operation plan can meet the requirements of each unit;
(4) stage of official planning
After the operation plan is checked to be passed, all the operation plan data can be collected into said flow.
Further, the step C includes a method for managing the uninterruptible power supply operation plan, which specifically includes:
(1) plan for new addition
Plan addition is carried out by plan entry of a job base planner;
(2) accountability audit
The special responsibility auditing mainly refers to submitting a plan to a special responsibility auditing interface after a team planner enters the plan, and after a related plan is specially responsible for logging in a system, the operation plan data submitted by the team under the jurisdiction of the team can be seen on the interface, in the interface, the plan special responsibility is combined with the actual situation to carry out plan approval, and after the approval is passed, the operation plan is transferred to the hands of a department planner to carry out the next process;
(3) job plan enablement
The operation plan starting mainly refers to starting the plan after the department planner passes the responsibility audit in the module;
the main data source in the process is mainly a plan which is subject to plan responsibility and passes audit, and a department planner can inquire operation plan data of which the plan state is a non-starting state, a closed loop state and the like in the process interface.
The functions of the department plan capable of operating in the flow interface are mainly as follows: enabling the plan to be a formal plan, modifying the plan which is not enabled and is returned in an abnormal state, and returning the plan to the functions of accountability, inquiry and import of the plan;
(4) auditing by cooperating with unit
On a coordination unit auditing interface, a data source is mainly started by a department planner and needs a plan of a coordination unit;
the operation plan time is checked by the cooperation unit in cooperation with unit checking, the checking is clicked to indicate that the plan can be normally executed and a formal plan is directly generated, the operation plan time is modified by an operation filling department according to the reason that the checking does not pass, and the checking is submitted again;
(5) plan modification
In plan modification, the data source is mainly the operation plan data which cannot be audited by the coordination unit, and after the operation plan data is audited by the coordination unit, the operation plan data which cannot be audited is modified according to the reason of the non-audit by the operation plan filing department;
(6) official plan query
In the formal plan query, all the operation plans which do not need to be matched with the unit are displayed in the list after the matched unit is checked and passed and submitted by the operation plan filing department, and each unit can query the operation plan data of the unit in the module and carry out plan export according to the format of import 4A.
Example 2: a power system main network operation plan management system is characterized in that a power system main network operation plan management method is formed based on functional modules in the power system main network operation plan management system, and a power failure operation plan management method and a power outage operation plan management method flow are shown in the figure 1-2; in order to achieve the aspects mentioned in the summary of the present invention, the system needs to develop a set of operation plan management system using computer language, which includes functional modules that can achieve the following effects, and the specific implementation effects are as follows:
human resource management: the new manpower resource menu bar mainly comprises: adding, modifying, checking, cross-road drawing, setting as a human resource template, exporting and the like.
The detailed functional description is as follows:
newly adding: and the human resource information of each day is recorded once according to the actual human resource arrangement condition of the current month of the class group.
Modifying: and according to the actual change condition of the human resources, the current monthly human resource information is changed.
And (6) viewing: and checking the human resource entry condition of the current month in the form of a calendar.
Cross-road drawing: the occupation condition of the current month human resources is mainly checked by combining the operation plan.
Setting as a human resource template: and selecting one condition of the human resources of the input system as a template, and automatically inputting the human resources according to the template when the system automatically adds the new human resources.
And (3) derivation: and exporting the human resource information of the current month.
Power outage operation plan management
1. Newly added power cut plan
The menu bar for the new function of the operation plan mainly comprises: adding, editing, deleting, inquiring, importing, exporting, downloading a plan template, previewing a plan, submitting responsibility for auditing and the like. The detailed functional description is as follows:
newly adding: the plan addition mainly comprises import and system addition functions. The plan import mainly comprises the steps of filling the operation plan data in an excel according to filling descriptions, and then completing the import of the operation plan through an import button; the operation plan is added into the system one by one through adding buttons, wherein the operation plan is added into the system one by one and can be divided into manual addition, historical plan addition and common template addition, and the introduction of each new adding mode is as follows:
(1) manually adding: the manual addition mainly refers to manually adding a piece of operation plan data from 0 to 1 according to the filling requirements of the operation plan.
(2) Newly adding a history plan: the method mainly includes the steps of selecting 1 filled job plan datum, referring to all data of the job plan, modifying and storing the data on the premise of the datum, and completing the addition of the job plan.
(3) Newly adding a template: the method mainly comprises the steps of setting a plurality of operation plans as common templates, selecting one template data from the newly-added operation plan templates to modify and store, and completing the newly-added operation plan data.
Editing: editing is mainly to modify the operation plan data which is added newly and is not submitted to the accountability audit.
And (3) deleting: deletion is mainly to delete the erroneous job plan data that is not submitted for accountability review.
And (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
And (3) importing template downloading: here, a specification template in the job plan import system is mainly downloaded.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
Submitting a special responsibility audit: the main is that after the team planner enters the job plan, the job plan is manually submitted to the accountability through the button. Note that: the job plan cannot be modified or deleted after being submitted to the obligation.
2. Accountability audit
The accountability audit function menu bar mainly comprises: adding, editing, deleting, inquiring, importing, exporting, downloading a plan template, previewing a plan, submitting a department planner, returning, pushing and the like. The detailed functional description is as follows:
newly adding: the plan addition mainly comprises import and system addition functions. The plan import mainly comprises the steps of filling the operation plan data in a form in excel according to filling instructions, and then completing the import of the operation plan through an import button; the operation plan is added one by one mainly by adding operation plan data in the system through a new button, wherein the operation plan can be divided into three types of manual addition, historical plan addition and common template addition, and the introduction of each new adding mode is as follows:
(1) manually adding: the manual addition mainly refers to manually adding a piece of operation plan data from 0 to 1 according to the filling requirements of the operation plan.
(2) Newly adding a history plan: the method mainly includes the steps of selecting 1 filled job plan datum, referring to all data of the job plan, modifying and storing the data on the premise of the datum, and completing the addition of the job plan.
(3) Newly adding a template: the method mainly comprises the steps of setting a plurality of operation plans as common templates, selecting one template data from the newly added operation plan templates to modify and store, and completing the newly added operation plan data.
Editing: editing is primarily to modify the job planning data of the uncommitted department planner.
And (3) deleting: deletion is mainly to delete erroneous job plan data of the non-submitting department planner.
And (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
And (3) importing template downloading: here, a specification template in the job plan import system is mainly downloaded.
Plan preview: the plan preview mainly loads all the job plans, and can view information lists of all job plan fields on one page.
Submitting department planner: the main point is that after the job plan meeting the job condition is approved by the responsibility audit, the job plan is manually submitted to the department planner through the button. Note that: the job plan, if submitted to a department planner, cannot be modified or deleted.
Withdrawing: the job plan which does not satisfy the job condition is returned to the hands of the team planner mainly through a return button.
Pushing: the operation plan is pushed to other special responsibilities under the department to be viewed mainly through the button.
3. Job plan enablement
The operation plan starting function menu bar mainly comprises: editing, querying, exporting, plan previewing, enabling as a primary plan, enabling as a backup plan, returning, etc. functions. The detailed functional description is as follows:
editing: editing is primarily to modify the job planning data of the uncommitted department planner.
And (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
Withdrawing: the operation plan which does not meet the operation condition is returned to the plan accountant through a return button.
The starting is a main plan: and the department planners automatically arrange the initial edition planning arrangement of the month according to the actual human resource condition of the month and the importance degree of the submitted plan, wherein the function has time limitation, and the specific usable time can be configured according to the actual condition.
Enabling as a supplementary plan: after the main plan passes through the stages of key work marking, initial review of coordination units, equilibrium meeting and the like, the phenomenon that the plan is actively returned occurs, but on the aspect of considering the problem of human resources, in the adjustment stage after the meeting, a function (original standby plan function) for adding a supplementary plan is introduced, and the purpose of the function is mainly to make up for the vacancy of the human resources.
4. Key plan marking
The key plan marking function menu bar mainly comprises: query, focus mark, cancel mark, export, plan preview, etc. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
Key marks are as follows: the 'key mark' is the main function of the interface, mainly operates as the plan submitted by the plan administrator of four departments of production, capital construction, marketing and system for the responsibility of each department plan, changes the state of the selected plan from 'whether belonging to the key plan' field to 'yes' through the 'key mark', and the default value of the field is 'no';
note that: secondly, whether the four large doors can only mark the plans related to the doors, and the requirements of the baggage, canoe and baggage workers are clear.
Canceling the mark: the plan administrator of the four major departments changes the status of the selected plan from 'whether the selected plan belongs to the important plan' to 'No' through 'unmarking' for the operation plan marked as the important plan, so as to realize unmarking operation of the important plan.
Description of the functions of submission and return of the data marked with the heavy points: the operation plan data system with key marks in the interface can not be directly submitted to the next flow, and manual submission is not supported; the submission and return of the operation plan data can be automatically judged only by the system according to the following judgment criteria: when the current time reaches the deadline of the key marking time of the operation plan, the system automatically submits and returns according to the value of 'whether the current time belongs to the key plan', wherein the key plan belongs to the next process automatically, and the part which does not belong to the key plan returns to a department planner.
5. Preliminary examination before meeting
The menu bar for matching the preliminary examination before meeting mainly comprises: inquiry, plan preview, export, balance conference discussion, return, filling in comments, cross-track map adjustment and the like. The detailed functional description is as follows:
inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
The balance will be discussed: the balance conference discussion mainly marks the selected operation plan, the system changes the value of the 'whether the selected operation plan is discussed in the balance conference' field into 'yes', the main function is to mark the operation plan, and the operation plan is loaded in the balance conference stage, and the specific description is described in the 'balance conference' stage.
And (3) withdrawing: returning is to check data submitted by the cooperation unit planner according to the offline operation unit, whether the operation plan can be executed or not is autonomously determined, and if the operation plan cannot be executed, the operation plan is directly returned to the operation plan reporter by a 'returning' button.
Filling in the comments: through the comment filling button, the related comments of the operation plan can be filled in by matching with the unit planner, and the function of referring the common comments is required to be supported functionally.
Adjusting a crosswalk diagram: the adjustment of the cross-road diagram is mainly to meet the requirement that a coordination unit planner can carry out the relevant adjustment of operation planning time and coordination personnel according to the human resource distribution condition of the coordination unit coordination team.
6. Annuage filling
The regional opinion filling menu bar mainly comprises: query, plan preview, export, fill out comments, balance meeting discussion, etc. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the job plan data meeting the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
The balance will be discussed: the balance conference discussion mainly marks the selected operation plan, the system changes the value of the 'whether the selected operation plan is discussed in the balance conference' field into 'yes', the main function is to mark the operation plan, and the operation plan is loaded in the balance conference stage, and the specific description is described in the 'balance conference' stage.
Filling in the comments: by filling in the opinions button, the local scheduling planner can fill in the related opinions of the work plan, and the function of referring to the commonly used opinions needs to be supported.
7. Balancing party
The balance meeting menu bar mainly comprises: query, plan preview, export, balance meeting fill, return, etc. The detailed functional description is as follows:
inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
Opinion of equilibrium: through the comment filling button, the user can fill in the related comments of the operation plan, and the function of referring to the commonly used comments is functionally required to be supported.
And (3) withdrawing: the method is mainly used for returning the work plan which cannot be executed to a work plan report unit department planner through a return button.
8. Adjustment after meeting
The balance meeting menu bar mainly comprises: query, export, modify, submit, add supplemental plan, and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) derivation: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Modifying: the modification is mainly to modify the job plan data whose 'uncommitted operation audit' is 'no'.
Submitting: the modified job plan data is mainly submitted to the relevant operation units through a submit button.
Adding a supplementary plan: for the unit that the operation plan can not execute the cancelled plan, plan supplement can be carried out according to the actual situation of the unit (the standby plan function is originally started), and the functional operation is mainly that a department planner adds a non-important plan or other non-started plans to the main flow by a type of the supplement plan through a 'supplement plan' button.
9. Run institute review
The operation of the auditor menu bar mainly comprises: and functions of inquiry, export, plan preview, audit pass, audit fail and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) derivation: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
And (4) passing the audit: the planner marks the modified job plan data as passed through the 'audit pass' button, and the system automatically submits the job plan data marked as passed to the local audit process.
The audit is not passed: the planner marks the job plan data which is not satisfied with the requirement after modification as fail through the 'check fail' button, fills in the fail reason at the same time, and the system automatically returns the job plan data marked as fail to the post-meeting adjustment stage.
10. Survey of local conditions
The local tone auditing menu bar mainly comprises: and functions of inquiry, export, plan preview, audit pass, audit fail and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) derivation: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
And (4) passing the audit: the planner marks the modified job plan data as pass through the 'check pass' button, and the system automatically submits the job plan data marked as pass to the initial version plan check flow.
The audit is not passed: the planner marks the job plan data which is not satisfied with the requirement after modification as fail through the 'check fail' button, fills in the fail reason at the same time, and the system automatically returns the job plan data marked as fail to the post-meeting adjustment stage.
11. Checking of original edition plan
The checking menu bar of the original plan mainly comprises: query, export, plan preview, audit pass, audit fail, etc. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
The verification is passed: after the operation plan is reported to the unit and the department planner of the matching unit checks that the operation plan has no problem, the 'pass' button is used for marking the checked operation plan data as pass, and after all the units are checked, the system automatically submits the operation plan after the 'pass' to the process of the plan to be issued.
The check fails: after the operation plan data are checked, the department planner of the cooperation unit marks the operation plan data which are not met with the requirements after being modified as fail through a 'check fail' button aiming at the operation plan data which are not met with the requirements, and simultaneously fills the fail reasons, and the system automatically pushes the operation plan data marked as fail to an original edition plan adjusting flow.
12. Project adjustment for original edition
The initial plan adjustment menu bar mainly comprises: querying, exporting, modifying, submitting auditing and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Modifying: the 'failure of verification' operation plan data is modified mainly according to the reason of failure of verification.
Submitting and auditing: the modified job plan data is mainly submitted to the next process through a submit button.
13. Examination by the department of the original edition planning
The examination menu bar of the original edition plan department mainly comprises: query, export, plan preview, audit pass, audit fail, etc. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
And (4) passing the audit: the planner marks the modified job plan data as passed through the 'audit pass' button, and the system automatically submits the job plan data marked as passed to the plan countersign flow.
The audit is not passed: the planner marks the job plan data which is not satisfied with the requirement after modification as fail through the 'check fail' button, and fills in the fail reason, and the system automatically returns the job plan data marked as fail to the initial edition plan adjusting stage.
14. Meeting label for original edition plan
The initial plan will sign menu bar mainly includes: and functions of inquiry, export, plan preview, audit pass, audit fail and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view information lists of all job plan fields on one page.
The verification is passed: after the department planners of the matching units and the department of biotechnology verify that the operation plans are not problematic, the verified operation plan data is marked as pass by using a pass button, and after all the units are verified, the system automatically submits the operation plans after the pass of the pass to the original edition plan operation institute for auditing process.
The check fails: after the department planner of the cooperation unit and the department of biotechnology checks the operation plan data, the operation plan data which does not meet the requirements after being modified is marked as fail through a 'check fail' button aiming at the operation plan data which does not meet the requirements, and simultaneously, the reason for the fail is filled, and the system automatically pushes the operation plan data marked as fail to an original edition plan adjusting flow.
15. Review of original edition plan operation institute
The auditing menu bar of the original plan operation institute mainly comprises: and functions of inquiry, export, plan preview, audit pass, audit fail and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the job plan data meeting the set query conditions.
And (3) derivation: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
And (4) passing the audit: the planner marks the modified operation plan data as passing through the 'pass-by-audit' button, and the system automatically submits the operation plan data marked as passing to the initial edition plan to adjust the audit process.
The audit is not passed: the planner marks the modified job plan data which does not meet the requirements as failed through the 'check failed' button, and fills the reasons of failure, and the system automatically returns the job plan data marked as failed to the original edition plan adjusting flow.
16. Project-to-make audit
The initial plan local adjustment auditing menu bar mainly comprises: and functions of inquiry, export, plan preview, audit pass, audit fail and the like. The detailed functional description is as follows:
inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
And (4) passing the audit: the planner marks the modified operation plan data as pass through the 'check pass' button, and the system automatically submits the operation plan data marked as pass to the to-be-issued plan viewing process.
The audit does not pass: the planner marks the modified job plan data which does not meet the requirements as failed through the 'check failed' button, and simultaneously fills the reasons of failure, and the system automatically returns the job plan data marked as failed to the initial edition plan adjusting flow.
17. To-be-published plan view
The to-be-released plan viewing menu bar mainly comprises: query, export, application modification, plan release, and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
And (4) modifying application: the operation plan filing department can fill in the modification reason to initiate the operation plan modification application to the dispatching before the operation plan is not released after forming the replacement sending and supplementing operation plan.
Planning and releasing: the technical department planner can change the state of the job plan to be distributed to the official plan through the distribution plan button, thereby realizing the function of distributing the official plan.
18. Amendment application review
The modification application auditing menu bar mainly comprises: and inquiring, checking to pass, checking not to pass and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the modification application meeting the conditions according to the set query conditions.
And (4) passing the audit: the map scheduler marks the modified application data as passed via the 'audit pass' button.
The audit is not passed: the map scheduler marks the modification application data as failed through the 'check failed' button, and the modification operation plan data cannot be modified for the modification application marked as failed.
19. Pending release plan modification
The to-be-released plan view menu bar mainly comprises: querying, exporting, modifying, submitting auditing and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) derivation: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Submitting and auditing: and the user submits the modified operation plan data to an operation place for examination through a submission examination button.
Modifying: and selecting a modification application, clicking plan modification, jumping the interface to a plan modification interface, and inquiring all operation plan information by the system, wherein the operation plan information can be modified and stored functionally.
20. Auditing of the operations institute (to-be-released plan)
The menu bar for operating the auditor (to-be-issued plan) mainly comprises: and inquiring, exporting, passing and failing to pass the audit and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
And (4) passing the audit: the planner marks the modified job plan data as passed through the 'audit pass' button, and the system automatically submits the job plan data marked as passed to the local audit (to-be-issued plan) flow.
The audit is not passed: and the planner marks the operation plan data which does not meet the requirements after modification as non-passing through the 'check non-passing' button, and fills the non-passing reason at the same time, and the system automatically returns the operation plan data marked as non-passing to the plan modification flow to be issued.
21. Local tone auditing (to be released plan)
The menu bar of local tone auditing (plan to be issued) mainly comprises: and inquiring, exporting, passing and failing to pass the audit and the like. The detailed functional description is as follows:
and (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) derivation: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
And (4) passing the audit: the planner marks the modified operation plan data as pass through by the 'audit pass' button, and the system updates the operation plan data after the local tone audit passes in the plan data to be issued.
The audit does not pass: and the planner marks the operation plan data which does not meet the requirements after modification as non-passing through the 'check non-passing' button, fills the non-passing reason at the same time, and the system automatically returns the operation plan data marked as non-passing to the plan modification interface to be issued.
Management of work plan without power outage
1. Plan for new addition
The menu bar for the new function of the operation plan mainly comprises: adding, editing, deleting, inquiring, importing, exporting, downloading a plan template, previewing a plan, submitting responsibility for auditing and the like. The detailed functional description is as follows:
newly adding: the plan addition mainly comprises import and system addition functions. The plan import mainly comprises the steps of filling the operation plan data in a form in excel according to filling instructions, and then completing the import of the operation plan through an import button; the operation plan is added into the system one by one through adding buttons, wherein the operation plan is added into the system one by one and can be divided into manual addition, historical plan addition and common template addition, and the introduction of each new adding mode is as follows:
(1) manually adding: the manual addition mainly refers to manually adding a piece of operation plan data from 0 to 1 according to the filling requirements of the operation plan.
(2) Newly adding a history plan: the method mainly includes the steps of selecting 1 filled job plan datum, referring to all data of the job plan, modifying and storing the data on the premise of the datum, and completing the addition of the job plan.
(3) Newly adding a template: the method mainly comprises the steps of setting a plurality of operation plans as common templates, selecting one template data from the newly added operation plan templates to modify and store, and completing the newly added operation plan data.
Editing: editing is mainly to modify the operation plan data which is added newly and is not submitted to the accountability audit.
And (3) deleting: deletion is mainly to delete erroneous job plan data that is not submitted for a dedicated audit.
And (3) inquiring: the query is mainly to query the job plan data meeting the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
And (3) importing template downloading: here, a specification template in the job plan import system is mainly downloaded.
Plan preview: the plan preview mainly loads all the job plans, and can view the information lists of all the job plan fields on one page.
Submitting a special responsibility and auditing: the team planner manually submits the operation plan to the accountability through the button after entering the operation plan.
2. Accountability audit
The accountability audit function menu bar mainly comprises: adding, editing, deleting, inquiring, importing, exporting, downloading a plan template, previewing a plan, submitting a department planner, returning and the like. The detailed functional description is as follows:
newly adding: the plan for adding new functions is mainly divided into import and system adding functions one by one. The plan import mainly comprises the steps of filling the operation plan data in a form in excel according to filling instructions, and then completing the import of the operation plan through an import button; the operation plan is added into the system one by one through adding buttons, wherein the operation plan is added into the system one by one and can be divided into manual addition, historical plan addition and common template addition, and the introduction of each new adding mode is as follows:
(1) manually adding: the manual addition mainly refers to manually adding a piece of operation plan data from 0 to 1 according to the filling requirements of the operation plan.
(2) Newly adding a history plan: mainly means that 1 filled job plan data is selected, all data of the job plan is quoted, data modification and storage are carried out on the premise of the data, and the new addition of the job plan is completed.
(3) Newly adding a template: the method mainly comprises the steps of setting a plurality of operation plans as common templates, selecting one template data from the newly-added operation plan templates to modify and store, and completing the newly-added operation plan data.
Editing: editing is primarily to modify the job planning data of the non-submitting department planner.
And (4) deleting: the deletion is mainly to delete erroneous job plan data of an uncommitted department planner.
And (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
And (3) importing template downloading: here, a specification template in the job plan import system is mainly downloaded.
Plan preview: the plan preview mainly loads all the job plans, and can view information lists of all job plan fields on one page.
Submitting department planner: the main point is that after the job plan meeting the job condition is approved by the responsibility audit, the job plan is manually submitted to the department planner through the button. Note that: the job plan cannot be modified or deleted after it is submitted to the department planner.
Withdrawing: the job plan which does not satisfy the job condition is returned to the team planner's hands mainly by the return button.
3. Job plan enablement
The accountability audit function menu bar mainly comprises: editing, querying, exporting, plan previewing, launching as a master plan, returning, etc. The detailed functional description is as follows:
editing: editing is primarily to modify the non-enabled job plan data.
And (3) inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Plan preview: the plan preview mainly loads all the job plans, and can view information lists of all job plan fields on one page.
And (3) withdrawing: the operation plan which does not meet the operation condition is returned to the planning accountant through a return button.
The starting is a main plan: and the department planners automatically arrange the initial edition plan arrangement according to the actual human resource condition of the month and the importance degree of the submitted plan, wherein the function has time limitation, and the specific usable time can be configured according to the actual condition.
4. Auditing by cooperating with unit
The menu bar for matching the preliminary examination before meeting mainly comprises: and the functions of inquiry, export, adjustment of a cross-road graph, passing and failing of examination and the like are realized. The detailed functional description is as follows:
inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Adjusting a crosswalk diagram: the adjustment of the cross-road map is mainly to meet the requirement that a coordinated unit planner can carry out the relevant adjustment of operation planning time and coordinated personnel according to the human resource distribution condition of the coordinated unit coordinated with a team.
And (4) passing the audit: the planner marks the modified job plan data as passed through the 'audit pass' button, and the system automatically publishes the job plan data marked as passed and generates a formal plan.
The audit is not passed: the planner passes the 'check fail' button, marks the job plan data as fail, and fills in the fail reason, the system automatically pushes the job plan data marked as fail to the job plan modification
5. Plan modification
The menu bar of the plan modification boundary mainly comprises: and querying, exporting, modifying, submitting auditing and the like. The detailed functional description is as follows:
inquiring: the query is mainly to query the operation plan data meeting the conditions according to the set query conditions.
And (3) deriving: the method mainly comprises the step of conducting excel table export data on the inquired operation plan data according to a specified format.
Modifying: the modification is mainly to modify the job plan data whose 'uncommitted operation audit' is 'no'.
Submitting and auditing: the modified operation plan data is submitted to a relevant coordination unit for examination through a submit button.
While the present invention has been described in detail with reference to the embodiments shown in the drawings, the present invention is not limited to the embodiments, and various changes can be made without departing from the spirit of the present invention within the knowledge of those skilled in the art.

Claims (7)

1. A power system major network operation plan management system is characterized in that: the system comprises a human resource management module, a power failure operation plan management module and a power failure operation plan management module;
the human resource management module is used for providing a reference for entering and adjusting a plan for an operation basic level planner, a basic level planner and a local dispatching mode by matching with the basic level team and entering the human resource condition in a specified time or according to a specified template;
the power failure operation plan management module is used for filling a power failure operation plan, determining whether the operation plan can be executed or not, checking an initial version plan, inquiring operation plan data to be issued, initiating an operation plan modification application, and performing operation plan modification operation after the operation plan is passed through;
the uninterrupted operation plan management module is used for carrying out plan addition, special responsibility examination, operation plan starting, coordination unit examination, plan modification and formal plan query;
the power failure operation plan management module comprises a power failure operation plan filling stage module, a pre-meeting and post-meeting stage module, an initial version plan checking stage module and a formal plan stage module;
the power failure operation plan reporting module is used for carrying out operation plan addition, special responsibility audit, operation plan starting and key marking; the operation plan is newly added by a team and then submitted to a special responsibility audit, the operation plan is submitted to a department planner after the special responsibility audit is passed, and the operation plan is started by the department planner in a unified way;
the pre-meeting and post-meeting stage module is used for determining whether the operation plan can be executed or not according to the paper application data submitted by the offline operation unit through the coordination unit, and directly returning the operation plan to an operation planner of an operation plan reporting department if the operation plan is not approved to be executed; secondly, the cooperation unit planner adjusts the operation time of the executable operation plan and fills in cooperation unit opinions;
the initial plan checking stage module is used for secondary checking or countersigning by the operation plan reporting unit and the operation plan adjusted after the coordination unit meets, and the module is used for checking whether the adjusted operation plan can meet the requirements of each unit;
the formal plan stage module is used for inquiring the operation plan data to be issued and also can initiate an operation plan modification application, and the operation plan modification operation can be carried out after the approval is passed.
2. The power system main network operation plan management system according to claim 1, characterized in that: the human resource management module comprises a human resource list module and a human resource adding module;
the human resource list module is used for providing a list display function after human resources are input, and the information list is used for displaying the units and groups of input human resources and the human resource distribution condition of each day in the current month in a default mode;
the human resource newly-increased module is used for realizing newly-increased, modification, viewing, crosswalk graph, setting as a human resource template and exporting functions, and specifically comprises the following steps:
newly adding: the method comprises the steps of recording human resource information of each day once according to the actual human resource arrangement condition of the current month of the team;
modifying: according to the actual change condition of the human resources, the current monthly human resource information is changed;
and (6) viewing: checking the human resource input condition of the current month in the form of a calendar;
cross-road drawing: checking the occupation condition of the current month human resources by combining the operation plan;
setting as a human resource template: selecting one condition of the manpower resources input into the system as a template, and automatically inputting the manpower resources according to the template when the system automatically adds the manpower resources;
and (3) deriving: and exporting the human resource information of the current month.
3. The power system main network operation plan management system according to claim 1, wherein: the uninterrupted operation plan management module comprises a plan newly-added module, a special responsibility auditing module, an operation plan starting module, a coordination unit auditing module, a plan modification module and a formal plan query module;
the plan adding module is used for carrying out plan input by an operation basic level planner;
the special responsibility auditing module is used for planning special responsibility and combining with the actual situation to carry out plan approval, and after approval is passed, the operation plan is transferred to the hands of department planners to carry out the next process;
the operation plan starting module is used for starting a plan after the department planner passes the responsibility audit;
the cooperation unit auditing module is used for auditing the operation plan time by the cooperation unit, clicking an auditing passing description plan to be normally executed to directly generate a formal plan, and submitting again the auditing after the auditing does not pass the requirement that the operation filling department modifies the operation plan time according to the failure reason;
the plan modification module is used for modifying the operation plan data which cannot be verified according to the reason that the verification cannot be passed after the operation plan data is verified by the cooperation unit for the operation plan filing department;
the formal plan query module is used for displaying all the operation plans which do not need the cooperation units and are checked by the cooperation units and submitted by the operation plan filing department in a list, and each unit can query the operation plan data of the unit in the module and export the plans according to the format of import 4A.
4. A method for managing a main network operation plan of an electric power system is characterized by comprising the following steps: the method comprises the following steps:
A. providing a reference for entering and adjusting a plan for an operation basic level planner, a basic level planner and a local adjustment mode by matching with the basic level team to enter in a specified time or importing human resource conditions according to a specified template;
B. filling the power failure operation plan, determining whether the operation plan can be executed, checking an initial version plan, inquiring operation plan data to be issued, initiating an operation plan modification application, and performing operation plan modification after the operation plan passes the verification;
C. and performing plan addition, accountability audit, operation plan starting, coordination unit audit, plan modification and formal plan query.
5. The power system main network operation plan management method according to claim 4, characterized in that: the A comprises the following steps:
providing a list display function after human resources are input, and displaying the units and groups of the input human resources and the human resource distribution condition of each day in the current month by default in an information list;
the method realizes the functions of newly adding, modifying, checking, setting a crosswalk graph as a human resource template and exporting, and specifically comprises the following steps:
newly adding: the method comprises the steps of recording human resource information of each day once according to the actual human resource arrangement condition of the current month of the team;
modifying: according to the actual change condition of the human resources, the current monthly human resource information is changed;
checking: checking the human resource input condition of the current month in the form of a calendar;
cross-road drawing: checking the occupation condition of the current month human resources by combining the operation plan;
setting as a human resource template: selecting one condition of the manpower resources input into the system as a template, and automatically inputting the manpower resources according to the template when the system automatically adds the manpower resources;
and (3) derivation: and exporting the human resource information of the current month.
6. The power system main network operation plan management method according to claim 4, characterized in that: the B comprises:
performing operation plan addition, accountability examination, operation plan starting and key marking; the operation plan is newly added by a team and then submitted to a special responsibility audit, the operation plan is submitted to a department planner after the special responsibility audit is passed, and the operation plan is started by the department planner in a unified way;
determining whether the operation plan can be executed or not by a matching unit according to paper application data submitted by an offline operation unit, and if the operation plan is not approved to be executed, directly returning the operation plan to an operation planner of an operation plan filing department; secondly, the cooperation unit planner adjusts the operation time of the executable operation plan and fills in cooperation unit opinions;
the operation plan reporting unit and the operation plan adjusted after meeting of the matching unit carry out secondary check or countersigning, and whether the adjusted operation plan can meet the requirements of each unit is checked in the module;
and inquiring the data of the operation plan to be issued, initiating an application for modifying the operation plan, and performing operation for modifying the operation plan after the data to be checked passes.
7. The power system main network operation plan management method according to claim 4, characterized in that: the C comprises:
carrying out plan entry by a job base-level planner;
plan accountability is combined with reality to carry out plan approval, after approval is passed, the operation plan is transferred to the hands of department planners to carry out the next process;
enabling the plan after the accountability audit is passed by the department planner in the module;
the cooperation unit audits the operation plan time, the normal execution of the audit passing description plan can be clicked to directly generate a formal plan, the audit does not pass the requirement, the operation filling department modifies the operation plan time according to the failure reason, and the audit is submitted again;
after the operation plan data is checked by the cooperation unit, the operation plan filing department modifies the operation plan data which cannot be checked according to the reason of the failure of checking;
and displaying all the operation plans which do not need to be matched with the unit and are checked and passed by the matching unit and submitted by the operation plan filing department in a list, wherein each unit can inquire the operation plan data of the unit in the module, and plan export is carried out according to the format of import 4A.
CN202010154590.9A 2020-03-08 2020-03-08 Main network operation plan management system and method for power system Active CN111383127B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010154590.9A CN111383127B (en) 2020-03-08 2020-03-08 Main network operation plan management system and method for power system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010154590.9A CN111383127B (en) 2020-03-08 2020-03-08 Main network operation plan management system and method for power system

Publications (2)

Publication Number Publication Date
CN111383127A CN111383127A (en) 2020-07-07
CN111383127B true CN111383127B (en) 2022-09-09

Family

ID=71221487

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010154590.9A Active CN111383127B (en) 2020-03-08 2020-03-08 Main network operation plan management system and method for power system

Country Status (1)

Country Link
CN (1) CN111383127B (en)

Families Citing this family (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112365114A (en) * 2020-08-24 2021-02-12 南方电网数字电网研究院有限公司 Power operation plan management method based on operation and maintenance management platform
CN112488482B (en) * 2020-11-25 2023-06-30 广东电网有限责任公司 Automatic operation method and system based on index system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102880790A (en) * 2012-08-24 2013-01-16 国家电网公司 Personal digital assistant (PDA)-mode-based field standard operating system and operating flow
CN108921420A (en) * 2018-06-27 2018-11-30 深圳供电局有限公司 Method and system for generating production plan by power plant station equipment
CN109377178A (en) * 2018-10-23 2019-02-22 国网江苏省电力有限公司经济技术研究院 Power grid technological transformation major repair project electronization review system and reviewing method
CN109670982A (en) * 2018-12-04 2019-04-23 上海欣能信息科技发展有限公司 A kind of electric service plateform system of fusion fortune inspection intelligence control system

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102880790A (en) * 2012-08-24 2013-01-16 国家电网公司 Personal digital assistant (PDA)-mode-based field standard operating system and operating flow
CN108921420A (en) * 2018-06-27 2018-11-30 深圳供电局有限公司 Method and system for generating production plan by power plant station equipment
CN109377178A (en) * 2018-10-23 2019-02-22 国网江苏省电力有限公司经济技术研究院 Power grid technological transformation major repair project electronization review system and reviewing method
CN109670982A (en) * 2018-12-04 2019-04-23 上海欣能信息科技发展有限公司 A kind of electric service plateform system of fusion fortune inspection intelligence control system

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
供电公司现场标准化作业系统的设计与实现;王奕;《中国优秀博硕士学位论文全文数据库(硕士)信息科技辑》;20160315(第3期);第4.1、5.1节 *

Also Published As

Publication number Publication date
CN111383127A (en) 2020-07-07

Similar Documents

Publication Publication Date Title
CN104951905A (en) Equipment dynamic ledger management system
US8099336B2 (en) Component inventory management
CN111383127B (en) Main network operation plan management system and method for power system
US20160048785A1 (en) A computer implemented system and method for project controls
CN105653442A (en) Method for satisfying evaluation target of DO-178C standard
CN102117444A (en) System for comprehensive arrangement and execution management of production equipment maintenance plan
CN110390607B (en) Target cost measuring and calculating method and system based on subject index system and computer readable storage medium
CN109961264A (en) A kind of enterprise information management system and management method
CN107526804B (en) Railway investment project data statistics system and method
CN115617325A (en) Component type low-code application configuration platform
CN111897866A (en) Remote sensing monitoring pattern spot docking system and using method thereof
CN109242332A (en) A kind of monitoring analysis system of tax collection and administration data, method and device
US20130268936A1 (en) Workflow management system and method
CN115564397A (en) Automatic model management method suitable for three-dimensional collaborative design platform
CN115545651A (en) Engineering construction joint surveying and mapping sharing system
CN115330226A (en) Digital research and development method and platform based on middle station
CN114077986A (en) Material plan full-process control method
CN114443675A (en) Patent management system and method integrated with multiple systems
CN113256243A (en) Project budget full life cycle management device and method
CN113407161A (en) Complex equipment-oriented collaborative research and development management system
CN111222793A (en) Data interaction method and system
CN117993870B (en) Online approval process information interaction method based on CAD
JP2006119917A (en) Process management support system, process management support method, and process management support program
CN117151617B (en) Method and system for checking work receiving party based on part attribute
Fil Business processes engineering for organizing the construction objects’ design

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant