CN111335302A
CN111335302A CN202010226266.3A CN202010226266A CN111335302A CN 111335302 A CN111335302 A CN 111335302A CN 202010226266 A CN202010226266 A CN 202010226266A CN 111335302 A CN111335302 A CN 111335302A
Authority
CN
China
Prior art keywords
prefabricated building
building structure
cage
prefabricated
glue
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010226266.3A
Other languages
Chinese (zh)
Inventor
许顺良
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010226266.3A priority Critical patent/CN111335302A/en
Publication of CN111335302A publication Critical patent/CN111335302A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/24Prefabricated piles
    • E02D5/30Prefabricated piles made of concrete or reinforced concrete or made of steel and concrete
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/14Pile framings, i.e. piles assembled to form the substructure
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/34Foundations for sinking or earthquake territories
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/223Details of top sections of foundation piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/48Piles varying in construction along their length, i.e. along the body between head and shoe, e.g. made of different materials along their length
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/52Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments
    • E02D5/523Piles composed of separable parts, e.g. telescopic tubes ; Piles composed of segments composed of segments
    • E02D5/526Connection means between pile segments
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/58Prestressed concrete piles

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Environmental & Geological Engineering (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention provides a prefabricated building structure, wherein a pre-embedded pipe is arranged in the prefabricated building structure, the pre-embedded pipe is arranged in the middle of the prefabricated building structure, the interior of the pre-embedded pipe is hollow, and a glue storage groove is formed in the end part of the prefabricated building structure. The prefabricated building structure provided by the invention is provided with the embedded pipe, so that the prefabricated building structure is divided into the solid part and the hollow part, the use of raw materials is reduced compared with the existing solid pile, the weight of the prefabricated building structure is reduced, and the manufacturing cost is saved; bearing capacity and life that can improve prefabricated building structure for current hollow pile for prefabricated building structure's application scope is wider.

Description

Prefabricated building structure
Technical Field
The invention relates to the technical field of buildings, in particular to a prefabricated building structure.
Background
In the field of building technology, in order to facilitate production and processing and reduce construction time, a prefabricated building structure is generally manufactured in a factory and then transported to a construction site for use. Most of the existing prefabricated building structures are solid structures or hollow structures, but the solid structures have the problems of overlarge weight, difficulty in transportation, waste of raw materials and the like; on the other hand, although the hollow structure can save raw materials, the earthquake-resistant mechanical property and the durability of the hollow structure cannot be guaranteed, and in addition, in the process that the prefabricated building structure is driven into the ground, sand, stone, soil and the like easily enter gaps among the prefabricated building structures, so that the connection strength of the prefabricated building structures is affected. Therefore, an improved prefabricated building structure is needed, which not only can reduce the weight and save raw materials, but also can improve the connection strength between prefabricated building structures, and ensure the earthquake-resistant mechanical property and durability of the prefabricated building structures.
Disclosure of Invention
In view of the above, there is a need for an improved prefabricated building structure.
The invention provides a prefabricated building structure, wherein a pre-embedded pipe is arranged in the prefabricated building structure, the pre-embedded pipe is arranged in the middle of the prefabricated building structure, the interior of the pre-embedded pipe is hollow, and a glue storage groove is formed in the end part of the prefabricated building structure.
The prefabricated building structure provided by the invention is provided with the embedded pipe, so that the prefabricated building structure is divided into the solid part and the hollow part, the use of raw materials is reduced compared with the existing solid pile, the weight of the prefabricated building structure is reduced, and the manufacturing cost is saved; bearing capacity and life that can improve prefabricated building structure for current hollow pile for prefabricated building structure's application scope is wider. When the prefabricated building structure is buried underground, the central part is located in a depth area (generally 2-15 meters below the foundation) with the highest seismic wave frequency below the foundation, so that the seismic capacity of the prefabricated building structure can be ensured, and the reliability of the prefabricated building structure in service is ensured. And the construction is facilitated, the penetration of a geological soil layer is stronger, the construction speed is higher, the damage rate is lower, the project construction period is facilitated to be saved, and the engineering quality is guaranteed. Meanwhile, underground water or corrosive substances cannot enter the prefabricated building structure, so that the durability of the prefabricated building structure is effectively guaranteed, and the quality safety of the building engineering is guaranteed. In addition, in the construction process, in order to ensure the length of the prefabricated building structure, two or even a plurality of prefabricated building structures are often connected for use. In order to increase the connection strength between the two prefabricated building structures, glue can be applied between the two prefabricated building structures besides the connection by the quick connecting piece. The prefabricated building structure is provided with a glue storage groove at the end part, and can be used for containing an adhesive; glue storage tank can hold more adhesives than smooth tip to, when burying prefabricated building structure underground, because there is pressure differential between underground and the earth's surface, the adhesive that holds in the glue storage tank can spill over and spread to two prefabricated building structure's junction, thereby has strengthened the joint strength between two prefabricated building structure.
In one embodiment of the invention, the area of the bottom wall of the glue storage tank is smaller than or equal to the area of the pattern surrounded by the edge of the glue storage tank on the end face of the prefabricated building structure.
By the arrangement, the speed of the adhesive diffusion can be increased, the adhesive can flow to the end parts of the prefabricated building structures more easily, the abutting area between the prefabricated building structures cannot be reduced, and the connecting strength between the two prefabricated building structures can be greatly improved.
In one embodiment of the invention, the glue storage groove is a square groove, a circular groove, a trapezoidal groove or a conical groove; and/or
The glue storage groove is provided with one or more glue storage grooves.
By the arrangement, the square groove can store more adhesive; the round groove, the trapezoid groove and the conical groove enable the resistance of the adhesive to be small during diffusion, the adhesive can be conveniently diffused to the periphery, and the connection strength between the two prefabricated building structures is improved; and the glue tank or tanks enable the glue stored in the glue tank or tanks to be more easily distributed to the ends of the prefabricated building structure.
In one embodiment of the invention, the glue storage tank is arranged in the center of the end of the prefabricated building structure; or the glue storage groove is annular.
So set up, can be so that the adhesive that stores in the glue storage groove can be even distribute to prefabricated building structure tip for two prefabricated building structures when the butt joint installation, the bonding of prefabricated building structure tip each department is even, can improve prefabricated building structure's joint strength.
In one embodiment of the invention, the glue storage tank has a depth of 1mm to 200mm in the axial direction of the prefabricated building structure.
So set up, can enough hold more adhesive, can not make prefabricated building structure's intensity reduce again to the adhesive in the glue storage tank of being convenient for spills over and spreads to two prefabricated building structure's the connection face on, has strengthened the leakproofness of connecting the face.
In one embodiment of the present invention, the prefabricated building structure further comprises a first cage disposed within the prefabricated building structure, the first cage enclosing the embedded pipe.
So set up, first cage body can increase substantially prefabricated building structure's intensity for prefabricated building structure's application scope is more extensive.
In an embodiment of the present invention, a second cage is further disposed in the prefabricated building structure, the second cage is disposed at an end of the embedded pipe in the axial direction, and the second cage is accommodated in the first cage.
So set up, the local reinforcement rate of solid portion has been improved in the setting of the second cage body for vertical atress ability and anti-shear force ability do not fall the adverse rise for solid prefabricated building structure, improve prefabricated building structure's tensile ability, compressive capacity, shock resistance and durability.
In one embodiment of the invention, said second cage is connected to said pre-buried pipe; or, the second cage is connected to the first cage; or, prefabricated building structure still includes the mounting panel, the mounting panel sets up the tip of embedded pipe axial direction, the second cage body is connected in the mounting panel.
According to the arrangement, the second cage body can be provided with multiple fixing modes, one end, far away from the end part of the prefabricated building structure, of the second cage body extends to the embedded pipe and is connected with the embedded pipe, and the second cage body is connected to the embedded pipe to enable the second cage body to be fixed;
in one embodiment of the present invention, the prefabricated building structure further comprises an embedded connector, the first cage extends to an end of the prefabricated building structure, and the embedded connector is arranged at the end of the first cage; and/or the second cage body extends to the end part of the prefabricated building structure, and the embedded connecting piece is arranged at the end part of the second cage body.
So set up, when the building construction, prefabricated building structure usually need with another prefabricated building structure amalgamation in order to prolong prefabricated building structure's length, perhaps pour the cushion cap behind prefabricated building structure's top connecting reinforcement in order to undertake superstructure load. The embedded connecting pieces are arranged on the first cage body or the second cage body, so that the combination rate between the two prefabricated building structures can be increased; or the reinforcement ratio of the bearing platform is improved, the connection mode between the prefabricated building structure and the bearing platform is simplified, the force transmission link in the stress process is reduced, the integral vertical stress capacity of the prefabricated building structure is improved, and the mechanical property of the prefabricated building structure and the bearing platform is guaranteed.
In one embodiment of the invention, corner protectors are provided on the peripheral wall of the end of the prefabricated building structure; the corner protector sleeve comprises a positioning ring, and the positioning ring is positioned at the end part of the corner protector sleeve and is fixedly connected to the first cage body; and/or, the prefabricated building structure further comprises a positioning rib, and the positioning rib is fixedly connected with the first cage body and the corner protection sleeve.
So set up, the position relatively fixed between angle bead cover and the location muscle, the shaping of prefabricated building structure of not only being convenient for can also strengthen prefabricated building structure's intensity, prevents that prefabricated building structure angle bead cover from taking place deformation when being in active service.
Drawings
FIG. 1 is a schematic view of a prefabricated building structure according to a first embodiment of the present invention;
FIG. 2 is a cross-sectional view of the prefabricated building structure of FIG. 1 taken along section A-A;
FIG. 3 is a cross-sectional view of the prefabricated building structure of FIG. 1 taken at section B-B;
FIG. 4 is a schematic view of the use of the pre-buried connector shown in FIG. 1;
FIG. 5 is a schematic diagram of a quick docking assembly according to one embodiment;
FIG. 6 is a schematic structural view of a quick docking assembly according to another embodiment;
FIG. 7 is a schematic view of a prefabricated building structure according to a second embodiment of the present invention;
fig. 8 is a schematic view of a prefabricated building structure according to a third embodiment of the present invention;
FIG. 9 is an enlarged view taken at X in FIG. 1;
FIG. 10 is a schematic view of a corner protector according to a fourth embodiment of the present invention;
fig. 11 is a schematic view of a prefabricated building structure according to a fifth embodiment of the present invention;
fig. 12 is a schematic view of a prefabricated building structure according to a sixth embodiment of the present invention;
FIG. 13 is a schematic view of the use of two prefabricated building structures in abutting joint;
FIG. 14 is an enlarged view at Y of FIG. 13;
FIG. 15 is a schematic view of a retaining ring of the prefabricated building structure of FIG. 13;
FIG. 16 is a schematic view of a partially prefabricated building structure according to a seventh embodiment of the present invention;
FIG. 17 is a schematic view of a prefabricated building structure and a cap;
fig. 18 is a partially enlarged view of a portion C shown in fig. 17.
100. Prefabricating a building structure; 10. a hollow portion; 20. a solid portion; 30. a first cage; 40. a second cage; 31. a first axial rib body; 32. a first radial rib; 41. a second axial rib; 42. a second radial rib body; 50. mounting a plate; 60. a corner protecting sleeve; 61. a positioning ring; 70. pre-burying a connecting piece; 80. pre-burying a pipe; 90 glue storage tank; 21. positioning ribs; 311. heading; 71. a constriction; 72. an annular projection; 101. chamfering; 111. a first hoop section; 112. a second hoop section; 1011. an insertion block; 1012 inserting grooves; 200. a quick docking assembly; 210. a first insert table; 211. a first fixed part; 212. a first insertion part; 213. a first extension portion; 214. a first step surface; 220. a first base; 221. a second fixed part; 222. a fin; 230. a second insert table; 231. a third fixed part; 232. a second insertion part; 233. a first groove; 240. a second base; 241. a first end face; 242. a second end face; 250. looping; 400. a bearing platform; 410. force transmission rib body.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
It will be understood that when an element is referred to as being "mounted on" another element, it can be directly mounted on the other element or intervening elements may also be present. When a component is referred to as being "disposed on" another component, it can be directly on the other component or intervening components may also be present. When an element is referred to as being "secured to" another element, it can be directly secured to the other element or intervening elements may also be present.
The prefabricated building structure 100 refers to various prefabricated building structures which are manufactured in advance and then transported to a construction site for use. The prefabricated building structure 100 may be produced centrally in a factory or prefabricated around a site. The axial length and the radial circumference of the prefabricated building structure 100 can be made as required, and the reinforcement ratio can be designed according to the stress during the transportation, hoisting and pressing of the pile, so that the flexibility is high. In addition, the prefabricated building structure 100 belongs to soil-squeezing piles, so that the cross-sectional area of the bearing platform 400 is effectively saved, the construction cost is saved, the penetration of a geological soil layer during construction is facilitated, the construction speed is high, the damage rate is lower, the project construction period is facilitated to be saved, and the engineering quality is guaranteed.
The present invention provides a prefabricated building structure 100 for use in a foundation building in the field of construction technology. In this embodiment, the prefabricated building structure 100 is used to prefabricate a vertically stressed pile. It is understood that in other embodiments, the prefabricated building structure 100 may also be used in other engineering fields, such as fabricated buildings, etc., and may also be used for horizontal load-bearing piles or composite load-bearing piles, etc.
Most of the existing prefabricated building structures are solid structures or hollow structures, but the solid structures have the problems of overlarge weight, difficulty in transportation, waste of raw materials and the like; on the other hand, although the hollow structure can save raw materials, the shock resistance mechanical property and durability of the hollow structure cannot be guaranteed.
Referring to fig. 1, fig. 1 is a schematic view illustrating a prefabricated building structure according to a first embodiment of the present invention.
The invention provides a prefabricated building structure 100, wherein a pre-embedded pipe 80 is arranged in the prefabricated building structure 100, the pre-embedded pipe 80 is arranged in the middle of the prefabricated building structure 100, the interior of the pre-embedded pipe 80 is hollow, and a glue storage groove 90 is formed in the end part of the prefabricated building structure 100.
The prefabricated building structure 100 provided by the invention is provided with the embedded pipe 80, so that the prefabricated building structure 100 is divided into the solid part 20 and the hollow part 10, the use of raw materials is reduced compared with the existing solid pile, the weight of the prefabricated building structure 100 is reduced, and the manufacturing cost is saved; compared with the existing hollow pile, the bearing capacity and the service life of the prefabricated building structure 100 can be improved, so that the application range of the prefabricated building structure 100 is wider; when the prefabricated building structure 100 is buried underground, the central part is located in a depth area (generally 2 meters to 15 meters below the foundation) with the highest seismic wave frequency below the foundation, so that the seismic capacity of the prefabricated building structure 100 can be ensured, and the reliability of the prefabricated building structure 100 in service is ensured. And the construction is facilitated, the penetration of a geological soil layer is facilitated, the construction speed is higher, the damage rate is lower, the project construction period is facilitated to be saved, and the engineering quality is guaranteed. Meanwhile, underground water or corrosive substances cannot enter the prefabricated building structure 100, so that the durability of the prefabricated building structure 100 is effectively guaranteed, and the quality safety of the building engineering is guaranteed. In addition, in order to ensure the length of the prefabricated building structure during the construction process, two or even a plurality of prefabricated building structures 100 are often connected for use. In order to increase the strength of the connection between the two prefabricated building structures 100, glue may be applied between the two prefabricated building structures 100, in addition to the quick connection. The prefabricated building structure 100 of the invention is provided with a glue storage groove 90 at the end part, and can be used for connecting other structures and/or containing adhesives; glue storage tank 90 can hold more adhesives than the smooth tip to, when burying prefabricated building structure underground, because there is pressure differential between underground and the earth's surface, the adhesive that holds in glue storage tank 90 can spill over and spread to the junction of two prefabricated building structures 100, thereby has strengthened the joint strength between two prefabricated building structures 100.
It is understood that the pre-buried pipe 80 may be disposed at the midpoint of the prefabricated building structure 100, or may be partially offset, and may be selected differently according to actual needs; the embedded pipe 80 can be a metal pipe, a plastic pipe or a ceramic pipe; the embedded pipe 80 can also be a pipe member arranged in other shapes, such as a circular pipe, a corrugated pipe or other polygonal prism; the interior of the embedded pipe 80 may be hollow, or may be filled with a foam material, concrete, a cushion material, or the like.
So set up, can so that prefabricated building structure 100 bearing capacity improves, can satisfy the demand of different operating modes, when satisfying the shock strength requirement and the durability of reality, also reduced the use of raw and other materials, alleviateed prefabricated building structure 100 self weight to the cost of manufacture has been saved.
In one embodiment, the prefabricated building structure 100 is a square pile having a chamfer 101.
In one embodiment of the invention, chamfer 101 is a fillet.
Due to the arrangement of the round corners, coarse aggregates (such as stones) in the raw materials are not easy to concentrate at the edges and corners during pile forming, mortar is distributed more uniformly, and the strength of concrete is higher; the pile is not easy to damage when being hung out of the die after being formed, and the integrity of the pile body is effectively protected; during transportation and construction, the fillet has strong capacity of resisting collision, and stress concentration is not easy to generate; during construction, when the pile body enters the soil, the destructive effect on the soil body can be greatly reduced, the soil body can rebound, and the effect that the soil body exerts friction resistance on the side surface of the prefabricated building structure 100 is ensured.
In one embodiment of the invention, the radius of the rounded corners is 1mm to 100 mm.
Preferably, the radius of the rounded corners is 10mm to 70 mm.
So set up, the radius of fillet is applicable to common square pile model in this within range, and processing is simple and convenient, easy to carry out.
It is understood that in other embodiments, chamfer 101 may also be other common shapes, such as a beveled shape.
In one embodiment, the radius of the chamfer 101 is 1/100 to 1/10 of the minor side length of the cross-section of the prefabricated building structure 100 in its radial direction.
With the arrangement, the occupation ratio of the chamfer 101 can play roles in homogenizing raw materials, preventing damage and increasing friction resistance in the range, and the strength of the prefabrication with the help of the structure cannot be influenced.
In one embodiment of the present invention, the prefabricated building structure 100 is a square pile.
By the arrangement, the square pile has large outer surface area and is square or polygonal, and the repose angle between the pile body and the soil in the soil layer is much larger than that of a round outer surface, so that the hollow square pile can obtain larger bearing capacity than a tubular pile under the same geological conditions, and a large amount of basic funds are saved for engineering; by contrast, the bearing capacity of the square pile is larger, and the manufacturing cost of the bearing capacity per kilo-newton (KN) is lower than that of the prestressed concrete pipe pile, so that a designer can prefer the square pile under the same design bearing capacity, and the fund is saved; the theoretically calculated shearing resistance of the square pile is 2-3 times of that of the equivalent tubular pile, which shows that the square pile has excellent seismic performance and is suitable for building foundations of areas with multiple earthquakes, high-rise buildings and large-area basements; the local hollow square pile inherits and develops the characteristic of low construction breakage rate of the original concrete square pile, and the high-strength concrete is matched with the square head, so that the high-strength concrete has better impact resistance and much lower pile head breakage rate than the tubular pile.
In one embodiment of the present invention, the area of the bottom wall of the glue storage tank 90 is smaller than or equal to the area of the pattern surrounded by the edge of the glue storage tank 90 on the end face of the prefabricated building structure 100.
With this arrangement, the speed of the adhesive diffusion can be increased, so that the adhesive can more easily flow to the end of the prefabricated building structures 100, and the connection strength between two prefabricated building structures 100 can be greatly increased without reducing the contact area between the prefabricated building structures 100.
In one embodiment, the surface of the glue storage tank 90, which is formed by the end of the glue storage tank 90 far away from the prefabricated building structure 100 and the prefabricated building structure 100, is the bottom wall of the glue storage tank 90, and the area of the bottom wall is smaller than the area of the pattern surrounded by the edge of the glue storage tank 90 on the end surface of the prefabricated building structure 100.
It is understood that in other embodiments, the adhesive may be stored in other patterns of adhesive storage tanks 90, so long as the adhesive is easily distributed between the two prefabricated building structures 100.
In one embodiment of the invention, the glue tank 90 is arranged in the center of the end of the prefabricated building structure 100; alternatively, the glue storage tank 90 is annular.
So set up, can make the adhesive that stores in glue storage tank 90 can be even distribute to prefabricated building structure 100 tip for two prefabricated building structures 100 when butt joint installation, the bonding of prefabricated building structure 100 tip everywhere is even, can improve prefabricated building structure 100's joint strength.
In one embodiment of the present invention, the glue storage tank 90 is a square tank, a circular tank, a trapezoidal tank or a tapered tank.
By the arrangement, the square groove can store more adhesive; the circular groove, the trapezoidal groove and the conical groove enable the resistance of the adhesive to be small when the adhesive is diffused, the adhesive can be conveniently diffused all around, and the connection strength between the two prefabricated building structures 100 is improved.
Specifically, the trough shape of the glue storage trough 90 may be rectangular, spherical, conical, etc., which are not listed here. It is understood that in other embodiments, the glue reservoir 90 may have other shapes as long as it is capable of storing glue.
In one embodiment of the present invention, one or more glue reservoirs 90 are provided.
With this arrangement, the adhesive stored in the adhesive storage tank 90 can more easily flow to the end of the prefabricated building structure 100, thereby improving the connection strength between the two prefabricated building structures 100.
In one embodiment of the present invention, the glue storage tank 90 has a depth of 1mm to 200mm in the axial direction of the prefabricated building structure 100.
So set up, can enough hold more adhesive, can not make prefabricated building structure's intensity reduce again to be convenient for store up the adhesive in the gluey groove 90 and spill over and spread to two prefabricated building structure 100 be connected the face on, strengthened the leakproofness of being connected the face.
In one embodiment, a glue coating (not shown) is also provided between two prefabricated building structures 100. The glue coating layer fills the gap between the two prefabricated building structures 100 and the gap between the prefabricated building structures 100 and the quick butt joint component 200, prevents water or oxygen from corroding the first cage body 30, the second cage body 40 and the quick butt joint component 200 after being immersed, and increases the corrosion resistance of the components; after the glue coating layer is cured, the two prefabricated building structures 100 can be shaken or rotated, the rapid butt joint assembly and the prefabricated building structures 100 can be prevented from shaking or rotating, and the stability of the prefabricated building structures 100 is improved; the cured glue coating layer can bear the force, so that the two prefabricated building structures 100 are combined more tightly and firmly, and the stress performance is better; in addition, the glue coating layer can also play a role in uniform stress after being cured, even if the situation that the stress is slightly uneven exists between the two prefabricated building structures 100 or between the prefabricated building structures 100 and the quick butt joint assembly 200, the cured glue coating layer can also balance the stress, the vertical stress capacity of the prefabricated building structures 100 is improved, and the service life of the prefabricated building structures 100 is prolonged.
In one embodiment, the adhesive is in a colloidal state, has certain fluidity and cannot be lost when being applied.
It is understood that in other embodiments, the adhesive may also be in the form of a paste or water, as long as the adhesive effect is achieved.
In one embodiment of the invention, the adhesive is a two-fluid hybrid cured adhesive (AB adhesive).
So set up, AB glue has that warehousing and transportation performance is good, uses more in a flexible way, and bonding strength is high, has advantages such as good vertical atress performance after the solidification.
In one embodiment of the invention, the adhesive is an epoxy.
According to the arrangement, the epoxy resin has strong adhesive force, the chemical structure of the epoxy resin contains aliphatic hydroxyl, ether and extremely active epoxy groups, and the hydroxyl and the ether have high polarity, so that the epoxy resin has strong adhesive force, and the epoxy resin can firmly bond concrete, stone and various metal materials; the epoxy resin AB glue can be prepared into glue with different viscosities, the curing degree of the AB glue can be adjusted through normal-temperature curing, heating curing and other modes, and the curing time can be controlled within minutes to hours; in addition, the epoxy resin AB glue has good performance, and the cured epoxy resin AB glue has good performance, high mechanical strength, yellowing resistance, medium resistance, long aging resistance time, good electrical insulation, water resistance and moisture resistance and small volume shrinkage; the epoxy resin AB glue is nontoxic, has no three-waste emission in production, does not bring harm to the environment when in use, and meets the requirement of environmental protection; in addition, the epoxy resin AB glue has wide and easily available sources, low price and low cost.
FIG. 2 is a cross-sectional view of the prefabricated building structure of FIG. 1 taken along section A-A; fig. 3 is a cross-sectional view of the prefabricated building structure shown in fig. 1, taken along section B-B.
In one embodiment of the present invention, the prefabricated building structure 100 further comprises a first cage 30, the first cage 30 being disposed within the prefabricated building structure 100, the first cage 30 enclosing the pre-buried pipe 80.
So set up, first cage 30 can increase substantially prefabricated building structure 100's intensity for prefabricated building structure 100's application scope is more extensive.
In one embodiment, the first cage 30 comprises a first radial rib 32 and a plurality of first axial ribs 31, the plurality of first axial ribs 31 forming a framework of the first cage 30, the first radial rib 32 spirally surrounding the framework of the first cage 30; the first radial rib 32 is fixedly connected with the first axial rib 31.
With the arrangement, the first cage body 30 has high bearing strength and simple processing, and only the first radial rib bodies 32 are wound on the frame formed by the first axial rib bodies 31 while the plurality of first axial rib bodies 31 are axially conveyed, so that the working hours are saved; and the number of turns and the encryption length that first radial muscle body 32 spirals around can be increased at the position that the atress degree is great as required for first cage 30, for example increase the number of turns and the encryption length that first radial muscle body 32 spirals around at the both ends of first cage 30, prevent that prefabricated building structure 100 from suffering destruction because of the atress is too big when burying underground.
It is understood that, in other embodiments, the first radial rib 32 and the first axial rib 31 may be fixed by welding, clamping, binding, etc., which are not listed here.
In one embodiment, the first axial reinforcement 31 is made of at least one of a steel bar for prestressed concrete (PC steel bar), a stainless steel bar, a hot rolled steel bar, a medium strength prestressed wire, a stress relief wire, a stranded wire, and a prestressed twisted steel; and/or the presence of a catalyst in the reaction mixture,
the first radial rib 32 is made of at least one of a steel bar for prestressed concrete (PC steel bar), a stainless steel bar, a hot rolled steel bar, a medium strength prestressed wire, a stress-relief wire, a strand, a prestressed twisted steel, a low carbon hot rolled steel disc strip, and a cold drawn low carbon wire for concrete products.
The shape of the outer edge of the cross section of the first cage 30 is circular or polygonal, and the polygonal shape is triangular, square/rectangular, pentagonal, hexagonal, etc., which are not listed here.
In one embodiment of the present invention, a second cage 40 is further disposed in the prefabricated building structure 100, the second cage 40 is disposed at an end of the embedded pipe 80 in the axial direction, and the second cage 40 is received in the first cage 30.
So set up, the local reinforcement rate of solid portion has been improved in the setting of second cage 40 for vertical atress ability and anti-shear force ability do not fall and rise for solid prefabricated building structure 100, improve prefabricated building structure 100's tensile ability, compressive capacity, shock resistance and durability.
It is understood that in other embodiments, only the first cage 30 and not the second cage 40 may be disposed in the prefabricated building structure 100, that is, both ends of the embedded pipe 80 are plain concrete; the second cage 40 can be arranged at one end of the embedded pipe 80, and can also be arranged at two ends of the embedded pipe 80; when the second cages 40 are provided at both ends of the embedded pipe 80, the lengths of the two second cages 40 may be the same or different, and the specific configurations of the two second cages 40 may be the same or different.
The shape of the outer edge of the cross section of the second cage 40 is circular or polygonal, and the polygonal shape is triangular, square, rectangular, pentagonal, hexagonal, etc., which are not listed here.
With the arrangement, the second cages 40 in different shapes can be designed according to the practical application and the corresponding stress condition of the prefabricated building structure 100, so as to achieve different force bearing effects.
In one embodiment, second cage 40 comprises second radial ribs 42 and a plurality of second axial ribs 41, second axial ribs 41 being arranged along the axial direction of prefabricated building structure 100; the second axial ribs 41 form a framework of the second cage 40, the second radial ribs 42 spirally surround the framework of the second cage 40, and the second radial ribs 42 are fixedly connected with the second axial ribs 41.
Due to the arrangement, the second cage body 40 is simple and convenient in processing method and easy to produce, and meanwhile, the second axial rib body 41 and the second radial rib body 42 are combined, so that the strength of the second cage body 40 is improved, the bearing capacity in the using process is improved, and the second cage body is not easy to deform.
It is understood that the second radial rib 42 and the second axial rib 41 can be fixed by welding, clamping, binding, etc., which are not listed here.
The second cage body 40 and the first cage body 30 are simple and convenient in processing method and easy to produce, and meanwhile, the binding force between the axial rib bodies and the radial rib bodies is strong, so that the cage body is high in strength and not easy to deform in the using process.
In one embodiment, the second axial rib body 41 is made of at least one of deformed steel bars, steel bars for prestressed concrete (PC steel bars), stainless steel bars, hot rolled steel bars, medium strength prestressed wires, stress relief wires, steel strands, and prestressed deformed steel bars; and/or the presence of a catalyst in the reaction mixture,
the second radial rib 42 is made of at least one of deformed steel bars, prestressed concrete steel bars (PC steel bars), stainless steel bars, hot-rolled steel bars, medium-strength prestressed steel wires, stress-relief steel wires, steel strands, prestressed twisted steel bars, low-carbon steel hot-rolled disc strips, and cold-drawn low-carbon steel wires for concrete products.
In one embodiment of the present invention, the prefabricated building structure 100 further comprises an embedded connector 70, the first cage 30 extends to an end of the prefabricated building structure 100, and the embedded connector 70 is disposed at the end of the first cage 30; and/or the second cage 40 extends to the end of the prefabricated building structure 100, and the embedded connector 70 is arranged at the end of the second cage 40.
So configured, during building construction, the prefabricated building structure 100 is usually spliced with another prefabricated building structure 100 to extend the length of the prefabricated building structure 100, or a bearing platform 400 is poured after connecting the reinforcing bars at the top of the prefabricated building structure 100 to bear superstructure load. The embedded connecting piece 70 is arranged on the first cage body 30 or the second cage body 40, so that the combination rate between the two prefabricated building structures 100 can be increased; or the reinforcement ratio of the bearing platform 400 is improved, the connection mode between the prefabricated building structure 100 and the bearing platform 400 is simplified, the force transmission link in the stress process is reduced, the integral vertical stress capacity of the prefabricated building structure 100 is improved, and the mechanical property of the prefabricated building structure 100 and the bearing platform 400 is guaranteed.
Fig. 4 is a schematic view illustrating the use of the embedded connector 70 shown in fig. 1, and as shown in fig. 4, in one embodiment, the embedded connector 70 has an internal thread, the first axial rib 31 and/or the second axial rib 41 has an external thread, and the first axial rib 31 and/or the second axial rib 41 is connected with the embedded connector 70 through a thread.
In one embodiment, the pre-embedded connector 70 has a contraction opening 71 for connecting with the second axial rib 41 or the first axial rib 31; the end of the second axial rib 41 or the first axial rib 31 connected with the embedded connector 70 is provided with an upset 311, and the contraction opening 71 is used for limiting the upset 311.
In one embodiment of the present invention, the embedded connector 70 is further protruded with an annular protrusion 72 on the outer circumferential wall relatively near the end of the prefabricated building structure 100. Preferably, the outer diameter of the annular protrusion 72 is gradually reduced from the end part of the embedded connector 70 to the middle part; the outer peripheral wall of the annular projection 72 is an arc surface.
With such an arrangement, the annular protrusion 72 can homogenize the prestress, so that the prestress which can be borne by the second cage 40 and/or the first cage 30 during the pre-stretching is larger, and the damage of the pre-buried connecting piece 70 is prevented.
It should be noted that the embedded connectors 70 in the two prefabricated building structures 100 may be of the same type or different types, and may be selected according to the working conditions.
In one embodiment of the present invention, the embedded connector 70 is formed together with the prefabricated building structure 100. It is understood that in other embodiments, the pre-embedded connectors 70 may be later connected to the second cage 40 or the first cage 30. The operation steps are that firstly, the concrete at the end part of the prefabricated building structure 100 is chiseled to expose the first axial rib body 31 or the second axial rib body 41, then the embedded connecting piece 70 is connected to the end part of the first axial rib body 31 or the second axial rib body 41, and then the end part of the first axial rib body 31 or the second axial rib body 41 is formed with an upset 311 through hot working, so that the connection is completed.
The prefabricated building structures 100 may be used not only alone, but in combination with a plurality of prefabricated building structures 100. For example, two, three, four or even more prefabricated building structures 100 may be docked for use as required by the operating conditions.
In one embodiment, the first cage 30 of each of the two prefabricated building structures 100 is provided with a quick connector, and the two quick connectors can be connected by a quick docking assembly 200 to extend the length of the prefabricated building structure 100.
In one embodiment, the quick docking assembly 200 is a ferrous metal. Preferably, the quick dock assembly 200 is carbon steel or alloy steel. Specifically, the quick butt joint assembly 200 is carbon steel, chromium vanadium steel, chromium nickel steel, chromium molybdenum steel, chromium nickel molybdenum steel, chromium manganese silicon steel, ultra-high strength steel or stainless steel. It is understood that in other embodiments, the quick dock assembly 200 may be constructed of other materials.
Referring to fig. 5, fig. 5 is a schematic structural diagram of a quick docking assembly 200 according to an embodiment.
The quick docking assembly 200 in the first embodiment includes a first docking station 210 and a first base 220, the first docking station 210 includes a first fixing portion 211, a first inserting portion 212 and a first extending portion 213 located between the first fixing portion 211 and the first inserting portion 212, the first base 220 includes a second fixing portion 221 and a plurality of fins 222 connected to the second fixing portion 221, the first docking station 210 is connected to the quick connector of one of the prefabricated building structures 100 through the first fixing portion 211, and the first base 220 is connected to the quick connector of another prefabricated building structure 100 through the second fixing portion 221; the first plug part 212 is convexly arranged on the first extension part 213, and a first step surface 214 is formed between the first plug part 212 and the first extension part 213; the plurality of fins 222 are arranged around each other; the first inserting stage 210 can pass through the openings defined by the plurality of fins 222 through elastic expansion of the fins 222, the fins 222 can elastically contract and enclose the first extending portion 213, and the end surfaces of the fins 222 and the first step surface 214 of the first inserting stage 210 are oppositely arranged.
In this embodiment, the rapid docking assembly 200 is used in a process that the first socket 210 is connected to the embedded connector 70 in one prefabricated building structure 100 through the first fixing portion 211, the first base 220 is connected to the embedded connector 70 in the other prefabricated building structure 100 through the second fixing portion 221, the first inserting portion 212 and the first extending portion 213 of the first socket 210 extend into the inner wall of the first base 220 and move along the inserting direction α, the first inserting portion 212 of the first socket 210 applies pressure to the fin 222 so that the fin 222 elastically expands until the first inserting portion 212 passes through the fin 222, the fin 222 elastically contracts and encloses the first extending portion 213 at the moment when the first inserting portion 212 passes through the fin 222, and when a force in a direction opposite to the inserting direction α is applied to the first socket 210, the end of the fin 222 abuts against the first step surface 214 between the first inserting portion 212 and the first extending portion 213 and limits the first socket 210.
The rapid docking assembly 200 and the embedded connector 70 provided by the embodiment are simple and convenient to mount, after the first plugging portion 212 of the first plugging platform 210 is inserted into the first base 220, the fin 222 can elastically contract and close the extension portion of the first base 220, the end portion of the fin 222 abuts against the step surface of the first plugging platform 210, and the abutting surface between the end portion of the fin 222 and the first step surface 214 of the first plugging platform 210 is approximately annular, so that the abutting area is large, the joint strength between two prefabricated building structures 100 can be ensured, and particularly, the vertical stress performance is greatly improved; the fins 222 not only can enclose the first extension part 213 of the insert table, but also can limit the first extension part 213, and prevent the first extension part 213 from shaking in the radial direction. In addition, the rapid docking assembly 200 provided by the embodiment has the advantages of simple processing technology, low cost and wide application range.
Referring to fig. 6, fig. 6 is a schematic structural diagram of another embodiment of a quick docking assembly 200.
The quick docking assembly 200 of the second embodiment includes a second socket 230, a second base 240 and a ring buckle 250, wherein the second socket 230 includes a third fixing portion 231 and a second plugging portion 232 disposed oppositely, and the second plugging portion 232 is formed with a first groove 233; the second base 240 includes a first end surface 241 and a second end surface 242 which are oppositely arranged; the ring buckle 250 has an opening (not shown) and can be elastically contracted, and the ring buckle 250 is sleeved on the second insert stage 230 and accommodated in the first groove 233; the ring buckle 250 can be inserted into the second base 240 along the insertion direction together with the second insertion portion 232 of the second socket 230, and the ring buckle 250 can abut against the second end surface 242 of the second base 240 through elastic expansion and limit the reverse movement of the second socket 230 along the insertion direction.
After the second inserting portion 232 of the second inserting stage 230 is inserted into the second base 240, the ring buckle 250 can be ejected out of the first groove 233 through the elastic expansion portion and abuts against the second end face 242 of the second base 240, an abutting surface between the ring buckle 250 and the second end face 242 is approximately annular, an abutting area is large, the joint strength between two embedded connectors 70 can be ensured, and particularly, the vertical stress performance is greatly improved. In addition, the rapid docking assembly 200 provided by the embodiment has the advantages of simple processing technology, low cost and wide application range.
It is understood that the insertion direction α may be, but is not limited to, the above-described directions, and that even partial angular offsets are intended to be within the scope of the present invention.
In one embodiment, after the two prefabricated building structures 100 are butted, a corner protector 60 is disposed on the peripheral wall of the junction between the two prefabricated building structures, and the corner protector 60 is used for fastening the butted portion of the two prefabricated building structures 100 to prevent the two prefabricated building structures 100 from being dislocated during use or service.
It is understood that the two prefabricated building structures 100 may be the same prefabricated pile or different prefabricated piles; the pile can be a solid pile, a hollow pile or a local hollow pile; can be a square pile or a tubular pile.
In one embodiment of the invention, the second cage 40 is connected to the pre-buried pipe 80; alternatively, the second cage 40 is connected to the first cage 30; or, the prefabricated building structure 100 further includes a mounting plate 50, the mounting plate 50 is disposed at an end of the embedded pipe 80 in the axial direction, and the second cage 40 is connected to the mounting plate 50. So set up for the fixed mode of second cage 40 has more selectivity, can select according to operating condition.
Referring to fig. 1, in one embodiment of the present invention, the end of the second cage 40 remote from the end of the prefabricated building structure 100 extends to the embedded pipe 80 and is connected with the embedded pipe 80.
So set up, the second cage 40 is connected in the embedded pipe 80 and not only can make the second cage 40 fixed, but also can improve the joint strength of the second cage 40, can prevent the second cage 40 from taking place deformation and dislocation in the in-service process.
Specifically, the embedded pipe 80 is a metal pipe, and the second cage body 40 is connected with the embedded pipe 80 by welding.
Referring to fig. 7, fig. 7 is a schematic view of a prefabricated building structure 100 according to a second embodiment of the present invention;
in one embodiment of the present invention, the second cage 40 is connected to the first cage 30 such that the second cage 40 is integrally connected to the first cage 30.
So set up, second cage 40 is connected in first cage 30, not only can improve the yield strength of second cage 40, can improve the joint strength and the bearing capacity of prefabricated building structure 100 moreover.
Specifically, the second cage 40 is locally and flexibly connected with the first cage 30 through binding steel bars.
Referring to fig. 8, fig. 8 is a schematic view of a prefabricated building structure 100 according to a third embodiment of the present invention;
in one embodiment of the present invention, the prefabricated building structure 100 further includes a mounting plate 50, the mounting plate 50 is disposed at an end of the embedded pipe 80 in the axial direction, and the second cage 40 extends to the mounting plate 50 and is connected to the mounting plate 50.
So set up, the second cage body 40 is connected and can also be in mounting panel 50, not only can make the second cage body 40 fixed, prevents that the second cage body 40 from warping and misplacing at the in-service in-process, can also share the power that the second axial muscle body 41 bore, increases prefabricated building structure 100's bearing capacity and wholeness.
Specifically, the mounting plate 50 is a steel plate. The second cage 40 is welded to the mounting plate 50.
In one embodiment of the present invention, the prefabricated building structure 100 further includes corner protectors 60, the corner protectors 60 being provided on the outer circumferential wall of the end of the prefabricated building.
With such an arrangement, the prefabricated building structure 100 can be prevented from falling off the concrete on the end of the prefabricated building structure 100 during the process of being buried underground or in service, so that the first cage 30 or the second cage 40 is exposed to corrosion, and the strength of the prefabricated building structure 100 is reduced.
In one embodiment of the present invention, as shown in fig. 9 and 12, fig. 9 is an enlarged view at X shown in fig. 1; FIG. 10 is a schematic view of a corner protector according to a fourth embodiment of the present invention; fig. 11 is a schematic view of a prefabricated building structure according to a fifth embodiment of the present invention; fig. 12 is a schematic view of a prefabricated building structure according to a sixth embodiment of the present invention.
The corner protector 60 includes at least one first hoop section 111 depressed toward the axial direction of the prefabricated building structure 100, and at least one second hoop section 112 protruded outwardly with respect to the first hoop section 111, and the first hoop section 111 is spaced apart from the second hoop section 112.
With such an arrangement, the corner protector 60 can be prevented from being displaced relative to the prefabricated building structure 100 during production, and the fixing performance is good; in addition, redundant concrete residual slurry can be removed from the die along with the corner protection sleeve 60 during production, so that the die is convenient to clean and maintain; the corner protection sleeve 60 can wrap the end part of the prefabricated building structure 100, so that the surface of the prefabricated building structure 100 is smoother and tidier, and concrete at the end part of the prefabricated building structure 100 can be protected from falling off when the prefabricated building structure 100 is used; because the angle bead cover 60 has wrapped the tip of prefabricated building structure 100, can make when filling the concrete vibrate more fully, prefabricated building structure 100's breakage rate is lower, and the prefabricated building structure 100 who makes is high, of high quality. When the prefabricated building structure 100 is buried in a soil body, the inward-concave first hoop section 111 can increase the wrapping force of the rebounded soil body, and is beneficial to transferring the bearing force of the prefabricated building structure 100 to the soil body, so that the bearing force of a single pile is improved; when the prefabricated building structure 100 is used for supporting the platform 400, the concave first hoop section 111 can increase the engaging force of the prefabricated building structure 100 and the concrete in the platform 400, which is beneficial for the force borne by the platform 400 to be transferred to the prefabricated building structure 100, thereby increasing the bearing capacity and integrity of the platform 400.
In one embodiment of the present invention, the first and second hoop sections 111 and 112 extend in the circumferential direction of the prefabricated building structure 100.
By the arrangement, the engaging force between the prefabricated building structure and the soil body or between the prefabricated building structure 100 and the bearing platform 400 can be increased, and the bearing capacity of the prefabricated building structure 100 is improved.
In one embodiment of the present invention, the first and second hoop sections 111 and 112 are both annular.
With such an arrangement, the prefabricated building structure 100 is less likely to generate stress concentration, which affects the use strength thereof. And the processing method is simple and the cost is low.
It is understood that the first hoop section 111 may be one circular groove, or a plurality of circular grooves may be uniformly arranged along the axial direction of the prefabricated building structure 100, or a plurality of square/circular/irregular grooves may be uniformly arranged along the radial direction of the prefabricated building structure 100, as long as the anchoring effect is achieved.
In one embodiment of the present invention, the width of the first cuff section 111 is 1mm to 100mm, and/or the depth of the first cuff section 111 is 0.1mm to 50 mm. It is understood that the width of the first hoop section 111 herein refers to the width of the first hoop section 111 that is concave in the axial direction of the prefabricated building structure 100; the depth of the first hoop section 111 refers to the depth of the first hoop section 111 that is concave in the radial direction of the prefabricated building structure 100.
So set up, neither can influence prefabricated building structure 100's bearing capacity, can make again to have higher snap-in force between prefabricated building structure 100 and the soil body to processing technology is simple, is favorable to the outflow of mix water in the concrete during production.
In one embodiment of the invention, the outer edge of the cross-section of the second hoop section 112 is the same as the outer edge of the cross-section of the prefabricated building structure 100.
So set up, prefabricated building structure 100 is the same with the biggest external diameter of angle bead cover 60 among the prefabricated building structure 100, can not produce the hindrance when burying the soil body to do not have unnecessary edges and corners in the mould of the prefabricated building structure 100 that corresponds, prevent to persist the surplus thick liquid of concrete in the mould.
In one embodiment of the present invention, the first hoop section 111 extends in the axial direction of the prefabricated building structure 100; the height of the first cuff section 111 is 10mm to 500mm, and/or the depth of the first cuff section 111 is 0.1mm to 50 mm. It is understood that the height of the first hoop section 111 herein refers to the height of the first hoop section 111 that is concave along the axial direction of the prefabricated building structure 100; the depth of the first hoop section 111 refers to the depth of the first hoop section 111 that is concave in the radial direction of the prefabricated building structure 100.
By the arrangement, the processing technology is simple, the bearing capacity of the single pile cannot be damaged, the resistance in underground water discharge can be reduced during construction, and the soil stress can be released; the size of the prefabricated building structure does not influence the bearing capacity of the prefabricated building structure 100, and the prefabricated building structure 100 and the soil body can have higher engaging force, so that the prefabricated building structure is beneficial to the outflow of mixing water in concrete during production.
Preferably, the first hoop sections 111 are a plurality of rectangular grooves, and the plurality of first hoop sections 111 are uniformly distributed on the outer circumferential wall of the prefabricated building structure 100 around the axial center of the prefabricated building structure 100. It is understood that the first hoop section 111 may also be circular in shape as shown in fig. 10. In other embodiments, the anchor may also be in other common shapes such as wave shape, triangle shape, trapezoid shape, etc., or may be non-uniformly distributed, as long as the anchoring effect is achieved.
In one embodiment of the present invention, the prefabricated building structure 100 is a pipe pile or a square pile.
The device has the advantages of simple manufacturing process, short production period, high single-pile bearing capacity, low unit bearing capacity manufacturing cost, good bending resistance and tensile property, reliable pile forming quality, convenient hoisting and wide application range.
Referring to fig. 13 to 16, fig. 13 is a schematic view illustrating the butt joint of two prefabricated building structures; FIG. 14 is an enlarged view at Y of FIG. 13; fig. 15 is a structural view illustrating a positioning ring of the prefabricated construction structures shown in fig. 13, and fig. 16 is a view illustrating a part of the prefabricated construction structures according to the sixth embodiment of the present invention.
In one embodiment of the present invention, the corner protector 60 further comprises a positioning ring 61, the positioning ring 61 being located at an end of the corner protector 60 and fixedly connected to the first cage 30.
So set up, the position relatively fixed between angle bead cover 60 and the first cage 30, just also with the relative position between the prefabricated building structure 100 is fixed, not only is convenient for prefabricated building structure 100's shaping, can also strengthen prefabricated building structure 100's intensity, prevents that prefabricated building structure 100 from taking place the deformation when being in service angle bead cover 60.
Specifically, in the present embodiment, the positioning ring 61 is sleeved on the embedded connector 70 at the end of the first axial rib 31, and the positioning ring 61 and the embedded connector 70 may be fixed only by sleeving or may be fixed by welding after sleeving. It is understood that in other embodiments, the positioning ring 61 may be directly sleeved on the first axial rib 31 without the embedded connector 70. As long as the position between the corner protector 60 and the first cage 30 can be relatively fixed by the positioning ring 61.
Furthermore, the number of the positioning rings 61 can be 1 or more, and each positioning ring 61 is sleeved with one embedded connecting piece 70 or one first axial rib body 31, so as to achieve a better fixing purpose.
In one embodiment, the pretensioning process for the first cage 30 in the prefabricated building structure 100 is: welding one end of the positioning ring 61, which is relatively far away from the ring shape, on the corner protector sleeve 60, sleeving and fixing the other end of the positioning ring 61 on the embedded connecting piece 70, then connecting the embedded connecting piece 70 with the end plate, wherein the positioning ring 61 cannot be separated from the embedded connecting piece 70 after connection, so that the relative fixation of the position between the corner protector sleeve 60 and the first cage body 30 is realized; and then moving the end plate to realize tensioning.
It is understood that the positioning ring 61 may also be circular, or may have other shapes, as long as it can be sleeved on the first axial rib 31 or the second axial rib 41.
In this embodiment, the positioning ring 61 is welded to the end of the corner protector 60. In other embodiments, the retaining ring 61 may also be integrally formed with the corner protector 60.
In one embodiment of the present invention, the prefabricated building structure 100 further comprises a positioning rib 21, and the positioning rib 21 is fixedly connected to the first cage 30 and the corner protector 60.
So set up, the position relatively fixed between angle bead cover 60 and the location muscle 21 not only is convenient for prefabricated building structure 100's shaping, can also strengthen prefabricated building structure 100's intensity, prevents that prefabricated building structure 100 from taking place the deformation in angle bead cover 60 when being in service.
Specifically, one end of the positioning rib 21 is connected to the first cage 30, and the other end is connected to the corner protection sleeve 60; the connection mode can be welding, can also be through steel wire ligature connection, can also be other connection modes, as long as can play the fixed action.
It will be appreciated that in other embodiments, the locating ring 61 and the locating rib 21 may be used together to better determine the relative position between the corner protector 60 and the first cage 30.
In one embodiment of the present invention, the first and second hoop sections 111 and 112 are connected by a right angle or a circular arc.
So set up, can select the connected mode of first hoop section 111 and second hoop section 112 according to operating condition demand or processing conditions to right angle connection or circular arc are connected the processing cost and are lower, easy to carry out.
It is understood that the first and second hoop sections 111 and 112 may be connected in other ways, regardless of the processing cost.
Referring to fig. 17, fig. 17 is a schematic structural diagram of the prefabricated building structure 100 and the platform 400.
In one embodiment, prefabricated building structure 100 is mated to a cap 400.
In this embodiment, the solid portion 20 of the prefabricated building structure 100 is connected to the cap 400. The ends of the second cage body 40 and the first cage body 30, which are relatively far away from the hollow part 10, are provided with pre-embedded connectors 70, the pre-embedded connectors 70 are fixedly connected with the force transmission rib bodies 410, a plurality of force transmission rib bodies 410 form a stress frame in the bearing platform 400, then concrete is poured into a mold, and the bearing platform 400 is formed after the concrete is dried and formed. In the embodiment, the second cage body 40 and the first cage body 30 are both provided with the embedded connecting pieces 70, so that the reinforcement ratio in the bearing platform 400 can be greatly improved, the bearing capacity of the bearing platform 400 can be improved, the force transmission link is reduced, and the method is safer and more reliable; but also better transfer the forces experienced by the cap 400 to the underlying foundation.
It is understood that in other embodiments, if the bearing platform 400 does not need to have very high bearing capacity, only the second cage 40 or the first cage 30 may be provided with the embedded connector 70 at the end relatively far from the hollow portion 10, and the embedded connector 70 is fixedly connected with the force transmission rib 410.
Referring to fig. 18, fig. 18 is a partially enlarged view of the portion C shown in fig. 17.
In one embodiment, the embedded connector 70 is provided with a through thread, one end of the embedded connector 70 is in threaded connection with the first axial rib 31 or the second axial rib 41, and the other end is in threaded connection with the force transmission rib 410.
Preferably, the force transmitting rib body 410 is a threaded steel.
It is understood that, in other embodiments, the embedded connector 70 may also be another type of steel bar, and the embedded connector 70 may also be fixedly connected to the first axial rib 31, the second axial rib 41, or the force transmission rib 410 by welding, clamping, or the like. Preferably, the embedded connector 70 is provided with an internal thread, the force transmission rib body 410 is provided with an external thread, and the two are connected in a threaded fit manner, so that the connection is simple and convenient, and the time cost during construction is saved.
The technical features of the above embodiments can be arbitrarily combined, and for the sake of brevity, all possible combinations of the technical features in the above embodiments are not described, but should be considered as the scope of the present specification as long as there is no contradiction between the combinations of the technical features.
It should be understood by those skilled in the art that the above embodiments are only for illustrating the present invention and are not to be used as a limitation of the present invention, and that suitable changes and modifications of the above embodiments are within the scope of the claimed invention as long as they are within the spirit and scope of the present invention.

Claims (10)

1. The prefabricated building structure (100) is characterized in that a pre-buried pipe (80) is arranged in the prefabricated building structure (100), the pre-buried pipe (80) is arranged in the middle of the prefabricated building structure (100), the interior of the pre-buried pipe (80) is hollow, and a glue storage groove (90) is formed in the end portion of the prefabricated building structure (100).
2. Prefabricated building structure (100) according to claim 1, characterised in that the area of the bottom wall of said glue reservoir (90) is smaller than or equal to the area of the figure enclosed by the edge of said glue reservoir (90) on the end face of said prefabricated building structure (100).
3. Prefabricated building structure (100) according to claim 2, characterized in that said glue reservoir (90) is a square, circular, trapezoidal or tapered groove; and/or the presence of a catalyst in the reaction mixture,
one or more glue storage grooves (90) are arranged.
4. Prefabricated building structure (100) according to claim 1, characterized in that said glue reservoir (90) is arranged centrally at the end of said prefabricated building structure (100); or the glue storage groove (90) is annular.
5. Prefabricated building structure (100) according to claim 1, characterised in that said glue reservoir (90) has a depth in the axial direction of said prefabricated building structure (100) of 1 to 200 mm.
6. The prefabricated building structure (100) of claim 1 wherein said prefabricated building structure (100) further comprises a first cage (30), said first cage (30) being disposed within said prefabricated building structure (100), said first cage (30) enclosing said pre-buried pipe (80).
7. Prefabricated building structure (100) according to claim 6, characterised in that a second cage (40) is arranged inside said prefabricated building structure (100), said second cage (40) being arranged at the end of said pre-buried pipe (80) in the axial direction, and said second cage (40) being housed inside said first cage (30).
8. Prefabricated building structure (100) according to claim 7, characterized in that said second cage (40) is connected to said pre-buried pipe (80); or the like, or, alternatively,
said second cage (40) being connected to said first cage (30); or the like, or, alternatively,
prefabricated building structure (100) still includes mounting panel (50), mounting panel (50) set up buried pipe (80) axial direction's tip, second cage (40) are connected in mounting panel (50).
9. The prefabricated building structure (100) of claim 8, wherein said prefabricated building structure (100) further comprises pre-buried connectors (70), said first cage (30) extending to an end of said prefabricated building structure (100), said pre-buried connectors (70) being provided at an end of said first cage (30); and/or the presence of a catalyst in the reaction mixture,
the second cage body (40) extends to the end of the prefabricated building structure (100), and the embedded connecting piece (70) is arranged at the end of the second cage body (40).
10. Prefabricated building structure (100) according to claim 9, characterized in that a corner protector (60) is provided on the peripheral wall of the end of said prefabricated building structure (100);
corner protector cover (60) are including holding ring (61), holding ring (61) are located the tip of corner protector cover (60), and fixed connection in first cage body (30), and/or, prefabricated building structure (100) still include location muscle (21), location muscle (21) fixed connection in first cage body (30) and corner protector cover (60).
CN202010226266.3A 2020-03-26 2020-03-26 Prefabricated building structure Pending CN111335302A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010226266.3A CN111335302A (en) 2020-03-26 2020-03-26 Prefabricated building structure

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010226266.3A CN111335302A (en) 2020-03-26 2020-03-26 Prefabricated building structure

Publications (1)

Publication Number Publication Date
CN111335302A true CN111335302A (en) 2020-06-26

Family

ID=71180466

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010226266.3A Pending CN111335302A (en) 2020-03-26 2020-03-26 Prefabricated building structure

Country Status (1)

Country Link
CN (1) CN111335302A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704471A (en) * 2012-05-22 2012-10-03 张俊峰 Prestress solid concrete preformed pile
CN104895052A (en) * 2015-06-25 2015-09-09 袁江 Rapid joint of precast concrete pile
CN104947658A (en) * 2015-06-26 2015-09-30 许顺良 Ejecting clamping type connecting piece and connecting pile
CN105040685A (en) * 2015-06-09 2015-11-11 周兆弟 Prefabricated member with hollow structure
CN204780883U (en) * 2015-06-09 2015-11-18 周兆弟 Prefab with hollow structure
CN212294625U (en) * 2020-03-26 2021-01-05 许顺良 Prefabricated building structure

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102704471A (en) * 2012-05-22 2012-10-03 张俊峰 Prestress solid concrete preformed pile
CN105040685A (en) * 2015-06-09 2015-11-11 周兆弟 Prefabricated member with hollow structure
CN204780883U (en) * 2015-06-09 2015-11-18 周兆弟 Prefab with hollow structure
CN104895052A (en) * 2015-06-25 2015-09-09 袁江 Rapid joint of precast concrete pile
CN104947658A (en) * 2015-06-26 2015-09-30 许顺良 Ejecting clamping type connecting piece and connecting pile
CN212294625U (en) * 2020-03-26 2021-01-05 许顺良 Prefabricated building structure

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
饶天赞: "《高层建筑基础工程施工》", 31 October 1995, 湖南科学技术出版社, pages: 160 - 162 *

Similar Documents

Publication Publication Date Title
CN112761138A (en) Prefabricated building structure
CN111335300A (en) Prefabricated building structure
CN212294625U (en) Prefabricated building structure
CN211898332U (en) Prefabricated building structure
CN111206570A (en) Prefabricated building structure
CN212452597U (en) Prefabricated building structure
CN212294628U (en) Prefabricated building structure
CN212452594U (en) Prefabricated building structure
CN212477702U (en) Prefabricated building structure
CN211898334U (en) Prefabricated building structure
CN212294623U (en) Prefabricated building structure
CN212714907U (en) Prefabricated building structure
CN211898335U (en) Prefabricated building structure
CN212294627U (en) Prefabricated building structure
CN211898333U (en) Prefabricated building structure
CN212452596U (en) Prefabricated building structure
CN212294622U (en) Prefabricated building structure
CN212294624U (en) Prefabricated building structure
CN111335302A (en) Prefabricated building structure
CN111335303A (en) Prefabricated building structure
CN212452595U (en) Prefabricated building structure
CN111441341A (en) Prefabricated building structure
CN111335301A (en) Prefabricated building structure
CN212452598U (en) Prefabricated building structure
CN212294626U (en) Prefabricated building structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination