CN111255118A - Detachable infill wall combination system and assembling method - Google Patents

Detachable infill wall combination system and assembling method Download PDF

Info

Publication number
CN111255118A
CN111255118A CN202010189677.XA CN202010189677A CN111255118A CN 111255118 A CN111255118 A CN 111255118A CN 202010189677 A CN202010189677 A CN 202010189677A CN 111255118 A CN111255118 A CN 111255118A
Authority
CN
China
Prior art keywords
module
wall
groove
foundation
tenon
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010189677.XA
Other languages
Chinese (zh)
Other versions
CN111255118B (en
Inventor
徐小明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Changzhou Vocational Institute of Engineering
Original Assignee
Changzhou Vocational Institute of Engineering
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Changzhou Vocational Institute of Engineering filed Critical Changzhou Vocational Institute of Engineering
Priority to CN202010189677.XA priority Critical patent/CN111255118B/en
Publication of CN111255118A publication Critical patent/CN111255118A/en
Application granted granted Critical
Publication of CN111255118B publication Critical patent/CN111255118B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/562Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with fillings between the load-bearing elongated members
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/18Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons
    • E04B1/20Structures comprising elongated load-supporting parts, e.g. columns, girders, skeletons the supporting parts consisting of concrete, e.g. reinforced concrete, or other stonelike material
    • E04B1/21Connections specially adapted therefor
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B1/00Constructions in general; Structures which are not restricted either to walls, e.g. partitions, or floors or ceilings or roofs
    • E04B1/38Connections for building structures in general
    • E04B1/48Dowels, i.e. members adapted to penetrate the surfaces of two parts and to take the shear stresses
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/02Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls built-up from layers of building elements
    • E04B2/04Walls having neither cavities between, nor in, the solid elements
    • E04B2/06Walls having neither cavities between, nor in, the solid elements using elements having specially-designed means for stabilising the position
    • E04B2/08Walls having neither cavities between, nor in, the solid elements using elements having specially-designed means for stabilising the position by interlocking of projections or inserts with indentations, e.g. of tongues, grooves, dovetails
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/56Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members
    • E04B2/64Load-bearing walls of framework or pillarwork; Walls incorporating load-bearing elongated members with elongated members of concrete

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)

Abstract

本发明公开了一种可拆装式填充墙组合体系及拼装方法。该组合体系包括独立基础模块DJ、框架柱模块KZ、地基梁模块DKL、填充墙下部模块QT1、填充墙上部模块QT2、圈梁模块QL、构造柱模块GZ,构造柱模块GZ的侧面设置有马牙槎和用于安装构造柱时伸出墙体端面的拉结筋可以通过构造柱的第一凹槽,填充墙下部模块QT1的顶面和填充墙体上部模块QT2的底面各设有两条墙体拉结筋的第二凹槽,且同一侧端面均设有用于构造柱模块GZ的马牙槎通过的第三凹槽。本发明的可拆装式填充墙组合体系及拼装方法具有结构合理、拆卸快捷,连接可靠等优点。

Figure 202010189677

The invention discloses a detachable filling wall combination system and an assembling method. The combined system includes an independent foundation module DJ, a frame column module KZ, a foundation beam module DKL, a lower infill wall module QT1, an upper infill wall module QT2, a ring beam module QL, and a structural column module GZ. The tie bars and the tie bars protruding from the end face of the wall when installing the structural column can pass through the first groove of the structural column, and there are two tie bars on the top surface of the lower module QT1 of the filling wall and the bottom surface of the upper module QT2 of the filling wall respectively. The second groove of the wall tie bars, and the end face on the same side is provided with a third groove for passing through the horse teeth of the column module GZ. The detachable infill wall combination system and the assembling method of the invention have the advantages of reasonable structure, quick disassembly, reliable connection and the like.

Figure 202010189677

Description

可拆装式填充墙组合体系及拼装方法Detachable infill wall combination system and assembling method

技术领域technical field

本发明涉及一种填充墙组合体系及拼装方法,特别涉及一种可拆装式填充墙组合体系及拼装方法。The invention relates to an infill wall combination system and an assembling method, in particular to a detachable infill wall combination system and an assembling method.

背景技术Background technique

框架、框剪等钢筋混凝土结构中填充墙属于墙体工程,该分部工程中涉及到诸多墙体施工和节点构造要求。框架结构的墙体是填充墙,起围护和分隔作用,重量由梁柱承担,填充墙不承重。框架结构分全框架和半框架,全框架没有承重墙,半框架有承重墙。墙体按照结构受力情况不同,有承重墙、非承重墙之分。非承重墙包括隔墙、填充墙、幕墙。凡分隔内部空间其重量由楼板或梁承受的墙称为隔墙;框架结构中填充在柱子之间的墙称框架填充墙。而主要悬挂于外部骨架间的轻质墙称幕墙。Infill walls in reinforced concrete structures such as frames and frame shears belong to wall engineering, and many wall construction and node structure requirements are involved in this sub-project. The wall of the frame structure is an infill wall, which plays the role of enclosure and separation. The weight is borne by the beams and columns, and the infill wall is not load-bearing. The frame structure is divided into full frame and half frame, the full frame has no bearing wall, and the half frame has bearing wall. Walls are divided into load-bearing walls and non-load-bearing walls according to different structural stress conditions. Non-load-bearing walls include partition walls, infill walls, and curtain walls. The wall that separates the internal space and its weight is borne by the floor or beam is called the partition wall; the wall filled between the columns in the frame structure is called the frame infill wall. The lightweight wall mainly suspended between the external skeletons is called the curtain wall.

现有填充墙结构存在设计不合理,拆卸过程耗时耗力,连接不可靠可靠等缺点。The existing infill wall structure has disadvantages such as unreasonable design, time-consuming and labor-intensive disassembly process, and unreliable and reliable connection.

发明内容SUMMARY OF THE INVENTION

针对现有技术中存在的上述问题,本发明提供一种可拆装式填充墙组合体系及拼装方法。In view of the above problems existing in the prior art, the present invention provides a detachable infill wall combination system and an assembling method.

本发明采用如下技术方案:The present invention adopts following technical scheme:

本发明提供一种可拆装式填充墙组合体系,包括独立基础模块DJ、框架柱模块KZ、地基梁模块DKL、填充墙下部模块QT1、填充墙上部模块QT2、圈梁模块QL、构造柱模块GZ,所述框架柱模块KZ榫接于独立基础模块DJ之上,所述地基梁模块DKL、圈梁模块QL相互平行榫接于两个框架柱模块KZ之间,所述构造柱模块GZ榫接于地基梁模块DKL和圈梁模块QL之间,所述填充墙下部模块QT1和填充墙上部模块QT2安装于地基梁模块DKL、圈梁模块QL、框架柱模块KZ、构造柱模块GZ共同形成的框架空间内,所述构造柱模块GZ的侧面设置有马牙槎和用于安装构造柱时伸出墙体端面的拉结筋可以通过构造柱的第一凹槽,所述填充墙体上部模块QT2的上部与圈梁模块QL榫接,其下部与填充墙下部模块QT1的上部榫接,所述填充墙下部模块QT1的下部与地基梁模块DKL榫接,填充墙下部模块QT1的顶面和填充墙体上部模块QT2的底面各设有两条墙体拉结筋的第二凹槽,且同一侧端面均设有用于构造柱模块GZ的马牙槎通过的第三凹槽。The invention provides a detachable infill wall combination system, which includes an independent foundation module DJ, a frame column module KZ, a foundation beam module DKL, a lower infill wall module QT1, an upper infill wall module QT2, a ring beam module QL, and a structural column module GZ, the frame column module KZ is tenoned on the independent foundation module DJ, the foundation beam module DKL and the ring beam module QL are tenoned between the two frame column modules KZ in parallel with each other, and the construction column module GZ is tenoned Connected between the foundation beam module DKL and the ring beam module QL, the infill wall lower module QT1 and the infill wall upper module QT2 are installed on the foundation beam module DKL, the ring beam module QL, the frame column module KZ, and the construction column module GZ. In the frame space, the side of the structural column module GZ is provided with horse teeth and the tie bars protruding from the end face of the wall when the structural column is installed can pass through the first groove of the structural column, and the upper part of the wall is filled. The upper part of the module QT2 is tenoned with the ring beam module QL, and its lower part is tenoned with the upper part of the lower part module QT1 of the infill wall; The bottom surface of the upper module QT2 and the filling wall are respectively provided with two second grooves for wall tie bars, and the end surfaces on the same side are provided with third grooves for passing through the horse teeth of the structural column module GZ.

更进一步的,所述独立基础模块DJ采用设有垫层的锥形独立基础,锥形独立基础的顶面设有连接榫头,通过连接榫头插入至上方框架柱模块KZ底面的榫槽内实现基础与框架柱之间的连接。Furthermore, the independent foundation module DJ adopts a conical independent foundation provided with a cushion layer, and the top surface of the conical independent foundation is provided with a connecting tenon, and the foundation is realized by inserting the connecting tenon into the tenon groove on the bottom surface of the upper frame column module KZ. Connections to frame columns.

更进一步的,所述框架柱模块KZ的底面设有与下方锥形独立基础连接的榫槽,且其侧面靠近柱下部位置设有与地基梁模块DKL连接的第一榫槽、靠近柱中间位置设有用于固定填充墙内拉结筋的孔槽。Further, the bottom surface of the frame column module KZ is provided with a tongue and groove connected with the lower conical independent foundation, and its side is provided with a first tongue and groove connected with the foundation beam module DKL at a position near the lower part of the column, and a position near the middle of the column. There are holes and slots for fixing the tie bars in the filling wall.

更进一步的,所述地基梁模块DKL的两头设置第一榫头,通过第一榫头插入至所述框架柱模块KZ侧面靠近下部位置的第一榫槽内,实现地基梁与框架柱之间连接;地基梁顶面的靠近两端各设有一个用于与填充墙体下部模块QT1连接的第二榫头,中间设有用于固定构造柱模块KZ的卡头。Further, the two ends of the foundation beam module DKL are provided with first tenons, and the first tenons are inserted into the first tenon grooves on the side of the frame column module KZ close to the lower position to realize the connection between the foundation beam and the frame column; Near both ends of the top surface of the foundation beam are provided with a second tenon for connecting with the lower module QT1 of the filling wall, and a clamp for fixing the structural column module KZ is provided in the middle.

更进一步的,所述圈梁模块QL的底面设有三个第二榫槽,其中靠近圈梁端部的两个第二榫槽与填充墙上部模块QT2顶面设置的第三榫头实现连接,中间的第二榫槽与构造柱模块GZ顶面设置的第四榫头实现连接。Further, the bottom surface of the ring beam module QL is provided with three second tongue grooves, wherein the two second tongue grooves near the end of the ring beam are connected with the third tenon provided on the top surface of the upper module QT2 on the filling wall, and the middle The second tenon and groove of the structure column module GZ is connected with the fourth tenon provided on the top surface of the construction column module GZ.

本发明还提供一种可拆装式填充墙组合体系的拼装方法,包括:The present invention also provides a method for assembling a detachable infill wall combination system, comprising:

步骤1:独立基础模块DJ与框架柱模块KZ拼装:利用锥形独立基础模块DJ顶面设有连接榫头插入至上方框架柱模块KZ底面设置的榫槽内,实现基础模块与框架柱模块之间的拼接;Step 1: Assemble the independent base module DJ and the frame column module KZ: Use the connecting tenon on the top surface of the tapered independent base module DJ to insert it into the tenon groove set on the bottom surface of the upper frame column module KZ to realize the connection between the base module and the frame column module. splicing;

步骤2:框架柱模块KZ与地基梁模块DKL拼装:在步骤1的基础上,利用地基梁模块DKL两头设置的第一榫头插入到框架柱模块KZ侧面靠近柱下部位置设有与地基梁模块连接的第一榫槽内,实现框架柱模块与地基梁模块之间的连接;Step 2: Assemble the frame column module KZ and the foundation beam module DKL: On the basis of step 1, use the first tenon set at both ends of the foundation beam module DKL to be inserted into the frame column module KZ near the lower part of the column, and there is a connection with the foundation beam module In the first tongue and groove of the frame, the connection between the frame column module and the foundation beam module is realized;

步骤3:填充墙体模块单元的拼装:在步骤2的基础上,首先采用填充墙下部模块QT1,利用模块QT1底面设置的榫槽与下方地基梁模块DKL相对应位置设置的第二榫头的插入实现拼接;然后在填充墙体上部模块QT1顶面两端设置的第二凹槽内,各放置两根墙体拉结筋,其中靠近框架柱模块KZ一端的墙体拉结筋的端头伸入框架柱模块侧面设置的孔槽内进行固定;待填充墙体下部模块QT1拼装完毕,利用填充墙体下部模块QT1顶面设置的第五榫头插入至上方填充墙体上部模块QT2底面相对应的位置设置的榫槽,实现上下两部分墙体模块的拼装;Step 3: Assembly of the infill wall module unit: On the basis of step 2, firstly use the lower module QT1 of the infill wall, and use the tongue and groove set on the bottom of the module QT1 to insert the second tongue set at the corresponding position of the lower foundation beam module DKL. To achieve splicing; then in the second grooves set at both ends of the top surface of the upper module QT1 of the filled wall, two wall tie bars are placed, and the end of the wall tie bars close to one end of the frame column module KZ stretches out. After the assembly of the lower module QT1 of the filling wall is completed, the fifth tenon set on the top surface of the lower module QT1 of the filling wall is inserted into the corresponding bottom surface of the upper module QT2 of the filling wall above. The tenon and groove set at the position realizes the assembly of the upper and lower wall modules;

步骤4:构造柱模块GZ拼装:在步骤3的基础上,利用构造柱底面设置的卡槽,从填充墙模块的一个侧面向另一个侧面的向前推进,直至卡槽与地基梁模块DKL顶面上的卡头完全吻合为止;在推行过程中,构造柱模块GZ的侧面设置的马牙槎完全通过填充墙端面设置的第三凹槽,且超出填充墙模块端面的拉结筋伸入至构造模块GZ侧面设置的第一凹槽内;Step 4: Assembly of the structural column module GZ: On the basis of step 3, use the clip slot set on the bottom surface of the construction column to push forward from one side of the infill wall module to the other side until the clip slot is connected to the top of the foundation beam module DKL. The clamps on the surface are completely matched; during the implementation process, the horse teeth set on the side of the structural column module GZ completely pass through the third groove set on the end face of the infill wall, and the tie bars beyond the end face of the infill wall module extend into the in the first groove provided on the side of the construction module GZ;

步骤5:圈梁模块QL拼装:在步骤4的基础上,利用圈梁的底面设置的三个榫槽分别与下方填充墙上部模块QT2顶面设置的榫头以及构造柱模块GZ顶面设置的榫头进行连接,实现圈梁与下方填充墙体和构造柱的拼接。Step 5: Assembling the ring beam module QL: On the basis of step 4, use the three tongue and groove set on the bottom surface of the ring beam and the tenon set on the top surface of the upper module QT2 of the lower filling wall and the tenon set on the top surface of the structural column module GZ respectively. Make connections to realize the splicing of ring beams and infill walls and structural columns below.

本发明的有益效果如下:The beneficial effects of the present invention are as follows:

可拆装式填充墙组合体系考虑到填充墙体体系与墙体周边框架柱、构造柱以及圈梁的连接方法,大大增强了填充墙体体系的功能性和实效性,具有结构合理、拆卸快捷,连接可靠等优点。The detachable infill wall combination system takes into account the connection method between the infill wall system and the surrounding frame columns, structural columns and ring beams of the wall, which greatly enhances the functionality and effectiveness of the infill wall system, with reasonable structure and quick disassembly. , the connection is reliable and so on.

附图说明Description of drawings

图1是独立基础模块DJ的结构示意图;Fig. 1 is the structural schematic diagram of the independent basic module DJ;

图2是框架柱模块KZ的结构示意图;Fig. 2 is the structural representation of frame column module KZ;

图3是地基梁模块DKL的结构示意图;Fig. 3 is the structural representation of foundation beam module DKL;

图4是填充墙下部模块QT1的结构示意图;Fig. 4 is the structural representation of the lower module QT1 of the filling wall;

图5是填充墙体上部模块QT2的结构示意图;Fig. 5 is the structural representation of filling wall upper module QT2;

图6是圈梁模块QL的结构示意图;Fig. 6 is the structural representation of ring beam module QL;

图7是构造柱模块GZ的结构示意图;Fig. 7 is the structural representation of the structural column module GZ;

图8是独立基础与框架柱拼接示意图;Figure 8 is a schematic diagram of the splicing of an independent foundation and a frame column;

图9是独立基础、框架柱与地基梁拼接示意图;Figure 9 is a schematic diagram of the splicing of an independent foundation, a frame column and a foundation beam;

图10是地基梁上填充墙拼接示意图一;Figure 10 is a schematic diagram 1 of the infill wall splicing on the foundation beam;

图11是地基梁上填充墙拼接示意图二;Figure 11 is the second schematic diagram of the infill wall splicing on the foundation beam;

图12是填充墙内安装构造柱示意图;Figure 12 is a schematic diagram of the installation of structural columns in the infill wall;

图13是填充墙上方安装圈梁示意图。Figure 13 is a schematic diagram of the installation of the ring beam above the infill wall.

图中标记:1、连接榫头;2、孔槽;3、第一榫槽;4、第一榫头;5、第二榫头;6、卡头;7、第二凹槽;8、第五榫头;9、第三凹槽;10、第三榫头;11、第二榫槽;12、马牙槎;13、第一凹槽;14、卡槽;15、第四榫头;16、拉结筋。Markings in the figure: 1, connecting tenon; 2, hole and groove; 3, first tenon and groove; 4, first tenon; 5, second tenon; 6, clip; 7, second groove; 8, fifth tenon ; 9, the third groove; 10, the third tenon; 11, the second groove; 12, the horse's tooth; 13, the first groove; .

具体实施方式Detailed ways

下面结合附图对本发明作进一步详细说明。The present invention will be further described in detail below in conjunction with the accompanying drawings.

本发明的可拆装式填充墙组合体系包括独立基础模块、地基梁模块、框架柱模块、构造柱模块、圈梁模块及填充墙砌体模块单元,并按照填充墙体在施工现场中实际施工工序设计了各模块的拼装方法及流程。The detachable infill wall combined system of the present invention includes an independent foundation module, a foundation beam module, a frame column module, a structural column module, a ring beam module and a masonry module unit of the infill wall, and is constructed according to the actual construction of the infill wall on the construction site. The process designs the assembly method and process of each module.

结合施工现场常见的框架结构设计了柱下独立基础。独立基础采用的是具有代表性的设有垫层的锥形独立基础模块DJ(如图1所示),为便于与基础上方框架柱连接,锥形独立基础顶面设有连接榫头1,通过榫头插入至上方框架柱模块KZ底面的榫槽内实现基础与框架柱之间的连接。Combined with the common frame structure on the construction site, the independent foundation under the column is designed. The independent foundation adopts a representative conical independent foundation module DJ (as shown in Figure 1) with cushion layer. In order to facilitate the connection with the frame column above the foundation, the top surface of the conical independent foundation is provided with a connecting tenon 1. The tenon is inserted into the tenon and groove on the bottom surface of the upper frame column module KZ to realize the connection between the foundation and the frame column.

框架柱模块KZ(如图2所示)除底面设有与基础连接的榫槽外,侧面靠近柱下部位置设有与地基梁模块连接的第一榫槽3,侧面的靠近柱中间位置设有用于固定填充墙内拉结筋的孔槽2。The frame column module KZ (as shown in Figure 2) is provided with a first tongue and groove 3 connected to the foundation beam module on the side near the lower part of the column, except that the bottom surface is provided with a tongue and groove connected with the foundation, and the side near the middle of the column is provided with a Fix the hole slot 2 of the tie bars in the fixed filling wall.

地基梁模块DKL(如图3所示)两头设置第一榫头4,通过榫头插入至上述框架柱模块侧面靠近下部位置设置的榫槽内,实现地基梁与框架柱之间连接;地基梁顶面靠近两端各设有一个用于与上部填充墙体模块连接的第二榫头5,中间设有用于固定构造柱的卡头6。The foundation beam module DKL (as shown in Figure 3) is provided with first tenons 4 at both ends, and the tenon is inserted into the tenon groove provided on the side of the frame column module near the lower position to realize the connection between the foundation beam and the frame column; the top surface of the foundation beam is A second tenon 5 for connecting with the upper filling wall module is provided near each end, and a clamping head 6 for fixing the structural column is provided in the middle.

填充墙模块单元分为填充墙下部模块QT1和填充墙上部模块QT2(如图4、5所示)。其中填充墙下部模块QT1的顶面和填充墙体上部模块QT2的底面,各设有两条墙体拉结筋的第二凹槽7,用于放置和固定墙体拉结筋;上下两部分填充墙体其中同一侧端面均设有用于构造柱安装时马牙槎通过的矩形第三凹槽9;下部填充墙QT1顶面设有第五榫头8,通过榫头插入至上部填充墙QT2底面相应位置设置的榫槽实现上下两部分墙体的连接,上部填充墙QT2顶面设置第三榫头10,用于与上方圈梁QL的连接。The infill wall module unit is divided into the infill wall lower module QT1 and the infill wall upper module QT2 (as shown in Figures 4 and 5). The top surface of the lower module QT1 of the filling wall and the bottom surface of the upper module QT2 of the filling wall are each provided with two second grooves 7 for wall tie bars, which are used to place and fix the wall tie bars; the upper and lower parts are The end faces on the same side of the infill wall are provided with a rectangular third groove 9 for passing through when the column is installed; the top surface of the lower infill wall QT1 is provided with a fifth tenon 8, which is inserted into the bottom surface of the upper infill wall QT2 through the tenon. The tenon and groove provided at the position realize the connection of the upper and lower parts of the wall, and the top surface of the upper filling wall QT2 is provided with a third tenon 10 for connection with the upper ring beam QL.

为了更好的贴近施工现场对构造柱的要求,构造柱模块GZ(如图7所示)的侧面按照构造要求设置马牙槎12用于提高墙体的连接性能,构造柱底面设有与地基梁连接的卡槽14,顶面设有与上方圈梁连接的第四榫头15。考虑到现场砌体工程中墙体拉结筋一端伸入到构造柱内锚固的实际情况,构造柱的侧面除设置马牙槎外还设置了构造柱安装时墙体拉结筋可以通过的第一凹槽13。In order to better meet the requirements of the construction site for structural columns, the side of the structural column module GZ (as shown in Figure 7) is provided with a horse tooth 12 to improve the connection performance of the wall according to the structural requirements. The slot 14 for beam connection is provided with a fourth tenon 15 connected to the upper ring beam on the top surface. Considering the actual situation that one end of the wall tie bar extends into the structural column for anchoring in the on-site masonry project, the side of the structural column is not only provided with horse teeth, but also has a second wall through which the wall tie bar can pass when the structural column is installed. A groove 13.

圈梁模块QL梁底设有三个第二榫槽11,其中两端的设置两个榫槽与下方填充墙模块QT2顶面设置的第三榫头10实现连接,中间榫槽与下方构造柱模块GZ顶面设置的第四榫头15实现连接。There are three second tenon grooves 11 at the bottom of the ring beam module QL beam, two tenon grooves at both ends are connected with the third tenon 10 provided on the top surface of the lower filling wall module QT2, and the middle tenon groove is connected with the top of the lower structural column module GZ. The fourth tenon 15 provided on the surface realizes the connection.

根据上述发明的组合模块,依照施工现场钢筋混凝土结构中填充墙施工的构造要求和施工工序,按照先后顺序进行独立基础DJ与框架柱KZ的拼装、框架柱KZ与地基梁DKL的瓶装、填充墙体单元(QT1、QT2)拼装、构造柱GZ与填充墙体单元拼装、圈梁QL与下方填充墙体QT2及构造柱GZ拼装。According to the combined module of the above invention, according to the structural requirements and construction procedures of the construction of the infill wall in the reinforced concrete structure of the construction site, the assembly of the independent foundation DJ and the frame column KZ, the bottled of the frame column KZ and the foundation beam DKL, and the infill wall are carried out in sequence. Assembly of body units (QT1, QT2), assembly of structural column GZ and infill wall unit, assembly of ring beam QL and infill wall QT2 below and structural column GZ.

按照填充墙体在施工中的构造要求并依照先砌筑填充墙再浇注构造柱的施工原则,设计了各组合模块的具体拼装方法及流程如下:According to the structural requirements of the infill wall during construction and in accordance with the construction principle of first building the infill wall and then pouring the structural column, the specific assembly method and process of each combined module are designed as follows:

1、独立基础模块DJ与框架柱模块KZ拼装:利用锥形独立基础模块DJ顶面设有连接榫头1插入至上方框架柱模块KZ底面设置榫槽内,实现基础模块与框架柱模块之间的拼接(如图8所示)。1. Assemble the independent base module DJ and the frame column module KZ: use the conical independent base module DJ top surface with connecting tenon 1 to insert it into the tenon groove set on the bottom surface of the upper frame column module KZ to realize the connection between the base module and the frame column module. Splicing (as shown in Figure 8).

2、框架柱模块KZ与地基梁模块DKL拼装:在步骤1的基础上,利用地基梁模块DKL两头设置第一榫头4插入到框架柱模块KZ侧面靠近柱下部位置设有与地基梁模块连接的第一榫槽3内,实现框架柱模块与地基梁模块之间的连接(如图9所示)。2. Assembling the frame column module KZ and the foundation beam module DKL: On the basis of step 1, use the first tenon 4 at both ends of the foundation beam module DKL to be inserted into the side of the frame column module KZ near the lower part of the column. In the first tongue groove 3, the connection between the frame column module and the foundation beam module is realized (as shown in FIG. 9).

3、填充墙体模块单元(QT1、QT2)的拼装:在步骤2的基础上,首先采用填充墙下部模块QT1,利用模块QT1底面设置的榫槽与下方地基梁模块DKL相对应位置设置的第二榫头5的插入实现拼接;然后在填充墙体上部模块QT1顶面两端设置的钢筋第二凹槽7内,各放置两根墙体拉结筋16,其中靠近框架柱模块KZ一端的墙体拉结筋16的端头伸入框架柱模块侧面设置的钢筋孔槽2内进行固定,靠近构造柱模块GZ一端的墙体拉结筋16的端头朝出填充墙模块端面一段距离,伸入至下一步骤安装的构造柱模块GZ位置内,起到拉结筋在构造柱内钢筋锚固的作用;待填充墙体下部模块QT1拼装完毕,利用填充墙体下部模块QT1顶面设置的第五榫头8插入至上方填充墙体上部模块QT2底面相对应的位置设置的榫槽,实现上下两部分墙体模块的拼装(如10、11所示)。3. Assembling of infill wall module units (QT1, QT2): On the basis of step 2, first use the lower module QT1 of the infill wall, and use the tongue and groove set on the bottom of the module QT1 to be set at the corresponding position of the foundation beam module DKL below. The insertion of the two tenons 5 realizes splicing; then in the second grooves 7 of the reinforcing bars set at both ends of the top surface of the upper module QT1 of the filled wall, two wall tie bars 16 are placed respectively, wherein the wall near one end of the frame column module KZ The ends of the body tie bars 16 extend into the reinforcement holes 2 provided on the side of the frame column module for fixing. Enter into the GZ position of the structural column module installed in the next step, and play the role of anchoring the tie bars in the structural column. The five tenons 8 are inserted into the tenon and groove provided at the corresponding position on the bottom surface of the upper module QT2 of the upper filling wall to realize the assembly of the upper and lower wall modules (as shown in 10 and 11).

4、构造柱模块GZ拼装:在步骤3的基础上,利用构造柱底面设置的卡槽14,从填充墙模块的一个侧面向另一个侧面的向前推行,直至卡槽14与地基梁模块DKL顶面上的卡头6完全吻合为止。在推行过程中,要保证构造柱模块GZ的侧面设置的马牙槎12完全通过填充墙端面设置的矩形第三凹槽9以及步骤3中超出填充墙模块端面的拉结筋16伸入至构造模块GZ侧面设置的第一凹槽13内(如图12所示)。4. Assembly of the structural column module GZ: On the basis of step 3, use the clamping slot 14 set on the bottom surface of the structural column to push forward from one side of the infill wall module to the other side until the clamping slot 14 and the foundation beam module DKL until the clamp head 6 on the top surface is completely matched. During the implementation process, it is necessary to ensure that the horse teeth 12 provided on the side of the structural column module GZ completely extend into the structure through the rectangular third groove 9 provided on the end face of the infill wall and the tie bars 16 beyond the end face of the infill wall module in step 3. Inside the first groove 13 provided on the side of the module GZ (as shown in FIG. 12 ).

5、圈梁模块QL拼装:在步骤4的基础上,利用圈梁的底面设置的三个榫槽11分别与下方填充墙上部模块QT2顶面设置的第三榫头10以及构造柱模块GZ顶面设置的第四榫头15进行连接,实现圈梁与下方填充墙体和构造柱的拼接(如图13所示)。5. Assembling the ring beam module QL: On the basis of step 4, use the three tenon grooves 11 set on the bottom surface of the ring beam and the third tenon 10 set on the top surface of the upper module QT2 on the lower filling wall and the top surface of the structural column module GZ respectively. The provided fourth tenon 15 is connected to realize the splicing of the ring beam with the lower filling wall and the structural column (as shown in FIG. 13 ).

这种可拆装的填充墙体组合模型体系,具有结构合理、拆卸快捷,连接可靠等优点。The dismountable infill wall combined model system has the advantages of reasonable structure, quick disassembly, reliable connection and the like.

以上所述仅为本发明的较佳实施例而已,并不用以限制本发明。凡在本发明的精神和原则之内所作的任何修改、等同替换和改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements and improvements made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (6)

1. Removable type infilled wall combination system, its characterized in that: comprises an independent foundation module DJ, a frame column module KZ, a foundation beam module DKL, a filler wall lower module QT1, a filler wall upper module QT2, a ring beam module QL and a constructional column module GZ, wherein the frame column module KZ is joggled on the independent foundation module DJ, the foundation beam module DKL and the ring beam module QL are mutually parallel and joggled between the two frame column modules KZ, the constructional column module GZ is joggled between the foundation beam module DKL and the ring beam module QL, the filler wall lower module 1 and the filler wall upper module QT2 are arranged in a frame space formed by the foundation beam module DKL, the ring beam module QL, the frame column module KZ and the constructional column module GZ together, the side surface of the constructional column module GZ is provided with a serrated racking joint (12) and a first groove (13) which can pass through a tie bar (16) for extending out the end surface of a wall body when the constructional column is installed, the upper part of the filler wall module 2 is joggled with the QTL, its lower part and infilled wall lower part module QT 1's upper portion joggle, the lower part and the foundation beam module DKL joggle of infilled wall lower part module QT1, the top surface of infilled wall lower part module QT1 and the bottom surface of infilled wall upper portion module QT2 respectively are equipped with second recess (7) of two wall body drawknot muscle, and all are equipped with third recess (9) that horse tooth raft (12) that are used for constructing post module GZ passed through with same side terminal surface.
2. The removable infill wall assembly system of claim 1, wherein: independent foundation module DJ adopts the independent basis of toper that is equipped with the bed course, and the top surface of the independent basis of toper is equipped with connecting tenon (1), inserts through connecting tenon (1) and realizes being connected between basis and the frame post to the tongue-and-groove of frame post module KZ bottom surface in the top.
3. The removable infill wall assembly system of claim 2, wherein: the bottom surface of frame post module KZ is equipped with the tongue-and-groove of being connected with the independent basis of below toper, and its side is close to post lower part position and is equipped with first tongue-and-groove (3) of being connected with foundation beam module DKL, is close to post intermediate position and is equipped with hole groove (2) that are used for fixed infilled wall interior drawknot muscle.
4. The removable infill wall assembly system of claim 3, wherein: two ends of the foundation beam module DKL are provided with first tenons (4), and the first tenons (4) are inserted into first mortises (3) on the side surface, close to the lower part, of the frame column module KZ to realize connection between a foundation beam and frame columns; the top surface of the foundation beam is provided with a second tenon (5) which is used for being connected with a filling wall lower module QT1 near two ends, and the middle of the top surface of the foundation beam is provided with a clamping head (6) which is used for fixing a constructional column module KZ.
5. The removable infill wall assembly system of claim 1, wherein: the bottom surface of ring beam module QL is equipped with three second tongue-and-groove (11), wherein two second tongue-and-groove (11) that are close to ring beam tip realize being connected with third tenon (10) that the module QT2 top surface of filler wall set up, and middle second tongue-and-groove (11) realize being connected with fourth tenon (15) that constructional column module GZ top surface set up.
6. The assembling method of the detachable infilled wall combination system comprises the following steps:
step 1: independent foundation module DJ assembles with frame post module KZ: the top surface of the conical independent foundation module DJ is provided with a connecting tenon (1) which is inserted into a mortise arranged on the bottom surface of the KZ of the upper frame column module, so that the foundation module and the frame column module are spliced;
step 2: the frame column module KZ and the foundation beam module DKL are assembled: on the basis of the step 1, first tenons (4) arranged at two ends of a foundation beam module DKL are inserted into first mortises (3) formed in the side face of a frame column module KZ and close to the lower part of a column and connected with the foundation beam module, so that the frame column module is connected with the foundation beam module;
and step 3: assembling the filling wall module units: on the basis of the step 2, firstly, a lower module QT1 of the filler wall is adopted, and splicing is realized by inserting a mortise arranged on the bottom surface of the module QT1 and a second tenon (5) arranged at a position corresponding to the lower foundation beam module DKL; then, two wall tie bars (16) are respectively placed in second grooves (7) formed in two ends of the top surface of a QT1 upper filling wall module, wherein the end of the wall tie bar (16) close to one end of a KZ frame column module extends into a hole groove (2) formed in the side surface of the frame column module for fixing; after the lower module QT1 of the filled wall is assembled, a fifth tenon (8) arranged on the top surface of the lower module QT1 of the filled wall is inserted into a mortise arranged at a position corresponding to the bottom surface of the upper module QT2 of the filled wall above, so that the upper and lower wall modules are assembled;
and 4, step 4: assembling a constructional column module GZ: on the basis of the step 3, a clamping groove (14) arranged on the bottom surface of the constructional column is utilized to push forward from one side surface of the filler wall module to the other side surface of the filler wall module until the clamping groove (14) is completely matched with a clamping head (6) on the top surface of the foundation beam module DKL; in the pushing process, a serrated racking (12) arranged on the side surface of the constructional column module GZ completely passes through a third groove (9) arranged on the end surface of the filling wall, and a tie bar (16) exceeding the end surface of the filling wall module extends into a first groove (13) arranged on the side surface of the constructional module GZ;
and 5: assembling a ring beam module QL: on the basis of the step 4, three second mortises (11) arranged on the bottom surface of the ring beam are respectively connected with a third tenon (10) arranged on the top surface of a QT2 on the lower filling wall and a fourth tenon (15) arranged on the top surface of a GZ constructional column module, so that the ring beam is spliced with the lower filling wall and the constructional column.
CN202010189677.XA 2020-03-18 2020-03-18 Detachable filling wall combined system and assembling method Active CN111255118B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010189677.XA CN111255118B (en) 2020-03-18 2020-03-18 Detachable filling wall combined system and assembling method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010189677.XA CN111255118B (en) 2020-03-18 2020-03-18 Detachable filling wall combined system and assembling method

Publications (2)

Publication Number Publication Date
CN111255118A true CN111255118A (en) 2020-06-09
CN111255118B CN111255118B (en) 2024-08-30

Family

ID=70941928

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010189677.XA Active CN111255118B (en) 2020-03-18 2020-03-18 Detachable filling wall combined system and assembling method

Country Status (1)

Country Link
CN (1) CN111255118B (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112560148A (en) * 2020-12-18 2021-03-26 中国二十冶集团有限公司 BIM-based wall modeling method and system for wall end processing

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6178714B1 (en) * 1999-07-06 2001-01-30 Robert S. Carney, Jr. Modular temporary building
WO2002088481A1 (en) * 2001-04-30 2002-11-07 Camille Jim Riviere Building element assembly
JP2005282089A (en) * 2004-03-29 2005-10-13 Miracle Three Corporation Building extension method, and extension building
NL2008248C2 (en) * 2011-06-23 2013-01-02 Cornelis Tadema BUILDING STONE, CONSTRUCTED WORK, AND METHOD FOR MANUFACTURING SUCH CONSTRUCTION.
CN106351511A (en) * 2016-10-10 2017-01-25 中建局集团第五建筑有限公司 Prefabricated component combined enclosing wall and installation method thereof
CN107401230A (en) * 2016-05-19 2017-11-28 长葛市唯美装饰行 Mortise-and-mortise connection without laying bricks and masonry
CN108104372A (en) * 2018-02-05 2018-06-01 天津城建大学 For the precast combined constructional column and construction method of masonry structure
CN109779128A (en) * 2019-03-08 2019-05-21 常州工程职业技术学院 Prefabricated block system suitable for cross-type handover and its assembling method
CN110552461A (en) * 2019-08-20 2019-12-10 湖北正浩建设集团有限公司 Prefabricated constructional column of masonry infilled wall and construction method thereof
AU2019204213A1 (en) * 2018-07-20 2020-02-06 Engineering Innovations Group Pty Limited Column and wall panel
CN212053343U (en) * 2020-03-18 2020-12-01 常州工程职业技术学院 Detachable infill wall combination system

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US6178714B1 (en) * 1999-07-06 2001-01-30 Robert S. Carney, Jr. Modular temporary building
WO2002088481A1 (en) * 2001-04-30 2002-11-07 Camille Jim Riviere Building element assembly
JP2005282089A (en) * 2004-03-29 2005-10-13 Miracle Three Corporation Building extension method, and extension building
NL2008248C2 (en) * 2011-06-23 2013-01-02 Cornelis Tadema BUILDING STONE, CONSTRUCTED WORK, AND METHOD FOR MANUFACTURING SUCH CONSTRUCTION.
CN107401230A (en) * 2016-05-19 2017-11-28 长葛市唯美装饰行 Mortise-and-mortise connection without laying bricks and masonry
CN106351511A (en) * 2016-10-10 2017-01-25 中建局集团第五建筑有限公司 Prefabricated component combined enclosing wall and installation method thereof
CN108104372A (en) * 2018-02-05 2018-06-01 天津城建大学 For the precast combined constructional column and construction method of masonry structure
AU2019204213A1 (en) * 2018-07-20 2020-02-06 Engineering Innovations Group Pty Limited Column and wall panel
CN109779128A (en) * 2019-03-08 2019-05-21 常州工程职业技术学院 Prefabricated block system suitable for cross-type handover and its assembling method
CN110552461A (en) * 2019-08-20 2019-12-10 湖北正浩建设集团有限公司 Prefabricated constructional column of masonry infilled wall and construction method thereof
CN212053343U (en) * 2020-03-18 2020-12-01 常州工程职业技术学院 Detachable infill wall combination system

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
叶必朝;: "某新型复合保温砌块的初步研究", 常州工程职业技术学院学报, no. 04, 15 December 2009 (2009-12-15) *
许清风;刘琼;张富文;贡春成;: "砖填充墙榫卯节点木框架抗震性能试验研究", 建筑结构, no. 06, 25 March 2015 (2015-03-25) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112560148A (en) * 2020-12-18 2021-03-26 中国二十冶集团有限公司 BIM-based wall modeling method and system for wall end processing

Also Published As

Publication number Publication date
CN111255118B (en) 2024-08-30

Similar Documents

Publication Publication Date Title
CN109642424B (en) Connection system and method for prefabricated volumetric building modules
CN108505619A (en) Prefabricated structural system and assembly method thereof
CN105143570B (en) Building structure and construction method thereof
CN103437425A (en) Connecting joint of prefabricated hollow steel-reinforced concrete column and steel beam and construction method
CN113250327A (en) Structural system of steel structure building and installation method thereof
KR20190143696A (en) Base forming unit for building of architectural slave and structural structure of the base forming unit
CN212053343U (en) Detachable infill wall combination system
CN111255118A (en) Detachable infill wall combination system and assembling method
CN104453013A (en) Prefabricated wall component and fabricated reinforced concrete shear wall
CN113463502B (en) A prefabricated assembled corrugated steel web composite bridge and its cantilever construction method
CN113513089B (en) FRP (fiber reinforced plastic) wrapped crossed steel reinforced concrete column-H-shaped steel beam connecting node and mounting method
CN114575453A (en) One-way double-mortise and tenon structure of assembled beam column component and construction method
CN107503446A (en) A kind of U-shaped steel bar connector connection Shear-wall Connecting Beam Used structure and assembly method
JP4976938B2 (en) Seismic reinforcement structure
CN109555232B (en) Precast beam mortise and tenon joint connects
CN218149077U (en) Reinforced concrete shear wall
CN111851743A (en) Concrete building archway structure and construction method thereof
CN212641739U (en) Assembly integral primary and secondary beam U-shaped steel bar connection node
KR20210026900A (en) Joining method of precast concrete pillar and girderin concrete structure
CN214364419U (en) House construction spandrel girder structure
CN111255060B (en) Detachable reinforced concrete strip foundation combination system and assembling method
CN110258784A (en) A kind of assembled arthitecutral structure
JP2003301542A (en) Construction method of plate wall in wooden building
CN221345863U (en) Assembly type wet connection frame node structure with U-shaped groove precast beam
CN116122308B (en) A prefabricated lattice beam slope protection structure and construction method thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant