CN111254800A - A composite beam suitable for urban bridges and its construction method - Google Patents

A composite beam suitable for urban bridges and its construction method Download PDF

Info

Publication number
CN111254800A
CN111254800A CN202010201545.4A CN202010201545A CN111254800A CN 111254800 A CN111254800 A CN 111254800A CN 202010201545 A CN202010201545 A CN 202010201545A CN 111254800 A CN111254800 A CN 111254800A
Authority
CN
China
Prior art keywords
steel
beams
longitudinal
cast
fulcrum
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010201545.4A
Other languages
Chinese (zh)
Inventor
贺耀北
刘榕
李文武
耿少波
陈�光
郑力之
曹伟
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hunan Provincial Communications Planning Survey and Design Institute Co Ltd
Original Assignee
Hunan Provincial Communications Planning Survey and Design Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hunan Provincial Communications Planning Survey and Design Institute Co Ltd filed Critical Hunan Provincial Communications Planning Survey and Design Institute Co Ltd
Priority to CN202010201545.4A priority Critical patent/CN111254800A/en
Publication of CN111254800A publication Critical patent/CN111254800A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D1/00Bridges in general
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D19/00Structural or constructional details of bridges
    • E01D19/12Grating or flooring for bridges; Fastening railway sleepers or tracks to bridges
    • E01D19/125Grating or flooring for bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The utility model provides a combination beam suitable for urban bridge, includes the coincide sub-roof beam of multi-disc parallel arrangement, the coincide sub-roof beam includes steel longeron and precast concrete decking, has set firmly the shear force spare on the steel longeron, is equipped with horizontal, vertical and anchor reinforcing bar in the precast decking, and horizontal reinforcing bar and vertical reinforcing bar stretch out to the outside, and the anchor reinforcing bar stretches out to the top, is equipped with vertical cast-in-place seam between the adjacent precast decking, is equipped with the cast-in-place decking of concrete on each precast decking and the vertical cast-in-place seam. The construction method comprises the following steps: manufacturing a steel longitudinal beam and presetting a shear part; erecting a prefabricated bridge deck formwork, laying steel bars in the prefabricated bridge deck, pouring prefabricated bridge deck concrete, demolding and storing to form a superposed sub-beam; transferring and hoisting the superposed sub-beams to be placed on the temporary support; pouring cast-in-place bridge decks and longitudinal cast-in-place seams; and (5) installing a permanent support and dismantling the temporary support. The invention has the advantages of light dead weight, convenient construction, capability of fully exerting the advantages of a combined structure, reasonable stress, strong bearing capacity and the like.

Description

一种适用于城市桥梁的组合梁及其施工方法A composite beam suitable for urban bridges and its construction method

技术领域technical field

本发明涉及桥梁工程技术领域,尤其涉及一种适用于城市桥梁的组合梁及其施工方法。The invention relates to the technical field of bridge engineering, in particular to a composite beam suitable for urban bridges and a construction method thereof.

背景技术Background technique

在城市桥梁建设中,越来越重视减少交通阻隔影响、注重环境保护、追求工程质量与效益的理念,因此选择合适的结构型式及相应的施工方法以满足“快捷、环保、高效”的建设理念是城市桥梁设计的重点、难点。In the construction of urban bridges, more and more attention is paid to the concept of reducing the impact of traffic barriers, focusing on environmental protection, and pursuing project quality and efficiency. Therefore, appropriate structural types and corresponding construction methods are selected to meet the construction concept of "fast, environmentally friendly and efficient". It is the focus and difficulty of urban bridge design.

近年来,城市桥梁建设进入飞速发展时期,预制装配梁在城市桥梁中所占比重日益增加。传统的预制装配结构(例如预制小箱梁、空心板)虽然设计施工都较为成熟,但施工工期较长,运输架设安装吨位较大,对施工条件和设备要求高,对交通干扰大。钢板组合梁由钢和混凝土两种材料通过连接组成整体,充分发挥了钢材的抗拉性能与混凝土的抗压性能,相比于传统的预制装配结构具有承载能力高、自重轻、刚度延性大、抗震性能好、施工方便等优点。但是传统的钢板组合梁在现场施工中依然存在大量的湿作业,施工时需要大量的模板;钢结构与混凝土桥面板分别加工预制,施工时先架设钢梁,再安装预制桥面板,最后浇筑湿接缝。这种施工方法存在以下问题:1、钢梁承担大部分恒载,而铺装及活载等小部分荷载由组合梁承担,没有充分发挥组合结构的优势。进一步地,该受力模式造成钢梁的梁高增加,主梁需设置竖向及水平加劲,增加施工难度。在净高受限时,需抬高线位,增加工程造价;2、受制于吊装能力与结构形式,桥面板一般采用纵向分段预制,不可避免的存在横向贯穿接缝,现场工作量大、质量不易控制,横向贯穿接缝成为结构的薄弱点;3、结构体系采用连续梁时,连接接头通常设置在弯矩较小的跨间位置,需设置临时墩,在高空完成钢梁的连接,施工难度大、施工精度低,措施费用高。In recent years, the construction of urban bridges has entered a period of rapid development, and the proportion of prefabricated beams in urban bridges has been increasing. Although the design and construction of traditional prefabricated assembly structures (such as prefabricated small box beams and hollow slabs) are relatively mature, the construction period is long, the tonnage of transportation, erection and installation is large, and the requirements for construction conditions and equipment are high, and the traffic interference is large. The steel plate composite beam is composed of two materials, steel and concrete, which are connected together to form a whole, which gives full play to the tensile performance of steel and the compressive performance of concrete. Good, convenient construction and so on. However, the traditional steel plate composite beam still has a lot of wet work in the field construction, and a lot of formwork is required during construction; the steel structure and the concrete bridge deck are prefabricated separately. During construction, the steel beam is erected first, then the prefabricated bridge deck is installed, and finally the wetted deck is poured. seam. This construction method has the following problems: 1. The steel beam bears most of the dead load, while a small part of the load such as pavement and live load is borne by the composite beam, which does not give full play to the advantages of the composite structure. Further, this stress mode causes the beam height of the steel beam to increase, and the main beam needs to be stiffened vertically and horizontally, which increases the difficulty of construction. When the clear height is limited, it is necessary to raise the line position and increase the project cost; 2. Subject to the hoisting capacity and structural form, the bridge deck is generally prefabricated in longitudinal sections, and there are inevitably horizontal penetration joints, which requires a large amount of on-site work, The quality is not easy to control, and the transverse penetration joints become the weak point of the structure; 3. When the structural system adopts continuous beams, the connecting joints are usually set at the position between the spans where the bending moment is small, and temporary piers need to be set up to complete the connection of steel beams at high altitude. The construction is difficult, the construction precision is low, and the cost of the measures is high.

发明内容SUMMARY OF THE INVENTION

本发明要解决的技术问题是克服现有技术的不足,提供一种自重轻、施工方便、能够充分发挥组合结构优势、受力合理、承载能力强的适用于城市桥梁的组合梁。The technical problem to be solved by the present invention is to overcome the deficiencies of the prior art and provide a composite beam suitable for urban bridges with light weight, convenient construction, full use of composite structure advantages, reasonable stress and strong bearing capacity.

本发明进一步提供一种上述适用于城市桥梁的组合梁的施工方法。The present invention further provides a construction method of the above-mentioned composite beam suitable for urban bridges.

为解决上述技术问题,本发明采用以下技术方案:In order to solve the above-mentioned technical problems, the present invention adopts the following technical solutions:

一种适用于城市桥梁的组合梁,包括多片沿横向平行布置的叠合子梁,所述叠合子梁包括钢纵梁和混凝土预制桥面板,所述钢纵梁上固设有剪力件并伸出至预制桥面板上方,所述预制桥面板内设有横向钢筋、纵向钢筋和锚固钢筋,所述横向钢筋和纵向钢筋伸出至预制桥面板外侧,所述锚固钢筋伸出至预制桥面板上方,横向相邻的两所述预制桥面板之间设有混凝土纵向现浇缝,各所述预制桥面板和纵向现浇缝上设有混凝土现浇桥面板。A composite beam suitable for urban bridges, comprising a plurality of composite sub-beams arranged in parallel in the transverse direction, the composite sub-beams include steel longitudinal beams and concrete prefabricated bridge decks, and shearing members are fixed on the steel longitudinal beams. Protruding to the top of the prefabricated bridge deck, the prefabricated bridge deck is provided with transverse reinforcement bars, longitudinal reinforcement bars and anchor reinforcement bars, the transverse reinforcement bars and longitudinal reinforcement bars protrude to the outside of the prefabricated bridge deck, and the anchor reinforcement bars are extended to the prefabricated bridge deck. Above, a longitudinal cast-in-place concrete joint is arranged between two laterally adjacent prefabricated bridge decks, and each of the prefabricated bridge decks and the longitudinal cast-in-place joint is provided with a concrete cast-in-place deck.

作为上述技术方案的进一步改进:横向相邻的两所述钢纵梁的之间固设有跨中钢横梁。跨中钢横梁可以提高体系的力学性能,钢纵梁自身的局部稳定性强。As a further improvement of the above technical solution, a mid-span steel cross beam is fixed between two transversely adjacent steel longitudinal beams. The mid-span steel beam can improve the mechanical properties of the system, and the steel longitudinal beam itself has strong local stability.

作为上述技术方案的进一步改进:所述预制桥面板下部与所述钢纵梁接触的位置厚度大于两侧的厚度。将预制桥面板下部与钢纵梁接触的位置厚度加大,形成倒梯形截面,有利于提高预制桥面板自身的受力性能。As a further improvement of the above technical solution, the thickness of the position where the lower part of the prefabricated bridge deck is in contact with the steel longitudinal beam is greater than the thickness of both sides. The thickness of the position where the lower part of the prefabricated bridge deck is in contact with the steel longitudinal beam is increased to form an inverted trapezoidal section, which is beneficial to improve the mechanical performance of the prefabricated bridge deck itself.

作为上述技术方案的进一步改进:还包括两道边支点横梁(也即位于桥梁两端部的横梁),两道边支点横梁之间设有至少一道中支点横梁(通常需要设置多道),所述边支点横梁与靠近边支点横梁的中支点横梁之间、以及相邻两道所述中支点横梁之间均连接有多片所述叠合子梁。As a further improvement of the above technical solution: it also includes two side fulcrum beams (that is, the beams located at both ends of the bridge), and at least one middle fulcrum beam (usually needs to be set up multiple) between the two side fulcrum beams, so A plurality of the laminated sub-beams are connected between the side fulcrum beam and the middle fulcrum beam close to the side fulcrum beam, and between two adjacent middle fulcrum beams.

作为上述技术方案的进一步改进:所述边支点横梁和中支点横梁均为现浇横梁,所述现浇桥面板靠近所述中支点横梁的一端留有后浇段,所述中支点横梁上端延伸至所述后浇段。边支点横梁和中支点横梁均采用现浇横梁,体系中仅有纵向现浇缝与墩顶现浇横梁,避免了在主要受力方向上的横向贯穿接缝,减少了结构的薄弱点及开裂风险,结构冗余度更高;现浇桥面板靠近中支点横梁的一端留有后浇段,相应的中支点横梁上端延伸至后浇段,使得现浇中支点横梁截面为T字形截面,相比常规的矩形截面,具有更好的力学性能和抗裂性能,结构也具有更好的整体性。As a further improvement of the above technical solution: the side fulcrum beam and the middle fulcrum beam are both cast-in-situ beams, the cast-in-place bridge deck is left with a post-cast section at one end of the middle fulcrum beam, and the upper end of the middle fulcrum beam extends to the post pouring section. Both the side fulcrum beam and the middle fulcrum beam are cast-in-place beams, and there are only longitudinal cast-in-place joints and cast-in-place beams at the top of the pier in the system, which avoids transverse penetration joints in the main stress direction and reduces the weak point and cracking of the structure. Risks and higher structural redundancy; the cast-in-place bridge deck is left with a post-cast section at one end of the beam near the mid-fulcrum point, and the upper end of the corresponding mid-fulcrum cross-beam extends to the post-cast section, so that the cast-in-place mid-fulcrum cross-beam has a T-shaped cross-section. Compared with the conventional rectangular section, it has better mechanical properties and crack resistance, and the structure also has better integrity.

作为上述技术方案的进一步改进:所述中支点横梁为高性能混凝土现浇横梁。高性能混凝土的加入可以将两侧的叠合子梁连接为整体,接缝位置可以达到比木材更好的力学性能,连接更为可靠。As a further improvement of the above technical solution: the middle fulcrum beam is a high-performance concrete cast-in-place beam. The addition of high-performance concrete can connect the composite sub-beams on both sides as a whole, and the joint position can achieve better mechanical properties than wood, and the connection is more reliable.

作为上述技术方案的进一步改进:所述边支点横梁和中支点横梁均为钢横梁,所述边支点横梁内侧沿长度方向预留多片第一连接纵梁,所述第一连接纵梁与靠近边支点横梁的钢纵梁一一对应固定连接,所述中支点横梁两侧沿长度方向预留多片第二连接纵梁,所述第二连接纵梁与靠近中支点横梁的钢纵梁一一对应固定连接。相比采用现浇横梁,边支点横梁和中支点横梁采用钢横梁,可以消除中支点横梁位置处的混凝土浇筑与养护,施工便捷、节约工期、连接可靠,进一步地,还可以取消盖梁,减小整体结构高度,降低线位,节省工程造价,对于净高受限的城市高架桥梁,具有广泛的发挥空间。As a further improvement of the above technical solution: the side fulcrum beam and the middle fulcrum beam are steel beams, and a plurality of first connecting longitudinal beams are reserved on the inner side of the side fulcrum beam along the length direction. The steel longitudinal beams of the side fulcrum beams are fixedly connected one by one, and a plurality of second connecting longitudinal beams are reserved on both sides of the middle fulcrum beam along the length direction. A corresponding fixed connection. Compared with cast-in-place beams, steel beams are used for side fulcrum beams and middle fulcrum beams, which can eliminate the concrete pouring and maintenance at the position of the middle fulcrum beams. The construction is convenient, the construction period is saved, and the connection is reliable. The overall structure height is small, the line position is reduced, and the engineering cost is saved. It has a wide range of development space for urban viaducts with limited clear height.

一种上述的适用于城市桥梁的组合梁的施工方法,包括以下步骤:A construction method of the above-mentioned composite beam suitable for urban bridges, comprising the following steps:

S1、制作各片钢纵梁并在钢纵梁上预设剪力件;S1. Make each piece of steel longitudinal beams and preset shear parts on the steel longitudinal beams;

S2、搭设预制桥面板模板,铺设预制桥面板内横向钢筋、纵向钢筋和锚固钢筋,浇筑预制桥面板混凝土,脱模并存放形成叠合子梁;S2. Set up the prefabricated bridge deck formwork, lay the transverse steel bars, longitudinal steel bars and anchoring steel bars in the prefabricated bridge deck, pour the prefabricated bridge deck concrete, demould and store them to form superimposed sub-beams;

S3、将叠合子梁转运至桥位,并吊装各片叠合子梁置于墩顶临时支座上;S3. Transfer the laminated sub-beam to the bridge position, and hoist each laminated sub-beam and place it on the temporary support on the top of the pier;

S4、铺设现浇桥面板和纵向现浇缝处钢筋网,浇筑现浇桥面板和纵向现浇缝混凝土;S4. Lay the cast-in-place bridge deck and the steel mesh at the longitudinal cast-in-place joints, and pour the cast-in-place bridge deck and the longitudinal cast-in-place joint concrete;

S6、待混凝土强度达到设计要求后,安装永久支座,拆除临时支座,完成从简支变连续的体系转换;S6. After the concrete strength reaches the design requirements, install the permanent support, remove the temporary support, and complete the system conversion from simply supported to continuous;

S7、施工桥面附属设施,完成全桥施工。S7. Construction of the auxiliary facilities of the bridge deck and completion of the whole bridge construction.

作为上述技术方案的进一步改进:当边支点横梁和中支点横梁采用现浇横梁时,相应的,步骤S4中,在浇筑现浇桥面板和纵向现浇缝混凝土之后,绑扎边支点横梁和中支点横梁钢筋,然后浇筑边支点横梁和中支点横梁混凝土。As a further improvement of the above technical solution: when the side fulcrum beam and the middle fulcrum beam are cast-in-place beams, correspondingly, in step S4, after pouring the cast-in-place bridge deck and the longitudinal cast-in-situ joint concrete, bind the side fulcrum beam and the middle fulcrum. Beam reinforcement, and then pour concrete for the side fulcrum beams and the center fulcrum beams.

作为上述技术方案的进一步改进:当边支点横梁和中支点横梁采用钢横梁时,相应的,步骤S1中,制作各片钢纵梁的同时制作边支点横梁和中支点横梁,步骤S3中,先吊装边支点横梁和中支点横梁,然后再吊装各片叠合子梁,将叠合子梁与对应的边支点横梁或中支点横梁固定连接,完成全桥架设。As a further improvement of the above technical solution: when the side fulcrum beam and the middle fulcrum beam are steel beams, correspondingly, in step S1, the side fulcrum beam and the middle fulcrum beam are made while making each piece of steel longitudinal beam, and in step S3, first Hoist the side fulcrum beam and the middle fulcrum beam, and then hoist each laminated sub-beam, and connect the superimposed sub-beam with the corresponding side fulcrum beam or the middle fulcrum beam to complete the whole bridge erection.

与现有技术相比,本发明的优点在于:本发明公开的适用于城市桥梁的组合梁,横桥向采用多片平行布置的叠合子梁,叠合子梁的钢纵梁与下层桥面板整体预制,预制桥面板作为桥面板的一部分参与受力,共同承担所有的恒载与活载,受力更合理,各叠合子梁横向通过上层现浇桥面板及纵向现浇缝实现连接,钢纵梁通过剪力件与下层预制桥面板、上层现浇桥面板进行连接,下层预制桥面板通过锚固钢筋上层现浇桥面板进行连接,将桥面板与钢纵梁连接为整体,保证了主梁的连接性能及整体受力性能,该体系能充分发挥钢-混凝土组合结构的优势,减少钢纵梁的梁高,降低线位,尤其适用于桥下净空受限的城市桥梁,有利于节约钢材、降低工程成本,整体优势明显;叠合子梁的钢纵梁与下层桥面板整体预制,上层桥面整体现浇,体系中仅有纵向现浇缝与墩顶现浇横梁(当中支点横梁采用混凝土现浇横梁的情况),避免了在主要受力方向上的横向贯穿接缝,减少了结构的薄弱点及开裂风险,结构性能更加可靠,耐久性好,冗余度更高;叠合子梁可以整跨预制、运输、安装,纵向连续接头设置在墩顶,不需要设置临时墩,降低了施工难度,节约工程造价;且由于叠合子梁仅包括钢梁及下层预制板,减少了大尺寸预制板制作及运输所带来的困难,吊装重量大大减轻,降低了吊装施工的难度,可以最大程度的利用常规设备,节约投资;桥面跨度、主梁布置间距与预制T梁、小箱梁相当,无需设置桥面横向预应力,构造简单,施工便捷,结构稳健性明显优于常规少主梁钢板组合梁。Compared with the prior art, the advantages of the present invention are: the composite beam disclosed in the present invention is suitable for urban bridges, and the transverse bridge adopts a plurality of stacked sub-girders arranged in parallel, and the steel longitudinal beams of the stacked sub-girders are integral with the lower deck deck. Prefabricated and prefabricated bridge decks participate in the force as part of the bridge deck, jointly bear all dead and live loads, and the stress is more reasonable. The beam is connected with the lower prefabricated bridge deck and the upper cast-in-situ bridge deck through shearing parts, and the lower prefabricated bridge deck is connected with the upper cast-in-situ deck by anchoring steel bars, and the bridge deck and the steel longitudinal beam are connected as a whole, which ensures the integrity of the main girder. Connection performance and overall stress performance, this system can give full play to the advantages of steel-concrete composite structure, reduce the beam height of steel longitudinal beams, and reduce the line position, especially suitable for urban bridges with limited clearance under the bridge, which is conducive to saving steel, The overall advantage is obvious in reducing engineering costs; the steel longitudinal beams of the superimposed sub-girders and the lower deck deck are integrally prefabricated, and the upper deck is cast-in-place as a whole. The case of pouring beams), avoiding the transverse penetration joints in the main stress direction, reducing the weak points of the structure and the risk of cracking, the structural performance is more reliable, the durability is good, and the redundancy is higher; the composite sub-beam can be integrated Across prefabrication, transportation, and installation, the longitudinal continuous joints are arranged on the top of the pier, and there is no need to set up temporary piers, which reduces the difficulty of construction and saves the cost of the project; and because the composite sub-beam only includes steel beams and lower prefabricated slabs, it reduces the need for large-sized prefabricated slabs. The difficulty caused by production and transportation, the weight of hoisting is greatly reduced, the difficulty of hoisting construction is reduced, the conventional equipment can be used to the greatest extent, and the investment is saved; There is no need to set the lateral prestress of the bridge deck, the structure is simple, the construction is convenient, and the structural robustness is obviously better than that of the conventional steel plate composite beam with few main beams.

本发明公开的适用于城市桥梁的组合梁的施工方法,叠合子梁整跨预制、运输、安装,纵向连续接头设置在墩顶,不需要设置临时墩,降低了施工难度,节约工程造价,下层预制桥面板在浇筑现浇桥面板时起到模板作用,从而可以简化施工,降低工程成本。The construction method of the composite beam suitable for urban bridges disclosed by the invention comprises the whole span prefabrication, transportation and installation of the composite sub-beam, the longitudinal continuous joint is arranged on the top of the pier, the temporary pier does not need to be arranged, the construction difficulty is reduced, the project cost is saved, and the lower layer The prefabricated bridge deck acts as a formwork when pouring the cast-in-place bridge deck, which can simplify the construction and reduce the engineering cost.

附图说明Description of drawings

图1是本发明适用于城市桥梁的组合梁的结构示意图。FIG. 1 is a schematic structural diagram of a composite beam of the present invention applicable to urban bridges.

图2是本发明中的叠合子梁的内部结构示意图。FIG. 2 is a schematic diagram of the internal structure of the laminated sub-beam in the present invention.

图3是本发明适用于城市桥梁的组合梁的俯视结构示意图。FIG. 3 is a schematic top view of the composite beam of the present invention applicable to urban bridges.

图4是本发明中的跨中钢横梁的结构示意图。4 is a schematic structural diagram of a mid-span steel beam in the present invention.

图5是本发明实施例一中的支点现浇横梁的结构示意图。FIG. 5 is a schematic structural diagram of a cast-in-place beam with a fulcrum in Embodiment 1 of the present invention.

图6是本发明实施例二中的钢横梁的结构示意图。6 is a schematic structural diagram of a steel beam in Embodiment 2 of the present invention.

图7是本发明实施例二中的中支点钢横梁的结构示意图。FIG. 7 is a schematic structural diagram of a middle fulcrum steel beam in Embodiment 2 of the present invention.

图8是本发明实施例二中的边支点钢横梁的结构示意图。FIG. 8 is a schematic structural diagram of a steel beam with a side fulcrum in Embodiment 2 of the present invention.

图中各标号表示:1、叠合子梁;11、钢纵梁;12、预制桥面板;13、剪力件;14、横向钢筋;15、纵向钢筋;16、锚固钢筋;17、纵向现浇缝;18、现浇桥面板;19、后浇段;2、边支点横梁;21、第一连接纵梁;3、中支点横梁;31、第二连接纵梁;4、跨中钢横梁。The symbols in the figure indicate: 1, superimposed sub-beam; 11, steel longitudinal beam; 12, prefabricated bridge deck; 13, shearing member; 14, transverse reinforcement; 15, longitudinal reinforcement; 16, anchoring reinforcement; 17, longitudinal cast-in-place 18. Cast-in-place bridge deck; 19. Post-casting section; 2. Side fulcrum beam; 21. First connecting longitudinal beam; 3. Middle fulcrum beam; 31. Second connecting longitudinal beam;

具体实施方式Detailed ways

以下结合说明书附图和具体实施例对本发明作进一步详细说明。The present invention will be further described in detail below with reference to the accompanying drawings and specific embodiments.

实施例一Example 1

图1至图5示出了本发明适用于城市桥梁的组合梁的第一种实施例,本实施例的适用于城市桥梁的组合梁包含6片叠合子梁1,相邻两片叠合子梁1的横向间距为2.3m。每片叠合子梁1包括钢纵梁11、预制桥面板12、剪力件13(例如常用的剪力钉等)、锚固钢筋16等。钢纵梁11采用工字型断面,梁高1100mm,包括钢纵梁顶板、钢纵梁腹板和钢纵梁底板,其中钢纵梁顶板宽400mm,厚16mm;钢纵梁腹板高1060mm,厚16mm;钢纵梁底板宽600mm,厚24mm。预制桥面板12宽度中梁和两侧的边梁分别为1900mm、1800mm,厚度均为150mm,所包含的预制板纵向钢筋15和预制板横向钢筋14伸出预制桥面板12外侧,便于搭接以连接成整体。叠合子梁1横桥向通过现浇桥面板18及纵向现浇缝17连接为整体,现浇桥面板18厚度为150mm,通过剪力件13、锚固钢筋16分别与钢纵梁11和预制桥面板12相连。纵向现浇缝17宽度为400mm,厚度为150mm,内设纵向普通钢筋、横向普通钢筋以及竖向普通钢筋,与预制板横向钢筋14相连。叠合子梁1纵向设两道及以上现浇横梁,边支点现浇横梁以及中支点现浇横梁的梁高均为1400mm,分别与叠合子梁1连接成为整体。1 to 5 show the first embodiment of the composite beam suitable for urban bridges according to the present invention. The composite beam suitable for urban bridges in this embodiment includes 6 laminated sub-beams 1, and two adjacent laminated sub-beams The horizontal spacing of 1 is 2.3m. Each laminated sub-beam 1 includes a steel longitudinal beam 11, a prefabricated bridge deck 12, a shearing member 13 (such as a commonly used shearing nail, etc.), an anchoring steel bar 16, and the like. The steel longitudinal beam 11 adopts an I-shaped section, and the beam height is 1100mm, including the steel longitudinal beam top plate, the steel longitudinal beam web plate and the steel longitudinal beam bottom plate. The steel longitudinal beam top plate is 400 mm wide and 16 mm thick; the steel longitudinal beam web plate is 1060 mm high. The thickness is 16mm; the steel longitudinal beam bottom plate is 600mm wide and 24mm thick. The width of the middle beam and the side beams on both sides of the prefabricated bridge deck 12 are 1900mm and 1800mm respectively, and the thickness is 150mm. The included prefabricated slab longitudinal steel bars 15 and prefabricated slab transverse steel bars 14 extend out of the prefabricated bridge deck 12, which is convenient for lap joints. connected as a whole. The transverse bridge direction of the superimposed sub-beam 1 is connected as a whole by the cast-in-place bridge deck 18 and the longitudinal cast-in-place joint 17. The thickness of the cast-in-place bridge deck 18 is 150mm. The panels 12 are connected. The longitudinal cast-in-place joint 17 has a width of 400mm and a thickness of 150mm, and is provided with longitudinal common steel bars, horizontal common steel bars and vertical common steel bars, and is connected with the transverse steel bars 14 of the prefabricated plate. The composite sub-beam 1 is longitudinally provided with two or more cast-in-situ beams, the side fulcrum cast-in-place beam and the middle fulcrum cast-in-place beam are both 1400mm high, and are respectively connected with the composite sub-beam 1 to form a whole.

进一步地,本实施例中,各片叠合子梁1横向连接除现浇桥面板18及纵向现浇缝17之外,还包括跨中钢横梁4,跨中钢横梁4同样采用工字形断面,梁高600mm,包括跨中钢横梁腹板、跨中钢横梁顶板和跨中钢横梁底板。其中,跨中钢横梁顶板和跨中钢横梁底板均宽300mm,厚16mm;钢横梁腹板高568mm,厚16mm。跨中钢横梁4与各片叠合子梁1之间通过多块拼接板以及高强螺栓实现固定连接。Further, in this embodiment, in addition to the cast-in-place bridge deck 18 and the longitudinal cast-in-place joint 17, the horizontal connection of each laminated sub-beam 1 also includes a mid-span steel beam 4, and the mid-span steel beam 4 also adopts an I-shaped section, The beam height is 600mm, including the mid-span steel beam web, the mid-span steel beam top plate and the mid-span steel beam bottom plate. Among them, the top plate of the steel beam across the middle and the bottom plate of the steel beam across the middle are both 300mm wide and 16mm thick; the steel beam web is 568mm high and 16mm thick. The steel beams 4 in the middle of the span and the laminated sub-beams 1 are fixedly connected by a plurality of splicing plates and high-strength bolts.

施工时,首先制作钢梁节段,在预制厂完成每孔钢纵梁11的拼接,随后在钢纵梁11上完成预制桥面板12,待混凝土强度达到设计强度后脱模并存放,形成叠合子梁1;接着将叠合子梁1运输至桥位,利用吊机吊运、安装,全桥架设完成后,浇筑现浇桥面板18及纵向现浇缝17,最后浇筑边支点横梁2和中支点横梁3,完成简支到连续的体系转换。During construction, the steel beam segments are first made, the splicing of each hole steel longitudinal beam 11 is completed in the prefabrication plant, and then the prefabricated bridge deck 12 is completed on the steel longitudinal beam 11. After the concrete strength reaches the design strength, it is demolded and stored to form a laminated sub-beam. 1; then transport the superimposed sub-beam 1 to the bridge position, use the crane to lift and install, after the whole bridge is erected, pour the cast-in-place bridge deck 18 and the longitudinal cast-in-place joint 17, and finally pour the side fulcrum beam 2 and the middle fulcrum beam. 3. Complete the transition from simply supported to continuous system.

本实施例的适用于城市桥梁的组合梁的施工方法具体如下:The construction method of the composite beam applicable to the urban bridge of the present embodiment is as follows:

1)分梁段加工制造钢纵梁11的钢纵梁顶板、钢纵梁腹板和钢纵梁底板,跨中钢横梁4腹板、跨中钢横梁顶板和跨中钢横梁底板,以及用于连接跨中钢横梁4与各片叠合子梁1的拼接钢板,在钢纵梁11的顶板上焊接剪力钉,完成每孔主梁段和跨中横梁段的拼接;1) The steel longitudinal beam top plate, steel longitudinal beam web and steel longitudinal beam bottom plate of steel longitudinal beam 11, the steel longitudinal beam bottom plate, the mid-span steel beam 4 web, the mid-span steel beam top plate and the mid-span steel beam bottom plate, and the For connecting the splicing steel plates of the steel cross beam 4 and each superposed sub-beam 1 in the span, the shear nails are welded on the top plate of the steel longitudinal beam 11 to complete the splicing of the main beam section of each hole and the cross beam section of the mid-span;

2)在预制厂预制台座上搭设预制桥面板12模板,铺设预制板纵向钢筋15、预制板横向钢筋14及锚固钢筋16,浇筑预制桥面板12混凝土,待混凝土强度达到设计值90%以上脱模,并存放,形成叠合子梁1;2) Set up the prefabricated bridge deck 12 formwork on the prefabricated pedestal of the prefabrication factory, lay the prefabricated slab longitudinal steel bars 15, the prefabricated slab transverse steel bars 14 and the anchoring steel bars 16, pour the prefabricated bridge deck 12 concrete, and demould when the concrete strength reaches more than 90% of the design value , and store it to form a composite sub-beam 1;

3)通过运梁设备将叠合子梁1等运至桥位,吊运安装各片叠合子梁1、跨中钢横梁4于临时支座上;3) Transport the laminated sub-beams 1 and the like to the bridge position by the beam transport equipment, and lift and install each laminated sub-beam 1 and the mid-span steel beam 4 on the temporary support;

4)铺设现浇桥面板18和纵向现浇缝17处钢筋网,浇筑现浇桥面板18及纵向现浇缝17混凝土;4) Lay the cast-in-place bridge deck 18 and the longitudinal cast-in-place joint 17 steel meshes, and pour the cast-in-place bridge deck 18 and the longitudinal cast-in-place joint 17 concrete;

5)绑扎边支点横梁2和中支点横梁3钢筋,浇筑边支点横梁2和中支点横梁3混凝土;5) Bind the side fulcrum beam 2 and the middle fulcrum beam 3 steel bars, and pour the side fulcrum beam 2 and the middle fulcrum beam 3 concrete;

6)待混凝土强度达到设计强度后,安装永久支座,拆除临时支座,完成简支变连续的体系转换;6) After the concrete strength reaches the design strength, install the permanent support, remove the temporary support, and complete the system conversion from simply support to continuous;

7)施工桥面铺装、栏杆及其他附属设施,完成全桥施工。7) Construction of bridge deck pavement, railings and other auxiliary facilities to complete the whole bridge construction.

实施例二Embodiment 2

图6至图8示出了本发明适用于城市桥梁的组合梁的第二种实施例,本实施例的适用于城市桥梁的组合梁与实施例一基本相同,不同之处在于,中支点横梁3和边支点横梁2均采用钢横梁,边支点钢横梁的梁高1300mm,宽1100mm,边支点钢横梁底板21宽1500mm,厚28mm,纵向通过第一连接纵梁21与钢纵梁11相连,其中第一连接纵梁21顶板与钢纵梁11顶板通过焊接连接,第一连接纵梁21腹板与钢纵梁11腹板通过拼接钢板和高强螺栓固定连接,第一连接纵梁21底板与钢纵梁11的腹板通过拼接钢板和高强螺栓固定连接;中支点钢横梁的梁高1300mm,宽1500mm,中支点钢横梁的底板23宽1900mm,厚28mm,纵向通过两侧预留的第二连接纵梁31与钢纵梁11相连,其中,第二连接纵梁31顶板与钢纵梁11顶板通过焊接连接,第二连接纵梁31腹板与钢纵梁11腹板通过拼接钢板和高强螺栓固定连接,第二连接纵梁31底板与钢纵梁11腹板通过拼接钢板和高强螺栓固定连接。6 to 8 show the second embodiment of the composite beam applicable to urban bridges of the present invention. The composite beam applicable to urban bridges in this embodiment is basically the same as the first embodiment, the difference is that the middle fulcrum beam 3 and the side fulcrum beam 2 are made of steel beams. The beam height of the side fulcrum steel beam is 1300mm and the width is 1100mm. The side fulcrum steel beam bottom plate 21 is 1500mm wide and 28mm thick. The top plate of the first connecting longitudinal beam 21 and the top plate of the steel longitudinal beam 11 are connected by welding, the web of the first connecting longitudinal beam 21 and the web plate of the steel longitudinal beam 11 are fixedly connected by splicing steel plates and high-strength bolts, and the bottom plate of the first connecting longitudinal beam 21 is connected to the The webs of the steel longitudinal beams 11 are fixedly connected by splicing steel plates and high-strength bolts; the beam height of the middle fulcrum steel beam is 1300mm and the width is 1500mm, and the bottom plate 23 of the middle fulcrum steel beam is 1900mm wide and 28mm thick. The connecting longitudinal beam 31 is connected with the steel longitudinal beam 11, wherein the top plate of the second connecting longitudinal beam 31 and the top plate of the steel longitudinal beam 11 are connected by welding, and the web of the second connecting longitudinal beam 31 and the web plate of the steel longitudinal beam 11 are connected by splicing steel plates and high-strength steel beams. Bolted connection, the bottom plate of the second connecting longitudinal beam 31 and the web of the steel longitudinal beam 11 are fixedly connected by splicing steel plates and high-strength bolts.

本实施实例适用于城市桥梁的组合梁的施工方法具体如下:This embodiment is applicable to the construction method of the composite beam of urban bridges as follows:

1)分梁段加工制造钢纵梁11的钢纵梁顶板、钢纵梁腹板和钢纵梁底板,边支点钢横梁、中支点钢横梁,跨中钢横梁4腹板、跨中钢横梁顶板和跨中钢横梁底板,以及用于连接跨中钢横梁4与各片叠合子梁1的拼接钢板,在钢纵梁11的顶板上焊接剪力钉,完成每孔主梁段和跨中横梁段的拼接;1) The steel longitudinal beam top plate, steel longitudinal beam web plate and steel longitudinal beam bottom plate of steel longitudinal beam 11 are processed and manufactured by beam section, side fulcrum steel beam, middle fulcrum steel beam, span middle steel beam 4 web, span middle steel beam The top plate and the bottom plate of the steel beam in the middle span, as well as the spliced steel plates used to connect the steel beam 4 in the middle span and each superposed sub-beam 1, weld shear nails on the top plate of the steel longitudinal beam 11 to complete the main beam section of each hole and the middle span. Splicing of beam sections;

2)在预制厂预制台座上搭设预制桥面板12模板,铺设预制板纵向钢筋15、预制板横向钢筋14及锚固钢筋16,浇筑预制桥面板12混凝土,待混凝土强度达到设计值90%以上脱模,并存放,形成叠合子梁1;2) Set up the prefabricated bridge deck 12 formwork on the prefabricated pedestal of the prefabrication factory, lay the prefabricated slab longitudinal steel bars 15, the prefabricated slab transverse steel bars 14 and the anchoring steel bars 16, pour the prefabricated bridge deck 12 concrete, and demould when the concrete strength reaches more than 90% of the design value , and store it to form a composite sub-beam 1;

3)通过运梁设备将叠合子梁1等运至桥位,先行吊装边支点钢横梁13、中支点钢横梁14,再吊运安装各片叠合子梁1、跨中钢横梁4于临时支座上,然后再通过边支点钢横梁预留的上第一连接纵梁21、中支点钢横梁预留的第二连接纵梁31的顶板与钢纵梁11顶板焊接,第一连接纵梁21、第二连接纵梁31的腹板、底板、与钢纵梁11的腹板、底板栓接,完成全桥架设;3) Transport the laminated sub-beams 1 and the like to the bridge position through the beam transport equipment, first hoist the side fulcrum steel beam 13 and the middle fulcrum steel beam 14, and then hoist and install each laminated sub-beam 1 and the mid-span steel beam 4 on the temporary support. On the seat, then through the upper first connecting longitudinal beam 21 reserved by the side fulcrum steel beam, the top plate of the second connecting longitudinal beam 31 reserved by the middle fulcrum steel beam is welded with the top plate of the steel longitudinal beam 11, and the first connecting longitudinal beam 21 , The web and bottom plate of the second connecting longitudinal beam 31 are bolted to the web and bottom plate of the steel longitudinal beam 11 to complete the erection of the full bridge;

4)铺设现浇桥面板18和纵向现浇缝17处钢筋网,浇筑现浇桥面板18及纵向现浇缝17混凝土;4) Lay the cast-in-place bridge deck 18 and the longitudinal cast-in-place joint 17 steel meshes, and pour the cast-in-place bridge deck 18 and the longitudinal cast-in-place joint 17 concrete;

5)待混凝土强度达到设计强度后,安装永久支座,拆除临时支座,完成简支变连续的体系转换;5) After the concrete strength reaches the design strength, install the permanent support, remove the temporary support, and complete the system conversion from simply support to continuous;

6)施工桥面铺装、栏杆及其他附属设施,完成全桥施工。6) Construction of bridge deck pavement, railings and other auxiliary facilities to complete the whole bridge construction.

虽然本发明已以较佳实施例揭露如上,然而并非用以限定本发明。任何熟悉本领域的技术人员,在不脱离本发明技术方案范围的情况下,都可利用上述揭示的技术内容对本发明技术方案做出许多可能的变动和修饰,或修改为等同变化的等效实施例。因此,凡是未脱离本发明技术方案的内容,依据本发明技术实质对以上实施例所做的任何简单修改、等同变化及修饰,均应落在本发明技术方案保护的范围内。Although the present invention has been disclosed above with preferred embodiments, it is not intended to limit the present invention. Any person skilled in the art, without departing from the scope of the technical solution of the present invention, can make many possible changes and modifications to the technical solution of the present invention by using the technical content disclosed above, or modify it into an equivalent implementation of equivalent changes. example. Therefore, any simple modifications, equivalent changes and modifications made to the above embodiments according to the technical essence of the present invention without departing from the content of the technical solutions of the present invention should fall within the protection scope of the technical solutions of the present invention.

Claims (10)

1. The utility model provides a composite beam suitable for city bridge which characterized in that: the composite bridge deck slab comprises a plurality of composite sub-beams (1) which are arranged in parallel in the transverse direction, wherein each composite sub-beam (1) comprises a steel longitudinal beam (11) and a concrete prefabricated bridge deck (12), a shear part (13) is fixedly arranged on each steel longitudinal beam (11) and extends out of the upper side of each prefabricated bridge deck (12), transverse reinforcing steel bars (14), longitudinal reinforcing steel bars (15) and anchoring reinforcing steel bars (16) are arranged in each prefabricated bridge deck (12), each transverse reinforcing steel bar (14) and each longitudinal reinforcing steel bar (15) extend out of the outer side of each prefabricated bridge deck (12), each anchoring reinforcing steel bar (16) extends out of the upper side of each prefabricated bridge deck (12), a concrete longitudinal cast-in-place seam (17) is arranged between every two transversely adjacent prefabricated bridge decks (12), and cast-in-place concrete bridge decks (18) are arranged on each prefabricated bridge deck (12) and each longitudinal.
2. The composite beam suitable for urban bridges of claim 1, wherein: a midspan steel cross beam (4) is fixedly arranged between two transversely adjacent steel longitudinal beams (11).
3. The composite beam suitable for urban bridges of claim 1, wherein: the thickness of the lower part of the prefabricated bridge deck (12) in contact with the steel longitudinal beam (11) is larger than that of the two sides.
4. The composite beam suitable for urban bridges of any one of claims 1 to 3, wherein: the folding device is characterized by further comprising two side fulcrum beams (2), at least one middle fulcrum beam (3) is arranged between the two side fulcrum beams (2), and a plurality of folding sub-beams (1) are connected between the side fulcrum beams (2) and the middle fulcrum beams (3) close to the side fulcrum beams (2) and between the adjacent two middle fulcrum beams (3).
5. The composite beam suitable for urban bridges of claim 4, wherein: the side fulcrum beam (2) and the middle fulcrum beam (3) are both cast-in-place beams, a post-cast section (19) is reserved at one end, close to the middle fulcrum beam (3), of the cast-in-place bridge deck (18), and the upper end of the middle fulcrum beam (3) extends to the post-cast section (19).
6. The composite beam suitable for urban bridges of claim 5, wherein: the middle fulcrum beam (3) is a high-performance concrete cast-in-place beam.
7. The composite beam suitable for urban bridges of claim 4, wherein: the steel beam is characterized in that the edge fulcrum beam (2) and the middle fulcrum beam (3) are steel beams, a plurality of first connecting longitudinal beams (21) are reserved on the inner side of the edge fulcrum beam (2) along the length direction, the first connecting longitudinal beams (21) are fixedly connected with the steel longitudinal beams (11) close to the edge fulcrum beam (2) in a one-to-one correspondence mode, a plurality of second connecting longitudinal beams (31) are reserved on the two sides of the middle fulcrum beam (3) along the length direction, and the second connecting longitudinal beams (31) are fixedly connected with the steel longitudinal beams (11) close to the middle fulcrum beam (3) in a one-to-one correspondence mode.
8. The construction method of a composite girder applicable to an urban bridge according to any one of claims 1 to 7, wherein: the method comprises the following steps:
s1, manufacturing each steel longitudinal beam (11) and presetting a shearing force piece (13) on each steel longitudinal beam (11);
s2, erecting a prefabricated bridge deck (12) template, laying transverse steel bars (14), longitudinal steel bars (15) and anchoring steel bars (16) in the prefabricated bridge deck (12), pouring concrete of the prefabricated bridge deck (12), demolding and storing to form a superposed sub-beam (1);
s3, transferring the superposed sub-beams (1) to a bridge site, and hoisting each superposed sub-beam (1) to be placed on the pier top temporary support;
s4, laying a cast-in-situ bridge deck (18) and a reinforcing mesh at the longitudinal cast-in-situ seam (17), and pouring concrete of the cast-in-situ bridge deck (18) and the longitudinal cast-in-situ seam (17);
s6, after the concrete strength meets the design requirement, installing a permanent support, and removing a temporary support to complete the system conversion from simple support to continuous support;
and S7, constructing auxiliary facilities of the bridge floor to finish full-bridge construction.
9. The construction method of the composite girder applicable to urban bridges according to claim 8, wherein: in the step S4, after concrete of the cast-in-place bridge deck (18) and the longitudinal cast-in-place seam (17) is poured, reinforcing steel bars of the side fulcrum beam (2) and the middle fulcrum beam (3) are bound, and then concrete of the side fulcrum beam (2) and the middle fulcrum beam (3) is poured.
10. The construction method of the composite girder applicable to urban bridges according to claim 8, wherein: in the step S1, the side fulcrum beam (2) and the middle fulcrum beam (3) are manufactured while the steel longitudinal beams (11) are manufactured, in the step S3, the side fulcrum beam (2) and the middle fulcrum beam (3) are hoisted firstly, then the superposed sub-beams (1) are hoisted, the superposed sub-beams (1) are fixedly connected with the corresponding side fulcrum beam (2) or middle fulcrum beam (3), and full-bridge erection is completed.
CN202010201545.4A 2020-03-20 2020-03-20 A composite beam suitable for urban bridges and its construction method Pending CN111254800A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010201545.4A CN111254800A (en) 2020-03-20 2020-03-20 A composite beam suitable for urban bridges and its construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010201545.4A CN111254800A (en) 2020-03-20 2020-03-20 A composite beam suitable for urban bridges and its construction method

Publications (1)

Publication Number Publication Date
CN111254800A true CN111254800A (en) 2020-06-09

Family

ID=70947856

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010201545.4A Pending CN111254800A (en) 2020-03-20 2020-03-20 A composite beam suitable for urban bridges and its construction method

Country Status (1)

Country Link
CN (1) CN111254800A (en)

Cited By (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112482231A (en) * 2020-11-27 2021-03-12 上海宝冶冶金工程有限公司 Construction method for prefabricated section of upper structure of viaduct
CN112502017A (en) * 2020-11-03 2021-03-16 中铁大桥勘测设计院集团有限公司 Durable web butt-joint type prefabricated combined beam bridge and construction method
CN113832826A (en) * 2021-10-09 2021-12-24 南京理工大学 Prestressed concrete slab beam bridge type and construction method thereof
CN114575260A (en) * 2022-03-22 2022-06-03 中铁宝桥(扬州)有限公司 Positioning and adjusting device for steel plate combined beam
CN115387196A (en) * 2022-08-17 2022-11-25 中铁大桥局集团第五工程有限公司 A steel-concrete composite continuous beam without wet joints and its construction method

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101239179B1 (en) * 2012-11-21 2013-03-05 주식회사 인터컨스텍 Construction method for prestressed concrete bulb-t girder bridge
CN105256723A (en) * 2015-09-01 2016-01-20 中铁大桥勘测设计院集团有限公司 Multi-girder section steel-doublelayer concrete bridge deck composite beam implementing technology
CN106284045A (en) * 2016-09-19 2017-01-04 武汉理工大学 A kind of secondary overlapping concrete slab girder steel combined bridge structure and construction method thereof
CN106677049A (en) * 2017-01-20 2017-05-17 福州大学 Assembled steel-concrete combination structure bridge and construction method
CN108118610A (en) * 2017-12-26 2018-06-05 上海市政工程设计研究总院(集团)有限公司 A kind of ultra-high performance concrete and regular reinforcement concrete combination beam
CN109082998A (en) * 2018-07-05 2018-12-25 湖南省交通规划勘察设计院有限公司 Integral prefabricated steel plate combination girder construction and construction method
CN212477387U (en) * 2020-03-20 2021-02-05 湖南省交通规划勘察设计院有限公司 Combination beam suitable for urban bridge

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR101239179B1 (en) * 2012-11-21 2013-03-05 주식회사 인터컨스텍 Construction method for prestressed concrete bulb-t girder bridge
CN105256723A (en) * 2015-09-01 2016-01-20 中铁大桥勘测设计院集团有限公司 Multi-girder section steel-doublelayer concrete bridge deck composite beam implementing technology
CN106284045A (en) * 2016-09-19 2017-01-04 武汉理工大学 A kind of secondary overlapping concrete slab girder steel combined bridge structure and construction method thereof
CN106677049A (en) * 2017-01-20 2017-05-17 福州大学 Assembled steel-concrete combination structure bridge and construction method
CN108118610A (en) * 2017-12-26 2018-06-05 上海市政工程设计研究总院(集团)有限公司 A kind of ultra-high performance concrete and regular reinforcement concrete combination beam
CN109082998A (en) * 2018-07-05 2018-12-25 湖南省交通规划勘察设计院有限公司 Integral prefabricated steel plate combination girder construction and construction method
CN212477387U (en) * 2020-03-20 2021-02-05 湖南省交通规划勘察设计院有限公司 Combination beam suitable for urban bridge

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112502017A (en) * 2020-11-03 2021-03-16 中铁大桥勘测设计院集团有限公司 Durable web butt-joint type prefabricated combined beam bridge and construction method
CN112482231A (en) * 2020-11-27 2021-03-12 上海宝冶冶金工程有限公司 Construction method for prefabricated section of upper structure of viaduct
CN113832826A (en) * 2021-10-09 2021-12-24 南京理工大学 Prestressed concrete slab beam bridge type and construction method thereof
CN114575260A (en) * 2022-03-22 2022-06-03 中铁宝桥(扬州)有限公司 Positioning and adjusting device for steel plate combined beam
CN114575260B (en) * 2022-03-22 2023-09-22 中铁宝桥(扬州)有限公司 Positioning and adjusting device for steel plate composite beam
CN115387196A (en) * 2022-08-17 2022-11-25 中铁大桥局集团第五工程有限公司 A steel-concrete composite continuous beam without wet joints and its construction method

Similar Documents

Publication Publication Date Title
CN109082998B (en) Integral prefabricated steel plate combination beam structure and construction method
CN109958049B (en) Modular steel-concrete combined small box girder simply-supported continuous bridge and construction method thereof
CN111254800A (en) A composite beam suitable for urban bridges and its construction method
CN108978434B (en) Bracket-free industrialized construction method of steel-concrete combined continuous box girder bridge
CN204662235U (en) A kind of steel plate combination T beam bridge
CN114592436B (en) Pier capping beam lower support system and construction method thereof
CN108824162A (en) A kind of steel_concrete composite beam and its construction method using plain plate and corrugated sheet steel mixing web
CN111206489A (en) An assembled corrugated web steel box-UHPC composite girder bridge and construction method
CN106894326A (en) The construction method of assembled pretensioned prestressing corrugated steel web plate composite box girder
CN109024225A (en) Ultra-high performance concrete truss arch blade unit, truss arch piece bridge and construction method
CN110344315A (en) A kind of Long span steel reinforced concrete combined bridge structure and construction technology
CN106930181A (en) A kind of simple-supported thencontinuous steel reinforced concrete combined bridge hogging moment area structure
CN112458877A (en) Assembled steel-concrete combined rigid frame bridge and construction method thereof
CN111877182A (en) Novel construction method for upper structure of multi-chamber continuous UHPC box girder bridge
CN110863417A (en) A fast-installed steel-concrete composite girder bridge and its construction method
CN207973983U (en) It can rapidly-assembled precast bridge
CN112982162A (en) Steel bar truss type steel-concrete combined bridge deck and construction method
CN211522899U (en) Long-span steel-concrete composite beam convenient to erect by bridge girder erection machine
CN206655141U (en) A kind of steel cantilever combined bridge deck widens reconstruction structure
CN110184903B (en) A truss-type prefabricated pipe column assembled bridge pier
CN211947879U (en) Assembled corrugated web steel box-UHPC (ultra high performance concrete) combined beam bridge
CN106835930B (en) A kind of bolt connecting type steel concrete combination beam
CN109972512B (en) Cast-in-place construction method of profiled steel sheet-concrete combined bridge deck slab
CN108221704B (en) Four-beam type I-steel-concrete composite beam for bridge and construction method
CN210596966U (en) Large-span steel-concrete composite bridge structure

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information
CB02 Change of applicant information

Address after: No. 598, Section 1, Yueliangdao Road, Wangcheng District, Changsha City, Hunan Province

Applicant after: HUNAN PROVINCIAL COMMUNICATIONS PLANNING SURVEY AND DESIGN INSTITUTE Co.,Ltd.

Address before: No. 598, Yueliang Island, Wangcheng District, Changsha City, Hunan Province

Applicant before: HUNAN PROVINCIAL COMMUNICATIONS PLANNING SURVEY AND DESIGN INSTITUTE Co.,Ltd.