CN111236230A - Construction method of pre-arranged type fracture concrete pile head - Google Patents

Construction method of pre-arranged type fracture concrete pile head Download PDF

Info

Publication number
CN111236230A
CN111236230A CN202010052258.1A CN202010052258A CN111236230A CN 111236230 A CN111236230 A CN 111236230A CN 202010052258 A CN202010052258 A CN 202010052258A CN 111236230 A CN111236230 A CN 111236230A
Authority
CN
China
Prior art keywords
jack
concrete
pile head
construction method
upper side
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010052258.1A
Other languages
Chinese (zh)
Inventor
林广东
邵一鸣
丁富军
高楠楠
刘庆洋
邓祖华
黄玉良
陈善波
贾晓峰
骆鹏程
徐普恩
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Individual
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN202010052258.1A priority Critical patent/CN111236230A/en
Publication of CN111236230A publication Critical patent/CN111236230A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D9/00Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof
    • E02D9/005Removing sheet piles bulkheads, piles, mould-pipes or other moulds or parts thereof removing the top of placed piles of sheet piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same

Landscapes

  • Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Piles And Underground Anchors (AREA)

Abstract

The invention relates to the field of civil engineering pile foundation construction, and discloses a construction method of a pre-arranged type fracture concrete pile head, which comprises the following steps of A, fixing a jack group on the upper side of a reinforcement cage (1) on a pre-section (2), arranging jacks (3) in the reinforcement cage (1), installing the reinforcement cage (1), and pouring concrete; B. after the concrete is solidified, pressurizing the jack group to pre-fracture the concrete at the position of the pre-fracture surface (2); C. after the foundation pit is excavated, continuing pressurizing the jack group, jacking the concrete on the upper side of the pre-fracture surface (2), and integrally hoisting the concrete on the upper side of the pre-fracture surface (2) by using a crane; D. and recovering the jack group for next use after finishing. The jack group generates upward jacking force on the concrete with the fractured pre-fracture surface, so that the concrete on the upper side of the fractured pre-fracture surface can be conveniently lifted off; the construction difficulty of prying the concrete on the upper side of the pre-fracture surface is simplified, the construction period of the project is ensured, and the potential safety hazard of the occupational health of workers is eliminated.

Description

Construction method of pre-arranged type fracture concrete pile head
Technical Field
The invention relates to the field of civil engineering pile foundation construction, in particular to a construction method of a pre-positioned type broken concrete pile head.
Background
In the existing construction of the cast-in-situ bored pile, the common method is as follows: chiseling with a small machine or cutting the pile head concrete at the designed elevation position by a cutting machine, chiseling the protective layer concrete of the super-sealed pile head manually, stripping the main reinforcement from the lateral direction, and cleaning the pile head concrete in blocks. The traditional construction method has the following defects: (1) the construction efficiency is low. The man-made construction breaks the poor working environment of the concrete pile head for 1-1.5 days (2). The stripping of the main reinforcement protective layer takes longer time, more construction dust and large noise. (3) The recovery of the waste concrete is difficult. After cutting, the large concrete is difficult to transport out of the foundation pit. (4) The construction quality is greatly influenced. When the main bar protective layer is peeled off, the reinforcing bar is damaged, and bending deformation of the reinforcing bar is caused, so that the tensile strength is reduced, and the joint position becomes a weak point. (5) The construction cost is high. The pile head construction period is long, and the costs of precipitation, water resistance, labor and machinery are high. (6) The construction potential safety hazard is many. In the construction process, electric shock, falling, crushing, collapse and other potential safety hazards exist.
Disclosure of Invention
Aiming at the defects in the prior art, the invention provides a construction method of a pre-arranged type broken concrete pile head.
In order to solve the technical problem, the invention is solved by the following technical scheme:
a construction method of a pre-arranged type fracture concrete pile head comprises the following steps,
A. the steel bars on the upper side of the pre-section of the steel bar cage are sleeved with a first wrapping layer; and fixing the jack group on the steel bars on the upper side of the pre-fracture surface, wherein the jack group comprises at least two jacks, the jacks are all arranged in a steel bar cage, the outer side of each jack is sleeved with a second wrapping layer, the steel bar cage is installed, and the concrete is poured. The sounding pipe and the hanging ribs are bound on the reinforcing steel bars, and the sounding pipe and the hanging ribs are both sleeved with the first wrapping layer. The steel bars in the steel bar cage are detection tubes.
B. After the concrete is solidified, pressurizing the jack group to break the concrete on the surface where the pre-section is located; pressurizing the jack set 1-2 days after the concrete is solidified (the strength is greater than 10 MPa), so that the concrete on the surface where the pre-section is located is broken.
C. After the foundation pit is excavated, continuously pressurizing the jack group, jacking the concrete on the upper side of the pre-fracture surface, and hoisting the concrete on the upper side of the pre-fracture surface away by using a crane;
D. recovering the jack group, and finishing for the next use; and recovering the first sleeve sleeved at the upper end of the reinforcement cage.
Preferably, the jack is a solid jack or a hollow jack, the reinforcement cage comprises at least three main reinforcement bars, and the solid jack or the hollow jack is arranged between the adjacent main reinforcement bars.
Preferably, the jack is arranged on the inner side or the outer side of the reinforcement cage, and the jack is a solid jack or a hollow jack.
Preferably, the jack is a hollow jack, the reinforcement cage comprises at least three main reinforcement bars, and the hollow jack is sleeved on the main reinforcement bars.
Preferably, a first wrapping layer is arranged between the hollow jack and the main reinforcing steel bars.
Preferably, the material of the first and second wrapping layers is a release medium. The first wrapping layer and the second wrapping layer are made of wrapping isolation media such as pearl wool, polyurethane or paper pulp.
Preferably, the pre-section is further provided with a cavity ring. The connecting pipe and the fixed plate of the jack group are arranged at the inner side of the cavity ring. The cavity ring reduces the cross section of the concrete, and the fracture of the pre-fracture surface is facilitated. The fixing plate is made of recyclable materials such as a rubber plate or a wood plate.
Preferably, the pre-section is also provided with a medium surface, and the medium surface is arranged at the lower end of the jack group.
Preferably, the jacks are connected in series or in parallel.
Preferably, the jack group further comprises oil pipes, and the jacks are connected in series through the oil pipes.
The jack group can automatically lift and separate from concrete, and stable recycling is realized.
The pre-arranged type breaking device for breaking the concrete pile head can be used for conveniently and automatically breaking and separating the concrete at the designed position of the pile top, so that the subsequent pile head concrete separation work efficiency is improved, the engineering construction cost is saved, the environmental pollution is reduced, the occupational health safety of workers is ensured, the engineering safety risk is reduced, and the engineering quality is improved. Due to the adoption of the technical scheme, the invention has obvious technical effect and social effect: the jack sets (hollow jacks or solid jacks) which are all arranged in the reinforcement cage are started, pressure is firstly generated on the concrete (namely, the pre-section) around the jack sets, and the pre-section concrete is broken. Starting again, the hollow jack or the solid jack generates upward pressure on the concrete with the fractured pre-fracture surface, so that the concrete on the upper side of the fractured pre-fracture surface can be conveniently lifted off; the construction difficulty of prying the concrete on the upper side of the pre-fracture surface by workers is simplified, the construction time is saved, the environmental pollution is reduced, and the occupational health and safety of the workers are guaranteed.
The interlayer is arranged on the outer side of the reinforcement cage, so that the reinforcement cage and the concrete are separated by the interlayer, and the gripping force cannot be formed; when the concrete on the upper side of the pre-fault is recycled, the concrete is easy to separate from the reinforcement cage. The outer side of the hollow jack or the solid jack is provided with a sleeve which is convenient to recover. The device has compact structure and convenient operation.
The cavity ring or the medium surface is used for protecting the jack group, so that the jack group can be conveniently recovered from concrete; has the advantages of low cost, recovery time saving and the like.
Drawings
FIG. 1 is a schematic structural view of example 1.
FIG. 2 is a schematic structural view of example 2.
FIG. 3 is a schematic structural view of embodiment 3.
FIG. 4 is a schematic structural view of example 4.
FIG. 5 is a schematic structural view of example 5.
Fig. 6 is a schematic structural diagram of the present invention.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings and examples. As shown, 6 is a foundation or casing.
Example 1
A construction method of a pre-arranged type fracture concrete pile head, as shown in figures 1 and 6, comprising the following steps,
A. sleeving a first wrapping layer 11 on the upper side of the pre-section of the reinforcement cage 1, fixing a jack group on the reinforcement cage 1 on the upper side of the pre-section 2, wherein the jack group comprises at least two jacks 3, the jacks 3 are all arranged in the reinforcement cage 1, sleeving a second wrapping layer 31 on the outer sides of the jacks 3 (the first wrapping layer 11 and the second wrapping layer 31 are made of wrapping isolation media such as pearl wool, polyurethane or paper pulp), installing the reinforcement cage 1, and pouring concrete;
B. after the concrete is solidified, pressurizing the jack group to break the concrete of the layer where the pre-section 2 is located;
C. continuing to pressurize the jack group, jacking the concrete on the upper side of the pre-fracture surface 2, and lifting away the concrete on the upper side of the pre-fracture surface 2;
D. and (5) recovering the jack group, and dismantling the first sleeve 11 sleeved at the upper end of the reinforcement cage 1.
The jack 3 is a solid jack or a hollow jack, the reinforcement cage 1 comprises at least three main reinforcement bars 12, and the solid jack or the hollow jack is arranged between the adjacent main reinforcement bars 12. The jack group also comprises an oil pipe 5, and the jacks 3 are connected in series through the oil pipe 5.
Example 2
A construction method of a pre-positioned type broken concrete pile head, as shown in figures 2 and 6, comprising the following steps,
A. sleeving a first wrapping layer 11 on the upper side of the pre-section of the reinforcement cage 1, fixing a jack group on the reinforcement cage 1 on the upper side of the pre-section 2, wherein the jack group comprises at least two jacks 3, the jacks 3 are all arranged in the reinforcement cage 1, sleeving a second wrapping layer 31 on the outer sides of the jacks 3 (the materials of the first wrapping layer 11 and the second wrapping layer 31 are pearl cotton or polyurethane or paper pulp), installing the reinforcement cage 1, and pouring concrete;
B. after the concrete is solidified, pressurizing the jack group to break the concrete of the layer where the pre-section 2 is located;
C. continuing to pressurize the jack group, jacking the concrete on the upper side of the pre-fracture surface 2, and lifting away the concrete on the upper side of the pre-fracture surface 2;
D. and (5) recovering the jack group, and dismantling the first sleeve 11 sleeved at the upper end of the reinforcement cage 1.
The jack 3 is a solid jack or a hollow jack, and the solid jack or the hollow jack is arranged on the inner side of the reinforcement cage 1. The jack group also comprises an oil pipe 5, and the jacks 3 are connected in series through the oil pipe 5.
Example 3
A construction method of a pre-positioned type broken concrete pile head, as shown in figures 3 and 6, comprising the following steps,
A. sleeving a first wrapping layer 11 on the upper side of the pre-section of the reinforcement cage 1, fixing a jack group on the reinforcement cage 1 on the upper side of the pre-section 2, wherein the jack group comprises at least two jacks 3, the jacks 3 are all arranged in the reinforcement cage 1, sleeving a second wrapping layer 31 on the outer sides of the jacks 3 (the materials of the first wrapping layer 11 and the second wrapping layer 31 are pearl cotton or polyurethane or paper pulp), installing the reinforcement cage 1, and pouring concrete;
B. after the concrete is solidified, pressurizing the jack group to break the concrete of the layer where the pre-section 2 is located;
C. continuing to pressurize the jack group, jacking the concrete on the upper side of the pre-fracture surface 2, and lifting away the concrete on the upper side of the pre-fracture surface 2;
D. and (5) recovering the jack group, and dismantling the first sleeve 11 sleeved at the upper end of the reinforcement cage 1.
The jack 3 is a solid jack or a hollow jack, and the solid jack or the hollow jack is arranged on the outer side of the reinforcement cage 1. The jack group also comprises an oil pipe 5, and the jacks 3 are connected in series through the oil pipe 5.
Example 4
A construction method of a pre-positioned type broken concrete pile head, as shown in fig. 4 and 6, comprising the following steps,
A. sleeving a first wrapping layer 11 on the upper side of the pre-section of the reinforcement cage 1, fixing a jack group on the reinforcement cage 1 on the upper side of the pre-section 2, wherein the jack group comprises at least two jacks 3, the jacks 3 are all arranged in the reinforcement cage 1, sleeving a second wrapping layer 31 on the outer sides of the jacks 3 (the materials of the first wrapping layer 11 and the second wrapping layer 31 are pearl cotton or polyurethane or paper pulp), installing the reinforcement cage 1, and pouring concrete;
B. after the concrete is solidified, pressurizing the jack group to break the concrete of the layer where the pre-section 2 is located;
C. continuing to pressurize the jack group, jacking the concrete on the upper side of the pre-fracture surface 2, and lifting away the concrete on the upper side of the pre-fracture surface 2;
D. and (5) recovering the jack group, and dismantling the first sleeve 11 sleeved at the upper end of the reinforcement cage 1.
The jack 3 is a hollow jack, the reinforcement cage 1 comprises at least three main reinforcement bars 12, and the hollow jack is sleeved on the main reinforcement bars 12. A first wrapping layer 11 is arranged between the hollow jack and the main reinforcing steel bar 12. The jack group also comprises an oil pipe 5, and the jacks 3 are connected in series through the oil pipe 5.
Example 5
A construction method of a pre-positioned type broken concrete pile head, as shown in fig. 5 and 6, comprising the following steps,
A. sleeving a first wrapping layer 11 on the upper side of the pre-section of the reinforcement cage 1, fixing a jack group on the reinforcement cage 1 on the upper side of the pre-section 2, wherein the jack group comprises at least two jacks 3, the jacks 3 are all arranged in the reinforcement cage 1, sleeving a second wrapping layer 31 on the outer sides of the jacks 3 (the materials of the first wrapping layer 11 and the second wrapping layer 31 are pearl cotton or polyurethane or paper pulp), installing the reinforcement cage 1, and pouring concrete;
B. after the concrete is solidified, pressurizing the jack group to break the concrete of the layer where the pre-section 2 is located;
C. continuing to pressurize the jack group, jacking the concrete on the upper side of the pre-fracture surface 2, and lifting away the concrete on the upper side of the pre-fracture surface 2;
D. and (5) recovering the jack group, and dismantling the first sleeve 11 sleeved at the upper end of the reinforcement cage 1.
The jack 3 is a solid jack or a hollow jack, the reinforcement cage 1 comprises at least three main reinforcement bars 12, and the solid jack or the hollow jack is arranged between the adjacent main reinforcement bars 12.
The pre-section 2 is also provided with a cavity ring or a medium surface 4, the connecting pipe of the jack group is arranged at the inner side of the cavity ring, or the medium surface 4 is arranged at the lower side of the jack group.
In summary, the above-mentioned embodiments are only preferred embodiments of the present invention, and all equivalent changes and modifications made in the claims of the present invention should be covered by the claims of the present invention.

Claims (10)

1. A construction method of a pre-arranged type fracture concrete pile head is characterized in that: comprises the following steps of (a) carrying out,
A. sleeving a steel bar (12) on the upper side of the pre-section of the steel bar cage (1) with a first wrapping layer (11), fixing a jack group on the steel bar cage (1) on the upper side of the pre-section (2), wherein the jack group comprises at least two jacks (3), the jacks (3) are all arranged in the steel bar cage (1), sleeving a second wrapping layer (31) on the outer side of each jack (3), installing the steel bar cage (1), and pouring concrete;
B. after the concrete is solidified, pressurizing the jack group to break the concrete on the surface of the pre-fracture surface (2);
C. after the foundation pit is excavated, continuing pressurizing the jack group, jacking the concrete on the upper side of the pre-fracture surface (2), and hoisting the concrete on the upper side of the pre-fracture surface (2) by using a crane;
D. recovering the jack group, and finishing for the next use; and a first sleeve (11) sleeved at the upper end of the steel reinforcement cage (1) is recovered.
2. The construction method of the pre-positioned type fracture concrete pile head according to claim 1, characterized in that: the jack (3) is a solid jack or a hollow jack, the reinforcement cage (1) comprises at least three main reinforcement bars (12), and the solid jack or the hollow jack is arranged between the adjacent main reinforcement bars (12).
3. The construction method of the pre-positioned type fracture concrete pile head according to claim 1, characterized in that: the jack (3) is arranged on the inner side or the outer side of the reinforcement cage (1), and the jack (3) is a solid jack or a hollow jack.
4. The construction method of the pre-positioned type fracture concrete pile head according to claim 1, characterized in that: the jack (3) is a hollow jack, the reinforcement cage (1) comprises at least three main reinforcement bars (12), and the hollow jack is sleeved on the main reinforcement bars (12).
5. The construction method of the pre-positioned broken concrete pile head according to claim 2, 3 or 4, wherein: a first wrapping layer (11) is arranged between the hollow jack and the main reinforcement steel bar (12).
6. The construction method of the pre-positioned type fracture concrete pile head according to claim 1, characterized in that: the materials of the first wrapping layer (11) and the second wrapping layer (31) are isolation media.
7. The construction method of the pre-positioned type fracture concrete pile head according to claim 1, characterized in that: the pre-section (2) is also provided with a cavity ring.
8. The construction method of the pre-positioned type fracture concrete pile head according to claim 1, characterized in that: the pre-fracture surface (2) is also provided with a medium surface (4), and the medium surface (4) is arranged at the lower end of the jack group.
9. The construction method of the pre-positioned type fracture concrete pile head according to claim 1, characterized in that: the jacks (3) are connected in series or in parallel.
10. The construction method of the pre-positioned type fracture concrete pile head according to claim 9, characterized in that: the jack group also comprises an oil pipe (5), and the jacks (3) are connected in series through the oil pipe (5).
CN202010052258.1A 2020-01-17 2020-01-17 Construction method of pre-arranged type fracture concrete pile head Pending CN111236230A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010052258.1A CN111236230A (en) 2020-01-17 2020-01-17 Construction method of pre-arranged type fracture concrete pile head

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010052258.1A CN111236230A (en) 2020-01-17 2020-01-17 Construction method of pre-arranged type fracture concrete pile head

Publications (1)

Publication Number Publication Date
CN111236230A true CN111236230A (en) 2020-06-05

Family

ID=70872725

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010052258.1A Pending CN111236230A (en) 2020-01-17 2020-01-17 Construction method of pre-arranged type fracture concrete pile head

Country Status (1)

Country Link
CN (1) CN111236230A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113373926A (en) * 2021-06-06 2021-09-10 中交路桥建设有限公司 Separation device for pile head breaking and construction method
CN113585263A (en) * 2021-07-28 2021-11-02 中建五局第三建设有限公司 Pile head breaking equipment and method

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425159A (en) * 2011-08-31 2012-04-25 浙江大学城市学院 Pile cutting construction method of bored concrete pile
CN204343285U (en) * 2014-11-13 2015-05-20 中交隧道工程局有限公司 A kind of pile foundation pile crown entirety abolishes structure
CN108547303A (en) * 2018-04-11 2018-09-18 云南建投基础工程有限责任公司 A kind of filling pile head abolishes auxiliary device and pile crown restructuring bankrupt
CN208668414U (en) * 2018-05-29 2019-03-29 武汉钟鑫市政建设工程有限公司 A kind of built-in cast-in-situ bored pile pile crown breaker

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102425159A (en) * 2011-08-31 2012-04-25 浙江大学城市学院 Pile cutting construction method of bored concrete pile
CN204343285U (en) * 2014-11-13 2015-05-20 中交隧道工程局有限公司 A kind of pile foundation pile crown entirety abolishes structure
CN108547303A (en) * 2018-04-11 2018-09-18 云南建投基础工程有限责任公司 A kind of filling pile head abolishes auxiliary device and pile crown restructuring bankrupt
CN208668414U (en) * 2018-05-29 2019-03-29 武汉钟鑫市政建设工程有限公司 A kind of built-in cast-in-situ bored pile pile crown breaker

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113373926A (en) * 2021-06-06 2021-09-10 中交路桥建设有限公司 Separation device for pile head breaking and construction method
CN113373926B (en) * 2021-06-06 2024-05-07 中交路桥建设有限公司 Separating device for pile head breaking and construction method
CN113585263A (en) * 2021-07-28 2021-11-02 中建五局第三建设有限公司 Pile head breaking equipment and method

Similar Documents

Publication Publication Date Title
CN111236230A (en) Construction method of pre-arranged type fracture concrete pile head
CN110512895A (en) A kind of high-rise cast-in-place concrete building demolition construction method
CN109183783B (en) Breaking-free separated pile head of concrete filling pile
CN105155553A (en) Green dismantling construction method combining concrete support static crush and splitting method
CN106055801B (en) A kind of determination method of Brace in Deep Footing Groove beam demolition blasting sequence
JP2017141573A (en) Solid splitting dismantling method using expansion tube and dismantling removal method of reinforced concrete slab of bridge
CN113774822B (en) Dismantling method of old reinforced concrete bridge
CN111576419A (en) Pile head breaking method
CN101403257A (en) Nondestructive demounting method for prefabricated part of IMS system Dai nationality folk house major structure
CN212427098U (en) Preset fracture system of concrete pile head that breaks
CN113668529A (en) Construction method for breaking and removing pile head with template based on steel wedge-shaped gap
CN212477710U (en) Flexibly-mounted equipment for pre-broken concrete pile head
CN108487238A (en) A kind of filling pile head processing unit and its construction method
CN211922619U (en) Pile head breaking device
KR102333978B1 (en) Pileless-up wall demolition method
CN212956526U (en) Equipment for pre-breaking concrete pile head
CN109877136A (en) A kind of hydraulic recycling plant of high quantity of reinforcement waste concrete and its disassembling method
TWM647959U (en) Medium pressure system
CN111877192A (en) Method for dismantling and recycling bridge hollow slab
CN111424679A (en) Deep foundation pit assembled reinforced concrete support and rapid installation and rapid removal construction method thereof
CN113373926B (en) Separating device for pile head breaking and construction method
CN113502818A (en) Construction method of pile foundation pile head
CN114134828A (en) Method for quickly dismantling upper structure of truss arch bridge
CN112962603A (en) Dismantling construction process for reinforced concrete cast-in-place pile
CN111254931B (en) Construction method for rear concrete pile head fracture

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200605