CN114134828A - Method for quickly dismantling upper structure of truss arch bridge - Google Patents

Method for quickly dismantling upper structure of truss arch bridge Download PDF

Info

Publication number
CN114134828A
CN114134828A CN202010918496.6A CN202010918496A CN114134828A CN 114134828 A CN114134828 A CN 114134828A CN 202010918496 A CN202010918496 A CN 202010918496A CN 114134828 A CN114134828 A CN 114134828A
Authority
CN
China
Prior art keywords
arch
bridge
hoisting
truss
dismantling
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN202010918496.6A
Other languages
Chinese (zh)
Inventor
端茂军
李壮壮
宋粲
王飞
朱俊天
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Nanjing Forestry University
Original Assignee
Nanjing Forestry University
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Nanjing Forestry University filed Critical Nanjing Forestry University
Priority to CN202010918496.6A priority Critical patent/CN114134828A/en
Publication of CN114134828A publication Critical patent/CN114134828A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D22/00Methods or apparatus for repairing or strengthening existing bridges ; Methods or apparatus for dismantling bridges

Abstract

The invention relates to the technical field of bridge demolition construction, in particular to a method for quickly demolishing an upper structure of a truss arch bridge, which comprises the following steps: (A) dismantling the bridge deck auxiliary structure comprising a railing and a sidewalk plate; (B) setting a temporary support system (a); (C) dismantling the bridge deck pavement and the micro bent plate; (D) dividing arch pieces, and cutting and separating the arch pieces; (E) and hoisting the arch sheet to a specified position. According to the invention, the construction sequence of the traditional truss arch bridge structure is optimized, and by arranging the temporary support system (a), the situation that the arch sheet is inclined laterally in the process of removing the upper structure of the truss arch bridge is avoided, the stability of the arch sheet in the removal process is ensured, the safety of the construction process is ensured, meanwhile, the construction process is optimized, the construction period is shortened, the construction efficiency is improved, the construction cost is reduced, and the temporary support system can be popularized in the actual engineering.

Description

Method for quickly dismantling upper structure of truss arch bridge
Technical Field
The invention relates to a method for quickly dismantling an upper structure of a truss arch bridge, and belongs to the technical field of bridge dismantling construction.
Background
The truss arch bridge is an arch bridge formed by a solid-web section in the middle and arch truss pieces on two sides. The truss arch sheets are connected into a whole by a bridge deck system and a transverse connecting system (a transverse strut and a cross brace). The device is characterized in that the solid-web section and the arched truss pieces at the two sides play a role in stressing an arch, and arch legs have horizontal thrust to reduce midspan bending moment; compared with the common rib arch bridge with arch building, the bridge has reasonable stress, can save materials and reduce self weight, and is suitable for occasions with poor foundation.
The truss arch bridge is a light arch bridge developed in the end of the 60 s, and at present, due to the fact that a plurality of truss arch bridges are long in construction years, the overall rigidity, strength and stability of the truss arch bridge are reduced to different degrees after operation for many years, and uncertain factors such as fatigue damage, plastic deformation, local damage and the like of a single component and a connecting part exist. With the rapid development of national economy, the traffic volume is greatly increased, and the passing requirements of people on bridges are higher and higher. Therefore, part of the truss arch bridge needs to be dismantled and rebuilt, and in the dismantling engineering of the truss arch bridge, the dismantling of the main arch ring is critical and needs to be prevented from continuously collapsing in the dismantling process. Under the action of vertical load, the cross section of the main arch ring mainly generates compressive stress, and the generated bending moment is very small relative to that of the equal-span simply supported beam. According to respective stress characteristics, the main arch ring and the equal-span simply supported beam have great difference in structure. The main arch ring can not be taken as a simply supported beam and is lifted by the integral simply support, otherwise, the middle part of the main arch ring is broken after being lifted, and the main arch ring is damaged, so that serious consequences are caused, and quality and safety accidents are caused.
Disclosure of Invention
In order to solve the problems, the invention provides a method for quickly dismantling the upper structure of a truss arch bridge.
The invention is realized by the following technical scheme.
The invention provides a method for quickly dismantling an upper structure of a truss arch bridge, which comprises the following steps:
(A) demolish bridge floor auxiliary structure and include railing and pavement slab: each side rail is removed from two sides to the middle one by one; chiseling the railing base by using an air pick, hoisting by using a crane, and loading and transporting away; the sidewalk cover plate and the pavement layer are directly pried up by a crowbar manually, and the concrete road teeth are crushed and dismantled by an air pick, loaded and transported away;
(B) setting a temporary supporting system: the support type is that a buttress is respectively erected at the positions of 1/4 and 3/4, and 4-8 steel pipe piles are arranged on two sides of each buttress; double-spliced I45I-shaped steel is arranged among the steel pipe piles to be used as transverse connection, double-spliced I25I-shaped steel is arranged below each arch sheet, and a wood support is paved on the double-spliced I25I-shaped steel;
(C) dividing arch pieces, cutting and separating the arch pieces: dividing the existing bridge into a plurality of arch pieces according to the cutting line of the expansion joints and the hinge joints of the existing bridge, and simultaneously determining the hoisting sequence of each arch piece;
(D) demolish bridge floor pavement and little bent plate: the bridge deck pavement layer and the micro bent plate are disassembled in blocks by adopting a diamond track cutting machine; before cutting, the monomer component is punched with 4 holes by a diamond punching machine for lifting the opening, the 4 holes are uniformly distributed at four corners of the component according to the size of the component, and the component is wrapped up and tightened by a high-strength steel wire rope;
(E) hoisting the arch sheet to a specified position: hoisting the arch pieces determined in the step (C) by using a floating crane or a crane according to the hoisting sequence of the arch pieces, selecting a high-strength steel wire rope to firmly bind the solid-web section at the hoisting point of the solid-web section, applying a hoisting force slightly larger than the weight of the solid-web section to the solid-web section by using a floating crane, and then cutting off the main arch ring at the division part of the solid-web section and the lower chord by using an air compressor; and (4) after the solid-web section is dismantled, the lower chord is dismantled, then the arch piece is hoisted to a specified position, and the process is repeated until the complete hoisting of the truss arch bridge is finished.
In the step (A), the removal of the bridge deck auxiliary structure is realized by manually using an air pick and a crowbar to cut or break the railings and the sidewalk plate, and then using a crane and manual loading to transport the railings and the sidewalk plate.
The method for quickly dismantling the upper structure of the truss arch bridge comprises the steps that in the step (B), a temporary supporting system is adopted, wherein the specification of the steel pipe pile is 530 mm in diameter and 630mm in wall thickness, and is 8-10 mm; the transverse connection double-spliced I45I-shaped steel adopts Q235-Q345 steel; the double-spliced I25I-shaped steel is made of Q235-Q345 steel.
The method for quickly dismantling the upper structure of the truss arch bridge comprises the following steps that (D) a diamond track cutting machine is used for paving a bridge deck and dismantling a micro bent plate; the member was punched using a diamond punch.
The method for quickly dismantling the upper structure of the truss arch bridge comprises the step (E) of hoisting the upper structure of the arch bridge by adopting a high-strength steel wire rope.
The invention has the following beneficial effects: through setting up interim support, avoided the arch bridge superstructure to demolish the condition that the arch piece lateral overturn probably appears in-process, guaranteed the stability of demolising in-process arch bridge, ensured the safety of work progress, shortened construction period, improved the efficiency of construction, reduced construction cost, can promote in actual engineering.
Drawings
FIG. 1 is a flow chart of a method for quickly removing the superstructure of a truss arch bridge;
FIG. 2 is a schematic longitudinal section of an arch bridge with temporary supports;
FIG. 3 is a schematic cross-sectional view of an arch bridge with temporary supports;
fig. 4 is a schematic elevation view of the temporary support.
1. Steel pipe piles; 2. double-spliced I45I-shaped steel; 3. double-spliced I25I-shaped steel; 4. a dome sheet.
Detailed Description
For a more complete understanding of the technical features, objects, and effects of the present invention, embodiments of the present invention will now be described with reference to the accompanying drawings.
Referring to fig. 1, in an embodiment of the present invention, a method for quickly dismantling a superstructure of a truss arch bridge specifically includes the following steps:
(A) demolish bridge floor auxiliary structure and include railing and pavement slab: each side rail is removed from two sides to the middle one by one; chiseling the railing base by using an air pick, hoisting by using a crane, and loading and transporting away; the sidewalk cover plate and the pavement layer are directly pried up by a crowbar manually, and the concrete road teeth are crushed and dismantled by an air pick, loaded and transported away;
(B) setting a temporary supporting system: the support type is that a buttress is respectively erected at the positions of 1/4 and 3/4, and 4-8 steel pipe piles are arranged on two sides of each buttress; double-spliced I45I-shaped steel is arranged among the steel pipe piles to be used as transverse connection, double-spliced I25I-shaped steel is arranged below each arch sheet, and a wood support is paved on the double-spliced I25I-shaped steel;
(C) dividing arch pieces, cutting and separating the arch pieces: dividing the existing bridge into a plurality of arch pieces according to the cutting line of the expansion joints and the hinge joints of the existing bridge, and simultaneously determining the hoisting sequence of each arch piece;
(D) demolish bridge floor pavement and little bent plate: the bridge deck pavement layer and the micro bent plate are disassembled in blocks by adopting a diamond track cutting machine; before cutting, the monomer component is punched with 4 holes by a diamond punching machine for lifting the opening, the 4 holes are uniformly distributed at four corners of the component according to the size of the component, and the component is wrapped up and tightened by a high-strength steel wire rope;
(E) hoisting the arch sheet to a specified position: hoisting the arch pieces determined in the step (C) by using a floating crane or a crane according to the hoisting sequence of the arch pieces, selecting a high-strength steel wire rope to firmly bind the solid-web section at the hoisting point of the solid-web section, applying a hoisting force slightly larger than the weight of the solid-web section to the solid-web section by using a floating crane, and then cutting off the main arch ring at the division part of the solid-web section and the lower chord by using an air compressor; and (4) after the solid-web section is dismantled, the lower chord is dismantled, then the arch piece is hoisted to a specified position, and the process is repeated until the complete hoisting of the truss arch bridge is finished.
In the step (A), the removal of the bridge deck auxiliary structure is realized by manually using an air pick and a crowbar to cut or break the railings and the sidewalk plate, and then using a crane and manual loading to transport the railings and the sidewalk plate.
The method for quickly dismantling the upper structure of the truss arch bridge comprises the steps that in the step (B), a temporary supporting system is adopted, wherein the specification of the steel pipe pile is 530 mm in diameter and 630mm in wall thickness, and is 8-10 mm; the transverse connection double-spliced I45I-shaped steel adopts Q235-Q345 steel; the double-spliced I25I-shaped steel is made of Q235-Q345 steel.
The method for quickly dismantling the upper structure of the truss arch bridge comprises the following steps that (D) a diamond track cutting machine is used for paving a bridge deck and dismantling a micro bent plate; the member was punched using a diamond punch.
The method for quickly dismantling the upper structure of the truss arch bridge comprises the step (E) of hoisting the upper structure of the arch bridge by adopting a high-strength steel wire rope.
The invention is not limited to the specific embodiments described above. Any equivalent modifications and substitutions to those skilled in the art are also within the scope of the present invention. Accordingly, equivalent changes and modifications made without departing from the spirit and scope of the present invention should be covered by the present invention.

Claims (5)

1. A method for rapidly dismantling the superstructure of a truss arch bridge is characterized by comprising the following steps:
(A) demolish bridge floor auxiliary structure and include railing and pavement slab: each side rail is removed from two sides to the middle one by one; chiseling the railing base by using an air pick, hoisting by using a crane, and loading and transporting away; the sidewalk cover plate and the pavement layer are directly pried up by a crowbar manually, and the concrete road teeth are crushed and dismantled by an air pick, loaded and transported away;
(B) setting a temporary support system (a): the support type bridges 1/4 and 3/4 are respectively provided with a buttress, and 4-8 steel pipe piles (1) are arranged on two sides of each buttress; double-spliced I45I-shaped steel (2) is arranged among the steel pipe piles to be used as transverse connection, double-spliced I25I-shaped steel (3) is arranged below each arch sheet, and a wood support is paved on the double-spliced I25I-shaped steel;
(C) dividing arch pieces, cutting and separating the arch pieces: dividing the existing bridge into a plurality of arch pieces according to the cutting line of the expansion joints and the hinge joints of the existing bridge, and simultaneously determining the hoisting sequence of each arch piece;
(D) demolish bridge floor pavement and little bent plate: the bridge deck pavement layer and the micro bent plate are disassembled in blocks by adopting a diamond track cutting machine; before cutting, the monomer component is punched with 4 holes by a diamond punching machine for lifting the opening, the 4 holes are uniformly distributed at four corners of the component according to the size of the component, and the component is wrapped up and tightened by a high-strength steel wire rope;
(E) hoisting the arch sheet to a specified position: hoisting the arch pieces determined in the step (C) by using a floating crane or a crane according to the hoisting sequence of the arch pieces, selecting a high-strength steel wire rope to firmly bind the solid-web section at the hoisting point of the solid-web section, applying a hoisting force slightly larger than the weight of the solid-web section to the solid-web section by using a floating crane, and then cutting off the main arch ring at the division part of the solid-web section and the lower chord by using an air compressor; and (4) after the solid-web section is dismantled, the lower chord is dismantled, then the arch piece is hoisted to a specified position, and the process is repeated until the complete hoisting of the truss arch bridge is finished.
2. The method for rapidly dismantling the superstructure of the truss arch bridge according to claim 1, wherein the dismantling of the deck auxiliary structure in the step (A) is manually to use an air pick and a crow bar to divide or break the railings and the sidewalk plate, and then to use a crane and a manual truck to transport away.
3. The method for rapidly dismantling the superstructure of a truss arch bridge as recited in claim 1, wherein the temporary support system (a) in the step (B) is adopted, wherein the steel pipe piles (1) are used with the diameter of 530 mm and the wall thickness of 630mm of 8-10 mm; the transverse connection double I45I-shaped steel (2) adopts Q235-Q345 steel; the double-spliced I25I-shaped steel (3) is made of Q235-Q345 steel.
4. The method for rapidly demolishing an upper structure of a truss arch bridge according to claim 1, wherein the step (D) uses a diamond track cutter for deck pavement and demolition of the microbends; the member was punched using a diamond punch.
5. A method for quickly dismantling the superstructure of a truss arch bridge as claimed in claim 1, wherein step (E) uses a high tensile steel cable to hoist the superstructure of the truss arch bridge.
CN202010918496.6A 2020-09-03 2020-09-03 Method for quickly dismantling upper structure of truss arch bridge Pending CN114134828A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010918496.6A CN114134828A (en) 2020-09-03 2020-09-03 Method for quickly dismantling upper structure of truss arch bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010918496.6A CN114134828A (en) 2020-09-03 2020-09-03 Method for quickly dismantling upper structure of truss arch bridge

Publications (1)

Publication Number Publication Date
CN114134828A true CN114134828A (en) 2022-03-04

Family

ID=80438583

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010918496.6A Pending CN114134828A (en) 2020-09-03 2020-09-03 Method for quickly dismantling upper structure of truss arch bridge

Country Status (1)

Country Link
CN (1) CN114134828A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960479A (en) * 2022-04-24 2022-08-30 广西北投交通养护科技集团有限公司 Method for dismantling arch-connected bridge based on shallow-buried foundation critical cross-sectional area overturning destruction

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747694A (en) * 2012-06-29 2012-10-24 浙江工业大学 Construction method for dismantling small-size river-crossing rigid frame arch bridge by floating crane method
CN204728216U (en) * 2015-06-03 2015-10-28 新疆旭日环保股份有限公司 Large-scale truss support device
CN109056557A (en) * 2018-08-17 2018-12-21 中铁五局集团有限公司 A kind of existing method for bridge construction of decomposition dismounting
CN110130203A (en) * 2019-05-30 2019-08-16 中铁第四勘察设计院集团有限公司 A kind of deck type arch-rigid frame-continuous girder composite bridge and construction method
CN110847063A (en) * 2019-11-29 2020-02-28 贵州省交通规划勘察设计研究院股份有限公司 Method for dismantling multi-span double-arch bridge
CN111676846A (en) * 2020-06-10 2020-09-18 贵州大通路桥工程建设有限公司 Construction method for dismantling truss type combined arch bridge

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102747694A (en) * 2012-06-29 2012-10-24 浙江工业大学 Construction method for dismantling small-size river-crossing rigid frame arch bridge by floating crane method
CN204728216U (en) * 2015-06-03 2015-10-28 新疆旭日环保股份有限公司 Large-scale truss support device
CN109056557A (en) * 2018-08-17 2018-12-21 中铁五局集团有限公司 A kind of existing method for bridge construction of decomposition dismounting
CN110130203A (en) * 2019-05-30 2019-08-16 中铁第四勘察设计院集团有限公司 A kind of deck type arch-rigid frame-continuous girder composite bridge and construction method
CN110847063A (en) * 2019-11-29 2020-02-28 贵州省交通规划勘察设计研究院股份有限公司 Method for dismantling multi-span double-arch bridge
CN111676846A (en) * 2020-06-10 2020-09-18 贵州大通路桥工程建设有限公司 Construction method for dismantling truss type combined arch bridge

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
"王勇 "浅谈钢筋砼桁架拱桥拆除施工技术",王勇,《江西建材》,第124页-125页" *
王勇: ""浅谈钢筋砼桁架拱桥拆除施工技术",王勇,《江西建材》,第124页-125页" *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114960479A (en) * 2022-04-24 2022-08-30 广西北投交通养护科技集团有限公司 Method for dismantling arch-connected bridge based on shallow-buried foundation critical cross-sectional area overturning destruction
CN114960479B (en) * 2022-04-24 2024-04-02 广西北投交通养护科技集团有限公司 Bridge dismantling method based on shallow foundation critical cross-section area overturning damage

Similar Documents

Publication Publication Date Title
CN108708305B (en) Construction method for dismantling low-pier bridge
CN110259184A (en) Column construction method is pulled out based on Removing Columns combined support jack-up system
CN111778883A (en) Non-unbalance-load quick dismantling method for multi-span concrete rigid frame arch bridge
CN110552296A (en) Cable-stayed bridge dismantling construction method
CN110905232A (en) Mechanical static force dismantling method for concrete structure
CN110656570A (en) Telescopic pedestrian bridge, construction device and construction method
CN111501584A (en) Bridge dismantling construction method for prestressed concrete continuous beam
CN113774822B (en) Dismantling method of old reinforced concrete bridge
CN112252212A (en) Method for dismantling prestressed concrete variable cross-section continuous beam bridge
CN110468743B (en) Movable hanging bracket for transformation of old bridge pier cap and construction method
CN106320192B (en) A kind of beam section replacing and reinforcing method for large span concrete continuous beam bridge
CN103276894A (en) Support system of large-cross-section girder transfer floor of hollow floor system and construction technology
CN114134828A (en) Method for quickly dismantling upper structure of truss arch bridge
CN115538340A (en) Rapid dismantling device and construction method for old bridge precast beam plate
CN112726434B (en) Three-span deck reinforced concrete arch bridge dismantling method
CN213233105U (en) Small-span concrete cast-in-place box girder support system
CN212096869U (en) Precast beam processingequipment
CN111593681B (en) Pier stud retaining cast-in-place box girder ecological dismantling system and construction method
CN113235470A (en) Large-radian overflow surface complex-structure reinforced concrete bridge and demolition method
JPH07300817A (en) Concrete-filled steel pipe truss pier and construction method
CN113481881A (en) Construction method for splicing, widening and dismantling reconstruction of T-shaped structure navigation bridge with hanging beams
CN206173812U (en) Novel construction of continuous beam displacement device of bridge
CN110886250A (en) Lifting device for dismantling concrete bridge anti-collision guardrail and construction method thereof
CN116791494B (en) Demolishing and newly-built construction method for riverbed power station traffic bridge
CN218757029U (en) Bridge girder erection machine for large-span pi-shaped beam

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20220304