CN111209614A - 一种基于bim技术的高大梁板一键识别方法 - Google Patents

一种基于bim技术的高大梁板一键识别方法 Download PDF

Info

Publication number
CN111209614A
CN111209614A CN201911002562.9A CN201911002562A CN111209614A CN 111209614 A CN111209614 A CN 111209614A CN 201911002562 A CN201911002562 A CN 201911002562A CN 111209614 A CN111209614 A CN 111209614A
Authority
CN
China
Prior art keywords
model
load
equal
beam width
multiplied
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911002562.9A
Other languages
English (en)
Inventor
李贲
卢福新
陈春城
孟辉
谭志刚
曾戈文
陈文卉
邹积霖
徐鹏飞
张峥嵘
於丙昊
李佳乐
徐子鸣
陈昂
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangzhou First Municipal Engineering Co ltd
Original Assignee
Guangzhou First Municipal Engineering Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangzhou First Municipal Engineering Co ltd filed Critical Guangzhou First Municipal Engineering Co ltd
Priority to CN201911002562.9A priority Critical patent/CN111209614A/zh
Publication of CN111209614A publication Critical patent/CN111209614A/zh
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects

Landscapes

  • Physics & Mathematics (AREA)
  • Engineering & Computer Science (AREA)
  • Computer Graphics (AREA)
  • Geometry (AREA)
  • Software Systems (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

本发明涉及一种基于BIM技术的高大梁板一键识别方法,将高大梁板搭设高度8m及以上,施工总荷载15kN/㎡及以上,集中线荷载20kN/m及以上,通过模型中上下两层板之间标高,通过REVIT API利用C#语言编码,限制模型中条件,改变模型中楼板或梁颜色,在模型中高亮显示出来。本发明利用BIM模型,通过REVIT API利用C#语言编码,制作自动识别属于模板支撑工程中定义的高大梁、板等构件的工具,实现高大梁、板一键识别,为编制高大支模施工方案提供准确依据;且将识别后的高大梁板三维直观展示给管理人员及工人,辅助项目现场安全管理。

Description

一种基于BIM技术的高大梁板一键识别方法
技术领域
本发明涉及BIM技术识别高大梁板荷载技术领域,具体是指一种基于BIM技术的高大梁板一键识别方法。
背景技术
现阶段多通过人工查图识别高大梁板,对于大型公共建筑或其他大体量现浇混凝土项目,其结构图数量、高大梁板数量之多,人工识图需要花费大量时间,且无法做到准确、无漏项,亟待改进。
发明内容
本发明要解决的技术问题是,克服现有技术缺点,提供一种基于BIM技术的高大梁板一键识别方法。
为解决上述技术问题,本发明提供的技术方案为:一种基于BIM技术的高大梁板一键识别方法,基于BIM技术,将高大梁板搭设高度8m及以上,通过模型中上下两层板之间标高,通过REVITAPI利用C#语言编码,限制模型中条件:当层间距≥8m,则改变模型中楼板或梁颜色,在模型中高亮显示出来;
施工总荷载15kN/㎡及以上,通过当模型中板厚h1≥350mm,则改变模型中所有满足该h1≥350mm楼板颜色,在模型中高亮显示出来;
集中线荷载20kN/m及以上,当梁宽b=300时,梁高h2>1.76m;当梁宽b≥400时,h2>1.32m;当梁宽b≥500时,h2>1.05m;当梁宽b≥600时,h2>0.86m;当梁宽b≥700时,h2>0.72m;当梁宽b≥800时,h2>0.62m;当梁宽b≥900时,h2>0.54m;当梁宽b≥900时,按其截面积>0.48㎡统一处理,满足上述条件时,自动改变模型中满足条件的所有梁,高亮显示或显示为自动选定状态,与模型其他构件区别开来,达到一键识别的效果。
进一步的,所述施工总荷载中荷载的组成包括均荷载=永久荷载×分项系数+施工均布活荷载×分项系数,其中永久荷载=钢筋砼自重+模板木方自重,其中钢筋砼自重=板厚×25KN/m3,其中单位模板木方自重0.3KN/m2,其中单位施工均布活荷载3KN/m2。
进一步的,所述集中线荷载=永久荷载×分项系数+施工均布活荷载×分项系数,其中永久荷载=钢筋砼自重+模板木方自重,其中单位钢筋砼自重=梁的截面积×25KN/m3,其中单位模板木方的自重=梁截面模板的周长×0.5KN/m2,其中单位施工均布活荷载=梁宽×3KN/m2。
本发明具有如下优点:本发明利用REVIT二次开发,通过超高大梁板荷载定义转换为计算机能识别的计算机语言自动选定定义中的梁、板等构件,实现一键识别属于《危险性较大的分部分项工程安全管理规定》中超过一定规模的混凝土模板支撑工程范畴内的混凝土梁、板等构件。
1、本发明在识别高大梁板时,可做到一键识别,节约大量人工识图、查图时间,且借助计算机软件的特性相比人工查找做到快速、准确、无缺漏。
2、识别后的三维立体图展示,可直观的向管理及作业人员展示该危大工程的具体部位和规模,相比传统二维展示更直观清晰,达到危大工程人人心中有数,有力辅助项目安全管理。
附图说明
图1是本发明中支模高度>8m识别后高亮显示部分的示意图。
图2是本发明中施工总荷载>15kN/㎡识别后高亮显示部分的示意图。
图3是本发明中集中线荷载>20kN/m识别后高亮显示部分的示意图。
具体实施方式
下面结合实施例对本发明做进一步的详细说明。
1.荷载计算方法
按JGJ130-2011《建筑施工扣件式钢管脚手架安全技术规范》进行计算。
1.1施工总荷载的计算方法
(一)荷载的组成:
均荷载=永久荷载(钢筋砼自重+模板木方自重)×分项系数+施工均布活荷载×分项系数钢筋砼自重=板厚(m)×25KN/m3(在计算均荷载时钢筋砼比重取值为25KN/m3)
模板木方自重:0.3KN/m2(计算均荷载时取值为0.3KN/m2)
施工均布活荷载:3KN/m2
(二)承受均布构件厚度的计算:
1.2×(25M+0.3)+1.4×3≥15得M≥0.348米,取整M=350mm
结论1:即板厚达到或超过350mm时属于施工总荷载15KN/㎡及以上的范畴。
1.2集中线荷载的计算方法
(一)荷载的组成:
集中线荷载=永久荷载(钢筋砼自重+模板木方自重)×分项系数+施工均布活荷载×分项系数
钢筋砼自重=梁的截面积(m2)×25KN/m3(集中线荷载时钢筋砼比重取值为25KN/m3)
模板木方的自重=梁截面模板的周长(m)×0.5KN/m2(集中线荷载时取值为0.5KN/m2)
施工均布活荷载=梁宽m×3KN/m2
由上,集中线荷载=31.2bh+1.2h+4.8b≤20KN/M
结论2:即当梁宽b=300时,h>1.76m,其线荷载>20KN/M;
当梁宽b=400时,h>1.32m,其线荷载>20KN/M;
当梁宽b=500时,h>1.05m,其线荷载>20KN/M;
当梁宽b=600时,h>0.86m,其线荷载>20KN/M;
当梁宽b=700时,h>0.72m,其线荷载>20KN/M;
当梁宽b=800时,h>0.62m,其线荷载>20KN/M;
当梁宽b=900时,h>0.54m,其线荷载>20KN/M;
依次类推得出,当梁b>900时,按其截面积>0.48㎡推定为集中线荷载20kN/m及以上的范畴。
2.荷载与BIM模型间联系转换
2.1搭设高度8m及以上:
通过模型中上下两层板之间标高(假设1F标高(H)为±0m,2F标高为8.5m);通过REVIT API利用C#语言编码,限制模型中条件(下2.2、2.3同):当H2F-H1F≥8,,则改变模型中楼板或梁颜色(或自动显示为选定状态),在模型中高亮显示出来。
2.2施工总荷载15kN/㎡及以上:
根据2.1中计算结果,通过模型中板厚(h),如果h≥350mm,则改变模型中所有满足该h≥350mm楼板颜色,在模型中高亮显示出来。
2.3集中线荷载20kN/m及以上(此处h为梁高):
根据2.2计算结果即当梁宽b=300时,梁高h>1.76m;
当梁宽b≥400时,h>1.32m;
当梁宽b≥500时,h>1.05m;
当梁宽b≥600时,h>0.86m;
当梁宽b≥700时,h>0.72m;
当梁宽b≥800时,h>0.62m;
当梁宽b≥900时,h>0.54m;
当梁宽b≥900时,按其截面积>0.48㎡统一处理
满足上述条件时,自动改变模型中满足条件的所有梁,高亮显示或显示为自动选定状态,与模型其他构件区别开来,达到一键识别的效果。
虽然,上文中已经用一般性说明及具体实施方案对本发明作了详尽的描述,但在本发明基础上,可以对之作一些修改或改进,这对本领域技术人员而言是显而易见的。因此,在不偏离本发明精神的基础上所做的这些修改或改进,均属于本发明要求保护的范围。

Claims (3)

1.一种基于BIM技术的高大梁板一键识别方法,其特征在于,基于BIM技术,将高大梁板搭设高度8m及以上,通过模型中上下两层板之间标高,通过REVITAPI利用C#语言编码,限制模型中条件:当层间距≥8m,则改变模型中楼板或梁颜色,在模型中高亮显示出来;
施工总荷载15kN/㎡及以上,通过当模型中板厚h1≥350mm,则改变模型中所有满足该h1≥350mm楼板颜色,在模型中高亮显示出来;
集中线荷载20kN/m及以上,当梁宽b=300时,梁高h2>1.76m;当梁宽b≥400时,h2>1.32m;当梁宽b≥500时,h2>1.05m;当梁宽b≥600时,h2>0.86m;当梁宽b≥700时,h2>0.72m;当梁宽b≥800时,h2>0.62m;当梁宽b≥900时,h2>0.54m;当梁宽b≥900时,按其截面积>0.48㎡统一处理,满足上述条件时,自动改变模型中满足条件的所有梁,高亮显示或显示为自动选定状态,与模型其他构件区别开来,达到一键识别的效果。
2.根据权利要求1所述的一种基于BIM技术的高大梁板一键识别方法,其特征在于:所述施工总荷载中荷载的组成包括均荷载=永久荷载×分项系数+施工均布活荷载×分项系数,其中永久荷载=钢筋砼自重+模板木方自重,其中钢筋砼自重=板厚×25KN/m3,其中单位模板木方自重0.3KN/m2,其中单位施工均布活荷载3KN/m2。
3.根据权利要求1所述的一种基于BIM技术的高大梁板一键识别方法,其特征在于:所述集中线荷载=永久荷载×分项系数+施工均布活荷载×分项系数,其中永久荷载=钢筋砼自重+模板木方自重,其中单位钢筋砼自重=梁的截面积×25KN/m3,其中单位模板木方的自重=梁截面模板的周长×0.5KN/m2,其中单位施工均布活荷载=梁宽×3KN/m2。
CN201911002562.9A 2019-10-21 2019-10-21 一种基于bim技术的高大梁板一键识别方法 Pending CN111209614A (zh)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911002562.9A CN111209614A (zh) 2019-10-21 2019-10-21 一种基于bim技术的高大梁板一键识别方法

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911002562.9A CN111209614A (zh) 2019-10-21 2019-10-21 一种基于bim技术的高大梁板一键识别方法

Publications (1)

Publication Number Publication Date
CN111209614A true CN111209614A (zh) 2020-05-29

Family

ID=70786946

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911002562.9A Pending CN111209614A (zh) 2019-10-21 2019-10-21 一种基于bim技术的高大梁板一键识别方法

Country Status (1)

Country Link
CN (1) CN111209614A (zh)

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112948938A (zh) * 2021-03-12 2021-06-11 中国建筑第八工程局有限公司 Bim三维建模计算、识别超重梁的方法
CN114065336A (zh) * 2021-09-28 2022-02-18 广州优比建筑咨询有限公司 一种基于Revit的高支模区域的检查方法、装置、介质及设备
CN114519229A (zh) * 2022-04-20 2022-05-20 中建五局第三建设有限公司 基于Revit的危大模板支撑构件识别方法、设备

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20160063722A1 (en) * 2014-08-28 2016-03-03 Textura Planswift Corporation Detection of a perimeter of a region of interest in a floor plan document
CN106294821A (zh) * 2016-08-16 2017-01-04 广州地铁设计研究院有限公司 一种bim模型校验方法
CN107357802A (zh) * 2017-05-19 2017-11-17 江苏龙腾工程设计股份有限公司 建筑信息模型数据库的关键词检索方法及系统
JP2018025951A (ja) * 2016-08-09 2018-02-15 株式会社ミスミ 設計支援方法、サーバ及び設計支援システム
CN107967574A (zh) * 2017-12-21 2018-04-27 深圳拎得清软件有限公司 基于bim的数字化审图方法及其系统
US20180321799A1 (en) * 2017-05-05 2018-11-08 Nucor Corporation System for on-site tracking, managing, planning and staging construction projects
CN110322772A (zh) * 2019-07-03 2019-10-11 大连海事大学 一种基于bim的实验室桥梁监测演示教学系统

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20160063722A1 (en) * 2014-08-28 2016-03-03 Textura Planswift Corporation Detection of a perimeter of a region of interest in a floor plan document
JP2018025951A (ja) * 2016-08-09 2018-02-15 株式会社ミスミ 設計支援方法、サーバ及び設計支援システム
CN106294821A (zh) * 2016-08-16 2017-01-04 广州地铁设计研究院有限公司 一种bim模型校验方法
US20180321799A1 (en) * 2017-05-05 2018-11-08 Nucor Corporation System for on-site tracking, managing, planning and staging construction projects
CN107357802A (zh) * 2017-05-19 2017-11-17 江苏龙腾工程设计股份有限公司 建筑信息模型数据库的关键词检索方法及系统
CN107967574A (zh) * 2017-12-21 2018-04-27 深圳拎得清软件有限公司 基于bim的数字化审图方法及其系统
CN110322772A (zh) * 2019-07-03 2019-10-11 大连海事大学 一种基于bim的实验室桥梁监测演示教学系统

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
迟安琦等: "高层建筑项目运维期BIM和传感器集成辅助决策系统框架", 《项目管理技术》 *
马少雄等: "基于BIM技术的大跨度桥梁施工管理平台研发及应用", 《图学学报》 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112948938A (zh) * 2021-03-12 2021-06-11 中国建筑第八工程局有限公司 Bim三维建模计算、识别超重梁的方法
CN114065336A (zh) * 2021-09-28 2022-02-18 广州优比建筑咨询有限公司 一种基于Revit的高支模区域的检查方法、装置、介质及设备
CN114519229A (zh) * 2022-04-20 2022-05-20 中建五局第三建设有限公司 基于Revit的危大模板支撑构件识别方法、设备
CN114519229B (zh) * 2022-04-20 2022-08-12 中建五局第三建设有限公司 基于Revit的危大模板支撑构件识别方法、设备

Similar Documents

Publication Publication Date Title
CN111209614A (zh) 一种基于bim技术的高大梁板一键识别方法
Banks et al. Enhancing high-rise residential construction through design for manufacture and assembly–a UK case study
Kannan et al. Constructability assessment of climbing formwork systems using building information modeling
CN112900692B (zh) 一种大跨度异形钢结构建筑及其支撑装置以及施工方法
CN113158295A (zh) 基于bim模板整装技术运用在模板支撑架体的施工工法
CN104712141A (zh) 现浇钢筋混凝土密肋梁楼板施工方法
CN105302938B (zh) 一种组装式桁架内力计算方法
CN112884336A (zh) 一种基于bim技术的装配式建筑筑造方法
CN106836600A (zh) 一种用于变电工程的钢筋组合楼板
CN112069586B (zh) 悬挑结构上安装型钢悬挑脚手架设计与施工方法
CN110258883A (zh) 一种空心楼盖bdf钢网膜填充箱体的施工方法
Kim et al. Improved productivity using a modified table formwork system for high-rise building in Korea
Abou Ibrahim et al. Expected lean effects of advanced high-rise formwork systems
CN203188596U (zh) 快装式组合楼梯
CN202081639U (zh) 钢桁架工具式砼框架工业厂房模板支撑结构
Al Jauhari et al. Comparative study of SNI 1726: 2012 and SNI 1726: 2019 guidelines for response spectrum 2D method (study case: GKT II building of Bengkalis State Polytechnic)
CN206143914U (zh) Sc装配式框架‑支撑结构体系
Mahdi et al. State of the art review on application of value engineering on construction projects: High rise building
CN104831850A (zh) 正交斜放u型钢、混凝土组合空腹楼盖及制作方法
CN205224366U (zh) 一种新型复合保温楼面板
Xiao The importance of formwork methods in the economical execution of concrete structures
Li A study of cost-effective reinforced concrete structural systems
Lee et al. Inhibiting factors and improvement plan of table formwork method in high-rise building construction
CN213390916U (zh) 一种楼梯板与踏步分离的全装配式楼梯体系
Poudel et al. Steel Module-to-Concrete Core Connection Methods in High Rise Modular Buildings: A Critical Review

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200529