CN111192342B - Project group management topological graph generation method, device, equipment and storage medium - Google Patents

Project group management topological graph generation method, device, equipment and storage medium Download PDF

Info

Publication number
CN111192342B
CN111192342B CN202010019626.2A CN202010019626A CN111192342B CN 111192342 B CN111192342 B CN 111192342B CN 202010019626 A CN202010019626 A CN 202010019626A CN 111192342 B CN111192342 B CN 111192342B
Authority
CN
China
Prior art keywords
project
nodes
item
information
node
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN202010019626.2A
Other languages
Chinese (zh)
Other versions
CN111192342A (en
Inventor
梁威
蔡伟
张克非
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Thinvent Digital Technology Co Ltd
Original Assignee
Thinvent Digital Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Thinvent Digital Technology Co Ltd filed Critical Thinvent Digital Technology Co Ltd
Priority to CN202010019626.2A priority Critical patent/CN111192342B/en
Publication of CN111192342A publication Critical patent/CN111192342A/en
Application granted granted Critical
Publication of CN111192342B publication Critical patent/CN111192342B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T11/002D [Two Dimensional] image generation
    • G06T11/20Drawing from basic elements, e.g. lines or circles
    • G06T11/203Drawing of straight lines or curves
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T11/002D [Two Dimensional] image generation
    • G06T11/20Drawing from basic elements, e.g. lines or circles
    • G06T11/206Drawing of charts or graphs

Landscapes

  • Engineering & Computer Science (AREA)
  • Business, Economics & Management (AREA)
  • Physics & Mathematics (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Data Mining & Analysis (AREA)
  • Economics (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Tourism & Hospitality (AREA)
  • General Business, Economics & Management (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The embodiment of the invention provides a project group management topological graph generation method, a project group management topological graph generation device, project group management topological graph generation equipment and a computer readable storage medium. The method comprises the following steps: acquiring item information of each item in the item group and an association relation between the items, wherein the item information comprises time information and/or resource information of the items; drawing a straight line connecting line between the project nodes according to the association relation and the project information, wherein the length of the connecting line is determined based on time information and/or resource information of the project at one end of the connecting line; adjusting the positions of project nodes to generate a project group management topological graph; the project nodes comprise project nodes corresponding to the project groups and virtual project nodes serving as starting nodes or ending nodes. In this way, the project information of each project node of the project group and the relation between projects can be intuitively displayed, so that a user can conveniently move the positions of the project nodes according to requirements or adjust overlapped project nodes.

Description

Project group management topological graph generation method, device, equipment and storage medium
Technical Field
The present invention relates to the field of computer technologies, and in particular, to a method, an apparatus, a device, and a storage medium for generating a project group management map.
Background
With the development and popularization of software technology, project management software is widely used in various industries, wherein projects need to share organization resources, and resource allocation among projects is needed so as to obtain benefits which cannot be obtained when independent management is performed. There is a need for unified coordinated management of a group of interrelated items, i.e. a group of items, typically investment items. Project management software is a computer application that is dedicated to helping to plan and control project resources, costs, and progress. The method is mainly used for collecting, integrating, balancing and distributing input and output of project management processes. Conventional project management software includes functional modules such as time schedule, cost control, resource scheduling, and graphic report output, and a project group management chart typically presents information such as time schedule, cost, etc. of each project in the form of a table or list.
According to the mode, the information such as project progress, cost and the like is represented by characters, the presentation is not visual enough, the user needs to calculate and compare by himself, the time progress, the cost, the resources and the like are all separated functional modules, the user can only browse respectively, the observation difficulty is high, and the comprehensive comparison of the conditions of each project is inconvenient; the relation among the items in the item group is complex, a plurality of front or rear items possibly exist in one item, the relation among the items in the item group cannot be intuitively presented in a form of a table or a list, the user is inconvenient to integrally know and control the condition of the item group, and the management efficiency is greatly influenced.
Disclosure of Invention
According to the embodiment of the invention, the project group management chart generation method is provided, management information such as time progress, cost, resources and the like of the project group can be graphically displayed in one interface, and the display mode is more visual and intelligent.
In a first aspect of the present disclosure, a method for generating a project group management topology is provided. The method comprises the following steps:
acquiring item information of each item in the item group and an association relation between the items, wherein the item information comprises time information and/or resource information of the items;
drawing a straight line connecting line between the project nodes according to the association relation and the project information, wherein the length of the connecting line is determined based on time information and/or resource information of the project at one end of the connecting line;
adjusting the position of the project node to generate the project group management topological graph;
the project nodes comprise project nodes corresponding to the project groups and virtual project nodes serving as starting nodes or ending nodes.
In accordance with aspects and any one of the possible implementations described above, there is further provided an implementation in which the time information and/or the resource information of the item is input into a preset algorithm to determine the length of the link.
Aspects and any one of the possible implementations as described above, further providing an implementation, the adjusting the location of the project node includes:
automatically adjusting the position of the project node according to the presentation interface or adjusting the position of the project node according to manual operation;
and adjusting the connection lines between the project nodes synchronously with the position adjustment of the project nodes, wherein the length of the connection lines between the project nodes is kept unchanged.
Aspects and any one of the possible implementations as described above, further providing an implementation, the method further including:
and generating characters or controls according to the time information and/or the resource information of the items, and displaying the characters or controls at the corresponding positions of the connecting lines.
Aspects and any possible implementation as described above, further providing an implementation, the item information further includes an item name and/or an item number, and the method further includes:
and generating characters or controls according to the project names and/or the project numbers, and displaying the characters or controls at the corresponding positions of the project nodes.
Aspects and any possible implementation manner as described above, further provide an implementation manner, where drawing the project node and the connection line between the project nodes according to the association relationship and the project information includes:
traversing all the items backwards from the initial items of the item group according to the association relation, and drawing item nodes of each item and connecting lines between the nodes;
drawing a connection line between a virtual project node serving as an ending node and a termination project node of the project group and the virtual project node;
the length of the connection line between the project nodes is determined based on time information and/or resource information of the project at the front end of the connection line.
Aspects and any possible implementation manner as described above, further provide an implementation manner, where drawing the project node and the connection line between the project nodes according to the association relationship and the project information includes:
traversing all the projects forward from the termination projects of the project group according to the association relation, and drawing project nodes of each project and connecting lines between the nodes;
drawing a connection line between a virtual project node serving as a starting node and the starting project node of the project group and the virtual project node;
the length of the connection line between the project nodes is determined based on time information and/or resource information of the project at the back end of the connection line.
In a second aspect of the present disclosure, a project group management topology generation apparatus is provided. The device comprises:
the acquisition module is used for acquiring item information of each item in the item group and association relation among the items, wherein the item information comprises time information and/or resource information of the items;
the drawing module is used for drawing the project nodes and the straight line connecting lines between the project nodes according to the association relation and the project information, and the length of the connecting lines is determined based on the time information and/or the resource information of the projects at one end of the connecting lines;
the adjustment module is used for adjusting the position of the project node and generating the project group management topological graph;
the project nodes comprise project nodes corresponding to the project groups and virtual project nodes serving as starting nodes or ending nodes. .
In a third aspect of the present disclosure, an electronic device is provided. The electronic device includes: a memory and a processor, the memory having stored thereon a computer program, the processor implementing the method as described above when executing the program.
In a fourth aspect of the present disclosure, there is provided a computer readable storage medium having stored thereon a computer program which when executed by a processor implements a method as according to the first aspect of the present disclosure.
According to the technical scheme provided by the embodiment of the invention, the generation method of the project group management topological graph is provided, project nodes of all projects of the project group are drawn based on project information of all projects in the project group and association relations among the projects, the project nodes are presented in a graphical mode, the position arrangement of the project nodes represents the time progress sequence of all the projects of the project group, the associated project nodes are connected through straight lines, and the topological structure of the project group is intuitively presented through the graph. The continuous length of the straight line is determined through calculation of a preset algorithm related to time information and/or resource information, the time progress, cost and resources of the project can be observed through the length of the connecting line, the user does not need to calculate the time progress, cost and resources of the project by himself, characters or controls are generated according to the time information and/or the resource information of the project and displayed at corresponding positions of the connecting line, and the conditions of each project can be intuitively compared and analyzed.
According to the method, each item of the item group is traversed, item nodes are drawn, and association relations and item information among the items are represented through connecting lines. Besides the project nodes corresponding to the project groups, virtual project nodes serving as starting nodes or ending nodes are added in the topological graph, so that project information of the project nodes is displayed completely, and when the relation among projects is complex, and a plurality of front projects or rear projects of the project groups are arranged, the relation among the projects in the project groups can be clearly displayed, so that a user can know and control the condition of the project groups in an integral manner.
The method can realize automatic adjustment or manual operation adjustment of the positions of the project nodes, is convenient for a user to move the positions of the project nodes according to requirements or overlap each covered project node when the adjustment paths are more, and the generated project group management topological graph can be uniformly displayed in one interface, so that the project group management topological graph is convenient to view and manage.
It should be understood that what is described in this summary is not intended to limit the critical or essential features of the embodiments of the disclosure nor to limit the scope of the disclosure. Other features of the present disclosure will become apparent from the following description.
Drawings
The above and other features, advantages and aspects of embodiments of the present disclosure will become more apparent by reference to the following detailed description when taken in conjunction with the accompanying drawings. In the drawings, wherein like or similar reference numerals denote like or similar elements, in which:
fig. 1 is a schematic flow chart of a project group management topology generation method according to an embodiment of the present invention;
fig. 2 is a schematic flow chart of a project group management topology generating method according to an embodiment of the present invention;
fig. 3 is a schematic flow chart of a project group management topology generating method according to an embodiment of the present invention;
FIG. 4 illustrates a project group management topology pictorial intent generated in accordance with a method provided by an embodiment of the present invention;
FIG. 5 shows a block diagram of an item group management topology generation apparatus provided according to an embodiment of the present invention;
fig. 6 shows a block diagram of an exemplary electronic device, according to an embodiment of the invention.
Detailed Description
For the purposes of making the objects, technical solutions and advantages of the embodiments of the present disclosure more apparent, the technical solutions of the embodiments of the present disclosure will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present disclosure, and it is apparent that the described embodiments are some embodiments of the present disclosure, but not all embodiments. All other embodiments, which can be made by one of ordinary skill in the art based on the embodiments in this disclosure without inventive faculty, are intended to be within the scope of this disclosure.
In addition, the term "and/or" herein is merely an association relationship describing an association object, and means that three relationships may exist, for example, a and/or B may mean: a exists alone, A and B exist together, and B exists alone. In addition, the character "/" herein generally indicates that the front and rear associated objects are an "or" relationship.
The embodiment of the invention discloses a method, a device, equipment and a computer readable storage medium for generating a project group management topological graph, so as to uniformly and intuitively display project information and association relations of each project of a project group in one interface.
As shown in fig. 1, a flow chart of a method for generating a project group management topological graph according to an embodiment of the present invention is shown, where the method includes:
step S102, acquiring item information and association relation among items in each item in the item group, wherein the item information comprises time information and/or resource information of the items.
Specifically, each item in the item group has corresponding time information and/or resource information and an association relation among the items, and the time information of the items is a time node or a required time length of the items; the resource information of the project includes a plurality of project management contents, and may include, for example, funds, manpower, supplies, and technology. It should be noted that the acquired project information may be set according to the requirement, which is not limited in this embodiment.
And step S104, drawing a straight line connecting line between the project nodes according to the association relation and the project information, wherein the length of the connecting line is determined based on the time information and/or the resource information of the project at one end of the connecting line.
According to the project information of each project in the project group and the association relation between the projects, the project nodes can be determined, and the topological structure of each project node is determined so as to determine the positions of the project nodes. After determining the item node corresponding to the item group and the node position thereof according to the item information of the items and the association relation between the items, and determining the starting item and the ending item of the item group, wherein the starting item and the ending item respectively have one or more items, the starting item is the item which starts the earliest in time, and the ending item is the item which ends the latest in time. And determining virtual item nodes and node positions thereof according to the starting item and the ending item, wherein the virtual item nodes are root nodes of item groups, and one item group is provided with only one virtual item node serving as the starting node or only one virtual item node serving as the ending node, namely one item group is provided with only one virtual item node serving as the starting node or only one virtual item node serving as the ending node. The virtual item node serving as the starting node is a preposed item node of one or more starting items, and the virtual item node serving as the ending node is a postsed item node of one or more ending item nodes. And drawing out the virtual project node according to the position of the virtual project node.
And traversing each item of the item group, drawing the item node and the virtual item node corresponding to the item group, wherein a specific traversal process is described below, and the topological structure of the item group is embodied through the positions of the item nodes.
Wherein the traversing process comprises drawing a straight line connection between two item nodes with adjacent relation, such as a connection between an item and a subsequent item, and determining the length of the connection based on time information and/or resource information of the item at one end of the connection. And drawing straight line connecting lines between the initial project nodes and/or between the termination project nodes and the virtual project nodes, wherein the number of the initial project nodes is multiple, the number of the connecting lines between the initial project nodes and the virtual project nodes is multiple, and the number of the termination project nodes is multiple, and the number of the connecting lines between the termination project nodes and the virtual project nodes is multiple.
Further, the length of the connection line is calculated by inputting one or more item information into a preset algorithm. When an item information is obtained, the connection line length can be obtained by multiplying a preset coefficient, and the preset coefficient represents the conversion relation between the unit of the item information and the length unit. In one embodiment, the management of the project group focuses on the control of time, the length of the connection line represents the length of the time, the preset coefficient is 5mm/day (i.e. the length of 5mm corresponds to the duration of 1 day), the planned implementation duration of a project is 10 days, and the length of the connection line between the project and the sub-project is 5cm. When a plurality of item information are provided, each item information may be multiplied by a weight and added, and the result of the addition is multiplied by a preset coefficient representing a conversion relationship. In another embodiment, the time information t and the fund information m need to be considered, and the connection length l= (at+bm) X, where a and b are weights of the time information and the fund information, and X is a preset coefficient, and units of each information may be set according to practical situations. Thus, the length of the link can intuitively represent the result of comprehensively considering time and funds for the project at one end of the link.
Step S106, the positions of the project nodes are adjusted, and a project group management topological graph is generated.
Automatically adjusting the position of the project node according to the presentation interface or adjusting the position of the project node according to manual operation; and adjusting the connection lines between the project nodes synchronously with the position adjustment of the project nodes, wherein the length of the connection lines between the project nodes is kept unchanged. The user can conveniently move the positions of the project nodes according to the requirements or adjust the overlapped project nodes when the paths are more. The length of the connection line between the project nodes of the project group is calculated and drawn based on the project information, so that when a user drags the project nodes to change the positions of the project nodes, the length of the connection line is unchanged and moves synchronously with the project nodes. Optionally, the time critical path and/or the time shortest path is characterized by the color of the connection line.
Based on the above embodiment, a method for generating a project group management topological graph is provided, the project group management topological graph produced by the method graphically displays all projects in the project group, the projects are sequenced in time to represent the process of project group progress, the connection lines are used for connecting the associated projects to represent the association relationship of the projects and paths of the project group, which are required to be completed in the proceeding process from the beginning to the ending, and the topological structure of the project group is clearly displayed.
In one embodiment of the invention, item information and association relation corresponding to the item group are acquired, a start item and a stop item are determined, a virtual item node serving as a stop node is determined according to the stop item, and all items are traversed backwards from the start item of the item group. The specific process of traversing is as follows:
step S202, setting a starting item as a current item;
step S204, acquiring item information and association relation of a current item, and drawing item nodes of the current item;
step S206, judging whether the current item has a non-drawn post item, if so, entering step S208, otherwise, entering step S210;
step S208, acquiring item information and association relations of the post-items, drawing connection lines between item nodes of the post-items and item nodes of the current items and each post-item, calculating the length of the connection lines based on time information and/or resource information of the items at the front end of the connection lines, namely the current items, respectively setting each post-item as the current item, and returning to the step S206;
step S210, judging whether a drawn post-item exists, if so, drawing a connecting line between a current item and an item node of the drawn post-item, wherein the length of the connecting line is calculated based on time information and/or resource information of the current item; otherwise, go to step S212;
step S212, judging whether a virtual item node serving as an end node exists, if not, entering step S214, and if so, entering step S216;
step S214, drawing a virtual item node serving as an end node and a connecting line between the item node of the current item and the virtual item node, wherein the current item is a termination item, and the length of the connecting line is calculated based on the time information and/or the resource information of the front end of the connecting line, namely the termination item.
Step S216, drawing a connection line between the project node of the current project and the virtual project node, wherein the current project is a termination project, and the length of the connection line is calculated based on the time information and/or the resource information of the front end of the connection line, namely the termination project.
When the current item has a plurality of non-drawn post items, respectively setting the plurality of post items as the current item, and executing the steps in parallel; when there are a plurality of initial items, the steps S202 to S216 are executed from each initial item, so as to complete the traversal of the whole item group, draw all item nodes from the virtual item node having one or more initial items to the virtual item node as the end node, and show the topology structure of the item nodes by using the connection line between the item nodes.
The embodiment of the invention discloses another project group management topological graph generation method, and in the embodiment, compared with the previous embodiment, the step S102 of drawing the project nodes and the connecting lines between the project nodes according to the association relation and the project information comprises the following steps:
acquiring item information and association relation of items corresponding to the item group, determining a start item and a stop item, determining virtual item nodes serving as start nodes according to the start item, and traversing all the items from the stop item of the item group. The specific process of traversing is as follows:
step S302, setting a termination item as a current item;
step S304, acquiring item information and association relation of a current item, and drawing item nodes of the current item;
step S306, judging whether the current item has a non-drawn pre-item, if so, entering step S308, otherwise, entering step S310;
step S308, acquiring item information and association relation of the pre-items, drawing connection lines between the item nodes of the pre-items and the current items and the item nodes of each pre-item, calculating the length of the connection lines based on time information and/or resource information of the items at the rear end of the connection lines, namely the current items, respectively setting each pre-item as the current item, and returning to the step S306;
step S310, judging whether a drawn pre-project exists, if so, drawing a connecting line between a current project and a project node of the drawn pre-project, wherein the length of the connecting line is calculated based on time information and/or resource information of the current project; otherwise, go to step S312;
step S312, judging whether a virtual item node serving as a starting node exists, if not, entering step S314, and if so, entering step S316;
step S314, drawing a virtual item node serving as a starting node, and a connecting line between the item node of the current item and the virtual item node, wherein the current item is the starting item, and the length of the connecting line is calculated based on time information and/or resource information of the starting item which is the rear end of the connecting line.
Step S316, drawing a connection line between the project node of the current project and the virtual project node, wherein the current project is a starting project, and the length of the connection line is calculated based on time information and/or resource information of the starting project which is the rear end of the connection line.
When the current item has a plurality of non-drawn pre-items, respectively setting the pre-items as the current items, and executing the steps in parallel; when there are a plurality of termination projects, the steps S302 to S316 are executed from each termination project, so that the whole project group is traversed, all project nodes from the virtual project node as the start node to the termination project with one or more termination projects are drawn, and the topology structure of the project nodes is shown by the connection line between the project nodes.
Based on the above traversal process, all the items of the item group are traversed, the item nodes of all the item group from the termination item with one or more to the virtual item node as the start node are drawn, and the topology structure of the item nodes is shown by the connection lines between the item nodes.
Compared with the embodiment, the method for generating the project group management topological graph draws a virtual project node serving as a starting node and a virtual project node serving as an ending node in one project group, and the length of a connecting line between the nodes is calculated based on time information and/or resource information of projects at the front end or the rear end of the connecting line.
Based on any embodiment, the invention discloses a project group management topological graph generating method, which further comprises the following steps: and generating characters or controls according to the time information and/or the resource information of the items, and displaying the characters or controls at the corresponding positions of the connecting lines.
The specific implementation method comprises the following steps:
step 1: responding to hovering or leaving of a mouse on the project group management topological graph by using a preset control;
step 2: triggering a preset function when the mouse hovers above the connecting line and a specified period of time passes;
step 3: acquiring time information and/or resource information of the project through the set function, generating characters and displaying the characters at the corresponding positions of the connecting lines;
step 4: triggering a preset function when the mouse is tracked to leave the upper part of the connecting line;
step 5: and hiding time information and/or resource information of the corresponding item through the set function, and starting tracking of the mouse hovering.
By the method, when the mouse hovers over the connecting line, the time information and/or the resource information of the corresponding item are displayed, so that a user can conveniently and directly check the item information corresponding to the item in the item group management topological graph, and the item information is hidden when the mouse leaves the corresponding connecting line, so that the method is simple and attractive.
Based on any of the above embodiments, the present invention discloses a method for generating a project group management topology map, where in this embodiment, the project information further includes a project name and/or a project number.
And generating characters or controls according to the project names and/or the project numbers, and displaying the characters or controls at corresponding positions of the project nodes.
The method for generating the project group management topology is exemplified here by:
for example, a project group of investment projects, the specific projects of the project group are shown in table 1:
TABLE 1
The generated project group management topology is shown in fig. 4 based on the project time information of each project in the project group of table 1. The project group comprises two branch projects, namely a project I branch and a project II branch, and the flow of one branch project comprises the following steps: the project group management topological graph comprises each project node in each branch path, and the associated project nodes are connected by connecting wires to represent the association relation and project information of the project. The number of initial items is A1 and A2, A1 and A2 are items which start at the earliest time in each branch, and A1 and A2 do not have a pre-item, that is, when the item group comprises a plurality of branch items, the number of initial items is a plurality, and the initial time of each initial item can be different, but the initial time of each initial item is the item which starts at the earliest time in the branch.
Based on the method, each item is traversed, the item nodes and the connection lines between the nodes are generated, the item nodes are ordered according to the flow sequence of the items, and the length of the connection lines is calculated according to the required time length of the items at the front end of the connection lines, so that the difference of the required time lengths of the two branch items can be intuitively seen in the graph. The specific algorithm is as follows: the required time length of the front-end project of the connecting line is multiplied by a preset coefficient to obtain the connecting line length, the preset coefficient represents the conversion relation between the unit of the project information and the length unit, and the preset coefficient is 5 mm/day. And generating a project name and a project number at the project nodes, and displaying time information of the project at the front end of the connecting line on the connecting line between the nodes, so that the user can conveniently check the time information. In the present embodiment, a virtual item node X is generated as an end node, and time information of the end item is displayed on the connection line between the nodes of the end items F1, F2 and the virtual item node.
It should be noted that, for simplicity of description, the foregoing method embodiments are all described as a series of acts, but it should be understood by those skilled in the art that the present disclosure is not limited by the order of acts described, as some steps may be performed in other orders or concurrently in accordance with the present disclosure. Further, those skilled in the art will also appreciate that the embodiments described in the specification are all alternative embodiments, and that the acts and modules referred to are not necessarily required by the present disclosure.
The foregoing is a description of embodiments of the method, and the following further describes embodiments of the present disclosure through examples of apparatus.
Fig. 5 shows a block diagram of an item group management topology generation apparatus 500 according to an embodiment of the invention. As shown in fig. 5, the apparatus 500 includes:
the acquiring module 502 is configured to acquire item information and an association relationship between items of each item in the item group, where the item information includes time information and/or resource information of the items;
a drawing module 504, configured to draw a straight line connection between the project nodes according to the association relationship and the project information, where the length of the connection is determined based on time information and/or resource information of the project at one end of the connection;
the adjustment module 506 is configured to adjust a position of a project node, and generate a project group management topology map;
the project nodes comprise project nodes corresponding to the project groups and virtual project nodes serving as starting nodes or ending nodes.
It will be clear to those skilled in the art that, for convenience and brevity of description, specific working procedures of the described modules may refer to corresponding procedures in the foregoing method embodiments, which are not described herein again.
Fig. 6 shows a schematic block diagram of an electronic device 600 that may be used to implement embodiments of the present disclosure. The apparatus 600 may be used to implement the project group management topology generation method of fig. 1. As shown in fig. 6, the apparatus 600 includes a Central Processing Unit (CPU) 601, which can perform various suitable actions and processes according to computer program instructions stored in a Read Only Memory (ROM) 602 or computer program instructions loaded from a storage unit 608 into a Random Access Memory (RAM) 603. In the RAM 603, various programs and data required for the operation of the device 600 can also be stored. The CPU 601, ROM 602, and RAM 603 are connected to each other through a bus 604. An input/output (I/O) interface 605 is also connected to bus 604.
Various components in the device 600 are connected to the I/O interface 605, including: an input unit 606 such as a keyboard, mouse, etc.; an output unit 607 such as various types of displays, speakers, and the like; a storage unit 608, such as a magnetic disk, optical disk, or the like; and a communication unit 609 such as a network card, modem, wireless communication transceiver, etc. The communication unit 609 allows the device 600 to exchange information/data with other devices via a computer network, such as the internet, and/or various telecommunication networks.
The processing unit 601 performs the respective methods and processes described above. For example, in some embodiments, the method may be implemented as a computer software program tangibly embodied on a machine-readable medium, such as storage unit 608. In some embodiments, part or all of the computer program may be loaded and/or installed onto the device 600 via the ROM 602 and/or the communication unit 609. When the computer program is loaded into RAM 603 and executed by CPU 601, one or more steps of the method described above may be performed. Alternatively, in other embodiments, CPU 601 may be configured to perform the method by any other suitable means (e.g., by means of firmware).
The functions described above herein may be performed, at least in part, by one or more hardware logic components. For example, without limitation, exemplary types of hardware logic components that may be used include: a Field Programmable Gate Array (FPGA), an Application Specific Integrated Circuit (ASIC), an Application Specific Standard Product (ASSP), a system on a chip (SOC), a load programmable logic device (CPLD), etc.
Program code for carrying out methods of the present disclosure may be written in any combination of one or more programming languages. These program code may be provided to a processor or controller of a general purpose computer, special purpose computer, or other programmable data processing apparatus such that the program code, when executed by the processor or controller, causes the functions/operations specified in the flowchart and/or block diagram to be implemented. The program code may execute entirely on the machine, partly on the machine, as a stand-alone software package, partly on the machine and partly on a remote machine or entirely on the remote machine or server.
In the context of this disclosure, a machine-readable medium may be a tangible medium that can contain, or store a program for use by or in connection with an instruction execution system, apparatus, or device. The machine-readable medium may be a machine-readable signal medium or a machine-readable storage medium. The machine-readable medium may include, but is not limited to, an electronic, magnetic, optical, electromagnetic, infrared, or semiconductor system, apparatus, or device, or any suitable combination of the foregoing. More specific examples of a machine-readable storage medium would include an electrical connection based on one or more wires, a portable computer diskette, a hard disk, a Random Access Memory (RAM), a read-only memory (ROM), an erasable programmable read-only memory (EPROM or flash memory), an optical fiber, a portable compact disc read-only memory (CD-ROM), an optical storage device, a magnetic storage device, or any suitable combination of the foregoing.
Moreover, although operations are depicted in a particular order, this should be understood as requiring that such operations be performed in the particular order shown or in sequential order, or that all illustrated operations be performed, to achieve desirable results. In certain circumstances, multitasking and parallel processing may be advantageous. Likewise, while several specific implementation details are included in the above discussion, these should not be construed as limiting the scope of the present disclosure. Certain features that are described in the context of separate embodiments can also be implemented in combination in a single implementation. Conversely, various features that are described in the context of a single implementation can also be implemented in multiple implementations separately or in any suitable subcombination.
Although the subject matter has been described in language specific to structural features and/or methodological acts, it is to be understood that the subject matter defined in the appended claims is not necessarily limited to the specific features or acts described above. Rather, the specific features and acts described above are example forms of implementing the claims.

Claims (9)

1. A method for generating a project group management topology, comprising:
acquiring item information of each item in the item group and an association relation between the items, wherein the item information comprises time information and resource information of the items;
drawing a straight line connecting line between the project node and two project nodes with front-back adjacent relations according to the association relation and the project information, wherein the length of the connecting line is determined based on the time information and the resource information of the project at one end of the connecting line,
inputting time information and resource information of the project into a preset algorithm to determine the length of the connecting line, and multiplying a preset coefficient to obtain the length of the connecting line when one project is information, wherein the preset coefficient represents the conversion relation between the unit of the project information and the length unit; when a plurality of item information are obtained, multiplying each item information by a weight and adding, and multiplying the added result by a preset coefficient representing a conversion relationship;
adjusting the position of the project node to generate the project group management topological graph;
the project nodes comprise project nodes corresponding to the project groups and virtual project nodes serving as starting nodes or ending nodes.
2. The method of claim 1, wherein said adjusting the location of the project node comprises:
automatically adjusting the position of the project node according to the presentation interface or adjusting the position of the project node according to manual operation;
and adjusting the connection lines between the project nodes synchronously with the position adjustment of the project nodes, wherein the length of the connection lines between the project nodes is kept unchanged.
3. The method as recited in claim 2, further comprising:
and generating characters or controls according to the time information and the resource information of the items, and displaying the characters or controls at the corresponding positions of the connecting lines.
4. A method according to claim 3, wherein the item information further comprises an item name and/or an item number, the method further comprising:
and generating characters or controls according to the project names and/or the project numbers, and displaying the characters or controls at the corresponding positions of the project nodes.
5. The method according to any one of claims 1-4, wherein the drawing the project node and the connection line between the project nodes according to the association relationship and the project information includes:
traversing all the items backwards from the initial items of the item group according to the association relation, and drawing item nodes of each item and connecting lines between the nodes;
drawing a connection line between a virtual project node serving as an ending node and a termination project node of the project group and the virtual project node;
the length of the connection line between the project nodes is determined based on the time information and the resource information of the project at the front end of the connection line.
6. The method according to any one of claims 1-4, wherein the drawing the project node and the connection line between the project nodes according to the association relationship and the project information includes:
traversing all the projects forward from the termination projects of the project group according to the association relation, and drawing project nodes of each project and connecting lines between the nodes;
drawing a connection line between a virtual project node serving as a starting node and the starting project node of the project group and the virtual project node;
the length of the connection line between the project nodes is determined based on the time information and the resource information of the project at the back end of the connection line.
7. An item group management topology generation apparatus, comprising:
the acquisition module is used for acquiring item information of each item in the item group and association relation among the items, wherein the item information comprises time information and resource information of the items;
a drawing module for drawing a straight line connecting line between the project nodes and two project nodes with front-back adjacent relations according to the association relation and the project information, wherein the length of the connecting line is determined based on the time information and the resource information of the project at one end of the connecting line,
inputting time information and resource information of the project into a preset algorithm to determine the length of the connecting line, and multiplying a preset coefficient to obtain the length of the connecting line when one project is information, wherein the preset coefficient represents the conversion relation between the unit of the project information and the length unit; when a plurality of item information are obtained, multiplying each item information by a weight and adding, and multiplying the added result by a preset coefficient representing a conversion relationship;
the adjustment module is used for adjusting the position of the project node and generating the project group management topological graph;
the project nodes comprise project nodes corresponding to the project groups and virtual project nodes serving as starting nodes or ending nodes.
8. An electronic device comprising a memory and a processor, the memory having stored thereon a computer program, characterized in that the processor, when executing the program, implements the method according to any of claims 1-6.
9. A computer readable storage medium, on which a computer program is stored, characterized in that the program, when being executed by a processor, implements the method according to any one of claims 1-6.
CN202010019626.2A 2020-01-08 2020-01-08 Project group management topological graph generation method, device, equipment and storage medium Active CN111192342B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010019626.2A CN111192342B (en) 2020-01-08 2020-01-08 Project group management topological graph generation method, device, equipment and storage medium

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010019626.2A CN111192342B (en) 2020-01-08 2020-01-08 Project group management topological graph generation method, device, equipment and storage medium

Publications (2)

Publication Number Publication Date
CN111192342A CN111192342A (en) 2020-05-22
CN111192342B true CN111192342B (en) 2024-01-16

Family

ID=70710755

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010019626.2A Active CN111192342B (en) 2020-01-08 2020-01-08 Project group management topological graph generation method, device, equipment and storage medium

Country Status (1)

Country Link
CN (1) CN111192342B (en)

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06332909A (en) * 1993-05-26 1994-12-02 Ishikawajima Harima Heavy Ind Co Ltd Plan managing system
US6363062B1 (en) * 1999-06-08 2002-03-26 Caly Corporation Communications protocol for packet data particularly in mesh topology wireless networks
CN102385720A (en) * 2010-09-06 2012-03-21 杨瑞宁 Project planning, tracking and predicating method
CN103647765A (en) * 2013-11-29 2014-03-19 北京广利核系统工程有限公司 A graphical representation method for describing a network protocol based on a UML sequence diagram and a topological graph
CN104317876A (en) * 2014-10-21 2015-01-28 百度在线网络技术(北京)有限公司 Road network vector data generation method and device
CN106529788A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Project plan chart generation method and device
CN106529904A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Branching view generating method and branching view generating device
CN107464092A (en) * 2017-07-18 2017-12-12 东软集团股份有限公司 The template switching method and device of business process map
CN108628432A (en) * 2017-03-22 2018-10-09 中国航天员科研训练中心 A kind of workload assessment method and system based on resource occupation and Annual distribution
CN109697118A (en) * 2017-10-20 2019-04-30 北京京东尚科信息技术有限公司 Streaming computing task management method, device, electronic equipment and storage medium

Family Cites Families (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20060184314A1 (en) * 2005-02-14 2006-08-17 Microsoft Corporation Multi-modal navigation system and method
US20070129976A1 (en) * 2005-08-04 2007-06-07 Prolify Ltd. Apparatus and methods for process and project management and control
US20180046959A1 (en) * 2016-08-10 2018-02-15 International Business Machines Corporation Similar project identification
US20180181892A1 (en) * 2016-12-23 2018-06-28 Caterpillar Inc. System for forecasting core return for remanufacturing

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPH06332909A (en) * 1993-05-26 1994-12-02 Ishikawajima Harima Heavy Ind Co Ltd Plan managing system
US6363062B1 (en) * 1999-06-08 2002-03-26 Caly Corporation Communications protocol for packet data particularly in mesh topology wireless networks
CN102385720A (en) * 2010-09-06 2012-03-21 杨瑞宁 Project planning, tracking and predicating method
CN103647765A (en) * 2013-11-29 2014-03-19 北京广利核系统工程有限公司 A graphical representation method for describing a network protocol based on a UML sequence diagram and a topological graph
CN104317876A (en) * 2014-10-21 2015-01-28 百度在线网络技术(北京)有限公司 Road network vector data generation method and device
CN106529788A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Project plan chart generation method and device
CN106529904A (en) * 2016-10-25 2017-03-22 乐视控股(北京)有限公司 Branching view generating method and branching view generating device
CN108628432A (en) * 2017-03-22 2018-10-09 中国航天员科研训练中心 A kind of workload assessment method and system based on resource occupation and Annual distribution
CN107464092A (en) * 2017-07-18 2017-12-12 东软集团股份有限公司 The template switching method and device of business process map
CN109697118A (en) * 2017-10-20 2019-04-30 北京京东尚科信息技术有限公司 Streaming computing task management method, device, electronic equipment and storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
多项目资源均衡问题及其遗传算法;王为新;《计算机应用研究》;全文 *

Also Published As

Publication number Publication date
CN111192342A (en) 2020-05-22

Similar Documents

Publication Publication Date Title
CN106500686B (en) Navigation interface display methods, logistics air navigation aid and device
CN106557457B (en) QT-based system for automatically generating cross-platform complex flow chart
CN107845011B (en) Method and apparatus for handling order
CN110388921A (en) Picking air navigation aid and device
CN109033001A (en) Method and apparatus for distributing GPU
CN109213486A (en) Method and apparatus for generating customized visualization component
CN111427901A (en) Interactive knowledge graph data editing method, computer device and storage medium
CN109063190A (en) Method and apparatus for handling data sequence
CN109598571A (en) Spell folk prescription method and relevant apparatus
CN110443531A (en) The method and apparatus for determining the bit information of article in order
CN115857920A (en) Application page development method, device and system, computing equipment and storage medium
US20130332897A1 (en) Creating a user model using component based approach
CN104915251A (en) Task scheduling method and device
CN112116679B (en) Train running chart generation method and device and electronic equipment
US20090007010A1 (en) Hosted data visualization service
CN109902182A (en) Knowledge data processing method, device, equipment and storage medium
CN109446384A (en) For generating the method and system of personnel arrangement Schema information
CN111192342B (en) Project group management topological graph generation method, device, equipment and storage medium
CN111157000B (en) Method and apparatus for generating path information
CN110135814A (en) The correlating method of BIM and project data, system and terminal device
CN108376177B (en) For handling the method and distributed system of information
CN110083351A (en) Method and apparatus for generating code
CN111104568A (en) Enterprise stock right relation deep search method and device, computer equipment and storage medium
CN113986380B (en) Data processing method, device and system, electronic equipment and storage medium
CN109656709A (en) A kind of method and apparatus of Codis cluster dilatation

Legal Events

Date Code Title Description