CN111155572A - 一种利用土工格栅调节新旧桩刚度的旧桩利用方法 - Google Patents
一种利用土工格栅调节新旧桩刚度的旧桩利用方法 Download PDFInfo
- Publication number
- CN111155572A CN111155572A CN202010017427.8A CN202010017427A CN111155572A CN 111155572 A CN111155572 A CN 111155572A CN 202010017427 A CN202010017427 A CN 202010017427A CN 111155572 A CN111155572 A CN 111155572A
- Authority
- CN
- China
- Prior art keywords
- pile
- old
- new
- geogrid
- head
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D37/00—Repair of damaged foundations or foundation structures
Landscapes
- Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Mining & Mineral Resources (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Foundations (AREA)
Abstract
本发明涉及一种利用土工格栅调节新旧桩刚度的旧桩利用方法,包括:1)拆除施工场地的原有上部结构和旧承台,在既有旧桩的地基上施工新桩;2)开挖土体,直至露出旧桩桩头,若旧桩桩头高于新桩,则需要进行凿除处理,若旧桩桩头显著低于新桩,则可按需求接桩,使新桩桩头略高于旧桩,以预留高度铺置土工格栅和回填土体;3)铺置土工格栅,回填土体,直至新桩桩顶,并压实处理;4)施工承台,连接新桩。在已有旧桩场地施工新桩,不用拔除旧桩,缩短工期,提升经济效益;通过土工格栅和回填土体实现新旧桩的刚度的被动调节,合理利用旧桩的承载能力;利用土工格栅调节新旧桩刚度,可靠性高、耐用性好,成本低、施工简单,经济效益更优。
Description
技术领域
本发明涉及土木工程领域,具体的说是一种利用土工格栅调节新旧桩刚度的旧桩利用方法。
背景技术
在对城市旧区改造过程中,往往要先拆除已有建筑,再在原来的地基上施工新的建筑。若已有建筑的基础属于桩基础,如何处理既有桩基成为工程中一个棘手的问题。常规做法是将旧桩完全拔除后再施工新桩,但这种做法不符合可持续发展理念,还会增加施工成本、延长工期,同时对地基土体产生扰动,不利于新建建筑的施工。因此旧桩利用成为工程实践的新趋势。
目前旧桩利用的方法可分为两大类:
(1)将旧桩通过植筋等方式使桩头与新建承台刚性连接(如专利一种采用组合桩施工的桩基加固结构,ZL201420650621)。这种方法不对旧桩或地基做特殊处理,施工容易;但缺点也是显而易见的:即使新桩长度尺寸等参数与旧桩完全相同,由于桩周土体固结程度不同,新旧桩的刚度也存在较大差异,这种同一承台下基桩刚度不同的桩基础容易造成承台的不均匀沉降,进而产生工程质量隐患。
(2)在旧桩头与承台之间添加主动或被动刚度调节装置(如专利桩端位移调节装置,ZL2005100403164;桩头的箍与带箍的桩,ZL 2007101609661;一种支承刚度可调式桩筏基础及施工工艺,ZL2009100283584)。这类装置较好地解决了基桩刚度差异的问题,实现了群桩基础的变刚度调平。但也带来了新的问题,新旧桩之间刚度的调节依赖结构复杂的刚度调节装置,而调节装置一旦在建筑漫长的使用年限中失效,或是使得旧桩与承台刚性连接,或是使得旧桩与承台脱离,无论何种情况都容易造成工程问题。另一方面,新增的调节装置也增加了施工成本和工艺复杂度。
发明内容
本发明旨在克服现有技术的缺陷,提供一种利用土工格栅调节新旧桩刚度的旧桩利用方法,通过在旧桩桩顶和新建承台之间铺置土工格栅、回填土体,达到调节新旧桩刚度的目的,实现与新桩共同承担荷载的作用。
为了解决上述技术问题,本发明是这样实现的:
一种利用土工格栅调节新旧桩刚度的旧桩利用方法,其特征在于它包括如下步骤:
步骤一:拆除施工场地的原有上部结构和旧承台,在既有旧桩的地基上施工新桩;
步骤二:开挖土体,直至露出旧桩桩头,若旧桩桩头高于新桩,则需要进行凿除处理,若旧桩桩头低于新桩,则可按需求接桩,凿除或接桩后需使新桩桩头略高于旧桩桩头,以预留高度铺置土工格栅和回填土体;
步骤三:在旧桩桩头上铺置土工格栅,回填土体,直至与新桩桩顶齐平,并压实处理;
步骤四:在新桩桩顶施工新承台,新承台下部与新桩连接。
所述的利用土工格栅调节新旧桩刚度的旧桩利用方法,其特征在于:旧桩桩头低于新桩三分之一时,在其上部接桩。
本发明的有益效果是:在已有旧桩场地施工新桩,不用拔除旧桩,缩短工期,提升经济效益;通过土工格栅和回填土体实现新旧桩的刚度的被动调节,合理利用旧桩的承载能力;对比现有技术手段,利用土工格栅调节新旧桩刚度,可靠性高、耐用性好,成本低、施工简单,经济效益更优。
附图说明
下面结合附图和实施方式对本发明作进一步的详细说明:
图1为施工前的示意图;
图2为施工至步骤2示意图;
图3为施工完成的示意图。
图中:1.旧承台;2.旧桩;3.新承台;4.回填土;5.土工格栅;6.新桩。
具体实施方式
实施例1
如图1所示,某场地已有旧桩2若干,通过旧承台1相连,为施工新建筑,还需增加若干新桩。本发明所述一种利用土工格栅调节新旧桩刚度的旧桩利用方法,包括如下步骤:
1)如图2所示,拆除原有旧承台1后,施工新桩6,并开挖土体,凿除旧桩2的一段桩头,使旧桩2的桩头标高低于新桩6的桩头标高;
2)如图3所示,分层铺设土工格栅5和回填土4,并分层压实,使场地达到设计标高;
3)施工新承台3,将新桩6刚性连接。
旧桩与新承台不直接连接,而是在旧桩和新承台之间铺置土工格栅、回填土体。土工格栅不提供竖向承载力,但能对格栅中的回填土体起到环抱和箍筋作用,使土体处于三向受力状态,大大增强回填土体的强度,提供一定的竖向承载能力。回填土体在传递竖向荷载的同时,发生一定程度的变形,能够保证新承台的一部分竖向荷载传递到旧桩,发挥旧桩的承载力,从而实现群桩基础的被动刚度调节。而土工格栅已经在路基工程、地基加固工程等方面得到了广泛运用,其结构简单、性质稳定,耐用性和可靠度已经得到证明,在建筑物的服务期内不会出现失效的情况。
Claims (2)
1.一种利用土工格栅调节新旧桩刚度的旧桩利用方法,其特征在于,它包括如下步骤:
步骤一:拆除施工场地的原有上部结构和旧承台,在既有旧桩的地基上施工新桩;
步骤二:开挖土体,直至露出旧桩桩头,若旧桩桩头高于新桩,则需要进行凿除处理,若旧桩桩头低于新桩,则可按需求接桩,凿除或接桩后需使新桩桩头略高于旧桩桩头,以预留高度铺置土工格栅和回填土体;
步骤三:在旧桩桩头上铺置土工格栅,回填土体,直至与新桩桩顶齐平,并压实处理;
步骤四:在新桩桩顶施工新承台,新承台下部与新桩连接。
2.根据权利要求1所述的利用土工格栅调节新旧桩刚度的旧桩利用方法,其特征在于:旧桩桩头低于新桩三分之一时,在其上部接桩。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010017427.8A CN111155572A (zh) | 2020-01-08 | 2020-01-08 | 一种利用土工格栅调节新旧桩刚度的旧桩利用方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN202010017427.8A CN111155572A (zh) | 2020-01-08 | 2020-01-08 | 一种利用土工格栅调节新旧桩刚度的旧桩利用方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111155572A true CN111155572A (zh) | 2020-05-15 |
Family
ID=70561908
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN202010017427.8A Pending CN111155572A (zh) | 2020-01-08 | 2020-01-08 | 一种利用土工格栅调节新旧桩刚度的旧桩利用方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111155572A (zh) |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SG103365A1 (en) * | 2002-10-08 | 2004-04-29 | Abv Engineering Pte Ltd | Repairing or reinforcing building foundations |
CN203729175U (zh) * | 2013-12-30 | 2014-07-23 | 浙江大学城市学院 | 桩网复合地基结构 |
CN104294769A (zh) * | 2014-09-16 | 2015-01-21 | 杭州江润科技有限公司 | 一种补桩与增大台帽组合加固已建桥台结构及施工方法 |
CN204282388U (zh) * | 2014-11-04 | 2015-04-22 | 昆明理工大学 | 一种采用组合桩施工的桩基加固结构 |
CN106894432A (zh) * | 2017-04-08 | 2017-06-27 | 山东省建筑科学研究院 | 一种桩承变刚度加筋垫层复合地基及其施工方法 |
CN108457204A (zh) * | 2018-02-10 | 2018-08-28 | 北京工业大学 | 一种针对旧桥基础承载力不足进行加固装置 |
CN109162210A (zh) * | 2018-09-04 | 2019-01-08 | 广东和立土木工程有限公司 | 用于桥梁维修加固或拓宽扩建的新增桩基施工方法 |
CN208717675U (zh) * | 2018-08-31 | 2019-04-09 | 周静 | 一种改扩建工程新旧路基路面拼接结构 |
-
2020
- 2020-01-08 CN CN202010017427.8A patent/CN111155572A/zh active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
SG103365A1 (en) * | 2002-10-08 | 2004-04-29 | Abv Engineering Pte Ltd | Repairing or reinforcing building foundations |
CN203729175U (zh) * | 2013-12-30 | 2014-07-23 | 浙江大学城市学院 | 桩网复合地基结构 |
CN104294769A (zh) * | 2014-09-16 | 2015-01-21 | 杭州江润科技有限公司 | 一种补桩与增大台帽组合加固已建桥台结构及施工方法 |
CN204282388U (zh) * | 2014-11-04 | 2015-04-22 | 昆明理工大学 | 一种采用组合桩施工的桩基加固结构 |
CN106894432A (zh) * | 2017-04-08 | 2017-06-27 | 山东省建筑科学研究院 | 一种桩承变刚度加筋垫层复合地基及其施工方法 |
CN108457204A (zh) * | 2018-02-10 | 2018-08-28 | 北京工业大学 | 一种针对旧桥基础承载力不足进行加固装置 |
CN208717675U (zh) * | 2018-08-31 | 2019-04-09 | 周静 | 一种改扩建工程新旧路基路面拼接结构 |
CN109162210A (zh) * | 2018-09-04 | 2019-01-08 | 广东和立土木工程有限公司 | 用于桥梁维修加固或拓宽扩建的新增桩基施工方法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN107142856B (zh) | 桥台改造方法、桥台、桥台改造的桥墩及顶升改造的桥梁 | |
CN103233454A (zh) | 湿陷性黄土地基的砂桩浸水真空预压及注浆处理方法 | |
WO2021027025A1 (zh) | 一种高层建筑沉降加固抬升纠偏的施工方法 | |
CN108412225A (zh) | 已有建筑的地下加层施工方法 | |
CN207092107U (zh) | 一种利用地下连续墙的抗沉陷结构 | |
CN108442370A (zh) | 预应力混凝土管桩的断桩接头处理方法 | |
CN103774674A (zh) | 一种钢管托换桩与锚杆深基坑支护结构及其施工方法 | |
KR100657613B1 (ko) | 말뚝 두부에 설치된 토목섬유를 포함하는 연약지반 지지력강화장치 | |
CN101215840B (zh) | 飞机式基础加固予力工法 | |
CN206941425U (zh) | 桥台、桥台改造的桥墩及顶升改造的桥梁 | |
KR100881944B1 (ko) | 연약지반의 지지력 강화 방법 및 말뚝 두부에 설치된토목섬유를 포함하는 연약지반 지지력 강화장치 | |
CN108385693B (zh) | 一种用于分期地下室支护的等代锚杆支护方法和支护体系 | |
CN114000524A (zh) | 一种深厚淤泥地质临近构造物的钢板桩围堰结构及施工方法 | |
CN111810185B (zh) | 一种隧道隧底预加固施工方法 | |
CN111235992B (zh) | 一种斜坡软土地基悬臂挡墙加固结构及构造方法 | |
CN108978680A (zh) | 一种淤泥质土电梯基坑支护施工装置及方法 | |
CN111593739A (zh) | 一种水泥土搅拌桩围护墙-型钢悬臂式组合支护 | |
CN111155572A (zh) | 一种利用土工格栅调节新旧桩刚度的旧桩利用方法 | |
CN108411886A (zh) | 一种仓储地坪沉降控制体系及其施工方法 | |
CN216275592U (zh) | 一种预应力混凝土管桩基础挡土墙防沉降结构 | |
CN215367385U (zh) | 一种非开挖施工的悬臂式挡土墙 | |
CN103266624A (zh) | 输油气管道穿越岩溶强活动区的管道穿越支撑方法 | |
CN212248277U (zh) | 一种既有隧道土质地基高填方结构 | |
CN220394552U (zh) | 一种设有斜撑的三排桩锚索基坑支护结构 | |
CN212742557U (zh) | 一种水泥土搅拌桩围护墙-型钢悬臂式组合支护 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200515 |