CN111151405A - Gas type finish paint baking assembly line - Google Patents
Gas type finish paint baking assembly line Download PDFInfo
- Publication number
- CN111151405A CN111151405A CN201911390403.0A CN201911390403A CN111151405A CN 111151405 A CN111151405 A CN 111151405A CN 201911390403 A CN201911390403 A CN 201911390403A CN 111151405 A CN111151405 A CN 111151405A
- Authority
- CN
- China
- Prior art keywords
- chamber
- baking
- gas
- drying
- dust blowing
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05B—SPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
- B05B16/00—Spray booths
- B05B16/20—Arrangements for spraying in combination with other operations, e.g. drying; Arrangements enabling a combination of spraying operations
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05B—SPRAYING APPARATUS; ATOMISING APPARATUS; NOZZLES
- B05B13/00—Machines or plants for applying liquids or other fluent materials to surfaces of objects or other work by spraying, not covered by groups B05B1/00 - B05B11/00
- B05B13/02—Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work
- B05B13/0221—Means for supporting work; Arrangement or mounting of spray heads; Adaptation or arrangement of means for feeding work characterised by the means for moving or conveying the objects or other work, e.g. conveyor belts
- B05B13/0264—Overhead conveying means, i.e. the object or other work being suspended from the conveying means; Details thereof, e.g. hanging hooks
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D—PROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D3/00—Pretreatment of surfaces to which liquids or other fluent materials are to be applied; After-treatment of applied coatings, e.g. intermediate treating of an applied coating preparatory to subsequent applications of liquids or other fluent materials
- B05D3/02—Pretreatment of surfaces to which liquids or other fluent materials are to be applied; After-treatment of applied coatings, e.g. intermediate treating of an applied coating preparatory to subsequent applications of liquids or other fluent materials by baking
- B05D3/0254—After-treatment
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B05—SPRAYING OR ATOMISING IN GENERAL; APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D—PROCESSES FOR APPLYING FLUENT MATERIALS TO SURFACES, IN GENERAL
- B05D3/00—Pretreatment of surfaces to which liquids or other fluent materials are to be applied; After-treatment of applied coatings, e.g. intermediate treating of an applied coating preparatory to subsequent applications of liquids or other fluent materials
- B05D3/04—Pretreatment of surfaces to which liquids or other fluent materials are to be applied; After-treatment of applied coatings, e.g. intermediate treating of an applied coating preparatory to subsequent applications of liquids or other fluent materials by exposure to gases
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B08—CLEANING
- B08B—CLEANING IN GENERAL; PREVENTION OF FOULING IN GENERAL
- B08B3/00—Cleaning by methods involving the use or presence of liquid or steam
- B08B3/02—Cleaning by the force of jets or sprays
- B08B3/022—Cleaning travelling work
-
- B—PERFORMING OPERATIONS; TRANSPORTING
- B08—CLEANING
- B08B—CLEANING IN GENERAL; PREVENTION OF FOULING IN GENERAL
- B08B5/00—Cleaning by methods involving the use of air flow or gas flow
- B08B5/02—Cleaning by the force of jets, e.g. blowing-out cavities
- B08B5/023—Cleaning travelling work
Abstract
The invention discloses a gas type finish paint baking assembly line which comprises a water curtain chamber, wherein a water pump is fixedly arranged on one side of the outer portion of the water curtain chamber, a drying chamber is arranged on one side of the water curtain chamber, an electric heating drying pipe is fixedly arranged on one side of the inner portion of the drying chamber, a dust blowing chamber is arranged on one side of the drying chamber, which is far away from the water curtain chamber, an electrostatic dust removal gun head is slidably arranged on one side of the inner portion of the dust blowing chamber, a paint spraying chamber is arranged on one side of the dust blowing chamber, which is far away from the drying chamber, a pre-baking chamber is arranged on one side of the paint spraying chamber, which is far away from the dust blowing chamber, an electric heating baking pipe is fixedly arranged on one side of the inner portion of the pre-baking chamber, a main baking chamber is arranged on one side. The method comprises two baking steps, namely, firstly, pre-baking operation is carried out to evaporate part of a solvent, a wet paint film is leveled, then, main baking operation is carried out to dry the surface forcibly, and the two steps are matched to ensure that the baking efficiency is high.
Description
Technical Field
The invention relates to the field of spraying, in particular to a gas-fired finish paint baking production line.
Background
In the process of paint spraying operation of an object, the required steps are various, and after general paint is sprayed, the painted object needs to be baked, namely finish paint baking operation.
Because the article process of spraying paint is more, generally carry out the operation one by one and wasted a large amount of time, need carry out corresponding processing operation to the article surface before the operation of spraying paint, handle improper effect that can't reach surfacing, generally the spraying is accomplished the back and is directly toasted the operation, the inside high temperature of oven or low excessively can all cause the influence to the lacquer surface, can't accurately judge the required temperature of surface, the spoilage is high, production efficiency is low.
Disclosure of Invention
The invention aims to solve the defects in the prior art and provides a gas-fired finish paint baking production line.
In order to achieve the purpose, the invention adopts the following technical scheme: the utility model provides a gas formula finish paint toasts assembly line, includes the cascade room, the fixed water pump that is provided with in outside one side of cascade room, one side of cascade room is provided with the drying chamber, the fixed electric heat drying tube that is provided with in inside one side of drying chamber, one side that the drying chamber deviates from the cascade room is provided with the dust blowing room, the inside one side slip of dust blowing room is provided with the electrostatic precipitator rifle head, one side that the dust blowing room deviates from the drying chamber is provided with the paint spray booth, one side that the paint spray booth deviates from the dust blowing room is provided with the pre-bake room, the fixed electric heat drying tube that is provided with in inside one side of pre-bake room, one side that the pre-bake room deviates from the paint spray booth is provided with main bake room, the fixed gas jar that is provided with in surface one side of main bake room, the inboard upper portion of cascade room runs through and is provided with the conveying, The drying chamber, the dust blowing chamber, the paint spraying chamber, the pre-baking chamber and the main baking chamber.
As a further description of the above technical solution:
the lower surface middle part rigidity of carrying the chain is provided with the hanger, the hanger is provided with a plurality ofly along the trend equidistance of carrying the chain.
As a further description of the above technical solution:
the fixed shunt tubes that is provided with of inside upside of cascade room, and the shunt tubes lies in the top of carrying the chain relatively, the pipe shaft lower surface equidistance of shunt tubes is provided with a plurality of heads that drench, the one end fixedly connected with water pipe of shunt tubes, and water pipe fixed connection is on the water pump.
As a further description of the above technical solution:
the electric heating drying tubes are fixedly arranged on the inner side wall of the drying chamber and are vertically arranged, two electric heating drying tubes are arranged on two sides of the inside of the drying chamber, and the two electric heating drying tubes are oppositely arranged on two sides of the conveying chain.
As a further description of the above technical solution:
the dust blowing chamber is characterized in that a sliding strip is fixedly arranged on the inner side wall of the dust blowing chamber, a sliding block is connected inside the sliding strip in a sliding mode, the middle of the side surface of the sliding block is fixedly connected with an electrostatic dust removal gun head, and the two side walls inside the dust blowing chamber are identical in structure.
As a further description of the above technical solution:
the electric heating baking tubes are fixedly arranged at the lower side and the left side and the right side of the interior of the pre-baking chamber, and the electric heating baking tubes are not in contact with each other.
As a further description of the above technical solution:
the inside wall of main baking chamber is fixed and is provided with the gas-distributing pipe, gas-distributing pipe's pipe shaft surface equidistance is provided with a plurality of gas and toasts the shower nozzle, and gas-distributing pipe one end fixed connection on the gas jar.
The invention has the following beneficial effects:
1. the structure assembly line of the invention is provided with six steps of washing, drying, dust blowing, paint spraying, pre-baking and main baking, the preparation work of the object is continuously carried out before baking under the action of the transmission chain and the hanging tool, the surface of the object is ensured to obtain a better coating to realize uniform spraying, and the baking effect is paved.
2. The structure production line is provided with two baking steps, firstly, the object is pre-baked to enable the solvent to be partially evaporated, the wet paint film is leveled, and then the main baking operation is carried out to enable the surface to be forcibly dried, and the baking effect is good due to the two baking processes.
Drawings
FIG. 1 is a front view of a gas-fired topcoat baking line;
FIG. 2 is a schematic view of a water curtain chamber structure of a gas-fired finish baking line;
FIG. 3 is a schematic view of a drying chamber structure of a gas-fired finish baking assembly line;
FIG. 4 is a schematic view of a dust blowing chamber of a gas-fired finish baking line;
FIG. 5 is a schematic view of a pre-baking chamber of a gas-fired topcoat baking line;
FIG. 6 is a schematic view of a main baking chamber structure of a gas-fired finish baking assembly line.
Illustration of the drawings:
1. a conveying chain; 2. a hanger; 3. a water curtain chamber; 4. a drying chamber; 5. a dust blowing chamber; 6. a paint spray booth; 7. a pre-baking chamber; 8. a main baking chamber; 9. a shunt tube; 10. spraying a head; 11. a water pump; 12. an electric heating drying tube; 13. a slide bar; 14. a slider; 15. an electrostatic precipitation gun head; 16. electrically heating the baking tube; 17. a gas distributing pipe; 18. a gas baking nozzle; 19. a gas tank.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
In the description of the present invention, it should be noted that the terms "center", "upper", "lower", "left", "right", "vertical", "horizontal", "inner", "outer", etc., indicate orientations or positional relationships based on the orientations or positional relationships shown in the drawings, and are only for convenience of description and simplicity of description, but do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be construed as limiting the present invention; the terms "first," "second," and "third" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance, and furthermore, unless otherwise explicitly stated or limited, the terms "mounted," "connected," and "connected" are to be construed broadly and may be, for example, fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood in specific cases to those skilled in the art.
Referring to fig. 1-6, one embodiment of the present invention is provided: a gas type finish paint baking assembly line comprises a water curtain chamber 3 for providing water washing operation, a water pump 11 is fixedly arranged on one side of the outside of the water curtain chamber 3 for providing water supply braking, a drying chamber 4 is arranged on one side of the water curtain chamber 3 for realizing object surface drying operation, an electric heating drying pipe 12 is fixedly arranged on one side of the inside of the drying chamber 4, a dust blowing chamber 5 is arranged on one side of the drying chamber 4, which is far away from the water curtain chamber 3, for providing object dust blowing space, an electrostatic dust removal gun head 15 is slidably arranged on one side of the inside of the dust blowing chamber 5 for realizing dust blowing operation, a paint spraying chamber 6 is arranged on one side of the dust blowing chamber 5, for spraying paint on the objects, a pre-baking chamber 7 is arranged on one side of the paint spraying chamber 6, an electric heating baking pipe 16 is fixedly arranged on one side of the inside of the pre-baking chamber 7, a main baking chamber 8 is arranged on one side of the pre-baking chamber 7, which is far, carry out the high temperature to the article and toast the operation, the fixed gas jar 19 that is provided with in surface one side of mainly toasting room 8 provides the gas and toasts the operation, and the inboard upper portion of cascade room 3 runs through and is provided with conveying chain 1, and conveying chain 1 from left to right passes cascade room 3, drying chamber 4, dust blowing room 5, paint spray booth 6, pre-toasting room 7 and mainly toasts room 8 in proper order, realizes the form of assembly line.
The middle position of the lower surface of the conveying chain 1 is fixedly provided with a hanging tool 2 which provides an object hanging position, the hanging tool 2 is equidistantly provided with a plurality of shower heads 10 along the moving direction of the conveying chain 1 to increase the work efficiency of the assembly line, the upper side inside the water curtain chamber 3 is fixedly provided with a shunt pipe 9, the shunt pipe 9 is relatively positioned above the conveying chain 1, the lower surface of the pipe body of the shunt pipe 9 is equidistantly provided with a plurality of shower heads 10 to realize the shower operation, one end of the shunt pipe 9 is fixedly connected with a water pipe which is fixedly connected on a water pump 11, an electrothermal drying pipe 12 is fixedly arranged on the inner side wall of the drying chamber 4, the electrothermal drying pipe 12 is vertically arranged, two electrothermal drying pipes 12 are arranged on two sides inside the drying chamber 4 to realize the integral drying operation, the two electrothermal drying pipes 12 are relatively positioned on two sides of the conveying chain 1, the inner side wall of the dust blowing chamber 5, slide 14's side surface middle part fixed connection electrostatic precipitator rifle head 15, realize that the rifle head reciprocates the dust removal operation, and blow the inside both sides wall structure of dirt room 5 the same, the electric heat is toasted pipe 16 and is being provided with threely in the inside downside and the left and right sides of stoving room 7 in advance, and each electric heat toasts pipe 16 contactless each other, guarantee low temperature and toast efficiency and structural feasibility, the fixed gas distribution pipe 17 that is provided with of inside wall of main chamber 8 of toasting, gas distribution pipe 17's pipe shaft surface equidistance is provided with a plurality of gas and toasts shower nozzle 18, and gas distribution pipe 17 one end fixed connection is on gas jar 19, realize the gas supply.
The working principle is as follows: when the paint spraying and baking line production of the object is carried out, the object is firstly hung on the hanging tool 2 on the lower surface of the conveying chain 1, the line production is realized through the action of the conveying chain 1, firstly, the dynamic water washing operation of the object is realized through the action of the shower head 10, then, the drying treatment of the object is realized through the electric heating drying tube 12 through the drying chamber 4, then, the dust is removed through the electrostatic dust removal gun head 15 in the dust blowing chamber 5, the object is conveyed to the paint spraying chamber 6 for paint spraying, after the paint spraying is finished, the object is moved to the inside of the pre-baking chamber 7 for low-temperature baking through the action of the electric heating baking tube 16, partial liquid is evaporated, and finally, the object is moved to the inside of the main baking chamber 8 for realizing high-temperature baking operation through the action of the gas tank 19, so as to achieve the purpose of baking line.
Finally, it should be noted that: although the present invention has been described in detail with reference to the foregoing embodiments, it will be apparent to those skilled in the art that modifications may be made to the embodiments or portions thereof without departing from the spirit and scope of the invention.
Claims (7)
1. The utility model provides a gas formula finish paint toasts assembly line, includes cascade room (3), its characterized in that: a water pump (11) is fixedly arranged on one side of the outside of the water curtain chamber (3), a drying chamber (4) is arranged on one side of the water curtain chamber (3), an electric heating drying pipe (12) is fixedly arranged on one side of the inside of the drying chamber (4), a dust blowing chamber (5) is arranged on one side of the drying chamber (4) departing from the water curtain chamber (3), an electrostatic dust removal gun head (15) is slidably arranged on one side of the inside of the dust blowing chamber (5), a paint spraying chamber (6) is arranged on one side of the dust blowing chamber (5) departing from the drying chamber (4), a pre-baking chamber (7) is arranged on one side of the paint spraying chamber (6) departing from the dust blowing chamber (5), an electric heating baking pipe (16) is fixedly arranged on one side of the inside of the pre-baking chamber (7), a main baking chamber (8) is arranged on one side of the pre-baking chamber (7) departing from the paint spraying chamber (6), a gas tank (19) is fixedly arranged on, the inner side upper portion of the water curtain chamber (3) is provided with a conveying chain (1) in a penetrating mode, and the conveying chain (1) sequentially penetrates through the water curtain chamber (3), the drying chamber (4), the dust blowing chamber (5), the paint spraying chamber (6), the pre-baking chamber (7) and the main baking chamber (8) from left to right.
2. The gas-fired finish paint baking production line as claimed in claim 1, characterized in that: the lower surface middle part rigidity of carrying chain (1) is provided with hanger (2), hanger (2) are provided with a plurality ofly along the trend equidistance of carrying chain (1).
3. The gas-fired finish paint baking production line as claimed in claim 1, characterized in that: the fixed shunt tubes (9) that are provided with of inside upside of cascade room (3), and shunt tubes (9) are located the top of carrying chain (1) relatively, the pipe shaft lower surface equidistance of shunt tubes (9) is provided with a plurality of heads (10) that drench, the one end fixedly connected with water pipe of shunt tubes (9), and water pipe fixed connection is on water pump (11).
4. The gas-fired finish paint baking production line as claimed in claim 1, characterized in that: the electric heating drying tubes (12) are fixedly arranged on the inner side wall of the drying chamber (4), the electric heating drying tubes (12) are vertically arranged, two electric heating drying tubes (12) are arranged on two sides of the inside of the drying chamber (4), and the two electric heating drying tubes (12) are oppositely located on two sides of the conveying chain (1).
5. The gas-fired finish paint baking production line as claimed in claim 1, characterized in that: the dust blowing chamber is characterized in that a sliding strip (13) is fixedly arranged on the inner side wall of the dust blowing chamber (5), a sliding block (14) is connected to the inside of the sliding strip (13) in a sliding mode, the middle of the side surface of the sliding block (14) is fixedly connected with an electrostatic dust removal gun head (15), and the structures of the two side walls in the dust blowing chamber (5) are the same.
6. The gas-fired finish paint baking production line as claimed in claim 1, characterized in that: the lower side and the left side and the right side of the interior of the pre-baking chamber (7) are fixedly provided with three electric baking tubes (16), and the electric baking tubes (16) are not contacted with each other.
7. The gas-fired finish paint baking production line as claimed in claim 1, characterized in that: the inside wall of main baking chamber (8) is fixed and is provided with gas-distributing pipe (17), the pipe shaft surface equidistance of gas-distributing pipe (17) is provided with a plurality of gas and toasts shower nozzle (18), and gas-distributing pipe (17) one end fixed connection is on gas jar (19).
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911390403.0A CN111151405A (en) | 2019-12-30 | 2019-12-30 | Gas type finish paint baking assembly line |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911390403.0A CN111151405A (en) | 2019-12-30 | 2019-12-30 | Gas type finish paint baking assembly line |
Publications (1)
Publication Number | Publication Date |
---|---|
CN111151405A true CN111151405A (en) | 2020-05-15 |
Family
ID=70559323
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911390403.0A Pending CN111151405A (en) | 2019-12-30 | 2019-12-30 | Gas type finish paint baking assembly line |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN111151405A (en) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113102198A (en) * | 2021-03-12 | 2021-07-13 | 中国联合工程有限公司 | Combined drying system for finish paint and color register process of vehicle parts |
Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201572727U (en) * | 2009-12-30 | 2010-09-08 | 林文渊 | Automatic spray coating system |
CN102463212A (en) * | 2010-11-04 | 2012-05-23 | 江苏麟龙新材料股份有限公司 | Coating-processing process for marine-climate resisting engineering-part surface coating |
CA2870682A1 (en) * | 2013-11-08 | 2015-05-08 | Vln Advanced Technologies Inc. | Integrated fluidjet system for stripping, prepping and coating a part |
CN206464141U (en) * | 2016-12-20 | 2017-09-05 | 靖江市达克罗涂覆工业有限公司 | Low-cost and high-performance automatic spraying line |
CN107138335A (en) * | 2017-03-29 | 2017-09-08 | 山东卫禾传动科技有限公司 | A kind of agricultural equipment gearbox paint line and its coating process |
CN107199168A (en) * | 2017-05-23 | 2017-09-26 | 安徽忠盛新型装饰材料有限公司 | A kind of handware baking finish process method |
CN107755163A (en) * | 2017-11-06 | 2018-03-06 | 楼娟 | A kind of efficient steel plate paint-spraying device |
CN109967297A (en) * | 2017-12-27 | 2019-07-05 | 震旦(中国)有限公司 | A kind of Furniture panel Full-automatic paint spraying production line |
-
2019
- 2019-12-30 CN CN201911390403.0A patent/CN111151405A/en active Pending
Patent Citations (8)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN201572727U (en) * | 2009-12-30 | 2010-09-08 | 林文渊 | Automatic spray coating system |
CN102463212A (en) * | 2010-11-04 | 2012-05-23 | 江苏麟龙新材料股份有限公司 | Coating-processing process for marine-climate resisting engineering-part surface coating |
CA2870682A1 (en) * | 2013-11-08 | 2015-05-08 | Vln Advanced Technologies Inc. | Integrated fluidjet system for stripping, prepping and coating a part |
CN206464141U (en) * | 2016-12-20 | 2017-09-05 | 靖江市达克罗涂覆工业有限公司 | Low-cost and high-performance automatic spraying line |
CN107138335A (en) * | 2017-03-29 | 2017-09-08 | 山东卫禾传动科技有限公司 | A kind of agricultural equipment gearbox paint line and its coating process |
CN107199168A (en) * | 2017-05-23 | 2017-09-26 | 安徽忠盛新型装饰材料有限公司 | A kind of handware baking finish process method |
CN107755163A (en) * | 2017-11-06 | 2018-03-06 | 楼娟 | A kind of efficient steel plate paint-spraying device |
CN109967297A (en) * | 2017-12-27 | 2019-07-05 | 震旦(中国)有限公司 | A kind of Furniture panel Full-automatic paint spraying production line |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113102198A (en) * | 2021-03-12 | 2021-07-13 | 中国联合工程有限公司 | Combined drying system for finish paint and color register process of vehicle parts |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN204583572U (en) | A kind of shaped steel automatic spraying production line | |
CN107414649B (en) | A kind of metal tube rust-cleaning integrating machine | |
CN111151405A (en) | Gas type finish paint baking assembly line | |
CN205667921U (en) | Multi-angle paint spraying line | |
CN112079574A (en) | Wear-resistant scratch-resistant glass product and preparation process thereof | |
CN209531220U (en) | A kind of auto spray painting device | |
CN109339413A (en) | A kind of Intelligent indoor mechanical float with full-automatic work performance | |
CN104324870A (en) | Painting method of hangers | |
CN203578089U (en) | Electrostatic spraying device for clothes rack | |
CN108355874B (en) | Wooden workpiece powder coating device, Powder Coating System and powder coating process | |
CN207170156U (en) | A kind of drying substrates spray equipment for aluminium base production | |
CN208407462U (en) | A kind of Furniture manufacturing automatic coating system | |
CN210855839U (en) | Device is paintd with fire retardant coating to glass processing | |
CN205761998U (en) | A kind of paint spray booth | |
CN211134421U (en) | Pipe paint spraying and drying device for appliance processing | |
CN209534500U (en) | A kind of spray code spraying apparatus of mineral water processing | |
CN210024960U (en) | Pipe wall anticorrosive coating device of electric heater heating through pipe | |
CN109261417A (en) | A kind of television set front casing spray-painting plant | |
CN220879357U (en) | Paint spraying device convenient to use | |
CN211160325U (en) | Baking finish box for zipper processing | |
CN111570155A (en) | Automatic powder spraying device with high spraying efficiency | |
CN214864769U (en) | Spraying device is used in sheet metal component production | |
CN211488262U (en) | Furniture surface machining coating machine with air drying function | |
CN209735903U (en) | Plasma AF spraying device is used in cell-phone panel production | |
CN112776145A (en) | Automatic glaze spraying device for ceramic production |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200515 |
|