CN111140001A - Mortar plastering construction method for stand column - Google Patents

Mortar plastering construction method for stand column Download PDF

Info

Publication number
CN111140001A
CN111140001A CN202010058332.0A CN202010058332A CN111140001A CN 111140001 A CN111140001 A CN 111140001A CN 202010058332 A CN202010058332 A CN 202010058332A CN 111140001 A CN111140001 A CN 111140001A
Authority
CN
China
Prior art keywords
mortar
upright post
frame body
fossil fragments
keel
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN202010058332.0A
Other languages
Chinese (zh)
Other versions
CN111140001B (en
Inventor
卢忆灵
骆宇阳
张芳
王鹰
王斌
程超锋
马炜杰
周桂萍
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Lvjing Environmental Engineering Co Ltd
Original Assignee
Zhejiang Lvjing Environmental Engineering Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Lvjing Environmental Engineering Co Ltd filed Critical Zhejiang Lvjing Environmental Engineering Co Ltd
Priority to CN202010058332.0A priority Critical patent/CN111140001B/en
Publication of CN111140001A publication Critical patent/CN111140001A/en
Application granted granted Critical
Publication of CN111140001B publication Critical patent/CN111140001B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04FFINISHING WORK ON BUILDINGS, e.g. STAIRS, FLOORS
    • E04F21/00Implements for finishing work on buildings
    • E04F21/02Implements for finishing work on buildings for applying plasticised masses to surfaces, e.g. plastering walls
    • E04F21/06Implements for applying plaster, insulating material, or the like
    • E04F21/08Mechanical implements

Abstract

The invention relates to a mortar plastering construction method of a stand column, which comprises the following steps: s1, building a frame body; the support body includes annular fossil fragments and stull fossil fragments, and annular fossil fragments cup joint in the stand outside. The stull fossil fragments are located four girders in stand top respectively under, and the stull fossil fragments are fixed in annular fossil fragments and are on a parallel with the girder that corresponds. S2, installing a hoisting device; a lifting point is determined on each main beam, a hanging rod is driven into the lifting point, and a hanging ring is fixed at the bottom of the hanging rod. And a winch is arranged under each of the four main beams, and a rope of the winch passes through the corresponding lifting ring and is bound on the corresponding cross-brace keel. S3, coating mortar; and a rubber sheet is glued on the inner ring of the annular keel and is arranged annularly. And coating mortar on the outer surface of the upright column, wherein the thickness of the mortar exceeds the gap between the rubber sheet and the outer wall of the upright column. S4, leveling the mortar; and starting the winch to drive the frame body to move up and down to level the mortar. The invention improves the effect of upright column mortar plastering quality.

Description

Mortar plastering construction method for stand column
Technical Field
The invention relates to the technical field of mortar plastering construction, in particular to a mortar plastering construction method of an upright post.
Background
The cross-section of the post is generally square in order to facilitate structural reinforcement and already save material. And because the flow of people is big in the hospital, when people or article hit the surface of stand, the edges and corners of the stand of square cross section easily cause the damage to human body or article, so circular cross section stand is in large numbers in the hospital. The construction steps of the circular upright post are generally binding a reinforcement cage, pouring concrete, plastering mortar and installing a veneer.
The existing mortar plastering construction method comprises the following steps: s1, coating mortar on the surface of the upright post by using a scraper knife; s2, trowelling the mortar to form a first troweling surface layer; and S3, before the first plastering layer is solidified, quickly scraping and coating the mortar on the surface of the first plastering layer by using a scraper knife, and forming a second plastering layer after trowelling. When the requirement on the uniformity of mortar on the surface of the upright post is higher, the construction of a third or even a fourth plastering layer is needed.
The above prior art solutions have the following drawbacks: because the mortar plastering thickness of the column with the circular section is difficult to measure, at least two mortar plastering steps are usually required to be carried out in order to improve the uniformity of mortar on the surface of the column. After at least two mortar plastering processes, the thickness of the column mortar is only nearly uniform. And when the section of the upright column is large, a plurality of constructors are needed to cooperate to finish mortar plastering, and the plastering of all the channels can be finished before mortar is solidified. The method needs old constructors with a lot of experience to carry out, and the construction quality cannot be guaranteed.
It is desirable to provide a mortar plastering construction method of a column, which can improve the uniformity of mortar plastering.
Disclosure of Invention
In view of the defects in the prior art, one of the purposes of the present invention is to provide a mortar plastering construction method for a column, which has the effect of improving the uniformity of mortar plastering.
The above object of the present invention is achieved by the following technical solutions:
a mortar plastering construction method of a stand column comprises the following steps:
s1, building a frame body;
building a frame body on the periphery of the upright post, wherein the frame body comprises an annular keel and a cross-brace keel; the annular keel is sleeved outside the upright post, and the perimeter of the inner ring of the annular keel is larger than that of the outer wall of the upright post; the cross-brace keels are fixed on the annular keels and are respectively positioned under the four main beams at the tops of the upright posts, and the cross-brace keels are parallel to the corresponding main beams;
s2, installing a hoisting device;
lofting the lower surfaces of the four main beams, and determining a lifting point on each main beam, wherein the vertical distances between the four lifting points and the axis of the upright post are the same; a hanging rod is driven into a lifting point, and a hanging ring is fixed at the bottom of the hanging rod; a winch is installed under each of the four main beams, and a rope of the winch penetrates through the corresponding lifting ring and is bound on the corresponding cross-brace keel;
s3, coating mortar;
gluing a rubber sheet on the inner ring of the annular keel, wherein the rubber sheet is annularly arranged, and the gap between one side of the rubber sheet facing the stand column and the outer wall of the stand column is consistent with the thickness required by mortar plastering; coating mortar on the outer surface of the upright column, wherein the thickness of the mortar exceeds the gap between the rubber sheet and the outer wall of the upright column;
s4, leveling the mortar;
and starting the winch to drive the frame body to move up and down, and leveling the mortar by the rubber sheets.
By adopting the technical scheme, the telescopic frame body is positioned at four points, so that the frame body cannot move along the horizontal direction, and the gap between the rubber sheet and the surface of the upright post is always kept unchanged. Utilize hoist engine drive support body up and down motion to make the rubber piece on the annular fossil fragments to floating the mortar on stand surface, guaranteed that the thickness of mortar can keep unanimous everywhere, improved the homogeneity of mortar plastering, improved construction quality. Meanwhile, due to mechanical operation, a plurality of constructors are prevented from conducting construction at the same time, and therefore manual loss is reduced.
Wherein, because the stand that the cross-section is circular can not regard as the side post usually, so each cross-section is four girders for circular stand top all is connected with.
The present invention in a preferred example may be further configured to: in S1' S the construction support body, the support body still includes the reinforcement fossil fragments, and the reinforcement fossil fragments are fixed between adjacent stull fossil fragments, and each reinforcement fossil fragments and the tie point between the corresponding stull fossil fragments to the interval between the stand outer wall the same.
Through adopting above-mentioned technical scheme, improve structural integrity and structural strength between the stull fossil fragments, make annular fossil fragments, stull fossil fragments and consolidate the whole of fossil fragments formation symmetry simultaneously for the whole atress of support body is more even, makes the holding capacity of support body stronger.
The present invention in a preferred example may be further configured to: in the erection hoisting of S2, a rope is tied at the connecting position of the wale keel and the reinforcement keel.
Through adopting above-mentioned technical scheme for tie point intensity between rope and the stull fossil fragments is higher, has reduced the injury of rope to the stull fossil fragments.
The present invention in a preferred example may be further configured to: in the installation and hoisting device of S2, before the hanger rod is installed, lofting is carried out on the outer wall of the upright post according to the design drawing of the suspended ceiling, and the bottom side line of the suspended ceiling is marked on the outer wall of the upright post; after the hanger rod and the hanging ring are installed, the bottom of the hanging ring is positioned above the side line of the bottom of the suspended ceiling; and when the support body moves to the highest position, the bottom of the support body is positioned above the side line of the bottom of the suspended ceiling.
Through adopting above-mentioned technical scheme for the stand outer wall of furred ceiling below can both paint the mortar, thereby guarantees the continuity of follow-up construction, has reduced constructor's time and the manpower of filling the mortar.
The present invention in a preferred example may be further configured to: in the blade coating mortar of S3, the thickness of the rubber sheet on the side facing the pillar gradually decreases in the direction approaching the pillar.
By adopting the technical scheme, the mortar is convenient to trowel, and the surface flatness of the mortar is improved.
The present invention in a preferred example may be further configured to: in the coating mortar of S3, at least three measuring points along the circumferential direction are selected on the upright post, the vertical distance between the measuring points and one side of the rubber sheet facing the upright post is measured, and the position of the frame body is adjusted until the absolute value of the difference between any two of the distance data measured by all the measuring points is not more than 1 mm.
Through adopting above-mentioned technical scheme for annular fossil fragments and stand can approach to coaxially, thereby when improving the floating mortar in later stage, the mortar homogeneity on the stand outer wall.
The present invention in a preferred example may be further configured to: in the floating mortar of S4, starting a winch to enable four ropes to be in a tight state at the same time, and enabling the frame body to be still positioned on the upper surface of the floor slab at the bottom of the upright post; and then, synchronously starting the four windlasses to drive the frame body to move upwards to trowel the mortar.
Through adopting above-mentioned technical scheme, the rope of four hoists is the same between rings and support body for when hoist engine drive support body up-and-down motion, the support body can not move along the horizontal direction, has further improved the homogeneity of mortar on the stand outer wall.
The present invention in a preferred example may be further configured to: in the plastering mortar of S4, when the frame body moves to the upper part of the upright post, the periphery of the bottom of the upright post is paved with waterproof cloth; when the frame body moves downwards to smear the mortar, the redundant mortar falls onto the waterproof cloth to be collected.
Through adopting above-mentioned technical scheme, when the downward motion of sheet rubber was smeared the mortar on the stand outer wall at ordinary times, unnecessary mortar dropped on the tarpaulin, can carry out cyclic utilization, has avoided the direct and floor contact of mortar simultaneously, can keep the planarization on floor surface.
The present invention in a preferred example may be further configured to: also comprises S5, the shelf body is reused; lofting is carried out on a floor slab at the top of the upright post, the arrangement position of the suspended ceiling suspender is determined, and the suspended ceiling suspender is driven into the floor slab; and starting the winch to enable the support body to move upwards to reach the bottom side line of the suspended ceiling, and fixing the suspended ceiling suspension rod and the support body.
Through adopting above-mentioned technical scheme, accomplish the floating back to the mortar when the support body, rise the support body to furred ceiling bottom sideline, carry out the installation of furred ceiling plate body as the frame of furred ceiling to avoid demolising of support body, also can accelerate the installation effectiveness of later stage furred ceiling. Simultaneously, the mortar of sheet rubber and annular fossil fragments upper surface can solidify for be connected between annular fossil fragments and the stand.
In summary, the invention includes at least one of the following beneficial technical effects:
1. the frame body is arranged outside the upright post, and the lifting device is arranged on the frame body, so that the frame body can move up and down along the upright post, mortar on the surface of the upright post is leveled, the uniformity of the mortar on the surface of the upright post is improved, and the construction efficiency can be accelerated;
2. the frame body is used as a frame for installing the later-stage suspended ceiling, so that the construction efficiency of the suspended ceiling is improved, and the dismantling of the frame body is avoided.
Drawings
FIG. 1 is a schematic view of the overall structure;
FIG. 2 is a cross-sectional view A-A of FIG. 1;
FIG. 3 is a cross-sectional view B-B of FIG. 2;
fig. 4 is a cross-sectional view of fig. 2 taken along line C-C.
In the figure, 1, a frame body; 11. an annular keel; 111. inserting grooves; 112. an L-shaped metal connector; 12. a cross-brace keel; 13. reinforcing the keel; 2. a main beam; 21. a boom; 211. a hoisting ring; 3. a winch; 31. a rope; 4. a rubber sheet; 5. and (4) a column.
Detailed Description
The present invention will be described in further detail with reference to the accompanying drawings.
Referring to fig. 1, the mortar plastering construction method for the upright column disclosed by the invention comprises the following steps:
s1, building a frame body 1;
with reference to fig. 1 and 2, a frame body 1 is built on the periphery of the upright post 5, and the frame body 1 comprises an annular keel 11, eight cross-brace keels 12 and eight reinforcing keels 13. The annular keel 11 is formed by splicing two semi-annular units, and the joint position of the two units is fixed through bolts or welding. The two units are sleeved on the periphery of the upright post 5 and fixed to form a whole. The distance between the inner ring forming the integral hair-ring-shaped keel 11 and the outer wall of the upright post 5 is 2cm-5 cm. Four insertion grooves 111 (see fig. 3) for positioning the cross-brace keels 12 are uniformly formed in the bottom of each unit, and the ends of the cross-brace keels 12 are inserted into the corresponding insertion grooves 111, so that the cross-brace keels 12 are perpendicular to the tangent line of the positions of the insertion grooves 111 corresponding to the annular keels 11. And the wale keel 12 and the ring keel 11 are fixed by using an L-shaped metal connector 112 and bolts.
Next, eight reinforcing keels 13 are placed above each adjacent two of the wale keels 12 so that the eight reinforcing keels 13 form a regular octagon, and the ends of the reinforcing keels 13 and the upper surfaces of the wale keels 12 are welded.
S2, installing a hoisting device;
lofting the lower surfaces of the four main beams 2 at the top of the upright post 5 to determine four lifting points, wherein the distance between each lifting point and the axle center of the upright post 5 is equal. And (5) lofting the surface of the upright post according to the design drawing of the suspended ceiling, and marking the bottom side line of the suspended ceiling on the outer wall of the upright post 5.
The hanging rods 21 are driven into the lifting point positions, the plumb bob is used for correcting the verticality of the hanging rods 21, and meanwhile the bottoms of the four hanging rods 21 are located on the same horizontal plane. Fixed welding rings 211 in the bottom of jib 21, rings 211's bottom is located furred ceiling bottom sideline top for the bottom of support body 1 can move the top of furred ceiling bottom sideline.
Four winches 3 are arranged on the floor corresponding to the bottom of the upright post 5, and the four winches 3 are respectively positioned under the four main beams 2. The vertical distances between the four winches 3 and the axes of the upright 5 are equal, and the hoisting ring 211 is positioned between the upright 5 and the winches 3. The end of the rope 31 on the hoisting machine 3 is pulled so that the end of the rope 31 passes through the hoisting ring 211 from the side of the hoisting ring 211 away from the upright 5.
The frame body 1 is rotated, so that the four cross-brace keels 12 are positioned under the four main beams 2, and the end parts of the ropes 31 are bound at the joints of the four cross-brace keels 12 and the corresponding reinforcing keels 13.
S3, coating mortar;
with reference to fig. 2 and 4, two semicircular rubber sheets 4 are placed on the inner ring of the annular keel 11, the edge of the rubber sheet 4 and the inner ring of the annular keel 11 are adhered by glue, and the end parts of the two semicircular rubber sheets 4 are adhered by glue, so that the two semicircular rubber sheets 4 form a whole. The vertical cross section of the rubber sheet 4 is in an isosceles trapezoid shape towards one end of the stand column 5, a gap of 2mm-5mm exists between one side of the rubber sheet 4 towards the stand column 5 and the outer wall of the stand column 5, and the mortar thickness is specifically determined according to the mortar thickness required by design on the stand column 5. In order to ensure that the gap between the outer wall of the upright post 5 and the rubber sheet 4 is uniform, six measuring points along the circumferential direction are selected on the upright post 5, and the measuring points are uniformly arranged on the upright post 5. And (3) measuring the vertical distance between the measuring points and one side of the rubber sheet 4 facing the upright post 5, and adjusting the position of the frame body 1 until the absolute value of the difference between any two of the measured distance data of all the measuring points is not more than 1 mm.
And coating mortar on the outer surface of the upright post 5, wherein the thickness of the mortar exceeds the gap between the rubber sheet 4 and the outer wall of the upright post 5.
S4, leveling the mortar;
with reference to fig. 1 and 2, the hoist 3 is started so that the four ropes 31 are simultaneously in a tight state while the frame 1 is still on the upper surface of the floor on which the bottom of the column 5 is located. And then, synchronously starting the four windlasses 3 to drive the frame body 1 to move upwards, and leveling the mortar on the outer wall of the upright post 5 by the rubber sheet 4. Excess mortar accumulates on the upper surfaces of the rubber sheet 4 and the ring runner 11. When the frame body 1 rises to the side line of the bottom of the ceiling lamp, waterproof cloth (not shown in the figure) is paved on the periphery of the bottom of the upright post 5. And starting the winch 3 to enable the frame body 1 to move downwards, trowelling the mortar on the surface of the stand column 5 again, and enabling the redundant mortar to fall onto the waterproof cloth. The frame body 1 is made to reciprocate up and down according to the mode until no redundant mortar falls on the waterproof cloth.
S5, recycling the rack body 1;
collecting the mortar on the waterproof cloth at the bottom of the upright post 5 and removing the waterproof cloth.
A layout is made on the floor at the top of the columns 5, the position of the ceiling hanger bar (not shown) is determined, and the ceiling hanger bar is driven into the floor. Start hoist engine 3 and make support body 1 upward movement reach furred ceiling bottom sideline, fix furred ceiling jib and support body 1 for support body 1 is as the structural framework of furred ceiling, thereby improves the efficiency of later stage furred ceiling construction.
The embodiments of the present invention are preferred embodiments of the present invention, and the scope of the present invention is not limited by these embodiments, so: all equivalent changes made according to the structure, shape and principle of the invention are covered by the protection scope of the invention.

Claims (9)

1. A mortar plastering construction method of a stand column is characterized in that: the method comprises the following steps:
s1, building a frame body (1);
a frame body (1) is built on the periphery of the upright post (5), and the frame body (1) comprises an annular keel (11) and a cross-bracing keel (12); the annular keel (11) is sleeved outside the upright post (5), and the circumference of the inner ring of the annular keel (11) is larger than that of the outer wall of the upright post (5); the cross-brace keels (12) are fixed on the annular keels (11), the cross-brace keels (12) are respectively positioned under the four main beams (2) at the tops of the upright columns (5), and the cross-brace keels (12) are parallel to the corresponding main beams (2);
s2, installing a hoisting device;
lofting the lower surfaces of the four main beams (2), determining a lifting point on each main beam (2), wherein the vertical distances between the four lifting points and the axis of the upright post (5) are the same; a hanging rod (21) is driven into a lifting point position, and a hanging ring (211) is fixed at the bottom of the hanging rod (21); a winch (3) is arranged under each of the four main beams (2), and a rope (31) of the winch (3) penetrates through the corresponding lifting ring (211) and is bound on the corresponding cross-brace keel (12);
s3, coating mortar;
gluing a rubber sheet (4) on an inner ring of the annular keel (11), wherein the rubber sheet (4) is arranged annularly, and a gap between one side of the rubber sheet (4) facing the upright post (5) and the outer wall of the upright post (5) is consistent with the thickness required by mortar plastering; mortar is smeared on the outer surface of the upright post (5), and the thickness of the mortar exceeds the gap between the rubber sheet (4) and the outer wall of the upright post (5);
s4, leveling the mortar;
the winch (3) is started to drive the frame body (1) to move up and down, and the rubber sheet (4) screeds the mortar.
2. The mortar plastering construction method of a column according to claim 1, wherein: in S1' S the construction support body (1), support body (1) still includes and consolidates fossil fragments (13), consolidates fossil fragments (13) and fixes between adjacent stull fossil fragments (12), and each consolidates the tie point between fossil fragments (13) and the corresponding stull fossil fragments (12) and to the interval between stand (5) outer wall the same.
3. The mortar plastering construction method of a column according to claim 2, wherein: in the installation and hoisting device of S2, a rope (31) is bound at the connecting position of the cross-brace keel (12) and the reinforcing keel (13).
4. The mortar plastering construction method of a column according to claim 1, wherein: in the installation and hoisting device of S2, before the hanger rod (21) is installed, lofting is carried out on the outer wall of the upright post (5) according to the design drawing of the suspended ceiling, and the bottom side line of the suspended ceiling is marked on the outer wall of the upright post (5); after the hanger rod (21) and the hanging ring (211) are installed, the bottom of the hanging ring (211) is positioned above the side line of the bottom of the suspended ceiling; and when the frame body (1) moves to the highest position, the bottom of the frame body (1) is positioned above the side line of the bottom of the suspended ceiling.
5. The mortar plastering construction method of a column according to claim 1, wherein: in the blade coating mortar of S3, the thickness of the rubber sheet (4) on the side facing the pillar (5) is gradually reduced in the direction approaching the pillar (5).
6. The mortar plastering method of a column according to claim 1 or 5, wherein: in the S3 blade coating mortar, at least three measuring points along the circumferential direction are selected on the upright post (5), the vertical distance between the measuring points and one side of the rubber sheet (4) facing the upright post (5) is measured, and the position of the frame body (1) is adjusted until the absolute value of the difference between any two of the distance data measured by all the measuring points is not more than 1 mm.
7. The mortar plastering construction method of a column according to claim 1, wherein: in the floating mortar of S4, firstly, starting the winch (3) to enable the four ropes (31) to be in a tight state at the same time, and the frame body (1) is still positioned on the upper surface of the floor where the bottom of the upright post (5) is positioned; and then, synchronously starting the four windlasses (3) to drive the frame body (1) to move upwards to trowel the mortar.
8. The mortar plastering construction method of a column according to claim 7, wherein: in the plastering mortar of S4, when the frame body (1) moves to the upper part of the upright post (5), the periphery of the bottom of the upright post (5) is paved with waterproof cloth; when the frame body (1) moves downwards to smear mortar, redundant mortar falls onto the waterproof cloth to be collected.
9. The mortar plastering construction method of a column according to claim 1, wherein: also comprises S5, the shelf body (1) is reused; lofting is carried out on a floor slab at the top of the upright post (5), the arrangement position of the suspended ceiling suspender (21) is determined, and the suspended ceiling suspender (21) is driven into the floor slab; the winch (3) is started to enable the frame body (1) to move upwards to reach the bottom side line of the suspended ceiling, and the suspended ceiling suspension rod (21) and the frame body (1) are fixed.
CN202010058332.0A 2020-01-18 2020-01-18 Mortar plastering construction method for stand column Active CN111140001B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN202010058332.0A CN111140001B (en) 2020-01-18 2020-01-18 Mortar plastering construction method for stand column

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN202010058332.0A CN111140001B (en) 2020-01-18 2020-01-18 Mortar plastering construction method for stand column

Publications (2)

Publication Number Publication Date
CN111140001A true CN111140001A (en) 2020-05-12
CN111140001B CN111140001B (en) 2021-05-28

Family

ID=70526095

Family Applications (1)

Application Number Title Priority Date Filing Date
CN202010058332.0A Active CN111140001B (en) 2020-01-18 2020-01-18 Mortar plastering construction method for stand column

Country Status (1)

Country Link
CN (1) CN111140001B (en)

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010179231A (en) * 2009-02-05 2010-08-19 Yasuhiro Fujita Openable ring shaped 360-degree coating method and device
CN201794274U (en) * 2010-03-03 2011-04-13 黄效红 Pillar plastering machine support
CN104514360A (en) * 2013-10-08 2015-04-15 天太·郭元焜 Automatic machine for plastering cylinder with cement mortar
CN104863342A (en) * 2015-05-29 2015-08-26 武汉建工集团股份有限公司 Cylinder plastering device and method
CN107620449A (en) * 2017-08-28 2018-01-23 中建八局第三建设有限公司 A kind of face of cylinder annular floating screed instrument and face of cylinder plastering method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2010179231A (en) * 2009-02-05 2010-08-19 Yasuhiro Fujita Openable ring shaped 360-degree coating method and device
CN201794274U (en) * 2010-03-03 2011-04-13 黄效红 Pillar plastering machine support
CN104514360A (en) * 2013-10-08 2015-04-15 天太·郭元焜 Automatic machine for plastering cylinder with cement mortar
CN104863342A (en) * 2015-05-29 2015-08-26 武汉建工集团股份有限公司 Cylinder plastering device and method
CN107620449A (en) * 2017-08-28 2018-01-23 中建八局第三建设有限公司 A kind of face of cylinder annular floating screed instrument and face of cylinder plastering method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
雷立等: "圆柱面环向抹灰及氟碳漆饰面施工技术 ", 《天津建设科技》 *

Also Published As

Publication number Publication date
CN111140001B (en) 2021-05-28

Similar Documents

Publication Publication Date Title
CN107338727B (en) Integrally-disassembled and assembled anti-collision wall template and walking type rail hanging and moving system thereof
CN106894639B (en) The hanging reverse construction method of installation of steel construction under a kind of
CN103758348B (en) Profile steel framework structure concrete floor slab suspension mould pouring construction method
CN102839601A (en) Fixed connection structure for steel pier column and cushion cap of portal rigid frame overbridge and construction method of fixed connection structure
CN112854745A (en) Construction process of assembled building aluminum alloy template
CN106592965A (en) Quick support system of high-rise steel structure house composite floor slab
CN106065681A (en) Superimposed sheet hoard strip construction method in a kind of overall assembled architecture based on BIM technology
CN202090605U (en) Tool type floor evenness and floor slab negative reinforcement protecting layer control device
CN103806647A (en) Assembly and disassembly process for large-span concrete bidirectional dense rib beam formwork case
CN202787055U (en) Pier fixed connection structure of steel structure overhead bridge
CN106193584A (en) A kind of self-supporting combined large steel model and fire wall construction method thereof
CN105178604A (en) Construction method of assembly type superimposed floor slab
CN208280003U (en) A kind of bridge pier over-form construction system
CN110682433A (en) Prefabricated stand column construction scheme
CN107571392A (en) A kind of beam making bench for the construction of transverse tensioning method prestressing force prefabricated small box girder
CN113202222A (en) Construction method for assembled type superposed beam slab
CN110905113A (en) Construction method of large-span concrete dome structure
CN103276894A (en) Support system of large-cross-section girder transfer floor of hollow floor system and construction technology
CN114438896A (en) Assembling construction method for assembled segmental beam of 100t span-pier gantry crane
CN108678181B (en) High-altitude construction method for steel truss and concrete combined structure on top of bin
CN202064281U (en) Slip form frame
CN111140001B (en) Mortar plastering construction method for stand column
CN202401753U (en) Sliding die device
CN110983987A (en) Construction method of steel-concrete combined beam
CN102635234A (en) Construction method for controlling thickness of upper-layer steel bar protection layer and board thickness of floorboard

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant