CN111041989A - Rapid installation method of prefabricated assembled bridge - Google Patents

Rapid installation method of prefabricated assembled bridge Download PDF

Info

Publication number
CN111041989A
CN111041989A CN201911273340.0A CN201911273340A CN111041989A CN 111041989 A CN111041989 A CN 111041989A CN 201911273340 A CN201911273340 A CN 201911273340A CN 111041989 A CN111041989 A CN 111041989A
Authority
CN
China
Prior art keywords
hoisting
support
lattice column
adopts
mode
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911273340.0A
Other languages
Chinese (zh)
Inventor
赵友禄
王伟
金东华
杨泽宇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Foundation Engineering Group Co Ltd
Original Assignee
Shanghai Foundation Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Foundation Engineering Group Co Ltd filed Critical Shanghai Foundation Engineering Group Co Ltd
Priority to CN201911273340.0A priority Critical patent/CN111041989A/en
Publication of CN111041989A publication Critical patent/CN111041989A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention relates to a method for quickly installing a prefabricated assembled bridge, which is characterized in that the transverse and vertical space distance is limited, the conventional hoisting mode cannot meet the field requirement, the method adopts a span-by-span withdrawing hoisting installation mode for hoisting, is restrained by the hoisting completion time, adopts a temporary lattice column support for system conversion, shortens the hoisting period, and comprises the following specific operation steps: construction preparation, cleaning of a bearing platform, hoisting of an upright column, assembling of a temporary lattice column support system, measurement of the elevation of the temporary lattice column support system, hoisting of a cover beam, grouting of the upright column and the cover beam, hoisting of a plate beam, hoisting of the next-span upright column, the cover beam and the plate beam, and dismantling of a support. The invention can greatly meet the requirement of rapid installation of the prefabricated part caused by limited space, and simultaneously, the installation of the lattice column support ensures the stability in the hoisting process of the structure, shortens the hoisting period of each span and ensures the target time of the construction period.

Description

Rapid installation method of prefabricated assembled bridge
Technical Field
The invention relates to a quick installation method of a prefabricated assembled bridge, in particular to a quick installation method of a prefabricated assembled bridge, which is used for a newly-built bridge and has the advantages of very limited or even very narrow construction operation space, limited vertical space distance and limited topographic conditions.
Background
At present, the reconstruction and expansion projects of urban bridges are increasing day by day, and the reconstruction, reconstruction and expansion projects of bridges in busy and downtown areas and urban sensitive areas are a large field where bridge construction cannot be seen in the future. The construction method is characterized in that reconstruction and expansion are carried out in the range of an original bridge, so that splicing of a new bridge and an old bridge is formed, and under the influence of peripheral important construction objects and pipeline protection requirements and under the condition that normal traffic is often required to be guaranteed for the existing bridge, the construction operation space of the newly-built bridge is very limited or even very narrow. The horizontal, vertical space distance of this engineering is limited, and the topography condition receives the restriction, consequently, need adopt to stride gradually and retreat to hoist the mode, adopts interim lattice column support in order to shorten the hoist and mount time simultaneously.
Disclosure of Invention
The invention provides a method for quickly installing a prefabricated assembled bridge, aiming at solving the technical problem of quickly installing the prefabricated assembled bridge, and the method can greatly meet the requirement of quickly installing prefabricated parts caused by limited space, and meanwhile, the stability of a structure in the hoisting process is ensured by installing a lattice column support, the hoisting period of each span is also shortened, and the target time of the construction period is ensured.
In order to achieve the purpose, the technical scheme of the invention is as follows: the utility model provides a prefabricated bridge quick installation method of assembling, receives the restriction in horizontal vertical direction spatial distance, and on-the-spot demand can not be satisfied to conventional hoist and mount mode, adopts and strides gradually to move back to hoist the mode of installation and hoist, receives the restraint of hoist and mount completion time simultaneously, adopts interim lattice column support to carry out the system conversion, shortens the hoist and mount cycle, and concrete operating procedure is in proper order: construction preparation, cleaning of a bearing platform, hoisting of an upright column, assembling of a temporary lattice column support system, measurement of the elevation of the temporary lattice column support system, hoisting of a cover beam, grouting of the upright column and the cover beam, hoisting of a plate beam, hoisting of the next-span upright column, the cover beam and the plate beam, and dismantling of a support.
Further, during the assembly of the temporary lattice column support system, the support is assembled by adopting standard parts, when the assembly height of the standard parts is not enough, the standard parts are connected in a welding mode, and the welding quality needs to be ensured during welding.
Further, the temporary lattice column support is installed on a poured bearing platform, the connection mode is that expansion bolts are used for connection, and after the support is dismantled, the expansion bolt holes are subjected to anti-corrosion treatment in a mortar plugging mode.
The beneficial results of the invention are: the hoisting of the members in the limited space can be met, the hoisting time is greatly shortened, and successful experience of the hoisting can guide type engineering construction.
Drawings
FIG. 1 is a schematic view of an occupied plane position of a back-hanging crane;
FIG. 2 is a schematic view of a temporary lattice column support;
fig. 3 is a cross-sectional view taken along a-a in fig. 2.
Detailed Description
Embodiments of the present invention are further illustrated below with reference to specific examples. It should be understood that these examples are for illustrative purposes only and are not intended to limit the scope of the present invention. Further, it should be understood that various changes or modifications of the present invention may be made by those skilled in the art after reading the teaching of the present invention, and such equivalents may fall within the scope of the present invention as defined in the appended claims.
The address of a newly-built bridge of the project is positioned between a subway No. 2 line and an S1 overhead, is limited by the distance between the subway No. 2 line and a transverse space and a vertical space, and can be hoisted only after the subway No. 2 line stops transporting at night.
The method for quickly installing the prefabricated assembled bridge is limited in transverse and vertical space distance, a conventional hoisting mode cannot meet the field requirement, the prefabricated assembled bridge is hoisted in a span-by-span retreating hoisting mode (shown in figure 1), meanwhile, the prefabricated assembled bridge is restrained by hoisting completion time, a temporary latticed column support (shown in figures 2 and 3) is used for system conversion, the hoisting period is shortened, and the specific operation steps are as follows: construction preparation, cleaning of a bearing platform, hoisting of an upright column, assembling of a temporary lattice column support system, measurement of the elevation of the temporary lattice column support system, hoisting of a cover beam, grouting of the upright column and the cover beam, hoisting of a plate beam, hoisting of the next-span upright column, the cover beam and the plate beam, and dismantling of a support.
And (3) carrying out support elevation control by adopting a total station in the process of erecting the temporary support, and ensuring that the cover beam erection elevation and the bridge deck elevation are matched with the design drawing. In the process of erecting the support, the upright post is connected with the hoop of the lattice column by utilizing the channel steel, so that the disturbance of the capping beam hoisting process to the pulp sitting at the bottom of the upright post is reduced.
1. Anticorrosion treatment for expansion bolt of bearing platform
Because the bearing platform is connected with the steel pipe upright post through the expansion bolts, the expansion bolts higher than the bearing platform surface are cut through a cutting machine after the support is dismantled, then the bolts are beaten to the position below the bearing platform surface through tools, and then the expansion bolt holes are plugged through mortar.
2. Pouring of support base stone
In order to accelerate the manufacturing speed of the on-site support and meet the strength requirement of the support, the cushion stone of the on-site support is poured by C100 grouting material, and the measurement of elevation data is emphasized in the pouring process, so that the bridge deck elevation meets the requirement of a design drawing after the plate girder is erected.
3. Welding requirements
During welding, the welding seam is required to be smooth, welding defects such as air holes and slag inclusion cannot be caused, and the defects are found and repaired in time. When intermittent welding is adopted, the length and the interval of the welding lines are uniform and consistent.
When the manufactured part requires sealed continuous welding, the phenomenon of air hole and sand hole at the welding seam is required not to occur. The height of the weld seam is required to be not less than the thickness of the base metal (weldment) during welding. When base materials (weldment) with different thicknesses are welded, the height of a welding seam cannot be smaller than the thickness of the thinnest base material (weldment).
4. Technical requirements for assembling and disassembling temporary supports
The connecting rod is assembled on site by the bolt in the support mounting process, after the stand column is mounted, the crane is used for hoisting and splicing, in the mounting process, the crane operator should be familiar with the environment, the information issued by commanders is noticed, and the collision with the pier stud in the support mounting process is avoided.
And (3) finishing the installation of the plate girder, cutting off top section steel, and after removing tie bars between the steel upright columns, conveying the steel support to the specified pier column position from the bottom of the plate girder by using a forklift or an excavator.

Claims (3)

1. The utility model provides a prefabricated bridge quick installation method of assembling, its characterized in that receives the restriction at horizontal vertical spatial distance, and conventional hoist and mount mode can not satisfy the on-the-spot demand, adopts to stride gradually to move back to hoist the mode of installation, receives the restraint of hoist and mount completion time simultaneously, adopts interim lattice column support to carry out the system conversion, shortens hoist and mount cycle, and concrete operating procedure is in proper order: construction preparation, cleaning of a bearing platform, hoisting of an upright column, assembling of a temporary lattice column support system, measurement of the elevation of the temporary lattice column support system, hoisting of a cover beam, grouting of the upright column and the cover beam, hoisting of a plate beam, hoisting of the next-span upright column, the cover beam and the plate beam, and dismantling of a support.
2. The method for quickly installing the prefabricated assembled bridge according to claim 1, wherein the method comprises the following steps: during interim lattice column mounting system assembles, the support adopts the standard component to assemble, and when the standard component was assembled highly inadequately, adopts the welded mode to connect, need guarantee welding quality during the welding.
3. The method for quickly installing the prefabricated assembled bridge according to claim 1, wherein the method comprises the following steps: the temporary lattice column support is installed on a poured bearing platform, the connection mode adopts expansion bolts for connection, and after the support is dismantled, the expansion bolt holes are subjected to anti-corrosion treatment in a mortar plugging mode.
CN201911273340.0A 2019-12-12 2019-12-12 Rapid installation method of prefabricated assembled bridge Pending CN111041989A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911273340.0A CN111041989A (en) 2019-12-12 2019-12-12 Rapid installation method of prefabricated assembled bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911273340.0A CN111041989A (en) 2019-12-12 2019-12-12 Rapid installation method of prefabricated assembled bridge

Publications (1)

Publication Number Publication Date
CN111041989A true CN111041989A (en) 2020-04-21

Family

ID=70236008

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911273340.0A Pending CN111041989A (en) 2019-12-12 2019-12-12 Rapid installation method of prefabricated assembled bridge

Country Status (1)

Country Link
CN (1) CN111041989A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900280A (en) * 2021-02-02 2021-06-04 中铁四局集团第三建设有限公司 Bridge prefabricated bent cap installation in-place construction method and construction structure

Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2381326C1 (en) * 2008-11-14 2010-02-10 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for lifting and erecting units of superstructure
CN201614746U (en) * 2009-12-30 2010-10-27 上海天演建筑物移位工程有限公司 Limit power transmission device for building jacking
CN102116094A (en) * 2009-12-30 2011-07-06 上海天演建筑物移位工程有限公司 Displacement limit force transmission device for jacking up building
CN102587286A (en) * 2012-03-28 2012-07-18 上海市第四建筑有限公司 Simply supported-continuous construction method for bridge superstructure
CN102900241A (en) * 2012-10-26 2013-01-30 上海建工四建集团有限公司 Integrated construction method for nodes of 'new beam and old column' in reconstruction of concrete structure
CN203487467U (en) * 2013-09-30 2014-03-19 上海建工七建集团有限公司 Multifunctional bracket for simply supported change continuous box beam construction
CN105780660A (en) * 2016-03-23 2016-07-20 中铁局集团有限公司 Segmental assembling box girder construction technology
CN205636496U (en) * 2016-04-07 2016-10-12 中铁二局集团有限公司 A interim strutting arrangement that is used for support frame bridge crane and whole hole case roof beam
CN106869028A (en) * 2015-12-13 2017-06-20 青岛星锐机械有限公司 A kind of lattice temporary support blocks
CN109208478A (en) * 2017-06-30 2019-01-15 中交第二航务工程局有限公司 A kind of prefabricated assembled bridge integration rapid constructing method
CN208632971U (en) * 2018-07-02 2019-03-22 中国二十冶集团有限公司 A kind of Demountable bracket

Patent Citations (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
RU2381326C1 (en) * 2008-11-14 2010-02-10 Открытое акционерное общество по проектированию строительства мостов "Институт Гипростроймост" Device for lifting and erecting units of superstructure
CN201614746U (en) * 2009-12-30 2010-10-27 上海天演建筑物移位工程有限公司 Limit power transmission device for building jacking
CN102116094A (en) * 2009-12-30 2011-07-06 上海天演建筑物移位工程有限公司 Displacement limit force transmission device for jacking up building
CN102587286A (en) * 2012-03-28 2012-07-18 上海市第四建筑有限公司 Simply supported-continuous construction method for bridge superstructure
CN102900241A (en) * 2012-10-26 2013-01-30 上海建工四建集团有限公司 Integrated construction method for nodes of 'new beam and old column' in reconstruction of concrete structure
CN203487467U (en) * 2013-09-30 2014-03-19 上海建工七建集团有限公司 Multifunctional bracket for simply supported change continuous box beam construction
CN106869028A (en) * 2015-12-13 2017-06-20 青岛星锐机械有限公司 A kind of lattice temporary support blocks
CN105780660A (en) * 2016-03-23 2016-07-20 中铁局集团有限公司 Segmental assembling box girder construction technology
CN205636496U (en) * 2016-04-07 2016-10-12 中铁二局集团有限公司 A interim strutting arrangement that is used for support frame bridge crane and whole hole case roof beam
CN109208478A (en) * 2017-06-30 2019-01-15 中交第二航务工程局有限公司 A kind of prefabricated assembled bridge integration rapid constructing method
CN208632971U (en) * 2018-07-02 2019-03-22 中国二十冶集团有限公司 A kind of Demountable bracket

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
胡胜全: "城市桥梁预制拼装施工与质量控制", 《中国市政工程》 *
高振锋: "科技创新引领京沪高铁上海虹桥站的建设", 《建筑施工》 *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112900280A (en) * 2021-02-02 2021-06-04 中铁四局集团第三建设有限公司 Bridge prefabricated bent cap installation in-place construction method and construction structure

Similar Documents

Publication Publication Date Title
CN107090975B (en) Formwork erecting construction method for ultrahigh large-span concrete cast-in-place beam bailey truss
JP5045214B2 (en) Column head construction method
CN114592436B (en) Pier capping beam lower support system and construction method thereof
CN113638304B (en) Concrete beam type bridge hidden cover beam structure system and construction method thereof
CN102720137B (en) Prefabrication construction method for trough girder sections of track traffic high-level bridge
CN111254804A (en) Construction method of steel box girder bridge of overpass highway
CN111236089A (en) Uneven jacking system and uneven jacking construction method for existing bridge superstructure
CN110725324A (en) Shear wall high-limb guide wall conversion supporting structure and construction method thereof
KR20100003791A (en) A precast type pre-stress box girder bridge excution method
CN111041989A (en) Rapid installation method of prefabricated assembled bridge
CN110080271B (en) Construction method for embedded quality control of foundation bolt embedded part
CN211006346U (en) Cast-in-place support of side span of dismouting of being convenient for suitable for bridge
JP4978444B2 (en) Method for adjusting gaps in steel plates for seismic reinforcement
CN113737661B (en) Construction method for steel-concrete combined section of tower base of cable-stayed bridge
CN114197303B (en) Bridge temporary expansion joint construction method
CN205711786U (en) Big cross section porous overlength cast-in-place box culvert formwork system
CN112962430A (en) Assembled replaceable bridge pier
CN113216015A (en) Construction method of viaduct jacking bearing platform pier column upgrading structure
JP2020153104A (en) Repair method of bridge pier
CN217758588U (en) Reinforced structure of water supply aqueduct
CN220431975U (en) Super-high adhesion structure of construction elevator
CN113668388B (en) Pier-beam collaborative integral rapid installation and removal method based on vehicle-mounted equipment
CN218088680U (en) Pre-buried nested combination formula tower crane festival device
CN219909302U (en) Post-cast strip supporting system
CN114458050B (en) Cast house roof protective dismantling method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200421

RJ01 Rejection of invention patent application after publication