CN111005760A - Drainage type drainage system for karst tunnel - Google Patents

Drainage type drainage system for karst tunnel Download PDF

Info

Publication number
CN111005760A
CN111005760A CN201911387657.7A CN201911387657A CN111005760A CN 111005760 A CN111005760 A CN 111005760A CN 201911387657 A CN201911387657 A CN 201911387657A CN 111005760 A CN111005760 A CN 111005760A
Authority
CN
China
Prior art keywords
drainage
tunnel
pipe
water
karst
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911387657.7A
Other languages
Chinese (zh)
Inventor
范雲鹤
罗禄森
赵万强
郑长青
周路军
喻渝
张永平
何昌国
匡亮
蒋立
何洋
刘佩斯
唐思聪
袁伟
杨学中
刘祥
华阳
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway Eryuan Engineering Group Co Ltd CREEC
Original Assignee
China Railway Eryuan Engineering Group Co Ltd CREEC
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway Eryuan Engineering Group Co Ltd CREEC filed Critical China Railway Eryuan Engineering Group Co Ltd CREEC
Priority to CN201911387657.7A priority Critical patent/CN111005760A/en
Publication of CN111005760A publication Critical patent/CN111005760A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F16/00Drainage
    • E21F16/02Drainage of tunnels
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21FSAFETY DEVICES, TRANSPORT, FILLING-UP, RESCUE, VENTILATION, OR DRAINING IN OR OF MINES OR TUNNELS
    • E21F17/00Methods or devices for use in mines or tunnels, not covered elsewhere
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F04POSITIVE - DISPLACEMENT MACHINES FOR LIQUIDS; PUMPS FOR LIQUIDS OR ELASTIC FLUIDS
    • F04FPUMPING OF FLUID BY DIRECT CONTACT OF ANOTHER FLUID OR BY USING INERTIA OF FLUID TO BE PUMPED; SIPHONS
    • F04F10/00Siphons

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mechanical Engineering (AREA)
  • General Engineering & Computer Science (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

The invention discloses a drainage type drainage system of a karst tunnel, which comprises a drilling hole, a drainage network, a drainage pipe and a tunnel drainage ditch, wherein the drilling hole is a declination drilling hole which is drilled from an arch wall of the tunnel to a karst development area, the drainage network is positioned on a soil body or a rock body near the bottom end of the drilling hole, at least part of the drainage network is positioned in the karst development area, the drainage network comprises a plurality of cracks, permeable concrete is filled in the cracks, all the cracks are mutually communicated, the drainage pipe is laid in the drilling hole, a water inlet of the drainage pipe is communicated with the drainage network, a water outlet of the drainage pipe is communicated with the tunnel drainage ditch, the height of the water inlet of the drainage pipe is lower than that of the water outlet of the drainage pipe, and the height of. The drainage type drainage system for the karst tunnel disclosed by the invention utilizes the siphoning effect, so that redundant underground water in the surrounding rock of the tunnel can be automatically and efficiently drained in real time as long as the underground water is gathered, and no external power or manual maintenance is needed.

Description

Drainage type drainage system for karst tunnel
Technical Field
The invention relates to the technical field of tunnel engineering, in particular to a drainage system of a karst tunnel.
Background
In recent years, the traffic industry such as railways, roads and the like in China is rapidly developed, and the number and the mileage of tunnels are continuously increased. Under the influence of complex geological environment and hydrogeological conditions, the construction and operation process of the tunnel still faces a plurality of engineering diseases at present. Karst tunnels in the southwest are widely distributed, karst water causes great harm to a tunnel lining structure, water pressure acts on the lining to change the stress characteristic of the lining structure, and the large water pressure behind the lining increases the load behind the tunnel structure, so that the generation of diseases such as tunnel lining cracking, inverted arch rising, grout pumping and the like is caused. Therefore, the drainage of the underground water behind the lining is very important. However, due to irregular distribution of karst fractures in a karst region, drainage blind spots often exist in drainage of the currently adopted lining back ring longitudinal blind pipes, and after a drainage channel formed by rock fractures is blocked in the later period, long-term effective drainage cannot be performed, so that the problem that tunnel lining damage is caused by unsmooth drainage is caused.
Disclosure of Invention
The invention aims to: aiming at the problem of difficult drainage of the karst tunnel in the prior art, the drainage type drainage system of the karst tunnel is provided.
In order to achieve the purpose, the invention adopts the technical scheme that:
a drainage type drainage system of a karst tunnel, which comprises a drill hole, a drainage network, a drainage pipe and a tunnel drainage ditch, the drill holes are declined drill holes which are punched from the tunnel arch wall to the karst development area, the drainage network is located on the soil or rock mass near the bottom end of the drill hole, at least part (or all) of the drainage network is located in the karst development area, the drainage network comprises a plurality of cracks, pervious concrete is filled in the cracks, all the cracks are communicated with each other, a drain pipe is laid in the drill hole, the water inlet of the drain pipe is communicated with the drainage network, the delivery port of drain pipe with the tunnel escape canal is linked together, the elevation of the water inlet of drain pipe is less than the elevation of the delivery port of drain pipe, just the elevation on drilling top is higher than the elevation of the delivery port of drain pipe.
Along with the development of karst, groundwater concentrates near the water inlet of drain pipe gradually through drainage network, and when the groundwater level line of drain pipe water inlet department improved, because the siphon effect, groundwater will be carried to the tunnel escape canal through the drain pipe, until the water level of drain pipe water inlet department equals the water level of the delivery port department of drain pipe, then accomplish once automatic drainage. The above automatic drainage process will occur many times during the operation of the tunnel.
The drainage system for the karst tunnel provided by the invention utilizes the siphon effect, can automatically and efficiently drain redundant underground water in the surrounding rock of the tunnel in real time as long as the underground water is gathered, and does not need any external power or manual maintenance. According to the invention, the pervious concrete is pressed into the surrounding rock of the tunnel under high pressure, and the pervious concrete forms a drainage network with high porosity after solidification, so that underground water is gathered near the drilled hole, the influence range of a single drainage hole on the generation of a landing funnel is enlarged, water is drained efficiently at one time, and the drainage efficiency can be obviously improved.
In a preferred embodiment of the present invention, a plurality of injection holes are circumferentially arranged along the borehole, and each slit is communicated with at least one of the injection holes. The jet holes are used for communicating the cracks with the drill holes, and the jet holes are convenient for jetting pervious concrete.
In a preferred embodiment of the present invention, the permeable concrete has a permeability coefficient of 0.01m/d or more, and is made of aggregate, cement, a reinforcing agent, and water.
As the preferable scheme of the invention, at least two drain pipes are arranged in the drill hole, so that the drainage efficiency is improved.
In a preferred embodiment of the present invention, a part of the drain pipe is laid in the drilled hole, and another part of the drain pipe is fixed to the inner wall of the tunnel.
As a preferable scheme of the invention, the lift of the drain pipe is smaller than the height of a water column corresponding to the atmospheric pressure of a construction site.
As a preferable scheme of the invention, the inclination angle of the drill hole is 10-30 degrees.
In a preferred embodiment of the present invention, the diameter of the bore is greater than or equal to 70 mm.
As a preferable scheme of the invention, the drain pipe is a PU pipe.
As a preferable scheme of the invention, the diameter of the drain pipe is more than or equal to 4 mm.
As a preferable scheme of the present invention, the tunnel drainage ditch is a tunnel side ditch, a water collection tank is arranged in the tunnel side ditch, and a water outlet of the drainage pipe is located in the water collection tank.
The invention also discloses a drainage method for the karst tunnel, which comprises the following steps:
the method comprises the following steps: according to a geological survey result, preliminarily determining a karst development area of the tunnel, and drilling downward inclined holes facing the karst development area from the tunnel arch wall. And if the drill hole can be directly drilled to the karst development area, directly drilling to the karst development area, and if the drill hole can not be directly drilled to the karst development area, drilling to the position near the karst development area as much as possible, so that after the pervious concrete is injected, at least part of the formed drainage network can be positioned in the karst development area, and the underground water of the karst development area is led out.
Step two: and placing a multi-nozzle sleeve at the bottom end of the drilled hole, wherein the multi-nozzle sleeve comprises a grouting hole, a plurality of jet holes and a movable sleeve, the movable sleeve is respectively connected with the grouting hole and the high-pressure pump, the movable sleeve is connected with the high-pressure pump, and the high-pressure pump is used for injecting pervious concrete into the multi-nozzle sleeve.
Step three: after the pervious concrete is injected, the movable sleeve is dismantled, and a water inlet of a drain pipe is placed at the bottom end of the drilled hole;
step four: and reversely filling water from the water outlet of the drain pipe, stopping reversely filling water after all the air in the drain pipe is discharged, and putting the water outlet of the drain pipe into a tunnel drainage ditch. According to the calculated volume of the drain pipe, the amount of water greater than or equal to the volume is injected, so that all the air in the drain pipe can be discharged.
According to the drainage method, the high-pressure pump is used for injecting the pervious concrete into the multi-nozzle sleeve, the pervious concrete enters the soil body or the rock body from the injection hole, the pervious concrete develops along the weak area of the soil body or the rock body, the whole crack space is filled and solidified when stratum rock and soil are fractured, a space high-permeability drainage network is formed, and underground water is drained to the drilling hole. And then the drain pipe is communicated between the drill hole and the tunnel drainage ditch, when the water level of the water inlet of the drain pipe is higher than that of the water outlet, the siphon effect is generated, the underground water is automatically discharged, after the primary drainage process is finished, the water inlet and the water outlet of the drain pipe are both positioned below the water surface, and air cannot enter the drain pipe, so that the drain pipe is kept in a vacuum state. When the ground water level at the water inlet rises again, the siphon action occurs again and the drain pipe drains water again.
The drainage method can automatically drain the underground water for multiple times in real time during the whole tunnel operation period only by once construction, and the drainage process automatically occurs without manual maintenance. The method utilizes the pervious concrete to be injected into the drilled hole, and can more easily and accurately position the karst development area along the crack direction of the rock-soil body under the condition that the karst development area is uncertain.
In a preferred embodiment of the present invention, all of the injection holes are uniformly arranged along a circumferential direction of the multi-nozzle casing.
As a preferable scheme of the invention, the multi-nozzle sleeve is a metal sleeve.
In summary, due to the adoption of the technical scheme, the invention has the beneficial effects that:
1. the drainage system for the karst tunnel provided by the invention utilizes the siphon effect, can automatically and efficiently drain redundant underground water in the surrounding rock of the tunnel in real time as long as the underground water is gathered, and does not need any external power or manual maintenance.
2. According to the invention, the pervious concrete is pressed into the surrounding rock of the tunnel under high pressure, and the pervious concrete forms a drainage network with high porosity after solidification, so that underground water is gathered near the drilled hole, the influence range of a single drainage hole on the generation of a landing funnel is enlarged, water is drained efficiently at one time, and the drainage efficiency can be obviously improved.
3. The drainage method can automatically drain the underground water for multiple times in real time during the whole tunnel operation period only by once construction, and the drainage process automatically occurs without manual maintenance.
4. The method utilizes the pervious concrete to be injected into the drilled hole, and can more easily and accurately position the karst development area along the crack direction of the rock-soil body under the condition that the karst development area is uncertain.
Drawings
Fig. 1 is a schematic structural diagram of a drainage system of a karst tunnel according to the first embodiment of the invention.
Fig. 2 is a schematic structural diagram of a drainage system of a karst tunnel according to the present invention.
FIG. 3 is a schematic diagram of a multiple nozzle tip cartridge according to the present invention.
Fig. 4 is a cross-sectional view of a tunnel lateral groove according to the present invention.
Fig. 5 is a plan view of a tunnel lateral groove according to the present invention.
Icon: 1-tunnel, 2-drilling, 3-multi-nozzle casing, 31-grouting hole, 32-injection hole, 33-movable casing, 4-pervious concrete, 5-drainage pipe, 6-tunnel side ditch, 61-water collecting tank, 7-karst development area and 8-underground water level line.
Detailed Description
The present invention will be described in detail below with reference to the accompanying drawings.
In order to make the objects, technical solutions and advantages of the present invention more apparent, the present invention is described in further detail below with reference to the accompanying drawings and embodiments. It should be understood that the specific embodiments described herein are merely illustrative of the invention and are not intended to limit the invention.
Example 1
A drainage type drainage system for a karst tunnel comprises a drill hole 2, a drainage network, a drainage pipe 5 and a tunnel drainage ditch.
The drill hole 2 is a declination drill hole, the inclination angle of the drill hole 2 is 10-30 degrees, and the diameter of the drill hole 2 is larger than or equal to 70 mm. The bore hole 2 is driven directly into the karst development zone 7 of the tunnel 1, as shown in figure 1; or the borehole 2 is not driven into the karst development zone 7 of the tunnel 1, but is located adjacent to the karst development zone 7, as illustrated in figure 2.
A multi-nozzle casing 3 is provided at the bottom end of the borehole 2, as shown in fig. 3, the multi-nozzle casing 3 includes a grouting hole 31, a plurality of injection holes 32, and a movable casing 33, and all the injection holes 32 are arranged circumferentially along the multi-nozzle casing 3. The grouting holes 31 are located in the drill holes 2, the grouting holes 31 are detachably connected with the movable sleeve 33, the movable sleeve 33 is connected with a high-pressure pump, the high-pressure pump is used for injecting permeable concrete 4 into the multi-nozzle sleeve 3, the permeable concrete 4 enters a soil body or a rock body from the injection holes 32, the permeable concrete 32 develops along a weak area of the soil body or the rock body, and when stratum rock soil is fractured, the whole crack space is filled and solidified to form a space high-permeability drainage network. After the pervious concrete 4 is poured, the movable sleeve 33 is removed, and the grouting hole 31 is communicated with the drain pipe 5. The direction of the grouting is shown by the arrow in fig. 3.
The drainage network is positioned on a soil body or a rock body near the bottom end of the drilling hole 2, at least part (or all) of the drainage network is positioned in the karst development area 7, the drainage network comprises a plurality of cracks, permeable concrete 4 is filled in the cracks, all the cracks are mutually communicated, each crack is at least communicated with one injection hole 32, the permeability coefficient of the permeable concrete 4 is greater than or equal to 0.01m/d, and the permeable concrete 4 is made of aggregate, cement, reinforcing agent and water.
At least two drain pipes 5 have been laid in drilling 2, drain pipe 5 is diameter 4 mm's PU pipe, drain pipe 5's lift is less than the water column height that construction site atmospheric pressure corresponds. One part of the drain pipe 5 is laid in the drilled hole, and the other part of the drain pipe 5 is fixed on the inner wall of the tunnel 1. And the water inlet of the drain pipe 5 is communicated with the drain network, and the water outlet of the drain pipe 5 is communicated with the tunnel drain. Specifically, as shown in fig. 4 to 5, the tunnel drainage ditch is a tunnel side ditch 6, a water collection tank 61 is arranged in the tunnel side ditch 6, and a water outlet of the drainage pipe 5 is located in the water collection tank 61.
The elevation of the water inlet of the drain pipe 5 is lower than that of the water outlet of the drain pipe 5, and the elevation of the top end of the drilling hole 2 is higher than that of the water outlet of the drain pipe 5.
Due to the arrangement of the drainage system, the underground water is gradually concentrated to the position near the water inlet of the drainage pipe 5 through the drainage network, when the underground water level line 8 at the water inlet of the drainage pipe 5 is increased, the underground water is conveyed to the water collecting tank 61 through the drainage pipe 5 due to the siphoning effect until the water level at the water inlet of the drainage pipe 5 is equal to the water level at the water outlet of the drainage pipe 5, and one-time automatic drainage is completed. The above automatic drainage process will occur many times during the operation of the tunnel.
Example 2
As shown in fig. 1 to 5, a drainage method for karst tunnels comprises the following steps:
the method comprises the following steps: according to a geological survey result, a karst development area 7 of the tunnel 1 is preliminarily determined, and a downward inclined drill hole 2 facing the karst development area 7 is drilled from the arch wall of the tunnel 1. If the drill hole 2 can be directly drilled to the karst development area 7, the drill hole is directly drilled to the karst development area 7, if the drill hole 2 cannot be directly drilled to the karst development area 7, the drill hole is drilled to the position near the karst development area 7 as far as possible, so that after the pervious concrete 4 is injected, at least part of the formed drainage network can be located in the karst development area 7, and the underground water of the karst development area 7 is led out.
Step two: the bottom of drilling 2 places many shower nozzles sleeve pipe 3, many shower nozzle sleeve pipe 3 includes injected hole 31, a plurality of jet orifice 32 and movable sleeve pipe 33, will movable sleeve pipe 33 respectively with injected hole 31, high-pressure pump are connected, utilize the high-pressure pump to in the many shower nozzle sleeve pipe 3 pour into pervious concrete 4. The pervious concrete 4 enters the soil body or rock body from the injection hole 32, the pervious concrete 32 develops along the weak area of the soil body or rock body, and the whole crack space is filled and solidified when stratum rock and soil are fractured, so that a spatial high-permeability drainage network is formed.
Step three: and after the pervious concrete 4 is injected, the movable sleeve 33 is removed, and the water inlet of the drain pipe 5 is placed at the bottom end of the drill hole 2.
Step four: and reversely filling water from the water outlet of the drain pipe 5, stopping reversely filling water after all the air in the drain pipe 5 is discharged, and putting the water outlet of the drain pipe 5 into the water collecting tank 61 of the tunnel side ditch 6. Based on the calculated volume of the drain pipe 5, the amount of water greater than or equal to the volume is injected, so that all the air in the drain pipe 5 can be discharged.
According to the drainage method, the high-pressure pump is used for injecting the pervious concrete into the multi-nozzle sleeve, the pervious concrete enters the soil body or rock body from the injection hole to form a spatial high-permeability drainage network, and underground water is drained to the drill hole. And then the drain pipe is communicated between the drill hole and the tunnel drainage ditch, when the water level of the water inlet of the drain pipe is higher than that of the water outlet, the siphon effect is generated, the underground water is automatically discharged, after the primary drainage process is finished, the water inlet and the water outlet of the drain pipe are both positioned below the water surface, and air cannot enter the drain pipe, so that the drain pipe is kept in a vacuum state. When the ground water level at the water inlet rises again, the siphon action occurs again and the drain pipe drains water again.
The above description is only for the purpose of illustrating the preferred embodiments of the present invention and is not to be construed as limiting the invention, and any modifications, equivalents and improvements made within the spirit and principle of the present invention are intended to be included within the scope of the present invention.

Claims (10)

1. The drainage network is located on soil or rock mass near the bottom end of the drilled hole, at least part of the drainage network is located in the karst development area, the drainage network comprises a plurality of cracks, permeable concrete is filled in the cracks, all the cracks are communicated with each other, a drainage pipe is laid in the drilled hole, a water inlet of the drainage pipe is communicated with the drainage network, a water outlet of the drainage pipe is communicated with the tunnel drainage ditch, the elevation of a water inlet of the drainage pipe is lower than that of a water outlet of the drainage pipe, and the elevation of the top end of the drilled hole is higher than that of the water outlet of the drainage pipe.
2. The drainage system of claim 1, wherein a plurality of injection holes are circumferentially arranged along the bore hole, and each slit is in communication with at least one of the injection holes.
3. The drainage system of claim 1, wherein the permeable concrete has a permeability coefficient greater than or equal to 0.01m/d, and is made of aggregate, cement, reinforcing agent and water.
4. The drainage system of claim 1, wherein at least two drainage pipes are disposed in the bore hole.
5. The drainage system of claim 4, wherein one part of the drainage pipe is laid in the drilled hole, and the other part of the drainage pipe is fixed on the inner wall of the tunnel.
6. The drainage system of claim 1, wherein the lift of the drainage pipe is less than the height of the water column corresponding to the atmospheric pressure of the construction site.
7. The drainage system of any one of claims 1 to 6, wherein the inclination angle of the bore hole is 10 degrees to 30 degrees, and the diameter of the bore hole is greater than or equal to 70 mm.
8. The karst tunnel drainage system of any one of claims 1-6, wherein the drain pipe is a PU pipe, and the diameter of the drain pipe is greater than or equal to 4 mm.
9. The karst tunnel drainage system of any one of claims 1-6, wherein the tunnel drainage ditch is a tunnel side ditch, a water collection tank is arranged in the tunnel side ditch, and a water outlet of the drainage pipe is located in the water collection tank.
10. A drainage type drainage method for a karst tunnel is characterized by comprising the following steps:
the method comprises the following steps: preliminarily determining a karst development area of the tunnel according to a geological survey result, and drilling downward inclined drill holes facing the karst development area from the tunnel arch wall;
step two: placing a multi-nozzle sleeve at the bottom end of the drilled hole, wherein the multi-nozzle sleeve comprises a grouting hole, a plurality of injection holes and a movable sleeve, the movable sleeve is respectively connected with the grouting hole and a high-pressure pump, and the high-pressure pump is used for injecting pervious concrete into the multi-nozzle sleeve;
step three: after the pervious concrete is injected, the movable sleeve is dismantled, and a water inlet of a drain pipe is placed at the bottom end of the drilled hole;
step four: and reversely filling water from the water outlet of the drain pipe, stopping reversely filling water after all the air in the drain pipe is discharged, and putting the water outlet of the drain pipe into a tunnel drainage ditch.
CN201911387657.7A 2019-12-27 2019-12-27 Drainage type drainage system for karst tunnel Pending CN111005760A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911387657.7A CN111005760A (en) 2019-12-27 2019-12-27 Drainage type drainage system for karst tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911387657.7A CN111005760A (en) 2019-12-27 2019-12-27 Drainage type drainage system for karst tunnel

Publications (1)

Publication Number Publication Date
CN111005760A true CN111005760A (en) 2020-04-14

Family

ID=70119561

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911387657.7A Pending CN111005760A (en) 2019-12-27 2019-12-27 Drainage type drainage system for karst tunnel

Country Status (1)

Country Link
CN (1) CN111005760A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794238A (en) * 2020-07-20 2020-10-20 中铁二院工程集团有限责任公司 Grouting structure for filling soluble crystals and construction method
CN111810234A (en) * 2020-07-20 2020-10-23 中铁二院工程集团有限责任公司 Tunnel water seepage and harmful gas discharge structure and semi-closed ice filling drilling construction method
CN112145202A (en) * 2020-11-04 2020-12-29 中铁五局集团第五工程有限责任公司 Device for ensuring impervious strength of tunnel cast concrete and construction method
CN116005719A (en) * 2023-03-07 2023-04-25 中铁二院工程集团有限责任公司 Composite material miniature pipe gallery and drainage method thereof

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635402A (en) * 2012-04-11 2012-08-15 浙江大学 Siphon drainage method for tunnel wall water seepage disposal by using dipping borehole
CN203412623U (en) * 2013-07-26 2014-01-29 中国矿业大学 Bottom plate water drainage pump drainage device
CN105821830A (en) * 2016-05-05 2016-08-03 浙江大学 Permeation increase siphon drainage system for low-permeability soil slope
CN105822347A (en) * 2016-04-19 2016-08-03 同济大学 Tunnel siphon water drainage system and construction method thereof
CN106089297A (en) * 2016-07-29 2016-11-09 中铁工程设计咨询集团有限公司 Railway tunnel bottom structure drainage device and method to set up thereof
CN107165672A (en) * 2017-06-30 2017-09-15 徐州市耐力高分子科技有限公司 A kind of descending borehole fissure water suction system of country rock
CN107237650A (en) * 2017-06-30 2017-10-10 浙江大学 A kind of drilling siphon drainage system and method for being used to handle the infiltration of Tunnel wall
CN110566273A (en) * 2019-09-17 2019-12-13 中国十九冶集团有限公司 Drainage system and drainage method for treating tunnel surrounding rock fracture water
CN211230546U (en) * 2019-12-27 2020-08-11 中铁二院工程集团有限责任公司 Drainage type drainage system for karst tunnel

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN102635402A (en) * 2012-04-11 2012-08-15 浙江大学 Siphon drainage method for tunnel wall water seepage disposal by using dipping borehole
CN203412623U (en) * 2013-07-26 2014-01-29 中国矿业大学 Bottom plate water drainage pump drainage device
CN105822347A (en) * 2016-04-19 2016-08-03 同济大学 Tunnel siphon water drainage system and construction method thereof
CN105821830A (en) * 2016-05-05 2016-08-03 浙江大学 Permeation increase siphon drainage system for low-permeability soil slope
CN106089297A (en) * 2016-07-29 2016-11-09 中铁工程设计咨询集团有限公司 Railway tunnel bottom structure drainage device and method to set up thereof
CN107165672A (en) * 2017-06-30 2017-09-15 徐州市耐力高分子科技有限公司 A kind of descending borehole fissure water suction system of country rock
CN107237650A (en) * 2017-06-30 2017-10-10 浙江大学 A kind of drilling siphon drainage system and method for being used to handle the infiltration of Tunnel wall
CN110566273A (en) * 2019-09-17 2019-12-13 中国十九冶集团有限公司 Drainage system and drainage method for treating tunnel surrounding rock fracture water
CN211230546U (en) * 2019-12-27 2020-08-11 中铁二院工程集团有限责任公司 Drainage type drainage system for karst tunnel

Cited By (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111794238A (en) * 2020-07-20 2020-10-20 中铁二院工程集团有限责任公司 Grouting structure for filling soluble crystals and construction method
CN111810234A (en) * 2020-07-20 2020-10-23 中铁二院工程集团有限责任公司 Tunnel water seepage and harmful gas discharge structure and semi-closed ice filling drilling construction method
CN111794238B (en) * 2020-07-20 2021-05-04 中铁二院工程集团有限责任公司 Grouting structure for filling soluble crystals and construction method
CN111810234B (en) * 2020-07-20 2021-06-29 中铁二院工程集团有限责任公司 Tunnel water seepage and harmful gas discharge structure and semi-closed ice filling drilling construction method
CN112145202A (en) * 2020-11-04 2020-12-29 中铁五局集团第五工程有限责任公司 Device for ensuring impervious strength of tunnel cast concrete and construction method
CN116005719A (en) * 2023-03-07 2023-04-25 中铁二院工程集团有限责任公司 Composite material miniature pipe gallery and drainage method thereof

Similar Documents

Publication Publication Date Title
CN104453913B (en) A kind of Shaft Stopes front pre-grouting method
CN111005760A (en) Drainage type drainage system for karst tunnel
CN109519220B (en) Grouting treatment method for broken water-rich section of diversion tunnel in karst area
CN103277120B (en) A kind of non-fully deeply freeze vertical thaw after water burst prevention and controls
CN105821830B (en) A kind of anatonosis siphon drainge system for hypotonicity slight slope
CN103758123B (en) The construction method of manually digging hole filling pile retaining wall lining
CN108661650B (en) Construction method for deep and large vertical shaft in water-rich rock-magma area
CN205172598U (en) Pipe curtain spouts a supporting construction soon
CN108547639B (en) Tunnel closes on the advanced same more conduit delamination pour slurry construction methods in hole of existing buildings
CN109593957B (en) Active extraction method for in-situ leaching of ionic rare earth ore
CN114233385B (en) Treatment method for mud-bursting water of inclined shaft
CN111810198A (en) Tunnel earth surface directional large-caliber deep hole grouting device and grouting method
CN107191188B (en) Bedrock section bad aquifer positioning and targeting grouting vertical shaft wall structure, construction device and construction method
CN110318410A (en) A kind of deep basal pit chance artesian water is prominent to gush decompression drought stress construction method
CN111852515A (en) Tunnel stratum pre-reinforcement comprehensive grouting method
CN113463670A (en) Water pumping and draining method and water pumping and draining structure for deep foundation pit bottom plate construction
CN104234726A (en) Internal dewatering and drainage construction method for tunnel passing through water-rich unconformable contact zone
CN108678753B (en) Reverse-slope tunnel construction method
CN105569051A (en) Foundation pit support system of sandy pebble boulder geological stratification and construction method
CN105926624A (en) Non-return type collecting hole grouting device and construction method thereof
CN104389634B (en) A kind of mine vertical shaft sieve well shaft wall structure and controlled trapping method thereof
CN105731978A (en) Grouting slurry for reinforcing tunnel face of jacking culvert of fine-sand layer and grouting method
CN108661652B (en) Reinforcing device and method for shield starting and receiving ends in mine tunnel
CN105274994B (en) Anti-suck sludge proof grouting process and grouting device in deep saturated sand
CN211230546U (en) Drainage type drainage system for karst tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination