CN111005548A - Construction method and system - Google Patents

Construction method and system Download PDF

Info

Publication number
CN111005548A
CN111005548A CN201911350857.5A CN201911350857A CN111005548A CN 111005548 A CN111005548 A CN 111005548A CN 201911350857 A CN201911350857 A CN 201911350857A CN 111005548 A CN111005548 A CN 111005548A
Authority
CN
China
Prior art keywords
construction
construction platform
platform
lifting
traction
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911350857.5A
Other languages
Chinese (zh)
Inventor
纪超超
梁佳尉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Mechanized Construction Group Co Ltd
Original Assignee
Shanghai Mechanized Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Mechanized Construction Group Co Ltd filed Critical Shanghai Mechanized Construction Group Co Ltd
Priority to CN201911350857.5A priority Critical patent/CN111005548A/en
Publication of CN111005548A publication Critical patent/CN111005548A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G3/30Mobile scaffolds; Scaffolds with mobile platforms suspended by flexible supporting elements, e.g. cables
    • E04G3/32Hoisting devices; Safety devices
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G3/00Scaffolds essentially supported by building constructions, e.g. adjustable in height
    • E04G3/28Mobile scaffolds; Scaffolds with mobile platforms
    • E04G2003/286Mobile scaffolds; Scaffolds with mobile platforms mobile vertically

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention provides a construction method and a construction system. The construction method comprises the following steps: building a construction platform, wherein the shape and the size of the construction platform are matched with the construction surface; and lifting the construction platform to an operation height through a lifting mechanism so as to construct the construction surface. The construction system includes: the construction platform is matched with the construction surface in shape and size; the lifting mechanism is used for lifting the construction platform to the working height. According to the construction platform, the construction platform with the shape and the size matched with the construction surface is built, and the construction platform is lifted to the working height by using the lifting mechanism, so that the construction of the construction surface of the whole concave position can be completed on one construction platform, and the problem of high-altitude operation of the concave position with a large area in the prior art can be solved.

Description

Construction method and system
Technical Field
The invention relates to the technical field of high-rise building construction, in particular to a construction method and a construction system.
Background
In the prior art, during the construction of high-rise buildings, a disc buckle type scaffold operating platform, an overhead crane or an overhead working hanging basket is usually used for carrying out overhead working.
The operation platform of the coil buckling type scaffold guarantees that each connection point is tightly placed in construction, meanwhile, the scaffold is supported in the same horizontal plane, and the scaffold is guaranteed to be evenly stressed. The coil-fastened scaffold has high bearing capacity, good bending resistance, pressure resistance and other performances, but cannot be constructed in a large area in the horizontal direction, has high requirement on the bearing capacity of a floor, and needs to be reinforced when necessary.
The high-altitude vehicle can be used for quickly installing a lifting device or a manned platform, functions of material lifting, hoisting, manned high-altitude operation and the like are realized, an interface is provided for quickly switching an expansion operation device and various working devices, and the high-altitude vehicle has the advantage of flexible operation. However, the danger coefficient of the high-altitude vehicle is relatively high, the height of the high-altitude vehicle is limited, the high-altitude vehicle cannot meet the requirement of high-rise installation, all plates cannot be installed due to the angle of the high-altitude vehicle, the requirement on floor load is high, and the high-altitude vehicle cannot adopt a large-tonnage high-altitude vehicle.
The aerial work hanging basket is simple in structure and easy to construct, but cannot be used for constructing all large-area areas, particularly concave positions.
Disclosure of Invention
The invention aims to provide a construction method and a construction system to solve the problem of large-area high-altitude operation at a concave position.
In order to solve the above technical problem, a first aspect of the present invention provides a construction method for recessed rail construction, including: building a construction platform, wherein the shape and the size of the construction platform are matched with the construction surface; and lifting the construction platform to an operation height through a lifting mechanism so as to construct the construction surface.
Optionally, the construction method of the construction platform includes: hinging a plurality of section steel beam beams and/or rigidly connecting the beam beams to form a section steel frame, wherein the shape and the size of the section steel frame are matched with the construction surface; respectively fixing a plurality of grids on the section steel frame to form a bearing surface on the section steel frame; the construction platform comprises the section steel frame and the grating.
Optionally, the construction method further includes: and leveling the construction platform when the construction platform is lifted for a set distance in the process of lifting the construction platform to the working height.
Optionally, after the construction platform is lifted to the working height, the construction method further includes: and arranging a fixing unit at the outer side of the construction platform, wherein the fixing unit is used for limiting the horizontal displacement of the construction platform.
Optionally, the lifting mechanism is a lifting mechanism, the lifting mechanism includes a traction portion, and the construction method further includes: and movably arranging the traction part on the construction surface, and vertically connecting one end of the traction part with the construction platform.
In order to solve the technical problem, a second aspect of the present invention provides a construction system for concave stop construction, including a construction platform and a lifting mechanism, wherein the shape and size of the construction platform are matched with the construction surface; the lifting mechanism is used for lifting the construction platform to the working height.
Optionally, the construction platform includes: a steel frame and a plurality of grids. The shape and the size of the profile steel frame are matched with the construction surface; the grating is fixed on the section steel frame, and the surfaces of all the gratings form a bearing surface.
Optionally, the lifting mechanism is a lifting mechanism, the lifting mechanism includes a guide part and a traction part, and the guide part is arranged on the construction surface; the traction part moves along the guide part and is divided into a first part and a second part which are connected through the guide part, the first part is vertically connected with the construction platform, and the second part is used for providing traction force.
Preferably, the lifting mechanism further comprises a drive part connected to the second part for providing power.
Optionally, the guide part, the traction part with the quantity of drive division is a plurality of, just the guide part the traction part with the drive division is the one-to-one setting, and is a plurality of the traction part with construction platform's tie point dispersion is connected.
Optionally, the lifting mechanism further comprises a controller for controlling the plurality of driving parts to operate simultaneously or individually.
Optionally, the driving part is a winch.
Optionally, the traction portion comprises a steel wire rope.
Optionally, a fixing unit is arranged on the outer side of the construction platform, and the fixing unit is used for limiting the horizontal displacement of the construction platform.
Preferably, the fixing unit is an angle steel.
Optionally, the construction platform includes a protection device, and the protection device is disposed at an edge position of the construction platform and used for providing safety protection.
According to the construction method and the construction system provided by the invention, the construction platform with the shape and the size matched with the construction surface is built, and the construction platform is lifted to the working height by using the lifting mechanism, so that the construction of the construction surface of the whole concave position can be completed on one construction platform, and the problem of high-altitude operation of the concave position with a large area in the prior art can be solved.
Furthermore, the construction platform can adopt a suspension lifting mode, so that the construction platform is vertically positioned right below a construction surface, and the construction at the position of the concave stop becomes convenient.
Drawings
FIG. 1 is a schematic illustration of a construction system in an operational state;
FIG. 2 is a schematic view of a grid structure;
FIG. 3 is a schematic structural view of a construction platform;
FIG. 4 is a schematic view of the connection of the grating and the section steel;
FIG. 5 is a schematic view of a first construction method;
FIG. 6 is a schematic view of a second construction method;
FIG. 7 is a schematic diagram of the controller connections;
FIG. 8 is a schematic view of a construction platform anchor point connection;
wherein the content of the first and second substances,
10-a building body; 11-construction surface; 20-construction of a platform; 30-a traction section (wire rope); 40-drive part (winding engine)
200-a grid; 201-carrying flat steel; 202-a cross bar; 210-section steel; 211-mounting clip-on clip; 212-mounting clip lower clip; 213-fixing screws;
21-section steel frame; 22-lifting points (lifting lugs); 23-fixed point (lifting lug);
12-a first via; 13-guide (fixed pulley); 14-floor level; 15-a second via; 16-a tripod; 17-chain
Detailed Description
The construction method and system of the present invention will be described in detail with reference to the accompanying drawings and specific embodiments. It is to be noted that the drawings are in a very simplified form and are not to precise scale, which is merely for the purpose of facilitating and distinctly claiming the embodiments of the present invention. Further, the structures illustrated in the drawings are often part of actual structures. In particular, the drawings may have different emphasis points and may sometimes be scaled differently.
Throughout the present specification, the connection of one element to another element includes not only a direct connection but also a mechanical connection and an electrical connection through other devices.
The embodiment provides a construction method, which is used for constructing a construction surface at a concave position and comprises the steps of constructing a construction platform, wherein the shape and the size of the construction platform are matched with those of the construction surface; and lifting the construction platform to an operation height through a lifting mechanism so as to construct the construction surface. In this embodiment, a ceiling with an isosceles trapezoid-shaped construction surface is taken as an example, as shown in fig. 1, the shape and size of the construction platform 20 are matched with those of the construction surface 11, and the construction platform 20 is lifted to an operation height by the lifting mechanism to construct the construction surface 11.
Further, the embodiment also provides a construction method of the construction platform 20, which includes that a plurality of section steel beam hinges and/or beam beams are rigidly connected to form a section steel frame, and the shape and size of the section steel frame are matched with the construction surface; respectively fixing a plurality of grids on the section steel frame to form a bearing surface on the section steel frame; the construction platform comprises the section steel frame and the grating.
Specifically, in this embodiment, a construction method of a grid is provided, as shown in fig. 2, the bearing flat steels 201 are erected laterally, and are sequentially arranged at equal intervals along the thickness direction (Y direction shown in fig. 2), the arrangement interval may be 30cm, one side (outer side in X direction shown in fig. 2) of the arranged bearing flat steels 201 is fixed by using another bearing flat steel 201, and the surface of the fixed bearing flat steel frame is a plane. The cross bars 202 are perpendicular to the length direction (along the Y direction shown in fig. 2) of the bearing flat steel 201, and are arranged at equal intervals along the length direction (along the X direction shown in fig. 2) of the bearing flat steel 201, the intervals may be 100cm, and the upper surface of the cross bars 202 is not higher than the upper surface of the bearing flat steel 201. In this way, the lattice 200 is formed by constructing the supporting flat bars 201 and the cross bars 202 in a matrix. Of course, in other embodiments, different intervals or materials may be selected for building the grating, and the strength of the grating needs to meet the bearing strength of the construction platform.
The manner of overlap between the sections 210 is known to those skilled in the art as beam-to-beam articulation and/or beam-to-beam stiffening. Fig. 3 is a schematic diagram of the construction platform 20 and the steel frame 21, the steel frame 21 should be constructed to meet the relevant industry standards, and this diagram is only used to illustrate the relationship between the steel frame and the construction platform.
After the profile steel frame 21 and the grating 200 are respectively constructed, the grating 200 needs to be fixed on the profile steel frame 21, and all surfaces of the grating 200 form a bearing surface. In order to facilitate the reuse of the construction platform and improve the detachable and reconfigurable capability of the construction platform, the installation clamp is preferably used for installation in the embodiment. As shown in FIG. 4, the grid 200 is placed on the section steel 210, a portion of the grid 200 should overlap the section steel 210, and a mounting clip upper clip 211 is placed on the upper portion of the grid 200, the mounting clip upper clip 211 being positioned such that a fixing screw 213 can pass through the grid 200 and the section steel 210 through a positioning hole of the mounting clip upper clip 211 and be coupled to a mounting clip lower clip 212 located at the lower portion of the section steel 210. And tightening the fixing screws 213 to tightly connect the grid 200 and the section steel 210 together. The entire steel framework 21 is lined with the grid 200 using this method. Of course, other means of fixing the grid, such as welding, may be used.
Preferably, in this embodiment, when the construction platform 20 is built, a plurality of lifting points 22, for example, 8 lifting points 22 distributed axisymmetrically, are provided on the construction platform 20, and the lifting points 22 may be lifting lugs, and are used for connecting the traction portion 30 to bear force during the lifting process. Should be according to construction platform characteristic evenly distributed when distributing the lifting point lug to make in subsequent lifting process can make construction platform level as far as, also make elevating system atress as far as even.
Preferably, in this embodiment, when the construction platform 20 is built, a plurality of fixing points 23, for example, 8 fixing points 23 distributed axisymmetrically, are further disposed on the construction platform 20, and the fixing points 23 may also be lifting lugs, and are used for being connected with a building main body, so that the construction platform can be fixed at a certain height, and meanwhile, the construction platform can be prevented from shaking. The distribution of the fixing points 23 should be reasonable, and the strength of the fixing points 23 should be capable of bearing the stress when the construction platform is suspended.
A schematic diagram of the distribution of the lifting points 22 and the fixing points 23 used in this embodiment is shown in fig. 3.
Preferably, this embodiment elevating system is hoist mechanism, hoist mechanism includes the traction part, will the traction part movably set up in the construction face, and will the one end of traction part with construction platform is perpendicular to be connected. In this embodiment, a steel wire rope is preferably used as the traction portion, and in other embodiments, a hinge or the like may also be used as the traction portion, which is not limited herein.
Furthermore, the lifting mechanism also comprises a guide part, and the guide part is arranged on the construction surface; the traction part moves along the guide part and is divided into a first part and a second part which are connected through the guide part, the first part is vertically connected with the construction platform, and the second part is used for providing traction force. The guide part in the embodiment is preferably a fixed pulley, and the steel wire rope is wound on the fixed pulley and is vertically connected with the construction platform. In other embodiments, rollers or the like may be used as the guide.
Still further, the lifting mechanism further comprises a driving part, and the driving part is connected with the second part and used for providing power. The driving unit in this embodiment is preferably a winch, and in other embodiments, a winch, a hoist, or the like may be used.
Specifically, the guide part, draw the portion with the quantity of drive division is a plurality of, just the guide part draw the portion with the drive division is the one-to-one setting, and is a plurality of draw the portion with construction platform's tie point dispersion is connected, so that construction platform keeps the level as far as possible in the lifting process.
In this embodiment, a fixed pulley, a wire rope, and a winch are taken as examples, and a one-to-one correspondence relationship between the guide portion, the traction portion, and the driving portion is specifically described. As shown in fig. 5 and 6, the fixed sheave 13 is disposed on the construction surface 11, the wire rope 30 passes through the fixed sheave 13, and the wire rope 30 is divided into a first portion 301 and a second portion 302 by the fixed sheave 13, wherein the first portion 301 is vertically connected to the construction platform 20, and the second portion 302 is connected to the hoisting machine 40.
Fig. 5 is a schematic diagram of a first construction method, as shown in the figure, a hole can be formed in a construction surface 11 to obtain a plurality of first through holes 12, the position projection of the first through holes 12 falls on the lifting point 22, a fixed pulley 13 is installed at the upper edge position of the first through holes 12, and a winch 40 is fixed on the same side of the fixed pulley 13. The wire rope 30 is passed through the first through hole 12 and wound around the fixed sheave 13. The wire rope 30 is divided into a first portion 301 and a second portion 302 connected through the fixed sheave 13, the first portion 301 is connected to the lifting lug at the lifting point 22, and the second portion 302 is connected to the winding machine 40. Since the first through hole 12 is located right above the lifting point 22, when lifting operation is performed, the first portion 301 of the steel wire rope 30 is in a vertical state, so that the construction platform is prevented from inclining due to traction lifting.
Fig. 6 is a schematic diagram of a second construction method, as shown in the figure, a plurality of fixed pulleys 13 are arranged at the lower part of a construction surface 11, and the positions of the fixed pulleys 13 correspond to lifting lugs at lifting points 22 on a construction platform 20 in a one-to-one manner, so that the projection of the positions of the fixed pulleys 13 falls on the lifting points 22. The hoist 40 is mounted on another floor 14, which floor 14 may be another floor or the ground of the building body. The wire rope 30 is wound on the fixed pulley 13, the wire rope 30 is divided into a first part 301 and a second part 302 through the fixed pulley 13, the first part 301 is connected to the lifting lug of the lifting point 22, and the second part 302 is connected to the winch 40. Since the fixed pulley 13 is located right above the lifting point 22, when lifting operation is performed, the second part of the steel wire rope 30 is in a vertical state, so that the construction platform is prevented from inclining due to traction lifting.
In this embodiment, the hoisting points 22 and the fixing points 23 are 8, for example, and the hoisting machines with the same number as the hoisting points 22, for example, 8, fixed pulleys used with the hoisting machines, for example, 8, and steel cables are matched. The number, types and connection manners of other related connection devices are well known to those skilled in the art and will not be described herein.
Since a plurality of winches are used in the embodiment, the models and parameter settings of the winches should be consistent to reduce the possibility of inclination of the construction platform during the ascending process.
Certainly, because the construction platform is bigger, the winches may be distributed at different positions, even a part of the winches are far away, in order to ensure that a plurality of winches work simultaneously and facilitate the operation of personnel, the lifting mechanism further comprises a controller, and the controller is used for controlling a plurality of driving parts to work simultaneously or independently. The controller is connected with all the winches 40. Furthermore, the controller can be used for numbering and identifying different windlasses, so that the operation and communication of personnel are facilitated. The connection diagram of the controller is shown in fig. 7.
And checking whether all the devices are properly connected, evacuating personnel on the platform and under the projection surface of the platform, and lifting the platform.
Further, in the process of lifting the construction platform to the working height, leveling the construction platform when lifting for a set distance.
This embodiment gives an example of leveling. Specifically, a controller master start switch is started to simultaneously start the hoist 40 for lifting operation. And when the construction platform 20 is lifted 100mm away from the ground, the elevation is measured at each lifting point 22, the lifting operation of a single winch is controlled through a single control switch of the controller, the construction platform 20 is leveled, and the height difference between each point is ensured to meet the requirement.
And starting the controller master starting switch again to lift the construction platform 20. And when the construction platform 20 is lifted 1m away from the ground, the elevation is measured, the construction platform 20 is leveled by the lifting operation of a single winch, and the elevation difference of each point is adjusted to be not more than 3 mm.
In the lifting process, the lifting is suspended every 1 meter, the elevation is measured, and after the elevation difference of each point is adjusted within 3mm, the lifting is continued for 1 meter to continue the measurement.
It should be noted that, in this embodiment, the requirement that the height difference of each point does not exceed 3mm is obtained by calculation. In other embodiments, the calculation is performed according to different actual requirements.
When the construction platform 20 is raised to a desired working height, the raising is stopped, so that construction work can be performed on the construction platform 20.
However, in general, in order to free the lifting mechanism and ensure the reliability of the bearing of the construction platform 20, the construction platform 20 needs to be connected with the main structure of the building. In this embodiment, the lifting lug at the fixing point 23 is connected to the building main body by using the chain 17 to meet the bearing requirement of the construction platform 20.
And stopping lifting when the construction platform 20 is lifted to a height higher than the required operation height, for example, stopping lifting at a position 30mm higher than the required operation height, and adjusting the elevations of all points to be close to consistency. The reason why the height of the construction platform 20 is higher than the required working height is two, one is to ensure that the chain 17 is in a free state when the chain 17 is connected with the fixed point 23, and the other is to ensure that the construction platform does not have sudden stress change when the stress of the steel wire rope is converted into the stress of the chain.
A number of chains 17 are prepared, corresponding to the number of fixing points 23, said chains 17 being of a uniform length so as to ensure that said construction platform 20 is level from the construction surface. One end of the chain 17 is connected with the construction surface 11, and the other end is connected with a lifting lug at a fixed point 23 on the construction platform 20. In this embodiment, as shown in fig. 8, a hole is first drilled in the construction surface 11 to obtain a plurality of second through holes 15, the position of the second through holes 15 is projected onto the fixing point 23, a tripod 16 is provided above the second through holes 15, the tripod 16 is used for pulling the chain 17, and the chain 17 is connected to the fixing point 23 through the second through holes 15.
After the connection is finished, a controller master start switch is started, so that the winches are started simultaneously, the descending operation is carried out, and the stress point of the construction platform 20 is transferred from the steel wire rope 30 to the chain 17 to be stressed. The operation of the hoist 40 is stopped when all the wire ropes 30 are in a slack state. And after all the equipment stops operating, disassembling equipment such as shackles, steel cables and the like at the lifting point 22.
Further, after the construction platform is lifted to the working height, the construction method further comprises the following steps: and arranging a fixing unit at the outer side of the construction platform, wherein the fixing unit is used for limiting the horizontal displacement of the construction platform.
For example, the construction platform 20 and the main structure may be welded by using angle steels at both side edges of the construction platform 20, or an ear plate may be welded to a web plate at the edge of the construction platform 20, holes may be punched in the ear plate and the angle steels, respectively, and the ear plate and the angle steels may be connected by bolts. This is not further enumerated here.
The embodiment also provides a construction system, the construction system is used for constructing a construction surface at a concave position, and fig. 1 is a schematic diagram of the construction system in a working state. As shown in fig. 1, the construction system includes: a construction platform and a lifting mechanism; the shape and the size of the construction platform are matched with those of the construction surface; the lifting mechanism is used for lifting the construction platform to the working height.
Further, the construction platform comprises: the shape and the size of the profile steel frame are matched with the construction surface; the grating is fixed on the section steel frame, and the surfaces of all the gratings form a bearing surface. The specific mounting method is as described above, and is not described herein again.
In this embodiment, the lifting mechanism is preferably a lifting mechanism, as shown in fig. 5 and 6, the lifting mechanism includes a guide part and a traction part, and the guide part is disposed on the construction surface; the traction part moves along the guide part and is divided into a first part and a second part which are connected through the guide part, the first part is vertically connected with the construction platform, and the second part is used for providing traction force. Optionally, the lifting mechanism further comprises a driving part, and the driving part is connected with the second part to provide power. As can be seen from the above, the guiding part may be a fixed pulley, the traction part may be a wire rope, and the driving part may be a winch.
Furthermore, the number of the guide parts, the traction parts and the driving parts is multiple, the guide parts, the traction parts and the driving parts are arranged in a one-to-one correspondence mode, and the traction parts are connected with the construction platform in a dispersed mode, so that the construction platform can be kept horizontal as far as possible in the lifting process.
In addition, the lifting mechanism further comprises a controller for controlling the plurality of driving parts to work simultaneously or separately.
Furthermore, a fixing unit is arranged on the outer side of the construction platform and used for limiting the horizontal displacement of the construction platform. Preferably, the fixing unit is an angle steel.
Still further, the construction platform comprises a protection device, and the protection device is arranged at the edge position of the construction platform and used for providing safety protection. For example, when the construction platform 20 is constructed, a sleeve can be welded to the outer side of the construction platform 20, and the shaped rail can be inserted into a circle of sleeve on the periphery. Or, after the construction platform 20 is suspended and fixed, the construction platform 20 and the passage in the floor are in the form of a scaffold, and the position close to the edge is sealed by adopting a fence. Or, the periphery of the feeding port is protected by a border, and the construction material is hung to a set position by the electric hoist and then is installed. The safety precautions described in this invention are for illustration only and are not limiting.
The above description is only for the purpose of describing the preferred embodiments of the present invention, and is not intended to limit the scope of the present invention, and any variations and modifications made by those skilled in the art based on the above disclosure are within the scope of the appended claims.

Claims (16)

1. A method of constructing a construction surface at a recessed portion, the method comprising:
building a construction platform, wherein the shape and the size of the construction platform are matched with the construction surface;
and lifting the construction platform to an operation height through a lifting mechanism so as to construct the construction surface.
2. The construction method according to claim 1, wherein the construction platform building method comprises:
hinging a plurality of section steel beam beams and/or rigidly connecting the beam beams to form a section steel frame, wherein the shape and the size of the section steel frame are matched with the construction surface;
respectively fixing a plurality of grids on the section steel frame to form a bearing surface on the section steel frame;
the construction platform comprises the section steel frame and the grating.
3. The construction method according to claim 1, further comprising:
and in the process of lifting the construction platform to the working height, leveling the construction platform when the construction platform is lifted for a set distance.
4. The construction method of claim 1, wherein after the construction platform is raised to the working height, the construction method further comprises:
and arranging a fixing unit at the outer side of the construction platform, wherein the fixing unit is used for limiting the horizontal displacement of the construction platform.
5. The construction method according to any one of claims 1 to 4, wherein the lifting mechanism is a lifting mechanism including a traction portion, and the construction method further comprises:
and movably arranging the traction part on the construction surface, and vertically connecting one end of the traction part with the construction platform.
6. A construction system for constructing a construction surface at a recessed stop location, the construction system comprising: a construction platform and a lifting mechanism, wherein,
the shape and the size of the construction platform are matched with those of the construction surface;
the lifting mechanism is used for lifting the construction platform to the working height.
7. The construction system of claim 6, wherein the construction platform comprises: a steel section frame and a plurality of grids,
the shape and the size of the profile steel frame are matched with the construction surface;
the grating is fixed on the section steel frame, and the surfaces of all the gratings form a bearing surface.
8. The construction system of claim 6, wherein the lifting mechanism is a lifting mechanism comprising a guide portion and a traction portion,
the guide part is arranged on the construction surface;
the traction part moves along the guide part and is divided into a first part and a second part which are connected through the guide part, the first part is vertically connected with the construction platform, and the second part is used for providing traction force.
9. The construction system according to claim 8, wherein the lifting mechanism further comprises a drive portion coupled to the second portion for providing power.
10. The construction system according to claim 9, wherein the number of the guide portion, the traction portion and the driving portion is plural, the guide portion, the traction portion and the driving portion are provided in one-to-one correspondence, and the plural traction portions are dispersedly connected to the connection points of the construction platform.
11. The construction system according to claim 10, wherein the lifting mechanism further comprises a controller for controlling the plurality of driving parts to operate simultaneously or individually.
12. The construction system according to claim 9, wherein the driving part is a hoist.
13. The construction system of claim 8, wherein the traction portion comprises a wire rope.
14. The construction system according to claim 6, wherein a fixing unit for limiting a horizontal displacement of the construction platform is provided at an outer side of the construction platform.
15. The construction system according to claim 14, wherein the fixing unit is an angle iron.
16. The construction system according to claim 6, wherein the construction platform comprises a guard device disposed at an edge location of the construction platform for providing safety protection.
CN201911350857.5A 2019-12-24 2019-12-24 Construction method and system Pending CN111005548A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911350857.5A CN111005548A (en) 2019-12-24 2019-12-24 Construction method and system

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911350857.5A CN111005548A (en) 2019-12-24 2019-12-24 Construction method and system

Publications (1)

Publication Number Publication Date
CN111005548A true CN111005548A (en) 2020-04-14

Family

ID=70116217

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911350857.5A Pending CN111005548A (en) 2019-12-24 2019-12-24 Construction method and system

Country Status (1)

Country Link
CN (1) CN111005548A (en)

Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2000223C2 (en) * 2006-09-08 2008-03-11 Doornbos Equipment B V Stabilization system for hanging baskets used for e.g. cleaning or painting walls, includes gripper device for securing to basket and engaging with wall
CN201221193Y (en) * 2008-06-17 2009-04-15 北京城建集团有限责任公司 High altitude packway ceiling construction operating platform
CN101476410A (en) * 2009-01-13 2009-07-08 杭州萧宏建设集团有限公司 Mounting and demounting method roof plate formwork support platform of concrete silo
CN203175023U (en) * 2013-04-23 2013-09-04 中国葛洲坝集团股份有限公司 Counter weight type cantilever hanging basket device
CN105386593A (en) * 2015-12-08 2016-03-09 上海市机械施工集团有限公司 Hanging-type operation platform and construction method
JP2019190263A (en) * 2018-04-21 2019-10-31 有限会社ケンテックシステムズ Work method for building outer surface

Patent Citations (6)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
NL2000223C2 (en) * 2006-09-08 2008-03-11 Doornbos Equipment B V Stabilization system for hanging baskets used for e.g. cleaning or painting walls, includes gripper device for securing to basket and engaging with wall
CN201221193Y (en) * 2008-06-17 2009-04-15 北京城建集团有限责任公司 High altitude packway ceiling construction operating platform
CN101476410A (en) * 2009-01-13 2009-07-08 杭州萧宏建设集团有限公司 Mounting and demounting method roof plate formwork support platform of concrete silo
CN203175023U (en) * 2013-04-23 2013-09-04 中国葛洲坝集团股份有限公司 Counter weight type cantilever hanging basket device
CN105386593A (en) * 2015-12-08 2016-03-09 上海市机械施工集团有限公司 Hanging-type operation platform and construction method
JP2019190263A (en) * 2018-04-21 2019-10-31 有限会社ケンテックシステムズ Work method for building outer surface

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
国振喜: "《建筑施工效率手册》", 31 October 1986 *

Similar Documents

Publication Publication Date Title
JP2006233486A (en) Traversing work device and work method thereby
CN106241618A (en) A kind of curtain wall profiles boom hoisting
CN111021744A (en) Curtain wall installation system and application construction method thereof
CN112942661B (en) Construction method of stay cable with flexible cable net boundary
JP4521024B2 (en) Reinforcing bar assembly method and reinforcing bar assembly jig for reinforcing structure of high structure
KR20050095600A (en) Integrated support for elevator machine, sheaves and terminations
CN110761193A (en) Cable tower construction equipment
JP5589183B2 (en) Cylindrical structure scaffolding apparatus and moving method thereof
CN112252741A (en) Full-rail crane for super high-rise unit curtain wall and installation and use method thereof
CN211113216U (en) Cable tower construction equipment
CN111005548A (en) Construction method and system
CN111411624B (en) Hoisting method for reinforcement cage of underground continuous wall in height-limited area
CN111071925B (en) Hoisting sheave platform for installing derrick crane and crane installation method
CN110040632A (en) A kind of segmental hoisting construction method of large span section steel beam
CN211974386U (en) Curtain wall mounting system
CN212532065U (en) Gantry crane capable of being used in different height difference places
JP2013216483A (en) Lifting height extending construction method for elevator for construction
CN113789725B (en) Suspension bridge construction method and lifting device
CN214062384U (en) Full-rail crane for super high-rise unit curtain wall
CN219931660U (en) Steel construction wallboard installation auxiliary assembly
CN220228131U (en) High-altitude pavement
KR20190012506A (en) Apparatus for installing a machine room less elevator rail
CN111470407A (en) Weighing rod type hoisting assembly, hoisting equipment and hoisting method
CN214463117U (en) Hydraulic lifting and hoisting equipment for chimney steel platform
CN112299223B (en) Hoisting tool and hoisting method for water stop

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200414