CN110994472A - 一种电气线管穿引线的方法 - Google Patents
一种电气线管穿引线的方法 Download PDFInfo
- Publication number
- CN110994472A CN110994472A CN201911300956.2A CN201911300956A CN110994472A CN 110994472 A CN110994472 A CN 110994472A CN 201911300956 A CN201911300956 A CN 201911300956A CN 110994472 A CN110994472 A CN 110994472A
- Authority
- CN
- China
- Prior art keywords
- pipe
- suction
- embedded
- lead
- suction pump
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- H—ELECTRICITY
- H02—GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
- H02G—INSTALLATION OF ELECTRIC CABLES OR LINES, OR OF COMBINED OPTICAL AND ELECTRIC CABLES OR LINES
- H02G1/00—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines
- H02G1/06—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle
- H02G1/08—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling
- H02G1/086—Methods or apparatus specially adapted for installing, maintaining, repairing or dismantling electric cables or lines for laying cables, e.g. laying apparatus on vehicle through tubing or conduit, e.g. rod or draw wire for pushing or pulling using fluid as pulling means, e.g. liquid, pressurised gas or suction means
Landscapes
- Electric Cable Installation (AREA)
Abstract
本发明提供了一种电气线管穿引线的方法,在预埋线管的一端利用吸力泵吸气,另一端放入引线,开启吸力泵后,在气流的推动下,引线会被推动并延伸到有吸力泵的一端,相对于现有技术中用铁丝拉动引线的穿引线方法,本发明的方法穿线方便快捷,施工人员可简单、快速地将引线穿过预埋在墙体或底板内的电气线管,省时省力,节约人工成本,缩短工期,同时无需消耗铁丝,节约资源。
Description
技术领域
本发明涉及电气施工领域,尤其是涉及一种电气线管穿引线的方法。
背景技术
在水电安装中,一直以来,电气管道穿引线是水电施工人员的一项难题,电气管道穿引线的传统工艺是将红绳绑在铁丝上,在管道的始端不停的转动铁丝,利用扭力不断旋转从而穿过线管,然后再取出铁丝并将红绳固定在埋在墙体或地板内的线管的两端,该穿引线的难度高,穿线耗时长,特别是对于长度较大、转弯较多的线管,需要耗费较多的人力成本,工作人员劳动强度大,这种方法不仅费时、费力,而且还消耗了铁丝。
发明内容
本发明的目的在于克服上述现有技术之不足,提供一种电气线管穿引线的方法,通过该方法,施工人员可简单、快速地将引线穿过预埋在墙体或底板内的电气线管,施工方便快捷,解决现有技术中存在的不仅费时、费力,而且还消耗了铁丝的技术问题。
本发明的目的通过以下技术方案予以实现:
一种电气线管穿引线的方法,包括以下步骤:
S1.在靠近预埋线管其中一端的地方设置吸力泵,将吸力泵的吸气管与所述预埋线管的一端连通;
S2.开启吸力泵,在所述预埋线管的远离所述吸力泵的一端放入引线的一端,所述引线的另一端固定于所述预埋线管外,利用吸力泵产生的吸力吸取引线的一端,其中,所述引线的长度大于所述预埋线管的长度;
S3.所述引线的一端完全穿过所述预埋线管后,将与所述预埋线管连接的吸气管拆下。
进一步的,在步骤S1中,所述吸气管与所述预埋线管通过吸嘴连接;其中,所述吸嘴包括一端连接有弯头的直线管,所述直线管的管径比所述预埋线管小一号尺寸,所述直线管可插入所述预埋线管内与所述预埋线管连通;所述吸气管与弯头远离所述直线管的一端连接。
进一步的,所述吸气管与所述吸嘴之间通过变截面管连接,所述变截面管两端的连接处包裹胶带进行密封处理;在进行步骤S1之前,先将所述吸嘴连接固定到所述吸气管上,在进行步骤S1时,将所述吸嘴上的直线管的一端插进所述预埋线管的一端内进行连通。
进一步的,在进行步骤S1之前,在将吸力泵的吸气管与所述吸嘴连接完成后,开启吸力泵,用人手靠近所述变截面管两端的接头处进行气密性检测,若人手感觉无明显空气流动,则表明气密性良好;若人手感觉明显空气流动,则表明气密性差,需进一步加强密封处理。
进一步的,在步骤S2中,开启吸力泵后,等待吸力泵运行一定时间后再将引线放入预埋线管中。
进一步的,对于两端高度不同的预埋线管,在步骤S1中,将吸力泵设置在靠近预埋线管较低的一端,在步骤S2中,从预埋线管较高的一端放入所述引线。
进一步的,步骤S2中放入的所述引线为塑料捆扎绳。
本发明具有如下有益效果:本发明提供了一种电气线管穿引线的方法,在预埋线管的一端利用吸力泵吸气,另一端放入引线,开启吸力泵后,在气流的推动下,引线会被推动并延伸到有吸力泵的一端,相对于现有技术中用铁丝拉动引线的穿引线方法,本发明的方法穿线方便快捷,施工人员可简单、快速地将引线穿过预埋在墙体或底板内的电气线管,省时省力,节约人工成本,缩短工期,同时无需消耗铁丝,节约资源。
附图说明
图1为本发明在穿引线的过程中吸嘴与预埋线管连通的结构示意图;
图2为本发明的引线穿过电气线管的结构示意图。
图中具体结构说明:1墙体、2预埋线管、3吸嘴、4吸气管、5引线。
具体实施方式
下面结合附图给出的实施例对本发明作进一步详细说明。
一种电气线管穿引线的方法,包括以下步骤:
S1.施工准备:准备吸力泵、塑料捆扎绳及配电箱,配电箱中的电源为三相电源,且该配电箱内配有漏电保护器;
S2.吸力泵的调试:吸力泵在工作时可能会产生较大的震动,在工作时安放平稳,在准备穿线前应将电力设施准备好,为保护工人在施工中的安全,做好保护措施,将装有三相电源与漏电保护器的配电箱检查并放置到位;
S3.安装吸嘴:将吸嘴3与吸力泵的吸气管4通过变截面管紧密连接,并在连接处用胶带重叠包裹,确保接头处包裹严实,满足气密性要求,其中,所述吸嘴包括一端连接有弯头的直线管,所述直线管的管径比所述预埋线管小一号尺寸,因此,所述直线管可插入所述预埋线管2内与所述预埋线管2连通,如图1所示;所述吸气管4与弯头远离所述直线管的一端连接;安装好一次吸嘴3后,带有吸嘴3的吸力泵可以重复使用为多个需要穿引线的预埋线管进行穿引线施工,工作时只需直接将吸嘴插入预埋线管的一端即可,该过程方便快捷,大大降低了施工人员的工作压力以及施工时长;
S4.气密性检查:在将吸力泵的吸气管4与所述吸嘴3连接完成后,开启吸力泵,用人手靠近所述变截面管两端的接头处进行气密性检测,若人手感觉无明显空气流动,则表明气密性良好;若人手感觉明显空气流动,则表明气密性差,需进一步加强密封处理;气密性检查是关系到此次施工能否成功的关键,接头处漏气可能会直接导致此次施工失败,因此,通过检查吸嘴3与吸气管4连接的气密性,能够保证施工过程中不会出现较大漏气,保证施工顺利进行;
S5.预埋线管的清理:将连接有吸嘴3的吸力泵放置在靠近预埋线管2一端的墙体外,如果是两端高度不同的预埋线管2,则将吸力泵设置在靠近预埋线管2较低的一端;将吸嘴3插入到预埋线管2内进行连通,开启吸力泵,利用吸力泵吸走预埋线管2内的水,灰土,石子等一些小型垃圾,以保证后期穿引线5的过程能够更加顺畅;因此,除了完成穿引线的工作外,利用本方法还能对预埋线管2内进行清理工作,以此也便于后期穿拉电线的施工;
S6.穿引线:清理完预埋线管2后,保持吸力泵开启,以塑料捆扎绳作为引线5,在所述预埋线管2的远离所述吸力泵的一端放入引线5,所述引线5的另一端固定于所述预埋线管2外,利用吸力泵产生的吸力吸取引线5的一端,其中,所述引线5的长度大于所述预埋线管2的长度;
S7.固定引线:所述引线5的一端完全穿过所述预埋线管2后,如图2所示,将与所述预埋线管2连接的吸嘴3拆下,同时将引线的两端分别固定在预埋线管2外两端,以备后续穿拉电线使用。
相对于现有技术中用铁丝拉动引线的穿引线方法,本发明的方法穿线方便快捷,施工人员可简单、快速地将引线穿过预埋在墙体或底板内的电气线管,省时省力,节约人工成本,缩短工期,同时无需消耗铁丝,节约资源。
以上所述者,仅为本发明的较佳实施例而已,当不能以此限定本发明实施的范围,即大凡依本发明申请专利范围及发明说明内容所作的简单的等效变化与修饰,皆仍属本发明专利涵盖的范围内。
Claims (7)
1.一种电气线管穿引线的方法,其特征在于,包括以下步骤:
S1.在靠近预埋线管其中一端的地方设置吸力泵,将吸力泵的吸气管与所述预埋线管的一端连通;
S2.开启吸力泵,在所述预埋线管的远离所述吸力泵的一端放入引线的一端,所述引线的另一端固定于所述预埋线管外,利用吸力泵产生的吸力吸取引线的一端,其中,所述引线的长度大于所述预埋线管的长度;
S3.所述引线的一端完全穿过所述预埋线管后,将与所述预埋线管连接的吸气管拆下。
2.如权利要求1所述的一种电气线管穿引线的方法,其特征在于:在步骤S1中,所述吸气管与所述预埋线管通过吸嘴连接;其中,所述吸嘴包括一端连接有弯头的直线管,所述直线管的管径比所述预埋线管小一号尺寸,所述直线管可插入所述预埋线管内与所述预埋线管连通;所述吸气管与弯头远离所述直线管的一端连接。
3.如权利要求2所述的一种电气线管穿引线的方法,其特征在于:所述吸气管与所述吸嘴之间通过变截面管连接,所述变截面管两端的连接处包裹胶带进行密封处理;在进行步骤S1之前,先将所述吸嘴连接固定到所述吸气管上,在进行步骤S1时,将所述吸嘴上的直线管的一端插进所述预埋线管的一端内进行连通。
4.如权利要求3所述的一种电气线管穿引线的方法,其特征在于:在进行步骤S1之前,在将吸力泵的吸气管与所述吸嘴连接完成后,开启吸力泵,用人手靠近所述变截面管两端的接头处进行气密性检测,若人手感觉无明显空气流动,则表明气密性良好;若人手感觉明显空气流动,则表明气密性差,需进一步加强密封处理。
5.如权利要求3所述的一种电气线管穿引线的方法,其特征在于:在步骤S2中,开启吸力泵后,等待吸力泵运行一定时间后再将引线放入预埋线管中。
6.如权利要求1所述的一种电气线管穿引线的方法,其特征在于:对于两端高度不同的预埋线管,在步骤S1中,将吸力泵设置在靠近预埋线管较低的一端,在步骤S2中,从预埋线管较高的一端放入所述引线。
7.如权利要求1所述的一种电气线管穿引线的方法,其特征在于:步骤S2中放入的所述引线为塑料捆扎绳。
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911300956.2A CN110994472A (zh) | 2019-12-17 | 2019-12-17 | 一种电气线管穿引线的方法 |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911300956.2A CN110994472A (zh) | 2019-12-17 | 2019-12-17 | 一种电气线管穿引线的方法 |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110994472A true CN110994472A (zh) | 2020-04-10 |
Family
ID=70094690
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911300956.2A Pending CN110994472A (zh) | 2019-12-17 | 2019-12-17 | 一种电气线管穿引线的方法 |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110994472A (zh) |
Cited By (1)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113140984A (zh) * | 2021-04-07 | 2021-07-20 | 中国电建集团河南工程有限公司 | 山地风电工程中风机基础预埋电缆管的施工工法 |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4953828A (en) * | 1987-11-20 | 1990-09-04 | Baldecchi Sauro S | Apparatus for practicing a pneumatic suction process permitting drawing cables through sheaths |
WO2005018067A1 (en) * | 2003-08-13 | 2005-02-24 | John Michael Holtzhausen | A conduit threading device and method |
US20050109518A1 (en) * | 2003-11-18 | 2005-05-26 | Blacklaw David W. | Fiber optic deployment apparatus and method |
GB2522230A (en) * | 2014-01-17 | 2015-07-22 | Deflux Holdings Ltd | Method and apparatus for removing a cable core from a cable sheath |
CN105870842A (zh) * | 2016-04-19 | 2016-08-17 | 山西五建集团有限公司 | 空气负压扫管穿线方法 |
CN105896399A (zh) * | 2014-12-18 | 2016-08-24 | 冯新年 | 管道穿带线专用机 |
CN106329408A (zh) * | 2016-08-31 | 2017-01-11 | 中国冶集团有限公司 | 一种电气线管穿引线装置及其穿引线方法 |
CN107240892A (zh) * | 2017-07-27 | 2017-10-10 | 中冶天工集团有限公司 | 一种利用负压快速穿线的方法 |
CN207004951U (zh) * | 2017-06-06 | 2018-02-13 | 王显亮 | 一种真空负压水泵 |
CN207651939U (zh) * | 2017-12-06 | 2018-07-24 | 中电建建筑集团有限公司 | 一种负压吸附式管线穿装系统 |
CN110233447A (zh) * | 2019-07-22 | 2019-09-13 | 广东电网有限责任公司 | 一种电力配网线路施工布线穿线器 |
-
2019
- 2019-12-17 CN CN201911300956.2A patent/CN110994472A/zh active Pending
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
US4953828A (en) * | 1987-11-20 | 1990-09-04 | Baldecchi Sauro S | Apparatus for practicing a pneumatic suction process permitting drawing cables through sheaths |
WO2005018067A1 (en) * | 2003-08-13 | 2005-02-24 | John Michael Holtzhausen | A conduit threading device and method |
US20050109518A1 (en) * | 2003-11-18 | 2005-05-26 | Blacklaw David W. | Fiber optic deployment apparatus and method |
GB2522230A (en) * | 2014-01-17 | 2015-07-22 | Deflux Holdings Ltd | Method and apparatus for removing a cable core from a cable sheath |
CN105896399A (zh) * | 2014-12-18 | 2016-08-24 | 冯新年 | 管道穿带线专用机 |
CN105870842A (zh) * | 2016-04-19 | 2016-08-17 | 山西五建集团有限公司 | 空气负压扫管穿线方法 |
CN106329408A (zh) * | 2016-08-31 | 2017-01-11 | 中国冶集团有限公司 | 一种电气线管穿引线装置及其穿引线方法 |
CN207004951U (zh) * | 2017-06-06 | 2018-02-13 | 王显亮 | 一种真空负压水泵 |
CN107240892A (zh) * | 2017-07-27 | 2017-10-10 | 中冶天工集团有限公司 | 一种利用负压快速穿线的方法 |
CN207651939U (zh) * | 2017-12-06 | 2018-07-24 | 中电建建筑集团有限公司 | 一种负压吸附式管线穿装系统 |
CN110233447A (zh) * | 2019-07-22 | 2019-09-13 | 广东电网有限责任公司 | 一种电力配网线路施工布线穿线器 |
Cited By (2)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN113140984A (zh) * | 2021-04-07 | 2021-07-20 | 中国电建集团河南工程有限公司 | 山地风电工程中风机基础预埋电缆管的施工工法 |
CN113140984B (zh) * | 2021-04-07 | 2022-04-19 | 中国电建集团河南工程有限公司 | 山地风电工程中风机基础预埋电缆管的施工工法 |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN206669127U (zh) | 水电一体工程集成管 | |
CN110994472A (zh) | 一种电气线管穿引线的方法 | |
CN204300520U (zh) | 一种电缆穿墙套管结构 | |
CN104659712A (zh) | 一种电气线路管道铺设方法 | |
CN207651939U (zh) | 一种负压吸附式管线穿装系统 | |
CN206918505U (zh) | 万能sf6充气管路连接装置 | |
CN207819344U (zh) | 燃气轮机动力装置压裂车及其电缆布线结构 | |
CN204962150U (zh) | 一种泄漏保护装置 | |
JP2015066718A (ja) | 排水管の補修装置及び補修方法 | |
CN207215601U (zh) | 高压管汇的压力测试装置 | |
KR100904384B1 (ko) | 변전소의 송배전 고압케이블 연결관 이음장치 | |
CN202065607U (zh) | 磁力组合式管道带压堵漏器 | |
CN103383027A (zh) | 一种小型管道对接器 | |
CN205583561U (zh) | 一种压缩机组适用的电缆桥架 | |
CN207195873U (zh) | 一种加油站管道双承插连接件 | |
CN204668893U (zh) | 膨胀堵塞 | |
CN205535056U (zh) | 一种充气连接装置 | |
CN207559475U (zh) | 一种密封性能强的建筑电气钢导管对口连接机构 | |
CN204470765U (zh) | 仪表管焊接充氩装置 | |
CN201449313U (zh) | 试水装置 | |
CN114910224B (zh) | 一种土木建设用仪器测试系统 | |
CN203215154U (zh) | 镀膜机用的水路接头机构 | |
JP4950355B1 (ja) | 分水栓施工後の漏水検査方法及びそれを実施するための漏水検査装置 | |
CN204387555U (zh) | 用于分体式空调器系统压力测试的辅助装置 | |
CN108151128A (zh) | 直热式空气源地板辐射供暖系统施工方法 |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
RJ01 | Rejection of invention patent application after publication | ||
RJ01 | Rejection of invention patent application after publication |