CN110991670A - Power cable management method - Google Patents

Power cable management method Download PDF

Info

Publication number
CN110991670A
CN110991670A CN201911211104.6A CN201911211104A CN110991670A CN 110991670 A CN110991670 A CN 110991670A CN 201911211104 A CN201911211104 A CN 201911211104A CN 110991670 A CN110991670 A CN 110991670A
Authority
CN
China
Prior art keywords
cable
management
channel
dimensional
data
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911211104.6A
Other languages
Chinese (zh)
Inventor
周文俊
张�浩
刘燕平
裘立峰
覃喜
张慧锋
麻潇波
朱梦慧
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Zhejiang Huayun Electric Power Engineering Design Consulting Co
Original Assignee
Zhejiang Huayun Electric Power Engineering Design Consulting Co
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Zhejiang Huayun Electric Power Engineering Design Consulting Co filed Critical Zhejiang Huayun Electric Power Engineering Design Consulting Co
Priority to CN201911211104.6A priority Critical patent/CN110991670A/en
Publication of CN110991670A publication Critical patent/CN110991670A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/20Administration of product repair or maintenance
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0639Performance analysis of employees; Performance analysis of enterprise or organisation operations
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Information and communication technology [ICT] specially adapted for implementation of business processes of specific business sectors, e.g. utilities or tourism
    • G06Q50/06Energy or water supply
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects

Landscapes

  • Business, Economics & Management (AREA)
  • Engineering & Computer Science (AREA)
  • Human Resources & Organizations (AREA)
  • Strategic Management (AREA)
  • Economics (AREA)
  • Physics & Mathematics (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Theoretical Computer Science (AREA)
  • General Physics & Mathematics (AREA)
  • Marketing (AREA)
  • General Business, Economics & Management (AREA)
  • Tourism & Hospitality (AREA)
  • Quality & Reliability (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Development Economics (AREA)
  • Health & Medical Sciences (AREA)
  • Game Theory and Decision Science (AREA)
  • Data Mining & Analysis (AREA)
  • Primary Health Care (AREA)
  • Computer Graphics (AREA)
  • Geometry (AREA)
  • Software Systems (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention belongs to the technical field of power cable construction and later-stage operation and maintenance management, and particularly relates to a power cable management method. Aiming at the defect that the existing two-dimensional power cable management system cannot meet visualization and refinement requirements, the power cable management method comprises the following steps of S1, accurately positioning a cable working well, accessory facilities, a cable channel and a cable track by a three-dimensional laser scanning technology to form three-dimensional data, and forming a three-dimensional simulation informatization platform of the power cable management system; and S2, managing the power cable management system through the whole life cycle of the guide project. The power cable management method has the beneficial effects that: the three-dimensional simulation is adopted to fuse all the specialties into the same three-dimensional system, so that information sharing is realized, communication barriers among all the specialties are broken, cooperative follow-up is realized, a convenient communication platform is provided for power cable management, and the realization of projects is promoted.

Description

Power cable management method
Technical Field
The invention belongs to the technical field of power cable construction and later-stage operation and maintenance management, and particularly relates to a power cable management method.
Background
With the increasing demand for fine design in practical projects, the power cable management system is required to be visualized and refined more reliably. In traditional two-dimensional design, along with the design progressively deepening, each professional design follows up respectively, can not reach fine cooperative relation to lead to the appearance of design change, after the drawing takes place the change, can produce the waste of manpower, material resources, financial resources that a series of derived, two-dimensional drawing mode has not satisfied the actual demand past. Therefore, in order to strengthen lean management of power transmission major, deepen standardized cable line construction work, improve the safe operation level of the cable line, realize a rail connection intelligent operation and inspection control mode, and push full force to the intelligent operation and inspection innovation work of a power grid, the three-dimensional informatization simulation technology gradually becomes a new development direction.
The three-dimensional informatization simulation technology can build a brand-new data sharing platform for the management of the cable engineering in the construction stage and the management of the operation, maintenance and overhaul stage after operation. The application of the technology can avoid the shortage of management informatization level caused by the lack or inaccuracy of basic data, effectively forms a modern management mode of digitization, visualization and informatization, and is vital to the realization of intelligent management and control of power cables and the promotion of intelligent innovation development of power grids. However, in the field of power cables, the development and application of three-dimensional informatization simulation technology are still lagged behind.
Disclosure of Invention
Aiming at the defect that the conventional two-dimensional power cable management system cannot meet visualization and refinement requirements, the invention provides a power cable management method, and the construction, operation and maintenance of a power cable are better realized by constructing a three-dimensional information platform.
In order to achieve the purpose, the invention adopts the following technical scheme: a power cable management method, the method comprising the steps of:
s1, accurately positioning a cable working well, an accessory facility, a cable channel and a cable track through a three-dimensional laser scanning technology to form three-dimensional data, simultaneously constructing an electronic coding identification system of equipment, establishing a three-dimensional model of the cable channel and an equipment basic data standardized database, forming a three-dimensional simulation informatization platform of the power cable management system, and realizing data interaction with a GIS (geographic information system) and a PMS (permanent magnet system);
and S2, the power cable management system runs through a guide project full life cycle management, the project full life cycle management is divided into two parts, namely cable project construction stage management and operation and maintenance after commissioning maintenance stage management, basic data management of equipment and channels is taken as a core, various working standard operation steps are standardized, engineering stage information, a typical defect and hidden danger elimination control scheme and maintenance test business processing work are standardized and designed, and a transportation and inspection unit is assisted to guide the development of standardized cable full life cycle management work.
The power cable management method of the invention comprises the following steps: compared with the traditional two-dimensional design, each professional design follows up respectively, and a good collaborative relationship cannot be achieved, so that design change occurs, and after a drawing is changed, a series of derived wastes of manpower, material resources and financial resources are generated. GIS is a geographic information system. The PMS is a production management system.
Furthermore, in the engineering construction stage management, a standardized technical parameter and process standard database is established, engineering process and equipment parameter standards are standardized, engineering construction defects are found in time, and the intrinsic safety level of equipment is improved.
Further, in the engineering construction stage management, the power cable management controls the basic data in multiple dimensions, the whole process of channel resources, three-dimensional display, quick positioning, external-break-prevention, fire-prevention, disaster-prevention and reduction functions and auxiliary engineering acceptance.
Further, the basic data multidimensional application management means: the PMS system cable and channel resource information is deeply applied, the cable and channel resource scale, the channel and working well change trend and hidden danger defects of each region are displayed in a multi-dimensional mode, and abnormal data alarming of the cable and the channel is achieved, so that lean management of the cable and the channel resources is achieved; information resources are mutually checked through any dimension of the cable name, the cable channel and the road, multi-dimensional information correlation analysis of the cable body, the joint, the channel and the environment is realized, and support is provided for cable planning and field intersection.
Further, the whole process management of channel resources refers to: the method comprises the steps that information of a starting well and an ending well is set, and the existing channel and the channel to be built are displayed graphically according to the channel type, the channel utilization rate, the channel material and the channel size related information, so that a reference basis is provided for a newly added cable path design scheme, and optimal planning of a cable path is realized; the inquiry of the channel resources for the cable is supported, a standard cable channel resource application, approval, reservation and occupation mechanism is established, the cable resource approval process is standardized, the lean management and control of the whole process of the use of the cable channel resources are realized, the nonstandard occupation of the channel resources is avoided, and the maximization of the utilization of the channel resources is realized.
Further, three-dimensional display management means: the underground cable and the channel are consulted and browsed in a panoramic simulation mode by adopting a three-dimensional informatization simulation technology, so that the digital, visualized and realistic management of the cable and channel basic data is realized; meanwhile, when the design requirements and the projects are changed, a collision test method is adopted for the changed areas through a three-dimensional informatization simulation technology, and potential problem hidden dangers are found and solved in advance; aiming at the ground excavation problem frequently occurring in the underground power grid management process, the three-dimensional information simulation technology provides ground excavation simulation of any region, the excavation depth and the boundary range are set, the three-dimensional terrain automatically collapses, the distribution condition of the underground power grid is exposed, and decision support is provided for construction.
Further, the fast positioning management means: the transmission and distribution operation personnel utilize the handheld mobile operation terminal to realize the real-time access to the accurate positioning and three-dimensional cable data of the cable line, call the latest state data of the cable line at any time, realize the inspection tour and the defect elimination management of the cable channel and the cable line, improve the daily operation maintenance efficiency of the cable, and promote the health management level of the cable channel.
Further, the management of functions of external damage prevention, fire prevention, disaster prevention and disaster reduction refers to: aiming at the current situations that construction points along a cable channel are diversified and wide, the cable channel is relatively isolated and dispersed, temporary construction is more at night, and operation and maintenance strength is relatively weak, accurate cable burial depth data, relative position relation with other municipal pipelines and pipe hole fireproof blocking conditions are provided based on three-dimensional results, and basic information is provided for channel hidden danger analysis and channel hidden danger coping strategy anti-external damage measure formulation; integrating big data resources by using a positioning and early warning positioning device for preventing external damage and an external damage video monitoring device, and establishing a cable external damage prevention control platform; meanwhile, the on-line monitoring device arranged on the power cable and the channel is used for displaying the running state of the line in real time, setting a data abnormity warning function and sending warning information according to the severity level.
Further, the auxiliary project acceptance management means: high-precision point cloud data of an underground comprehensive pipe gallery, an electric power tunnel, a cable trench and a cable well cable channel are acquired based on three-dimensional laser scanning, the underground facility scene is visualized and measurable, and the underground facility scene is superposed and compared with three-dimensional BIM design data and two-dimensional CAD design data, so that the evaluation of the construction quality of the power cable concealed project is realized.
Furthermore, in equipment operation stage management, building a covering operation and maintenance management, state management and live detection management function module, and combining GIS two-dimensional digital geographic information display to realize full-period closed-loop management of cable and channel operation and inspection processes; establishing a standardized data standard system, uniformly accessing partial discharge detection, an intelligent grounding box, optical fiber temperature measurement, video monitoring, an intelligent well cover and an intelligent inspection robot monitoring system to a lean management platform for centralized monitoring, and comprehensively analyzing and utilizing monitoring data; based on a GIS two-dimensional geographic information system, the RFID electronic tag is in butt joint with the intelligent inspection terminal, the running state, the monitoring value and the position information of monitoring equipment are mastered in real time, and the alarm information of monitoring points of abnormal equipment on site is automatically pushed; through a three-dimensional virtual reality modeling technology, the functions of vertical/horizontal clear distance measurement, channel section display, simulated excavation analysis and intelligent planning line selection are realized in a three-dimensional field of view, and the deep excavation application level of basic data of the urban underground cable and peripheral pipelines thereof is improved.
Furthermore, the equipment operation stage management comprises five management modules of emergency repair plans, risk evaluation and insulation evaluation, intelligent data analysis, modular online monitoring and intensive environment deployment; emergency repair plan management means: the method comprises the steps that electricity simulates engineering first-aid repair drilling based on a three-dimensional virtual reality scene, an emergency first-aid repair plan is customized, and the site first-aid repair implementation efficiency and the first-aid repair success rate are greatly improved through a precise positioning system and the first-aid repair plan; the risk evaluation and insulation evaluation management means: based on the real-time data of the running state of the field equipment, the equipment ledger and the on-site overhaul and repair conditions, and in combination with a cable professional typical information library, a risk assessment and insulation evaluation system based on big data is established to realize the state assessment of the cable line; the intelligent data analysis management means that: establishing a technical standard and installation process standard database aiming at different manufacturer models, intelligently assisting in judging the installation process result and simultaneously giving out standardized process requirements; equipment abnormality is timely found through transverse and longitudinal comparison calculation; a multidimensional cross module data analysis mode is applied to realize automatic study and judgment of the system and assist in generating management decisions; the modularized online monitoring management means that: by developing a modular online monitoring system and a standardized data standard system, the traditional system operated by multiple independent manufacturers is integrated in a centralized manner, and a technical specification and a solution are provided for the access of subsequent monitoring equipment of multiple manufacturers; intensive environment deployment management refers to: the design principle of uniform deployment and reinforced integration is adopted, the boundary division and cooperation intercommunication among the modules are fully considered, and the production work benefit of a cable transportation and inspection department is improved.
The power cable management method has the beneficial effects that: compared with the traditional two-dimensional design, the three-dimensional simulation is adopted to fuse all the specialties into the same three-dimensional system, so that information sharing is realized, communication barriers among all the specialties are broken, cooperative follow-up is realized, a convenient communication platform is provided for power cable management, and the realization of projects is promoted.
Drawings
Fig. 1 is a block diagram of a power cable management system according to an embodiment of the present invention.
Detailed Description
The technical solutions of the embodiments of the present invention will be explained and explained below with reference to the drawings of the embodiments of the present invention, but the embodiments described below are only preferred embodiments of the present invention, and are not all embodiments. Other embodiments obtained by persons skilled in the art without any inventive work based on the embodiments in the embodiment belong to the protection scope of the invention.
Referring to fig. 1, a power cable management method, the method comprising the steps of:
s1, accurately positioning a cable working well, an accessory facility, a cable channel and a cable track through a three-dimensional laser scanning technology to form three-dimensional data, simultaneously constructing an electronic coding identification system of equipment, establishing a three-dimensional model of the cable channel and an equipment basic data standardized database, forming a three-dimensional simulation informatization platform of the power cable management system, and realizing data interaction with a GIS (geographic information system) and a PMS (permanent magnet system);
and S2, the power cable management system runs through a guide project full life cycle management, the project full life cycle management is divided into two parts, namely cable project construction stage management and operation and maintenance after commissioning maintenance stage management, basic data management of equipment and channels is taken as a core, various working standard operation steps are standardized, engineering stage information, a typical defect and hidden danger elimination control scheme and maintenance test business processing work are standardized and designed, and a transportation and inspection unit is assisted to guide the development of standardized cable full life cycle management work.
The power cable management method of the invention comprises the following steps: compared with the traditional two-dimensional design, each professional design follows up respectively, and a good collaborative relationship cannot be achieved, so that design change occurs, and after a drawing is changed, a series of derived wastes of manpower, material resources and financial resources are generated. GIS is a geographic information system. The PMS is a production management system.
Furthermore, in the engineering construction stage management, a standardized technical parameter and process standard database is established, engineering process and equipment parameter standards are standardized, engineering construction defects are found in time, and the intrinsic safety level of equipment is improved.
Further, in the engineering construction stage management, the power cable management controls the basic data in multiple dimensions, the whole process of channel resources, three-dimensional display, quick positioning, external-break-prevention, fire-prevention, disaster-prevention and reduction functions and auxiliary engineering acceptance.
Further, the basic data multidimensional application management means: the PMS system cable and channel resource information is deeply applied, the cable and channel resource scale, the channel and working well change trend and hidden danger defects of each region are displayed in a multi-dimensional mode, and abnormal data alarming of the cable and the channel is achieved, so that lean management of the cable and the channel resources is achieved; information resources are mutually checked through any dimension of the cable name, the cable channel and the road, multi-dimensional information correlation analysis of the cable body, the joint, the channel and the environment is realized, and support is provided for cable planning and field intersection.
Further, the whole process management of channel resources refers to: the method comprises the steps that information of a starting well and an ending well is set, and the existing channel and the channel to be built are displayed graphically according to the channel type, the channel utilization rate, the channel material and the channel size related information, so that a reference basis is provided for a newly added cable path design scheme, and optimal planning of a cable path is realized; the inquiry of the channel resources for the cable is supported, a standard cable channel resource application, approval, reservation and occupation mechanism is established, the cable resource approval process is standardized, the lean management and control of the whole process of the use of the cable channel resources are realized, the nonstandard occupation of the channel resources is avoided, and the maximization of the utilization of the channel resources is realized.
Further, three-dimensional display management means: the underground cable and the channel are consulted and browsed in a panoramic simulation mode by adopting a three-dimensional informatization simulation technology, so that the digital, visualized and realistic management of the cable and channel basic data is realized; meanwhile, when the design requirements and the projects are changed, a collision test method is adopted for the changed areas through a three-dimensional informatization simulation technology, and potential problem hidden dangers are found and solved in advance; aiming at the ground excavation problem frequently occurring in the underground power grid management process, the three-dimensional information simulation technology provides ground excavation simulation of any region, the excavation depth and the boundary range are set, the three-dimensional terrain automatically collapses, the distribution condition of the underground power grid is exposed, and decision support is provided for construction.
Further, the fast positioning management means: the transmission and distribution operation personnel utilize the handheld mobile operation terminal to realize the real-time access to the accurate positioning and three-dimensional cable data of the cable line, call the latest state data of the cable line at any time, realize the inspection tour and the defect elimination management of the cable channel and the cable line, improve the daily operation maintenance efficiency of the cable, and promote the health management level of the cable channel.
Further, the management of functions of external damage prevention, fire prevention, disaster prevention and disaster reduction refers to: aiming at the current situations that construction points along a cable channel are diversified and wide, the cable channel is relatively isolated and dispersed, temporary construction is more at night, and operation and maintenance strength is relatively weak, accurate cable burial depth data, relative position relation with other municipal pipelines and pipe hole fireproof blocking conditions are provided based on three-dimensional results, and basic information is provided for channel hidden danger analysis and channel hidden danger coping strategy anti-external damage measure formulation; integrating big data resources by using a positioning and early warning positioning device for preventing external damage and an external damage video monitoring device, and establishing a cable external damage prevention control platform; meanwhile, the on-line monitoring device arranged on the power cable and the channel is used for displaying the running state of the line in real time, setting a data abnormity warning function and sending warning information according to the severity level.
Further, the auxiliary project acceptance management means: high-precision point cloud data of an underground comprehensive pipe gallery, an electric power tunnel, a cable trench and a cable well cable channel are acquired based on three-dimensional laser scanning, the underground facility scene is visualized and measurable, and the underground facility scene is superposed and compared with three-dimensional BIM design data and two-dimensional CAD design data, so that the evaluation of the construction quality of the power cable concealed project is realized.
Furthermore, in equipment operation stage management, building a covering operation and maintenance management, state management and live detection management function module, and combining GIS two-dimensional digital geographic information display to realize full-period closed-loop management of cable and channel operation and inspection processes; establishing a standardized data standard system, uniformly accessing partial discharge detection, an intelligent grounding box, optical fiber temperature measurement, video monitoring, an intelligent well cover and an intelligent inspection robot monitoring system to a lean management platform for centralized monitoring, and comprehensively analyzing and utilizing monitoring data; based on a GIS two-dimensional geographic information system, the RFID electronic tag is in butt joint with the intelligent inspection terminal, the running state, the monitoring value and the position information of monitoring equipment are mastered in real time, and the alarm information of monitoring points of abnormal equipment on site is automatically pushed; through a three-dimensional virtual reality modeling technology, the functions of vertical/horizontal clear distance measurement, channel section display, simulated excavation analysis and intelligent planning line selection are realized in a three-dimensional field of view, and the deep excavation application level of basic data of the urban underground cable and peripheral pipelines thereof is improved.
Furthermore, the equipment operation stage management comprises five management modules of emergency repair plans, risk evaluation and insulation evaluation, intelligent data analysis, modular online monitoring and intensive environment deployment; emergency repair plan management means: the method comprises the steps that electricity simulates engineering first-aid repair drilling based on a three-dimensional virtual reality scene, an emergency first-aid repair plan is customized, and the site first-aid repair implementation efficiency and the first-aid repair success rate are greatly improved through a precise positioning system and the first-aid repair plan; the risk evaluation and insulation evaluation management means: based on the real-time data of the running state of the field equipment, the equipment ledger and the on-site overhaul and repair conditions, and in combination with a cable professional typical information library, a risk assessment and insulation evaluation system based on big data is established to realize the state assessment of the cable line; the intelligent data analysis management means that: establishing a technical standard and installation process standard database aiming at different manufacturer models, intelligently assisting in judging the installation process result and simultaneously giving out standardized process requirements; equipment abnormality is timely found through transverse and longitudinal comparison calculation; a multidimensional cross module data analysis mode is applied to realize automatic study and judgment of the system and assist in generating management decisions; the modularized online monitoring management means that: by developing a modular online monitoring system and a standardized data standard system, the traditional system operated by multiple independent manufacturers is integrated in a centralized manner, and a technical specification and a solution are provided for the access of subsequent monitoring equipment of multiple manufacturers; intensive environment deployment management refers to: the design principle of uniform deployment and reinforced integration is adopted, the boundary division and cooperation intercommunication among the modules are fully considered, and the production work benefit of a cable transportation and inspection department is improved.
The three-dimensional informatization simulation technology of the power cable runs through the whole life cycle of a project, and relates to a planning and design stage, a purchasing and construction stage, an operation and maintenance stage and the like. The appearance of the three-dimensional design of the power cable provides a brand-new data platform for the management system, and on the basis, the common cooperation of multiple participants in design, management, construction and the like is realized. The cable engineering construction stage management and the equipment operation stage management are not unrelated, the concept of standardized full-life management is applied, the work flow is standardized, the lean management system takes basic data management of equipment and channels as a core, various working standardized operation steps are standardized, the standardized design is carried out on engineering stage information, a typical defect and hidden danger elimination control scheme, maintenance test business processing and other works, a brand-new cable professional management mode is formed, and a transportation and inspection unit is guided to carry out standardized cable full-life cycle management work in an auxiliary mode.
The power cable management method has the beneficial effects that: compared with the traditional two-dimensional design, the three-dimensional simulation is adopted to fuse all the specialties into the same three-dimensional system, so that information sharing is realized, communication barriers among all the specialties are broken, cooperative follow-up is realized, a convenient communication platform is provided for power cable management, and the realization of projects is promoted.
While the invention has been described with reference to specific embodiments thereof, it will be understood by those skilled in the art that the invention is not limited thereto but is intended to cover various modifications and changes, including but not limited to the details shown in the drawings and described in the foregoing detailed description. Any modification which does not depart from the functional and structural principles of the invention is intended to be included within the scope of the following claims.

Claims (10)

1. The power cable management method is characterized by comprising the following steps: the method comprises the following steps:
s1, accurately positioning a cable working well, an accessory facility, a cable channel and a cable track through a three-dimensional laser scanning technology to form three-dimensional data, simultaneously constructing an electronic coding identification system of equipment, establishing a three-dimensional model of the cable channel and an equipment basic data standardized database, forming a three-dimensional simulation informatization platform of the power cable management system, and realizing data interaction with a GIS (geographic information system) and a PMS (permanent magnet system);
and S2, the power cable management system runs through a guide project full life cycle management, the project full life cycle management is divided into two parts, namely cable project construction stage management and operation and maintenance after commissioning maintenance stage management, basic data management of equipment and channels is taken as a core, various working standard operation steps are standardized, engineering stage information, a typical defect and hidden danger elimination control scheme and maintenance test business processing work are standardized and designed, and a transportation and inspection unit is assisted to guide the development of standardized cable full life cycle management work.
2. The power cable management method of claim 1, wherein: in the engineering construction stage management, a standardized technical parameter and process standard database is built, engineering process and equipment parameter standards are standardized, engineering construction defects are found in time, and the intrinsic safety level of equipment is improved; in the engineering construction stage management, the power cable management is managed and controlled from six aspects of basic data multi-dimensional application, the whole process of channel resources, three-dimensional display, quick positioning, external-break-prevention, fire-prevention, disaster-prevention and reduction functions and auxiliary engineering acceptance.
3. The power cable management method of claim 2, wherein: the basic data multi-dimensional application management means that: the PMS system cable and channel resource information is deeply applied, the cable and channel resource scale, the channel and working well change trend and hidden danger defects of each region are displayed in a multi-dimensional mode, and abnormal data alarming of the cable and the channel is achieved, so that lean management of the cable and the channel resources is achieved; information resources are mutually checked through any dimension of the cable name, the cable channel and the road, multi-dimensional information correlation analysis of the cable body, the joint, the channel and the environment is realized, and support is provided for cable planning and field intersection.
4. The power cable management method of claim 2, wherein: the whole process management of channel resources refers to: the method comprises the steps that information of a starting well and an ending well is set, and the existing channel and the channel to be built are displayed graphically according to the channel type, the channel utilization rate, the channel material and the channel size related information, so that a reference basis is provided for a newly added cable path design scheme, and optimal planning of a cable path is realized; the inquiry of the channel resources for the cable is supported, a standard cable channel resource application, approval, reservation and occupation mechanism is established, the cable resource approval process is standardized, the lean management and control of the whole process of the use of the cable channel resources are realized, the nonstandard occupation of the channel resources is avoided, and the maximization of the utilization of the channel resources is realized.
5. The power cable management method of claim 2, wherein: the three-dimensional display management means: the underground cable and the channel are consulted and browsed in a panoramic simulation mode by adopting a three-dimensional informatization simulation technology, so that the digital, visualized and realistic management of the cable and channel basic data is realized; meanwhile, when the design requirements and the projects are changed, a collision test method is adopted for the changed areas through a three-dimensional informatization simulation technology, and potential problem hidden dangers are found and solved in advance; aiming at the ground excavation problem frequently occurring in the underground power grid management process, the three-dimensional information simulation technology provides ground excavation simulation of any region, the excavation depth and the boundary range are set, the three-dimensional terrain automatically collapses, the distribution condition of the underground power grid is exposed, and decision support is provided for construction.
6. The power cable management method of claim 2, wherein: the fast positioning management means: the transmission and distribution operation personnel utilize the handheld mobile operation terminal to realize the real-time access to the accurate positioning and three-dimensional cable data of the cable line, call the latest state data of the cable line at any time, realize the inspection tour and the defect elimination management of the cable channel and the cable line, improve the daily operation maintenance efficiency of the cable, and promote the health management level of the cable channel.
7. The power cable management method of claim 2, wherein: the management of the functions of external damage prevention, fire prevention, disaster prevention and disaster reduction refers to: aiming at the current situations that construction points along a cable channel are diversified and wide, the cable channel is relatively isolated and dispersed, temporary construction is more at night, and operation and maintenance strength is relatively weak, accurate cable burial depth data, relative position relation with other municipal pipelines and pipe hole fireproof blocking conditions are provided based on three-dimensional results, and basic information is provided for channel hidden danger analysis and channel hidden danger coping strategy anti-external damage measure formulation; integrating big data resources by using a positioning and early warning positioning device for preventing external damage and an external damage video monitoring device, and establishing a cable external damage prevention control platform; meanwhile, the on-line monitoring device arranged on the power cable and the channel is used for displaying the running state of the line in real time, setting a data abnormity warning function and sending warning information according to the severity level.
8. The power cable management method of claim 2, wherein: the auxiliary project acceptance management means: high-precision point cloud data of an underground comprehensive pipe gallery, an electric power tunnel, a cable trench and a cable well cable channel are acquired based on three-dimensional laser scanning, the underground facility scene is visualized and measurable, and the underground facility scene is superposed and compared with three-dimensional BIM design data and two-dimensional CAD design data, so that the evaluation of the construction quality of the power cable concealed project is realized.
9. The power cable management method of claim 1, wherein: in equipment operation stage management, building covering operation and maintenance management, overhaul management, state management and live detection management functional modules, and combining GIS two-dimensional digital geographic information display to realize full-period closed-loop management of cable and channel operation and inspection processes; establishing a standardized data standard system, uniformly accessing partial discharge detection, an intelligent grounding box, optical fiber temperature measurement, video monitoring, an intelligent well cover and an intelligent inspection robot monitoring system to a lean management platform for centralized monitoring, and comprehensively analyzing and utilizing monitoring data; based on a GIS two-dimensional geographic information system, the RFID electronic tag is in butt joint with the intelligent inspection terminal, the running state, the monitoring value and the position information of monitoring equipment are mastered in real time, and the alarm information of monitoring points of abnormal equipment on site is automatically pushed; through a three-dimensional virtual reality modeling technology, the functions of vertical/horizontal clear distance measurement, channel section display, simulated excavation analysis and intelligent planning line selection are realized in a three-dimensional field of view, and the deep excavation application level of basic data of the urban underground cable and peripheral pipelines thereof is improved.
10. The power cable management method of claim 9, wherein: the equipment operation stage management comprises five management modules of emergency repair plans, risk evaluation and insulation evaluation, intelligent data analysis, modular online monitoring and intensive environment deployment; emergency repair plan management means: the method comprises the steps that electricity simulates engineering first-aid repair drilling based on a three-dimensional virtual reality scene, an emergency first-aid repair plan is customized, and the site first-aid repair implementation efficiency and the first-aid repair success rate are greatly improved through a precise positioning system and the first-aid repair plan; the risk evaluation and insulation evaluation management means: based on the real-time data of the running state of the field equipment, the equipment ledger and the on-site overhaul and repair conditions, and in combination with a cable professional typical information library, a risk assessment and insulation evaluation system based on big data is established to realize the state assessment of the cable line; the intelligent data analysis management means that: establishing a technical standard and installation process standard database aiming at different manufacturer models, intelligently assisting in judging the installation process result and simultaneously giving out standardized process requirements; equipment abnormality is timely found through transverse and longitudinal comparison calculation; a multidimensional cross module data analysis mode is applied to realize automatic study and judgment of the system and assist in generating management decisions; the modularized online monitoring management means that: by developing a modular online monitoring system and a standardized data standard system, the traditional system operated by multiple independent manufacturers is integrated in a centralized manner, and a technical specification and a solution are provided for the access of subsequent monitoring equipment of multiple manufacturers; intensive environment deployment management refers to: the design principle of uniform deployment and reinforced integration is adopted, the boundary division and cooperation intercommunication among the modules are fully considered, and the production work benefit of a cable transportation and inspection department is improved.
CN201911211104.6A 2019-12-02 2019-12-02 Power cable management method Pending CN110991670A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911211104.6A CN110991670A (en) 2019-12-02 2019-12-02 Power cable management method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911211104.6A CN110991670A (en) 2019-12-02 2019-12-02 Power cable management method

Publications (1)

Publication Number Publication Date
CN110991670A true CN110991670A (en) 2020-04-10

Family

ID=70088915

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911211104.6A Pending CN110991670A (en) 2019-12-02 2019-12-02 Power cable management method

Country Status (1)

Country Link
CN (1) CN110991670A (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111798004A (en) * 2020-05-14 2020-10-20 河北沧海石化工程有限公司 BIM-based petrochemical system operation and maintenance scheduling method and system
CN112186613A (en) * 2020-09-30 2021-01-05 国网北京市电力公司 Cable management method, device and system
CN112349056A (en) * 2020-11-06 2021-02-09 暨南大学 Cable channel prevents outer broken intelligent front end control and early warning system
CN112670891A (en) * 2021-01-18 2021-04-16 内蒙古电力(集团)有限责任公司呼和浩特供电局 Method for overhauling underground cable based on virtual reality
CN112907421A (en) * 2021-02-24 2021-06-04 中煤科工集团重庆智慧城市科技研究院有限公司 Service scene acquisition system and method based on spatial analysis
CN113689651A (en) * 2021-07-16 2021-11-23 国网江苏省电力有限公司电力科学研究院 Early fire early warning method and device for cable channel, early warning monitoring platform and storage medium
CN114861378A (en) * 2022-06-25 2022-08-05 鹏宇实业发展(广州)有限公司 Refined design method for pipeline engineering power cable
CN116030422A (en) * 2023-03-28 2023-04-28 深圳市海威恒泰智能科技有限公司 Visual video monitoring intelligent operation and maintenance management system

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180262571A1 (en) * 2016-03-04 2018-09-13 Sabrina Akhtar Integrated IoT (Internet of Things) System Solution for Smart Agriculture Management
CN109217163A (en) * 2018-09-11 2019-01-15 贵州电网有限责任公司 Urban electric power cable comprehensive monitoring and intelligent operational system based on geographical location
CN109360287A (en) * 2018-03-27 2019-02-19 浙江华云电力工程设计咨询有限公司 Transmission line of electricity three-dimensional digital fortune inspection management system

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180262571A1 (en) * 2016-03-04 2018-09-13 Sabrina Akhtar Integrated IoT (Internet of Things) System Solution for Smart Agriculture Management
CN109360287A (en) * 2018-03-27 2019-02-19 浙江华云电力工程设计咨询有限公司 Transmission line of electricity three-dimensional digital fortune inspection management system
CN109217163A (en) * 2018-09-11 2019-01-15 贵州电网有限责任公司 Urban electric power cable comprehensive monitoring and intelligent operational system based on geographical location

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
刘燕平等: "基于三维仿真技术的电力电缆管理系统设计" *

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111798004A (en) * 2020-05-14 2020-10-20 河北沧海石化工程有限公司 BIM-based petrochemical system operation and maintenance scheduling method and system
CN112186613A (en) * 2020-09-30 2021-01-05 国网北京市电力公司 Cable management method, device and system
CN112349056A (en) * 2020-11-06 2021-02-09 暨南大学 Cable channel prevents outer broken intelligent front end control and early warning system
CN112349056B (en) * 2020-11-06 2022-05-10 暨南大学 Cable channel prevents outer broken intelligent front end control and early warning system
CN112670891A (en) * 2021-01-18 2021-04-16 内蒙古电力(集团)有限责任公司呼和浩特供电局 Method for overhauling underground cable based on virtual reality
CN112907421A (en) * 2021-02-24 2021-06-04 中煤科工集团重庆智慧城市科技研究院有限公司 Service scene acquisition system and method based on spatial analysis
CN112907421B (en) * 2021-02-24 2023-08-01 中煤科工集团重庆智慧城市科技研究院有限公司 Business scene acquisition system and method based on spatial analysis
CN113689651A (en) * 2021-07-16 2021-11-23 国网江苏省电力有限公司电力科学研究院 Early fire early warning method and device for cable channel, early warning monitoring platform and storage medium
CN113689651B (en) * 2021-07-16 2023-01-31 国网江苏省电力有限公司电力科学研究院 Early fire early warning method and device for cable channel, early warning monitoring platform and storage medium
CN114861378A (en) * 2022-06-25 2022-08-05 鹏宇实业发展(广州)有限公司 Refined design method for pipeline engineering power cable
CN116030422A (en) * 2023-03-28 2023-04-28 深圳市海威恒泰智能科技有限公司 Visual video monitoring intelligent operation and maintenance management system
CN116030422B (en) * 2023-03-28 2023-05-30 深圳市海威恒泰智能科技有限公司 Visual video monitoring intelligent operation and maintenance management system

Similar Documents

Publication Publication Date Title
CN110991670A (en) Power cable management method
CN111091609B (en) Transformer substation field operation management and control system and method based on three-dimensional dynamic modeling
Yin et al. A BIM-based framework for operation and maintenance of utility tunnels
CN111145479B (en) Construction dangerous environment real-time early warning platform and method based on BIM positioning technology
CN111444568A (en) Engineering monitoring BIM cooperative platform based on Internet of things
CN204303029U (en) For the BIM Database Systems of subway pipeline collision detection and later stage operation maintenance
CN111027834A (en) Power cable informatization management system and method based on three-dimensional detection technology
CN112989532A (en) BIM-based construction method for changing municipal pipeline of subway station
CN105425752A (en) Real-time monitoring system of pipe network and working method of same
CN110866161A (en) Urban underground space three-dimensional information visualization system and method
CN112258159B (en) BIM + GIS-based hydraulic structure management system and method
CN106651074A (en) Intelligent underground pipeline management system
CN113096477A (en) Visual operation and maintenance work platform of virtual power station
CN108875273A (en) Base pit engineering Top-Down Design and operation management system based on BIM
CN116415816B (en) M-CPS intelligent mine management platform and system
CN115456814A (en) Tunnel management platform taking construction organization as core
Zhou et al. A BIM-based identification and classification method of environmental risks in the design of Beijing subway
CN113722797A (en) Lightweight BIM prefabricated part full life cycle comprehensive information management system
KR20230083388A (en) Building information modeling(bim)-grid maintenance system for underground area of urban railway, and method for the same
CN112365246A (en) AI + GIS + BIM-based intelligent pipe gallery comprehensive management platform
CN112464494A (en) Construction system is built to wisdom
CN116720242A (en) Digital twin panoramic monitoring system for high-voltage cable tunnel
CN210072621U (en) BIM management-based deepened transformation system for vehicle section with ultra-large cover body
CN115329416A (en) Building construction method based on BIM
CN113837453A (en) Deep sewage drainage tunnel wisdom operation system

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200410