CN110985010A - Loess tunnel construction method and two operation surface structures in single-footage construction - Google Patents

Loess tunnel construction method and two operation surface structures in single-footage construction Download PDF

Info

Publication number
CN110985010A
CN110985010A CN201911331492.1A CN201911331492A CN110985010A CN 110985010 A CN110985010 A CN 110985010A CN 201911331492 A CN201911331492 A CN 201911331492A CN 110985010 A CN110985010 A CN 110985010A
Authority
CN
China
Prior art keywords
layer
steel pipe
construction
footage
water
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911331492.1A
Other languages
Chinese (zh)
Inventor
张玉伟
宋战平
王军保
卫守峰
张登飞
王志鹏
张闯
赵辉
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Xian University of Architecture and Technology
Original Assignee
Xian University of Architecture and Technology
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Xian University of Architecture and Technology filed Critical Xian University of Architecture and Technology
Priority to CN201911331492.1A priority Critical patent/CN110985010A/en
Publication of CN110985010A publication Critical patent/CN110985010A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D9/00Tunnels or galleries, with or without linings; Methods or apparatus for making thereof; Layout of tunnels or galleries
    • E21D9/04Driving tunnels or galleries through loose materials; Apparatus therefor not otherwise provided for
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/14Lining predominantly with metal
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Environmental & Geological Engineering (AREA)
  • Excavating Of Shafts Or Tunnels (AREA)

Abstract

A loess tunnel construction method and two kinds of operation face structures in the single footage construction, first, confirm the outline line of excavation face, drive into the steel pipe with grouting hole along the outline line of excavation face, then slip casting; excavating a water injection hole on the tunnel face; after water is injected, quickly excavating along the full section of the inner ring; after the excavation is finished, a concrete layer is sprayed, a waterproof layer is arranged, secondary lining is applied, and at the moment, the current footage construction is finished; repeating the steps to carry out the construction of the next footage; according to the invention, water is injected into the area to be excavated through the water injection holes, so that the loess strength can be reduced, and the water stop layer consisting of the steel pipe and the grouting body is constructed, so that in the construction process, on one hand, the water injected through the water injection holes can be prevented from entering the surrounding rock, the surrounding rock strength is reduced, and the purpose of softening the area to be excavated is achieved; on the other hand, the protective effect is achieved, and the full-section rapid excavation is facilitated; the invention has the characteristics of high efficiency, safety and strong controllability.

Description

Loess tunnel construction method and two operation surface structures in single-footage construction
Technical Field
The invention belongs to the technical field of tunnel construction, and particularly relates to a loess tunnel construction method and two operation surface structures in single-footage construction.
Background
With the implementation of the strategy developed in western China, the traffic infrastructure is rapidly developed. The loess strata in the western region are widely distributed, and with the continuous improvement of a traffic network, more and more tunnels need to be built in the loess strata. At present, loess tunnel construction is carried out by referring to a soft rock tunnel construction method, a step method, a reserved core soil annular excavation method, a CD method, a CRD method and the like are often adopted, and although the methods can ensure normal construction of the loess tunnel, the methods do not consider the particularity of loess, so that the construction efficiency is low; loess has obvious soaking and collapsible properties, and if the characteristic can be fully considered in construction, the construction efficiency can be greatly improved.
Disclosure of Invention
In order to overcome the defects in the prior art, the invention aims to provide a loess tunnel construction method and two operation surface structures in single-footage construction, which can fully utilize the characteristic that loess is soaked and collapsed, control the soaking and collapsing range of the loess through an isolation structure and a support structure so as to improve the construction efficiency, and have the characteristics of high efficiency, safety and strong controllability.
In order to achieve the purpose, the invention adopts the following technical scheme:
a loess tunnel construction method includes the following steps:
step 1: determining an excavation surface contour line; determining the length of a footage to be 5-15 m, and performing construction of the current footage;
step 2: a circle of steel pipes 1 with grouting holes 7 are driven into the loess surrounding rock at an outward insertion angle of 1-5 degrees along the contour line of the excavation surface, and the steel pipes 1 are mutually attached to enclose a steel pipe circle layer 6;
and step 3: grouting the surrounding rock through a grouting device through the steel pipe 1, and forming a water stop layer 9 by the steel pipe ring layer 6 and the grouting body 8;
and 4, step 4: excavating 3-5 water injection holes 2 on the tunnel face; when the construction of the first stage is finished, the construction of the second stage is carried out; in the two-stage construction, water is injected into the water injection holes 2 to ensure that the loess is soaked and softened;
and 5: excavating the contour surface along the inner wall of the water stopping layer 9 by adopting a cantilever excavator;
step 6: after the section is excavated and formed, a concrete layer 3 is sprayed on the inner ring of the steel pipe ring layer 6, and a waterproof layer 4 is arranged on the inner ring of the concrete layer through a waterproof board;
and 7: after the waterproof layer 4 is arranged, a secondary lining 5 is constructed on the inner wall of the waterproof layer 4, and tunnel auxiliary facilities are constructed;
and 8: and (4) after one construction footage is finished, repeating the steps 2 to 7, and constructing the next footage until the tunnel is communicated.
The length of the water injection hole 2 is 1.5-2.5 meters less than that of the steel pipe 1; the length part of the steel pipe 1, which is larger than the water injection hole, is used as the lap joint length of the current footage and the next footage.
The thickness of the concrete layer 3 is 3-7 cm.
The length of the steel pipe 1 is 8-12 meters, the diameter is 3-5 cm, and the wall thickness is 0.5-0.8 cm.
The steel pipe 1 is provided with a row of grouting holes 7 on two opposite sides, the diameter of each grouting hole 7 is 1-3 cm, and the interval between every two grouting holes 7 is 5-10 cm.
The utility model provides an operation face structure that single footage one-stage construction was ended in loess tunnel construction, includes stagnant water layer 9, be equipped with a plurality of water injection hole 2 in the soil body of stagnant water layer 9 inside.
The water stopping layer 9 comprises a steel pipe ring layer 6 and a grouting body 8; the steel pipe ring layer 6 is formed by mutually clinging and enclosing the steel pipes 1.
The steel pipe 1 is driven into loess surrounding rock at an external insertion angle of 1-5 degrees.
The length of the steel pipe 1 is 8-12 meters, the diameter is 3-5 cm, and the wall thickness is 0.5-0.8 cm.
And two opposite sides of the steel pipe 1 are respectively provided with a row of grouting holes 7.
The diameter of the grouting holes 7 is 1-3 cm, and the interval between the grouting holes 7 is 5-10 cm.
The utility model provides an operation face structure that single advance two-stage construction was ended in loess tunnel construction, includes stagnant water layer 9, and the inner circle of stagnant water layer 9 is equipped with concrete layer 3, and waterproof layer 4 has been laid to concrete layer 3's inboard, and secondary lining 5 has been executed to waterproof layer 4's inboard.
The water stopping layer 9 comprises a steel pipe ring layer 6 and a grouting body 8; the steel pipe ring layer 6 is formed by mutually clinging and enclosing the steel pipes 1.
The steel pipe 1 is driven into loess surrounding rock at an external insertion angle of 1-5 degrees.
The length of the steel pipe 1 is 8-12 meters, the diameter is 3-5 cm, and the wall thickness is 0.5-0.8 cm.
And two opposite sides of the steel pipe 1 are respectively provided with a row of grouting holes 7.
The diameter of the grouting holes 7 is 1-3 cm, and the interval between the grouting holes 7 is 5-10 cm.
The thickness of the concrete layer 3 is 3-7 cm.
The invention has the beneficial effects that: water is injected into the area to be excavated through the water injection holes 2, so that the loess strength can be reduced; in the construction process, the water stop layer 9 is formed by the steel pipe ring layer 6 and the grouting body 8, so that on one hand, water in the water injection hole 2 can be prevented from entering the surrounding rock, the strength of the surrounding rock is reduced, and the purpose of only softening an area to be excavated is achieved, and in addition, the water stop layer 9 can also be used as a main supporting structure; the concrete layer 3 is applied without supporting and leveling, so that the construction efficiency can be improved and the investment can be saved; the water stopping layer 9 plays a role in protection, and is favorable for rapid excavation of a full section; the construction disturbance can be reduced by adopting full-section rapid excavation; the secondary lining 5 can form a supporting ring in time to ensure safety.
Drawings
Fig. 1 is a working face structure in which construction is finished at a single advancing stage in loess tunnel construction.
Fig. 2 is a working face structure in which construction at a single advancing stage and construction at two stages in loess tunnel construction are finished.
Fig. 3 is a side cross-sectional view of the work surface after completion of the single-track two-stage construction.
Fig. 4 is a schematic structural view of the steel pipe 1.
In the figure: 1. a steel pipe; 2. a water injection hole; 3. a concrete layer; 4. a waterproof layer; 5. secondary lining; 6. a steel pipe ring layer; 7. grouting holes; 8. grouting; 9. and (5) a water stopping layer.
Detailed Description
The invention is further explained below with reference to the figures and examples.
Referring to fig. 1 and 2, a loess tunnel construction method includes the steps of:
step 1: determining an excavation surface contour line; determining the length of one footage to be 8m, and performing construction of the current footage;
step 2: a circle of steel pipes 1 with grouting holes 7 are driven into the loess surrounding rock at an outer plug angle of 2 degrees along the contour line of the excavation surface, and the steel pipes 1 are mutually attached to enclose a steel pipe circle layer 6;
and step 3: grouting the surrounding rock through a grouting device through the steel pipe 1, and forming a water stop layer 9 by the steel pipe ring layer 6 and the grouting body 8;
and 4, step 4: excavating 3 water injection holes 2 on the tunnel face; when the construction of the first stage is finished, the construction of the second stage is carried out; in the two-stage construction, water is injected into the water injection holes 2 to ensure that the loess is soaked and softened;
and 5: excavating the contour surface along the inner wall of the water stopping layer 9 by adopting a cantilever excavator;
step 6: after the section is excavated and formed, a concrete layer 3 is sprayed on the inner ring of the steel pipe ring layer 6, and a waterproof layer 4 is arranged on the inner ring of the concrete layer through a waterproof board;
and 7: after the waterproof layer 4 is arranged, the secondary lining 5 is integrally constructed, and the auxiliary facilities of the tunnel are constructed;
and 8: and (4) after one construction footage is finished, repeating the steps 2 to 7, and constructing the next footage until the tunnel is communicated.
Referring to fig. 1 and 2, the length of the water injection hole 2 is 8m, and the length of the water injection hole 2 is 2m less than that of the steel pipe 1 in practical use, and the 2m is used as the overlapping length of the next footage.
Referring to fig. 2, the thickness of the concrete layer 3 is 5 cm.
Referring to fig. 4, the steel pipe 1 has a length of 10m, a diameter of 3cm and a wall thickness of 0.6 cm.
The steel pipe 1 is provided with a row of grouting holes 7 on two opposite sides, the diameter of each grouting hole 7 is 2cm, and the interval between every two grouting holes 7 is 7.5 cm.
And (3) carrying out full-face rapid excavation on the contour surface along the inner wall of the steel pipe 1 by adopting a cantilever tunneling machine.
Referring to fig. 1, the working face structure for single-footage one-stage construction completion in loess tunnel construction comprises a water stopping layer 9, wherein a plurality of water injection holes 2 are formed in a soil body inside the water stopping layer 9.
The water stop layer 9 comprises a steel pipe ring layer 6 and a grouting body 8.
Referring to fig. 1 and 2, the length of the water injection hole 2 is 8m, and the length of the water injection hole 2 is 2m less than that of the steel pipe 1 in practical use, and the 2m is used as the overlapping length of the next footage.
Referring to fig. 3, the steel pipe ring layer 6 is formed by the steel pipes 1 which are tightly attached to each other; the steel pipe 1 is driven into the loess surrounding rock at an external insertion angle of 2 degrees.
Referring to fig. 4, the steel pipe 1 has a length of 10m, a diameter of 3cm and a wall thickness of 0.6 cm.
Referring to fig. 4, two opposite sides of the steel pipe 1 are respectively provided with a row of grouting holes 7; the diameter of the grouting holes 7 is 2cm, and the interval between the grouting holes 7 is 7.5 cm.
The utility model provides an operation face structure that single advance two-stage construction was ended in loess tunnel construction, includes stagnant water layer 9, and the inner circle of stagnant water layer 9 is equipped with concrete layer 3, and waterproof layer 4 has been laid to concrete layer 3's inboard, and secondary lining 5 has been executed to waterproof layer 4's inboard.
Referring to fig. 1 and 2, the water stop layer 9 comprises a steel pipe ring layer 6 and a grouting body 8; the steel pipe ring layer 6 is formed by mutually clinging and enclosing the steel pipes 1.
Referring to fig. 1 and 2, the length of the water injection hole 2 is 8m, and the length of the water injection hole 2 is 2m less than that of the steel pipe 1 in practical use, and the 2m is used as the overlapping length of the next footage.
Referring to fig. 2, the thickness of the concrete layer 3 is 5 cm.
Referring to fig. 3, the steel pipe 1 is driven into the loess surrounding rock at an external insertion angle of 2 °.
Referring to fig. 4, the steel pipe 1 has a length of 10m, a diameter of 3cm and a wall thickness of 0.6 cm.
Referring to fig. 4, two opposite sides of the steel pipe 1 are respectively provided with a row of grouting holes 7; the diameter of the grouting holes 7 is 2cm, and the interval between the grouting holes 7 is 7.5 cm.
The working principle of the invention is as follows: injecting water into the area to be excavated through the water injection hole 2, softening soil in the area to be excavated and reducing the strength of the soil; a steel pipe-grouting body water stop layer is arranged to prevent water in the water injection holes 2 from entering the surrounding rock and reduce the strength of the surrounding rock; the construction disturbance is reduced by adopting full-section rapid excavation; the secondary lining 5 can form a supporting and protecting ring to ensure safety.

Claims (10)

1. A loess tunnel construction method is characterized by comprising the following steps:
step 1: determining an excavation surface contour line; determining the length of a footage to be 5-15 m, and performing construction of the current footage;
step 2: a circle of steel pipes (1) with grouting holes (7) are driven into the loess surrounding rock at an extrapolation angle of 1-5 degrees along the contour line of the excavation surface, and the steel pipes (1) are mutually attached to form a steel pipe circle layer (6);
and step 3: grouting the surrounding rock through a grouting device through a steel pipe (1), and forming a water stop layer (9) by a steel pipe ring layer (6) and a grouting body (8);
and 4, step 4: excavating 3-5 water injection holes (2) on the tunnel face; when the construction of the first stage is finished, the construction of the second stage is carried out; in the two-stage construction, water is injected into the water injection holes (2) to ensure that the loess is soaked and softened;
and 5: excavating the profile surface along the inner wall of the water stopping layer (9) by adopting a cantilever excavator;
step 6: after the section is excavated and formed, a concrete layer (3) is sprayed on the inner ring of the steel pipe ring layer (6), and a waterproof layer (4) is arranged on the inner ring of the concrete layer through a waterproof board;
and 7: after the waterproof layer (4) is arranged, the secondary lining (5) is integrally constructed, and the tunnel auxiliary facilities are constructed;
and 8: and (4) after one construction footage is finished, repeating the steps 2 to 7, and constructing the next footage until the tunnel is communicated.
2. The loess tunnel construction method according to claim 1, wherein the steel pipe (1) has a length of 8 to 12 m, a diameter of 3 to 5cm and a wall thickness of 0.5 to 0.8 cm.
3. The loess tunnel construction method according to claim 1, wherein the length of the water injection holes (2) is 1.5 to 2.5 m less than that of the steel pipes (1); the length part of the steel pipe (1) which is larger than the water injection hole (2) is used as the lapping length of the current footage and the next footage.
4. The loess tunnel construction method according to claim 1 or 2, wherein a row of injection holes (7) are formed at opposite sides of the steel pipe (1), the diameter of the injection holes (7) is 1-3 cm, and the interval between the injection holes (7) is 5-10 cm.
5. The loess tunnel construction method according to claim 1, wherein the thickness of the concrete layer (3) is 3 to 7 cm.
6. The utility model provides a single footage one-stage construction's operation face structure that finishes in loess tunnel construction, its characterized in that includes stagnant water layer (9), be equipped with a plurality of water injection hole (2) in the soil body of stagnant water layer (9) inside.
7. The working face structure of a single-footage one-stage construction completion in loess tunnel construction according to claim 6, wherein the water stopping layer (9) comprises a steel pipe ring layer (6) and a grout (8); the steel pipe ring layer (6) is formed by mutually clinging and enclosing the steel pipes (1); the steel pipe (1) is driven into loess surrounding rock at an external insertion angle of 1-5 degrees; two opposite sides of the steel pipe (1) are respectively provided with a row of grouting holes (7).
8. The working face structure for single-footage one-stage construction completion in loess tunnel construction according to claim 7, wherein the diameter of the grout holes (7) is 1 to 3cm, and the interval between the grout holes (7) is 5 to 10 cm.
9. The working face structure is characterized by comprising a water stopping layer (9), wherein a concrete layer (3) with the thickness of 3-7 cm is arranged on an inner ring of the water stopping layer (9), a waterproof layer (4) is laid on the inner side of the concrete layer (3), and a secondary lining (5) is laid on the inner side of the waterproof layer (4).
10. The working face structure for completing construction at a single-footage two-stage in loess tunnel construction according to claim 9, wherein the water stopping layer (9) comprises a steel pipe ring layer (6) and a grouting body (8); the steel pipe ring layer (6) is formed by mutually clinging and enclosing the steel pipes (1); the steel pipe (1) is driven into loess surrounding rock at an external insertion angle of 1-5 degrees; the length of the steel pipe (1) is 8-12 meters, the diameter is 3-5 cm, and the wall thickness is 0.5-0.8 cm; two opposite sides of the steel pipe (1) are respectively provided with a row of grouting holes (7).
CN201911331492.1A 2019-12-21 2019-12-21 Loess tunnel construction method and two operation surface structures in single-footage construction Pending CN110985010A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911331492.1A CN110985010A (en) 2019-12-21 2019-12-21 Loess tunnel construction method and two operation surface structures in single-footage construction

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911331492.1A CN110985010A (en) 2019-12-21 2019-12-21 Loess tunnel construction method and two operation surface structures in single-footage construction

Publications (1)

Publication Number Publication Date
CN110985010A true CN110985010A (en) 2020-04-10

Family

ID=70074550

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911331492.1A Pending CN110985010A (en) 2019-12-21 2019-12-21 Loess tunnel construction method and two operation surface structures in single-footage construction

Country Status (1)

Country Link
CN (1) CN110985010A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012770A (en) * 2020-07-26 2020-12-01 中铁二院工程集团有限责任公司 Underground water advanced treatment structure and construction method for ultra-deep vertical shaft of railway tunnel

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1851145A (en) * 2006-05-18 2006-10-25 贵阳铝镁设计研究院 Wet-fall loess foundation submerging consolidation method
CN202140103U (en) * 2011-07-22 2012-02-08 中铁十一局集团有限公司 Rock burst tunnel supporting structure
CN103527202A (en) * 2012-07-27 2014-01-22 中国有色金属工业第六冶金建设有限公司 Method for constructing tunnel under complicated geological conditions
CN205013011U (en) * 2015-09-28 2016-02-03 中铁二十局集团有限公司 Pyroclastic flow stratum tunnel advance support structure
CN109723443A (en) * 2018-12-30 2019-05-07 中铁十四局集团有限公司 Method for tunnel construction
CN209067230U (en) * 2018-11-22 2019-07-05 中铁二十局集团第六工程有限公司 Advanced solid matter ductule loess tunnel is into hole ruggedized construction
CN212054692U (en) * 2019-12-21 2020-12-01 西安建筑科技大学 Two kinds of operation face structures of different stages in single footage construction in loess tunnel

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1851145A (en) * 2006-05-18 2006-10-25 贵阳铝镁设计研究院 Wet-fall loess foundation submerging consolidation method
CN202140103U (en) * 2011-07-22 2012-02-08 中铁十一局集团有限公司 Rock burst tunnel supporting structure
CN103527202A (en) * 2012-07-27 2014-01-22 中国有色金属工业第六冶金建设有限公司 Method for constructing tunnel under complicated geological conditions
CN205013011U (en) * 2015-09-28 2016-02-03 中铁二十局集团有限公司 Pyroclastic flow stratum tunnel advance support structure
CN209067230U (en) * 2018-11-22 2019-07-05 中铁二十局集团第六工程有限公司 Advanced solid matter ductule loess tunnel is into hole ruggedized construction
CN109723443A (en) * 2018-12-30 2019-05-07 中铁十四局集团有限公司 Method for tunnel construction
CN212054692U (en) * 2019-12-21 2020-12-01 西安建筑科技大学 Two kinds of operation face structures of different stages in single footage construction in loess tunnel

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112012770A (en) * 2020-07-26 2020-12-01 中铁二院工程集团有限责任公司 Underground water advanced treatment structure and construction method for ultra-deep vertical shaft of railway tunnel

Similar Documents

Publication Publication Date Title
CN111594181B (en) Construction method for communicating and connecting newly-added underground excavation channel and existing station hall layer
CN102606167B (en) Settlement control construction method for transverse grouting guide pipe of shallow underground excavation tunnel
WO2021120991A1 (en) Method for reconstructing shield tunnel for mining construction
CN100554646C (en) Shield method combines the job practices of building the subway station with shallow burial hidden digging
CN102606168B (en) Construction method for preventing settlement and deformation of shallow-buried-excavation tunnel in excavation
CN204476470U (en) A kind of waterproof and water drainage system of applicable tunnel project seam
CN105862990B (en) A kind of prefabrication and assembly construction shaft wall structure and its construction method
CN110017145B (en) Sea area shield mine junction tunnel intra-cavity connection joint and construction method thereof
CN102979531B (en) Reinforce construction method and the structure of large-scale rock slope deep weak structural plane
CN102094650A (en) Construction method for shield holing under complicated working conditions
CN109026020B (en) Water-rich tunnel karst cave treatment and excavation method
CN205296175U (en) High pressure -bearing depth of water excavation supporting stock structure
CN105240024A (en) Parallel shield tunneling method for extended construction of subway station
CN105114098A (en) Method for treating unfavorable geological tunnel section of diversion tunnel and large-diameter diversion tunnel structure
CN105065009A (en) Method for shield expanding construction of subway station
CN103670439B (en) Lining construction method
CN207033463U (en) Mine shield handing-over tunnel folded type joint design in the middle part of marine site
CN109209443A (en) A kind of construction method of breaking surrounding rock tunnel structure
CN115045688A (en) Method for treating gushing water of high-buried-depth tunnel by adopting blocking-before-draining method
CN110985010A (en) Loess tunnel construction method and two operation surface structures in single-footage construction
CN212054692U (en) Two kinds of operation face structures of different stages in single footage construction in loess tunnel
CN204716253U (en) Circular major diameter diversion tunnel structure
CN113107500A (en) Variable cross-section tunnel construction method
CN105240023A (en) Method of adopting curved pipe-jacking supporting structure for extension of shield-driven subway station
CN117489367A (en) Tunnel collapse treatment reinforcing structure and method under bad geological conditions of hydropower station

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination