CN110984158A - Offshore wind power large-diameter rock-socketed single pile grouting construction method - Google Patents

Offshore wind power large-diameter rock-socketed single pile grouting construction method Download PDF

Info

Publication number
CN110984158A
CN110984158A CN201911160272.7A CN201911160272A CN110984158A CN 110984158 A CN110984158 A CN 110984158A CN 201911160272 A CN201911160272 A CN 201911160272A CN 110984158 A CN110984158 A CN 110984158A
Authority
CN
China
Prior art keywords
grouting
pipe
steel
pile
prefabricated
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911160272.7A
Other languages
Chinese (zh)
Inventor
朱嵘华
李庆东
其他发明人请求不公开姓名
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Guangdong Huayun Offshore Wind Power Technology Co Ltd
Original Assignee
Guangdong Huayun Offshore Wind Power Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Guangdong Huayun Offshore Wind Power Technology Co Ltd filed Critical Guangdong Huayun Offshore Wind Power Technology Co Ltd
Priority to CN201911160272.7A priority Critical patent/CN110984158A/en
Publication of CN110984158A publication Critical patent/CN110984158A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/04Placing concrete in mould-pipes, pile tubes, bore-holes or narrow shafts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D15/00Handling building or like materials for hydraulic engineering or foundations
    • E02D15/02Handling of bulk concrete specially for foundation or hydraulic engineering purposes
    • E02D15/06Placing concrete under water
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/10Deep foundations
    • E02D27/12Pile foundations
    • E02D27/16Foundations formed of separate piles
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/42Foundations for poles, masts or chimneys
    • E02D27/425Foundations for poles, masts or chimneys specially adapted for wind motors masts
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D27/00Foundations as substructures
    • E02D27/32Foundations for special purposes
    • E02D27/52Submerged foundations, i.e. submerged in open water
    • E02D27/525Submerged foundations, i.e. submerged in open water using elements penetrating the underwater ground
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/22Piles
    • E02D5/34Concrete or concrete-like piles cast in position ; Apparatus for making same
    • E02D5/38Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds
    • E02D5/385Concrete or concrete-like piles cast in position ; Apparatus for making same making by use of mould-pipes or other moulds with removal of the outer mould-pipes
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/22Foundations specially adapted for wind motors
    • FMECHANICAL ENGINEERING; LIGHTING; HEATING; WEAPONS; BLASTING
    • F03MACHINES OR ENGINES FOR LIQUIDS; WIND, SPRING, OR WEIGHT MOTORS; PRODUCING MECHANICAL POWER OR A REACTIVE PROPULSIVE THRUST, NOT OTHERWISE PROVIDED FOR
    • F03DWIND MOTORS
    • F03D13/00Assembly, mounting or commissioning of wind motors; Arrangements specially adapted for transporting wind motor components
    • F03D13/20Arrangements for mounting or supporting wind motors; Masts or towers for wind motors
    • F03D13/25Arrangements for mounting or supporting wind motors; Masts or towers for wind motors specially adapted for offshore installation
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2250/00Production methods
    • E02D2250/003Injection of material
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D2300/00Materials
    • E02D2300/0026Metals
    • E02D2300/0029Steel; Iron
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/72Wind turbines with rotation axis in wind direction
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E10/00Energy generation through renewable energy sources
    • Y02E10/70Wind energy
    • Y02E10/727Offshore wind turbines

Landscapes

  • Engineering & Computer Science (AREA)
  • General Engineering & Computer Science (AREA)
  • Structural Engineering (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Mining & Mineral Resources (AREA)
  • Paleontology (AREA)
  • Civil Engineering (AREA)
  • Sustainable Development (AREA)
  • Sustainable Energy (AREA)
  • Chemical & Material Sciences (AREA)
  • Combustion & Propulsion (AREA)
  • Mechanical Engineering (AREA)
  • Foundations (AREA)

Abstract

A construction method for grouting large-diameter rock-socketed single piles of offshore wind power belongs to the technical field of foundation grouting of offshore wind power. The construction method is used for grouting construction of large-diameter rock-socketed single piles in offshore wind power plant construction, solves the problems of bottom sealing and side wall grouting in the grouting construction process, and overcomes the technical defects of a common grouting method. The difficult problem of back cover that the major diameter single pile brought has been solved through the grout back cover, through the even arrangement of prefabricated grout pipe in the steel-pipe pile, the inhomogeneous problem of major diameter steel-pipe pile grout material distribution has been solved, the application of emergent grout pipe, the risk that makes the grout is very reduced, the steel protects a section of thick bamboo promotion and the coordinated action of grout, the appearance of the ageing phenomenon of cohering of steel casing and grout material has been avoided, make the steel protect a section of thick bamboo can reuse, marine wind power infrastructure's cost has been reduced, the security of marine wind power foundation construction has been improved.

Description

Offshore wind power large-diameter rock-socketed single pile grouting construction method
Technical Field
The invention relates to a grouting construction method for a large-diameter rock-socketed single pile of offshore wind power, and belongs to the technical field of offshore wind power foundation grouting.
Background
In the offshore wind power development process, the geological conditions of some fields are complex, the shallow surface layer is a soft covering soil layer, and a hard rock layer is arranged below the covering layer. If the surface layer earthing is only squeezed into to the pile foundation of major diameter single pile basis, the bearing capacity that the pile foundation provided can't satisfy the demand, in order to satisfy the designing requirement of bearing capacity, major diameter single pile foundation pile point portion need imbed in the rock layer under the overburden layer, forms the embedded rock stake.
The rock-socketed pile is constructed by drilling and sinking the pile, and the diameter of the pile hole generated by drilling is larger than that of the single pile, so that the large-diameter single pile can be directly implanted into the drilling hole in the follow-up process. There is the space between steel-pipe pile outer wall and stake hole, need fill the space between steel-pipe pile and the stake hole through the grout of certain intensity, treat that the grout is ageing back, guarantee the bearing capacity and the steadiness of single pile to resist the impact of fan load and external environment load. The particularity of the rock-socketed single pile construction brings a series of technical problems to grouting operation: (1) the grouting of the rock-socketed single pile is finished underwater, the grouting clearance is small, and the underwater monitoring difficulty is high; (2) the diameter of a single pile reaches several meters, the use of a rubber ring or a steel plate for bottom sealing is high in cost, the method is complex, the effect is difficult to guarantee, failure is easy to occur once collision occurs in the installation process, and if the bottom sealing fails, grouting material flows into the pile barrel, so that a large amount of grouting material is wasted; (3) in the drilling and tunneling process, a steel casing needs to be lowered to ensure that the soft soil of the upper surface covering layer cannot collapse in the drilling process, the progress between the steel casing and grouting operation needs to be coordinated and promoted in the side wall grouting process, if the steel casing is promoted too fast, the soft soil of the upper surface covering layer is disturbed, the drilling collapse is easily caused, if the steel casing is promoted too slowly, grouting materials are condensed, the steel casing and a steel pipe pile are bonded together, and the steel casing is difficult to pull out, so that an engineering accident is caused; (4) the length of the grouting section of the rock-socketed single pile reaches dozens of meters, the grouting amount is large, and grouting needs to be finished by bottom grouting and bottom sealing and pile soil side wall gap grouting. Therefore, the reasonable grouting construction method has important significance for the safety and the economical efficiency of rock-socketed single pile construction.
Disclosure of Invention
In order to solve the technical problem, the invention provides a grouting construction method for a large-diameter rock-socketed single pile of offshore wind power, which is used for grouting construction of the large-diameter rock-socketed single pile in offshore wind power plant construction. The grouting method solves the difficult problems of bottom sealing and side wall grouting in the grouting construction process, and overcomes the technical defects of the common grouting method.
The technical scheme adopted by the invention is as follows: a construction method for grouting large-diameter rock-socketed single piles of offshore wind power plants comprises the following steps:
(a) arranging the steel casing in the mud layer according to the design requirement, wherein the bottom of the steel casing is in contact with the rock stratum, and the top of the steel casing is higher than the sea level;
(b) emptying a mud layer in the pile casing on the inner side of the steel pile casing and a lower rock stratum of the pile casing at the bottom of the steel pile casing;
(c) hoisting a prefabricated steel pipe pile into a steel casing by using a crane for positioning, and forming an annular cavity between a rock wall formed by the steel pipe pile and an empty rock stratum under the steel casing and the steel casing;
(d) hoisting a grouting pipe into the steel pipe pile and extending to the bottom of the pile hole, pumping grouting material to a position which is 500mm away from the bottom of the pile hole by the grouting pipe so that the grouting material is filled at the bottom of the steel pipe pile, lifting the grouting pipe at a constant speed in the subsequent grouting process (lifting the grouting pipe by a crane on a construction ship when grouting at a certain height), enabling a grouting opening of the grouting pipe to be always positioned at a position which is 150 mm below the surface of the grouting material, stopping grouting when the grouting is performed until the thickness of the grouting material is 1000 mm and 1100mm, removing the grouting pipe, lifting the steel pipe pile, enabling the grouting material to enter an annular cavity, then laying the pile down, standing for 24h, and forming a bottom sealing grouting layer after the grouting material is aged;
(e) hoisting the emergency grouting pipe into the annular cavity, wherein the upper interface of the emergency grouting opening of the emergency grouting pipe, which is higher than the bottom sealing grouting layer, is 400-500 mm; grouting the annular cavity through the first prefabricated grouting pipe, grouting the annular cavity by using the second prefabricated grouting pipe when the slurry surface in the annular cavity rises to a second grouting opening of the second prefabricated grouting pipe until the slurry surface of the annular cavity rises to the position of a mud surface, and stopping grouting the annular cavity; in the process of grouting the annular cavity by using the first prefabricated grouting pipe and the second prefabricated grouting pipe, when the slurry surface in the annular cavity is higher than the mudstone boundary surface, the emergency grouting pipe and the steel protective barrel are lifted at a constant speed, so that the emergency grouting opening of the emergency grouting pipe is always higher than the slurry surface of the annular cavity by 400-plus-500 mm (the lifting speed of a grouting interface is calculated according to the grouting volume of the annular cavity and the production capacity of grouting equipment, and the emergency grouting pipe is lifted by using a crane according to the lifting speed); only when the first prefabricated grouting pipe and the second prefabricated grouting pipe cannot be grouted due to faults, the emergency grouting pipe is used for grouting the annular cavity, and the emergency grouting pipe is enabled to intermittently move around the steel pipe pile in the annular cavity while grouting;
(f) and when the slurry surface of the annular cavity rises to the position of the mud surface, the steel protecting cylinder is lifted away from the mud layer, and the steel protecting cylinder is recovered.
The inner wall of the steel pipe pile is provided with a first prefabricated grouting pipe fixed by a plurality of first supporting rods) and a second prefabricated grouting pipe fixed by a plurality of second supporting rods, the first prefabricated grouting pipe is communicated with a first grouting opening arranged on the pile wall, and the second prefabricated grouting pipe is communicated with a second grouting opening arranged on the pile wall.
The second grouting opening is located above the first grouting opening, and the distance between the first grouting opening and the bottom end of the steel pipe pile is 1200-1300 mm.
The invention has the beneficial effects that: the offshore wind power large-diameter rock-socketed single pile grouting construction method solves the bottom sealing problem caused by large-diameter single piles through grouting material bottom sealing, solves the problem of uneven distribution of grouting materials of large-diameter steel pipe piles through uniform arrangement of prefabricated grouting pipes in the steel pipe piles, and reduces the grouting risk greatly by applying emergency grouting pipes.
Drawings
Fig. 1 is a structural view of a precast grout pipe of a steel pipe pile.
FIG. 2 is a cross-sectional view taken along line I-I of FIG. 1.
FIG. 3 is a sectional view taken along line II-II in FIG. 1.
FIG. 4 is a schematic diagram of a steel casing driving into a mud layer and emptying the mud layer and the rock layer below the casing.
Fig. 5 is a schematic view of the installation and positioning of the steel pipe pile in the steel casing.
Fig. 6 is a schematic view of forming a back-cover grouting layer by grouting a bottom of a steel pipe pile with a grouting pipe.
Fig. 7 is a schematic illustration of grouting an annular cavity with a pre-fabricated grout tube in a steel pipe pile.
Figure 8 is a schematic illustration of completion of annular cavity grouting.
In the figure: 1. the device comprises a steel pipe pile, a steel casing, a 2a protective casing inner mud layer, a 2b protective casing lower rock stratum, a 3, a first prefabricated grouting pipe, a 3a first supporting rod, a 3b first grouting opening, a 4, a second prefabricated grouting pipe, a 4a second supporting rod, a 4b second grouting opening, a 5, a grouting pipe, a 5a grouting opening, a 6, an emergency grouting pipe, a 6a emergency grouting opening, a 7, a bottom sealing grouting layer, a 8 and an annular cavity; A. a mud layer, a B rock layer, a C mudstone interface, a D mudface.
Detailed Description
The grouting construction method of the offshore wind power large-diameter rock-socketed single pile is further explained below with reference to the accompanying drawings.
Fig. 1, 2 and 3 show the structure of the prefabricated grouting pipe of the steel pipe pile. Be equipped with two first prefabricated grout pipes 3 that fix with a plurality of first bracing pieces 3a and two prefabricated grout pipes 4 of second that fix with a plurality of second bracing pieces 4a on the inner wall of steel-pipe pile 1, first prefabricated grout pipe 3 and the alternate equipartition of second prefabricated grout pipe 4 are on the inner wall of steel-pipe pile 1. The first prefabricated grouting pipe 3 is communicated with a first grouting opening 3b formed in the pile wall, and the second prefabricated grouting pipe 4 is communicated with a second grouting opening 4b formed in the pile wall. The second grouting opening 4b is positioned above the first grouting opening 3b, and the distance between the first grouting opening 3b and the bottom end of the steel pipe pile 1 is 1200-1300 mm.
As shown in fig. 4 and 5, the bottom end of the steel casing 2 is driven into the mud layer a, the bottom of the steel casing is in contact with the rock stratum B, the top end of the steel casing 2 is located above the horizontal plane, a pile hole is dug under the protection of the steel casing 2, and the mud layer 2a in the steel casing 2 and the rock stratum 2B under the steel casing 2 at the bottom of the steel casing 2 are emptied. And then, sinking the steel pipe pile 1 into the excavated pile hole, wherein annular cavities 8 between the steel pipe pile 1 and the rock hole wall and between the steel pipe pile 1 and the steel casing 2 are positions needing grouting and backfilling.
After the steel pipe pile 1 is sunk to a preset elevation and leveled, the grouting pipe 5 is lowered to a position 300-500mm away from the pile bottom, as shown in fig. 6. Pumping grouting material to the inside of the steel pipe pile 1 by using the grouting pipe 5, enabling the grouting material to fill the bottom of the steel pipe pile 1, lifting the grouting pipe 5 at a constant speed in the subsequent grouting process, enabling a grouting opening 5a of the grouting pipe 5 to be always located at the position of 150-sand-adding 250mm below the grout surface, stopping grouting when the thickness of the grouting material is 1000-sand-adding 1100mm, removing the grouting pipe 5, lifting the steel pipe pile 1, enabling the grouting material to enter an annular cavity 8, then putting down the steel pipe pile 1, standing for 24 hours, and forming a bottom-sealing grouting layer 7 after the grouting material is aged.
As shown in fig. 7, the emergency grouting pipe 6 is lowered in the annular cavity 8 between the steel pipe pile 1 and the steel casing 2 to a position 400-500mm above the bottom sealing grouting layer 7. At first, grout ring cavity 8 through first prefabricated grout pipe 3, when the thick liquids face in ring cavity 8 risees to the second grout mouth 4a of prefabricated grout pipe 4 of second, change to use prefabricated grout pipe 4 of second to grout ring cavity 8, rise to the position of mud face D until the thick liquids face of ring cavity 8, stop 8 grout in ring cavity 8. In the process of grouting the annular cavity 8 by using the first prefabricated grouting pipe 3 and the second prefabricated grouting pipe 4, when the slurry surface in the annular cavity 8 is higher than a mudstone interface C, the emergency grouting pipe 6 and the steel casing 2 are required to be lifted at a constant speed, so that the emergency grouting opening 6a of the emergency grouting pipe 6 is always higher than the slurry surface 400-500mm of the annular cavity 8. Only when the first prefabricated grouting pipe 3 and the second prefabricated grouting pipe 4 cannot be grouted due to faults, the emergency grouting pipe 6 is used for grouting the annular cavity 8, and the emergency grouting pipe 6 is enabled to intermittently move around the steel pipe pile 1 in the annular cavity 8 while grouting.
As shown in fig. 8, when the slurry level in the annular chamber 8 rises to the position of the mud level D, the steel casing 2 is lifted away from the mud layer a, and the steel casing 2 is recovered.
The offshore wind power large-diameter rock-socketed single pile grouting construction method provided by the invention is explained above. The above cases are intended to help the skilled person understand the method and its core ideas referred to in the present invention. It should be noted that those skilled in the art can make modifications necessary to the present invention without departing from the principle of the present invention, and such modifications are also within the scope of the appended claims.

Claims (3)

1. A construction method for grouting large-diameter rock-socketed single piles of offshore wind power plants is characterized by comprising the following steps: the method comprises the following steps:
(a) arranging the steel casing (2) in the mud layer (A) according to the design requirement, wherein the bottom of the steel casing is in contact with the rock layer (B), and the top of the steel casing is higher than the horizontal plane;
(b) emptying a casing inner mud layer (2 a) at the inner side of the steel casing (2) and a casing lower rock stratum (2 b) at the bottom of the steel casing (2);
(c) hoisting a prefabricated steel pipe pile (1) into a steel casing (2) by using a crane for positioning, and forming an annular cavity (8) between a rock wall formed by the steel pipe pile (1) and an empty lower rock stratum (2 b) of the casing and the steel casing (2);
(d) the method comprises the steps that a steel pile grouting pipe (5) is hung into a steel pipe pile (1) and extends to the bottom of a pile hole, grouting materials are pumped to the bottom of the pile hole through the steel pile grouting pipe (5) and have the thickness of 300-250 mm, so that the grouting materials are filled in the bottom of the steel pipe pile (1), the steel pile grouting pipe (5) is lifted at a constant speed in the subsequent grouting process, a steel pile grouting opening (5 a) of the steel pile grouting pipe (5) is always located 150-250mm below a slurry surface, grouting is stopped until the thickness of the slurry is 1000-1100mm, grouting is stopped, the steel pile grouting pipe (5) is removed, the steel pipe pile (1) is lifted, the grouting materials enter an annular cavity (8), the steel pipe pile (1) is placed down, standing is carried out for 24 hours, and a bottom sealing grouting layer (7) is formed after the grouting materials are aged;
(e) the emergency grouting pipe (6) is hung in the annular cavity (8), and the upper interface of the emergency grouting opening (6 a) of the emergency grouting pipe (6) which is higher than the bottom sealing grouting layer (7) is 400-plus-500 mm; grouting an annular cavity (8) through a first prefabricated grouting pipe (3), when the slurry level in the annular cavity (8) rises to a second grouting opening (4 a) of a second prefabricated grouting pipe (4), grouting the annular cavity (8) by using the second prefabricated grouting pipe (4) until the slurry level of the annular cavity (8) rises to the position of a mud surface (D), and stopping grouting the annular cavity (8); in the process of grouting the annular cavity (8) by using the first prefabricated grouting pipe (3) and the second prefabricated grouting pipe (4), when the slurry surface in the annular cavity (8) is higher than a mudstone interface (C), the emergency grouting pipe (6) and the steel casing (2) are lifted at a constant speed, so that the emergency grouting opening (6 a) of the emergency grouting pipe (6) is always 400-500mm higher than the slurry surface of the annular cavity (8); only when the first prefabricated grouting pipe (3) and the second prefabricated grouting pipe (4) cannot be grouted due to faults, the emergency grouting pipe (6) is used for grouting the annular cavity (8), and the emergency grouting pipe (6) is enabled to intermittently move around the steel pipe pile (1) in the annular cavity (8) while grouting;
(f) when the slurry surface in the annular cavity (8) rises to the position of the mud surface (D), the steel casing (2) is lifted away from the mud layer (A) to recover the steel casing (2).
2. The offshore wind power large-diameter rock-socketed single pile grouting construction method according to claim 1, characterized by comprising the following steps: be equipped with on the inner wall of steel-pipe pile (1) with first prefabricated grout pipe (3) that a plurality of first bracing pieces (3 a) are fixed and with prefabricated grout pipe (4) of second that a plurality of second bracing pieces (4 a) are fixed, first prefabricated grout pipe (3) and first grout mouth (3 b) the intercommunication of setting on the pile wall, prefabricated grout pipe of second (4) and second grout mouth (4 b) the intercommunication of setting on the pile wall.
3. The offshore wind power large-diameter rock-socketed single pile grouting construction method according to claim 2, characterized by comprising the following steps: the second grouting opening (4 b) is positioned above the first grouting opening (3 b), and the distance between the first grouting opening (3 b) and the bottom end of the steel pipe pile (1) is 1200-1300 mm.
CN201911160272.7A 2019-11-23 2019-11-23 Offshore wind power large-diameter rock-socketed single pile grouting construction method Pending CN110984158A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911160272.7A CN110984158A (en) 2019-11-23 2019-11-23 Offshore wind power large-diameter rock-socketed single pile grouting construction method

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911160272.7A CN110984158A (en) 2019-11-23 2019-11-23 Offshore wind power large-diameter rock-socketed single pile grouting construction method

Publications (1)

Publication Number Publication Date
CN110984158A true CN110984158A (en) 2020-04-10

Family

ID=70086125

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911160272.7A Pending CN110984158A (en) 2019-11-23 2019-11-23 Offshore wind power large-diameter rock-socketed single pile grouting construction method

Country Status (1)

Country Link
CN (1) CN110984158A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827274A (en) * 2020-07-22 2020-10-27 浙江大学 High-strength grouting method for marine wind power weakly-weathered bedrock single-pile socketed foundation
CN113006161A (en) * 2021-02-04 2021-06-22 浙江大学 Offshore wind power pile foundation anti-scouring construction method based on solidification side bulldozing
CN113653092A (en) * 2021-07-28 2021-11-16 中国能源建设集团广东省电力设计研究院有限公司 Double-pile sleeve type foundation and installation method thereof
CN114032888A (en) * 2021-11-22 2022-02-11 中国电建集团华东勘测设计研究院有限公司 Grouting pile casing structure for offshore rock-socketed pile and construction method

Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2666912A1 (en) * 2012-05-25 2013-11-27 WeserWind GmbH Offshore Construction Georgsmarienhütte Method for anchoring offshore facilities to the sea bed, foundation structure for offshore facilities and device
CN104912081A (en) * 2015-06-29 2015-09-16 中国能源建设集团广东省电力设计研究院有限公司 Foundation grouting method for offshore wind power and foundation grouting work barge for offshore wind power
CN107558488A (en) * 2017-09-05 2018-01-09 华电重工股份有限公司 A kind of embedding rock single pile of offshore wind farm and its construction system and construction method
CN108547293A (en) * 2018-03-07 2018-09-18 江苏龙源振华海洋工程有限公司 A kind of embedding rock single pile plantation construction technology
CN109208589A (en) * 2018-10-11 2019-01-15 中交上海港湾工程设计研究院有限公司 A kind of embedding rock single pile grouting system of embedded type major diameter and construction method

Patent Citations (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
EP2666912A1 (en) * 2012-05-25 2013-11-27 WeserWind GmbH Offshore Construction Georgsmarienhütte Method for anchoring offshore facilities to the sea bed, foundation structure for offshore facilities and device
CN104912081A (en) * 2015-06-29 2015-09-16 中国能源建设集团广东省电力设计研究院有限公司 Foundation grouting method for offshore wind power and foundation grouting work barge for offshore wind power
CN107558488A (en) * 2017-09-05 2018-01-09 华电重工股份有限公司 A kind of embedding rock single pile of offshore wind farm and its construction system and construction method
CN108547293A (en) * 2018-03-07 2018-09-18 江苏龙源振华海洋工程有限公司 A kind of embedding rock single pile plantation construction technology
CN109208589A (en) * 2018-10-11 2019-01-15 中交上海港湾工程设计研究院有限公司 A kind of embedding rock single pile grouting system of embedded type major diameter and construction method

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111827274A (en) * 2020-07-22 2020-10-27 浙江大学 High-strength grouting method for marine wind power weakly-weathered bedrock single-pile socketed foundation
CN113006161A (en) * 2021-02-04 2021-06-22 浙江大学 Offshore wind power pile foundation anti-scouring construction method based on solidification side bulldozing
CN113653092A (en) * 2021-07-28 2021-11-16 中国能源建设集团广东省电力设计研究院有限公司 Double-pile sleeve type foundation and installation method thereof
CN114032888A (en) * 2021-11-22 2022-02-11 中国电建集团华东勘测设计研究院有限公司 Grouting pile casing structure for offshore rock-socketed pile and construction method

Similar Documents

Publication Publication Date Title
CN110984158A (en) Offshore wind power large-diameter rock-socketed single pile grouting construction method
US11746493B2 (en) Wall sinking construction method
CN210086275U (en) Double-wall hollow open caisson foundation
CN112878375A (en) Vertical jacking implementation method and structure in underwater tunnel suitable for hard stratum
CN112761644A (en) Suspension sinking vertical shaft well completion process
CN108005096A (en) A kind of suspension type wall submersion construction method for city vertical shaft construction
CN102808407B (en) Construction method of soft-foundation reinforced concrete cast-in-place pile
CN104264683A (en) Concave ultra-deep foundation pit zoned supporting method for three-side surrounded cultural protection building
CN114033388B (en) Shaft construction method for water-rich silty sand layer underground tunnel roof pipe
CN114892690A (en) Construction method of double-wall steel-jacketed box cofferdam
CN109403981B (en) Construction process of main body structure of subway shield well
CN114482099A (en) Steel sheet pile cofferdam construction method
CN111501739A (en) Structure for limiting horizontal displacement of pile foundation in deformable rock formation and construction method
CN104264679A (en) Construction method of tower transmission iron tower foundation large-diameter underwater cast-in-place piles
CN115596446A (en) Construction method of vertical shaft
CN206368375U (en) A kind of electric power pylon basis
CN214784305U (en) High-efficient safe tailing storehouse radiation well device of digging a well
CN103982187A (en) Sinking drum reinforcing device for shaft construction
CN113338278A (en) Complex interactive powder fine sand layer super-long large-diameter pile foundation casing and construction method
CN103215965A (en) Laminate type high-rise platform pile tower crane foundation and construction method
CN113668555A (en) Deep foundation pit supporting construction method for large-pipe-diameter prestressed row piles
CN202913431U (en) Immersed tube bottom end jack type deviation-rectifying accurate adjustment system
CN209779615U (en) Active tracking layered grouting system for tree root piles
CN104060636A (en) Depressurization and anti-floating method and device thereof for foundation construction in high water level region building
CN214738266U (en) Vertical jacking implementation structure in underwater tunnel suitable for hard stratum

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200410

WD01 Invention patent application deemed withdrawn after publication