CN110947901A - Three-station chain link integrated production equipment - Google Patents

Three-station chain link integrated production equipment Download PDF

Info

Publication number
CN110947901A
CN110947901A CN201911026485.0A CN201911026485A CN110947901A CN 110947901 A CN110947901 A CN 110947901A CN 201911026485 A CN201911026485 A CN 201911026485A CN 110947901 A CN110947901 A CN 110947901A
Authority
CN
China
Prior art keywords
piston
hydraulic
mounting plate
hydraulic pump
impact
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911026485.0A
Other languages
Chinese (zh)
Inventor
邵坚
王州
程万春
程腾飞
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
ANHUI HUANGSHAN HENGJIU CHAIN DRIVE CO LTD
Original Assignee
ANHUI HUANGSHAN HENGJIU CHAIN DRIVE CO LTD
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by ANHUI HUANGSHAN HENGJIU CHAIN DRIVE CO LTD filed Critical ANHUI HUANGSHAN HENGJIU CHAIN DRIVE CO LTD
Priority to CN201911026485.0A priority Critical patent/CN110947901A/en
Publication of CN110947901A publication Critical patent/CN110947901A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B21MECHANICAL METAL-WORKING WITHOUT ESSENTIALLY REMOVING MATERIAL; PUNCHING METAL
    • B21LMAKING METAL CHAINS
    • B21L11/00Making chains or chain links of special shape
    • B21L11/02Making chains or chain links of special shape each link being formed of a single member of which both ends are bent or shaped to engage the middle portions of the next link
    • B21L11/08Making chains or chain links of special shape each link being formed of a single member of which both ends are bent or shaped to engage the middle portions of the next link the ends being interengaged with other parts of the same link

Landscapes

  • Engineering & Computer Science (AREA)
  • Mechanical Engineering (AREA)
  • Presses And Accessory Devices Thereof (AREA)

Abstract

The application discloses three station chain link integration production facility, the upper end that bears the weight of the base is installed and is born the mould, impact motor and impact shaft are installed to one side of first mounting panel, install connecting rod and impact head on the impact shaft, the upper end that bears the weight of the base still installs the second hydraulic pump, second hydraulic piston and second hydraulic piston axle are installed to the lower extreme of second hydraulic pump, install first clamp plate on the second hydraulic piston axle, install first hydraulic pump on the second mounting panel, first hydraulic piston and first hydraulic piston axle are installed to the lower extreme of first hydraulic pump installing support, install the second clamp plate on the first hydraulic piston axle, the cushion table is installed to the upper end that bears the base, the third hydraulic pump is still installed to the upper end that bears the base, third hydraulic piston and third hydraulic piston axle are installed to the lower extreme of third hydraulic pump, install the drilling head on the third hydraulic piston axle. The invention can realize the integrated processing of straightening, bending and punching of the chain link and improve the processing efficiency of the chain link.

Description

Three-station chain link integrated production equipment
Technical Field
The invention relates to the technical field of cutting devices, in particular to a three-station chain link integrated production device.
Background
The chain links are the components of the anchor chain, and a complete anchor chain is formed by connecting a plurality of anchor chain links to each other to form an anchor chain link with a certain length, and then a plurality of anchor chain links are connected through connecting chain links or connecting shackles to form the whole anchor chain. In the process of the existing chain link production, straightening, bending and drilling are respectively carried out, so that the efficiency is low, the quality is poor, and the requirement of actual production cannot be met.
Disclosure of Invention
Aiming at the defects and shortcomings of the prior art, the invention aims to provide a production device capable of realizing the integration of straightening, bending and punching of chain links.
After adopting the structure, the invention provides the following technical scheme:
a three-station chain link integrated production device comprises a bearing base, wherein a first mounting plate is mounted at the upper end of the bearing base, a bearing mold is mounted at the upper end of the bearing base and positioned at one side of the first mounting plate, an impact motor support is mounted at one side of the first mounting plate, an impact motor is mounted at the upper end of the impact motor support, an impact shaft is mounted at the lower end of the impact motor support, a connecting rod is mounted at one side of the impact shaft, which is far away from the impact motor support, an impact head is mounted at one end of the connecting rod, which is far away from the impact shaft, and is overlapped with the central line of the bearing mold, a second mounting plate is further mounted at the upper end of the bearing base, a bearing seat is mounted at the upper end of the bearing base and positioned at one side of the second mounting plate, a second hydraulic pump mounting bracket is further mounted at one side, a second hydraulic piston shaft is arranged at one end of the second hydraulic piston, which is far away from the second hydraulic pump mounting bracket, a first pressing plate is arranged on the second hydraulic piston shaft, a first hydraulic pump mounting bracket is arranged at one side of the second mounting plate and at one side of the second hydraulic pump mounting bracket, a first hydraulic pump is arranged at the upper end of the first hydraulic pump mounting bracket, a first hydraulic piston is arranged at the lower end of the first hydraulic pump mounting bracket, a first hydraulic piston shaft is arranged at one end of the first hydraulic piston, which is far away from the first hydraulic pump mounting bracket, a second pressing plate is arranged at one end of the first hydraulic piston shaft, which is far away from the first hydraulic piston, a buffer table is arranged at the upper end of the bearing base, a third mounting plate is also arranged at the upper end of the bearing base, a fourth mounting plate is arranged at one side of the third mounting plate, a third hydraulic pump is arranged at the upper end, and a third hydraulic piston shaft is installed at one end, far away from the third hydraulic pump, of the third hydraulic piston, a fifth installation plate is installed at one end, far away from the third hydraulic piston, of the third hydraulic piston shaft, and drilling heads are symmetrically installed on the fifth installation plate relative to the center of the fifth installation plate.
According to the embodiment of the invention, a balancing weight mounting seat is mounted at one end of the connecting rod, which is far away from the impact shaft, a balancing weight is mounted on the balancing weight mounting seat, and an impact head is mounted at one end of the balancing weight, which is far away from the balancing weight mounting seat.
According to the embodiment of the invention, a first piston is arranged on one side of a balancing weight close to an impact head, a first piston shaft is arranged on one side of the first piston far away from the balancing weight, a second piston is arranged on one side of the first piston shaft far away from the first piston, the second piston is arranged on the impact head, a first spring is arranged between the first piston and the second piston, and the first spring is sleeved on the periphery of the first piston shaft.
The second mounting plate is provided with a first sliding groove, a first pulley is arranged in the first sliding groove, and the second pressing plate is fixedly connected with the first pulley and slides in the first sliding groove through the first pulley to move in the vertical direction.
The third mounting plate is provided with a second sliding groove, a second pulley is arranged in the second sliding groove, and the fifth mounting plate is fixedly connected with the second pulley and moves in the vertical direction along with the sliding of the second pulley in the second sliding groove.
According to the embodiment of the invention, a third piston is arranged on one side, close to a fifth mounting plate, of a fourth mounting plate, a second piston shaft is arranged on one side, far away from the fourth mounting plate, of the third piston, a fourth piston is arranged on one end, far away from the third piston, of the second piston shaft, the fourth piston is arranged on the fifth mounting plate, a second spring is arranged between the third piston and the fourth piston, and the second spring is sleeved on the periphery of the second piston shaft.
The lower end of the bearing base is provided with the buffer rubber, and one end of the buffer rubber, which is far away from the bearing base, is provided with the base.
The invention has the beneficial effects that: the workpiece to be processed is firstly placed in a bearing mould, the impact shaft is driven by the impact motor to move in the vertical direction, and drives the connecting rod to drive the impact head to impact the workpiece to be processed in the bearing die to straighten the workpiece, the straightened workpiece is placed at the upper end of the bearing seat, the first hydraulic pump drives the first hydraulic piston to drive the first hydraulic piston shaft to realize the fixation of the second pressure plate on the workpiece to be processed, then the second hydraulic pump drives the second hydraulic piston shaft to drive the first pressing plate to extrude the other end of the workpiece to be machined so as to realize the bending of the workpiece, then the workpiece is placed on the buffer platform, then the third hydraulic pump drives the third hydraulic piston to drive the third hydraulic piston shaft to drive the drilling head to drill the workpiece, the chain piece straightening, bending and drilling operations are realized, the integrated production is realized on one device through three operations, and the chain piece processing and production efficiency is greatly improved.
Other features and advantages of the present invention will be disclosed in more detail in the following detailed description of the invention and the accompanying drawings.
Drawings
FIG. 1 is a schematic structural diagram of a three-station chain link integrated production device;
FIG. 2 is an enlarged partial schematic view at A of FIG. 1;
fig. 3 is a partially enlarged schematic view at B in fig. 1.
The figures are numbered:
1. a base; 2. a cushion rubber; 3. a load bearing base; 4. a first mounting plate; 5. carrying the mold; 6. an impact head; 7. an impact shaft; 8. impacting the motor bracket; 9. an impact motor; 10. a connecting rod; 11. a bearing seat; 12. a first chute; 13. a first pulley; 14. a second hydraulic pump mounting bracket; 15. a second hydraulic piston; 16. a second hydraulic piston shaft; 17. a first platen; 18. a workpiece to be processed; 19. a first hydraulic pump mounting bracket; 20. a first hydraulic piston; 21. a first hydraulic piston shaft; 22. a second platen; 23. a buffer table; 24. a counterweight block mounting seat; 25. a balancing weight; 26. a first piston; 27. a first piston shaft; 28. a second piston; 29. a third mounting plate; 30. a second chute; 31. a second pulley; 32. a fourth mounting plate; 33. a third hydraulic piston; 34. a third piston; 35. a second spring; 36. a second piston shaft; 37. a fourth piston; 38. a fifth mounting plate; 39. drilling a hole head; 40. a third hydraulic piston shaft; 41. and a third hydraulic pump.
Detailed Description
The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the drawings in the embodiments of the present invention, and it is obvious that the described embodiments are only a part of the embodiments of the present invention, and not all of the embodiments.
Referring to fig. 1-3, the three-station chain link integrated production equipment comprises a first mounting plate 4 mounted at the upper end of a bearing base 2, a bearing mold 5 mounted at one side of the first mounting plate 4 at the upper end of the bearing base 2, an impact motor bracket 8 mounted at one side of the first mounting plate 4, an impact motor 9 mounted at the upper end of the impact motor bracket 8, an impact shaft 7 mounted at the lower end of the impact motor bracket 8, a connecting rod 10 mounted at one side of the impact shaft 7 far away from the impact motor bracket 8, an impact head 6 mounted at one end of the connecting rod 10 far away from the impact shaft 7, the impact head 6 and the central line of the bearing mold 5 are arranged in a superposition manner, a second mounting plate 12 is further mounted at the upper end of the bearing base 2, a bearing seat 11 is mounted at one side of the second mounting plate 12 at the upper end of the bearing base 2, and a second, a second hydraulic pump 13 is installed at the upper end of a second hydraulic pump installation support 14, a second hydraulic piston 15 is installed at the lower end of the second hydraulic pump 13, a second hydraulic piston shaft 16 is installed at one end, far away from the second hydraulic pump installation support 14, of the second hydraulic piston 15, a first pressing plate 17 is installed on the second hydraulic piston shaft 16, a first hydraulic pump installation support 19 is installed at one side of the second installation plate 12 and at one side of the second hydraulic pump installation support 14, a first hydraulic pump 18 is installed at the upper end of the first hydraulic pump installation support 19, a first hydraulic piston 20 is installed at the lower end of the first hydraulic pump installation support 19, a first hydraulic piston shaft 21 is installed at one end, far away from the first hydraulic piston 20, of the first hydraulic piston shaft 21, a second pressing plate 22 is installed at one end, far away from the first hydraulic piston 20, and a buffer table 23 is installed at the upper end of the bearing base 3, the upper end of the bearing base 3 is also provided with a third mounting plate 29, one side of the third mounting plate 29 is provided with a fourth mounting plate 32, the upper end of the fourth mounting plate 32 is provided with a third hydraulic pump 41, the lower end of the third hydraulic pump 41 is provided with a third hydraulic piston 33, one end of the third hydraulic piston 33 far away from the third hydraulic pump 41 is provided with a third hydraulic piston shaft 40, one end of the third hydraulic piston shaft 40 far away from the third hydraulic piston 33 is provided with a fifth mounting plate 38, and the fifth mounting plate 38 is symmetrically provided with drilling heads 39 relative to the center thereof.
When the chain piece straightening and bending device is used, a piece to be machined 18 is firstly placed in a bearing mold 5, an impact shaft 7 is driven by an impact motor 9 to move in the vertical direction, a connecting rod 10 is driven to drive an impact head 6 to impact the piece to be machined 18 in the bearing mold 5 to straighten the piece, the straightened piece is placed at the upper end of a bearing seat 11, a first hydraulic pump 18 drives a first hydraulic piston 20 to drive a first hydraulic piston shaft 21 to realize the fixation of a second pressing plate 22 to the piece to be machined, then a second hydraulic pump 13 drives a second hydraulic piston shaft 16 to drive a first pressing plate 17 to extrude the other end of the piece to be machined to realize the bending of the piece, then the piece is placed on a buffer platform 23, then a third hydraulic pump 41 drives a third hydraulic piston 33 to drive a third hydraulic piston shaft 40 to drive a drilling head 39 to perform the drilling operation on the piece, and therefore the chain piece straightening, bending and drilling operations are realized, the three operations realize integrated production on one device, and greatly improve the efficiency of chain piece processing production.
In this embodiment, a counterweight mounting seat 24 is installed at an end of the connecting rod 10 away from the impact shaft 7, a counterweight 25 is installed on the counterweight mounting seat 24, and an impact head 6 is installed at an end of the counterweight 25 away from the counterweight mounting seat 24. Therefore, the impact stability of the impact head 6 is ensured, and the straightening efficiency and quality are improved.
In this embodiment, a first piston 26 is installed on one side of the counterweight 25 close to the impact head 6, a first piston shaft 27 is installed on one side of the first piston 26 far from the counterweight 25, a second piston 28 is installed on one side of the first piston shaft 27 far from the first piston 26, the second piston 28 is installed on the impact head 6, a first spring 25 is arranged between the first piston 26 and the second piston 28, and the first spring 25 is sleeved on the periphery of the first piston shaft 27. Therefore, the impact stability of the impact head 6 is ensured, and the straightening efficiency and quality are improved.
In this embodiment, the second mounting plate 12 is provided with a first sliding slot 12, the first sliding slot 12 is provided with a first pulley 13, and the second pressing plate 22 is fixedly connected with the first pulley 13 and slides in the first sliding slot 12 by the first pulley 13 to move in the vertical direction. Therefore, the stability of the movement of the third pressing plate 22 is ensured, and the bending efficiency and quality of the chain piece are improved.
In this embodiment, the third mounting plate 29 is provided with a second sliding chute 30, a second pulley 31 is provided in the second sliding chute 30, and the fifth mounting plate 38 is fixedly connected to the second pulley 31 and moves in the vertical direction as the second pulley 31 slides in the second sliding chute 30. Therefore, the stability of the drilling head 39 is ensured, and the efficiency and the quality of the drilling are improved.
In this embodiment, a third piston 34 is mounted on a side of the fourth mounting plate 32 close to the fifth mounting plate 38, a second piston shaft 36 is mounted on a side of the third piston 34 far from the fourth mounting plate 32, a fourth piston 37 is mounted on one end of the second piston shaft 36 far from the third piston 34, the fourth piston 37 is mounted on the fifth mounting plate 38, a second spring 35 is arranged between the third piston 34 and the fourth piston 37, and the second spring 35 is sleeved on the outer periphery of the second piston shaft 36. The third piston 34, the second piston shaft 36, the fourth piston 37 and the second spring 35 cooperate to realize buffering, so that the drilling efficiency and the drilling quality of the drilling head 39 are improved.
In this embodiment, the cushion rubber 2 is installed at the lower end of the bearing base 3, and the base 1 is installed at the end of the cushion rubber 2 far away from the bearing base 3. The arrangement of the buffer rubber 2 greatly improves the stability of the device in use.
The above description is only for the preferred embodiment of the present invention, but the scope of the present invention is not limited thereto, and any person skilled in the art should be considered to be within the technical scope of the present invention, and the technical solutions and the inventive concepts thereof according to the present invention should be equivalent or changed within the scope of the present invention.

Claims (7)

1. The utility model provides a three station chain link integration production facility which characterized in that: the hydraulic impact mechanism comprises a bearing base, a first mounting plate is mounted at the upper end of the bearing base, a bearing mold is mounted at the upper end of the bearing base and on one side of the first mounting plate, an impact motor support is mounted at one side of the first mounting plate, an impact motor is mounted at the upper end of the impact motor support, an impact shaft is mounted at the lower end of the impact motor support, a connecting rod is mounted at one side of the impact shaft away from the impact motor support, an impact head is mounted at one end of the connecting rod away from the impact shaft and is overlapped with the central line of the bearing mold, a second mounting plate is further mounted at the upper end of the bearing base, a bearing seat is mounted at the upper end of the bearing base and on one side of the second mounting plate, a second hydraulic pump mounting support is further mounted at one side of the second mounting plate, a second hydraulic pump is mounted at the upper end of the second hydraulic pump mounting support, a second hydraulic, a first pressing plate is arranged on the second hydraulic piston shaft, a first hydraulic pump mounting bracket is arranged on one side of the second mounting plate and one side of the second hydraulic pump mounting bracket, a first hydraulic pump is arranged at the upper end of the first hydraulic pump mounting bracket, a first hydraulic piston is arranged at the lower end of the first hydraulic pump mounting bracket, a first hydraulic piston shaft is arranged at one end of the first hydraulic piston far away from the first hydraulic pump mounting bracket, a second pressing plate is arranged at one end of the first hydraulic piston shaft far away from the first hydraulic piston, a buffer platform is arranged at the upper end of the bearing base, a third mounting plate is also arranged at the upper end of the bearing base, a fourth mounting plate is arranged at one side of the third mounting plate, a third hydraulic pump is arranged at the upper end of the fourth mounting plate, a third hydraulic piston is arranged at the lower end of the third hydraulic pump, and a third hydraulic piston shaft is arranged at one end, and a fifth mounting plate is arranged at one end of the third hydraulic piston shaft, which is far away from the third hydraulic piston, and drilling heads are symmetrically arranged on the fifth mounting plate relative to the center of the fifth mounting plate.
2. The three-station chain link integrated production equipment as claimed in claim 1, wherein: the balancing weight mount pad is installed to the one end that the connecting rod kept away from the impact shaft, installs the balancing weight on the balancing weight mount pad, and the balancing weight is kept away from the one end of balancing weight mount pad and is installed the head of strikeing.
3. The three-station chain link integrated production equipment as claimed in claim 1, wherein: the balancing weight is close to the one side of strikeing the head and installs first piston, and first piston is kept away from one side of balancing weight and is installed first piston shaft, and the one side that first piston was kept away from to first piston shaft is installed the second piston, and the second piston is installed on strikeing the head, is equipped with first spring between first piston and the second piston, and first spring cup joints the periphery at first piston shaft.
4. The three-station chain link integrated production equipment as claimed in claim 1, wherein: the second mounting plate is provided with a first sliding groove, a first pulley is arranged in the first sliding groove, and the second pressing plate is fixedly connected with the first pulley and moves in the vertical direction due to the fact that the first pulley slides in the first sliding groove.
5. The three-station chain link integrated production equipment as claimed in claim 1, wherein: and a second sliding groove is formed in the third mounting plate, a second pulley is arranged in the second sliding groove, and the fifth mounting plate is fixedly connected with the second pulley and moves in the vertical direction along with the sliding of the second pulley in the second sliding groove.
6. The three-station chain link integrated production equipment as claimed in claim 1, wherein: the third piston is installed to one side that the fourth mounting panel is close to the fifth mounting panel, and the second piston axle is installed to one side that the fourth mounting panel was kept away from to the third piston, and the fourth piston is installed to the one end that the third piston was kept away from to the second piston axle, and the fourth piston is installed on the fifth mounting panel, is equipped with the second spring between third piston and the fourth piston, and the second spring cup joints the periphery at the second piston axle.
7. The three-station chain link integrated production equipment as claimed in claim 1, wherein: the lower extreme that bears the weight of the base is installed cushion rubber, and cushion rubber keeps away from the one end that bears the weight of the base and installs the base.
CN201911026485.0A 2019-10-26 2019-10-26 Three-station chain link integrated production equipment Pending CN110947901A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911026485.0A CN110947901A (en) 2019-10-26 2019-10-26 Three-station chain link integrated production equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911026485.0A CN110947901A (en) 2019-10-26 2019-10-26 Three-station chain link integrated production equipment

Publications (1)

Publication Number Publication Date
CN110947901A true CN110947901A (en) 2020-04-03

Family

ID=69976375

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911026485.0A Pending CN110947901A (en) 2019-10-26 2019-10-26 Three-station chain link integrated production equipment

Country Status (1)

Country Link
CN (1) CN110947901A (en)

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU927389A1 (en) * 1980-07-01 1982-05-15 Друскининское Предприятие Художественных Изделий Sheets apparatus for producing decorative chains of metallic strip
JP2003053453A (en) * 2001-08-10 2003-02-26 Seiko Epson Corp Metallic die
CN201223920Y (en) * 2008-07-18 2009-04-22 安徽黄山恒久链传动有限公司 Chain-plate continuous automatic molding machine
CN208276078U (en) * 2018-04-16 2018-12-25 霍邱县佳祥电子配件有限公司 A kind of sealing wire ear bending tool
CN208759729U (en) * 2018-09-03 2019-04-19 安徽新恒辉反光材料有限公司 A kind of reflectorized material perforating device
CN109719191A (en) * 2018-12-10 2019-05-07 国网浙江宁海县供电有限公司 A kind of perforating press being grounded band iron
CN209426213U (en) * 2018-08-01 2019-09-24 南京茂中数控科技有限公司 A kind of machine driving precision lubricating type high velocity ram machine

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
SU927389A1 (en) * 1980-07-01 1982-05-15 Друскининское Предприятие Художественных Изделий Sheets apparatus for producing decorative chains of metallic strip
JP2003053453A (en) * 2001-08-10 2003-02-26 Seiko Epson Corp Metallic die
CN201223920Y (en) * 2008-07-18 2009-04-22 安徽黄山恒久链传动有限公司 Chain-plate continuous automatic molding machine
CN208276078U (en) * 2018-04-16 2018-12-25 霍邱县佳祥电子配件有限公司 A kind of sealing wire ear bending tool
CN209426213U (en) * 2018-08-01 2019-09-24 南京茂中数控科技有限公司 A kind of machine driving precision lubricating type high velocity ram machine
CN208759729U (en) * 2018-09-03 2019-04-19 安徽新恒辉反光材料有限公司 A kind of reflectorized material perforating device
CN109719191A (en) * 2018-12-10 2019-05-07 国网浙江宁海县供电有限公司 A kind of perforating press being grounded band iron

Similar Documents

Publication Publication Date Title
CN204052991U (en) Blast pipe three-hole flange drilling equipment
CN202292644U (en) Device for press-mounting bushings into lifting rings
CN202367408U (en) Pressing bush quick-change device
CN218836145U (en) Perforating device for aluminum profiles
CN206169080U (en) Swing arm upper plate multistation stamping die under vehicle chassis
CN202292038U (en) Bushing block press-mounting device of shock absorber assembly
CN212822711U (en) Automatic turnover mechanism for high-speed lathe
CN110947901A (en) Three-station chain link integrated production equipment
CN202963282U (en) Automatic loading and unloading mechanical hand for stamping
CN210080627U (en) Precision die forging equipment
CN204769926U (en) Drawbench with adjustable
CN213103996U (en) Automobile parts stamping device
CN209829976U (en) Die-cut device is used in production of preceding suspension support
CN209849792U (en) Mould structure with bracket
CN208341441U (en) A kind of linear drives double swing-bar terminal bending device
CN208051464U (en) Sword toy clamp system
CN206535882U (en) Aluminium sheet is molded spreadboard
CN220279858U (en) Stamping die is used in circuit board production
CN101898220A (en) Forming method of steel wire in car seat
CN219112618U (en) Continuous stamping die for automobile door bracket
CN221454254U (en) Arc guide rail riveting jig
CN213916216U (en) Automatic puncher of optical axis
CN205110594U (en) A work piece conveying mechanism for press
CN205110595U (en) A work piece conveying mechanism for press
CN220992647U (en) New energy automobile panel stamping device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200403

RJ01 Rejection of invention patent application after publication