CN110929965A - Project risk assessment method and device - Google Patents

Project risk assessment method and device Download PDF

Info

Publication number
CN110929965A
CN110929965A CN201811092186.2A CN201811092186A CN110929965A CN 110929965 A CN110929965 A CN 110929965A CN 201811092186 A CN201811092186 A CN 201811092186A CN 110929965 A CN110929965 A CN 110929965A
Authority
CN
China
Prior art keywords
project
risk
risk assessment
dimension
assessment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811092186.2A
Other languages
Chinese (zh)
Inventor
宋艳丽
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Gridsum Technology Co Ltd
Original Assignee
Beijing Gridsum Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing Gridsum Technology Co Ltd filed Critical Beijing Gridsum Technology Co Ltd
Priority to CN201811092186.2A priority Critical patent/CN110929965A/en
Publication of CN110929965A publication Critical patent/CN110929965A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0635Risk analysis of enterprise or organisation activities
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/10Office automation; Time management
    • G06Q10/103Workflow collaboration or project management

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Economics (AREA)
  • Tourism & Hospitality (AREA)
  • Marketing (AREA)
  • Operations Research (AREA)
  • Quality & Reliability (AREA)
  • Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • General Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Game Theory and Decision Science (AREA)
  • Development Economics (AREA)
  • Educational Administration (AREA)
  • Data Mining & Analysis (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention discloses a project risk assessment method, a device, a storage medium and a processor, wherein the project risk assessment method comprises the following steps: acquiring project information data; determining the project risk assessment dimension according to the project information data; and calculating and obtaining a risk index of the project according to a risk assessment grade corresponding to the project risk assessment dimension, wherein the risk index represents the risk complexity of the project. The complexity of the project risk can be obtained based on the project risk index, so that the risk assessment can be carried out on the project at any time, and the assessment dimension and the assessment standard of the project risk can be clearly known, so that objective and accurate risk assessment results can be provided for the strategy adjustment of the project.

Description

Project risk assessment method and device
Technical Field
The invention relates to the technical field of risk assessment, in particular to a project risk assessment method and device.
Background
For the project which is subject to contract, a lot of quality and risk problems exist in the early stage of project execution and in the project delivery process, and project group follow-up is required to realize the tracking of project progress, so that corresponding strategies can be adjusted in the project process to ensure the smooth progress and the delivery quality of project delivery.
The conventional project risk management system carries out risk identification in the project process by predefining a risk mode and then judges the risk of the project, but the project risk identification method can only be carried out in the project process and cannot evaluate the risk complexity at any time, and meanwhile, each evaluation standard of the risk cannot be dynamically mastered.
Disclosure of Invention
In view of the above, the present invention has been made to provide a project risk assessment method and apparatus that overcomes or at least partially solves the above-mentioned problems.
The specific technical scheme is as follows:
a method of project risk assessment, comprising:
acquiring project information data;
determining the project risk assessment dimension according to the project information data;
and calculating and obtaining a risk index of the project according to a risk assessment grade corresponding to the project risk assessment dimension, wherein the risk index represents the risk complexity of the project.
Optionally, the method further comprises:
and generating strategy adjustment suggestion information of the project according to the risk index of the project.
Optionally, the method further comprises:
and carrying out strategy adjustment on the project according to the risk index of the project and/or the strategy adjustment suggestion information of the project.
Optionally, the method further comprises:
and creating a risk management table according to the historical project information data, wherein the risk management table is used for storing the risk assessment dimension, the project risk assessment grade and the project risk assessment index of the historical project.
Optionally, the creating a project risk management table according to the historical project information data includes:
acquiring historical project information data, and determining a project risk evaluation dimension according to the historical project information data;
generating a first mapping relation between the project risk assessment dimension and the risk assessment grade;
generating a second mapping relation between the risk assessment grade and the risk index;
and generating a risk management table of the project according to the first mapping relation and the second mapping relation, and recording the generation logic of the risk management table to generate a macro file.
Optionally, the calculating to obtain the project risk index according to the risk assessment level corresponding to the project risk assessment dimension includes:
and calculating to obtain the project risk index by calling a pre-recorded macro file according to the risk evaluation grade corresponding to the project risk evaluation dimension.
A project risk assessment apparatus comprising:
an acquisition unit configured to acquire project information data;
the determining unit is used for determining the project risk assessment dimension according to the project information data;
and the calculating unit is used for calculating and obtaining the risk index of the project according to the risk evaluation grade corresponding to the project risk evaluation dimension, wherein the risk index represents the risk complexity of the project.
A storage medium comprising a stored program, wherein the program performs the above project risk assessment method.
A processor configured to execute a program, wherein the program executes the above-mentioned project risk assessment method.
By means of the technical scheme, the project risk assessment method, the project risk assessment device, the storage medium and the processor provided by the invention can determine the project risk assessment dimension based on the acquired project information data when a project is not executed or is assessed at any time in the project execution process, namely in the whole life cycle of the project, further calculate and obtain the risk index of the project according to the risk assessment grade corresponding to the project risk assessment dimension, and know the complexity of the project risk based on the project risk index, so that the risk assessment can be performed on the project at any time, and the assessment dimension and the assessment standard of the project risk can be clearly known, so that objective and accurate risk assessment results can be provided for the strategy adjustment of the project.
The foregoing description is only an overview of the technical solutions of the present invention, and the embodiments of the present invention are described below in order to make the technical means of the present invention more clearly understood and to make the above and other objects, features, and advantages of the present invention more clearly understandable.
Drawings
Various other advantages and benefits will become apparent to those of ordinary skill in the art upon reading the following detailed description of the preferred embodiments. The drawings are only for purposes of illustrating the preferred embodiments and are not to be construed as limiting the invention. Also, like reference numerals are used to refer to like parts throughout the drawings. In the drawings:
FIG. 1 is a flow chart of a project risk assessment method according to an embodiment of the present invention;
FIG. 2 is a schematic diagram of a risk management table provided by an embodiment of the invention;
fig. 3 is a schematic structural diagram illustrating a project risk assessment apparatus according to an embodiment of the present invention.
Detailed Description
Exemplary embodiments of the present disclosure will be described in more detail below with reference to the accompanying drawings. While exemplary embodiments of the present disclosure are shown in the drawings, it should be understood that the present disclosure may be embodied in various forms and should not be limited to the embodiments set forth herein. Rather, these embodiments are provided so that this disclosure will be thorough and complete, and will fully convey the scope of the disclosure to those skilled in the art.
In an embodiment of the present invention, a method for assessing risk of a project is provided, which includes, with reference to fig. 1:
and S11, acquiring the project information data.
For each project, project information data of the project are different according to different nodes of project risk monitoring. For example, for a project that has just entered into a contract, the risk of the project as a whole or the risk of the project in the course of later execution needs to be known; the potential risks of each execution link need to be known for the project being executed, so that the potential risks can be known in time, and the strategy adjustment is carried out to ensure that the project is performed normally and smoothly.
The project information data represents the main information of the project, so that the related information of the whole project can be known by workers or project monitoring personnel. For example, the project information data includes, but is not limited to, project name, customer name, contract amount, total number of invested people, total number of invested days, leading business line, other participating business lines, and other information, and these information data can be set by themselves according to different projects.
And S12, determining the project risk assessment dimension according to the project information data.
After the project information data is acquired, an evaluation dimension for evaluating the project risk complexity needs to be set, and the project risk evaluation dimension can be different according to different projects. Thus, the determined project risk assessment dimension is matched with the project to be risk assessed. The risk assessment dimension of the project can be set by itself, or the risk assessment of the completed project can be recorded in the prior art as a reference, for example, the assessment dimension of the project to be subjected to the risk assessment can be determined by referring to the risk assessment dimension of the completed project.
For example, project risk assessment dimensions may include, but are not limited to, complexity of system integration, cross-line delivery management, project delivery, customer environment, customer transfers, contract clause structure, solution manager, risk manager, partners, and so forth.
And S13, calculating and obtaining the risk index of the project according to the risk assessment grade corresponding to the project risk assessment dimension.
In the embodiment of the invention, a corresponding judgment standard is not directly set for each item risk assessment dimension, but risk assessment grades are correspondingly set under each item risk assessment dimension, and the risk assessment grades are pre-stored judgment standards for the risk assessment dimensions, so that the evaluation diversity and objectivity under the same item risk assessment dimension can be ensured. For example, the risk assessment rating may be set to three levels, high, medium, and low, each level corresponding to its assessment rating condition. The weight value for each risk assessment level may also be set for more accurate description.
The risk assessment level conditions are exemplified below by setting the risk assessment level to the third highest gear, the second lowest gear and the third highest gear.
For example, the evaluation condition with a low risk evaluation level is: there are solutions and delivery resources that are relevant prior to the project, based on previously mature technologies or services, rather than new markets and reusable resources, more projects with previously relevant similar experience, etc., low dependency on customers and third party resources, etc.
The evaluation conditions in the risk evaluation scale were: there are related solutions and delivery resources, even mature technologies or services, rather than new markets and reusable resources, more projects with related prior similar experience, etc., low dependency on customer and third party resources, etc.
The evaluation conditions with high risk evaluation grades are as follows: there are no relevant solutions and delivery resources, no mature technologies or services, no reusable resources, no relevant similar experience, full dependence on customer and third party resources, etc.
After the project risk assessment dimension and the project risk assessment grade are determined, the risk index of the project is calculated and obtained according to the grade coefficient or the grade weight value corresponding to the project. Assuming that the item is provided with two risk assessment dimensions corresponding to three branch evaluation levels, taking setting of a weight value as an example for explanation, the method further includes:
setting a weight value of each risk assessment level based on the risk assessment levels;
and calculating to obtain the risk index of the project according to the weight value of each risk assessment grade.
Specifically, the risk assessment system comprises two risk assessment dimensions a and B, wherein the dimension a comprises three criteria a, B and c, the weighted values of the three criteria d, e and f are respectively 1, 5 and 8, the dimension B comprises three criteria d, e and f, the weighted values of the three criteria are respectively 2, 4 and 7, if the item meets the assessment criteria of B in the dimension a, the weighted value of the dimension a is 0.5, and if the item meets the assessment criteria of a in the dimension B, and the weighted value of the dimension B is 0.3, the risk index is 0.5 +0.3 + 2 is 3.1. The above calculation of the risk index by using the weight value is only one method provided in the embodiment of the present invention, and the risk index may also be obtained by calculating through a preset logical correspondence, for example, by calling a macro file representing a logical relationship of the risk index obtained by calculating the risk dimension to perform calculation.
Wherein the risk index characterizes the risk complexity of the item. The risk complexity indicates the risk level of the project, and if the complexity is higher, the risk of the project in the subsequent execution process or in the execution process is higher. Further, as illustrated above, if the risk complexity of the project is first level, the risk index range is [0, 3], if the risk complexity of the project is second level, the risk index range is (3, 6), and the like, the risk index of the project is 3.1, and the risk complexity is second level.
According to the project risk assessment method provided by the invention, when a project is not executed or in the project execution process, namely, assessment is carried out at any time in the whole life cycle of the project, the project risk assessment dimension can be determined based on the obtained project information data, then the risk assessment grade corresponding to the project risk assessment dimension is finally calculated to obtain the risk index of the project, the complexity of the project risk can be obtained based on the project risk index, so that the risk assessment can be carried out on the project at any time, and the assessment dimension and the assessment standard of the project risk can be clearly known, so that objective and accurate risk assessment results can be provided for the strategy adjustment of the project.
In another embodiment of the present invention, after obtaining the risk index, the method further comprises:
and generating strategy adjustment suggestion information of the project according to the risk index of the project.
Specifically, the risk index of the project is calculated according to the risk assessment grade, which represents the complexity of the risk of the project, and since the risk index can be calculated in real time in the project execution process, if the risk index of the project is used to know that the project has a certain risk in the execution process, some strategies in the project are expected to be adjusted to reduce the risk of the project. Thus, after the risk index of the project is obtained, the strategy adjustment suggestion information can be generated according to the risk index. The risk index implicitly includes a risk assessment dimension, a project risk assessment dimension with a high risk assessment level can be obtained after the risk index is obtained through calculation, and policy adjustment suggestion information is generated according to information included in the project risk assessment dimension, for example, if index information representing a technology or a service included in the project risk assessment dimension is lower than a preset standard, the corresponding generated policy adjustment suggestion information corresponds to a relevant parameter for improving the technology or service index. The strategy adjustment suggestion information is generated according to the risk index, and the strategy adjustment information covers more dimensions if the risk index is high, and the strategy adjustment dimensions are less if the risk index is low, so that smooth proceeding of the project can be ensured, and waste of adjustment resources can be reduced. Certainly, a policy adjustment suggestion information table may be preset, where the table includes a plurality of pieces of policy adjustment suggestion information, and each piece of policy adjustment information corresponds to a numerical value of the risk index, that is, a corresponding relationship between the policy risk adjustment information and the risk index is generated, and after the risk index is obtained, the corresponding policy risk adjustment information may be determined according to the corresponding relationship.
Correspondingly, strategy adjustment is carried out on the project according to the risk index of the project and/or the project adjustment suggestion information, so that the project can be normally carried out.
That is, in the process of risk analysis of a project, in addition to calculating and obtaining a risk index, strategy adjustment suggestion information of the project can be generated according to the risk index. It should be noted that the policy adjustment suggestions for these projects may be automatically generated according to the risk assessment dimension, that is, the suggestions provided for the project assessment dimension, or may be generated according to the risk assessment level of the project, that is, the relevant executives may be replaced, or the project nodes may be modified.
Therefore, while performing risk assessment on the project, the method can autonomously generate the strategy adjustment suggestion information of the project, display the strategy adjustment suggestion information so that the risk control staff can know the strategy adjustment suggestion information, and certainly perform strategy adjustment on the project based on the strategy adjustment suggestions, or adjust the project according to the set strategy. Specifically, if the strategy of the project is adjusted according to the project risk index, the project management and control staff can obtain the execution condition of the project through the project risk index based on the project, obtain the current execution information of the project, and adjust the information which affects the project risk index and is included in the execution information, so as to reduce the risk of the project in the subsequent execution process. If the strategy adjustment is performed on the project according to the strategy adjustment information of the project, the corresponding adjustment information or adjustment parameter in the strategy adjustment information can be acquired, the project is adjusted according to the adjustment information or adjustment parameter, or the adjustment information or adjustment parameter can be sent to the corresponding project control personnel, and the strategy adjustment is performed on the project after the adjustment information or adjustment parameter is determined. The embodiment of the invention is not limited in this respect, and the response is made by referring to the risk index both in the nature of the adjustment period and the autonomous adjustment period.
In order to facilitate the presentation of the risk assessment of the project information or the intuitive understanding of the risk management personnel, the assessment process and the result of the project risk can be displayed based on a form or a document. The project information that has been evaluated can also be recorded and presented in the mode of a risk management table.
Namely, a risk management table is created according to the information data of the historical project, wherein the risk management table is used for storing the risk assessment dimension, the project risk assessment grade and the project risk assessment index of the historical project.
Specifically, a risk management table is created according to the historical project information data, wherein the risk management table is used for storing risk assessment dimensions, project risk assessment grades and project risk assessment indexes of the historical projects.
The specific process of generating the risk management table may be as follows:
generating a first mapping relation between the project risk assessment dimension and the risk assessment grade;
generating a second mapping relation between the risk assessment grade and the risk index;
and generating a risk management table of the project according to the first mapping relation and the second mapping relation, and recording the generation logic of the risk management table to generate a macro file.
It should be noted that, when the macro file is recorded, processes of how to match the risk assessment level with the risk assessment dimension and how to match the risk index with the risk assessment level are mainly recorded.
Referring to fig. 2, a schematic diagram of a risk management table provided for the embodiment of the present invention is provided, in which related information of the project is recorded, and various evaluation dimensions, such as "complexity of integrated system", "project executor", "project period", and also risk level and level evaluation condition of the project, and a final risk evaluation result, are recorded. The project risk management and control personnel can intuitively know the evaluation process of the project. Of course, the risk management table can also be stored, and a favorable reference is provided for the auditing of an auditing department.
In order to represent the project risk assessment result in more detail, a risk assessment report can be generated according to the project risk assessment dimension, and the risk assessment report under different dimensions is sent to the pre-stored contact matched with the risk assessment report, so that management and control personnel can know the assessment process of the project in time at any place conveniently. Certainly, the contact person is only stored in advance in one mode in the embodiment of the present invention, and may be automatically sent to the contact person related to the project in advance, or may be sent to any person needing to obtain the evaluation result, such as a project person, a company leadership person, and the like, directly by inputting the contact person without storing in advance.
In response to the fact that a certain link of a certain project is changed in the process of risk assessment of the project, after change information is obtained, the assessment dimension and the assessment standard of the project can be directly updated in time, and assessment accuracy of the whole process is guaranteed.
Specifically, the project risk assessment method provided by the embodiment of the present invention can be specifically implemented by using functions in some office software, so that the operation cost of the method can be reduced, and the popularization range of the method is wider.
The different dimensions of the corresponding evaluation and the use of some associated formulas of the corresponding EXCEL are configured in this tool or plug-in. And inputting information of related items so that the final report can know which item is when being discharged. The evaluation dimension for evaluating the risk complexity of the project is set, and the evaluation dimension can be set according to different projects. Each dimension may be set with different evaluation criteria. Setting internal commands through a corresponding EXCEL formula according to a certain logic relationship, realizing a corresponding logic calculation relationship through macros, obtaining different dimensionality recording macros according to the previous setting, and determining the risk complexity through different combinations. And obtaining a final report of the risk result according to the selected answer: the risk of the three grades of different high, medium and low grades can be selected for different dimensions, the risk complexity and the risk level can be automatically evaluated by clicking operation, wherein the risk complexity is set by different combinations through the nested macros in the previous step, the risk level is also set through the macros, and the specific risk level can be set according to the project. If a general report is to be generated, the general report can be realized by the formula of EXCEL, the statements of Isblank, contentnate, index and If, and the final general report can be obtained by the statements, including the basic information of the item, the evaluation time, the version number and the risk complexity, and the risk complexity can be recorded at any time. Therefore, the risk complexity of the project can be evaluated at any time point and any time period through the tool, and corresponding strategy adjustment can be carried out according to the evaluation result.
There is therefore also provided, in another embodiment of the present invention, a method of calculating a risk index, including:
and calculating to obtain the project risk index by calling a pre-recorded macro file according to the risk evaluation grade corresponding to the project risk evaluation dimension.
The calculation of the item risk index in this embodiment is accomplished by calling a macro file. The macro file is used for macro recording in the process of processing the batch data information, so that the next time the same type of data information is processed, the macro file can be directly called to obtain a processing result. The macro file in the embodiment of the present invention is a macro recording based on a process of summarizing, counting, analyzing, and risk evaluating historical project information, that is, the macro file is a recording of a process of creating a risk management table.
Correspondingly, in an embodiment of the present invention, there is also provided a project risk assessment apparatus, referring to fig. 3, including:
an acquisition unit 10 for acquiring project information data;
a determining unit 20, configured to determine the project risk assessment dimension according to the project information data;
and the calculating unit 30 is used for calculating and obtaining a risk index of the project according to the risk assessment grade corresponding to the project risk assessment dimension, wherein the risk index represents the risk complexity of the project.
Further, the apparatus further comprises:
and the generating unit is used for generating strategy adjustment suggestion information of the project according to the risk index of the project.
Further, the apparatus further comprises:
and the adjusting unit is used for carrying out strategy adjustment on the project according to the risk index of the project and/or the project adjustment suggestion information.
Further, the apparatus further comprises:
and the management table creating unit is used for creating a risk management table according to the historical project information data, wherein the risk management table is used for storing the risk evaluation dimension, the project risk evaluation grade and the project risk evaluation index of the historical project.
Further, the management table creating unit includes:
the dimension determining subunit is used for acquiring historical project information data and determining project risk assessment dimensions according to the historical project information data;
the first generation subunit is used for generating a first mapping relation between the project risk assessment dimension and the risk assessment grade;
the second generation subunit is used for generating a second mapping relation between the risk assessment grade and the risk index;
and the third generation subunit is used for generating a risk management table of the project according to the first mapping relation and the second mapping relation, recording the generation logic of the risk management table and generating a macro file.
Further, the computing unit is specifically configured to:
and calculating to obtain the project risk index by calling a pre-recorded macro file according to the risk evaluation grade corresponding to the project risk evaluation dimension.
Further, the apparatus further comprises:
the report generating unit is used for generating a risk assessment report according to each item risk assessment dimension;
and the sending unit is used for sending the risk assessment report to a pre-stored contact person.
According to the project risk assessment device provided by the invention, when a project is not executed or the project is executed, namely the project is assessed at any time in the whole life cycle of the project, the project risk assessment dimension can be determined in the determining unit based on the project information data acquired by the acquiring unit, and then the complexity of the project risk can be obtained based on the project risk index according to the risk index of the project calculated and acquired in the calculating unit, so that the risk assessment can be performed on the project at any time, and the assessment dimension and the assessment standard of the project risk can be clearly known, so that objective and accurate risk assessment results can be provided for the strategy adjustment of the project.
It should be noted that, for the working processes of each module, sub-module, and unit in this embodiment, please refer to the corresponding description in the above embodiments, which is not described herein again.
Optionally, an embodiment of the present invention further provides a project risk assessment apparatus, where the obtaining unit, the determining unit, and the calculating unit are all stored in a memory as program units, and a processor executes the program units stored in the memory to implement corresponding functions.
The processor comprises a kernel, and the kernel calls the corresponding program unit from the memory. The kernel can be set to be one or more than one, risk assessment can be carried out on the project at any time by adjusting kernel parameters, and assessment dimensions and assessment standards of the risk of the project can be clearly known, so that objective and accurate risk assessment results can be provided for strategy adjustment of the project.
The memory may include volatile memory in a computer readable medium, Random Access Memory (RAM) and/or nonvolatile memory such as Read Only Memory (ROM) or flash memory (flash RAM), and the memory includes at least one memory chip.
An embodiment of the present invention provides a storage medium on which a program is stored, the program implementing a project risk assessment method when executed by a processor.
The embodiment of the invention provides a processor, which is used for running a program, wherein the program executes the project risk assessment method during running.
The embodiment of the invention provides equipment, which comprises a processor, a memory and a program which is stored on the memory and can run on the processor, wherein the processor executes the program and realizes the following steps:
acquiring project information data;
determining the project risk assessment dimension according to the project information data;
and calculating and obtaining a risk index of the project according to a risk assessment grade corresponding to the project risk assessment dimension, wherein the risk index represents the risk complexity of the project.
Further, the method also comprises the following steps:
and generating strategy adjustment suggestion information of the project according to the risk index of the project.
Further, the method also comprises the following steps:
and carrying out strategy adjustment on the project according to the risk index of the project and/or the strategy adjustment suggestion information of the project.
Further, the method also comprises the following steps:
and creating a risk management table according to the historical project information data, wherein the risk management table is used for storing the risk assessment dimension, the project risk assessment grade and the project risk assessment index of the historical project.
Further, the creating of the project risk management table according to the historical project information data includes:
acquiring historical project information data, and determining a project risk evaluation dimension according to the historical project information data;
generating a first mapping relation between the project risk assessment dimension and the risk assessment grade;
generating a second mapping relation between the risk assessment grade and the risk index;
and generating a risk management table of the project according to the first mapping relation and the second mapping relation, and recording the generation logic of the risk management table to generate a macro file.
Further, the calculating and obtaining the project risk index according to the risk assessment level corresponding to the project risk assessment dimension includes:
and calculating to obtain the project risk index by calling a pre-recorded macro file according to the risk evaluation grade corresponding to the project risk evaluation dimension.
As will be appreciated by one skilled in the art, embodiments of the present application may be provided as a method, system, or computer program product. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, and the like) having computer-usable program code embodied therein.
The present application is described with reference to flowchart illustrations and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the application. It will be understood that each flow and/or block of the flow diagrams and/or block diagrams, and combinations of flows and/or blocks in the flow diagrams and/or block diagrams, can be implemented by computer program instructions. These computer program instructions may be provided to a processor of a general purpose computer, special purpose computer, embedded processor, or other programmable data processing apparatus to produce a machine, such that the instructions, which execute via the processor of the computer or other programmable data processing apparatus, create means for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be stored in a computer-readable memory that can direct a computer or other programmable data processing apparatus to function in a particular manner, such that the instructions stored in the computer-readable memory produce an article of manufacture including instruction means which implement the function specified in the flowchart flow or flows and/or block diagram block or blocks.
These computer program instructions may also be loaded onto a computer or other programmable data processing apparatus to cause a series of operational steps to be performed on the computer or other programmable apparatus to produce a computer implemented process such that the instructions which execute on the computer or other programmable apparatus provide steps for implementing the functions specified in the flowchart flow or flows and/or block diagram block or blocks.
In a typical configuration, a computing device includes one or more processors (CPUs), input/output interfaces, network interfaces, and memory.
The memory may include forms of volatile memory in a computer readable medium, Random Access Memory (RAM) and/or non-volatile memory, such as Read Only Memory (ROM) or flash memory (flash RAM). The memory is an example of a computer-readable medium.
Computer-readable media, including both non-transitory and non-transitory, removable and non-removable media, may implement information storage by any method or technology. The information may be computer readable instructions, data structures, modules of a program, or other data. Examples of computer storage media include, but are not limited to, phase change memory (PRAM), Static Random Access Memory (SRAM), Dynamic Random Access Memory (DRAM), other types of Random Access Memory (RAM), Read Only Memory (ROM), Electrically Erasable Programmable Read Only Memory (EEPROM), flash memory or other memory technology, compact disc read only memory (CD-ROM), Digital Versatile Discs (DVD) or other optical storage, magnetic cassettes, magnetic tape magnetic disk storage or other magnetic storage devices, or any other non-transmission medium that can be used to store information that can be accessed by a computing device. As defined herein, a computer readable medium does not include a transitory computer readable medium such as a modulated data signal and a carrier wave.
It should also be noted that the terms "comprises," "comprising," or any other variation thereof, are intended to cover a non-exclusive inclusion, such that a process, method, article, or apparatus that comprises a list of elements does not include only those elements but may include other elements not expressly listed or inherent to such process, method, article, or apparatus. Without further limitation, an element defined by the phrase "comprising an … …" does not exclude the presence of other identical elements in the process, method, article, or apparatus that comprises the element.
As will be appreciated by one skilled in the art, embodiments of the present application may be provided as a method, system, or computer program product. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including, but not limited to, disk storage, CD-ROM, optical storage, and the like) having computer-usable program code embodied therein.
The above are merely examples of the present application and are not intended to limit the present application. Various modifications and changes may occur to those skilled in the art. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present application should be included in the scope of the claims of the present application.

Claims (10)

1. A method for project risk assessment, comprising:
acquiring project information data;
determining the project risk assessment dimension according to the project information data;
and calculating and obtaining a risk index of the project according to a risk assessment grade corresponding to the project risk assessment dimension, wherein the risk index represents the risk complexity of the project.
2. The method of claim 1, further comprising:
and generating strategy adjustment suggestion information of the project according to the risk index of the project.
3. The method of claim 2, further comprising:
and carrying out strategy adjustment on the project according to the risk index of the project and/or the strategy adjustment suggestion information of the project.
4. The method of claim 1, further comprising:
and creating a risk management table according to the historical project information data, wherein the risk management table is used for storing the risk assessment dimension, the project risk assessment grade and the project risk assessment index of the historical project.
5. The method of claim 4, said creating an item risk management table from historical item information data, comprising:
acquiring historical project information data, and determining a project risk evaluation dimension according to the historical project information data;
generating a first mapping relation between the project risk assessment dimension and the risk assessment grade;
generating a second mapping relation between the risk assessment grade and the risk index;
and generating a risk management table of the project according to the first mapping relation and the second mapping relation, and recording the generation logic of the risk management table to generate a macro file.
6. The method according to claim 5, wherein the calculating the item risk index according to the risk assessment level corresponding to the item risk assessment dimension comprises:
and calculating to obtain the project risk index by calling a pre-recorded macro file according to the risk evaluation grade corresponding to the project risk evaluation dimension.
7. The method of claim 1, further comprising:
generating a risk assessment report according to each item risk assessment dimension;
and sending the risk assessment report to a pre-stored contact.
8. A project risk assessment apparatus, comprising:
an acquisition unit configured to acquire project information data;
the determining unit is used for determining the project risk assessment dimension according to the project information data;
and the calculating unit is used for calculating and obtaining the risk index of the project according to the risk evaluation grade corresponding to the project risk evaluation dimension, wherein the risk index represents the risk complexity of the project.
9. A storage medium comprising a stored program, wherein the program performs the project risk assessment method of any one of claims 1 to 7.
10. A processor configured to run a program, wherein the program when running performs the method of risk assessment of a project of any one of claims 1 to 7.
CN201811092186.2A 2018-09-19 2018-09-19 Project risk assessment method and device Pending CN110929965A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811092186.2A CN110929965A (en) 2018-09-19 2018-09-19 Project risk assessment method and device

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811092186.2A CN110929965A (en) 2018-09-19 2018-09-19 Project risk assessment method and device

Publications (1)

Publication Number Publication Date
CN110929965A true CN110929965A (en) 2020-03-27

Family

ID=69855084

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811092186.2A Pending CN110929965A (en) 2018-09-19 2018-09-19 Project risk assessment method and device

Country Status (1)

Country Link
CN (1) CN110929965A (en)

Cited By (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111489074A (en) * 2020-04-07 2020-08-04 支付宝(杭州)信息技术有限公司 Data processing method, device, equipment and storage medium
CN111832912A (en) * 2020-06-28 2020-10-27 厦门思在信息科技有限公司 Project feasibility management and control method, device and terminal based on risk assessment
CN112001629A (en) * 2020-08-24 2020-11-27 北京鸿联九五信息产业有限公司 Risk early warning method, device, system and storage medium
CN112308460A (en) * 2020-11-23 2021-02-02 国网北京市电力公司 Safety production risk assessment method and device, processor and risk assessment system
CN112651616A (en) * 2020-12-21 2021-04-13 深圳科诺医学检验实验室 Project system person analysis and evaluation method, application server, system and medium
CN113935566A (en) * 2021-07-30 2022-01-14 中煤建工集团有限公司 Risk assessment method based on confidence index
CN114429296A (en) * 2022-01-24 2022-05-03 深圳市商汤科技有限公司 Risk assessment method and device, electronic equipment and readable storage medium
CN115953032A (en) * 2023-03-10 2023-04-11 山东柏源技术有限公司 Enterprise project execution risk assessment system based on data analysis
CN117575335A (en) * 2024-01-17 2024-02-20 成都赛力斯科技有限公司 Vehicle development project risk monitoring method, device, system, equipment and medium

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070271198A1 (en) * 2006-05-19 2007-11-22 Accenture Global Services Gmbh Semi-quantitative risk analysis
CN106780117A (en) * 2016-12-02 2017-05-31 国网浙江省电力公司经济技术研究院 A kind of power distribution network project financial leasing methods of risk assessment
US20170308966A1 (en) * 2016-04-22 2017-10-26 Economy Research Institute of State Grid Zhejiang Electric Power Post-evaluation and risk management and control method of power transmission engineering cost
CN108280762A (en) * 2018-01-19 2018-07-13 平安科技(深圳)有限公司 Customer risk ranking method, server and computer readable storage medium

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20070271198A1 (en) * 2006-05-19 2007-11-22 Accenture Global Services Gmbh Semi-quantitative risk analysis
US20170308966A1 (en) * 2016-04-22 2017-10-26 Economy Research Institute of State Grid Zhejiang Electric Power Post-evaluation and risk management and control method of power transmission engineering cost
CN106780117A (en) * 2016-12-02 2017-05-31 国网浙江省电力公司经济技术研究院 A kind of power distribution network project financial leasing methods of risk assessment
CN108280762A (en) * 2018-01-19 2018-07-13 平安科技(深圳)有限公司 Customer risk ranking method, server and computer readable storage medium

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
汪树年: ""筑工程项目风险评估与分析", 《安徽建筑》 *

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111489074A (en) * 2020-04-07 2020-08-04 支付宝(杭州)信息技术有限公司 Data processing method, device, equipment and storage medium
CN111832912A (en) * 2020-06-28 2020-10-27 厦门思在信息科技有限公司 Project feasibility management and control method, device and terminal based on risk assessment
CN112001629A (en) * 2020-08-24 2020-11-27 北京鸿联九五信息产业有限公司 Risk early warning method, device, system and storage medium
CN112308460A (en) * 2020-11-23 2021-02-02 国网北京市电力公司 Safety production risk assessment method and device, processor and risk assessment system
CN112651616A (en) * 2020-12-21 2021-04-13 深圳科诺医学检验实验室 Project system person analysis and evaluation method, application server, system and medium
CN112651616B (en) * 2020-12-21 2022-11-08 深圳科诺医学检验实验室 Project system person analysis and evaluation method, application server, system and medium
CN113935566A (en) * 2021-07-30 2022-01-14 中煤建工集团有限公司 Risk assessment method based on confidence index
CN114429296A (en) * 2022-01-24 2022-05-03 深圳市商汤科技有限公司 Risk assessment method and device, electronic equipment and readable storage medium
CN115953032A (en) * 2023-03-10 2023-04-11 山东柏源技术有限公司 Enterprise project execution risk assessment system based on data analysis
CN117575335A (en) * 2024-01-17 2024-02-20 成都赛力斯科技有限公司 Vehicle development project risk monitoring method, device, system, equipment and medium
CN117575335B (en) * 2024-01-17 2024-05-03 成都赛力斯科技有限公司 Vehicle development project risk monitoring method, device, system, equipment and medium

Similar Documents

Publication Publication Date Title
CN110929965A (en) Project risk assessment method and device
US10592811B1 (en) Analytics scripting systems and methods
CN109542789B (en) Code coverage rate statistical method and device
CN106156809A (en) For updating the method and device of disaggregated model
US10740679B1 (en) Analytics scripting systems and methods
CN109299178A (en) A kind of application method and data analysis system
CN112116313A (en) Employee portrait-based approval method, device and medium
CN110363468B (en) Method and device for determining purchase order, server and readable storage medium
CN118446744A (en) Rights and interests data conversion method and system based on artificial intelligence
CN117436924A (en) Sales data analysis method, equipment and medium based on Web front-end technology
CN110858355A (en) Project budget balance prediction method and device
CN112580915A (en) Project milestone determination method and device, storage medium and electronic equipment
De Andrés et al. Using nonlinear quantile regression for the estimation of software cost
CN114548631A (en) Dynamic evaluation method and device
CN112348455A (en) Warehouse area attendance checking method, device and medium
CN111210110A (en) Method and device for generating prevention strategy based on stress test and electronic equipment
Pereira et al. A multicriteria decision making model for assessment and selection of an ERP in a logistics context
CN115841275B (en) Physical examination method and device based on AI (advanced technology attachment) data management level
Pribil et al. A churn analysis using data mining techniques: Case of electricity distribution company
CN111062816B (en) Account asset supervision method and device
Redkin et al. 3.5 PROCEDURES AND TOOLS OF PROJECT MARKETING IN THE CREATION OF INNOVATIONS AND SYSTEMS OF THEIR HIGH-TECH PRODUCTION
CN117407583A (en) Recommendation method and device, electronic equipment and storage medium
CN116911982A (en) Financial credit user screening method and device and electronic equipment
CN113723710A (en) Customer loss prediction method, system, storage medium and electronic equipment
CN117611115A (en) Salary generation method, system, storage medium and processor

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication

Application publication date: 20200327

RJ01 Rejection of invention patent application after publication