CN110886418A - Combined building curtain wall - Google Patents

Combined building curtain wall Download PDF

Info

Publication number
CN110886418A
CN110886418A CN201911312658.5A CN201911312658A CN110886418A CN 110886418 A CN110886418 A CN 110886418A CN 201911312658 A CN201911312658 A CN 201911312658A CN 110886418 A CN110886418 A CN 110886418A
Authority
CN
China
Prior art keywords
frame
curtain wall
fixed
attachment
movable
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911312658.5A
Other languages
Chinese (zh)
Inventor
刘升华
周虎山
周正
古桂林
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHENZHEN GASU ADORN DESIGN ENGINEERING Co Ltd
Original Assignee
SHENZHEN GASU ADORN DESIGN ENGINEERING Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN GASU ADORN DESIGN ENGINEERING Co Ltd filed Critical SHENZHEN GASU ADORN DESIGN ENGINEERING Co Ltd
Priority to CN201911312658.5A priority Critical patent/CN110886418A/en
Publication of CN110886418A publication Critical patent/CN110886418A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04BGENERAL BUILDING CONSTRUCTIONS; WALLS, e.g. PARTITIONS; ROOFS; FLOORS; CEILINGS; INSULATION OR OTHER PROTECTION OF BUILDINGS
    • E04B2/00Walls, e.g. partitions, for buildings; Wall construction with regard to insulation; Connections specially adapted to walls
    • E04B2/88Curtain walls
    • E04B2/96Curtain walls comprising panels attached to the structure through mullions or transoms
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B3/00Window sashes, door leaves, or like elements for closing wall or like openings; Layout of fixed or moving closures, e.g. windows in wall or like openings; Features of rigidly-mounted outer frames relating to the mounting of wing frames
    • E06B3/32Arrangements of wings characterised by the manner of movement; Arrangements of movable wings in openings; Features of wings or frames relating solely to the manner of movement of the wing
    • E06B3/34Arrangements of wings characterised by the manner of movement; Arrangements of movable wings in openings; Features of wings or frames relating solely to the manner of movement of the wing with only one kind of movement
    • E06B3/42Sliding wings; Details of frames with respect to guiding
    • E06B3/46Horizontally-sliding wings
    • EFIXED CONSTRUCTIONS
    • E06DOORS, WINDOWS, SHUTTERS, OR ROLLER BLINDS IN GENERAL; LADDERS
    • E06BFIXED OR MOVABLE CLOSURES FOR OPENINGS IN BUILDINGS, VEHICLES, FENCES OR LIKE ENCLOSURES IN GENERAL, e.g. DOORS, WINDOWS, BLINDS, GATES
    • E06B7/00Special arrangements or measures in connection with doors or windows
    • E06B7/16Sealing arrangements on wings or parts co-operating with the wings
    • E06B7/22Sealing arrangements on wings or parts co-operating with the wings by means of elastic edgings, e.g. elastic rubber tubes; by means of resilient edgings, e.g. felt or plush strips, resilient metal strips
    • E06B7/23Plastic, sponge rubber, or like strips or tubes

Landscapes

  • Engineering & Computer Science (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Physics & Mathematics (AREA)
  • Electromagnetism (AREA)
  • Load-Bearing And Curtain Walls (AREA)

Abstract

本发明公开了一种组合式建筑幕墙,包括外侧与土建结构连接的上附框、下附框、左附框、右附框,对应设于附框内侧的上框、下框、左框、右框构成;还包括卡接于所述主框中的两扇固定幕墙,两扇能相对于该固定幕墙平面滑动的活动幕墙;所述的两扇固定幕墙分别设置于两侧,所述的活动幕墙能够向中间滑动对接或各自向两侧滑动。本发明采用非常便于现场安装的主框、附框组合体系,有效解决了框架式玻璃幕墙现场安装工作量大,控制点多,安装周期长,质量难于保证的问题,以及有效解决了单元式幕墙运输比困难,成本高,维修或更换比较困难的问题。

Figure 201911312658

The invention discloses a combined building curtain wall, comprising an upper attachment frame, a lower attachment frame, a left attachment frame and a right attachment frame which are connected with the civil structure on the outside, and the upper frame, the lower frame, the left frame, The right frame is formed; it also includes two fixed curtain walls clamped on the main frame, and the two movable curtain walls can slide relative to the fixed curtain wall plane; the two fixed curtain walls are respectively arranged on both sides, and the two The movable curtain wall can be slid to the middle or to each side. The invention adopts the main frame and the attached frame combination system which is very convenient for on-site installation, effectively solves the problems of large on-site installation workload, many control points, long installation period and difficult quality assurance of the frame type glass curtain wall, and effectively solves the problems of the unit type curtain wall. Problems that are difficult to transport, high cost, and difficult to repair or replace.

Figure 201911312658

Description

一种组合式建筑幕墙A composite building curtain wall

技术领域technical field

本发明涉及建筑幕墙,具体涉及一种组合式建筑幕墙。The invention relates to a building curtain wall, in particular to a combined building curtain wall.

背景技术Background technique

目前随着人们对建筑物外观的美观性及使用功能要求的不断提高,玻璃幕墙作为建筑物外墙装饰用的重要结构形式,建筑幕墙具有建设速度快、结构质量轻、易维护的特点。因此,建筑幕墙在当今的建筑物中得到了极为广泛的应用。At present, with the continuous improvement of people's requirements for the appearance of buildings and their functional requirements, glass curtain walls are an important structural form for building exterior wall decoration. Building curtain walls have the characteristics of fast construction, light structure and easy maintenance. Therefore, the building curtain wall has been widely used in today's buildings.

目前国内外大面积使用的一般有单元式幕墙和构件式建筑幕墙两种,这两种幕墙均存在各自的优缺点,在应用上也受到一定的限制。主要表现在:框架式玻璃幕墙是先将工厂制作的一根根元件(立柱、横梁)和一块块玻璃(组件)运往工地,将立柱用连接件安装在主体结构上,再在立柱上安装横梁,形成幕墙框格后安装固定玻璃(组件)。因此,框架式玻璃幕墙构造简单,适应主体结构能力强,安装顺序基本不受主体结构的影响。但框架式玻璃幕墙现场安装工作量大,控制点多,安装周期长,质量难于保证;单元式幕墙是指由各种幕墙面板与支承框架在一个完整的幕墙结构基本单元,直接安装在主体结构上的建筑幕墙。单元式幕墙在工厂不仅要加工竖框、横框等元件,还要用这些元件拼装成单元组件框,并将幕墙面板(玻璃、铝板等)安装在单元组件框的相应位置上,形成单元组件。单元式幕墙主要工作量是在工厂完成,大大提高劳动生产率和产品质量。但由于单元式幕墙在工厂组装成了单元组件,所以运输比较困难,同时受单元式幕墙构造影响,单元式幕墙的铝型材用量较大,成本一般比采用相同材料的框架式幕墙高,维修或更换比较困难。At present, there are generally two types of unit curtain walls and component building curtain walls used in large areas at home and abroad. Both of these two types of curtain walls have their own advantages and disadvantages, and are also limited in application. Mainly as follows: the frame glass curtain wall is to first transport the factory-made elements (columns, beams) and pieces of glass (components) to the construction site, install the columns on the main structure with connectors, and then install the beams on the columns. , and then install the fixed glass (component) after forming the curtain wall frame. Therefore, the frame type glass curtain wall has a simple structure, strong ability to adapt to the main structure, and the installation sequence is basically not affected by the main structure. However, the on-site installation of framed glass curtain wall has a large workload, many control points, long installation period, and difficult to guarantee quality; on the building curtain wall. In the factory, the unitized curtain wall not only needs to process the mullion, horizontal frame and other components, but also use these components to assemble the unit component frame, and install the curtain wall panel (glass, aluminum plate, etc.) on the corresponding position of the unit component frame to form the unit component. . The main workload of the unitized curtain wall is completed in the factory, which greatly improves labor productivity and product quality. However, because the unitized curtain wall is assembled into unit components in the factory, it is difficult to transport. At the same time, due to the structure of the unitized curtain wall, the amount of aluminum profiles in the unitized curtain wall is larger, and the cost is generally higher than that of the framed curtain wall using the same material. Maintenance or It is more difficult to replace.

因此,如何解决框架式玻璃幕墙现场安装工作量大,控制点多,安装周期长,质量难于保证的问题,以及解决单元式幕墙运输比困难,成本高,维修或更换比较困难的问题成为业界的重要工作。Therefore, how to solve the problems of large on-site installation workload, many control points, long installation period, and difficult quality assurance of framed glass curtain walls, and how to solve the problems of difficult transportation, high cost, and difficult maintenance or replacement of unitized curtain walls have become the industry's most common problems. important work.

发明内容SUMMARY OF THE INVENTION

本发明提供一种组合式建筑幕墙,以解决框架式玻璃幕墙现场安装工作量大,控制点多,安装周期长,质量难于保证的问题,以及解决单元式幕墙运输比困难,成本高,维修或更换比较困难的问题。The invention provides a combined building curtain wall to solve the problems of large installation workload, many control points, long installation period and difficult quality assurance of the frame type glass curtain wall on site, as well as to solve the problems of the unit type curtain wall being difficult to transport, high cost, maintenance or repair. Replacing more difficult problems.

本发明提出的一种组合式建筑幕墙,其包括外侧与土建结构连接的附框,该附框由上附框、下附框、左附框、右附框构成,设于该附框内侧的主框,该主框由上框、下框、左框、右框构成;还包括卡接于所述主框内侧中的两扇固定幕墙,能相对于该固定幕墙的平面滑动的两扇活动幕墙;所述的两扇固定幕墙分别设置于所述主框的两侧,所述的活动幕墙能够向中间滑动对接或各自向两侧滑动打开。A combined building curtain wall proposed by the present invention includes an attachment frame connected to the civil structure on the outside, and the attachment frame is composed of an upper attachment frame, a lower attachment frame, a left attachment frame, and a right attachment frame. The main frame, which is composed of an upper frame, a lower frame, a left frame and a right frame; it also includes two fixed curtain walls that are clamped on the inner side of the main frame, and can slide relative to the plane of the fixed curtain wall. Curtain walls; the two fixed curtain walls are respectively arranged on both sides of the main frame, and the movable curtain walls can be slidably connected to the middle or slid open to both sides respectively.

较优的,所述附框的内侧为槽型结构,附框的内侧面设有耐候密封胶,所述主框的四侧对应嵌入所述附框的凹槽中,所述的附框侧面和主框侧面之间的间隙设有定位密封条作固定密封。Preferably, the inner side of the attached frame is a groove structure, the inner side of the attached frame is provided with weather-resistant sealant, the four sides of the main frame are correspondingly embedded in the grooves of the attached frame, and the side of the attached frame is embedded in the groove of the attached frame. The gap between it and the side of the main frame is provided with a positioning sealing strip for fixed sealing.

较优的,所述的固定幕墙包括分别设于上框内侧、左右框的内侧以及下框内侧的面板扣件,还包括上端与所述上框内侧连接、下端与所述下框内侧连接的固定立框,设于该固定立框内侧的卡槽,固定面板的四边分别卡插于所述的面板扣件及卡槽的卡槽内,固定面板的两侧平面与面板扣件之间设有第二定位密封胶条。Preferably, the fixed curtain wall includes panel fasteners respectively arranged on the inner side of the upper frame, the inner side of the left and right frames, and the inner side of the lower frame, and also includes a panel fastener whose upper end is connected to the inner side of the upper frame, and the lower end is connected to the inner side of the lower frame. The fixed vertical frame is provided with a card slot on the inner side of the fixed vertical frame, the four sides of the fixed panel are respectively inserted into the said panel fastener and the card slot of the card slot, and the two sides of the fixed panel and the panel fastener are provided between There is a second positioning sealant strip.

较优的,所述的活动幕墙包括由上活动门扇、下活动门扇以及两侧立框构成的活动门扇,分别设于所述上活动门扇、下活动门扇以及两侧立框内侧卡槽,活动面板的四边分别卡插于所述的卡槽内,活动面板的两侧与卡槽之间设有第二定位密封胶条;所述上活动门扇侧面及下活动门扇侧面与所述上框、下框之间设有密封条。Preferably, the movable curtain wall includes a movable door leaf composed of an upper movable door leaf, a lower movable door leaf and vertical frames on both sides, which are respectively arranged on the upper movable door leaf, the lower movable door leaf and the inner card slots of the vertical frames on both sides. The four sides of the panel are respectively inserted into the card slots, and a second positioning sealant strip is arranged between the two sides of the movable panel and the card slots; the side surfaces of the upper movable door leaf and the lower movable door leaf are connected to the upper frame, There is a sealing strip between the lower frames.

较优的,所述下活动门扇的底面横向设有凹槽,该凹槽中设有滑轮,该滑轮能沿着设于所述下框上的滑轨移动。Preferably, a groove is laterally provided on the bottom surface of the lower movable door leaf, and a pulley is arranged in the groove, and the pulley can move along a slide rail provided on the lower frame.

较优的,所述的下附框通过一横梁与下侧的土建结构连接;Preferably, the lower attached frame is connected to the lower civil structure through a beam;

较优的,所述横梁与所述下附框之间、横梁与土建结构之间均设有弹性件,所述的下附框与横梁、横梁与土建结构之间的缝隙设有耐候密封胶。Preferably, elastic parts are provided between the beam and the lower frame, between the beam and the civil structure, and the gaps between the lower frame and the beam, and the beam and the civil structure are provided with weather-resistant sealant. .

较优的,所述的下框底部的外侧面设有耐候密封胶;所述下框中和下附框外侧壁体上设有排水孔。Preferably, the outer side of the bottom of the lower frame is provided with weather-resistant sealant; and the outer side walls of the lower frame and the lower attached frame are provided with drainage holes.

较优的,所述固定立框的朝向所述活动门扇的侧面设有限制对应活动幕墙向中间越位移动的U形槽,每一活动门扇上外端立框的内侧设有与所述U形槽对应钩挂的挂钩。Preferably, the side of the fixed vertical frame facing the movable door leaf is provided with a U-shaped groove that restricts the offside movement of the corresponding movable curtain wall to the middle, and the inner side of the upper outer end vertical frame of each movable door leaf is provided with the U-shaped groove. The slots correspond to the hooks that are hooked.

较优的,所述的两活动门扇对接的立框侧面设有密封胶条。Preferably, a sealing strip is provided on the side of the vertical frame where the two movable door leaves are butted.

本发明与现有技术的构造相比,在于设置了非常便于现场组装、安装的主框、附框组合体系,有效解决了框架式玻璃幕墙现场安装工作量大,控制点多,安装周期长,质量难于保证的问题,以及有效解决了单元式幕墙运输比困难,成本高,维修或更换比较困难的问题。Compared with the structure of the prior art, the present invention is provided with a main frame and an additional frame combination system that is very convenient for on-site assembly and installation, effectively solving the problem of the large on-site installation workload, many control points and long installation period of the frame-type glass curtain wall. The problem that the quality is difficult to guarantee, and the problem that the unitized curtain wall is difficult to transport, the cost is high, and the maintenance or replacement is difficult.

附图说明Description of drawings

图1为本发明实施例的封闭状态示意图;1 is a schematic diagram of a closed state according to an embodiment of the present invention;

图1-1为图1中1-1纵向的剖视图;Figure 1-1 is a longitudinal sectional view of 1-1 in Figure 1;

图1-2为图1中2-2纵向的剖视图;Fig. 1-2 is a longitudinal cross-sectional view of 2-2 in Fig. 1;

图1-3为图1中3-3横向的剖视图;Fig. 1-3 is a cross-sectional view of Fig. 1 in the transverse direction of 3-3;

图2、图3分别为图1-2中C部、D部的放大图;Fig. 2 and Fig. 3 are respectively enlarged views of parts C and D in Fig. 1-2;

图4、图5、图6分别为图1-3中I部、H部和E部的放大图;Fig. 4, Fig. 5, Fig. 6 are the enlarged views of I part, H part and E part in Fig. 1-3 respectively;

图7、图8分别为图1-1中A部、B部的放大图;Figure 7 and Figure 8 are enlarged views of parts A and B in Figure 1-1, respectively;

图9、图10分别为图1-3中F部、G部的放大图。FIG. 9 and FIG. 10 are enlarged views of parts F and G in FIGS. 1-3 , respectively.

具体实施方式Detailed ways

如图1所示,本发明提出的一种组合式建筑幕墙的实施例。该实施例设有两扇固定幕墙5、8,分别固定于左右两侧,还设有两扇活动幕墙6、7,能够向中间滑动对接成封闭状态(如图1所示),也可以各自向两侧滑动,重叠于固定幕墙的前面成打开状态。本实施例中,固定幕墙为固定玻璃墙体5、8,固定面板为固定玻璃;活动幕墙为推拉门6、7,活动面板为推拉门玻璃。As shown in FIG. 1 , an embodiment of a combined building curtain wall proposed by the present invention is shown. In this embodiment, two fixed curtain walls 5 and 8 are provided, which are respectively fixed on the left and right sides, and two movable curtain walls 6 and 7 are provided, which can be slid and connected to the middle to form a closed state (as shown in FIG. 1 ), or they can be respectively Slide to both sides and overlap the front of the fixed curtain wall to open. In this embodiment, the fixed curtain walls are fixed glass walls 5, 8, and the fixed panels are fixed glass; the movable curtain walls are sliding doors 6, 7, and the movable panels are sliding door glass.

如图1至图6所示,本实施例的组合式建筑幕墙,其包括外侧与土建结构螺栓连接的槽型附框,一般附框与土建结构之间会设置密封垫等,并用耐候密封胶和水泥填充两者之间的缝隙。该附框由上附框9、下附框10、左附框11、右附框12构成。还有设于该附框内侧的主框,该主框由上框13、下框14、左框15、右框16构成。还包括通过扣件以及定位密封件固定于主框中的两扇固定玻璃墙体5、8,能相对于该固定玻璃墙体平面滑动的两扇推拉门6、7。所述附框的内侧为槽型结构,附框的内侧面设有耐候密封胶17,主框的四侧对应嵌入附框的凹槽中,附框侧面和主框侧面之间的间隙设有定位密封条,起到定位、密封和连接的作用。定位密封条可以采用两种类型,请阅图2,第一种定位密封条18设有与附框的槽口相匹配的固定凸台结构,便于预先安装于附框上,用于朝向室外一面的主框与附框的定位密封,第二种定位密封条19,用于朝向用于室内一面的主框与附框的定位密封,密封条19弹性好,且设有在外力作用下容易出现挤压变形的现象,以形成附框与主框形成稳定的结构体系。请阅图3、图8,下附框10可以通过一铝通或方通形状的横梁20与下侧的土建结构连接;横梁20与下附框10之间、横梁与土建结构之间均设有具有一定变形能力的调节垫片,下附框与横梁、横梁与土建结构之间的缝隙设有耐候密封胶。下框14底部的下侧面也设有耐候密封胶17,下框14平面结构和下附框10外侧壁上设有排水孔21,用于将渗进主框及附框内的水排出。As shown in Fig. 1 to Fig. 6, the combined building curtain wall of this embodiment includes a groove-shaped frame attached to the outer side and the civil structure with bolts. Generally, a gasket or the like is provided between the frame and the civil structure, and a weather-resistant sealant is used. and cement to fill the gap between the two. The attachment frame is composed of an upper attachment frame 9 , a lower attachment frame 10 , a left attachment frame 11 , and a right attachment frame 12 . There is also a main frame arranged inside the attached frame. The main frame is composed of an upper frame 13 , a lower frame 14 , a left frame 15 and a right frame 16 . It also includes two fixed glass walls 5 and 8 fixed to the main frame through fasteners and positioning seals, and two sliding doors 6 and 7 that can slide relative to the plane of the fixed glass walls. The inner side of the attached frame is a groove structure, the inner side of the attached frame is provided with weather-resistant sealant 17, the four sides of the main frame are correspondingly embedded in the grooves of the attached frame, and the gap between the side of the attached frame and the side of the main frame is provided with The positioning sealing strip plays the role of positioning, sealing and connecting. There are two types of positioning sealing strips, please refer to Figure 2. The first type of positioning sealing strip 18 is provided with a fixed boss structure matching the notch of the attached frame, which is convenient for pre-installing on the attached frame and is used for the side facing the outside. The positioning seal of the main frame and the attached frame, the second type of positioning sealing strip 19 is used for the positioning sealing of the main frame and the attached frame for the indoor side. The sealing strip 19 has good elasticity, and it is easy to appear under external force. The phenomenon of extrusion deformation to form a stable structural system between the attached frame and the main frame. Please refer to Fig. 3 and Fig. 8, the lower frame 10 can be connected to the civil structure on the lower side through a beam 20 in the shape of an aluminum pass or square pass; There are adjusting gaskets with certain deformation ability, and the gaps between the lower attached frame and the beam, the beam and the civil structure are provided with weather-resistant sealant. The lower side of the bottom of the lower frame 14 is also provided with weather-resistant sealant 17 , and the planar structure of the lower frame 14 and the outer side wall of the lower attachment frame 10 are provided with drainage holes 21 for draining the water seeping into the main frame and the attachment frame.

如图1至图6所示,以右侧固定玻璃墙体5为例,其包括分别设于上框13内侧、右框16的内侧的凹槽形转接扣件22,设于下框14内的折弯形玻璃扣件23,该玻璃扣件23与下框14中的卡边形成卡槽。还包括上端与上框13内侧连接、下端与下框14内侧连接的固定立框24,设于该固定立框24内侧的卡槽,固定玻璃25的上侧边和右侧边插入转接扣件22的卡槽内、下侧边和左侧边插入所述卡槽的卡槽内,而且该固定玻璃25的两侧平面与转接扣件22以及卡槽的之间设有第二定位密封胶条19。As shown in FIG. 1 to FIG. 6 , taking the fixed glass wall 5 on the right side as an example, it includes groove-shaped adapter fasteners 22 respectively provided on the inner side of the upper frame 13 and the inner side of the right frame 16 , which are arranged on the lower frame 14 . Inside the bending glass fastener 23, the glass fastener 23 and the card edge in the lower frame 14 form a card slot. It also includes a fixed vertical frame 24 whose upper end is connected to the inner side of the upper frame 13 and the lower end is connected to the inner side of the lower frame 14, a card slot is arranged on the inner side of the fixed vertical frame 24, and the upper and right sides of the fixed glass 25 are inserted into the transfer buckle. The lower side and the left side of the component 22 are inserted into the card grooves of the card groove, and the two sides of the fixed glass 25 are provided with a second position between the two side planes of the fixing glass 25 and the transfer fastener 22 and the card groove. Sealing strip 19.

请结合图7~图10所示,所述的推拉门5,以右侧推拉门6为例,其包括由上活动门扇26、下活动门扇27以及左右两侧立框28、29构成的活动门扇,推拉门玻璃30的四边分别卡插于所述的卡槽内。推拉门玻璃30的两侧平面与卡槽之间设有第二定位及密封胶条19;上活动门扇26的两侧平面及下活动门扇27的内侧平面对应与所述上框13、下框14之间设有密封条31。下活动门扇27的底面横向设有凹槽,该凹槽中设有数个滑轮32,该滑轮置于下框14上的横向滑轨33上,并能沿着该滑轨移动,以便两推拉门6、7各自向两侧打开或向中间靠拢对接封闭。下活动门扇27的凹槽与滑轨33的两侧之间也设有密封条31。固定玻璃墙体5上的固定立框24朝向推拉门6的一侧面,设有限制对应推拉门6向中间越位移动的U形槽。见附图5,该本实施例中,横向设有两个U形槽,该槽中设有U形胶垫34,而对应相对滑动的推拉门6上右侧(外侧)立框29的内侧设有与所述U形槽对应钩挂的挂钩35。本实施例,左侧的固定玻璃墙体8和左侧的侧推拉门7结构与右侧的固定玻璃墙体5和右侧的推拉门6的结构对称设置。7 to 10, the sliding door 5, taking the right sliding door 6 as an example, includes an upper movable door leaf 26, a lower movable door leaf 27 and a movable frame 28, 29 on the left and right sides. The door leaf and the four sides of the sliding door glass 30 are respectively inserted into the card slots. A second positioning and sealing rubber strip 19 is provided between the two side planes of the sliding door glass 30 and the card slot; the two side planes of the upper movable door leaf 26 and the inner plane of the lower movable door leaf 27 correspond to the upper frame 13 and the lower frame. A sealing strip 31 is provided between 14 . The bottom surface of the lower movable door leaf 27 is laterally provided with grooves, and several pulleys 32 are arranged in the grooves. 6 and 7 respectively open to both sides or close to the middle for butt closure. A sealing strip 31 is also provided between the groove of the lower movable door leaf 27 and both sides of the slide rail 33 . One side of the fixed vertical frame 24 on the fixed glass wall 5 facing the sliding door 6 is provided with a U-shaped groove for restricting the offside movement of the corresponding sliding door 6 to the middle. Referring to FIG. 5 , in this embodiment, two U-shaped grooves are laterally provided, and U-shaped rubber pads 34 are arranged in the grooves, and the inner side of the right (outer) vertical frame 29 on the right side (outer side) of the sliding door 6 corresponding to the relative sliding A hook 35 corresponding to the U-shaped groove is provided. In this embodiment, the structure of the left fixed glass wall 8 and the left side sliding door 7 is symmetrical with the structure of the right fixed glass wall 5 and the right sliding door 6 .

如图10所示,两扇推拉门6、7对接的立框侧面还设有“F”状的密封胶条,该密封胶条可对两扇推拉门6、7对接缝的纵向和横向进行密封,还可以缓冲两扇推拉门对接时的撞击,减低噪音。两扇推拉门6、7对接的立框之间还可以设置推拉门锁39。如图7、8所示,上框13的内侧表面对应上活动门扇26滑动的一侧还设有推拉门6的限位块36,上框13的内侧该限位块36旁的一侧还设有封堵装饰扣件37扣装于上框内面的右侧上;下框14的滑轨33旁的一侧也设有一下框盖板38,封盖在下框14的右侧。As shown in Figure 10, the side of the vertical frame where the two sliding doors 6, 7 are butted is also provided with an "F"-shaped sealing strip, which can seal the longitudinal and transverse directions of the butt joints of the two sliding doors 6, 7. Sealing can also buffer the impact when the two sliding doors are docked, reducing noise. A sliding door lock 39 may also be provided between the vertical frames where the two sliding doors 6 and 7 are butted. As shown in FIGS. 7 and 8 , a limit block 36 of the sliding door 6 is also provided on the inner side surface of the upper frame 13 corresponding to the sliding side of the upper movable door leaf 26 , and a side beside the limit block 36 is also provided on the inner side of the upper frame 13 . A blocking and decorative fastener 37 is installed on the right side of the inner surface of the upper frame; the lower frame 14 is also provided with a lower frame cover plate 38 on the side beside the slide rail 33 , which covers the right side of the lower frame 14 .

本发明是这样安装连接的:The present invention is installed and connected like this:

1)附框的安装:通过膨胀螺丝将附框---上附框、下附框、左附框、右附框与土建结构连接,同时通过胶垫、耐候密封胶实现与土建接口缝隙的防水等。也可以在下附框与土建结构之间安装一横梁—采用铝通或钢方通,作为调整安装高差的构造。1) Installation of the attached frame: Connect the attached frame—the upper attached frame, the lower attached frame, the left attached frame, and the right attached frame to the civil structure through expansion screws, and at the same time realize the gap with the civil engineering interface through rubber pads and weather-resistant sealants. Waterproof, etc. It is also possible to install a beam between the lower attached frame and the civil structure - using an aluminum pass or a steel square pass, as a structure for adjusting the installation height difference.

2)主框的安装:将主框--上框、下框、左框、右框组合成一体后,再将主框安放于已安装就位的附框内,再通过第一定位及密封胶条、第二定位及密封胶条将主框固定于附框上。2) Installation of the main frame: After combining the main frame - the upper frame, the lower frame, the left frame and the right frame into one, place the main frame in the attached frame that has been installed in place, and then pass the first positioning and sealing. The rubber strip, the second positioning and the sealing rubber strip fix the main frame on the attached frame.

3)固定玻璃墙体的安装:先将转换扣件、玻璃扣件固定在主框内侧上,再将固定玻璃的四边插入转换扣件、玻璃扣件等构成卡槽内,再通过第二定位密封胶条将固定玻璃固定于与主框一体的转换扣件、玻璃扣件等构成的卡槽中。3) Installation of the fixed glass wall: first fix the conversion fasteners and glass fasteners on the inner side of the main frame, then insert the four sides of the fixed glass into the card slots formed by the conversion fasteners, glass fasteners, etc., and then pass the second positioning The sealing tape fixes the fixed glass in the card slot formed by the conversion fasteners, glass fasteners, etc. integrated with the main frame.

4)推拉门的安装:先将推拉门扇中的上、下、左、右活动门扇料组装成一体的推拉门扇,再将推拉门玻璃插入推拉门扇内侧的玻璃安装卡槽内,再通过第二定位及密封胶条将推拉门玻璃固定于推拉门扇上的凹槽中,最后将推拉门安装于主框内侧相应的位置。4) Installation of the sliding door: first assemble the upper, lower, left and right movable door leaf materials in the sliding door leaf into an integrated sliding door leaf, then insert the sliding door glass into the glass installation slot on the inner side of the sliding door leaf, and then pass the second sliding door. The positioning and sealing strips fix the sliding door glass in the groove on the sliding door leaf, and finally install the sliding door at the corresponding position inside the main frame.

拉动两扇推拉门,使其向中间靠拢,并可以通过推拉门锁39将两扇推拉门锁闭。由于相对滑动的推拉门和固定玻璃的固定立框之间设有U形槽对应钩挂的挂钩,因此,推拉门被限制了向一侧的滑动,从而使得固定幕墙和活动幕墙横向展开形成封闭状态。需要打开时,先解除锁定,将推拉门向两侧移动便可。Pull the two sliding doors to make them close to the middle, and the two sliding doors can be locked by the sliding door lock 39 . Since there are hooks corresponding to the U-shaped grooves between the sliding sliding door and the fixed vertical frame for fixing the glass, the sliding door is restricted from sliding to one side, so that the fixed curtain wall and the movable curtain wall are laterally expanded to form a closed state. When it needs to be opened, first unlock it and move the sliding door to both sides.

本发明设置了非常便于现场组装、安装的主框、附框组合体系,有效解决了框架式玻璃幕墙现场安装工作量大,控制点多,安装周期长,质量难于保证的问题,以及有效解决了单元式幕墙运输比困难,成本高,维修或更换比较困难的问题。The invention sets up a main frame and an attached frame combination system that is very convenient for on-site assembly and installation, effectively solves the problems of large on-site installation workload, many control points, long installation period and difficult quality assurance of the frame-type glass curtain wall, and effectively solves the problems of The unit curtain wall transportation ratio is difficult, the cost is high, and the maintenance or replacement is more difficult.

以上所述仅为本发明的具体实施方式。应当指出的是,凡在本发明构思的精神和框架内所做出的任何修改、等同替换和变化,都应包含在本发明的保护范围之内。The above descriptions are merely specific embodiments of the present invention. It should be pointed out that any modifications, equivalent replacements and changes made within the spirit and framework of the present invention should be included within the protection scope of the present invention.

Claims (5)

1.一种组合式建筑幕墙,其特征在于,包括外侧与土建结构连接的附框,该附框由上附框、下附框、左附框、右附框构成,设于该附框内侧的主框,该主框由上框、下框、左框、右框构成;还包括卡接于所述主框内侧中的两扇固定幕墙,能相对于该固定幕墙的平面滑动的两扇活动幕墙;所述的两扇固定幕墙分别设置于所述主框的两侧,所述的活动幕墙能够向中间滑动对接或各自向两侧滑动打开。1. a composite building curtain wall, is characterized in that, comprises the attachment frame that the outer side is connected with civil structure, and this attachment frame is made up of upper attachment frame, lower attachment frame, left attachment frame, right attachment frame, and is arranged on the inside of this attachment frame The main frame is composed of an upper frame, a lower frame, a left frame and a right frame; it also includes two fixed curtain walls that are clamped on the inner side of the main frame and can slide relative to the plane of the fixed curtain wall. A movable curtain wall; the two fixed curtain walls are respectively arranged on both sides of the main frame, and the movable curtain walls can be slidably connected to the middle or slid open to both sides respectively. 2.如权利要求1所述的组合式建筑幕墙,其特征在于,所述附框的内侧为槽型结构,附框的内侧面设有耐候密封胶,所述主框的四侧对应嵌入所述附框的凹槽中,所述的附框侧面和主框侧面之间的间隙设有定位密封条作固定密封。2. The combined building curtain wall according to claim 1, wherein the inner side of the attached frame is a groove-shaped structure, the inner side of the attached frame is provided with a weather-resistant sealant, and the four sides of the main frame are correspondingly embedded in the In the groove of the attached frame, the gap between the side surface of the attached frame and the side surface of the main frame is provided with a positioning sealing strip for fixed sealing. 3.如权利要求1所述的组合式建筑幕墙,其特征在于,所述的固定幕墙包括分别设于上框内侧、左右框的内侧以及下框内侧的面板扣件,还包括上端与所述上框内侧连接、下端与所述下框内侧连接的固定立框,设于该固定立框内侧的卡槽,固定面板的四边分别卡插于所述的面板扣件及卡槽的卡槽内,固定面板的两侧平面与面板扣件之间设有第二定位密封胶条。3. The combined building curtain wall according to claim 1, wherein the fixed curtain wall comprises panel fasteners respectively arranged on the inner side of the upper frame, the inner side of the left and right frames, and the inner side of the lower frame, and also includes an upper end and the described panel fasteners. A fixed vertical frame connected to the inner side of the upper frame and the lower end connected to the inner side of the lower frame, is set in a card slot on the inner side of the fixed vertical frame, and the four sides of the fixed panel are respectively inserted into the said panel fastener and the card slot of the card slot. and a second positioning sealant strip is arranged between the two side planes of the fixed panel and the panel fasteners. 4.如权利要求1所述的组合式建筑幕墙,其特征在于,所述固定立框的朝向所述活动门扇的侧面设有限制对应活动幕墙向中间越位移动的U形槽,每一活动门扇的外端立框的内侧设有与所述U形槽对应钩挂的挂钩。4. The combined building curtain wall as claimed in claim 1, wherein the side of the fixed vertical frame is provided with a U-shaped groove that restricts the offside movement of the corresponding movable curtain wall toward the middle of the movable door leaf. The inner side of the outer end vertical frame is provided with hooks corresponding to the U-shaped grooves. 5.如权利要求1所述的组合式建筑幕墙,其特征在于,所述的两活动门扇对接的立框侧面设有密封胶条。5 . The combined building curtain wall according to claim 1 , wherein a sealing strip is provided on the side of the vertical frame where the two movable door leaves are butted. 6 .
CN201911312658.5A 2019-12-18 2019-12-18 Combined building curtain wall Pending CN110886418A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911312658.5A CN110886418A (en) 2019-12-18 2019-12-18 Combined building curtain wall

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911312658.5A CN110886418A (en) 2019-12-18 2019-12-18 Combined building curtain wall

Publications (1)

Publication Number Publication Date
CN110886418A true CN110886418A (en) 2020-03-17

Family

ID=69752417

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911312658.5A Pending CN110886418A (en) 2019-12-18 2019-12-18 Combined building curtain wall

Country Status (1)

Country Link
CN (1) CN110886418A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113513112A (en) * 2021-04-08 2021-10-19 深圳市嘉信建设集团有限公司 Combined building curtain wall and using method thereof

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006104880A (en) * 2004-10-08 2006-04-20 Ykk Ap株式会社 Sliding door
CN201810136U (en) * 2010-06-09 2011-04-27 刘俊羽 A high airtight sliding window
CN201953256U (en) * 2011-02-09 2011-08-31 李艳文 Seal sliding door
CN202467526U (en) * 2012-01-11 2012-10-03 河北奥润顺达窗业有限公司 Thermal-insulation aluminium alloy push-and-pull energy-saving door window
CN204591009U (en) * 2015-02-11 2015-08-26 中山盛兴股份有限公司 A kind of monorail sliding door
CN110107194A (en) * 2019-06-06 2019-08-09 重庆华厦钢结构有限公司 A kind of high airtight sliding door and window of steel plastic compount
CN211714305U (en) * 2019-12-18 2020-10-20 深圳市嘉信装饰设计工程有限公司 A composite building curtain wall

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2006104880A (en) * 2004-10-08 2006-04-20 Ykk Ap株式会社 Sliding door
CN201810136U (en) * 2010-06-09 2011-04-27 刘俊羽 A high airtight sliding window
CN201953256U (en) * 2011-02-09 2011-08-31 李艳文 Seal sliding door
CN202467526U (en) * 2012-01-11 2012-10-03 河北奥润顺达窗业有限公司 Thermal-insulation aluminium alloy push-and-pull energy-saving door window
CN204591009U (en) * 2015-02-11 2015-08-26 中山盛兴股份有限公司 A kind of monorail sliding door
CN110107194A (en) * 2019-06-06 2019-08-09 重庆华厦钢结构有限公司 A kind of high airtight sliding door and window of steel plastic compount
CN211714305U (en) * 2019-12-18 2020-10-20 深圳市嘉信装饰设计工程有限公司 A composite building curtain wall

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
陈广龙;杨耀宾;: "建筑玻璃幕墙的构造形式简析", 门窗, no. 10, 20 October 2011 (2011-10-20) *

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113513112A (en) * 2021-04-08 2021-10-19 深圳市嘉信建设集团有限公司 Combined building curtain wall and using method thereof

Similar Documents

Publication Publication Date Title
CN102518234B (en) Hurricane-resistant unitized curtain wall
NZ507152A (en) Wall cladding assembly with cladding having recesses along opposite sides to engage with flanges of support members
US4141188A (en) Wall construction
RU179800U9 (en) Translucent factory-assembled module for glazing building structures
CN109403818B (en) Internal flat-open or external flat-open fireproof safety window device
CN211714305U (en) A composite building curtain wall
GB2455169A (en) Method of installing a window unit and fixing bracket
CN110984408B (en) Sealing device between externally hung wallboards for assembled building
US12054944B2 (en) Curtain wall frame gaskets
CN110886418A (en) Combined building curtain wall
CN102817427A (en) Component type curtain wall system provided with vertical keel at outdoor side
GB2565255A (en) Seal element, assembly, and method
JP7724840B2 (en) Door and window construction
RU112252U1 (en) SYSTEM OF ALUMINUM PROFILES (OPTIONS)
CN219365844U (en) General door leaf and vertical hinged door and sliding door using same
CN205297171U (en) Lifting sliding door for beam vertical column connected curtain wall
CN211735833U (en) Sealing device between external wall boards for assembly type building
US11634941B2 (en) Window/shutter/door for outdoor settings
US4339901A (en) System for improving heat insulating characteristics of a building wall structure
CN211623160U (en) Energy-saving integral box type inward opening window with externally perforated plate
KR20230112441A (en) Curtain Wall System with Expaned Frame Structure
CN114277983A (en) Glass curtain wall frame node and installation method thereof
KR20230111856A (en) Curtain wall system With SideGasket
RU2781208C1 (en) Window or door block
CN207597654U (en) One kind is floatd Window curtain wall unit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
CB02 Change of applicant information

Address after: 518000 floor 20, Junzi Plaza, 3076 Qiaoxiang Road, Futian District, Shenzhen, Guangdong

Applicant after: Shenzhen Jiaxin Construction Group Co.,Ltd.

Address before: 518000 Gentleman Plaza, 3076 Qiaoxiang Road, Futian District, Shenzhen City, Guangdong Province, 19-20 floors

Applicant before: SHENZHEN GASU ADORN DESIGN ENGINEERING Co.,Ltd.

CB02 Change of applicant information
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200317

WD01 Invention patent application deemed withdrawn after publication