CN110872807A - A kind of construction method of steel stool bridge and steel stool bridge - Google Patents

A kind of construction method of steel stool bridge and steel stool bridge Download PDF

Info

Publication number
CN110872807A
CN110872807A CN201811024711.7A CN201811024711A CN110872807A CN 110872807 A CN110872807 A CN 110872807A CN 201811024711 A CN201811024711 A CN 201811024711A CN 110872807 A CN110872807 A CN 110872807A
Authority
CN
China
Prior art keywords
military
military beam
steel
chord
end frame
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201811024711.7A
Other languages
Chinese (zh)
Inventor
赵余夫
吴传波
傅珺
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hongrun Construction Group Co Ltd
Original Assignee
Hongrun Construction Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hongrun Construction Group Co Ltd filed Critical Hongrun Construction Group Co Ltd
Priority to CN201811024711.7A priority Critical patent/CN110872807A/en
Publication of CN110872807A publication Critical patent/CN110872807A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D15/00Movable or portable bridges; Floating bridges
    • E01D15/12Portable or sectional bridges
    • EFIXED CONSTRUCTIONS
    • E01CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
    • E01DCONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
    • E01D21/00Methods or apparatus specially adapted for erecting or assembling bridges

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Bridges Or Land Bridges (AREA)

Abstract

The invention discloses a construction method of a steel temporary bridge and the steel temporary bridge, and relates to the technical field of engineering. One embodiment of the method comprises: pre-burying a top crown beam of a bored pile, and pre-burying bolts for fixing an end frame of a military beam at the upper part of the top crown beam of the bored pile; after confirming that the earthwork in the foundation pit is excavated to the bottom surface elevation of the military beam, erecting according to the axis of each standard triangle of the military beam; installing a whole military beam based on the set frame and the pre-embedded top crown beam of the bored pile, and pouring; wherein the whole military beam consists of more than one standard triangle and two end frameworks; and paving a pavement system on the upper edge of the upper chord of the whole military beam. The method reduces personnel investment and equipment investment, and has the advantages of low cost, short construction period and remarkable economic benefit.

Description

一种钢便桥的施工方法以及钢便桥A kind of construction method of steel stool bridge and steel stool bridge

技术领域technical field

本发明涉及工程技术领域,尤其涉及一种钢便桥的施工方法以及钢便桥。The invention relates to the technical field of engineering, in particular to a construction method of a steel bridge and a steel bridge.

背景技术Background technique

钢便桥通常是为了解决临时交通问题为设的栈桥,以便于车辆和行人通行。现有技术中,多采用贝雷片与主梁连为一体的结构。但是,在实施过程中,发现现有技术存在以下问题:由于钢便桥多是临时设计搭建,现有技术无法满足钢便桥的快速运输、拼接和快速撤离的需求;而且,将钢便桥运输到作业地点非常不便。Steel bridges are usually trestle bridges designed to solve temporary traffic problems to facilitate the passage of vehicles and pedestrians. In the prior art, the structure in which the Bailey sheet and the main beam are connected into one body is often used. However, in the process of implementation, it was found that the existing technology has the following problems: because the steel stool bridges are mostly designed and constructed temporarily, the existing technology cannot meet the needs of rapid transportation, splicing and rapid evacuation of the steel stool bridges; The location is very inconvenient.

发明内容SUMMARY OF THE INVENTION

有鉴于此,本发明实施例提供一种钢便桥的施工方法以及钢便桥,能够减少人员、设备的投入,具有成本低、施工周期短且经济效益显著的优点。In view of this, the embodiments of the present invention provide a construction method of a steel walkway bridge and a steel walkway bridge, which can reduce the investment of personnel and equipment, and have the advantages of low cost, short construction period and significant economic benefits.

为实现上述目的,根据本发明实施例的一个方面,提供了一种钢便桥的施工方法。In order to achieve the above object, according to an aspect of the embodiments of the present invention, a construction method of a steel bridge is provided.

本发明实施例的钢便桥的施工方法包括:预埋钻孔灌注桩顶冠梁,以及所述钻孔灌注桩顶冠梁的上部预埋用于固定军用梁的端构架的螺栓;确认基坑内土方开挖至军用梁底面标高后,根据军用梁的每片标准三角的轴线进行设架;基于所述设架和预埋的钻孔灌注桩顶冠梁,安装整片的军用梁,并进行灌注;其中,所述整片的军用梁由一片以上的标准三角以及两个端构架组成;在所述整片的军用梁上弦杆上缘铺设路面系。The construction method of the steel bridge according to the embodiment of the present invention includes: pre-embedding the top crown beam of the bored pile, and pre-embedding the upper part of the top crown beam of the bored pile for fixing the end frame of the military beam; After the earthwork is excavated to the elevation of the bottom surface of the military beam, erection is carried out according to the axis of each standard triangle of the military beam; based on the erection and the pre-buried bored pile top crown beam, the entire military beam is installed and carried out. pouring; wherein, the whole piece of military beam is composed of more than one standard triangle and two end frames; pavement system is laid on the upper edge of the chord of the whole piece of military beam.

可选地,在所述整片的军用梁上弦杆上缘铺设路面系的步骤包括:依次铺设木板、橡胶板和钢板,其中,所述钢板为焊接的整体;在所述钢板上铺设焊接的防滑板。Optionally, the step of laying a pavement system on the upper edge of the chord on the whole piece of military beam includes: laying wooden boards, rubber sheets and steel sheets in sequence, wherein the steel sheets are welded as a whole; Skid plate.

可选地,在安装整片的军用梁之前,还包括:在平整的场地中的军用梁拼装节点处,垫放10*10cm的方木,所述方木间距与军用梁拼装节点间距一致;在每个节点处并排放置两根方木,并用水准仪进行抄平;将需要拼装的端构架、标准三角通过吊车调放在方木上,逐个销孔进行对位,孔位对准后即安装钢销固定孔位;拼装端构架与标准三角,以及安装端弦杆;拼装标准三角,以及安装水平弦杆。Optionally, before installing the whole piece of military beams, the method further includes: placing 10*10cm square wood at the assembling nodes of the military beams in the flat site, and the spacing between the square woods is consistent with the spacing between the assembling nodes of the military beams; Place two square logs side by side at each node, and use a level to level them; place the end frame and standard triangle that need to be assembled on the square log by means of a crane, align the pin holes one by one, and install after the holes are aligned. Steel pin fixing holes; assembling end frame and standard triangle, and installing end chord; assembling standard triangle and installing horizontal chord.

可选地,基于所述设架和预埋的钻孔灌注桩顶冠梁,安装整片的军用梁的步骤包括:将已经施工完成的冠梁表面的浮碴及杂物清理干净,剔除所述预埋的螺栓上的保护塑料纸;将基坑内土方开挖至军用梁底面标高;采用全站仪或经纬仪进行每片军用梁的标准三角的纵横轴线的测设,采用水准仪进行标高测设;确定冠梁和临时条基砼强度达到预设值后,在冠梁和临时条基上放样出每片军用梁的轴线里程,并且依据放线轴线准确进行架设;安装所述端构架的固定钢板;军用梁纵向安装预设长度后,安装所述整片的军用梁下部的联接系槽钢及横联套管螺栓。Optionally, based on the erected and pre-buried bored pile top crown beam, the step of installing the whole piece of military beam includes: cleaning up the floating ballast and debris on the surface of the crown beam that has been constructed, and removing all The protective plastic paper on the pre-embedded bolts; excavate the earthwork in the foundation pit to the elevation of the bottom surface of the military beam; use a total station or theodolite to measure the vertical and horizontal axes of the standard triangle of each military beam, and use a level to measure the elevation ; After confirming that the concrete strength of the crown beam and the temporary strip foundation reaches the preset value, set out the axis mileage of each military beam on the crown beam and the temporary strip foundation, and set up accurately according to the axis of the payout; Install the fixed end frame Steel plate; after the military beam is longitudinally installed with a preset length, the connecting channel steel and the horizontal connecting casing bolts at the lower part of the entire military beam are installed.

可选地,所述钻孔灌注桩顶冠梁为L型。Optionally, the top and crown beams of the bored piles are L-shaped.

可选地,所述军用梁为单层式的六四式军用梁,所述端构架为2m端构架。Optionally, the military beam is a single-layer 64-type military beam, and the end frame is a 2m end frame.

可选地,在所述整片的军用梁上弦杆上缘铺设路面系之后,还包括:布设用于监测的监测点,以及在所述监测点安装表面应变计;基于所述表面应变计的初始数据和读取的实时数据,确当出应变值P:Optionally, after the pavement system is laid on the upper edge of the upper chord of the whole piece of military beam, the method further includes: arranging a monitoring point for monitoring, and installing a surface strain gauge at the monitoring point; The initial data and the real-time data read, the strain value P is indeed obtained:

P=K(Fi-F0)+b(Ti-T0)P=K(F i -F 0 )+b(T i -T 0 )

其中,P为应变值,正值表示受拉,负值表示受压;K为标定系数;F0为初始频率模数;Fi为测读时频率模数;b为温度修正值;T0为室温;Ti为测读的温度。Among them, P is the strain value, positive value means tension, negative value means compression; K is the calibration coefficient; F 0 is the initial frequency modulus; F i is the frequency modulus during measurement and reading; b is the temperature correction value; T 0 is room temperature; Ti is the temperature measured.

可选地,所述监测点包括沉降监测点和内力监测点。Optionally, the monitoring points include settlement monitoring points and internal force monitoring points.

为实现上述目的,根据本发明实施例的一个方面,提供了一种钢便桥。In order to achieve the above object, according to an aspect of the embodiments of the present invention, a steel stool bridge is provided.

本发明实施例的钢便桥的施工方法包括:所述军用梁的两端为端构架,两端的端构架之间依次连接有一片以上的标准三角;以及,所述军用梁通过其两端的端构架和所述钻孔灌注桩顶冠梁进行固定;在所述军用梁的上弦杆上设置有路面系,所述路面系由下至上依次铺设有木板、橡胶板和钢板,其中,所述军用梁上布置有5个内力监测点,分别设置在所述军用梁的竖压杆、上弦杆、斜腹杆、加强三角中竖杆和下弦杆上。The construction method of the steel bridge according to the embodiment of the present invention includes: the two ends of the military beam are end frames, and more than one standard triangle is connected between the end frames at both ends in turn; and, the military beam passes through the end frames at both ends of the military beam. It is fixed with the top crown beam of the bored cast-in-place pile; a pavement system is arranged on the upper chord of the military beam, and the pavement system is sequentially laid with wooden boards, rubber plates and steel plates from bottom to top, wherein the military beam There are 5 internal force monitoring points arranged on the upper part, which are respectively arranged on the vertical pressure rod, upper chord rod, inclined abdominal rod, middle vertical rod and lower chord rod of the military beam.

可选地,所述钻孔灌注桩顶冠梁为L型,所述钻孔灌注桩顶冠梁的上部预埋用于固定军用梁的端构架的螺栓,所述军用梁为单层式的六四式军用梁,以及所述端构架为2m端构架。Optionally, the top crown beam of the bored pile is L-shaped, and the upper part of the top crown beam of the bored pile is pre-embedded with bolts for fixing the end frame of the military beam, and the military beam is a single-layer type. The six-four-type military beam, and the end frame is a 2m end frame.

上述发明中的一个实施例具有如下优点或有益效果:通过军用梁作为主要的承受路面车辆荷载的构件,其具有结构轻便、拼装快速、适应性强等特点。进而,本发明实施例解决了现有技术中无法满足钢便桥的快速运输、拼接和快速撤离需求的问题。而且,便于将钢便桥运输到作业地点。同时,其施工过程便捷,减少了人员、设备的投入,具有成本低、施工周期短且经济效益显著的优点。One embodiment of the above invention has the following advantages or beneficial effects: the military beam is used as the main component for bearing the load of the road vehicle, which has the characteristics of light structure, quick assembly, and strong adaptability. Furthermore, the embodiment of the present invention solves the problem that the prior art cannot meet the requirements of rapid transportation, splicing and rapid evacuation of the steel bridge. Moreover, it is convenient to transport the steel side bridge to the job site. At the same time, the construction process is convenient, the input of personnel and equipment is reduced, and the cost is low, the construction period is short, and the economic benefits are significant.

上述的非惯用的可选方式所具有的进一步效果将在下文中结合具体实施方式加以说明。Further effects of the above non-conventional alternatives will be described below in conjunction with specific embodiments.

附图说明Description of drawings

附图用于更好地理解本发明,不构成对本发明的不当限定。其中:The accompanying drawings are used for better understanding of the present invention and do not constitute an improper limitation of the present invention. in:

图1是根据本发明实施例的钢便桥的施工方法的主要流程的示意图;Fig. 1 is the schematic diagram of the main flow of the construction method of the steel bridge according to the embodiment of the present invention;

图2是根据本发明实施例的军用梁的结构示意图;2 is a schematic structural diagram of a military beam according to an embodiment of the present invention;

图3是根据本发明实施例的内力监测点的示意图;3 is a schematic diagram of an internal force monitoring point according to an embodiment of the present invention;

图4是根据本发明实施例的L型冠梁的示意图;4 is a schematic diagram of an L-shaped crown beam according to an embodiment of the present invention;

图5是根据本发明实施例的钢便桥的结构示意图;5 is a schematic structural diagram of a steel stool bridge according to an embodiment of the present invention;

图6是根据本发明实施例的标准三角的示意图;6 is a schematic diagram of a standard triangle according to an embodiment of the present invention;

图中,In the figure,

1-端构架;2-标准三角;3-横联套管螺栓;4-端构架联结系;5-端弦杆;6-斜腹杆联结系;7-下弦杆联结系;8-标准弦杆;9-横联套管螺栓;10-端弦杆;11a、11b、11c、11d、11e-表面应变计;12-路面系;13-钻孔灌注桩顶冠梁;14-标准段矩形冠梁。1-end frame; 2-standard triangle; 3-transverse casing bolt; 4-end frame connection; 5-end chord; 6-oblique web connection; 7-lower chord connection; 8-standard chord Rod; 9- Transverse casing bolt; 10- End chord; 11a, 11b, 11c, 11d, 11e- Surface strain gauge; 12- Pavement system; 13- Bored pile top crown beam; 14- Standard section rectangle Crown beam.

具体实施方式Detailed ways

以下结合附图对本发明的示范性实施例做出说明,其中包括本发明实施例的各种细节以助于理解,应当将它们认为仅仅是示范性的。因此,本领域普通技术人员应当认识到,可以对这里描述的实施例做出各种改变和修改,而不会背离本发明的范围和精神。同样,为了清楚和简明,以下的描述中省略了对公知功能和结构的描述。Exemplary embodiments of the present invention are described below with reference to the accompanying drawings, which include various details of the embodiments of the present invention to facilitate understanding and should be considered as exemplary only. Accordingly, those of ordinary skill in the art will recognize that various changes and modifications of the embodiments described herein can be made without departing from the scope and spirit of the invention. Also, descriptions of well-known functions and constructions are omitted from the following description for clarity and conciseness.

图1是根据本发明实施例的钢便桥的施工方法的主要流程的示意图,如图1所示,本发明实施例的钢便桥的施工方法主要包括:Fig. 1 is the schematic diagram of the main flow of the construction method of the steel stool bridge according to the embodiment of the present invention, as shown in Fig. 1, the construction method of the steel stool bridge of the embodiment of the present invention mainly includes:

步骤S101:预埋钻孔灌注桩顶冠梁,以及钻孔灌注桩顶冠梁的上部预埋用于固定军用梁的端构架的螺栓。军用梁为单层式的六四式军用梁,端构架为2m端构架。军用梁是一种全焊构架、销接组装、单层或双层的多片式、明桥面体系的拆装式上承钢桁梁。本发明实施例采用单层结构,选用加强型单层六四式军用梁(由加强三角架和辅助端构架组合而成)。六四式铁路军用梁(代号:102—1)的主桁包括标准三角(代号①)、端构架(代号②)、标准弦杆(代号③)、端弦杆(代号④)、和斜弦杆(代号⑤)和撑杆(代号⑥)等六种基本构件和钢销、撑抨销栓等两种节点联结伴组成,可组装成符合国家标准(GB904—65)按4米变化的铁路标准跨度的单层式或双层式桁梁。加强型六四式铁路军用梁(代号:102—2)只是主桁用加强三角(代号21)和加强弦杆(代号23)两种构件分别代替了标准三角(代号①)和标准弦杆(代号③),其余构件和节点联结件和六四式铁路军用梁完全相同,主要用以适应较大的跨度。Step S101 : pre-embedding the top and crown beams of the bored cast-in-place piles, and pre-embedding bolts for fixing the end frames of the military beams in the upper part of the top and top beams of the bored cast-in-place piles. The military beam is a single-layer six-four-type military beam, and the end frame is a 2m end frame. Military girder is a disassembled upper-bearing steel truss girder of all-welded frame, pinned assembly, single-layer or double-layer multi-piece, open bridge deck system. The embodiment of the present invention adopts a single-layer structure, and selects a reinforced single-layer six-four-type military beam (composed of a reinforced tripod and an auxiliary end frame). The main truss of the 64-type railway military beam (code: 102-1) includes standard triangle (code ①), end frame (code ②), standard chord (code ③), end chord (code ④), and inclined chord It is composed of six basic components such as rod (code ⑤) and strut (code ⑥) and two types of joints such as steel pin and support pin bolt, which can be assembled into railways that meet the national standard (GB904-65) and vary by 4 meters Single or double deck girders of standard span. The reinforced six-four-type railway military beam (code: 102-2) is only the main truss with the reinforcement triangle (code 21) and the reinforcement chord (code 23) two components to replace the standard triangle (code ①) and standard chord (code 1) respectively. Code ③), the rest of the components and joints are exactly the same as the military beams of the 64-type railway, which are mainly used to adapt to larger spans.

图2是根据本发明实施例的军用梁的结构示意图,如图2所示,本发明实施例的军用梁主要包括:端构架1、标准三角2、横联套管螺栓3、端构架联结系4、端弦杆5、斜腹杆联结系6、下弦杆联结系7、标准弦杆8、横联套管螺栓9、端弦杆10。军用梁的配件是通用的,共有十一种。按用途分为四类:构件联结销钉包括钢销和撑杆销栓二种;联结系配件包括横联套管螺栓、联结系槽钢、二号U型螺栓、三号U型螺栓四种;桥面系配件包括面板、一号U型螺栓、压板、压板螺栓四种;对于支座,每套支座包括预埋定位螺栓、定位钢压板和联结螺栓;钢销用途为上下主弦杆构件节点联结,横联套管螺栓主要用以各片主桁间的弦杆联结,联结系槽钢主要为平面和断面联结杆件。一号U型螺栓联结面板与主桁上弦杆,二号U型螺栓联结联结系槽钢与主桁下弦杆及撑杆。三号U型螺栓联结联结系槽钢与腹杆(包括撑杆)。FIG. 2 is a schematic structural diagram of a military beam according to an embodiment of the present invention. As shown in FIG. 2 , the military beam according to the embodiment of the present invention mainly includes: an end frame 1, a standard triangle 2, a horizontal sleeve bolt 3, an end frame connection 4. End chord 5, oblique web connection 6, lower chord connection 7, standard chord 8, transverse casing bolt 9, end chord 10. The accessories of military beams are universal, and there are eleven kinds in total. It is divided into four categories according to the purpose: the component connecting pins include steel pins and support rod pins; the connecting accessories include horizontal casing bolts, connecting channel steel, No. 2 U-bolts and No. 3 U-bolts; The bridge deck accessories include four types: panel, No. 1 U-bolt, pressure plate, and pressure plate bolt; for supports, each set of supports includes pre-embedded positioning bolts, positioning steel pressure plates and connecting bolts; steel pins are used for upper and lower main chord members For node connection, transverse casing bolts are mainly used for chord connection between each main truss, and the connection channel steel is mainly plane and section connection members. No. 1 U-bolt connects the panel with the upper chord of the main truss, and No. 2 U-bolt connects the channel steel with the lower chord and strut of the main truss. No. 3 U-bolt connection connects the channel steel and the web rod (including the strut).

军用梁的拼装在堆放场地内进行,先将场地平整,在军用梁拼装节点处垫放10*10cm方木,方木间距与军用梁各节点间距一致,每个节点处并排放置两根方木,并用水准仪进行抄平,保证方木标高一致,偏差控制在3mm之内。将需要拼装的2m端构架、两片标准三角通过吊车调放在方木上,逐个销孔进行对位,孔位对准后即安装钢销固定孔位。先安装端构架与标准三角,再安装端弦杆,然后安装标准三角,最后安装水平弦杆,单片军用梁拼装完成。对拼装成片的军用梁的轴线及水平进行复核,拼装误差满足规范要求后即可运往现场进行安装具体的,在平整的场地中的军用梁拼装节点处,垫放10*10cm的方木,方木间距与军用梁拼装节点间距一致。然后,在每个节点处并排放置两根方木,并用水准仪进行抄平。以及,将需要拼装的端构架、标准三角通过吊车调放在方木上,逐个销孔进行对位,孔位对准后即安装钢销固定孔位。拼装端构架与标准三角,以及安装端弦杆。并且,拼装标准三角,以及安装水平弦杆。结合六四梁结构,按照平面结构进行分析,计算采用PKPM软件钢结构模块对单层六四梁平面结构进行计算。在本发明实施例中,若六四梁自重系统自动计算,桥面系自重按照前述荷载的一半取值为1.0KN/m,货车荷载按照一辆货车通行宽度为7片六四梁宽度,平面模型荷载为1000/14=71KN,,荷载施加于跨中六四梁单元三个节点,考虑一定的安全系数,每个节点施加荷载为28KN。The assembly of military beams is carried out in the stacking site. First, level the site and place 10*10cm square wood at the joints of the military beam assembly. The distance between the square wood is the same as that of each node of the military beam, and two square woods are placed side by side at each node. , and use a level for leveling to ensure that the elevation of the square wood is consistent and the deviation is controlled within 3mm. Place the 2m end frame and two standard triangles that need to be assembled on the square wood by crane, and align the pin holes one by one. After the holes are aligned, install the steel pins to fix the holes. First install the end frame and standard triangle, then install the end chord, then install the standard triangle, and finally install the horizontal chord, and the single-piece military beam is assembled. Review the axis and level of the assembled military beams. After the assembly errors meet the requirements of the specification, they can be transported to the site for installation. Specifically, at the assembly nodes of the military beams in the flat site, place 10*10cm square wood. The spacing of square wood is the same as that of military beam assembly nodes. Then, place two square logs side by side at each node and level them with a level. And, the end frame and standard triangle to be assembled are placed on the square wood by a crane, and the pin holes are aligned one by one. After the holes are aligned, the steel pins are installed to fix the holes. Assembled end frame and standard triangle, and installed end chord. Also, assemble standard triangles and install horizontal chords. Combined with the six-four beam structure, the plane structure is analyzed, and the PKPM software steel structure module is used to calculate the single-story six-four beam plane structure. In the embodiment of the present invention, if the self-weight system of the six-four beams is automatically calculated, the dead weight of the bridge deck is 1.0KN/m according to half of the aforementioned load, and the truck load is 7 pieces of six-four beam width according to the passing width of one truck. The model load is 1000/14=71KN, and the load is applied to three nodes of the six-four beam element in the mid-span. Considering a certain safety factor, the load applied to each node is 28KN.

图4是根据本发明实施例的L型冠梁的示意图,如图4所示,钻孔灌注桩顶冠梁为L型。设置在基坑周边支护(围护)结构(多为桩和墙)顶部的钢筋混凝土连续梁,其作用其一是把所有的桩基连到一起(如钻孔灌注桩,旋挖桩等),防止基坑(竖井)顶部边缘产生坍塌,其二是通过牛腿承担钢支撑(或钢筋混凝土支撑)的水平挤靠力和竖向剪力,冠梁施工时必须凿除桩顶的浮浆等。FIG. 4 is a schematic diagram of an L-shaped crown beam according to an embodiment of the present invention. As shown in FIG. 4 , the top crown beam of the bored pile is L-shaped. The reinforced concrete continuous beam set at the top of the supporting (enclosure) structure (mostly piles and walls) around the foundation pit, one of its functions is to connect all the pile foundations together (such as bored piles, rotary excavation piles, etc. ), to prevent the top edge of the foundation pit (shaft) from collapsing, and the second is to bear the horizontal pressing force and vertical shear force of the steel support (or reinforced concrete support) through the corbel. pulp etc.

步骤S102:确认基坑内土方开挖至军用梁底面标高后,根据军用梁的每片标准三角的轴线进行设架。Step S102: After confirming that the earthwork in the foundation pit is excavated to the elevation of the bottom surface of the military beam, erect the frame according to the axis of each standard triangle of the military beam.

步骤S103:基于设架和预埋的钻孔灌注桩顶冠梁,安装整片的军用梁,并进行灌注。其中,整片的军用梁由一片以上的标准三角以及两个端构架组成。具体的,将已经施工完成的冠梁表面的浮碴及杂物清理干净,剔除预埋的螺栓上的保护塑料纸;将基坑内土方开挖至军用梁底面标高;采用全站仪或经纬仪进行每片军用梁的标准三角的纵横轴线的测设,采用水准仪进行标高测设;确定冠梁和临时条基砼强度达到预设值后,在冠梁和临时条基上放样出每片军用梁的轴线里程,并且依据放线轴线准确进行架设;安装端构架的固定钢板;军用梁纵向安装预设长度后,安装整片的军用梁下部的联接系槽钢及横联套管螺栓。Step S103: Based on the erected and pre-buried bored cast-in-place pile top and crown beams, install a whole piece of military beams, and perform pouring. Among them, the whole military beam is composed of more than one standard triangle and two end frames. Specifically, clean up the floating ballast and debris on the surface of the crown beam that has been constructed, and remove the protective plastic paper on the embedded bolts; excavate the earthwork in the foundation pit to the elevation of the bottom surface of the military beam; use a total station or theodolite to carry out For the measurement and design of the vertical and horizontal axes of the standard triangle of each piece of military beam, use a level to measure and set the elevation; after confirming that the concrete strength of the crown beam and the temporary strip foundation reaches the preset value, stake out each piece of military beam on the crown beam and the temporary strip foundation. Install the fixed steel plate of the end frame; after the military beam is longitudinally installed with a preset length, install the connecting channel steel and horizontal casing bolts at the lower part of the entire military beam.

由上可知,军用梁安装的过程主要包括现场清理、测量放线和安装,在现场清理中,将已经施工完成冠梁表面的浮碴及杂物清理干净,预埋螺栓上的保护塑料纸剔除,以利军用梁的安装。以及,基坑内土方开挖至军用梁底面标高。在测量放线过程中,由测量组采用全站仪或经纬仪进行每片军用梁的纵横轴线的测设,采用水准仪进行标高测设。在本发明实施例的安装过程中,冠梁和临时条基砼强度达到85%以后,在冠梁和临时条基上放样出每片军用梁的轴线里程,依据放线轴线准确进行架设。安装端构架的固定钢板,固定整片军用梁的位置。军用梁下部的联接系槽钢及横联套管螺栓在军用梁纵向安装一定长度后安装。然后,浇带混凝土浇注。在该过程中,冠梁后浇带混凝土在盖板安装前进行灌注。混凝土浇注完成后上部即回填土方至军用梁间,进行养护。It can be seen from the above that the installation process of military beams mainly includes on-site cleaning, measuring and laying out and installation. During the on-site cleaning, the floating ballast and debris on the surface of the crown beam that has been constructed are cleaned up, and the protective plastic paper on the embedded bolts is removed. , to facilitate the installation of military beams. And, the earthwork in the foundation pit is excavated to the elevation of the bottom surface of the military beam. In the process of measuring and laying out the line, the survey team uses a total station or theodolite to measure and design the longitudinal and horizontal axes of each military beam, and use a level to measure and design the elevation. In the installation process of the embodiment of the present invention, after the concrete strength of the crown beam and the temporary strip foundation reaches 85%, the axis mileage of each military beam is set out on the crown beam and the temporary strip foundation, and the erection is carried out accurately according to the axis of the payout. Install the fixed steel plate of the end frame to fix the position of the entire military beam. The lower part of the military beam is connected to the channel steel and the horizontal casing bolts are installed after a certain length of longitudinal installation of the military beam. Then, the strip concrete is poured. In this process, the crown beam post-cast strip concrete is poured before the cover plate is installed. After the concrete pouring is completed, the upper part is backfilled with earthwork to the military beams for maintenance.

步骤S104:在整片的军用梁上弦杆上缘铺设路面系。具体的,依次铺设木板、橡胶板和钢板,其中,钢板为焊接的整体;在钢板上铺设焊接的防滑板。路面系两端搁置在军用梁上弦杆上缘上,路面板铺装时板与板的标高一致,拼接紧密、齐平,不得有错落现象。在本发明实施例中,铺设军用梁上部的路面体系的过程中,首先满铺5cm厚木板,再铺设10mm厚橡胶板,然后满铺20mm厚钢板并焊接为整体,最后上面铺设0.4mm厚花纹钢板,钢板之间可靠焊接,形成一个整体。Step S104: Lay a pavement system on the upper edge of the chord on the entire piece of military beam. Specifically, a wooden board, a rubber board and a steel plate are laid in sequence, wherein the steel plate is a welded whole; a welded anti-skid plate is laid on the steel plate. Both ends of the pavement system are placed on the upper edge of the upper chord of the military beam. When the pavement deck is paved, the elevation of the slab and the slab are the same, the splicing is tight and flush, and there should be no staggered phenomenon. In the embodiment of the present invention, in the process of laying the pavement system on the upper part of the military beam, firstly lay 5cm thick wooden boards, then lay 10mm thick rubber sheets, then lay 20mm thick steel plates and weld them as a whole, and finally lay 0.4mm thick patterns on the top. The steel plates are reliably welded between the steel plates to form a whole.

在整片的军用梁上弦杆上缘铺设路面系之后,还包括:布设用于监测的监测点,以及在监测点安装表面应变计。并且,监测点包括沉降监测点和内力监测点。基于表面应变计的初始数据和读取的实时数据,确当出应变值P:After the pavement system is laid on the upper edge of the upper chord of the entire military beam, it also includes: arranging monitoring points for monitoring, and installing surface strain gauges at the monitoring points. Moreover, the monitoring points include settlement monitoring points and internal force monitoring points. Based on the initial data of the surface strain gauge and the real-time data read, the strain value P is determined:

P=K(Fi-F0)+b(Ti-T0)P=K(F i -F 0 )+b(T i -T 0 )

其中,P为应变值,正值表示受拉,负值表示受压;K为标定系数;F0为初始频率模数;Fi为测读时频率模数;b为温度修正值;T0为室温;Ti为测读的温度。Among them, P is the strain value, positive value means tension, negative value means compression; K is the calibration coefficient; F 0 is the initial frequency modulus; F i is the frequency modulus during measurement and reading; b is the temperature correction value; T 0 is room temperature; Ti is the temperature measured.

军用梁是主要的承受路面车辆荷载的构件,为确保车辆的正常通过和基坑的稳定,保证主体结构的正常施工,特对军用梁进行监测,验证结构设计,为结构设计和施工方案的修订提供反馈信息。监测内容主要包括军用梁沉降监测和内力监测,所需的检测仪器主要包括:精密水准仪、因瓦尺,以及EBJ-57型表面应变计、振弦式频率接收仪。Military beams are the main components that bear the load of road vehicles. In order to ensure the normal passage of vehicles and the stability of the foundation pit, and ensure the normal construction of the main structure, the military beams are specially monitored to verify the structural design and revise the structural design and construction plan. Provide feedback. The monitoring content mainly includes military beam settlement monitoring and internal force monitoring. The required testing instruments mainly include: precision level, Inwa ruler, EBJ-57 surface strain gauge, and vibrating wire frequency receiver.

对于沉降监测,可沿军用梁临时条基端,布设沉降观测点,观测军用梁在车辆荷载作用下的沉降情况,同时掌握临时条基的沉降情况。For settlement monitoring, settlement observation points can be arranged along the base end of the temporary strip of the military beam to observe the settlement of the military beam under the action of the vehicle load, and at the same time grasp the settlement of the temporary strip foundation.

图3是根据本发明实施例的内力监测点的示意图。内力监测共选取两个监测断面,即选两榀军用梁进行内力监测。根据军用梁结构受力特征,视单榀军用梁为桁架结构。在本发明实施例中,每榀梁布置5个内力监测点,分别布设在军用梁的上弦杆、下弦杆、加强三角中竖杆、竖压杆及斜腹杆上。如图3所示,在5个内力监测点上安装表面应变计11a、11b、11c、11d、11e,即表面应变计11a、11b、11c、11d、11e分别设置在竖压杆、上弦杆、斜腹杆、加强三角中竖杆和下弦杆上。FIG. 3 is a schematic diagram of an internal force monitoring point according to an embodiment of the present invention. A total of two monitoring sections were selected for internal force monitoring, namely, two military beams were selected for internal force monitoring. According to the stress characteristics of the military beam structure, the single military beam is regarded as a truss structure. In the embodiment of the present invention, each beam is arranged with 5 internal force monitoring points, which are respectively arranged on the upper chord, the lower chord, the middle vertical rod, the vertical pressure rod and the inclined web rod of the military beam. As shown in Figure 3, the surface strain gauges 11a, 11b, 11c, 11d, and 11e are installed on the five internal force monitoring points, that is, the surface strain gauges 11a, 11b, 11c, 11d, and 11e are respectively arranged on the vertical pressure rod, the upper chord, On the oblique abdominal rod, the middle vertical rod of the reinforced triangle and the lower chord rod.

在安装表面应变计的过程中:①安装时套上标准芯棒,两端外侧面必须与安装架外侧面齐平,然后用扳手拧紧两只M10螺钉。②将装好标准芯棒的安装架用高强专用胶粘贴在钢支撑表面。粘贴时首先要将军用梁基面除锈清理。应变计必须与支撑轴线平行,最好是重合。③松开两只M10螺钉,从一端取出标准芯棒,再把标准芯棒装入另一副安装架内继续进行下一只的安装。④待安装架与钢支撑粘贴牢固后,即可进行应变计的正式安装。安装时应把应变计从一端慢慢推入安装架内,到位后再把两只M10螺钉拧紧即可。⑤记下安装时的零点频率值及当时温度值。In the process of installing the surface strain gauge: ① Put on the standard mandrel during installation, the outer sides of both ends must be flush with the outer side of the mounting frame, and then tighten the two M10 screws with a wrench. ② Paste the mounting frame with the standard mandrel on the steel support surface with high-strength special glue. When pasting, first of all, the base surface of the general beam should be derusted and cleaned. The strain gauge must be parallel to the support axis, preferably coincident. ③ Loosen the two M10 screws, take out the standard mandrel from one end, and then put the standard mandrel into the other mounting frame to continue the installation of the next one. ④ After the mounting frame and the steel support are firmly attached, the formal installation of the strain gauge can be carried out. When installing, slowly push the strain gauge into the mounting frame from one end, and then tighten the two M10 screws in place. ⑤ Note down the zero frequency value and the temperature value at the time of installation.

以及,把应变计推入安装架时,严禁使应变计弯曲变形,要平稳地推入;严禁使应变计扭转变形,要在自由状态下推入;应变计到位后必须与安装架的两端外侧面齐平。拧紧M10螺钉时,接上频率读数仪,在拧紧前测一次频率值(f1);拧紧M10螺钉时必须观测应变计的频率值(f2),此时应将频率控制在f2=f1±100Hz之内,两只螺钉应相应地慢慢地拧入,直至拧紧为止,严禁拧紧一只后再拧另一只。And, when pushing the strain gauge into the mounting frame, it is strictly forbidden to bend the strain gauge and push it in smoothly; it is strictly forbidden to twist the strain gauge and push it in a free state; after the strain gauge is in place, it must be in contact with the two ends of the mounting frame. Outer sides are flush. When tightening the M10 screw, connect the frequency reading instrument and measure the frequency value (f1) once before tightening; when tightening the M10 screw, the frequency value (f2) of the strain gauge must be observed, at this time, the frequency should be controlled within the range of f2=f1±100Hz Inside, the two screws should be screwed in slowly until they are tightened, and it is strictly forbidden to tighten one and then screw the other.

对于本发明实施例,通过军用梁作为主要的承受路面车辆荷载的构件,其具有结构轻便、拼装快速、适应性强等特点。进而,本发明实施例解决了现有技术中无法满足钢便桥的快速运输、拼接和快速撤离需求的问题。而且,便于将钢便桥运输到作业地点。同时,其施工过程便捷,减少了人员、设备的投入,具有成本低、施工周期短且经济效益显著的优点。For the embodiment of the present invention, the military beam is used as the main component that bears the load of the road vehicle, which has the characteristics of light structure, quick assembly, and strong adaptability. Furthermore, the embodiment of the present invention solves the problem that the prior art cannot meet the requirements of rapid transportation, splicing and rapid evacuation of the steel bridge. Moreover, it is convenient to transport the steel side bridge to the job site. At the same time, the construction process is convenient, the input of personnel and equipment is reduced, and the cost is low, the construction period is short, and the economic benefits are significant.

图5是根据本发明实施例的钢便桥的结构示意图,图6是根据本发明实施例的标准三角的示意图。如图5和图6所示,本发明实施例的钢便桥主要包括:钻孔灌注桩顶冠梁13、军用梁和路面系12;军用梁的两端为端构架1,两端的端构架1之间依次连接有一片以上的标准三角2。以及,军用梁通过其两端的端构架1和钻孔灌注桩顶冠梁13进行固定。在钻孔灌注桩顶冠梁13下方埋设有标准段矩形冠梁14。在军用梁的上弦杆上设置有路面系12。本发明实施例的钢便桥横跨主体基坑,其系统主要由:钻孔灌注桩顶冠梁、加强型六四式铁路军用梁、路面系等组成。加强型六四式铁路军用梁(简称军用梁)作为主要的承受路面车辆荷载的构件,其具有结构轻便、拼装快速、适应性强等特点。如图5所示,本发明实施例的钢便桥总长24.48m,含5个标准三角、2个端构架及其配件。主要工程材料包括加强型六四式军用梁、C25混凝土和Q235钢。以及,六四式军用梁的六种主桁构件中,所有杆件和节点钣全都是16锰低合金钢材。加强型六四式铁路军用梁的六种主桁构件中,除加强三角的上弦和加强弦杆以及个销接节点钣采用15锰钒氮低合金钢钢材外,这两种构件中的其他杆件和其他四种构件都是16锰低合金钢钢材。辅助端构架的所有杆件和节点钣全都是16锰低合金钢钢材。主桁构件都是全焊结构。主桁节点联接件(钢销和撑杆销栓)采用35硅锰合金结构钢,并经调质处理。配合标准套使用,标准套中2m长的端构架②,以调整桥跨长度为辅助构件。以及,采用钢材和上述焊接材料焊接的焊缝金属的设计基本容许应力如下表:FIG. 5 is a schematic structural diagram of a steel stool bridge according to an embodiment of the present invention, and FIG. 6 is a schematic diagram of a standard triangle according to an embodiment of the present invention. As shown in FIGS. 5 and 6 , the steel bridge of the embodiment of the present invention mainly includes: a top crown beam 13 of bored piles, a military beam and a pavement system 12; the two ends of the military beam are end frames 1, and the end frames 1 at both ends are There are more than one standard triangle 2 connected in turn. And, the military beam is fixed by the end frame 1 and the top crown beam 13 of the bored pile at both ends thereof. A standard section rectangular crown beam 14 is embedded under the top crown beam 13 of the bored pile. A pavement system 12 is provided on the upper chord of the military beam. The steel access bridge of the embodiment of the present invention spans the main foundation pit, and the system is mainly composed of a top crown beam of bored cast-in-place piles, a reinforced 64-type railway military beam, a pavement system, and the like. Reinforced 64-type railway military beam (referred to as military beam) is the main component that bears the load of road vehicles. It has the characteristics of light structure, fast assembly and strong adaptability. As shown in FIG. 5 , the total length of the steel stool bridge of the embodiment of the present invention is 24.48m, including 5 standard triangles, 2 end frames and their accessories. The main engineering materials include reinforced 64-type military beams, C25 concrete and Q235 steel. And, in the six main truss members of the 64-type military beam, all the members and the node plates are all 16 manganese low-alloy steel. Among the six main truss members of the reinforced 64-type railway military beam, except that the upper chord and the reinforced chord of the reinforced triangle and the pinned joint sheet are made of 15 manganese vanadium nitrogen low alloy steel, the other rods in these two members are made of 15 manganese vanadium nitrogen low alloy steel The parts and the other four components are all 16 manganese low alloy steel. All members and node plates of the auxiliary end frame are made of 16 manganese low alloy steel. The main truss members are all welded structures. The main truss joints (steel pins and strut pins) are made of 35 silicon-manganese alloy structural steel and are quenched and tempered. Used in conjunction with the standard set, the 2m-long end frame ② in the standard set is used to adjust the span length as an auxiliary component. And, the design basic allowable stress of the weld metal welded with steel and the above welding consumables is as follows:

Figure BDA0001788165110000091
Figure BDA0001788165110000091

本发明实施例提供了一种钢便桥,如图2-6所示,其主要包括:钻孔灌注桩顶冠梁13、军用梁和路面系12;军用梁的两端为端构架1,两端的端构架1之间依次连接有一片以上的标准三角2;以及,军用梁通过其两端的端构架1和钻孔灌注桩顶冠梁13进行固定。以及,在钻孔灌注桩顶冠梁13下方埋设有标准段矩形冠梁14。在军用梁的上弦杆上设置有路面系12,路面系12由下至上依次铺设有木板、橡胶板和钢板。军用梁为单层式的六四式军用梁,端构架1为2m端构架。钻孔灌注桩顶冠梁13为L型,进而提升了结构的稳固性。以及,钻孔灌注桩顶冠梁13的上部预埋用于固定军用梁的端构架的螺栓。以及,钢板上铺设有焊接的防滑板。木板、橡胶板和钢板的厚度分别为50mm、10mm、20mm,防滑板的厚度为4mm。军用梁的竖压杆、上弦杆、斜腹杆、加强三角中竖杆和下弦杆上,分别设置有内力监测点11a、11b、11c、11d、11e。The embodiment of the present invention provides a steel bridge, as shown in FIGS. 2-6 , which mainly includes: a crown beam 13 of bored piles, a military beam and a pavement system 12; the two ends of the military beam are end frames 1, and two More than one standard triangle 2 is sequentially connected between the end frames 1 at the ends; and the military beam is fixed by the end frames 1 at both ends and the top crown beam 13 of the bored pile. And, a standard section rectangular crown beam 14 is embedded under the top crown beam 13 of the bored pile. A pavement system 12 is arranged on the upper chord of the military beam, and the pavement system 12 is sequentially laid with wooden boards, rubber sheets and steel plates from bottom to top. The military beam is a single-layer six-four-type military beam, and the end frame 1 is a 2m end frame. The top crown beam 13 of the bored pile is L-shaped, which improves the stability of the structure. And, bolts for fixing the end frame of the military beam are embedded in the upper part of the top crown beam 13 of the bored pile. And, a welded skid plate is laid on the steel plate. The thickness of wood board, rubber board and steel plate are 50mm, 10mm and 20mm respectively, and the thickness of skid plate is 4mm. Internal force monitoring points 11a, 11b, 11c, 11d, and 11e are respectively set on the vertical pressure rod, upper chord rod, inclined web rod, reinforced triangle middle vertical rod and lower chord rod of the military beam.

对于本发明实施例的钢便桥,其结构轻便、拼装快速、适应性强,能够减少了施工过程中的人员投入和设备投入,具有成本低、施工周期短且经济效益显著的优点。The steel toilet bridge of the embodiment of the present invention has the advantages of light structure, quick assembly and strong adaptability, which can reduce the investment of personnel and equipment in the construction process, and has the advantages of low cost, short construction period and significant economic benefits.

上述具体实施方式,并不构成对本发明保护范围的限制。本领域技术人员应该明白的是,取决于设计要求和其他因素,可以发生各种各样的修改、组合、子组合和替代。任何在本发明的精神和原则之内所作的修改、等同替换和改进等,均应包含在本发明保护范围之内。The above-mentioned specific embodiments do not constitute a limitation on the protection scope of the present invention. It should be understood by those skilled in the art that various modifications, combinations, sub-combinations and substitutions may occur depending on design requirements and other factors. Any modifications, equivalent replacements and improvements made within the spirit and principle of the present invention shall be included within the protection scope of the present invention.

Claims (10)

1.一种钢便桥的施工方法,其特征在于,包括:1. a construction method of a steel bridge, is characterized in that, comprises: 预埋钻孔灌注桩顶冠梁,以及所述钻孔灌注桩顶冠梁的上部预埋用于固定军用梁的端构架的螺栓;pre-embedded bored pile top crown beam, and the upper part of the bored cast-in-situ pile top crown beam is embedded with bolts for fixing the end frame of the military beam; 确认基坑内土方开挖至军用梁底面标高后,根据军用梁的每片标准三角的轴线进行设架;After confirming that the earthwork in the foundation pit is excavated to the elevation of the bottom surface of the military beam, erect the frame according to the axis of each standard triangle of the military beam; 基于所述设架和预埋的钻孔灌注桩顶冠梁,安装整片的军用梁,并进行灌注;其中,所述整片的军用梁由一片以上的标准三角以及两个端构架组成;Based on the erected and pre-buried bored pile top crown beams, a whole piece of military beam is installed and poured; wherein, the whole piece of military beam is composed of more than one standard triangle and two end frames; 在所述整片的军用梁上弦杆上缘铺设路面系。A pavement system is laid on the upper edge of the chord on the whole piece of the military beam. 2.根据权利要求1所述的方法,其特征在于,在所述整片的军用梁上弦杆上缘铺设路面系的步骤包括:2. The method according to claim 1, wherein the step of laying a pavement system on the upper edge of the chord on the entire piece of military beam comprises: 依次铺设木板、橡胶板和钢板,其中,所述钢板为焊接的整体;Lay wooden boards, rubber sheets and steel sheets in sequence, wherein the steel sheets are welded as a whole; 在所述钢板上铺设焊接的防滑板。A welded skid plate is laid on the steel plate. 3.根据权利要求1所述的方法,其特征在于,在安装整片的军用梁之前,还包括:3. The method according to claim 1, characterized in that, before installing the whole piece of military beam, further comprising: 在平整的场地中的军用梁拼装节点处,垫放10*10cm的方木,所述方木间距与军用梁拼装节点间距一致;Place 10*10cm square wood at the assembling nodes of military beams in a flat site, and the spacing between the square woods and the assembling nodes of military beams is the same; 在每个节点处并排放置两根方木,并用水准仪进行抄平;Place two square logs side by side at each node and level them with a level; 将需要拼装的端构架、标准三角通过吊车调放在方木上,逐个销孔进行对位,孔位对准后即安装钢销固定孔位;Place the end frame and standard triangle that need to be assembled on the square wood by crane, and align the pin holes one by one. After the holes are aligned, install the steel pins to fix the holes; 拼装端构架与标准三角,以及安装端弦杆;Assembly end frame and standard triangle, and installation end chord; 拼装标准三角,以及安装水平弦杆。Assemble standard triangles and install horizontal chords. 4.根据权利要求1所述的方法,其特征在于,基于所述设架和预埋的钻孔灌注桩顶冠梁,安装整片的军用梁的步骤包括:4. method according to claim 1, is characterized in that, based on described erection and pre-buried bored pile top crown beam, the step of installing the whole piece of military beam comprises: 将已经施工完成的冠梁表面的浮碴及杂物清理干净,剔除所述预埋的螺栓上的保护塑料纸;Clean up the floating ballast and debris on the surface of the crown beam that has been constructed, and remove the protective plastic paper on the embedded bolts; 将基坑内土方开挖至军用梁底面标高;Excavate the earthwork in the foundation pit to the elevation of the bottom surface of the military beam; 采用全站仪或经纬仪进行每片军用梁的标准三角的纵横轴线的测设,采用水准仪进行标高测设;Use a total station or theodolite to measure and design the vertical and horizontal axes of the standard triangle of each military beam, and use a level to measure and design the elevation; 确定冠梁和临时条基砼强度达到预设值后,在冠梁和临时条基上放样出每片军用梁的轴线里程,并且依据放线轴线准确进行架设;After confirming that the concrete strength of the crown beam and the temporary strip foundation reaches the preset value, the axis mileage of each military beam is set out on the crown beam and the temporary strip foundation, and the erection is carried out accurately according to the axis of the payout; 安装所述端构架的固定钢板;Mounting the fixed steel plate of the end frame; 军用梁纵向安装预设长度后,安装所述整片的军用梁下部的联接系槽钢及横联套管螺栓。After the military beam is longitudinally installed with a preset length, the connecting channel steel and the transverse connecting casing bolts at the lower part of the entire military beam are installed. 5.根据权利要求1所述的方法,其特征在于,所述钻孔灌注桩顶冠梁为L型。5 . The method according to claim 1 , wherein the top and crown beams of the bored piles are L-shaped. 6 . 6.根据权利要求1所述的方法,其特征在于,所述军用梁为单层式的六四式军用梁,所述端构架为2m端构架。6 . The method according to claim 1 , wherein the military beam is a single-layer 64-type military beam, and the end frame is a 2m end frame. 7 . 7.根据权利要求1所述的方法,其特征在于,在所述整片的军用梁上弦杆上缘铺设路面系之后,还包括:7. The method according to claim 1, characterized in that, after the pavement system is laid on the upper edge of the upper chord of the whole piece of military beam, the method further comprises: 布设用于监测的监测点,以及在所述监测点安装表面应变计;laying out monitoring points for monitoring, and installing surface strain gauges at said monitoring points; 基于所述表面应变计的初始数据和读取的实时数据,确当出应变值P:Based on the initial data of the surface strain gage and the real-time data read, the strain value P is determined: P=K(Fi-F0)+b(Ti-T0)P=K(F i -F 0 )+b(T i -T 0 ) 其中,P为应变值,正值表示受拉,负值表示受压;K为标定系数;F0为初始频率模数;Fi为测读时频率模数;b为温度修正值;T0为室温;Ti为测读的温度。Among them, P is the strain value, positive value means tension, negative value means compression; K is the calibration coefficient; F 0 is the initial frequency modulus; F i is the frequency modulus during measurement and reading; b is the temperature correction value; T 0 is room temperature; Ti is the temperature measured. 8.根据权利要求7所述的方法,其特征在于,所述监测点包括沉降监测点和内力监测点。8. The method according to claim 7, wherein the monitoring points comprise settlement monitoring points and internal force monitoring points. 9.一种钢便桥,其特征在于,包括钻孔灌注桩顶冠梁、军用梁和路面系;9. A steel bridge, characterized in that it comprises a bored pile top crown beam, a military beam and a pavement system; 所述军用梁的两端为端构架,两端的端构架之间依次连接有一片以上的标准三角;以及,所述军用梁通过其两端的端构架和所述钻孔灌注桩顶冠梁进行固定;Both ends of the military beam are end frames, and more than one standard triangle is sequentially connected between the end frames at both ends; and, the military beam is fixed by the end frames at both ends and the top crown beam of the bored pile ; 在所述军用梁的上弦杆上设置有路面系,所述路面系由下至上依次铺设有木板、橡胶板和钢板,A pavement system is arranged on the upper chord of the military beam, and the pavement system is sequentially laid with wooden boards, rubber boards and steel plates from bottom to top. 其中,所述军用梁上布置有5个内力监测点,分别设置在所述军用梁的竖压杆、上弦杆、斜腹杆、加强三角中竖杆和下弦杆上。Wherein, five internal force monitoring points are arranged on the military beam, which are respectively arranged on the vertical pressure rod, the upper chord, the inclined abdominal rod, the middle vertical rod and the lower chord of the military beam. 10.根据权利要求9所述的钢便桥,其特征在于,所述钻孔灌注桩顶冠梁为L型,所述钻孔灌注桩顶冠梁的上部预埋用于固定军用梁的端构架的螺栓,所述军用梁为单层式的六四式军用梁,以及所述端构架为2m端构架。10 . The steel bridge according to claim 9 , wherein the top and crown beams of the bored piles are L-shaped, and the upper parts of the top and crown beams of the bored piles are pre-buried for fixing the end frames of the military beams. 11 . The bolts, the military beam is a single-layer six-four-type military beam, and the end frame is a 2m end frame.
CN201811024711.7A 2018-09-04 2018-09-04 A kind of construction method of steel stool bridge and steel stool bridge Pending CN110872807A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201811024711.7A CN110872807A (en) 2018-09-04 2018-09-04 A kind of construction method of steel stool bridge and steel stool bridge

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201811024711.7A CN110872807A (en) 2018-09-04 2018-09-04 A kind of construction method of steel stool bridge and steel stool bridge

Publications (1)

Publication Number Publication Date
CN110872807A true CN110872807A (en) 2020-03-10

Family

ID=69716874

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201811024711.7A Pending CN110872807A (en) 2018-09-04 2018-09-04 A kind of construction method of steel stool bridge and steel stool bridge

Country Status (1)

Country Link
CN (1) CN110872807A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112779850A (en) * 2020-12-31 2021-05-11 浙大城市学院 Granular material cargo transporting trestle platform for river-crossing tunnel navigation sealing cofferdam construction and construction method
RU2769236C1 (en) * 2021-04-22 2022-03-29 Валерий Александрович Комаров Dancing bridge

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4912795A (en) * 1988-09-06 1990-04-03 Acrow Corporation Of America Prefabricated unit construction modular bridging system
JP2003253623A (en) * 2002-03-04 2003-09-10 Taisei Corp Bridge girder replacement method
CN201106155Y (en) * 2007-10-16 2008-08-27 中铁大桥局集团第四工程有限公司 Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN101906751A (en) * 2010-07-20 2010-12-08 郑志文 Ready-package emergency bridge and construction method for changing same into permanent bridge
CN102433844A (en) * 2011-09-26 2012-05-02 中交四航局第一工程有限公司 Cantilever beam lifting system of trestle, and bridge deck precast beam erection construction system and method
CN202530367U (en) * 2012-03-14 2012-11-14 中铁二十二局集团第一工程有限公司 Deepwater complex geology foundation construction system
CN204455794U (en) * 2014-12-25 2015-07-08 浙江兴土桥梁专用装备制造有限公司 A kind of assembled steel bridge
CN106978777A (en) * 2017-05-22 2017-07-25 中铁第五勘察设计院集团有限公司 A kind of make-shift bridge device
CN207143708U (en) * 2017-07-26 2018-03-27 中国建筑第二工程局有限公司 Hoisting type foundation pit-crossing comprehensive steel trestle

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US4912795A (en) * 1988-09-06 1990-04-03 Acrow Corporation Of America Prefabricated unit construction modular bridging system
JP2003253623A (en) * 2002-03-04 2003-09-10 Taisei Corp Bridge girder replacement method
CN201106155Y (en) * 2007-10-16 2008-08-27 中铁大桥局集团第四工程有限公司 Inclined guy cable auxiliary full cantaliver crane trussed steel beam device
CN101906751A (en) * 2010-07-20 2010-12-08 郑志文 Ready-package emergency bridge and construction method for changing same into permanent bridge
CN102433844A (en) * 2011-09-26 2012-05-02 中交四航局第一工程有限公司 Cantilever beam lifting system of trestle, and bridge deck precast beam erection construction system and method
CN202530367U (en) * 2012-03-14 2012-11-14 中铁二十二局集团第一工程有限公司 Deepwater complex geology foundation construction system
CN204455794U (en) * 2014-12-25 2015-07-08 浙江兴土桥梁专用装备制造有限公司 A kind of assembled steel bridge
CN106978777A (en) * 2017-05-22 2017-07-25 中铁第五勘察设计院集团有限公司 A kind of make-shift bridge device
CN207143708U (en) * 2017-07-26 2018-03-27 中国建筑第二工程局有限公司 Hoisting type foundation pit-crossing comprehensive steel trestle

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘晖: "地铁盖挖车站军用梁铺盖体系应用及工况分析", 《隧道建设》 *
李辉: "地铁盖挖车站钢便桥施工技术", 《山西建筑》 *
陆鼎铭: "《绿色施工方案的编制与评价体系》", 30 November 2016, 河海大学出版社 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112779850A (en) * 2020-12-31 2021-05-11 浙大城市学院 Granular material cargo transporting trestle platform for river-crossing tunnel navigation sealing cofferdam construction and construction method
RU2769236C1 (en) * 2021-04-22 2022-03-29 Валерий Александрович Комаров Dancing bridge

Similar Documents

Publication Publication Date Title
CN110184950B (en) Construction method for rebuilding and expanding new bridge at original site of bridge under condition of ensuring communication
CN107245951A (en) Across bilateral while closure construction method in cable-stayed bridge
CN110700100A (en) Bailey beam bundle construction method for cast-in-situ platform of high-pier small-radius curve ramp bridge
KR102411253B1 (en) Method for checking integral abutment bridge applicability in bridge having expension joint and method for repairing bridge having expension joint as integral abutment bridge
CN112144408A (en) A kind of prefabricated trestle building construction method
CN212925807U (en) Cast-in-place continuous box girder side span straightway template support system
CN110872807A (en) A kind of construction method of steel stool bridge and steel stool bridge
CN112854004A (en) Fish-bellied box girder column type support construction method
CN220580509U (en) Energy-saving environment-friendly spherical rigid node scaffold structure
CN208792138U (en) A kind of steel suspension bridge
CN106245539B (en) A kind of freely-supported plate girder bridge is used for the reinforcement means of Over-size transport
Wipf et al. Demonstration project using railroad flatcars for low-volume road bridges
CN108978494A (en) A kind of steel pipe concrete cable-carried bowstring arch bridge construction method of base-supporting
CN110184929B (en) Comprehensive construction method for main and auxiliary lines of public rail co-constructed bridge
Rizzo et al. Strengthening of off-system bridges with mechanically fastened pre-cured FRP laminates
O'Connor Composite bridge decking: Final project report
Wipf et al. Investigation of the Modified Beam-in-Slab Bridge System
CN215758529U (en) Tied beam supporting structure
CN114808663B (en) Bridge widening structure and construction method thereof
CN218232977U (en) Steel spring vibration isolation system
Wipf Investigation of the Modified Beam-in-Slab Bridge System: Design Manual Volume 2 of 3.
Shukla et al. Damage Analysis of Simple RC Bridge Girder and its Strengthening Measures
CN116163234A (en) Method for erecting and prepressing concrete cast-in-situ bracket at lower layer of double-layer swivel bridge
CN119980897A (en) A design and construction method for urban sewage pipeline bridge reconstruction
CN119663738A (en) Installation technology of double-layer steel truss arch bridge

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200310