CN110861994A CN201810987528.0A CN201810987528A CN110861994A CN 110861994 A CN110861994 A CN 110861994A CN 201810987528 A CN201810987528 A CN 201810987528A CN 110861994 A CN110861994 A CN 110861994A
Authority
CN
China
Prior art keywords
guide rail
steel structure
fixing device
bracket
structure hoistway
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201810987528.0A
Other languages
Chinese (zh)
Inventor
陈新会
张珂
朱光锐
付西伟
顾跃斌
李骏夫
张家昭
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
JIANGSU XIDE ELEVATOR CO Ltd
Original Assignee
JIANGSU XIDE ELEVATOR CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by JIANGSU XIDE ELEVATOR CO Ltd filed Critical JIANGSU XIDE ELEVATOR CO Ltd
Priority to CN201810987528.0A priority Critical patent/CN110861994A/en
Publication of CN110861994A publication Critical patent/CN110861994A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • BPERFORMING OPERATIONS; TRANSPORTING
    • B66HOISTING; LIFTING; HAULING
    • B66BELEVATORS; ESCALATORS OR MOVING WALKWAYS
    • B66B7/00Other common features of elevators
    • B66B7/02Guideways; Guides
    • B66B7/023Mounting means therefor

Abstract

The invention discloses a fixing device for a guide rail of a steel structure hoistway of an elevator and a construction method thereof, wherein the fixing device comprises a guide rail bracket, the guide rail bracket is fixedly connected with the steel structure hoistway through a guide rail bracket connecting arm, and a guide rail is arranged on one side of the guide rail bracket, which faces the inner side of the steel structure hoistway; the guide rail fixing device is characterized by further comprising a limiting plate group, the limiting plate group is mounted on the guide rail support and can limit the transverse displacement of the guide rail, and the guide rail can vertically move relative to the limiting plate group and is fixed at any position in the vertical direction through the limiting plate group. The guide rail fixing device limits the transverse displacement of the guide rail after the position and the verticality of the guide rail are adjusted through the guide rail transverse positioning plate and the guide rail bracket, so that the later construction and calibration precision is improved; in addition, the guide rail is locked after the adjacent guide rails are aligned through the guide rail pressing plates, the guide rails cannot slide in the vertical direction after alignment, the whole adjusting process is very convenient, the relative positions of the guide rails can be adjusted when the guide rails are preassembled in a factory, the construction efficiency is improved, and manpower and material resources are saved.

Description

Elevator steel structure hoistway guide rail fixing device and construction method thereof
Technical Field
The invention relates to an elevator construction technology, in particular to a guide rail fixing/pre-installing device of an elevator steel structure hoistway and a method for realizing rapid and accurate elevator steel structure hoistway construction by utilizing the guide rail fixing/pre-installing device.
Background
The elevator is mainly supported by an elevator steel structure hoistway which is formed by connecting floors, the common elevator steel structure hoistway is a steel structure frame which is fixed in the floors, most of the existing elevator steel structure hoistways are of a quadrilateral frame structure according to past experience, and in addition, the elevator can slide up and down along the elevator steel structure hoistway mainly by utilizing a guide rail in the steel structure hoistway, so the installation position of the guide rail and the verticality of the guide rail directly influence the operation reliability of the elevator;
in addition, as the general building with higher floors is constructed in sections during elevator construction, the building needs to be transported to a construction area after the steel structure well of the elevator leaves a factory, then constructors calibrate and install the adjacent steel structure well of the elevator, and the guide rails need to be aligned during construction and installation, but in actual construction, the phenomenon that the guide rails and even the whole steel structure well cannot be aligned often occurs, or even if the guide rails can be aligned, the constructors consume large manpower and material resources, therefore, the traditional construction method taking hoisting and manual calibration as main means in the prior art cannot meet the construction requirements of the elevator at the current stage.
Disclosure of Invention
The invention aims to provide a fixing device for a guide rail of a steel structure hoistway of an elevator and a construction method thereof, which can realize quick alignment of the guide rail, do not need secondary adjustment, meet the requirement of quick construction and save manpower and material resources.
In order to achieve the above purpose, the invention provides the following technical scheme:
the invention discloses a fixing device for a guide rail of a steel structure hoistway of an elevator, which is used for pre-mounting the guide rail and the steel structure hoistway and comprises the following components:
the guide rail bracket is fixedly connected with the steel structure well through a guide rail bracket connecting arm, and the guide rail is arranged on one side of the guide rail bracket, which faces the inner side of the steel structure well;
the limiting plate group is arranged on the guide rail bracket and can limit the transverse displacement of the guide rail, and the guide rail can vertically move relative to the limiting plate group and is fixed at any position in the vertical direction through the limiting plate group.
Furthermore, the guide rail bracket is a channel steel transversely arranged in the steel structure hoistway, and the limiting plate group comprises a guide rail transverse positioning plate fixedly connected to the upper end of the guide rail bracket and a guide rail pressing plate fixedly connected to the front side of the guide rail bracket;
the guide rail transverse positioning plate is used for limiting the transverse displacement of the guide rail;
the guide rail pressing plate is used for fixing the guide rail at any position in the vertical direction.
Furthermore, a positioning groove is formed in the front side of the guide rail transverse positioning plate, the guide rail is embedded in the positioning groove, and the guide rail limits transverse displacement through the positioning groove.
Further, the guide rail has two parts, partly for towards the inside convex guide rail body of steel construction well and form in the guide rail body is close to the connector of guide rail bracket one end, guide rail clamp plate one side part press hold in on the connector, guide rail clamp plate's the other side extends to guide rail bracket department, guide rail clamp plate passes through guide rail clamp plate set screw fastening, and will the guide rail is fixed in vertical direction's optional position.
Furthermore, the guide rail transverse positioning plate is fixedly connected to the guide rail bracket through positioning plate fixing screws.
The invention discloses a construction method of an elevator steel structure hoistway, which comprises the following steps:
s1, after the steel structure well is manufactured, the sections are combined in a factory, the size is checked, and the guide rail is pre-installed through a fixing device;
s2, adjusting the position and the verticality of the guide rail in a paying-off mode, finishing the transverse positioning of the guide rail through a guide rail transverse positioning plate of the fixing device, and locking the guide rail through a positioning plate fixing screw after the transverse positioning;
s3, transporting the steel structure well pre-provided with the guide rail to a construction site;
s4, loosening the guide rail pressing plate during construction and installation of the adjacent steel structure well, adjusting the vertical position of the guide rail, and locking the guide rail through the guide rail pressing plate fixing screw when the adjacent guide rails are connected.
In the technical scheme, the elevator steel structure hoistway guide rail fixing device and the steel structure hoistway construction method provided by the invention have the following beneficial effects:
1. the guide rail fixing device limits the transverse displacement of the guide rail after the position and the verticality of the guide rail are adjusted through the guide rail transverse positioning plate and the guide rail bracket, so that the later construction and calibration precision is improved; in addition, the guide rails are locked after the adjacent guide rails are aligned through the guide rail pressing plates, so that the guide rails cannot slide in the vertical direction after alignment, the whole adjusting process is very convenient, the relative positions of the guide rails can be adjusted when the guide rails are preassembled in a factory, the construction efficiency is improved, and manpower and material resources are saved;
2. the elevator steel structure hoistway adopting the guide rail fixing device is very quick to construct, meanwhile, the fixing device can accurately realize transverse positioning and vertical positioning of the guide rail, and the construction effect is good.
Drawings
In order to more clearly illustrate the embodiments of the present application or technical solutions in the prior art, the drawings needed to be used in the embodiments will be briefly described below, and it is obvious that the drawings in the following description are only some embodiments described in the present invention, and other drawings can be obtained by those skilled in the art according to the drawings.
Fig. 1 is a schematic structural view of a fixing device for a hoistway guide rail of a steel structure of an elevator according to an embodiment of the present invention in a construction state;
fig. 2 is a schematic structural diagram of a fixing device for a hoistway guide rail of an elevator steel structure according to an embodiment of the present invention.
Description of reference numerals:
1. a steel structure hoistway; 2. a fixing device; 3. a guide rail;
201. a rail bracket; 202. a guide rail bracket connecting arm; 203. a guide rail transverse positioning plate; 204. a guide rail pressing plate;
20301. positioning a groove; 20302. a positioning plate fixing screw;
20401. a guide rail pressing plate fixing screw;
301. a guide rail body; 302. a connector.
Detailed Description
In order to make the technical solutions of the present invention better understood, those skilled in the art will now describe the present invention in further detail with reference to the accompanying drawings.
As shown in fig. 1 to 2, an elevator steel structure hoistway guide rail fixing device 2 according to an embodiment of the present invention is used for pre-installing a guide rail 3 and a steel structure hoistway 1, and includes:
the guide rail bracket 201 is fixedly connected with the steel structure hoistway 1 through a guide rail bracket connecting arm 202, and the guide rail 3 is arranged on one side of the guide rail bracket 201 facing the inner side of the steel structure hoistway 1;
and the limiting plate group is arranged on the guide rail bracket 201 and can limit the transverse displacement of the guide rail 3, and the guide rail 3 can vertically move relative to the limiting plate group and is fixed at any position in the vertical direction through the limiting plate group.
Specifically, this embodiment discloses a can realize that 3 pre-installations of guide rail of elevator steel construction well 1, and make things convenient for guide rail fixing device 2 of 1 construction installation of later stage steel construction well, this fixing device 2 mainly is used for guide rail 3 and steel construction well 1's location installation, it mainly includes the rail brackets 201 that links firmly with steel construction well 1, wherein, what this embodiment adopted is that the fixing of utilizing the rail brackets linking arm 202 of symmetry to accomplish rail brackets 201, and rail brackets 201 and rail brackets linking arm 202, the fixed mode between rail brackets linking arm 202 and the steel construction well 1 can be the welding, also can be the fastener fastening, here no longer give unnecessary details one by one. The main points of the present embodiment are: the fixing device 2 of this embodiment has the limiting plate group that can restrict guide rail 3 and preinstall back lateral displacement and realize vertical orientation location to guide rail 3, when the guide rail 3 of factory steel construction well 1 was preinstalled, at first utilize existing technical means, accomplish the location of guide rail 3 lateral position according to the construction requirement, and accomplish the lateral displacement locking through foretell limiting plate group, then will preinstall steel construction well 1 transport to the job site installation, adjacent steel construction well 1 can lock after need counterpointing during construction usually, therefore, the limiting plate group of this embodiment can also make things convenient for guide rail 3 to adjust its vertical position, and fix guide rail 3 after adjusting vertical position. The fixing device 2 of the embodiment can improve the positioning accuracy of the adjacent steel structure shafts 1 and the guide rails 3 during construction and installation, and realize rapid construction.
Preferably, in this embodiment, the guide rail bracket 201 is a channel steel horizontally arranged in the steel structure hoistway 1, and the limiting plate group includes a guide rail horizontal positioning plate 203 fixedly connected to the upper end of the guide rail bracket 201, and a guide rail pressing plate 204 fixedly connected to the front side of the guide rail bracket 201;
the guide rail transverse positioning plate 203 is used for limiting the transverse displacement of the guide rail 3;
the rail presser 204 is used to fix the rail 3 at an arbitrary position in the vertical direction.
In order to realize the two main functions of the above-mentioned limiting plate group, the limiting plate group of the present embodiment mainly includes two parts, one part is a guide rail transverse positioning plate 203 for realizing the transverse positioning of the guide rail 3, and a guide rail pressing plate 204 for realizing the vertical positioning of the guide rail 3.
As a preferable technical scheme of the embodiment: the horizontal locating plate of guide rail 203 front side is opened and is equipped with constant head tank 20301, and guide rail 3 inlays in this constant head tank 20301, and guide rail 3 passes through constant head tank 20301 restriction lateral displacement. The positioning groove 20301 provides an embedding space for the guide rail 3, and during installation, the edge of the guide rail 3 is basically attached to the groove surface of the positioning groove 20301, so that the transverse displacement of the guide rail 3 can be limited after the guide rail transverse positioning plate 203 is locked, and even the inclination of the guide rail 3 is limited.
Preferably, in this embodiment, the guide rail 3 has two parts, one part is a guide rail body 301 protruding toward the inside of the steel structure hoistway 1, and a connecting body 302 formed at one end of the guide rail body 301 close to the guide rail bracket 201, one side part of the guide rail pressing plate 204 is pressed and held on the connecting body 302, the other side of the guide rail pressing plate 204 extends to the guide rail bracket 201, and the guide rail pressing plate 204 is fastened by a guide rail pressing plate fixing screw 20401 to fix the guide rail 3 at an arbitrary position in the vertical direction. In general, the number of guide rails 3 of the steel structure hoistway 1 of the elevator can be adjusted according to actual conditions, but the structure of the guide rails 3 described in the above embodiment is not specified, and the above embodiment merely illustrates the relationship between the limiting plate group and the guide rails 3 in a preferred embodiment. The guide rail pressing plate 204 in this embodiment may be bent with a certain gradient in order to contact both the guide rail 3 and the guide rail bracket 201, or both the guide rail 3 and the guide rail bracket 201 are provided with bolt holes, and are fixed by the guide rail pressing plate fixing screws 20401. Finally, the connection structure of the rail pressing plate 204 and the rail 3 of the present embodiment may be other similar structures.
Preferably, in this embodiment, the guide rail transverse positioning plate 203 is fixedly connected to the guide rail bracket 201 through a positioning plate fixing screw 20302.
The invention discloses a construction method of an elevator steel structure hoistway 1, which comprises the following steps:
s1, after the steel structure well 1 is manufactured, the combined section is combined in a factory, the size is checked, and the guide rail 3 is pre-installed through the fixing device 2;
s2, adjusting the position and the verticality of the guide rail 3 in a paying-off mode, finishing the transverse positioning of the guide rail 3 through the guide rail transverse positioning plate 203 of the fixing device 2, and locking the guide rail 3 through a positioning plate fixing screw 20302 after the transverse positioning;
s3, transporting the steel structure hoistway 1 with the guide rail 3 pre-installed to a construction site;
s4, when the adjacent steel structure well 1 is constructed and installed, the guide rail pressing plate 204 is loosened, the vertical position of the guide rail 3 is adjusted, and when the adjacent guide rails 3 are connected, the guide rail 3 is locked through the guide rail pressing plate fixing screws 20401.
In the construction, steel construction well 1 is at the mill preparation and is built, and utilizes fixing device 2 of this application can be in the mill in advance in installation guide rail 3, utilizes the mode of unwrapping wire to adjust the position and the straightness that hangs down of guide rail 3 simultaneously, and the unwrapping wire refers to the common plumb line in the engineering, can assist the workman to confirm whether guide rail 3 is perpendicular. And the horizontal displacement of guide rail 3 after adjusting with this kind of mode realizes fixing a position through the horizontal locating plate 203 of guide rail among the spacing plate group, and the guide rail 3 lateral displacement appears when avoiding later stage steel construction well 1 to build to the earlier stage work that leads to loses the effect and is difficult to the relative position between adjacent steel construction well 1 and the guide rail 3 of accuse. As can be seen from the above construction method, when the guide rail 3 is assembled on site, the guide rail pressing plate 204 needs to be selectively loosened or the guide rail pressing plate 204 needs to be locked. When the guide rail pressing plate 204 is loosened, the height of the guide rail 3 can be vertically adjusted by constructors, so that the butt joint of the adjacent guide rails 3 is realized; when the guide rail pressing plate 204 is locked, the vertical position of the guide rail 3 is fixed, and the phenomenon that the guide rail 3 slides or falls off when the constructor operates other positions can not occur.
In the technical scheme, the elevator steel structure hoistway guide rail fixing device and the steel structure hoistway 1 construction method provided by the invention have the following beneficial effects:
the guide rail fixing device 2 limits the transverse displacement of the guide rail 3 after the position and the verticality of the guide rail are adjusted through the guide rail transverse positioning plate 203 and the guide rail bracket 201, and aims to improve the later construction and calibration precision; in addition, the guide rail 3 is locked after the adjacent guide rails 3 are aligned through the guide rail pressing plate 204, so that the guide rails 3 cannot slide in the vertical direction after alignment, the whole adjustment process is very convenient, the relative positions of the guide rails 3 can be adjusted when the guide rails are pre-installed in a factory, the construction efficiency is improved, and manpower and material resources are saved;
the construction of the elevator steel structure hoistway 1 after the guide rail fixing device 2 is adopted is very quick, meanwhile, the fixing device 2 can accurately realize the transverse positioning and the vertical positioning of the guide rail 3, and the construction effect is good.
While certain exemplary embodiments of the present invention have been described above by way of illustration only, it will be apparent to those of ordinary skill in the art that the described embodiments may be modified in various different ways without departing from the spirit and scope of the invention. Accordingly, the drawings and description are illustrative in nature and should not be construed as limiting the scope of the invention.

Claims (6)

1. Elevator steel construction well guide rail fixing device, this fixing device (2) are used for guide rail (3) and steel construction well (1) pre-installation, its characterized in that includes:
the guide rail bracket (201) is fixedly connected with the steel structure hoistway (1) through a guide rail bracket connecting arm (202), and the guide rail (3) is arranged on one side, facing the inner side of the steel structure hoistway (1), of the guide rail bracket (201);
the limiting plate group is arranged on the guide rail bracket (201) and can limit the transverse displacement of the guide rail (3), and the guide rail (3) can vertically move relative to the limiting plate group and is fixed at any position in the vertical direction through the limiting plate group.
2. The elevator steel structure hoistway guide rail fixing device according to claim 1, wherein the guide rail bracket (201) is a channel steel transversely arranged in the steel structure hoistway (1), and the limiting plate group comprises a guide rail transverse positioning plate (203) fixedly connected to the upper end of the guide rail bracket (201) and a guide rail pressing plate (204) fixedly connected to the front side of the guide rail bracket (201);
the guide rail transverse positioning plate (203) is used for limiting the transverse displacement of the guide rail (3);
the guide rail pressing plate (204) is used for fixing the guide rail (3) at any position in the vertical direction.
3. The fixing device for the guide rails of the steel structure hoistway of the elevator according to claim 2, wherein a positioning groove (20301) is formed in the front side of the guide rail transverse positioning plate (203), the guide rail (3) is embedded in the positioning groove (20301), and the guide rail (3) limits the transverse displacement through the positioning groove (20301).
4. The elevator steel structure hoistway guide rail fixing device of claim 2, wherein the guide rail (3) has two parts, one part is a guide rail body (301) protruding towards the inside of the steel structure hoistway (1), and a connecting body (302) formed at one end of the guide rail body (301) close to the guide rail bracket (201), one side part of the guide rail pressing plate (204) is pressed on the connecting body (302), the other side of the guide rail pressing plate (204) extends to the guide rail bracket (201), and the guide rail pressing plate (201) is fastened by a guide rail pressing plate fixing screw (20401) and fixes the guide rail (3) at any position in the vertical direction.
5. The elevator steel structure hoistway rail fixing device of claim 3, wherein the rail transverse positioning plate (203) is fixedly connected to the rail bracket (201) by a positioning plate fixing screw (20302).
6. The construction method of the elevator steel structure hoistway is characterized by comprising the following steps:
s1, splicing and leaning in a factory after the steel structure hoistway (1) is manufactured, checking the size, and pre-installing the guide rail (3) through the fixing device (2);
s2, adjusting the position and the verticality of the guide rail (3) in a paying-off mode, finishing the transverse positioning of the guide rail (3) through a guide rail transverse positioning plate (203) of the fixing device (2), and locking the guide rail (3) through a positioning plate fixing screw (20302) after the transverse positioning;
s3, transporting the steel structure hoistway (1) with the guide rail (2) pre-installed to a construction site;
s4, loosening the guide rail pressing plate (204) during construction and installation of the adjacent steel structure well (1), adjusting the vertical position of the guide rail (3), and locking the guide rail (3) through the guide rail pressing plate fixing screw (20401) when the adjacent guide rail (3) is connected.
CN201810987528.0A 2018-08-28 2018-08-28 Elevator steel structure hoistway guide rail fixing device and construction method thereof Pending CN110861994A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201810987528.0A CN110861994A (en) 2018-08-28 2018-08-28 Elevator steel structure hoistway guide rail fixing device and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201810987528.0A CN110861994A (en) 2018-08-28 2018-08-28 Elevator steel structure hoistway guide rail fixing device and construction method thereof

Publications (1)

Publication Number Publication Date
CN110861994A true CN110861994A (en) 2020-03-06

Family

ID=69651750

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201810987528.0A Pending CN110861994A (en) 2018-08-28 2018-08-28 Elevator steel structure hoistway guide rail fixing device and construction method thereof

Country Status (1)

Country Link
CN (1) CN110861994A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111824901A (en) * 2020-08-06 2020-10-27 深圳市建工中泰机电工程有限公司 Elevator installation construction method

Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002338168A (en) * 2001-05-15 2002-11-27 Mitsubishi Electric Corp Guide rail device for elevator
JP2003300682A (en) * 2002-04-10 2003-10-21 Mitsubishi Electric Corp Support device of elevator guide rail for base-isolated building
CN201882737U (en) * 2010-12-13 2011-06-29 北京升华电梯集团有限公司 Elevator guide rail bracket
CN102583130A (en) * 2011-01-04 2012-07-18 张向阳 Elevator shaft wall assembled by combined shaft frame
US20140000986A1 (en) * 2012-06-28 2014-01-02 Daniel Quinn Device and method for fastening and aligning a guide rail
CN205187550U (en) * 2015-10-25 2016-04-27 天津利福特电梯部件有限公司 Heavy rail brackets of high -speed elevator broadside on
CN106586768A (en) * 2017-02-22 2017-04-26 张家港奥斯卡电梯部件有限公司 Mounting assembly for hollow elevator guide rail
CN107399657A (en) * 2017-08-25 2017-11-28 张家港市通达电梯装璜有限公司 A kind of hollow cage guide and the mounting structure for connecing guiding element
CN207258956U (en) * 2017-09-29 2018-04-20 邓潮森 The mounting structure of connection plate for elevator guide rail, guide rail and rail brackets
CN208883241U (en) * 2018-08-28 2019-05-21 江苏西德电梯有限公司 Elevator hoistway with steel structure guide rail fixer

Patent Citations (10)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP2002338168A (en) * 2001-05-15 2002-11-27 Mitsubishi Electric Corp Guide rail device for elevator
JP2003300682A (en) * 2002-04-10 2003-10-21 Mitsubishi Electric Corp Support device of elevator guide rail for base-isolated building
CN201882737U (en) * 2010-12-13 2011-06-29 北京升华电梯集团有限公司 Elevator guide rail bracket
CN102583130A (en) * 2011-01-04 2012-07-18 张向阳 Elevator shaft wall assembled by combined shaft frame
US20140000986A1 (en) * 2012-06-28 2014-01-02 Daniel Quinn Device and method for fastening and aligning a guide rail
CN205187550U (en) * 2015-10-25 2016-04-27 天津利福特电梯部件有限公司 Heavy rail brackets of high -speed elevator broadside on
CN106586768A (en) * 2017-02-22 2017-04-26 张家港奥斯卡电梯部件有限公司 Mounting assembly for hollow elevator guide rail
CN107399657A (en) * 2017-08-25 2017-11-28 张家港市通达电梯装璜有限公司 A kind of hollow cage guide and the mounting structure for connecing guiding element
CN207258956U (en) * 2017-09-29 2018-04-20 邓潮森 The mounting structure of connection plate for elevator guide rail, guide rail and rail brackets
CN208883241U (en) * 2018-08-28 2019-05-21 江苏西德电梯有限公司 Elevator hoistway with steel structure guide rail fixer

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111824901A (en) * 2020-08-06 2020-10-27 深圳市建工中泰机电工程有限公司 Elevator installation construction method
CN111824901B (en) * 2020-08-06 2022-02-18 深圳市建工中泰机电工程有限公司 Elevator installation construction method

Similar Documents

Publication Publication Date Title
TWI654352B (en) Rail fastening point piece and crevice piece for the rail fastening point piece
RU2595339C2 (en) Adjustable bracket elevator guide
CN208883241U (en) Elevator hoistway with steel structure guide rail fixer
CN110861994A (en) Elevator steel structure hoistway guide rail fixing device and construction method thereof
CN202201602U (en) Elevator car guide rail bracket of high-speed elevator
KR20210023465A (en) Hydraulic Lifting Machine for Steel Frame
CN111634791B (en) Elevator landing door assembly installation method
CN104401889A (en) Wall attaching frame and construction lifting machine with wall attaching frame
US8366068B2 (en) Bracing structure, fastener and method for bracing a support structure having props for ceiling formworks
KR20130012088A (en) Draft plate fixing device which is suitable to high speed flow in large cavitation tunnel
CN102951519A (en) Guide rail support of elevator car for high-speed elevator
CN114104926B (en) Landing assembly positioning tool and elevator landing door assembly mounting method
CN205998806U (en) Monoblock type elevator guiderail base
JP6713144B1 (en) Connecting fittings for hoisting work scaffolds and installation method
JP2021024651A (en) Installation method of guide rail fixing device and guide rail fixing device
CN219671091U (en) Support preformed hole adjusting device
CN115059227B (en) Stay cable glass curtain wall installation method for curtain wall lug plate with deviation
CN104589040B (en) T-shaped guide rail mounting tool for elevator
CN220445562U (en) Frock bed-jig suitable for steel case roof beam arch rib preparation
CN213897547U (en) Strong post and weak beam connection structure
CN216662182U (en) Pre-buried hoisting point location structure of prefabricated panel
CN109235873B (en) Detachable and detachable creeping formwork wall-attached device and installation, correction and construction method thereof
CN107651544B (en) Hoistway door pocket fixing assembly and door pocket fixing claw
CN216840678U (en) Device is assembled fast to precast concrete wall body combination formula
JPH01150687A (en) Guide rail fixing device for elevator

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination