CN110847620A - Assembled wall body temporary connection fixed equipment - Google Patents

Assembled wall body temporary connection fixed equipment Download PDF

Info

Publication number
CN110847620A
CN110847620A CN201911160004.5A CN201911160004A CN110847620A CN 110847620 A CN110847620 A CN 110847620A CN 201911160004 A CN201911160004 A CN 201911160004A CN 110847620 A CN110847620 A CN 110847620A
Authority
CN
China
Prior art keywords
rod
plate
gear
wall
clamping
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911160004.5A
Other languages
Chinese (zh)
Other versions
CN110847620B (en
Inventor
张亚
张晋源
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Jiangsu Bangde Lvjian Decoration Co ltd
Original Assignee
Individual
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Individual filed Critical Individual
Priority to CN201911160004.5A priority Critical patent/CN110847620B/en
Publication of CN110847620A publication Critical patent/CN110847620A/en
Application granted granted Critical
Publication of CN110847620B publication Critical patent/CN110847620B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G21/00Preparing, conveying, or working-up building materials or building elements in situ; Other devices or measures for constructional work
    • E04G21/24Safety or protective measures preventing damage to building parts or finishing work during construction
    • E04G21/26Strutting means for wall parts; Supports or the like, e.g. for holding in position prefabricated walls

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Conveying And Assembling Of Building Elements In Situ (AREA)

Abstract

The invention relates to a temporary connection and fixation device for an assembled wall, which comprises a bottom plate, a flat plate, a supporting device, a clamping device and a propping device, wherein the flat plate is arranged on the bottom plate, the supporting devices are symmetrically arranged at the left end and the right end of the bottom plate, the clamping device is arranged on the supporting device, and the propping device is arranged on the flat plate; two, traditional reinforcing apparatus need set up the screw hole on the wall body, uses the threaded rod to install the steel sheet at the threaded hole of wall body, with upper end of the support bar welding on the steel sheet, bury the bracing piece lower extreme subaerial, not only waste time and energy like this, have structural damage to the assembled wall body moreover, have to support tightly reinforce effectual and work efficiency height advantage.

Description

Assembled wall body temporary connection fixed equipment
Technical Field
The invention relates to the technical field of assembly type buildings, in particular to an assembly type wall temporary connecting and fixing device.
Background
The prefabricated building which has emerged in recent years is a typical representative of green buildings, not only represents the technological revolution and the industrial revolution direction of a new round of building industry, but also is a great revolution of the construction mode, is beneficial to saving resource and energy, improving the labor production efficiency and the quality safety level, further promoting the deep integration of the building industry and the information industry, improving the industrialization level and the resource utilization rate of the building, promoting the industrialization and the industrialization of the building, gradually transforming the building engineering from a cast-in-place concrete structure to the prefabricated type, factory-producing and standardizing structural components, and the assembly type technology of the ground engineering is gradually mature.
However, the following problems exist in the assembly of the current assembly wall, namely, after most of the assembly walls are assembled in place, when joint construction is not completed, the assembly walls cannot be stably placed, and the assembly walls are temporarily abutted by using a support rod manually, so that the possibility of safety accidents is greatly increased, and the assembly walls cannot be stably abutted; two, traditional reinforcing apparatus need set up the screw hole on the wall body, uses the threaded rod to install the steel sheet at the threaded hole of wall body, with upper end of the support bar welding on the steel sheet, bury the bracing piece lower extreme subaerial, not only waste time and energy like this, have structural damage to the assembled wall body moreover, have to support tightly reinforce effectual and work efficiency height advantage.
Disclosure of Invention
Technical problem to be solved
The temporary connecting and fixing equipment for the assembled wall can solve the problems existing in the assembly of the assembled wall.
(II) technical scheme
In order to achieve the purpose, the invention adopts the following technical scheme that the temporary connecting and fixing equipment for the assembled wall comprises a bottom plate, a flat plate, supporting devices, clamping devices and abutting devices, wherein the flat plate is installed on the bottom plate, the supporting devices are symmetrically installed at the left end and the right end of the bottom plate, the clamping devices are installed on the supporting devices, and the abutting devices are installed on the flat plate.
The supporting device comprises a telescopic supporting rod, straight plates, a supporting slide block, a telescopic cylinder, an inserting shaft, a hollow ring and an inserting rod, wherein a sliding groove is formed in the bottom plate and the flat plate in a matched manner, the telescopic cylinders are symmetrically arranged on the inner walls of the left end and the right end of the sliding groove, the supporting slide block is symmetrically arranged in the sliding groove in a left-right manner in a sliding fit manner and is arranged at the output end of the telescopic cylinder, the straight plates are symmetrically arranged on the supporting slide block in a left-right manner, the telescopic supporting rod is arranged between the straight plates through the inserting shaft, a rotating mechanism is arranged at the upper end of the telescopic supporting rod, a telescopic mechanism is arranged on the outer wall of the telescopic supporting rod, the hollow ring is arranged on the outer wall of the straight plate at the left end, jacks are uniformly arranged on the hollow ring along the circumferential direction of the hollow ring, jacks, the angle of the telescopic supporting rod is easier to adjust and position.
Telescopic machanism include crank, bevel gear, No. two bevel gears, flexible threaded rod, flexible threaded sleeve, square plate and roof, the square plate install on flexible bracing piece lower extreme outer wall, the square groove has been seted up on the square plate, install flexible threaded rod through the bearing on the square groove lower extreme inner wall, install bevel gear on the flexible threaded rod, install the crank through the bearing on the square groove front end outer wall, install the No. two bevel gears with bevel gear meshing on the crank, install the roof on the connecting plate outer wall, install on the roof and flexible threaded rod intermeshing's flexible threaded sleeve, make the better concertina movement that carries on of flexible bracing piece, better control clamping device's position through the rotation of manual control crank.
Rotary mechanism include No. two motors, No. two gears, pin rod and connecting plate, the connecting plate install in flexible bracing piece upper end, the pin rod is installed to the connecting plate upper end, gear draw-in groove has been seted up to the pin rod middle-end, the swivelling chute has been seted up to the clamp plate front end, the straight flute has been seted up on the swivelling chute inner wall, install No. two motors on the straight flute inner wall, No. two motors output install with No. two gears of gear draw-in groove meshing, the pin rod passes through the bearing and installs on the inner wall of both ends about the swivelling chute, rotate the rotation that drives clamp plate self through No. two gears in the clamp plate, the rotation angle of control clamp.
The clamping device comprises a first motor, a first gear, a first rotary gear rod, a second rotary gear rod, a clamping plate, a holding plate, a straight rod, a clamping rod and a rubber plate, wherein the clamping plate is arranged on the supporting device, a clamping groove is formed in the rear end of the clamping plate, the first motor is arranged on the inner wall of the clamping groove, the first gear is arranged at the output end of the first motor, the first rotary gear rod and the second rotary gear rod are symmetrically arranged at the front end and the rear end of the middle part of the upper end of the clamping plate through pin shafts, the clamping rods are symmetrically arranged at the front end and the rear end of the middle part of the lower end of the clamping plate through pin shafts, the straight rod is symmetrically arranged at the front end and the rear end of the upper end and the lower end of the front end of the clamping plate, the middle end of the holding plate is arranged between the inner walls of the straight rod at the upper end and the lower, install between No. two rotary gear poles and rear end clamping lever inner wall through the round pin axle on the board is embraced to the rear end, it has the rubber slab to install on the board to embrace, and the slip phenomenon can not take place after rubber slab and the outer wall of assembled wall compress tightly for it is tight to the better clamp of assembled wall to embrace the board.
The bottom plate is evenly provided with through holes, the flat plate is evenly provided with the conical rods, the flat plate is arranged on the bottom plate, the conical rods penetrate through the through holes, and the bottom plate is better stabilized on the ground.
The tightening device comprises a third motor, a rotating shaft, a clamping plate, a fourth motor, a tightening threaded rod, a tightening threaded sleeve, a tightening block, a long strip plate and a sucker, the flat plate is provided with a long strip groove, the inner wall of the long strip groove is provided with a third motor, the output end of the third motor is provided with a rotating shaft, the rotating shaft is uniformly provided with a clamping plate from left to right, the clamping plate is provided with a groove, the inner wall of the groove is provided with a fourth motor, the output end of the fourth motor is provided with a tightening threaded rod, the tightening threaded rod is provided with a tightening threaded sleeve which is in threaded engagement, the upper end of the tightening threaded sleeve is provided with a tightening block, the tightening block is provided with a long strip plate, the long strip plate is uniformly provided with a circular groove, and a sucking disc is, through sucking tightly on sucking disc and the external wall of assembled wall, the in close contact with on circular cone pole and the ground makes the more firm placing of bottom plate subaerial, and further consolidates the assembled wall.
(III) advantageous effects
1. The invention can solve the following problems existing in the assembly of the existing assembly wall, namely, after most of the assembly walls are assembled in place, the assembly walls can not be stably placed when joint construction is not completed, and the support rods are usually used manually to temporarily abut against the assembly walls, so that the possibility of safety accidents is greatly increased, and the assembly walls can not be stably abutted; two, traditional reinforcing apparatus need set up the screw hole on the wall body, uses the threaded rod to install the steel sheet at the threaded hole of wall body, with upper end of the support bar welding on the steel sheet, bury the bracing piece lower extreme subaerial, not only waste time and energy like this, have structural damage to the assembled wall body moreover, have to support tightly reinforce effectual and work efficiency height advantage.
2. According to the supporting device, the telescopic mechanism and the clamping device, the clamping device extends into the window position of the assembled wall body through the thread transmission between the telescopic threaded rod and the telescopic threaded sleeve, the clamping device enables the holding plate and the rubber plate to clamp the outer wall of the assembled wall body through the gear engagement and the connecting rod action, the assembled wall body cannot be structurally damaged, and the assembled wall body can be better connected and fixed.
3. The tight-abutting device designed by the invention enables the conical rod to abut against the ground through the thread transmission between the tight-abutting threaded rod and the tight-abutting threaded sleeve, the sucker on the long slat is tightly sucked on the outer wall of the assembled wall body, and the tight-abutting threaded rod and the tight-abutting threaded sleeve are mutually extruded, so that the bottom plate is more stably placed on the ground, and the assembled wall body is further reinforced.
Drawings
The invention is further illustrated with reference to the following figures and examples.
FIG. 1 is a schematic structural view of the present invention;
FIG. 2 is a cross-sectional view of FIG. 1 of the present invention;
FIG. 3 is a cross-sectional view taken along line A-A of FIG. 2 in accordance with the present invention;
FIG. 4 is a schematic view of the support device of the present invention;
FIG. 5 is a schematic view of the clamping assembly of the present invention;
FIG. 6 is a schematic view of the telescoping mechanism of the present invention;
FIG. 7 is a schematic view of the structure of the tightening device of the present invention;
fig. 8 is a schematic view of the bottom plate and the bottom structure of the plate of the present invention.
Detailed Description
The embodiments of the invention will be described in detail below with reference to the drawings, but the invention can be implemented in many different ways as defined and covered by the claims.
As shown in fig. 1 to 8, an assembly type wall temporary connection fixing device comprises a bottom plate 1, a flat plate 2, supporting devices 3, clamping devices 4 and abutting devices 5, wherein the flat plate 2 is installed on the bottom plate 1, the supporting devices 3 are symmetrically installed at the left end and the right end of the bottom plate 1, the clamping devices 4 are installed on the supporting devices 3, and the abutting devices 5 are installed on the flat plate 2.
The supporting device 3 comprises a telescopic supporting rod 31, straight plates 32, a supporting sliding block 33, a telescopic cylinder 34, an inserting shaft 35, a hollow circular ring 36 and an inserting rod 37, a sliding groove is formed in the bottom plate 1 and the flat plate 2 in a matched mode, the telescopic cylinders 34 are symmetrically arranged on the inner walls of the left end and the right end of the sliding groove, the supporting sliding blocks 33 are symmetrically arranged in the sliding groove in a left-right mode in a sliding fit mode, the supporting sliding blocks 33 are arranged at the output end of the telescopic cylinder 34 in a left-right mode, the straight plates 32 are symmetrically arranged on the supporting sliding blocks 33 in a left-right mode, the telescopic supporting rod 31 is arranged between the straight plates 32 through the inserting shaft 35, a rotating mechanism 38 is arranged at the upper end of the telescopic supporting rod 31, a telescopic mechanism 39 is arranged on the outer wall of the telescopic supporting rod 31, the hollow circular ring 36 is arranged on the, the insertion rod 37 and the insertion hole are matched for use.
The telescopic mechanism 39 comprises a crank 391, a first bevel gear 392, a second bevel gear 393, a telescopic threaded rod 394, a telescopic threaded sleeve 395, a square plate 396 and a top plate 397, the square plate 396 is installed on the outer wall of the lower end of the telescopic supporting rod 31, a square groove is formed in the square plate 396, the telescopic threaded rod 394 is installed on the inner wall of the lower end of the square groove through a bearing, the first bevel gear 392 is installed on the telescopic threaded rod 394, the crank 391 is installed on the outer wall of the front end of the square groove through a bearing, the second bevel gear 393 meshed with the first bevel gear 392 is installed on the crank 391, the top plate 397 is installed on the outer wall of the connecting plate 384, and the telescopic threaded sleeve 395 meshed with the telescopic threaded rod 394 is installed on the top plate 397.
During specific work, move equipment to needs to connect fixed assembled wall body side, shrink cylinder 34 promotes the supporting slide 33 and slides to suitable position after, with flexible bracing piece 31 rotate certain angle after, insert the jack with inserted bar 37, make flexible bracing piece 31 fix a position at suitable angle, it drives bevel gear 392 to rotate crank 391, bevel gear 392 drives No. two bevel gear 393 and rotates, bevel gear 393 drives flexible threaded rod 394 and rotates, flexible threaded rod 394 drives flexible threaded sleeve 395 up-end motion through the mode of thread engagement, make clamping device 4 move to suitable position.
The rotating mechanism 38 comprises a second motor 381, a second gear 382, a pin rod 383 and a connecting plate 384, the connecting plate 384 is installed at the upper end of the telescopic supporting rod 31, the pin rod 383 is installed at the upper end of the connecting plate 384, a gear clamping groove is formed in the middle end of the pin rod 383, a rotating groove is formed in the front end of the clamping plate 45, a straight groove is formed in the inner wall of the rotating groove, the second motor 381 is installed on the inner wall of the straight groove, the second gear 382 meshed with the gear clamping groove is installed at the output end of the second motor 381, and the pin rod 383 is installed on the inner walls of the left end and.
The clamping device 4 comprises a first motor 41, a first gear 42, a first rotary gear rod 43, a second rotary gear rod 44, a clamping plate 45, a holding plate 46, a straight rod 47, a clamping rod 48 and a rubber plate 49, the clamping plate 45 is installed on the supporting device 3, a clamping groove is formed in the rear end of the clamping plate 45, the first motor 41 is installed on the inner wall of the clamping groove, the first gear 42 is installed at the output end of the first motor 41, the first rotary gear rod 43 and the second rotary gear rod 44 are symmetrically installed at the front end and the rear end of the middle part of the upper end of the clamping plate 45 through pin shafts, the clamping rod 48 is symmetrically installed at the front end and the rear end of the middle part of the lower end of the clamping plate 45 through pin shafts, the straight rod 47 is symmetrically installed at the front end and the rear end of the upper end and the lower end of the front end of the clamping plate 45, the holding plate 46 is symmetrically installed at the front end and rear end of the clamping plate 45 between the inner walls of the straight rod 47 at the upper end, the rear end holding plate 46 is mounted between the second rotary gear rod 44 and the inner wall of the rear end clamping rod 48 through a pin shaft, and a rubber plate 49 is mounted on the holding plate 46.
The first gear 42, the first rotary gear rod 43 and the second rotary gear rod 44 are all in gear engagement.
After clamping device 4 moved to suitable position, No. two motors 381 drove No. two gears 382 and rotates on gear clamping groove, make clamp plate 45 rotate after suitable position, shrink cylinder 34 drove behind supporting slide 33 slided to clamping position, No. one motor 41 drove No. one gear 42 and rotates, No. one gear 42 drove No. one rotatory gear rod 43 and rotates, No. one rotatory gear rod 43 drove No. two rotatory gear rod 44 and rotates, No. one rotatory gear rod 43 and No. two rotatory gear rod 44 drive straight-bar 47 and clamp rod 48 through the connecting rod effect and rotate, make and hold tightly board 46 to the middle motion, rubber slab 49 on the board 46 of holding tightly presss from both sides on the window front and back both ends outer wall on the assembled wall body.
The abutting device 5 comprises a third motor 51, a rotating shaft 52, a clamping plate 53, a fourth motor 54, an abutting threaded rod 55, an abutting threaded sleeve 56, an abutting block 57, a long strip plate 58 and a sucking disc 59, a long strip groove is formed in the flat plate 2, the third motor 51 is installed on the inner wall of the long strip groove, the rotating shaft 52 is installed at the output end of the third motor 51, the clamping plate 53 is evenly installed on the rotating shaft 52 from left to right, a groove is formed in the clamping plate 53, the fourth motor 54 is installed on the inner wall of the groove, the abutting threaded rod 55 is installed at the output end of the fourth motor 54, the abutting threaded sleeve 56 in threaded engagement is installed on the abutting threaded rod 55, the abutting block 57 is installed at the upper end of the abutting threaded sleeve 56, the long strip plate 58 is installed on the abutting block 57, circular grooves are evenly formed in the long strip plate 58, and the.
The bottom plate 1 is uniformly provided with through holes, the flat plate 2 is uniformly provided with conical rods 21, the flat plate 2 is arranged on the bottom plate 1, and the conical rods 21 penetrate through the through holes.
After the tightly holding plate 46 clamps the outer wall of the assembled wall body, the third motor 51 drives the rotating shaft 52 to rotate, the rotating shaft 52 drives the clamping plate 53 to rotate, so that the sucking disc 59 is tightly sucked on the outer wall of the assembled wall body, the fourth motor 54 drives the tightly abutting threaded rod 55 to rotate, the tightly abutting threaded rod 55 rotates in the tightly abutting threaded sleeve 56 in a threaded engagement mode, the long strip plate 58 at the upper end of the tightly abutting threaded sleeve 56 abuts on the outer wall of the assembled wall body, the conical rod 21 on the flat plate 2 abuts on the ground, and the bottom plate 1 is more stably placed on the ground and cannot move.
During operation
The first step is as follows: moving the equipment to the side of an assembled wall to be connected and fixed, pushing a supporting slide block 33 to slide to a proper position by a contraction cylinder 34, rotating a telescopic supporting rod 31 to a certain angle, positioning the telescopic supporting rod 31 at the proper angle by using an inserting rod 37, driving a second bevel gear 393 to rotate by a rotating crank 391 through a first bevel gear 392, driving a telescopic threaded rod 394 to rotate by the second bevel gear 393, and driving a telescopic threaded sleeve 395 to move upwards to drive a clamping device 4 to the proper position;
the second step is that: the second motor 381 drives the second gear 382 to rotate on the gear clamping groove, so that after the clamping plate 45 rotates to a proper position, the contraction cylinder 34 drives the supporting slide block 33 to slide to a clamping position, the first motor 41 drives the first rotary gear rod 43 to rotate through the first gear 42, the first rotary gear rod 43 drives the second rotary gear rod 44 to rotate, the first rotary gear rod 43 and the second rotary gear rod 44 drive the straight rod 47 and the clamping rod 48 to rotate through the action of the connecting rod, so that the holding plate 46 moves towards the middle, and the rubber plates 49 on the holding plate 46 clamp the outer walls of the front end and the rear end of the window on the assembled wall body;
the third step: no. three motor 51 drives cardboard 53 through pivot 52 and rotates for sucking disc 59 tightly is inhaled on the assembled wall body outer wall, and No. four motor 54 drives and supports tight threaded rod 55 and rotate, supports tight threaded rod 55 and drives and support the rectangular board 58 of tight threaded sleeve 56 upper end and support tightly on the assembled wall body outer wall, makes the circular cone pole 21 on the dull and stereotyped 2 support tightly subaerial, makes bottom plate 1 place more firmly and can not take place to remove subaerial.
The above description is only a preferred embodiment of the present invention and is not intended to limit the present invention, and various modifications and changes may be made by those skilled in the art. Any modification, equivalent replacement, or improvement made within the spirit and principle of the present invention should be included in the protection scope of the present invention.

Claims (7)

1. The utility model provides an assembled wall body temporary connection fixed equipment, includes bottom plate (1), flat board (2), strutting arrangement (3), clamping device (4) and supports tight device (5), its characterized in that: the bottom plate (1) is provided with a flat plate (2), the left end and the right end of the bottom plate (1) are symmetrically provided with supporting devices (3), the supporting devices (3) are provided with clamping devices (4), and the flat plate (2) is provided with a pressing device (5); wherein:
the clamping device (4) comprises a first motor (41), a first gear (42), a first rotating gear rod (43), a second rotating gear rod (44), a clamping plate (45), a holding plate (46), a straight rod (47), a clamping rod (48) and a rubber plate (49), wherein the clamping plate (45) is installed on the supporting device (3), a clamping groove is formed in the rear end of the clamping plate (45), the first motor (41) is installed on the inner wall of the clamping groove, the first gear (42) is installed at the output end of the first motor (41), the first rotating gear rod (43) and the second rotating gear rod (44) are symmetrically installed at the front end and the rear end of the upper end of the clamping plate (45) through pin shafts, the clamping rod (48) is symmetrically installed at the front end and the rear end of the clamping plate (45) through pin shafts at the front end and the rear end of the lower end of the clamping plate (45), the straight rod (47) is, both ends around grip block (45) are installed to grip block (46) symmetry, grip block (46) middle-end is installed between upper and lower both ends straight-bar (47) inner wall through the round pin axle, install on front end grip block (46) between a rotatory gear pole (43) and front end clamp bar (48) inner wall through the round pin axle, install on rear end grip block (46) between No. two rotatory gear poles (44) and rear end clamp bar (48) inner wall through the round pin axle, it has rubber slab (49) to install on grip block (46).
2. The temporary connecting and fixing equipment for the assembled wall according to claim 1, wherein the supporting device (3) comprises a telescopic supporting rod (31), straight plates (32), supporting sliding blocks (33), contracting cylinders (34), an inserting shaft (35), a hollow ring (36) and an inserting rod (37), sliding grooves are formed in the bottom plate (1) and the flat plate (2) in a matching manner, the contracting cylinders (34) are symmetrically arranged on the inner walls of the left end and the right end of the sliding grooves, the supporting sliding blocks (33) are symmetrically arranged in the sliding grooves in a sliding manner, the supporting sliding blocks (33) are arranged at the output end of the contracting cylinders (34), the straight plates (32) are symmetrically arranged on the supporting sliding blocks (33), the telescopic supporting rod (31) is arranged between the straight plates (32) through the inserting shaft (35), a rotating mechanism (38) is arranged at the upper end of the telescopic supporting rod (31), and a telescopic mechanism (39) is arranged on the outer wall of, install hollow ring (36) on the straight board of left end (32) outer wall, have evenly seted up the jack along its circumference direction on hollow ring (36), have seted up the jack on inserted shaft (35), and in inserted bar (37) inserted the jack, the cooperation was used between inserted bar (37) and the jack.
3. The temporary connection and fixation device for the assembled wall body as claimed in claim 2, wherein the rotating mechanism (38) comprises a second motor (381), a second gear (382), a pin rod (383) and a connecting plate (384), the connecting plate (384) is installed at the upper end of the telescopic supporting rod (31), the pin rod (383) is installed at the upper end of the connecting plate (384), a gear clamping groove is formed in the middle end of the pin rod (383), a rotating groove is formed in the front end of the clamping plate (45), a straight groove is formed in the inner wall of the rotating groove, the second motor (381) is installed on the inner wall of the straight groove, the second gear (382) meshed with the gear clamping groove is installed at the output end of the second motor (381), and the pin rod (383) is installed on the inner walls of the left end and the.
4. An assembly type wall body temporary connection fixing device as claimed in claim 2, wherein said telescopic mechanism (39) comprises a crank (391), a first bevel gear (392), a second bevel gear (393), a telescopic threaded rod (394), a telescopic threaded sleeve (395), a square plate (396) and a top plate (397), square plate (396) install on flexible bracing piece (31) lower extreme outer wall, the square groove has been seted up on square plate (396), install flexible threaded rod (394) through the bearing on the square groove lower extreme inner wall, install bevel gear (392) on flexible threaded rod (394), install crank (391) through the bearing on the square groove front end outer wall, install No. two bevel gear (393) with bevel gear (392) meshing on crank (391), install roof (397) on connecting plate (384) outer wall, install on roof (397) with flexible threaded rod (394) intermeshing's flexible thread bush (395).
5. The temporary connecting and fixing equipment for the assembled wall body according to claim 1, wherein the tightening device (5) comprises a third motor (51), a rotating shaft (52), a clamping plate (53), a fourth motor (54), a tightening threaded rod (55), a tightening threaded sleeve (56), a tightening block (57), a long strip plate (58) and a sucking disc (59), the flat plate (2) is provided with a long strip groove, the inner wall of the long strip groove is provided with the third motor (51), the output end of the third motor (51) is provided with the rotating shaft (52), the clamping plate (53) is uniformly arranged on the rotating shaft (52) from left to right, the clamping plate (53) is provided with a groove, the inner wall of the groove is provided with the fourth motor (54), the output end of the fourth motor (54) is provided with the tightening threaded rod (55), and the tightening threaded sleeve (56) which is in threaded engagement is arranged on the tightening threaded rod (55), the upper end of the abutting threaded sleeve (56) is provided with an abutting block (57), the abutting block (57) is provided with a long strip plate (58), the long strip plate (58) is uniformly provided with a circular groove, and a sucker (59) is arranged in the circular groove.
6. The temporary connecting and fixing device for the assembled wall body as claimed in claim 1, wherein the bottom plate (1) is uniformly provided with through holes, the flat plate (2) is uniformly provided with the conical rods (21), the flat plate (2) is arranged on the bottom plate (1) and the conical rods (21) pass through the through holes.
7. An assembly type wall body temporary connection fixing device as claimed in claim 1, wherein the first gear (42), the first rotary gear rod (43) and the second rotary gear rod (44) are all in gear engagement.
CN201911160004.5A 2019-11-23 2019-11-23 Assembled wall body temporary connection fixed equipment Active CN110847620B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911160004.5A CN110847620B (en) 2019-11-23 2019-11-23 Assembled wall body temporary connection fixed equipment

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911160004.5A CN110847620B (en) 2019-11-23 2019-11-23 Assembled wall body temporary connection fixed equipment

Publications (2)

Publication Number Publication Date
CN110847620A true CN110847620A (en) 2020-02-28
CN110847620B CN110847620B (en) 2021-07-02

Family

ID=69603909

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911160004.5A Active CN110847620B (en) 2019-11-23 2019-11-23 Assembled wall body temporary connection fixed equipment

Country Status (1)

Country Link
CN (1) CN110847620B (en)

Cited By (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111894280A (en) * 2020-07-21 2020-11-06 潘秋萍 Assembled building wall supporting method
CN112392262A (en) * 2020-10-23 2021-02-23 杭州原创木结构工程有限公司 Fixed construction equipment of assembled building wall
CN112412076A (en) * 2020-11-20 2021-02-26 娄底市新越鼎建材科技有限公司 Auxiliary device for assembly type building
CN112922140A (en) * 2021-01-26 2021-06-08 南京嘉奋棠建筑科技有限公司 Construction method for building modular integrated house
CN113235958A (en) * 2021-05-14 2021-08-10 林迟文 Diversified guide system that supports of assembly type structure wall assembly
CN113323420A (en) * 2021-06-29 2021-08-31 吉林建筑大学 Prefabricated building wallboard pre-positioning device and method
CN113914500A (en) * 2021-11-08 2022-01-11 重庆工程职业技术学院 Light high strength assembled wall
CN114484140A (en) * 2022-01-24 2022-05-13 黄帅 Shock attenuation resistance to compression type cement tubular column

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3874625A (en) * 1972-06-02 1975-04-01 Robert N Hansen Support brace for walls and the like
CN206707332U (en) * 2017-05-04 2017-12-05 王伟华 A kind of construction support meanss
CN107663861A (en) * 2017-11-06 2018-02-06 成都新澳冠医疗器械有限公司 A kind of bridge construction piling equipment
CN108005385A (en) * 2017-12-23 2018-05-08 郑州诚合信息技术有限公司 A kind of construction shear wall frame support apparatus
CN207794672U (en) * 2017-12-04 2018-08-31 彭舰君 A kind of reinforcing support construction for architectural engineering
CN207959991U (en) * 2018-01-22 2018-10-12 张家口恒泰集成房屋有限公司 Integrated house wallboard installs supporting member
CN109853950A (en) * 2019-04-07 2019-06-07 正太集团有限公司 A kind of building trade form clamp
CN209114873U (en) * 2018-11-16 2019-07-16 山西建设投资集团有限公司 A kind of civil engineering basic mode stationary fixture

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US3874625A (en) * 1972-06-02 1975-04-01 Robert N Hansen Support brace for walls and the like
CN206707332U (en) * 2017-05-04 2017-12-05 王伟华 A kind of construction support meanss
CN107663861A (en) * 2017-11-06 2018-02-06 成都新澳冠医疗器械有限公司 A kind of bridge construction piling equipment
CN207794672U (en) * 2017-12-04 2018-08-31 彭舰君 A kind of reinforcing support construction for architectural engineering
CN108005385A (en) * 2017-12-23 2018-05-08 郑州诚合信息技术有限公司 A kind of construction shear wall frame support apparatus
CN207959991U (en) * 2018-01-22 2018-10-12 张家口恒泰集成房屋有限公司 Integrated house wallboard installs supporting member
CN209114873U (en) * 2018-11-16 2019-07-16 山西建设投资集团有限公司 A kind of civil engineering basic mode stationary fixture
CN109853950A (en) * 2019-04-07 2019-06-07 正太集团有限公司 A kind of building trade form clamp

Cited By (11)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111894280A (en) * 2020-07-21 2020-11-06 潘秋萍 Assembled building wall supporting method
CN111894280B (en) * 2020-07-21 2021-05-11 广东长海建设工程有限公司 Assembled building wall body support equipment
CN112392262A (en) * 2020-10-23 2021-02-23 杭州原创木结构工程有限公司 Fixed construction equipment of assembled building wall
CN112412076A (en) * 2020-11-20 2021-02-26 娄底市新越鼎建材科技有限公司 Auxiliary device for assembly type building
CN112922140A (en) * 2021-01-26 2021-06-08 南京嘉奋棠建筑科技有限公司 Construction method for building modular integrated house
CN113235958A (en) * 2021-05-14 2021-08-10 林迟文 Diversified guide system that supports of assembly type structure wall assembly
CN113235958B (en) * 2021-05-14 2022-07-19 中海建筑有限公司 Diversified guide system that supports of assembly type structure wall assembly
CN113323420A (en) * 2021-06-29 2021-08-31 吉林建筑大学 Prefabricated building wallboard pre-positioning device and method
CN113914500A (en) * 2021-11-08 2022-01-11 重庆工程职业技术学院 Light high strength assembled wall
CN113914500B (en) * 2021-11-08 2022-11-25 重庆工程职业技术学院 Light high strength assembled wall
CN114484140A (en) * 2022-01-24 2022-05-13 黄帅 Shock attenuation resistance to compression type cement tubular column

Also Published As

Publication number Publication date
CN110847620B (en) 2021-07-02

Similar Documents

Publication Publication Date Title
CN110847620B (en) Assembled wall body temporary connection fixed equipment
CN211074017U (en) Vibrating device with automatic floating function
CN211058020U (en) Connecting device for building external hanging and building main body
CN112049436A (en) Construction method for installing steel structure framework of plastic greenhouse
CN106703403A (en) Pouring formwork and wall pouring equipment
CN112196469B (en) Pile expanding equipment for bridge pile foundation
CN103233471A (en) Multi-functional hole cleaning machine for buildings
CN215518888U (en) Whole basement tower crane foundation and raft joint structure
CN113305688B (en) Repairing device for plank road plate
CN212052929U (en) Hydraulic engineering desilting device
CN210508276U (en) Wall cement laying equipment for building site
CN209829647U (en) Workshop dust collector for stone material processing
CN214657033U (en) Pile digging device for concrete pipe piles in constructional engineering
CN216324780U (en) Construction steel bar straightening device
CN217798254U (en) Prevent bending machine that pipeline processing skidded
CN212294658U (en) Hand-push type pile cutting machine for constructional engineering
CN216515640U (en) Channel lateral wall support equipment for hydraulic engineering construction
CN218557577U (en) Wall drilling equipment is used to house decoration
CN211663269U (en) Civil engineering reforms transform and transports transfer device with cement pipe way
CN212837583U (en) Pile digging device for concrete pipe piles in constructional engineering
CN220226922U (en) Waterproof board trolley convenient for laying coiled materials
CN217002374U (en) Corrosion-resistant chemical standard pump shaft
CN211057556U (en) Slip form method cement concrete side ditch construction equipment
CN216426682U (en) Municipal administration inspection shaft that facilitates use lid is with installation device
CN220056215U (en) Maintenance platform for air conditioner outdoor unit

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
TA01 Transfer of patent application right
TA01 Transfer of patent application right

Effective date of registration: 20210608

Address after: 223400 No.23, ximiao formation, miaodai village, Yixing Town, Lianshui County, Huai'an City, Jiangsu Province

Applicant after: Miao Zhenlu

Address before: North China University, No.3 Xueyuan Road, Taiyuan City, Shanxi Province

Applicant before: Zhang Ya

CB02 Change of applicant information
CB02 Change of applicant information

Address after: 223400 room 107, building 8, rongchuang Taohuayuan, No.9, Gaohe Road, Suzhou Industrial Park, Jiangsu Province

Applicant after: Miao Zhenlu

Address before: 223400 No.23, ximiao formation, miaodai village, Yixing Town, Lianshui County, Huai'an City, Jiangsu Province

Applicant before: Miao Zhenlu

GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right
TR01 Transfer of patent right

Effective date of registration: 20210831

Address after: 215159 Building 5, 205 Fengshan Road, Guangfu Town, Wuzhong District, Suzhou City, Jiangsu Province

Patentee after: Jiangsu Yuansong Building Decoration Engineering Co.,Ltd.

Address before: 223400 room 107, building 8, rongchuang Taohuayuan, No.9, Gaohe Road, Suzhou Industrial Park, Jiangsu Province

Patentee before: Miao Zhenlu

CP01 Change in the name or title of a patent holder
CP01 Change in the name or title of a patent holder

Address after: 215159 Building 5, 205 Fengshan Road, Guangfu Town, Wuzhong District, Suzhou City, Jiangsu Province

Patentee after: Jiangsu Bangde Lvjian Decoration Co.,Ltd.

Address before: 215159 Building 5, 205 Fengshan Road, Guangfu Town, Wuzhong District, Suzhou City, Jiangsu Province

Patentee before: Jiangsu Yuansong Building Decoration Engineering Co.,Ltd.