CN110836121A - A kind of anti-floating reinforcement structure and construction method of operating subway tunnel - Google Patents

A kind of anti-floating reinforcement structure and construction method of operating subway tunnel Download PDF

Info

Publication number
CN110836121A
CN110836121A CN201911184264.6A CN201911184264A CN110836121A CN 110836121 A CN110836121 A CN 110836121A CN 201911184264 A CN201911184264 A CN 201911184264A CN 110836121 A CN110836121 A CN 110836121A
Authority
CN
China
Prior art keywords
tunnel
floating
anchor rod
grouting
steel plate
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911184264.6A
Other languages
Chinese (zh)
Inventor
俞国骅
丁智
李栋樑
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Hangzhou Heyue Technology Co Ltd
Hongfujin Precision Industry Shenzhen Co Ltd
Original Assignee
Hangzhou Heyue Technology Co Ltd
Hongfujin Precision Industry Shenzhen Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Hangzhou Heyue Technology Co Ltd, Hongfujin Precision Industry Shenzhen Co Ltd filed Critical Hangzhou Heyue Technology Co Ltd
Priority to CN201911184264.6A priority Critical patent/CN110836121A/en
Publication of CN110836121A publication Critical patent/CN110836121A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/003Linings or provisions thereon, specially adapted for traffic tunnels, e.g. with built-in cleaning devices
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/08Lining with building materials with preformed concrete slabs
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/04Lining with building materials
    • E21D11/10Lining with building materials with concrete cast in situ; Shuttering also lost shutterings, e.g. made of blocks, of metal plates or other equipment adapted therefor
    • E21D11/105Transport or application of concrete specially adapted for the lining of tunnels or galleries ; Backfilling the space between main building element and the surrounding rock, e.g. with concrete
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D11/00Lining tunnels, galleries or other underground cavities, e.g. large underground chambers; Linings therefor; Making such linings in situ, e.g. by assembling
    • E21D11/38Waterproofing; Heat insulating; Soundproofing; Electric insulating
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D20/00Setting anchoring-bolts
    • E21D20/02Setting anchoring-bolts with provisions for grouting
    • E21D20/021Grouting with inorganic components, e.g. cement
    • EFIXED CONSTRUCTIONS
    • E21EARTH OR ROCK DRILLING; MINING
    • E21DSHAFTS; TUNNELS; GALLERIES; LARGE UNDERGROUND CHAMBERS
    • E21D21/00Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection
    • E21D21/0026Anchoring-bolts for roof, floor in galleries or longwall working, or shaft-lining protection characterised by constructional features of the bolts

Landscapes

  • Engineering & Computer Science (AREA)
  • Mining & Mineral Resources (AREA)
  • Structural Engineering (AREA)
  • Architecture (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Geochemistry & Mineralogy (AREA)
  • Geology (AREA)
  • Civil Engineering (AREA)
  • Chemical & Material Sciences (AREA)
  • Inorganic Chemistry (AREA)
  • Lining And Supports For Tunnels (AREA)

Abstract

本发明涉及一种已运营地铁隧道抗浮加固结构及施工方法,其特征在于:隧道衬砌内部设有内加固结构,隧道衬砌外部设有外加固结构和抗浮结构;内加固结构包括间隔设置的钢套圈和加劲板,加劲板与钢套圈焊接,钢套圈通过壁挂膨胀螺栓与隧道衬砌固定;所述的外加固结构包括注浆加固土体,注浆加固土体对称设在隧道衬砌两侧偏上部位置;所述的抗浮结构包括锚杆,锚杆设在隧道衬砌底部,锚杆顶端锚入道床内部,隧道衬砌以下部分的锚杆周围设有灌浆体。本发明能减少周围土体扰动对地铁隧道的影响,增加地铁隧道抗浮性能与隧道刚度,在地下水位上升或隧道上覆土体开挖时,减小隧道的上浮量与断面变形量。

Figure 201911184264

The invention relates to an anti-floating reinforcement structure and a construction method for an already operated subway tunnel. The steel ferrule and the stiffening plate, the stiffening plate and the steel ferrule are welded, and the steel ferrule is fixed with the tunnel lining through wall-mounted expansion bolts; the external reinforcement structure includes grouting reinforcement of the soil body, and the grouting reinforcement soil body is symmetrically arranged in the tunnel lining The two sides are located at the upper part; the anti-floating structure includes an anchor rod, the anchor rod is arranged at the bottom of the tunnel lining, the top of the anchor rod is anchored into the track bed, and a grouting body is provided around the anchor rod at the lower part of the tunnel lining. The invention can reduce the influence of surrounding soil disturbance on the subway tunnel, increase the anti-floating performance and tunnel rigidity of the subway tunnel, and reduce the floating amount and the section deformation of the tunnel when the groundwater level rises or the soil overlying the tunnel is excavated.

Figure 201911184264

Description

一种已运营地铁隧道抗浮加固结构及施工方法A kind of anti-floating reinforcement structure and construction method of operating subway tunnel

技术领域technical field

本发明涉及地铁隧道抗浮技术领域,尤其涉及一种已运营地铁隧道抗浮加固结构及施工方法。The invention relates to the technical field of anti-floating subway tunnels, in particular to an anti-floating reinforcement structure and a construction method of an already operated subway tunnel.

背景技术Background technique

随着车流量的日益增长,地面道路的交通压力逐渐加剧,由此地下空间的开发建设也正在全国各地掀起高潮,城市下穿隧道在空间上分离了交叉车流,提高了交通舒畅性,极大的缓解了城市交通压力。在地铁运营阶段,由于地下水位变化或周边施工活动,盾构隧道会发生上浮现象,管片上浮会对列车运行速度、运行安全、乘客舒适度产生不利影响。With the increasing traffic flow, the traffic pressure on the surface road is gradually intensifying. As a result, the development and construction of underground space is also setting off a climax all over the country. The urban underpass tunnels spatially separate the cross-traffic flow, improve the traffic comfort, and greatly improve the traffic comfort. relieve the pressure of urban traffic. During the subway operation stage, due to changes in groundwater level or surrounding construction activities, shield tunnels will float upward, and the floating of segments will adversely affect train running speed, running safety, and passenger comfort.

地铁隧道作为重要的城市交通生命线,对其变形要求极其严格。根据现有的相关规定,隧道绝对最大位移不能超过20mm,隧道回弹变形不超过15mm,隧道变形曲率半径必须大于15000m,相对变形必须小于1/2500。As an important urban traffic lifeline, subway tunnels have extremely strict deformation requirements. According to the existing relevant regulations, the absolute maximum displacement of the tunnel should not exceed 20mm, the rebound deformation of the tunnel should not exceed 15mm, the radius of curvature of the tunnel deformation must be greater than 15000m, and the relative deformation must be less than 1/2500.

目前最为常见的隧道结构抗浮方法是在设计阶段利用深埋于地面以下且位于地铁隧道顶部以上的土体自身重量,使这些土体的重量足以抵抗地铁隧道在地下所可能受到的浮力。但是,在沿海城市常年地下水位较高,地质条件较差,且地下水位随着季节变化也会发生较大变化,当地下隧道结构以上覆土产生的自重效应无法抵抗地下水浮力时,结构将产生上浮现象,严重时将导致盾构管片连接开裂,危及结构安全。另外,既有地铁隧道邻侧进行建筑施工活动日增多,当地铁隧道上方需要进行基坑开挖等土体卸荷工程时,由于基坑开挖会引起坑内土体回弹,会对近接地下建(构)筑造成附加位移,引起近接地铁隧道的上浮变形,造成隧道垂直直径变小,水平直径变大,隧道横断面形状改变,如果不及时对地铁隧道进行抗浮加固处理,隧道上浮位移超限,进而导致隧道管片破损,甚至会造成隧道涌水、坍塌等问题,危害生命和财产安全。At present, the most common anti-floating method for tunnel structures is to use the weight of the soil buried deep below the ground and above the top of the subway tunnel in the design stage, so that the weight of these soils is sufficient to resist the buoyancy that the subway tunnel may experience underground. However, in coastal cities, the groundwater level is high all year round and the geological conditions are poor, and the groundwater level will change greatly with the seasonal changes. When the self-weight effect of the overlying soil above the underground tunnel structure cannot resist the buoyancy of groundwater, the structure will float up. In severe cases, the connection of shield segments will be cracked, which will endanger the safety of the structure. In addition, construction activities on the adjacent sides of existing subway tunnels are increasing day by day. When soil unloading works such as foundation pit excavation are required above the subway tunnel, the soil body in the pit will rebound due to the excavation of the foundation pit, which will affect the adjacent ground. The construction (construction) causes additional displacement, causing the floating deformation of the adjacent subway tunnel, resulting in a smaller vertical diameter of the tunnel, a larger horizontal diameter, and a change in the shape of the cross section of the tunnel. Exceeding the limit will lead to the damage of the tunnel segment, and even cause problems such as tunnel water inflow and collapse, endangering life and property safety.

随着城市轨道交通运营里程的快速增加及运营时间的增长,加之盾构隧道邻侧区域一直是建筑热地,地铁运营阶段隧道发生上浮病害预计会越来越多,有必要研究运营阶段盾构隧道管片上浮病害治理措施,合理地选择隧道抗浮加固措施与手段,保证地铁隧道的正常使用。With the rapid increase of urban rail transit operation mileage and the increase of operation time, and the adjacent area of shield tunnel has always been a hot spot for construction, it is expected that more and more floating diseases will occur in the tunnel during the operation stage of the subway. It is necessary to study the shield tunnel during the operation stage. The control measures for the floating disease of the tunnel segment, and the reasonable selection of tunnel anti-floating reinforcement measures and means to ensure the normal use of the subway tunnel.

发明内容SUMMARY OF THE INVENTION

本发明的目的在于针对现有技术中缺乏有效措施解决运营地铁隧道抗浮加固问题以及施工结构承载力不足、施工整体性偏弱等缺陷,提出了一种针对已运营地铁、抗浮与加固相结合、步骤简单、设计合理且施工简便、施工结构整体性好、适合地铁停运窗口期施工的地铁隧道抗浮加固结构及施工方法。The purpose of the present invention is to solve the problems of anti-floating reinforcement of operating subway tunnels, insufficient bearing capacity of construction structures, weak construction integrity and other defects in the prior art due to the lack of effective measures. The invention discloses an anti-floating reinforcement structure and a construction method for a subway tunnel, which are combined, have simple steps, reasonable design, simple construction, good construction structure integrity, and are suitable for construction in the subway outage window period.

为了达到目的,本发明提供的技术方案为:In order to achieve the purpose, the technical scheme provided by the invention is:

本发明涉及的一种已运营地铁隧道抗浮加固结构,包括隧道衬砌,隧道衬砌内部设有道床,道床两侧设有承台,其特征在于:所述的隧道衬砌内部设有内加固结构,隧道衬砌外部设有外加固结构和抗浮结构;所述的内加固结构包括间隔设置的钢套圈和加劲板,加劲板与钢套圈焊接,钢套圈紧贴隧道衬砌内表面,并通过壁挂膨胀螺栓与隧道衬砌固定,钢套圈两侧采用环氧胶泥封堵,钢套圈与隧道衬砌之间的空隙采用环氧树脂填充;所述的外加固结构包括注浆加固土体,注浆加固土体对称设在隧道衬砌两侧偏上部位置;所述的抗浮结构包括若干锚杆,锚杆设在隧道衬砌底部,锚杆顶端锚入道床内部,隧道衬砌以下部分的锚杆周围设有灌浆体。The invention relates to an anti-floating reinforcement structure for an already operated subway tunnel, which includes a tunnel lining, a track bed is arranged inside the tunnel lining, and caps are arranged on both sides of the track bed. An outer reinforcement structure and an anti-floating structure are arranged outside the tunnel lining; the inner reinforcement structure includes a steel ferrule and a stiffening plate arranged at intervals. The wall-mounted expansion bolts are fixed with the tunnel lining, the two sides of the steel ferrule are sealed with epoxy cement, and the gap between the steel ferrule and the tunnel lining is filled with epoxy resin; The soil reinforced by the slurry is symmetrically arranged at the upper part of the two sides of the tunnel lining; the anti-floating structure includes several bolts, the bolts are arranged at the bottom of the tunnel lining, the top of the bolts are anchored into the track bed, and the lower part of the tunnel lining is around the bolts With grout body.

优选地,所述的钢套圈包括左弧形钢板和右弧形钢板,所述的加劲板包括左加劲板和右加劲板;左弧形钢板和右弧形钢板的弧度与隧道衬砌内侧弧度相同,隧道衬砌的内表面设有螺孔,左弧形钢板和右弧形钢板上对应位置设有螺孔,左弧形钢板和右弧形钢板紧贴隧道衬砌内表面设置,左弧形钢板和右弧形钢板均通过穿过螺孔的壁挂膨胀螺栓与隧道衬砌连接;左加劲板沿左弧形钢板的中轴线焊接连接,右加劲板沿右弧形钢板的中轴线焊接连接,左加劲板和右加劲板的顶端均设有连接顶板,两侧的连接顶板通过对拉螺栓相互连接;左弧形钢板和右弧形钢板的底部均焊接有底部连接板,底部连接板通过地脚螺栓配合螺帽固定在两侧的承台的上表面。Preferably, the steel ferrule includes a left arc-shaped steel plate and a right arc-shaped steel plate, and the stiffening plate includes a left stiffening plate and a right stiffening plate; the arc of the left arc-shaped steel plate and the right arc-shaped steel plate is the same as the inner arc of the tunnel lining Similarly, the inner surface of the tunnel lining is provided with screw holes, and the corresponding positions of the left and right curved steel plates are provided with screw holes. The left and right arc-shaped steel plates are connected to the tunnel lining through wall-mounted expansion bolts that pass through the screw holes; The tops of the plate and the right stiffening plate are provided with connecting top plates, and the connecting top plates on both sides are connected to each other by the pull bolts; the bottoms of the left arc steel plate and the right arc steel plate are welded with bottom connecting plates, and the bottom connecting plates are connected by anchor bolts The mating nuts are fixed on the upper surfaces of the caps on both sides.

优选地,所述的注浆加固土体内设有若干注浆花管,两侧注浆加固土体内的注浆花管左右对称,所述的隧道衬砌的左右两侧对应注浆花管的位置设有注浆孔,注浆花管贯穿注浆孔并插入隧道衬砌两侧的加固土体中,且注浆孔内填充密封材料封堵注浆孔。Preferably, several grouting flower tubes are arranged in the grouting reinforcement soil body, the grouting flower tubes in the grouting reinforcement soil body on both sides are symmetrical on the left and right, and the left and right sides of the tunnel lining correspond to the grouting flower tubes. A grouting hole is provided at the location, and the grouting flower pipe runs through the grouting hole and is inserted into the reinforced soil on both sides of the tunnel lining, and the grouting hole is filled with sealing material to block the grouting hole.

优选地,所述的锚杆包括锚杆主筋、若干抗浮加强筋、止水钢板和钢筋定位器;锚杆主筋贯穿止水钢板,抗浮加强筋的底端焊接于锚杆主筋与止水钢板的交汇处,止水钢板埋于道床内,并与道床钢筋焊接,钢筋定位器焊接于隧道衬砌以下部分的锚杆主筋上;所述的锚杆主筋和抗浮加强筋的顶端均设有弯折部分,抗浮加强筋的底端设有与锚杆主筋向平行的搭接部分,弯折部分的长度至少为锚杆主筋或抗浮加强筋直径的15倍,搭接部分的长度至少为抗浮加强筋直径的55倍。Preferably, the anchor rod includes a main anchor rod, several anti-floating reinforcing ribs, a water-stop steel plate and a steel locator; At the intersection of the steel plates, the water-stop steel plates are buried in the ballast and welded with the steel bars of the ballast, and the steel bar locators are welded to the main anchor bars of the lower part of the tunnel lining; In the bent part, the bottom end of the anti-floating reinforcement is provided with a lap joint parallel to the direction of the main reinforcement of the anchor rod. It is 55 times the diameter of the anti-floating reinforcement.

所述的承台通过若干膨胀螺栓与隧道衬砌连接。The bearing platform is connected with the tunnel lining through several expansion bolts.

本发明还涉及一种上述已运营地铁隧道抗浮加固结构的施工方法,其特征在于:其包括以下步骤:The present invention also relates to a construction method for the above-mentioned anti-floating reinforcement structure of an already operated subway tunnel, characterized in that it comprises the following steps:

1)对地铁轨道两侧的道床及水沟进行切割和凿除,至盾构管片露出;1) Cut and chisel the ballast bed and water ditch on both sides of the subway track until the shield segment is exposed;

2)在地铁轨道两侧道床切割和凿除的位置施工承台;2) Construction of the cap at the position where the ballast bed is cut and chiseled on both sides of the subway track;

3)在隧道衬砌两侧偏上部位置钻注浆孔,每钻孔形成一个注浆孔后立即沿注浆孔打入注浆花管,并注入水泥浆,硬化后形成注浆加固土体,然后在注浆孔位置灌注防水混凝土形成密封材料;3) Drill grouting holes at the upper part of the two sides of the tunnel lining. After each drilled hole forms a grouting hole, immediately drive a grouting flower tube along the grouting hole, and inject cement slurry. After hardening, the grouting reinforcement soil is formed. Then pour waterproof concrete at the position of the grouting hole to form a sealing material;

4)判断引起隧道上浮的原因,并计算单环隧道管片所需要的抗浮力F抗浮4) Determine the cause of the tunnel floating, and calculate the anti-buoyancy F anti-floating required for the single-ring tunnel segment;

5)根据单环隧道管片所受到浮力F值计算单根锚杆的轴向拉力设计值、锚杆配筋、锚杆长度、锚固体与锚杆的锚固长度;5) Calculate the axial tension design value of a single anchor rod, the anchor rod reinforcement, the anchor rod length, and the anchorage length of the anchor body and the anchor rod according to the buoyancy F floating value of the single ring tunnel segment;

6)对地铁隧道处的道床进行钻孔并根据步骤5计算的参数设置锚杆;6) Drill the track bed at the subway tunnel and set the anchor rod according to the parameters calculated in step 5;

7)安装刚套圈和加劲板。7) Install the ferrule and stiffener.

优选地,所述步骤4)为地下水上升引起的隧道上浮,单环隧道管片所需要的抗浮力F抗浮的计算步骤如下:Preferably, the step 4) is the floating of the tunnel caused by the rise of groundwater, and the calculation steps of the anti -buoyancy F required by the single-ring tunnel segment are as follows:

4.1)计算单环隧道管片的上覆土柱有效重量G4.1) Calculate the effective weight G soil of the overlying soil column of the single-ring tunnel segment,

4.2)计算单环隧道管片的自重G4.2) Calculate the self -weight G of the single-ring tunnel segment,

G=δπ(R2-r2c Gself =δπ(R 2 −r 2c ;

4.3)计算单环隧道管片所受到的地下水浮力F4.3) Calculate the groundwater buoyancy F float on the single-ring tunnel segment,

F=δπR2γwF float = δπR 2 γ w ;

4.4)计算所需抗浮力F抗浮4.4) Calculate the required anti-buoyancy F anti-buoyancy ,

Figure BDA0002292027800000041
Figure BDA0002292027800000041

其中,γa为土体饱和容重,γw为水的容重,R为盾构隧道外直径,h为管道上覆土层厚度,δ为单环管片的宽度,r为盾构隧道内直径;γf为使用阶段盾构隧道安全抗浮系数,取1.2;γ为隧道上覆土层重量分项系数,取1.0;γ为隧道结构自重分项系数,取1.0;γ抗浮为锚杆抗浮分项系数,取1.0。Among them, γ a is the saturated bulk density of soil, γ w is the bulk density of water, R is the outer diameter of the shield tunnel, h is the thickness of the overlying soil layer on the pipeline, δ is the width of the single ring segment, and r is the inner diameter of the shield tunnel; γ f is the safety anti - floating coefficient of the shield tunnel in the use stage, which is taken as 1.2; Anti-float sub-item coefficient, take 1.0.

优选地。所述步骤4)为隧道上方卸载引起隧道上浮,单环隧道管片所需要的抗浮力F抗浮的计算步骤如下:Preferably. The step 4) is that the unloading above the tunnel causes the tunnel to float, and the calculation steps of the anti -buoyancy F required by the single-ring tunnel segment are as follows:

4.1)根据基坑底部任一点的坐标(ξ,η)上的卸荷荷载pdξdη,计算隧道轴线处(x,y,z0)的附加应力σz4.1) According to the unloading load pd ξ d η on the coordinates (ξ, η) of any point at the bottom of the foundation pit, calculate the additional stress σ z at the tunnel axis (x, y, z 0 ),

式中,In the formula,

Figure BDA0002292027800000043
Figure BDA0002292027800000043

Figure BDA0002292027800000044
Figure BDA0002292027800000044

υ为泊松比;z0为隧道中心线与地表距离;h为基坑开挖深度;υ is Poisson’s ratio; z 0 is the distance between the tunnel centerline and the surface; h is the excavation depth of the foundation pit;

4.2)对于每环盾构管片,假定轴线处各点的附加应力相同,则每环管片由于基坑开挖受到的附加荷载F附加为4.2) For each ring of shield segments, assuming that the additional stress at each point at the axis is the same, the additional load F received by each ring segment due to the excavation of the foundation pit is:

F附加=δRσzF additional = δRσ z ;

4.3)则根据力的平衡关系,取F抗浮=F附加4.3) According to the force balance relationship, take F anti-floating = F additional .

优选地,所述步骤5)的具体步骤为:Preferably, the concrete steps of described step 5) are:

5.1)根据步骤4计算所得的F抗浮,计算锚杆的轴向拉力标准值Nak5.1) According to the F anti-floating calculated in step 4, calculate the standard value N ak of the axial tension of the bolt,

Nak=F抗浮N ak =F anti-float ;

5.2)根据轴向拉力标准值Nak计算单根锚杆轴向拉力设计值Nt5.2) Calculate the design value N t of the axial tensile force of a single bolt according to the standard value of the axial tensile force N ak ,

Nt=γQNakN tQ N ak ,

式中,γQ为荷载分项系数,取1.3;In the formula, γ Q is the load sub-item coefficient, which is taken as 1.3;

5.3)计算锚杆钢筋截面积As5.3) Calculate the cross-sectional area A s of the reinforcement bar of the anchor rod,

Figure BDA0002292027800000051
Figure BDA0002292027800000051

式中,Kt为锚杆杆体抗拉的安全系数;fyk为钢筋抗拉强度标准值;In the formula, K t is the safety factor of the tensile strength of the bolt body; f yk is the standard value of the tensile strength of the steel bar;

并根据计算得到的锚杆钢筋截面积As,确定锚杆钢筋的实配根数;And according to the calculated cross-sectional area A s of the anchor bar, determine the actual number of anchor bars;

5.4)计算地层与锚固体之间的长度La1和锚固体与锚杆钢筋之间La25.4) Calculate the length L a1 between the stratum and the anchor and the L a2 between the anchor and the steel bar,

Figure BDA0002292027800000052
Figure BDA0002292027800000052

选取La1和La2中较大的值,作为锚固体与锚杆(8)的锚固长度LaSelect the larger value between L a1 and L a2 as the anchoring length L a between the anchor and the bolt (8);

式中,fmg为地层与锚固注浆体之间的粘结强度标准值;fms为钢筋与锚固注浆体之间的粘结强度标准值;K为锚杆的抗拔安全系数,取2.0;D为锚杆锚固段的钻孔直径,取150mm;d为锚杆钢筋的直径,根据实际配筋确定;n为锚杆钢筋的数量,根据每环管片实际配筋确定;

Figure BDA0002292027800000053
为钢筋截面的粘结强度的降低系数,取值范围在0.6~0.85之间;ψ为锚杆锚固长度对粘结强度的影响系数,取1.0。In the formula, f mg is the standard value of the bond strength between the stratum and the anchor grouting body; f ms is the standard value of the bond strength between the steel bar and the anchor grouting body; K is the pullout safety factor of the anchor rod, which is taken as 2.0; D is the diameter of the drilled hole in the anchoring section of the bolt, which is 150mm; d is the diameter of the steel bar of the bolt, which is determined according to the actual reinforcement; n is the number of reinforcement bars of the anchor, which is determined according to the actual reinforcement of each ring segment;
Figure BDA0002292027800000053
is the reduction coefficient of the bond strength of the steel bar section, and the value ranges from 0.6 to 0.85; ψ is the influence coefficient of the anchorage length of the bolt on the bond strength, which is taken as 1.0.

优选地,所属步骤6)中锚杆的安装步骤为:Preferably, the installation steps of the anchor rod in step 6) are:

6.1)按照道床混凝土凿除迹线凿除混凝土,再利用潜孔锤成孔;6.1) Chisel the concrete according to the track of the concrete chisel of the track bed, and then use the down-the-hole hammer to form a hole;

6.2)将预先制作好的锚杆放入钻孔中,采用二次注浆的方式进行注浆;6.2) Put the pre-fabricated bolt into the drilled hole, and use the method of secondary grouting for grouting;

6.3)待浆液初凝后,回灌高强混凝土,填补道床混凝土凿除部位。6.3) After the initial setting of the slurry, refill the high-strength concrete to fill up the concrete chiseled part of the track bed.

优选地,所述步骤7)中刚套圈和加劲板的安装步骤为:Preferably, the installation steps of the rigid ferrule and the stiffening plate in the step 7) are:

7.1)根据钢套圈螺孔位置在隧道衬砌上设置相应的螺孔;7.1) Set corresponding screw holes on the tunnel lining according to the position of the screw holes of the steel ferrule;

7.2)将左加劲板焊接在左弧形钢板上,将右加劲板焊接在右弧形钢板上,将左弧形钢板与右弧形钢板吊装至指定位置,并用壁挂膨胀螺栓将左弧形钢板和右加劲板锚固在隧道衬砌上;7.2) Weld the left stiffening plate on the left arc-shaped steel plate, weld the right stiffening plate on the right arc-shaped steel plate, hoist the left arc-shaped steel plate and the right arc-shaped steel plate to the designated position, and use the wall-mounted expansion bolts to fix the left arc-shaped steel plate. And the right stiffener is anchored on the tunnel lining;

7.3)用对拉螺栓将两侧弧形钢板的连接顶板相互连接;7.3) Connect the connecting top plates of the curved steel plates on both sides to each other with the tension bolts;

7.4)分别采用地脚螺栓将左弧形钢板与左加劲板、右弧形钢板与右加劲板固定在两侧的承台上。7.4) Use anchor bolts to fix the left arc-shaped steel plate and the left stiffening plate, and the right arc-shaped steel plate and the right stiffening plate on the bearing platforms on both sides.

采用本发明涉及的方案,与现有技术相比存在以下有益效果:Adopt the scheme involved in the present invention, compared with the prior art, there are the following beneficial effects:

(1)本发明在隧道衬砌的内部设有由钢套圈和加劲板组成的内加固结构,隧道衬砌外部的左右两侧分别设有注浆加固土体,可以迅速抑制隧道上浮趋势,起到“速效”的作用,与内加固结构搭配在隧道衬砌的内外部形成了加固体系,提高隧道结构的稳定性,减小隧道的断面变形量,减少周边建筑施工活动对隧道造成的损坏。(1) In the present invention, an inner reinforcement structure composed of a steel ferrule and a stiffening plate is provided inside the tunnel lining, and the left and right sides of the outside of the tunnel lining are respectively provided with grouting reinforcement soil, which can quickly suppress the upward trend of the tunnel and play a role in The effect of "quick effect", combined with the inner reinforcement structure, forms a reinforcement system on the inside and outside of the tunnel lining, which improves the stability of the tunnel structure, reduces the cross-section deformation of the tunnel, and reduces the damage to the tunnel caused by surrounding construction activities.

(2)本发明在隧道衬砌的底部设置了抗浮结构,该抗浮结构与隧道上覆土配合抵消地下水对隧道的浮力,当水位发生变化或上覆土挖除时,抗浮结构起到阻止隧道上浮的作用,避免因隧道上浮而导致结构破坏,可以在荷载周期内长效控制隧道位移值。(2) In the present invention, an anti-floating structure is set at the bottom of the tunnel lining, and the anti-floating structure cooperates with the overlying soil of the tunnel to offset the buoyancy of groundwater on the tunnel. When the water level changes or the overlying soil is excavated, the anti-floating structure prevents the tunnel. The function of floating can avoid the structural damage caused by the floating of the tunnel, and can control the displacement value of the tunnel for a long time during the load period.

(3)本发明涉及的隧道衬砌的底部设置了抗浮结构的施工方法步骤简单,多以拼装结构为主,提高了施工效率,适用于已运营隧道短施工窗口期的工程特点,为已运营隧道的上浮变形提供了新的主动抗浮思路。(3) The construction method in which the anti-floating structure is arranged at the bottom of the tunnel lining involved in the present invention is simple in steps, mostly based on the assembled structure, which improves the construction efficiency, and is suitable for the engineering characteristics of the operating tunnel in the short construction window period, which is the most suitable for the operating tunnel. The floating deformation of the tunnel provides a new idea of active anti-floating.

(4)本发明同时解决了隧道上浮变形及隧道断面变形的两种隧道结构灾害,较大降低了施工成本,提高了隧道的抗变形能力,延长了隧道的使用寿命,实用价值高且使用效果好。(4) The present invention simultaneously solves two kinds of tunnel structural disasters, namely, the floating deformation of the tunnel and the deformation of the tunnel section, which greatly reduces the construction cost, improves the deformation resistance of the tunnel, prolongs the service life of the tunnel, and has high practical value and use effect. it is good.

(5)针对不同直径、不同地区的已运营地铁隧道的上浮变形修正均可采用本发明所公开技术,特别适用于在富水软弱地区等易发生衬砌病害危险地层中的隧道保护与加固,适用面广。(5) The technology disclosed in the present invention can be used to correct the floating deformation of the operating subway tunnels with different diameters and different regions, and is especially suitable for tunnel protection and reinforcement in dangerous strata prone to lining diseases such as water-rich and weak areas. Wide.

附图说明Description of drawings

图1是本发明涉及的地铁隧道抗浮加固结构的结构示意图;Fig. 1 is the structural schematic diagram of the subway tunnel anti-floating reinforcement structure involved in the present invention;

图2是附图1所示的地铁隧道抗浮加固结构的A-A剖面图;Fig. 2 is the A-A sectional view of the subway tunnel anti-floating reinforcement structure shown in accompanying drawing 1;

图3是注浆孔、锚杆孔、螺孔成孔结构的A-A剖面图;Fig. 3 is the A-A sectional view of the grouting hole, the bolt hole and the screw hole forming structure;

图4是设置锚杆后结构的A-A剖面图;Fig. 4 is the A-A sectional view of the structure after setting the anchor rod;

图5是锚杆节点大样图;Figure 5 is a large sample diagram of the anchor node;

图6是锚杆节点大样的1-1剖面图;Figure 6 is a 1-1 sectional view of a large sample of an anchor node;

图7是锚杆大样图;Figure 7 is a large sample drawing of the anchor rod;

图8是锚杆的配筋图;Figure 8 is the reinforcement diagram of the anchor rod;

图9是水位上升引起隧道上浮计算示意图;Figure 9 is a schematic diagram of the calculation of the floating of the tunnel caused by the rise of the water level;

图10是隧道上方卸载引起隧道上浮计算示意图;Figure 10 is a schematic diagram of the tunnel floating calculation caused by unloading above the tunnel;

图11是隧道管片位移监测图。Fig. 11 is the displacement monitoring diagram of the tunnel segment.

标注说明:1-隧道衬砌,2-道床,3-承台,4-钢套圈,5-加劲板,6-壁挂膨胀螺栓,7-注浆加固土体,8-锚杆,9-灌浆体,10-注浆花管,11-左弧形钢板,12-右弧形钢板,13-左加劲板,14-右加劲板,15-连接顶板,16-密封材料,17-地脚螺栓,18-底部连接板,19-对拉螺栓,20-道床钢筋,21-注浆孔,22-锚杆孔,23-膨胀螺栓,24-螺孔,25-锚杆主筋,26-抗浮加强筋,27-止水钢板,28-钢筋定位器,29-道床混凝土凿除迹线。Labeling instructions: 1-tunnel lining, 2-track bed, 3-cap, 4-steel ring, 5-stiffening plate, 6-wall expansion bolt, 7-grouting reinforcement, 8-anchor rod, 9-grouting Body, 10-grouting flower tube, 11-left curved steel plate, 12-right curved steel plate, 13-left stiffening plate, 14-right stiffening plate, 15-connecting top plate, 16-sealing material, 17-anchor bolt , 18- Bottom connecting plate, 19- Pair of tie bolts, 20- Ballistic bar, 21- Grouting hole, 22- Anchor rod hole, 23- Expansion bolt, 24- Screw hole, 25- Anchor rod main reinforcement, 26- Anti-floating Reinforcing ribs, 27-water-stop steel plate, 28-steel bar locator, 29-track bed concrete chisel trace.

具体实施方式Detailed ways

为进一步了解本发明的内容,结合实施例对本发明作详细描述,以下实施例用于说明本发明,但不用来限制本发明的范围。In order to further understand the content of the present invention, the present invention is described in detail with reference to the embodiments. The following embodiments are used to illustrate the present invention, but are not intended to limit the scope of the present invention.

实施例1Example 1

结合附图1~4所示,本发明涉及的一种已运营地铁隧道抗浮加固结构,用于解决因水位上升引起的隧道上浮或隧道上方卸载引起隧道上浮问题,该结构包括隧道衬砌1,隧道衬砌1内部设有道床2和内加固结构,隧道衬砌1外部设有外加固结构和抗浮结构,道床2两侧设有承台3,承台3通过若干膨胀螺栓23与隧道衬砌1连接。With reference to Figures 1 to 4, the present invention relates to an anti-floating reinforcement structure for an already operating subway tunnel, which is used to solve the problem of tunnel floating caused by rising water level or unloading above the tunnel. The structure includes a tunnel lining 1, The inside of the tunnel lining 1 is provided with a ballast bed 2 and an inner reinforcement structure, the outside of the tunnel lining 1 is provided with an outer reinforcement structure and an anti-floating structure, and a cap 3 is provided on both sides of the ballast bed 2, and the cap 3 is connected with the tunnel lining 1 through a number of expansion bolts 23 .

结合附图1~4所示,所述的内加固结构包括间隔设置的钢套圈4和加劲板5,加劲板5与钢套圈4焊接,钢套圈4包括左弧形钢板11和右弧形钢板12,加劲板5包括左加劲板13和右加劲板14;左弧形钢板11和右弧形钢板12的弧度与隧道衬砌1内侧弧度相同,隧道衬砌1的内表面设有螺孔24,左弧形钢板11和右弧形钢板12上对应位置设有螺孔,左弧形钢板11和右弧形钢板12紧贴隧道衬砌1内表面设置,左弧形钢板11和右弧形钢板12均通过穿过螺孔24的壁挂膨胀螺栓6与隧道衬砌1连接,进而使钢套圈4紧贴隧道衬砌1内表面,钢套圈4两侧采用环氧胶泥封堵,钢套圈4与隧道衬砌1之间的空隙采用环氧树脂填充;左加劲板13沿左弧形钢板11的中轴线焊接连接,右加劲板14沿右弧形钢板12的中轴线焊接连接,左加劲板13和右加劲板14的顶端均设有连接顶板15,两侧的连接顶板15通过对拉螺栓19相互连接;左弧形钢板11和右弧形钢板12的底部均焊接有底部连接板18,底部连接板18通过地脚螺栓17配合螺帽固定在两侧的承台3的上表面。As shown in Figures 1 to 4, the inner reinforcement structure includes a steel ferrule 4 and a stiffening plate 5 arranged at intervals, the stiffening plate 5 is welded with the steel ferrule 4, and the steel ferrule 4 includes a left arc-shaped steel plate 11 and a right The arc steel plate 12 and the stiffening plate 5 include a left stiffening plate 13 and a right stiffening plate 14; the arc of the left arc steel plate 11 and the right arc steel plate 12 is the same as the inner arc of the tunnel lining 1, and the inner surface of the tunnel lining 1 is provided with screw holes 24. There are screw holes on corresponding positions of the left arc-shaped steel plate 11 and the right arc-shaped steel plate 12. The left arc-shaped steel plate 11 and the right arc-shaped steel plate 12 are arranged close to the inner surface of the tunnel lining 1. The left arc-shaped steel plate 11 and the right arc-shaped steel plate The steel plates 12 are all connected to the tunnel lining 1 through the wall-mounted expansion bolts 6 passing through the screw holes 24, so that the steel ferrule 4 is closely attached to the inner surface of the tunnel lining 1. Both sides of the steel ferrule 4 are sealed with epoxy cement, and the steel ferrule The gap between 4 and the tunnel lining 1 is filled with epoxy resin; the left stiffening plate 13 is welded and connected along the central axis of the left arc-shaped steel plate 11, the right stiffening plate 14 is welded and connected along the central axis of the right arc-shaped steel plate 12, and the left stiffening plate 13 and the top of the right stiffening plate 14 are provided with a connecting top plate 15, and the connecting top plates 15 on both sides are connected to each other through a pair of tension bolts 19; the bottom of the left arc-shaped steel plate 11 and the right arc-shaped steel plate 12 are welded with a bottom connecting plate 18, The bottom connecting plate 18 is fixed on the upper surfaces of the bearing platforms 3 on both sides by means of anchor bolts 17 and nuts.

结合附图1、2和4所述的外加固结构包括注浆加固土体7,注浆加固土体7对称设在隧道衬砌1两侧偏上部位置,注浆加固体7是通过若干注浆花管10向两侧的土中注入水泥浆,水泥浆硬化后形成的,注浆花管10不再拔出;两侧注浆加固土体7内的注浆花管10左右对称,隧道衬砌1的左右两侧对应注浆花管10的位置设有注浆孔21,注浆花管10贯穿注浆孔21并插入隧道衬砌1两侧土壤中,通过注浆花管10向土中注入水泥浆,水泥浆硬化后形成加固土体7,且注入水泥浆后,在注浆孔21内浇筑混凝土,形成填充密封材料16,用于封堵注浆孔21,防止水泥浆从注浆孔21处倒流。The external reinforcement structure described in conjunction with Figures 1, 2 and 4 includes a grouting reinforcement soil body 7, and the grouting reinforcement soil body 7 is symmetrically arranged at the upper part of both sides of the tunnel lining 1. The grouting reinforcement 7 is formed by several grouting. The flower tube 10 injects cement slurry into the soil on both sides, and formed after the cement slurry hardens, the grouting flower tube 10 will not be pulled out; The left and right sides of 1 are provided with grouting holes 21 at the positions corresponding to the grouting flower tube 10. The grouting flower tube 10 penetrates the grouting hole 21 and is inserted into the soil on both sides of the tunnel lining 1, and is injected into the soil through the grouting flower tube 10. Cement slurry, the cement slurry is hardened to form a reinforced soil body 7, and after the cement slurry is injected, concrete is poured in the grouting hole 21 to form a filling and sealing material 16, which is used to block the grouting hole 21 and prevent the cement slurry from entering the grouting hole. 21 backflows.

结合附图1~4所示,所述的抗浮结构包括若干锚杆8,结合附图5~7所示,锚杆8包括锚杆主筋25、若干抗浮加强筋26、止水钢板27和钢筋定位器28;锚杆主筋25贯穿止水钢板27,抗浮加强筋26的底端焊接于锚杆主筋25与止水钢板27的交汇处,止水钢板27埋于道床2内,并与道床钢筋20焊接,钢筋定位器28焊接于隧道衬砌1以下部分的锚杆主筋25上;结合附图5、7和8所示,所述的锚杆主筋25和抗浮加强筋26的顶端均设有弯折部分,抗浮加强筋26的底端设有与锚杆主筋25向平行的搭接部分,弯折部分的长度至少为锚杆主筋25或抗浮加强筋26直径的15倍,搭接部分的长度至少为抗浮加强筋26直径的55倍,锚杆8插入设在隧道衬砌1底部的土中,钢筋定位器28位于锚杆孔22内,钢筋定位器28的外径略小于锚杆孔22的孔径,水泥浆可以透过钢筋定位器28与锚杆孔22之间的空隙,锚杆8顶端锚入道床2内部,隧道衬砌1以下部分的锚杆8周围注入水泥浆形成灌浆体9。As shown in Figures 1 to 4, the anti-floating structure includes several anchor rods 8. As shown in Figures 5 to 7, the anchor rod 8 includes anchor rod main bars 25, several anti-floating reinforcement ribs 26, and water-stop steel plates 27. and the steel bar locator 28; the main anchor bar 25 runs through the water-stop steel plate 27, and the bottom end of the anti-floating reinforcing bar 26 is welded at the intersection of the anchor bar main bar 25 and the water-stop steel plate 27, and the water-stop steel plate 27 is buried in the ballast 2, and Welded with the ballast reinforcement 20, the reinforcement locator 28 is welded to the main anchor reinforcement 25 of the lower part of the tunnel lining 1; as shown in Figures 5, 7 and 8, the top of the main anchor reinforcement 25 and the anti-floating reinforcement 26 Both are provided with a bent part, the bottom end of the anti-floating reinforcing rib 26 is provided with an overlapping part parallel to the main anchor 25, and the length of the bent part is at least 15 times the diameter of the anchor main rib 25 or the anti-floating reinforcing rib 26 , the length of the overlapping part is at least 55 times the diameter of the anti-floating reinforcement 26, the anchor rod 8 is inserted into the soil provided at the bottom of the tunnel lining 1, the reinforcement locator 28 is located in the anchor rod hole 22, and the outer diameter of the reinforcement locator 28 Slightly smaller than the diameter of the bolt hole 22, the cement slurry can pass through the gap between the steel bar locator 28 and the bolt hole 22, the top of the bolt 8 is anchored into the track bed 2, and cement is injected around the bolt 8 in the part below the tunnel lining 1 The grout forms the grout body 9 .

实施例2Example 2

当已运营地铁隧道因水位上升引起隧道上浮时,采用以下步骤进行施工:When the operating subway tunnel floats up due to the rising water level, the following steps are used for construction:

1)根据运营线路的限界、线路的最小半径、最大坡度等施工环境选定施工用的机械手和平板车;然后对盾构隧道内部管线迁改,主要是将强弱电侧支架移位,线路归整等,为施工提供有效作用场地;然后对地铁轨道两侧的道床2及水沟进行切割和凿除,至盾构管片露出,切割后将道床2的侧面进行凿毛处理,并且,利用高压水枪对隧道衬砌1表面进行清洗,对管片表面的崩块、钙化物等松动物进行处理。1) Select manipulators and flatbed trucks for construction according to the construction environment such as the limit of the operating line, the minimum radius of the line, and the maximum slope; Then, the track bed 2 and the water ditch on both sides of the subway track are cut and chiseled until the shield segment is exposed. After cutting, the side of the track bed 2 is chiseled. The high-pressure water gun cleans the surface of the tunnel lining 1, and treats loose animals such as disintegration and calcification on the surface of the segment.

2)在地铁轨道两侧道床切割和凿除的位置施工承台3:根据道床2的切割尺寸现场放样加工承台3,利用专用平板车运至现场,将承台3吊装到位后采用植入式砼将100mmM16不锈钢膨胀螺栓23锚固在管片上,进而将承台3固定,并在接缝处回灌水泥浆,承台3与道床2形成整体。2) Construction of platform 3 at the position where the ballast bed is cut and chiseled on both sides of the subway track: According to the cutting size of the ballast bed 2, the platform 3 is staked out and processed on site, transported to the site by a special flatbed truck, and the platform 3 is hoisted in place and then implanted The concrete anchors 100mmM16 stainless steel expansion bolts 23 on the segment, and then fixes the cap 3, and re-grows cement at the joint, so that the cap 3 and the track bed 2 form a whole.

3)在隧道衬砌1两侧偏上部位置钻注浆孔21,每侧设置两排,每排3个孔,每钻孔形成一个注浆孔21后立即沿注浆孔21打入注浆花管10,注浆花管10的打入深度为2m,并注入水泥浆,注浆压力0.3~0.5Mpa,水泥浆硬化后形成注浆加固土体7,然后在注浆孔21位置灌注防水混凝土形成密封材料16,密封材料16的作用在于避免地下水进入隧道衬砌1以及水泥浆外渗。3) Drill grouting holes 21 at the upper part of both sides of the tunnel lining 1, and set up two rows on each side with 3 holes in each row. After each drilled hole forms a grouting hole 21, immediately drive grouting flowers along the grouting hole 21. Pipe 10, the grouting flower pipe 10 has a driving depth of 2m, and injects grout with a grouting pressure of 0.3-0.5Mpa. After the grout is hardened, the grouting reinforcement soil 7 is formed, and then water-proof concrete is poured into the grouting hole 21. The sealing material 16 is formed, and the function of the sealing material 16 is to prevent the groundwater from entering the tunnel lining 1 and the cement slurry from seeping out.

4)判断引起隧道上浮的原因,并计算单环隧道管片所需要的抗浮力F抗浮,本实施例中是因水位上升引起的隧道上浮,结合附图9所示,计算方式为:4) Determine the cause of the tunnel floating, and calculate the anti-buoyancy F anti-floating required for the single-ring tunnel segment. In the present embodiment, it is the tunnel floating caused by the rise of the water level. Combined with Figure 9, the calculation method is:

4.1)计算单环隧道管片的上覆土柱有效重量G4.1) Calculate the effective weight G soil of the overlying soil column of the single-ring tunnel segment,

Figure BDA0002292027800000091
Figure BDA0002292027800000091

4.2)计算单环隧道管片的自重G4.2) Calculate the self -weight G of the single-ring tunnel segment,

G=δπ(R2-r2c Gself =δπ(R 2 −r 2c ;

4.3)计算单环隧道管片所受到的地下水浮力F4.3) Calculate the groundwater buoyancy F float on the single-ring tunnel segment,

F=δπR2γwF float = δπR 2 γ w ;

4.4)计算所需抗浮力F抗浮4.4) Calculate the required anti-buoyancy F anti-buoyancy ,

Figure BDA0002292027800000092
Figure BDA0002292027800000092

其中,γa为土体饱和容重,γw为水的容重,R为盾构隧道外直径,h为管道上覆土层厚度,δ为单环管片的宽度,r为盾构隧道内直径;γf为使用阶段盾构隧道安全抗浮系数,取1.2;γ为隧道上覆土层重量分项系数,取1.0;γ为隧道结构自重分项系数,取1.0;γ抗浮为锚杆抗浮分项系数,取1.0。Among them, γ a is the saturated bulk density of soil, γ w is the bulk density of water, R is the outer diameter of the shield tunnel, h is the thickness of the overlying soil layer on the pipeline, δ is the width of the single ring segment, and r is the inner diameter of the shield tunnel; γ f is the safety anti - floating coefficient of the shield tunnel in the use stage, which is taken as 1.2; Anti-float sub-item coefficient, take 1.0.

5)根据单环隧道管片所受到浮力F值计算单根锚杆8的轴向拉力设计值、锚杆8配筋、锚杆8长度、锚固体与锚杆8的锚固长度,具体步骤为:5) Calculate the axial tension design value of a single anchor rod 8, the reinforcement of the anchor rod 8, the length of the anchor rod 8, the anchoring length of the anchor body and the anchor rod 8 according to the floating value of the buoyancy F of the single-ring tunnel segment, and the specific steps for:

5.1)根据步骤4计算所得的F抗浮,计算锚杆的轴向拉力标准值Nak5.1) According to the F anti-floating calculated in step 4, calculate the standard value N ak of the axial tension of the bolt,

Nak=F抗浮N ak =F anti-float ;

5.2)根据轴向拉力标准值Nak计算单根锚杆轴向拉力设计值Nt5.2) Calculate the design value N t of the axial tensile force of a single bolt according to the standard value of the axial tensile force N ak ,

Nt=γQNakN tQ N ak ,

式中,γQ为荷载分项系数,取1.3;In the formula, γ Q is the load sub-item coefficient, which is taken as 1.3;

5.3)计算锚杆钢筋截面积As5.3) Calculate the cross-sectional area A s of the reinforcement bar of the anchor rod,

Figure BDA0002292027800000101
Figure BDA0002292027800000101

式中,Kt为锚杆杆体抗拉的安全系数;fyk为钢筋抗拉强度标准值;In the formula, K t is the safety factor of the tensile strength of the bolt body; f yk is the standard value of the tensile strength of the steel bar;

并根据计算得到的锚杆钢筋截面积As,确定锚杆钢筋的实配根数;And according to the calculated cross-sectional area A s of the anchor bar, determine the actual number of anchor bars;

5.4)计算地层与锚固体之间的长度La1和锚固体与锚杆钢筋之间La25.4) Calculate the length L a1 between the stratum and the anchor and the L a2 between the anchor and the steel bar,

Figure BDA0002292027800000102
Figure BDA0002292027800000102

选取La1和La2中较大的值,作为锚固体与锚杆(8)的锚固长度LaSelect the larger value between L a1 and L a2 as the anchoring length L a between the anchor and the bolt (8);

式中,fmg为地层与锚固注浆体之间的粘结强度标准值;fms为钢筋与锚固注浆体之间的粘结强度标准值;K为锚杆的抗拔安全系数,取2.0;D为锚杆锚固段的钻孔直径,取150mm;d为锚杆钢筋的直径,根据实际配筋确定;n为锚杆钢筋的数量,根据每环管片实际配筋确定;

Figure BDA0002292027800000103
为钢筋截面的粘结强度的降低系数,取值范围在0.6~0.85之间;ψ为锚杆锚固长度对粘结强度的影响系数,取1.0。In the formula, f mg is the standard value of the bond strength between the stratum and the anchor grouting body; f ms is the standard value of the bond strength between the steel bar and the anchor grouting body; K is the pullout safety factor of the anchor rod, which is taken as 2.0; D is the diameter of the drilled hole in the anchoring section of the bolt, which is 150mm; d is the diameter of the steel bar of the bolt, which is determined according to the actual reinforcement; n is the number of reinforcement bars of the anchor, which is determined according to the actual reinforcement of each ring segment;
Figure BDA0002292027800000103
is the reduction coefficient of the bond strength of the steel bar section, and the value ranges from 0.6 to 0.85; ψ is the influence coefficient of the anchorage length of the bolt on the bond strength, which is taken as 1.0.

6)对地铁隧道处的道床进行钻孔并根据步骤5)计算的参数设置锚杆8,具体方法为:6) Drilling the track bed at the subway tunnel and setting the anchor rod 8 according to the parameters calculated in step 5), the specific method is:

6.1)按照面状布置的原则放线定位分别布置在边长为60cm正方形的四个角点,做好锚杆位置标记,按照道床混凝土凿除迹线29凿除混凝土,形成圆台形凹槽,凿除时应尽量减少对道床钢筋的损伤,再利用潜孔锤成孔,孔径偏差不大于2cm,深度偏差不大于设计深度1%,钻孔时应避开道床2及隧道衬砌1钢筋位置,成孔后的结构如附图3所示;6.1) According to the principle of planar arrangement, the line positioning is arranged at the four corner points of the square with a side length of 60cm, and the position of the anchor rod is marked, and the concrete is chiseled according to the track 29 of the concrete chisel of the track bed to form a circular truncated groove. When chiseling, the damage to the steel bars of the track bed should be minimized, and then the down-the-hole hammer should be used to form holes. The diameter deviation should not be greater than 2cm, and the depth deviation should not be greater than 1% of the design depth. When drilling, the steel bars of track bed 2 and tunnel lining 1 should be avoided. The structure after the hole formation is shown in accompanying drawing 3;

6.2)将预先制作好的锚杆8放入钻孔中,采用二次注浆的方式,注浆压力大于1.0Mpa进行注浆作业;6.2) Put the prefabricated bolt 8 into the drill hole, and use the method of secondary grouting, and the grouting pressure is greater than 1.0Mpa to carry out the grouting operation;

6.3)待浆液初凝形成灌浆体9,在焊接止水钢板27上方回灌高强混凝土,填补道床混凝土凿除部位,形成附图4的结构。6.3) After the initial setting of the slurry to form the grouting body 9, the high-strength concrete is refilled above the welded water-stop steel plate 27 to fill the chiseled part of the track bed concrete to form the structure of FIG. 4 .

7)安装刚套圈4和加劲板5,刚套圈4和加劲板5的安装方法为:7) Install the rigid ferrule 4 and the stiffening plate 5. The installation method of the rigid ferrule 4 and the stiffening plate 5 is:

7.1)根据钢套圈螺孔位置在隧道衬砌1上设置相应的螺孔24,在左侧隧道衬砌1的管片上设置2排螺孔环向均匀布置,每排6个,右侧隧道衬砌1的管片亦是如此;7.1) Set corresponding screw holes 24 on the tunnel lining 1 according to the position of the screw holes of the steel ferrule, and set 2 rows of screw holes on the segment of the tunnel lining 1 on the left side and evenly arranged in the circumferential direction, 6 in each row, and 1 in the right tunnel lining 1 The same is true for the segment;

7.2)左右弧形钢板选用截面尺寸为20mm×150mm的钢拉条,弧度与隧道衬砌1内壁弧度一致,左右加劲板选用截面尺寸为20mm×80mm的钢条,弧度与弧形钢板弧度一致,将左加劲板13焊接在左弧形钢板11上,将右加劲板14焊接在右弧形钢板12上,钢板之间进行整体焊接,已保证形成一个良好的受力体系,焊缝均采用坡口焊,同时采用气体保护焊,焊缝等级要求为三级(钢材进场前表面均做防腐处理,焊缝需要重做防腐处理),利用机械手将左弧形钢板11与右弧形钢板12吊装至指定位置,并用壁挂膨胀螺栓6将左弧形钢板11和右加劲板14锚固在隧道衬砌1上;7.2) The left and right arc-shaped steel plates are made of steel rods with a section size of 20mm × 150mm, and the arc is the same as that of the inner wall of the tunnel lining 1. The left and right stiffening plates are selected from steel strips with a section size of 20mm × 80mm, and the arc is the same as that of the arc-shaped steel plate. The left stiffening plate 13 is welded on the left arc-shaped steel plate 11, and the right stiffening plate 14 is welded on the right arc-shaped steel plate 12. The steel plates are welded together as a whole to ensure a good stress system, and the welds are all grooved. Welding, gas shielded welding is used at the same time, and the weld level is required to be level 3 (the surface of the steel is subjected to anti-corrosion treatment before entering the site, and the weld needs to be redone anti-corrosion treatment). The left arc steel plate 11 and the right arc steel plate 12 are hoisted by a robot to the designated position, and anchor the left arc-shaped steel plate 11 and the right stiffening plate 14 on the tunnel lining 1 with wall-mounted expansion bolts 6;

7.3)用对拉螺栓19将两侧弧形钢板的连接顶板15相互连接;7.3) Connect the connecting top plates 15 of the arc-shaped steel plates on both sides to each other with the tension bolts 19;

7.4)分别采用地脚螺栓17将左弧形钢板11与左加劲板13、右弧形钢板12与右加劲板14固定在两侧的承台3上,形成内加固结构,如附图2所示;左右弧形钢板11、12形成完整的刚套圈4后,在刚套圈4两侧与隧道衬砌1的管片接缝处采用环氧胶泥封堵,刚套圈4两侧封堵预留注浆孔和出气孔,每侧管片不少于4个,再利用小型电动注浆泵自下而上压注环氧树脂,直至顶部预留孔溢出树脂为施工结束标志,并反复进行压注,最后管线、排水沟等设施恢复。7.4) Use anchor bolts 17 to fix the left arc-shaped steel plate 11 and the left stiffening plate 13, the right arc-shaped steel plate 12 and the right stiffening plate 14 on the bearing platforms 3 on both sides respectively to form an inner reinforcement structure, as shown in Figure 2. After the left and right arc-shaped steel plates 11 and 12 form a complete rigid ferrule 4, epoxy cement is used to seal the joints between the two sides of the rigid ferrule 4 and the segment of the tunnel lining 1, and both sides of the rigid ferrule 4 are sealed Reserve grouting holes and air outlet holes, with no less than 4 segments on each side, and then use a small electric grouting pump to inject epoxy resin from bottom to top until the resin overflows from the top reserved hole to mark the end of construction, and repeat the process. Pressure injection is carried out, and finally pipelines, drainage ditches and other facilities are restored.

结合附图11所示,在施工过程中,对隧道的沉降、水平位移、椭圆度、收敛等变形情况进行全面实时监控,如发现变形突变,立即采取应对措施,沉降量正值代表上浮,负值代表沉降,通过在管片上安置本发明,隧道管片的上浮趋势得到有效抑制,并出现明显回落并在位移量允许范围内保持稳定。With reference to Figure 11, during the construction process, comprehensive real-time monitoring of the deformation of the tunnel, such as settlement, horizontal displacement, ellipticity, and convergence, is carried out. The value represents the settlement, and by arranging the present invention on the segment, the upward tendency of the tunnel segment is effectively suppressed, and a significant drop occurs and remains stable within the allowable range of displacement.

实施例3Example 3

当已运营地铁隧道因隧道上方卸载引起隧道上浮时,采用以下步骤进行施工:When the operating subway tunnels float up due to unloading above the tunnels, the following steps are used for construction:

1)根据运营线路的限界、线路的最小半径、最大坡度等施工环境选定施工用的机械手和平板车;然后对盾构隧道内部管线迁改,主要是将强弱电侧支架移位,线路归整等,为施工提供有效作用场地;然后对地铁轨道两侧的道床2及水沟进行切割和凿除,至盾构管片露出,切割后将道床2的侧面进行凿毛处理,并且,利用高压水枪对隧道衬砌1表面进行清洗,对管片表面的崩块、钙化物等松动物进行处理。1) Select manipulators and flatbed trucks for construction according to the construction environment such as the limit of the operating line, the minimum radius of the line, and the maximum slope; Then, the track bed 2 and the water ditch on both sides of the subway track are cut and chiseled until the shield segment is exposed. After cutting, the side of the track bed 2 is chiseled. The high-pressure water gun cleans the surface of the tunnel lining 1, and treats loose animals such as disintegration and calcification on the surface of the segment.

2)在地铁轨道两侧道床切割和凿除的位置施工承台3:根据道床2的切割尺寸现场放样加工承台3,利用专用平板车运至现场,将承台3吊装到位后采用植入式砼将100mmM16不锈钢膨胀螺栓23锚固在管片上,进而将承台3固定,并在接缝处回灌水泥浆,承台3与道床2形成整体。2) Construction of platform 3 at the position where the ballast bed is cut and chiseled on both sides of the subway track: According to the cutting size of the ballast bed 2, the platform 3 is staked out and processed on site, transported to the site by a special flatbed truck, and the platform 3 is hoisted in place and then implanted The concrete anchors 100mmM16 stainless steel expansion bolts 23 on the segment, and then fixes the cap 3, and re-grows cement at the joint, so that the cap 3 and the track bed 2 form a whole.

3)在隧道衬砌1两侧偏上部位置钻注浆孔21,每侧设置两排,每排3个孔,每钻孔形成一个注浆孔21后立即沿注浆孔21打入注浆花管10,注浆花管10的打入深度为2m,并注入水泥浆,注浆压力0.3~0.5Mpa,水泥浆硬化后形成注浆加固土体7,然后在注浆孔21位置灌注防水混凝土形成密封材料16,密封材料16的作用在于避免地下水进入隧道衬砌1以及水泥浆外渗。3) Drill grouting holes 21 at the upper part of both sides of the tunnel lining 1, and set up two rows on each side with 3 holes in each row. After each drilled hole forms a grouting hole 21, immediately drive grouting flowers along the grouting hole 21. Pipe 10, the grouting flower pipe 10 has a driving depth of 2m, and injects grout with a grouting pressure of 0.3-0.5Mpa. After the grout is hardened, the grouting reinforcement soil 7 is formed, and then water-proof concrete is poured into the grouting hole 21. The sealing material 16 is formed, and the function of the sealing material 16 is to prevent the groundwater from entering the tunnel lining 1 and the cement slurry from seeping out.

4)判断引起隧道上浮的原因,并计算单环隧道管片所需要的抗浮力F抗浮,本实施例中是因隧道上方卸载引起的隧道上浮,结合附图10所示,计算方式为:4) Determine the cause of the tunnel floating, and calculate the anti-buoyancy F anti-floating required for the single-ring tunnel segment. In this embodiment, the tunnel is floating due to unloading above the tunnel. Combined with Figure 10, the calculation method is:

4.1)根据基坑底部任一点的坐标(ξ,η)上的卸荷荷载pdξdη,计算隧道轴线处(x,y,z0)的附加应力σz4.1) According to the unloading load pd ξ d η on the coordinates (ξ, η) of any point at the bottom of the foundation pit, calculate the additional stress σ z at the tunnel axis (x, y, z 0 ),

Figure BDA0002292027800000121
Figure BDA0002292027800000121

式中,In the formula,

Figure BDA0002292027800000132
Figure BDA0002292027800000132

υ为泊松比;z0为隧道中心线与地表距离;h为基坑开挖深度;υ is Poisson’s ratio; z 0 is the distance between the tunnel centerline and the surface; h is the excavation depth of the foundation pit;

4.2)对于每环盾构管片,假定轴线处各点的附加应力相同,则每环管片由于基坑开挖受到的附加荷载F附加4.2) For each ring of shield segments, assuming that the additional stress at each point at the axis is the same, the additional load F received by each ring segment due to the excavation of the foundation pit is:

F附加=δRσzF additional = δRσ z ;

4.3)根据力的平衡关系与隧道设计规范,4.3) According to the force balance relationship and the tunnel design specification,

F抗浮≥F附加 F anti-float ≥ F additional

则取F抗浮=F附加Then take F anti-float = F additional .

5)根据单环隧道管片所受到浮力F值计算单根锚杆8的轴向拉力设计值、锚杆8配筋、锚杆8长度、锚固体与锚杆8的锚固长度,具体步骤为:5) Calculate the axial tension design value of a single anchor rod 8, the reinforcement of the anchor rod 8, the length of the anchor rod 8, the anchoring length of the anchor body and the anchor rod 8 according to the floating value of the buoyancy F of the single-ring tunnel segment, and the specific steps for:

5.1)根据步骤4计算所得的F抗浮,计算锚杆的轴向拉力标准值Nak5.1) According to the F anti-floating calculated in step 4, calculate the standard value N ak of the axial tension of the bolt,

Nak=F抗浮N ak =F anti-float ;

5.2)根据轴向拉力标准值Nak计算单根锚杆轴向拉力设计值Nt5.2) Calculate the design value N t of the axial tensile force of a single bolt according to the standard value of the axial tensile force N ak ,

Nt=γQNakN tQ N ak ,

式中,γQ为荷载分项系数,取1.3;In the formula, γ Q is the load sub-item coefficient, which is taken as 1.3;

5.3)计算锚杆钢筋截面积As5.3) Calculate the cross-sectional area A s of the reinforcement bar of the anchor rod,

Figure BDA0002292027800000133
Figure BDA0002292027800000133

式中,Kt为锚杆杆体抗拉的安全系数;fyk为钢筋抗拉强度标准值;In the formula, K t is the safety factor of the tensile strength of the bolt body; f yk is the standard value of the tensile strength of the steel bar;

并根据计算得到的锚杆钢筋截面积As,确定锚杆钢筋的实配根数;And according to the calculated cross-sectional area A s of the anchor bar, determine the actual number of anchor bars;

5.4)计算地层与锚固体之间的长度La1和锚固体与锚杆钢筋之间La25.4) Calculate the length L a1 between the stratum and the anchor and the L a2 between the anchor and the steel bar,

Figure BDA0002292027800000134
Figure BDA0002292027800000134

选取La1和La2中较大的值,作为锚固体与锚杆8的锚固长度LaSelect the larger value between L a1 and L a2 as the anchoring length L a between the anchor and the anchor rod 8;

式中,fmg为地层与锚固注浆体之间的粘结强度标准值;fms为钢筋与锚固注浆体之间的粘结强度标准值;K为锚杆的抗拔安全系数,取2.0;D为锚杆锚固段的钻孔直径,取150mm;d为锚杆钢筋的直径,根据实际配筋确定;n为锚杆钢筋的数量,根据每环管片实际配筋确定;

Figure BDA0002292027800000141
为钢筋截面的粘结强度的降低系数,取值范围在0.6~0.85之间;ψ为锚杆锚固长度对粘结强度的影响系数,取1.0。In the formula, f mg is the standard value of the bond strength between the stratum and the anchor grouting body; f ms is the standard value of the bond strength between the steel bar and the anchor grouting body; K is the pullout safety factor of the anchor rod, which is taken as 2.0; D is the diameter of the drilled hole in the anchoring section of the bolt, which is 150mm; d is the diameter of the steel bar of the bolt, which is determined according to the actual reinforcement; n is the number of reinforcement bars of the anchor, which is determined according to the actual reinforcement of each ring segment;
Figure BDA0002292027800000141
is the reduction coefficient of the bond strength of the steel bar section, and the value ranges from 0.6 to 0.85; ψ is the influence coefficient of the anchorage length of the bolt on the bond strength, which is taken as 1.0.

6)对地铁隧道处的道床进行钻孔并根据步骤5)计算的参数设置锚杆8,具体方法为:6) Drilling the track bed at the subway tunnel and setting the anchor rod 8 according to the parameters calculated in step 5), the specific method is:

6.1)按照面状布置的原则放线定位分别布置在边长为60cm正方形的四个角点,做好锚杆位置标记,按照道床混凝土凿除迹线29凿除混凝土,形成圆台形凹槽,凿除时应尽量减少对道床钢筋的损伤,再利用潜孔锤成孔,孔径偏差不大于2cm,深度偏差不大于设计深度1%,钻孔时应避开道床2及隧道衬砌1钢筋位置,成孔后的结构如附图3所示;6.1) According to the principle of planar arrangement, the line positioning is arranged at the four corner points of the square with a side length of 60cm, and the position of the anchor rod is marked, and the concrete is chiseled according to the track 29 of the concrete chisel of the track bed to form a circular truncated groove. When chiseling, the damage to the steel bars of the track bed should be minimized, and then the down-the-hole hammer should be used to form holes. The diameter deviation should not be greater than 2cm, and the depth deviation should not be greater than 1% of the design depth. When drilling, the steel bars of track bed 2 and tunnel lining 1 should be avoided. The structure after the hole formation is shown in accompanying drawing 3;

6.2)将预先制作好的锚杆8放入钻孔中,采用二次注浆的方式,注浆压力大于1.0Mpa进行注浆作业;6.2) Put the prefabricated bolt 8 into the drill hole, and use the method of secondary grouting, and the grouting pressure is greater than 1.0Mpa to carry out the grouting operation;

6.3)待浆液初凝形成灌浆体9,在焊接止水钢板27上方回灌高强混凝土,填补道床混凝土凿除部位,形成附图4的结构。6.3) After the initial setting of the slurry to form the grouting body 9, the high-strength concrete is refilled above the welded water-stop steel plate 27 to fill the chiseled part of the track bed concrete to form the structure of FIG. 4 .

7)安装刚套圈4和加劲板5,刚套圈4和加劲板5的安装方法为:7) Install the rigid ferrule 4 and the stiffening plate 5. The installation method of the rigid ferrule 4 and the stiffening plate 5 is:

7.1)根据钢套圈螺孔位置在隧道衬砌1上设置相应的螺孔24,在左侧隧道衬砌1的管片上设置2排螺孔环向均匀布置,每排6个,右侧隧道衬砌1的管片亦是如此;7.1) Set corresponding screw holes 24 on the tunnel lining 1 according to the position of the screw holes of the steel ferrule, and set 2 rows of screw holes on the segment of the tunnel lining 1 on the left side and evenly arranged in the circumferential direction, 6 in each row, and 1 in the right tunnel lining 1 The same is true for the segment;

7.2)左右弧形钢板选用截面尺寸为20mm×150mm的钢拉条,弧度与隧道衬砌1内壁弧度一致,左右加劲板选用截面尺寸为20mm×80mm的钢条,弧度与弧形钢板弧度一致,将左加劲板13焊接在左弧形钢板11上,将右加劲板14焊接在右弧形钢板12上,钢板之间进行整体焊接,已保证形成一个良好的受力体系,焊缝均采用坡口焊,同时采用气体保护焊,焊缝等级要求为三级(钢材进场前表面均做防腐处理,焊缝需要重做防腐处理),利用机械手将左弧形钢板11与右弧形钢板12吊装至指定位置,并用壁挂膨胀螺栓6将左弧形钢板11和右加劲板14锚固在隧道衬砌1上;7.2) The left and right arc-shaped steel plates are made of steel rods with a section size of 20mm × 150mm, and the arc is the same as that of the inner wall of the tunnel lining 1. The left and right stiffening plates are selected from steel strips with a section size of 20mm × 80mm, and the arc is the same as that of the arc-shaped steel plate. The left stiffening plate 13 is welded on the left arc-shaped steel plate 11, and the right stiffening plate 14 is welded on the right arc-shaped steel plate 12. The steel plates are welded together as a whole to ensure a good stress system, and the welds are all grooved. Welding, gas shielded welding is used at the same time, and the weld level is required to be level 3 (the surface of the steel is subjected to anti-corrosion treatment before entering the site, and the weld needs to be redone anti-corrosion treatment). The left arc steel plate 11 and the right arc steel plate 12 are hoisted by a robot to the designated position, and anchor the left arc-shaped steel plate 11 and the right stiffening plate 14 on the tunnel lining 1 with wall-mounted expansion bolts 6;

7.3)用对拉螺栓19将两侧弧形钢板的连接顶板15相互连接;7.3) Connect the connecting top plates 15 of the arc-shaped steel plates on both sides to each other with the tension bolts 19;

7.4)分别采用地脚螺栓17将左弧形钢板11与左加劲板13、右弧形钢板12与右加劲板14固定在两侧的承台3上,形成内加固结构,如附图2所示;左右弧形钢板11、12形成完整的刚套圈4后,在刚套圈4两侧与隧道衬砌1的管片接缝处采用环氧胶泥封堵,刚套圈4两侧封堵预留注浆孔和出气孔,每侧管片不少于4个,再利用小型电动注浆泵自下而上压注环氧树脂,直至顶部预留孔溢出树脂为施工结束标志,并反复进行压注,最后管线、排水沟等设施恢复。7.4) Use anchor bolts 17 to fix the left arc-shaped steel plate 11 and the left stiffening plate 13, the right arc-shaped steel plate 12 and the right stiffening plate 14 on the bearing platforms 3 on both sides respectively to form an inner reinforcement structure, as shown in Figure 2. After the left and right arc-shaped steel plates 11 and 12 form a complete rigid ferrule 4, epoxy cement is used to seal the joints between the two sides of the rigid ferrule 4 and the segment of the tunnel lining 1, and both sides of the rigid ferrule 4 are sealed Reserve grouting holes and air outlet holes, with no less than 4 segments on each side, and then use a small electric grouting pump to inject epoxy resin from bottom to top until the resin overflows from the top reserved hole to mark the end of construction, and repeat the process. Pressure injection is carried out, and finally pipelines, drainage ditches and other facilities are restored.

结合附图11所示,在施工过程中,对隧道的沉降、水平位移、椭圆度、收敛等变形情况进行全面实时监控,如发现变形突变,立即采取应对措施,沉降量正值代表上浮,负值代表沉降,通过在管片上安置本发明,隧道管片的上浮趋势得到有效抑制,并出现明显回落并在位移量允许范围内保持稳定。With reference to Figure 11, during the construction process, comprehensive real-time monitoring of the deformation of the tunnel, such as settlement, horizontal displacement, ellipticity, and convergence, is carried out. The value represents the settlement, and by arranging the present invention on the segment, the upward tendency of the tunnel segment is effectively suppressed, and a significant drop occurs and remains stable within the allowable range of displacement.

以上结合实施例对本发明进行了详细说明,但所述内容仅为本发明的较佳实施例,不能被认为用于限定本发明的实施范围。凡依本发明申请范围所作的均等变化与改进等,均应仍属于本发明的专利涵盖范围之内。The present invention has been described in detail above with reference to the embodiments, but the above contents are only preferred embodiments of the present invention and cannot be considered to limit the implementation scope of the present invention. All equivalent changes and improvements made according to the scope of the application of the present invention should still fall within the scope of the patent of the present invention.

Claims (10)

1. The utility model provides an anti reinforced structure that floats of operation subway tunnel, includes tunnel lining (1), and tunnel lining is inside to be equipped with ballast bed (2), and ballast bed (2) both sides are equipped with cushion cap (3), its characterized in that: an inner reinforcing structure is arranged inside the tunnel lining (1), and an outer reinforcing structure and an anti-floating structure are arranged outside the tunnel lining; the inner reinforcing structure comprises steel sleeves (4) and reinforcing plates (5) which are arranged at intervals, the reinforcing plates (5) are welded with the steel sleeves (4), the steel sleeves (4) are tightly attached to the inner surface of the tunnel lining (1) and are fixed with the tunnel lining (1) through wall-mounted expansion bolts (6), two sides of the steel sleeves (4) are plugged by epoxy cement, and a gap between the steel sleeves (4) and the tunnel lining (1) is filled by epoxy resin; the outer reinforcing structure comprises grouting reinforcing soil bodies (7), and the grouting reinforcing soil bodies (7) are symmetrically arranged at the upper parts of the two sides of the tunnel lining (1); anti floating structure include a plurality of stock (8), establish in tunnel lining (1) bottom stock (8), inside stock (8) top anchor income railway roadbed (2), be equipped with grout body (9) around stock (8) of the following part of tunnel lining (1).
2. The operated subway tunnel anti-floating reinforcement structure according to claim 1, characterized in that: the steel sleeve (4) comprises a left arc-shaped steel plate (11) and a right arc-shaped steel plate (12), and the stiffening plate (5) comprises a left stiffening plate (13) and a right stiffening plate (14); the radian of the left arc-shaped steel plate (11) and the right arc-shaped steel plate (12) is the same as that of the inner side of the tunnel lining (1), the inner surface of the tunnel lining (1) is provided with a screw hole (24), the corresponding positions of the left arc-shaped steel plate (11) and the right arc-shaped steel plate (12) are provided with screw holes, the left arc-shaped steel plate (11) and the right arc-shaped steel plate (12) are arranged close to the inner surface of the tunnel lining (1), and the left arc-shaped steel plate (11) and the right arc-shaped steel plate (12) are connected with the tunnel lining (1) through wall-hanging expansion bolts (6) penetrating through the; the left stiffening plate (13) is welded and connected along the central axis of the left arc-shaped steel plate (11), the right stiffening plate (14) is welded and connected along the central axis of the right arc-shaped steel plate (12), the top ends of the left stiffening plate (13) and the right stiffening plate (14) are respectively provided with a connecting top plate (15), and the connecting top plates (15) at the two sides are mutually connected through split bolts (19); bottom connecting plates (18) are welded at the bottoms of the left arc-shaped steel plate (11) and the right arc-shaped steel plate (12), and the bottom connecting plates (18) are fixed on the upper surfaces of the bearing platforms (3) on the two sides through foundation bolts (17) matched with nuts.
3. The operated subway tunnel anti-floating reinforcement structure according to claim 1, characterized in that: the tunnel lining is characterized in that a plurality of grouting floral tubes (10) are arranged in the grouting reinforced soil body (7), the grouting floral tubes (10) in the grouting reinforced soil body (7) on two sides are bilaterally symmetrical, grouting holes (21) are formed in the positions, corresponding to the grouting floral tubes (10), on the left side and the right side of the tunnel lining (1), the grouting floral tubes (10) penetrate through the grouting holes (21) and are inserted into the reinforced soil body (7) on two sides of the tunnel lining (1), and the grouting holes (21) are filled with sealing materials (16) for plugging the grouting holes (21).
4. The operated subway tunnel anti-floating reinforcement structure according to claim 1, characterized in that: the anchor rod (8) comprises anchor rod main ribs (25), a plurality of anti-floating reinforcing ribs (26), a water stop steel plate (27) and a steel bar positioner (28); the anchor rod main rib (25) penetrates through the water stop steel plate (27), the bottom end of the anti-floating reinforcing rib (26) is welded at the junction of the anchor rod main rib (25) and the water stop steel plate (27), the water stop steel plate (27) is buried in the ballast bed (2) and is welded with ballast bed reinforcing steel bars (20), and the reinforcing steel bar positioner (28) is welded on the anchor rod main rib (25) of the part below the tunnel lining (1); the anchor rod main rib (25) and the anti-floating reinforcing rib (26) are respectively provided with a bending part at the top end, the bottom end of the anti-floating reinforcing rib (26) is provided with an overlap joint part parallel to the anchor rod main rib (25), the length of the bending part is at least 15 times of the diameter of the anchor rod main rib (25) or the anti-floating reinforcing rib (26), and the length of the overlap joint part is at least 55 times of the diameter of the anti-floating reinforcing rib (26).
5. A construction method of the operated subway tunnel anti-floating reinforcement structure of claim 1, characterized in that: which comprises the following steps:
1) cutting and chiseling the ballast beds and the ditches on the two sides of the subway track until shield segments are exposed;
2) constructing bearing platforms (3) at the cutting and chiseling positions of the track beds on the two sides of the subway track;
3) drilling grouting holes (21) at the upper positions of the two sides of the tunnel lining (1), driving a grouting perforated pipe (10) along the grouting holes (21) immediately after each drilling hole forms one grouting hole (21), injecting cement paste, forming a grouting reinforced soil body (7) after hardening, and then injecting waterproof concrete at the grouting hole positions to form a sealing material (16);
4) judging the reason causing the tunnel to float upwards, and calculating the anti-floating force F required by the single-ring tunnel segmentAnti-floating
5) According to the buoyancy F borne by the single-ring tunnel segmentFloating bodyCalculating the axial tension design value of a single anchor rod (8), the reinforcement of the anchor rod (8), the length of the anchor rod (8) and the anchoring length of an anchoring body and the anchor rod (8);
6) drilling a track bed at the subway tunnel and setting an anchor rod (8) according to the parameters calculated in the step 5);
7) and (5) installing the steel ferrule (4) and the stiffening plate.
6. The construction method of the operated subway tunnel anti-floating reinforcement structure according to claim 5, characterized in that: the step 4) is the floating of the tunnel caused by the rising of underground water and the anti-floating force F required by the single-ring tunnel segmentAnti-floatingThe calculation steps are as follows:
4.1) calculating the effective weight G of the overlying soil column of the single-ring tunnel segmentSoil for soil
Figure FDA0002292027790000021
4.2) calculating the dead weight G of the single-ring tunnel segmentFrom
GFrom=δπ(R2-r2c
4.3) calculation of Single Ring TunnelGroundwater buoyancy F suffered by pipe pieceFloating body
FFloating body=δπR2γw
4.4) calculating the required anti-buoyancy FAnti-floating
Figure FDA0002292027790000031
Wherein, γaIs the saturated volume weight of the soil body, gammawThe volume weight of water is shown, R is the outer diameter of the shield tunnel, h is the thickness of a soil layer on the pipeline, delta is the width of a single-ring segment, and R is the inner diameter of the shield tunnel; gamma rayfTaking 1.2 as the safe anti-floating coefficient of the shield tunnel in the using stage; gamma raySoil for soilTaking the weight coefficient of the overburden layer on the tunnel as 1.0; gamma rayFromTaking 1.0 as the self-weight item coefficient of the tunnel structure; gamma rayAnti-floatingTaking the coefficient of the anti-floating component of the anchor rod as 1.0.
7. The construction method of the operated subway tunnel anti-floating reinforcement structure according to claim 5, characterized in that: the step 4) causes the tunnel to float up for the unloading above the tunnel, and the anti-floating force F required by the single-ring tunnel segmentAnti-floatingThe calculation steps are as follows:
4.1) unloading load pd according to the coordinate (ξ) of any point at the bottom of the foundation pitξdηCalculating (x, y, z) at the tunnel axis0) Additional stress σ ofz
Figure FDA0002292027790000033
Figure FDA0002292027790000034
In the formula (I), the compound is shown in the specification,
Figure FDA0002292027790000035
upsilon is Poisson's ratio; z is a radical of0The distance between the central line of the tunnel and the earth surface is taken as the distance; h is the excavation depth of the foundation pit;
4.2) for each ring of shield segments, assuming that the additional stress of each point at the axis is the same, the additional load F borne by each ring of shield segments due to foundation pit excavationAttachment(s)Is composed of
FAttachment(s)=δRσz
4.3) according to the balance relation of the forces and the design specification of the tunnel, taking FAnti-floating=FAttachment(s)
8. The construction method of the operated subway tunnel anti-floating reinforcement structure according to claim 5, characterized in that: the specific steps of the step 5) are as follows:
5.1) F calculated according to step 4Anti-floatingCalculating the axial tension standard value N of the anchor rodak
Nak=FAnti-floating
5.2) according to the axial tension standard value NakCalculating the design value N of the axial tension of a single anchor rodt
Nt=γQNak
In the formula, gammaQTaking the load element coefficient as 1.3;
5.3) calculating the section area A of the reinforcing steel bar of the anchor rods
Figure FDA0002292027790000041
In the formula, KtThe safety factor of the tensile strength of the anchor rod body is increased; f. ofykThe standard value of the tensile strength of the steel bar is;
and according to the calculated sectional area A of the anchor rod reinforcing steel barsDetermining the number of actual matching anchor rod reinforcing steel bars;
5.4) calculating the length L between the formation and the anchora1And L between anchor body and anchor rod steel bara2
Figure FDA0002292027790000042
Selecting La1And La2The larger value is used as the anchoring length L between the anchoring body and the anchor rod (8)a
In the formula (f)mgThe standard value of the bonding strength between the stratum and the anchoring grouting body is obtained; f. ofmsThe standard value of the bonding strength between the steel bar and the anchoring grouting body is obtained; k is the anti-pulling safety coefficient of the anchor rod, and 2.0 is taken; d is the drilling diameter of the anchor rod anchoring section, and is taken as 150 mm; d is the diameter of the anchor rod steel bar and is determined according to actual reinforcement; n is the number of anchor rod reinforcing steel bars and is determined according to the actual reinforcing steel bars of each ring pipe sheet;the coefficient is the reduction coefficient of the bonding strength of the section of the steel bar, and the value range is between 0.6 and 0.85; psi is the influence coefficient of anchor rod anchoring length to bonding strength, takes 1.0.
9. The construction method of the operated subway tunnel anti-floating reinforcement structure according to claim 5, characterized in that: the installation steps of the anchor rod (8) in the step 6) are as follows:
6.1) chiseling concrete according to the track bed concrete chiseling trace (29), and then forming holes by using a down-the-hole hammer;
6.2) placing the anchor rod (8) which is manufactured in advance into the drilled hole, and grouting in a secondary grouting mode;
6.3) after the slurry is initially set, recharging the high-strength concrete and filling the chiseling part of the ballast bed concrete.
10. The construction method of the operated subway tunnel anti-floating reinforcement structure according to claim 5, characterized in that: the step 7) of mounting the steel ferrule (4) and the stiffening plate (5) comprises the following steps:
7.1) arranging corresponding screw holes (24) on the tunnel lining (1) according to the positions of the screw holes of the steel sleeve ring;
7.2) welding the left stiffening plate (13) on the left arc-shaped steel plate (11), welding the right stiffening plate (14) on the right arc-shaped steel plate (12), hoisting the left arc-shaped steel plate (11) and the right arc-shaped steel plate (12) to specified positions, and anchoring the left arc-shaped steel plate (11) and the right stiffening plate (14) on the tunnel lining (1) by using wall-hanging expansion bolts (6);
7.3) connecting the connecting top plates (15) of the arc-shaped steel plates at the two sides with each other by using split bolts (19);
7.4) fixing the left arc-shaped steel plate (11) and the left stiffening plate (13) and the right arc-shaped steel plate (12) and the right stiffening plate (14) on the bearing platforms (3) at two sides by adopting foundation bolts (17) respectively.
CN201911184264.6A 2019-11-27 2019-11-27 A kind of anti-floating reinforcement structure and construction method of operating subway tunnel Pending CN110836121A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911184264.6A CN110836121A (en) 2019-11-27 2019-11-27 A kind of anti-floating reinforcement structure and construction method of operating subway tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911184264.6A CN110836121A (en) 2019-11-27 2019-11-27 A kind of anti-floating reinforcement structure and construction method of operating subway tunnel

Publications (1)

Publication Number Publication Date
CN110836121A true CN110836121A (en) 2020-02-25

Family

ID=69577566

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911184264.6A Pending CN110836121A (en) 2019-11-27 2019-11-27 A kind of anti-floating reinforcement structure and construction method of operating subway tunnel

Country Status (1)

Country Link
CN (1) CN110836121A (en)

Cited By (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111428304A (en) * 2020-03-31 2020-07-17 浙江大学城市学院 Displacement deformation prediction method for shield tunnel with anti-floating anchor rod under excavation of foundation pit
CN111878119A (en) * 2020-07-08 2020-11-03 上海地铁维护保障有限公司工务分公司 Subway tunnel ballast bed pipe piece wall post-grouting method
CN113090326A (en) * 2021-04-08 2021-07-09 苏州中车建设工程有限公司 Pressure-reducing drainage anti-floating comprehensive treatment system of shield tunnel and construction method thereof
CN113137273A (en) * 2021-04-08 2021-07-20 苏州中车建设工程有限公司 Large-diameter shield tunnel deformation control structure and construction method thereof
CN113279771A (en) * 2021-06-22 2021-08-20 中建交通建设集团有限公司 Prevent prefabricated assembled structure of shield tunnel section of jurisdiction come-up under water
CN113389555A (en) * 2021-07-30 2021-09-14 中铁十二局集团有限公司 Construction protection method suitable for high-risk pipeline penetrating under underground excavation tunnel
CN113803084A (en) * 2021-08-25 2021-12-17 东南大学 Tunnel segment pretreatment method for ballast bed emptying shield tunnel
CN113982637A (en) * 2021-09-28 2022-01-28 广西大学 Tunnel reinforcing method for controlling deformation of lower horizontal shield tunnel caused by excavation of foundation pit in upward floating manner
CN115467357A (en) * 2022-10-26 2022-12-13 深圳市勘察测绘院(集团)有限公司 Bearing platform pile anchor structure suitable for undulating topography
CN116291552A (en) * 2023-03-24 2023-06-23 佛山轨道交通设计研究院有限公司 A shallow buried tunnel anti-floating structure
CN116517598A (en) * 2023-05-08 2023-08-01 武汉容晟吉美科技有限公司 Lining reinforcement and shield tunnel lining reinforcement method
WO2024234605A1 (en) * 2023-05-17 2024-11-21 中山大学•深圳 Shield tunnel segment float control apparatus and method

Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020083918A (en) * 2001-04-30 2002-11-04 윤영재 Method for Constructing a Lining Panel of a Tunnel, Lining Pannel System for a Tunnel and Omnidirectional Ventilation and Drain System for a Tunnel using the Same
KR20090129001A (en) * 2008-06-12 2009-12-16 삼성중공업 주식회사 Floating bridge structure
CN207161094U (en) * 2017-01-19 2018-03-30 兰州交通大学 A kind of new construction for reinforcing Existing Railway Line tunnel rhegma lining cutting
CN108086994A (en) * 2018-01-08 2018-05-29 兰州理工大学 One kind passes through unfavourable geological tunnel set bridge underground structure and construction method
CN207568618U (en) * 2017-10-16 2018-07-03 广州地铁设计研究院有限公司 tunnel reinforcement structure
CN109241631A (en) * 2018-09-12 2019-01-18 上海隧道工程有限公司 Duct pieces of shield tunnel float-amount calculation method
CN110230504A (en) * 2019-06-25 2019-09-13 深圳市综合交通设计研究院有限公司 A kind of soft lower hard full packet waterproof of compound stratum composite lining structure resistant to pressure and its construction method
CN211598680U (en) * 2019-11-27 2020-09-29 杭州合跃科技有限责任公司 An anti-floating reinforcement structure for an already operating subway tunnel

Patent Citations (8)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
KR20020083918A (en) * 2001-04-30 2002-11-04 윤영재 Method for Constructing a Lining Panel of a Tunnel, Lining Pannel System for a Tunnel and Omnidirectional Ventilation and Drain System for a Tunnel using the Same
KR20090129001A (en) * 2008-06-12 2009-12-16 삼성중공업 주식회사 Floating bridge structure
CN207161094U (en) * 2017-01-19 2018-03-30 兰州交通大学 A kind of new construction for reinforcing Existing Railway Line tunnel rhegma lining cutting
CN207568618U (en) * 2017-10-16 2018-07-03 广州地铁设计研究院有限公司 tunnel reinforcement structure
CN108086994A (en) * 2018-01-08 2018-05-29 兰州理工大学 One kind passes through unfavourable geological tunnel set bridge underground structure and construction method
CN109241631A (en) * 2018-09-12 2019-01-18 上海隧道工程有限公司 Duct pieces of shield tunnel float-amount calculation method
CN110230504A (en) * 2019-06-25 2019-09-13 深圳市综合交通设计研究院有限公司 A kind of soft lower hard full packet waterproof of compound stratum composite lining structure resistant to pressure and its construction method
CN211598680U (en) * 2019-11-27 2020-09-29 杭州合跃科技有限责任公司 An anti-floating reinforcement structure for an already operating subway tunnel

Non-Patent Citations (3)

* Cited by examiner, † Cited by third party
Title
刘学彦等: "基于抗浮稳定的盾构隧道合理覆土厚度研究", 中国工程科学, no. 01, 15 January 2015 (2015-01-15), pages 88 - 95 *
叶飞等: "大断面盾构隧道施工抗浮计算研究", 地下空间与工程学报, no. 05, 15 October 2007 (2007-10-15), pages 849 - 853 *
隆文武;: "运营地铁盾构隧道钢板加固设计与施工", 广东土木与建筑, no. 07, 15 July 2012 (2012-07-15), pages 54 - 56 *

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111428304A (en) * 2020-03-31 2020-07-17 浙江大学城市学院 Displacement deformation prediction method for shield tunnel with anti-floating anchor rod under excavation of foundation pit
CN111878119B (en) * 2020-07-08 2022-03-18 上海地铁维护保障有限公司工务分公司 Subway tunnel ballast bed pipe piece wall post-grouting method
CN111878119A (en) * 2020-07-08 2020-11-03 上海地铁维护保障有限公司工务分公司 Subway tunnel ballast bed pipe piece wall post-grouting method
CN113090326A (en) * 2021-04-08 2021-07-09 苏州中车建设工程有限公司 Pressure-reducing drainage anti-floating comprehensive treatment system of shield tunnel and construction method thereof
CN113137273A (en) * 2021-04-08 2021-07-20 苏州中车建设工程有限公司 Large-diameter shield tunnel deformation control structure and construction method thereof
CN113279771A (en) * 2021-06-22 2021-08-20 中建交通建设集团有限公司 Prevent prefabricated assembled structure of shield tunnel section of jurisdiction come-up under water
CN113389555A (en) * 2021-07-30 2021-09-14 中铁十二局集团有限公司 Construction protection method suitable for high-risk pipeline penetrating under underground excavation tunnel
CN113389555B (en) * 2021-07-30 2023-05-26 中铁十二局集团有限公司 Construction protection method suitable for high-risk pipeline under undercut tunnel
CN113803084A (en) * 2021-08-25 2021-12-17 东南大学 Tunnel segment pretreatment method for ballast bed emptying shield tunnel
CN113803084B (en) * 2021-08-25 2024-02-06 东南大学 A kind of pretreatment method for shield tunnel segments with track bed emptying
CN113982637A (en) * 2021-09-28 2022-01-28 广西大学 Tunnel reinforcing method for controlling deformation of lower horizontal shield tunnel caused by excavation of foundation pit in upward floating manner
CN113982637B (en) * 2021-09-28 2023-06-06 广西大学 A Tunnel Reinforcement Method for Controlling Upward Floating Deformation of Underlying Shield Tunnel Caused by Excavation of Foundation Pit
CN115467357A (en) * 2022-10-26 2022-12-13 深圳市勘察测绘院(集团)有限公司 Bearing platform pile anchor structure suitable for undulating topography
CN115467357B (en) * 2022-10-26 2024-03-12 深圳市勘察测绘院(集团)有限公司 Pile cap pile anchor structure suitable for relief topography
CN116291552A (en) * 2023-03-24 2023-06-23 佛山轨道交通设计研究院有限公司 A shallow buried tunnel anti-floating structure
CN116517598A (en) * 2023-05-08 2023-08-01 武汉容晟吉美科技有限公司 Lining reinforcement and shield tunnel lining reinforcement method
WO2024234605A1 (en) * 2023-05-17 2024-11-21 中山大学•深圳 Shield tunnel segment float control apparatus and method
US12371994B2 (en) 2023-05-17 2025-07-29 Shenzhen Campus of Sun Yat-sen University Control apparatus and method for buoyancy adjustment of shield tunnel segments

Similar Documents

Publication Publication Date Title
CN110836121A (en) A kind of anti-floating reinforcement structure and construction method of operating subway tunnel
CN104818991B (en) A kind of construction method in Shallow-buried residual soil slope tunnel
CN107190635B (en) Dumbbell-shaped concrete-filled steel tubular composite pier and its connection structure and method with bearing platform
CN108547645B (en) Assembled tunnel supporting device and method capable of realizing prestress
CN111254984B (en) A tube joint connection structure of an underwater cable-stayed suspension tunnel
CN106013052A (en) Steel sheet pile and open caisson combined underground garage and construction method thereof
CN109578035B (en) Steel pipe drainage lock foot pile and construction method
CN111764926B (en) Control structure and control method for long-term settlement of shield or pipe-jacking tunnel
CN111778793A (en) A cavity collapse prevention structure and construction method
CN115679981A (en) Vertical supporting structure of combination formula steel pipe under support and landing stage load
CN205225280U (en) A combined supporting structure that is used for steel -pipe pile bar planting tunnel composite lining of soft base
CN211598680U (en) An anti-floating reinforcement structure for an already operating subway tunnel
CN119435012A (en) A method for concealed excavation of a three-layer six-hole subway station
CN110552702B (en) Underground excavation construction method for assembled corrugated steel plate underground comprehensive pipe gallery
CN118911155A (en) Deep foundation pit supporting device and construction method
CN113107019A (en) Pre-buried anchor rod connecting structure passing through pre-built building and construction method thereof
CN106812359A (en) A kind of assembled underground garage and its method of construction
CN206941372U (en) Concrete-filled steel tube with dumbbell sections assembled pier and the attachment structure with cushion cap
CN112323816A (en) Unloading type combined retaining structure and construction method thereof
CN117605481A (en) Micro-deformation control method for ultra-small clear distance of large-section subway tunnel to span existing tunnel
CN110645003A (en) Completely weathered granite bias steep slope tunnel entry construction method
CN114382157B (en) Construction method of concrete gas permeable well
CN117759253A (en) Uplift control structure and implementation method of existing tunnels on the upper span of large-section tunnels with small clear distances
CN206298896U (en) A kind of Tunnel Passing structures steel pipe isolation pile stratum consolidation system
CN212296394U (en) Control structure for long-term settlement of shield or pipe-jacking tunnel

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
AD01 Patent right deemed abandoned

Effective date of abandoning: 20250627

AD01 Patent right deemed abandoned