CN110820803A - Open excavation construction method for transverse connection channel of shield tunnel - Google Patents

Open excavation construction method for transverse connection channel of shield tunnel Download PDF

Info

Publication number
CN110820803A
CN110820803A CN201911097475.6A CN201911097475A CN110820803A CN 110820803 A CN110820803 A CN 110820803A CN 201911097475 A CN201911097475 A CN 201911097475A CN 110820803 A CN110820803 A CN 110820803A
Authority
CN
China
Prior art keywords
tunnel
shield
shield tunnel
line
frame structure
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911097475.6A
Other languages
Chinese (zh)
Other versions
CN110820803B (en
Inventor
刘明高
李建林
陈仁东
庞康
王霞
陈明奎
毕强
吴金刚
陈兵
蔡东明
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Beijing Zhiyuan Engineering Construction Supervision Co ltd
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Original Assignee
Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Beijing General Municipal Engineering Design and Research Institute Co Ltd filed Critical Beijing General Municipal Engineering Design and Research Institute Co Ltd
Priority to CN201911097475.6A priority Critical patent/CN110820803B/en
Publication of CN110820803A publication Critical patent/CN110820803A/en
Application granted granted Critical
Publication of CN110820803B publication Critical patent/CN110820803B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/04Making large underground spaces, e.g. for underground plants, e.g. stations of underground railways; Construction or layout thereof
    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D29/00Independent underground or underwater structures; Retaining walls
    • E02D29/045Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them
    • E02D29/05Underground structures, e.g. tunnels or galleries, built in the open air or by methods involving disturbance of the ground surface all along the location line; Methods of making them at least part of the cross-section being constructed in an open excavation or from the ground surface, e.g. assembled in a trench

Abstract

The invention discloses an open cut construction method of a transverse connection channel of a shield tunnel, comprising the following steps of firstly, constructing a first underground continuous wall and a second underground continuous wall in the range of the transverse connection channel which is planned to be excavated and extending to the surrounding periphery of a left-line shield tunnel and a right-line shield tunnel; secondly, cutting and breaking underground continuous walls II in the left line shield tunnel and the right line shield tunnel by adopting a shield machine, and erecting spliced shield segment structures in the left line shield tunnel and the right line shield tunnel; step three, constructing foundation pit support layer by the foundation pit dug openly from the ground surface; fourthly, removing the shield segments on the left line and the shield segments on the right line; constructing a main tunnel frame structure and a transverse connection channel inner frame structure in the left-line shield tunnel and the right-line shield tunnel; and step six, backfilling earthwork above the main tunnel frame structure and the transverse communication channel frame structure, and dismantling the foundation pit support to recover the existing ground. The invention has small construction risk and low construction cost.

Description

Open excavation construction method for transverse connection channel of shield tunnel
Technical Field
The invention belongs to the technical field of tunnel transverse connection channel construction, and particularly relates to an open cut construction method of a shield tunnel transverse connection channel.
Background
At present, according to the design specifications of the existing highways, municipal and subway tunnels and the requirements of related technical standards, communication channels are required to be arranged between double-hole tunnels, the arrangement type and the spacing are respectively 1, the first civil engineering work of the highway tunnel design specification JTG3370.1-2018, the 4.5.1, the arrangement type and the spacing are defined as ①, the spacing is preferably 250m and is not more than 350m, ②, the arrangement spacing is preferably 750m and is not more than 1000 m.2, the design specifications of urban underground road engineering specification CJJ221-2015, the 8.3.5, the arrangement type and the spacing are defined as ①, the transverse pedestrian evacuation channels or the transverse pedestrian evacuation channels are arranged, the spacing between ②, the spacing between underground roads and the transverse pedestrian evacuation channels is preferably 250 m-300 m, the arrangement type and the spacing between 250 m-8.3.6, the arrangement type and the spacing between ①, the urban underground tunnels of two or three types of motor vehicles are preferably 500-500, the arrangement type and the spacing between 500, the transverse underground vehicle channels are preferably 500, the spacing between 500, the transverse underground vehicle access channels are 500, the arrangement type and the spacing between 500, the transverse evacuation channels are preferably 1000, the arrangement type and the spacing between 800-1000-year-on-year-on-year-on-year-on-year-on-for the underground tunnel design specifications of underground tunnel for the same-on-underground vehicle-on-by-under-for the same-underground tunnel design specifications of underground vehicle-on-by-underground vehicle-underground tunnel design specification, the same tunnel design specification of underground vehicle-for the same tunnel design specification of underground vehicle-underground vehicle.
The existing shield tunnel connection channel construction method comprises a mine method, a pipe jacking method and a shield method, and different methods have different characteristics and applicability. 1) A mine method: the technology of the contact channel constructed by the mine method is relatively mature, the application is extremely wide, and the mine method is mostly adopted for construction particularly in the construction of the contact channel of the urban subway tunnel in China. But the defects are obvious, such as low construction efficiency, poor economy and high safety risk, and meanwhile, the reinforcement effect of the soil around the contact channel has great influence on the success of construction. At present, ground reinforcing methods, in-hole grouting reinforcing methods and freezing methods are used for soil body reinforcing methods, wherein particularly the freezing method has the defects of numerous control influence factors of construction effects, great safety risks, long construction period, high cost, prominent operation and maintenance diseases, and many cases of construction failures caused by the freezing method are adopted in China. 2) Pipe jacking method: the pipe jacking method is used as a modern underground pipeline construction method, and during construction, the pipe is pressed into a soil layer through a force transmission jacking iron and a guide rail and a hydraulic jack supported on a back wall, and soil on the front side of the pipe is dug and carried away. And after the first pipe joint is completely jacked into the soil layer, connecting the second pipe joint behind the first pipe joint and jacking continuously, and jacking the first pipe joint in such a way to make a joint, thereby constructing a channel. The pipe jacking method has small influence on the environment, high mechanization degree and short construction period, but special equipment and a jacking rack need to be equipped during construction, the internal space of the finished structure of the main line shield tunnel is occupied, the influence on construction organization and construction period is large, and the stress and the influence on the structure are not clear in the construction process. At present, the domestic application cases are few. 3) A shield method: the shield method is adopted to directly cut and break the segments of the main line tunnel structure and apply the segments to the contact channel, and has the advantages of strong stratum adaptability, high mechanization degree, long tunneling distance, short construction period and the like. Meanwhile, the shield construction method also needs to be matched with a special small shield machine, a muddy water treatment system and a backup rack, occupies larger internal space of the finished structure of the main line shield tunnel, and has larger influence on construction organization and construction period. On the other hand, the construction of the small shield machine has the engineering risks of starting and receiving, and the construction cost is relatively high.
At present, no case report is found in the construction of a transverse connection channel of a main line shield tunnel section by adopting an open excavation method.
Disclosure of Invention
The invention provides an open excavation construction method for a transverse connection channel of a shield tunnel, and aims to solve the problems that the construction cost of the conventional transverse connection channel of the shield tunnel is high and the engineering risk is relatively high.
The invention adopts the following technical scheme:
an open excavation construction method for a transverse connection channel of a shield tunnel comprises the following construction steps:
step one, constructing a first underground continuous wall in a direction parallel to the tunnel line position and a second underground continuous wall in a direction vertical to the tunnel line position around the left line shield tunnel and the right line shield tunnel in the range of the horizontal communication channel planned to be excavated and extending to the left line shield tunnel and the right line shield tunnel, and enclosing to form a closed annular shaft;
cutting and breaking the second underground continuous wall in the direction perpendicular to the tunnel line position in the left line shield tunnel and the right line shield tunnel by using a shield machine, and erecting assembled shield segment structures in the left line shield tunnel and the right line shield tunnel;
step three, performing foundation pit support on the foundation pit dug by the ground surface downwards in the area surrounded by the first underground continuous wall and the second underground continuous wall layer by layer until the bottom elevation position of the transverse communication channel;
fourthly, dismantling the shield segments on the left line and the shield segments on the right line in the left line shield tunnel and the right line shield tunnel in the surrounding area and above the bottom elevation of the transverse communication channel;
constructing a main tunnel frame structure and a transverse connection channel inner frame structure in the left-line shield tunnel and the right-line shield tunnel;
and sixthly, backfilling earthwork above the main tunnel frame structure and the transverse connection channel frame structure, removing the foundation pit support, recovering the ground in the current situation, and completing construction of the transverse connection channel.
The invention has the following advantages:
the method of the invention is adopted to carry out the construction of the transverse connection channel of the shield tunnel, which not only can meet the requirement of the double-hole tunnel for arranging the transverse connection channel specified by the tunnel design specification, but also can reduce the risk and the construction cost of the connection channel adopting the mining method, the pipe jacking method and the shield method, and provides a good choice for the safe and effective construction of the transverse connection channel of the shield tunnel.
Description of the drawings:
FIG. 1 is a schematic plan view of the present invention.
Fig. 2 is a schematic cross-sectional structure of the present invention.
FIG. 3 is a schematic diagram of the structure of the invention in a vertical section.
Reference numerals:
1 underground diaphragm wall, 1-1 underground diaphragm wall I, 1-2 underground diaphragm wall II, 2 left line shield tunnel, 3 right line shield tunnel, 4 shield segment structure, 4-1 left line lower shield segment, 4-2 left line upper shield segment, 5-1 right line lower shield segment, 5-2 right line upper shield segment, 6 main tunnel frame structure, 7 transverse communication channel, 8 foundation pit support, 8-1 foundation pit support first cross brace, 8-2 foundation pit support Nth cross brace, 9 on-site ground surface support
The specific implementation mode is as follows:
the following further describes the embodiments of the present invention with reference to the drawings.
As shown in fig. 1, 2 and 3, an open excavation construction method for a transverse communication channel of a shield tunnel comprises the following construction steps:
step one, constructing an underground continuous wall 1-1 in a direction parallel to the tunnel line position and an underground continuous wall 2 in a direction vertical to the tunnel line position in the surrounding of the left line shield tunnel 2 and the right line shield tunnel 3 in the range of the horizontal communication channel 7 to be excavated and extending to the left line shield tunnel 2 and the right line shield tunnel 3, and enclosing to form a closed annular shaft, wherein the role of the closed annular shaft is to form a soil retaining and water stopping structure which is beneficial to forming later-stage excavation safety and stability, and the enclosed annular shaft is shown in the attached drawing 1;
secondly, cutting and breaking the underground continuous wall II 1-2 in the direction vertical to the tunnel line position in the left line shield tunnel 2 and the right line shield tunnel 3 by using a shield machine, erecting an assembled shield segment structure 4 in the left line shield tunnel 2 and the right line shield tunnel 3, and resisting the action of soil layer pressure and some special loads, and referring to the attached drawing 1;
step three, constructing foundation pit supports 8 layer by layer in the areas surrounded by the underground continuous walls I1-1 and the underground continuous walls II 1-2 from the ground surface to the bottom elevation position of the transverse communication channel 7, and referring to the attached figure 2;
fourthly, dismantling the shield segments 4-2 on the left line and the shield segments 5-2 on the right line in the shield tunnels 2 and 3 on the left line and the shield segments 5-2 on the right line in the surrounding area, wherein the shield segments are positioned above the bottom elevation of the transverse communication channel 7, and refer to the attached drawing 2;
constructing a main tunnel frame structure 6 in the left shield tunnel 2 and the right shield tunnel 3 and an inner frame structure in the transverse communication channel 7, and referring to the attached drawing 2;
and sixthly, backfilling earthwork above the main tunnel frame structure 6 and the transverse connection channel 7 frame structure, removing the foundation pit support 8, recovering the existing ground 9, and completing construction of the transverse connection channel 7, wherein the construction is shown in the attached drawing 3.
The underground continuous wall is constructed by adopting a conventional method, and the following construction method can be adopted: excavating along the periphery of a foundation pit under the condition of slurry wall protection to form a groove with a certain length, then placing the manufactured reinforcement cage into the groove section, performing underwater concrete pouring by adopting a conduit method to form a unit wall section, and mutually connecting all the wall sections by adopting a specific joint mode (such as a joint made of a joint pipe or a joint box) to form a continuous underground reinforced concrete wall.

Claims (1)

1. An open excavation construction method of a transverse connection channel of a shield tunnel is characterized in that: the method comprises the following construction steps:
step one, constructing an underground continuous wall I (1-1) parallel to the tunnel line position direction and an underground continuous wall II (1-2) vertical to the tunnel line position direction around the left line shield tunnel (2) and the right line shield tunnel (3) in the range of the horizontal communication channel (7) planned to be excavated and extending to the left line shield tunnel and the right line shield tunnel to form a closed annular shaft;
secondly, cutting and breaking the second underground continuous wall (1-2) in the direction vertical to the tunnel line position in the left line shield tunnel (2) and the right line shield tunnel (3) by using a shield machine, and erecting an assembled shield segment structure (4) in the left line shield tunnel (2) and the right line shield tunnel (3);
step three, constructing foundation pit supports (8) layer by layer in the areas surrounded by the underground continuous walls I (1-1) and the underground continuous walls II (1-2) from the ground surface to the bottom elevation position of the transverse communication channel (7);
fourthly, dismantling the shield segments (4-2) on the left line and the shield segments (5-2) on the right line in the shield tunnels (2, 3) on the left line and the shield segments (5-2) on the right line in the surrounding area and above the bottom elevation of the transverse communication channel (7);
constructing a main tunnel frame structure (6) in the left shield tunnel (2) and the right shield tunnel (3) and an inner frame structure in the transverse communication channel (7);
and sixthly, backfilling earthwork above the main tunnel frame structure (6) and the transverse connection channel (7) frame structure, removing the foundation pit support (8), recovering the existing ground (9), and completing construction of the transverse connection channel (7).
CN201911097475.6A 2019-11-11 2019-11-11 Open excavation construction method for transverse connection channel of shield tunnel Active CN110820803B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911097475.6A CN110820803B (en) 2019-11-11 2019-11-11 Open excavation construction method for transverse connection channel of shield tunnel

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911097475.6A CN110820803B (en) 2019-11-11 2019-11-11 Open excavation construction method for transverse connection channel of shield tunnel

Publications (2)

Publication Number Publication Date
CN110820803A true CN110820803A (en) 2020-02-21
CN110820803B CN110820803B (en) 2021-06-22

Family

ID=69554148

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911097475.6A Active CN110820803B (en) 2019-11-11 2019-11-11 Open excavation construction method for transverse connection channel of shield tunnel

Country Status (1)

Country Link
CN (1) CN110820803B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113187491A (en) * 2021-05-17 2021-07-30 中铁十二局集团第四工程有限公司 Subway tunnel transverse passage small shield construction process
CN115162408A (en) * 2022-06-14 2022-10-11 长江勘测规划设计研究有限责任公司 Construction method for repairing collapsed tunnel

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5341025A (en) * 1976-09-24 1978-04-14 Kubota Ltd Underground structure
CN101598027A (en) * 2009-07-10 2009-12-09 广东华隧建设股份有限公司 The tunnel connection channel construction method in a kind of shield structure interval
CN105089670A (en) * 2015-07-26 2015-11-25 北京工业大学 Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JPS5341025A (en) * 1976-09-24 1978-04-14 Kubota Ltd Underground structure
CN101598027A (en) * 2009-07-10 2009-12-09 广东华隧建设股份有限公司 The tunnel connection channel construction method in a kind of shield structure interval
CN105089670A (en) * 2015-07-26 2015-11-25 北京工业大学 Construction method for enlarging and excavating subway station on basis of parallel interval shield tunnel

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
杨慧林: "国内结合盾构法修建地铁车站的技术方案分析", 《铁道标准设计》 *
赵璞琪: "浅埋盾构隧道联络通道明挖施工", 《隧道建设》 *

Cited By (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113187491A (en) * 2021-05-17 2021-07-30 中铁十二局集团第四工程有限公司 Subway tunnel transverse passage small shield construction process
CN115162408A (en) * 2022-06-14 2022-10-11 长江勘测规划设计研究有限责任公司 Construction method for repairing collapsed tunnel
CN115162408B (en) * 2022-06-14 2024-02-02 长江勘测规划设计研究有限责任公司 Construction method for repairing collapse tunnel

Also Published As

Publication number Publication date
CN110820803B (en) 2021-06-22

Similar Documents

Publication Publication Date Title
CN110485470B (en) Rectangular working well with pre-arranged jacking pipe door opening and sliding type rear wall in water-rich stratum and construction method of rectangular working well
CN103061777B (en) Method for building urban underground tunnel shield cutter repairing space with preset reinforcing pile groups
CN106049532B (en) A kind of pipe gallery open-cut branch blocking means and its construction method
CN103485790A (en) Shallow tunneling method for pipe-proof-supporting structure combined system
CN103032075B (en) Construction method for building ground inlet and outlet type shield tunnel
CN203174616U (en) Clay foundation rain falling and water saving system
CN112647956B (en) Construction method for short-distance underpass subway station of water-rich composite stratum shield
CN103114857A (en) Shield tunnel construction method
CN112160755B (en) Subway line construction method for expanding excavation station after shield tunnel construction in advance
CN109578014B (en) Anti-surging bottom sealing structure and construction method
CN102817621B (en) Comprehensive construction method applicable to controlling arch basement sedimentation for tunnel in unfavorable geological conditions
CN110924961A (en) Construction method for starting shield tunneling machine to pass through existing station
CN110820803B (en) Open excavation construction method for transverse connection channel of shield tunnel
CN102182464A (en) Construction structure and construction method of channel structure
CN112502734A (en) Construction method of shield interval contact channel of water-rich sand layer
CN101532386B (en) Method and device for underpinning antifriction separator for shallow underground space construction
CN103485791A (en) Construction method for in-situ maintenance or extension of road tunnel
CN109594574A (en) Large-scale push pipe open caisson reversed construction method based on the confined space
CN105065774B (en) A kind of underground piping branch connects construction method
CN104895100B (en) Building close quarters builds underground space Caisson method
CN113958322B (en) Tunnel excavation method under existing subway line
CN114592892A (en) Implementation method for pulling out anchor cable of shield tunnel in steel sleeve in soft soil area
CN110485465B (en) Circular working well with water-rich stratum with preset pipe jacking door opening and construction method of circular working well
Zhang et al. Construction applicability of mechanical methods for connecting aisle in the bohai mudstone stratum with high water pressure
CN109578004B (en) Combined pipe jacking machine with soil pressure balance and mud water balance and construction method

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant
TR01 Transfer of patent right

Effective date of registration: 20240229

Address after: 100082, building 32, No. 3 North Main Street, Haidian District, Beijing, Xizhimen

Patentee after: BEIJING GENERAL MUNICIPAL ENGINEERING DESIGN & RESEARCH INSTITUTE Co.,Ltd.

Country or region after: China

Patentee after: BEIJING ZHIYUAN ENGINEERING CONSTRUCTION SUPERVISION CO.,LTD.

Address before: 100082, building 32, No. 3 North Main Street, Haidian District, Beijing, Xizhimen

Patentee before: BEIJING GENERAL MUNICIPAL ENGINEERING DESIGN & RESEARCH INSTITUTE Co.,Ltd.

Country or region before: China

TR01 Transfer of patent right