CN110820572A - Integrated assembly construction method of prefabricated piers and main beams based on cable-stayed bridge erectors - Google Patents
Integrated assembly construction method of prefabricated piers and main beams based on cable-stayed bridge erectors Download PDFInfo
- Publication number
- CN110820572A CN110820572A CN201911053352.2A CN201911053352A CN110820572A CN 110820572 A CN110820572 A CN 110820572A CN 201911053352 A CN201911053352 A CN 201911053352A CN 110820572 A CN110820572 A CN 110820572A
- Authority
- CN
- China
- Prior art keywords
- prefabricated
- pulley
- bridge
- main
- cable
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Withdrawn
Links
- 238000010276 construction Methods 0.000 title claims abstract description 70
- 229910000831 Steel Inorganic materials 0.000 claims description 10
- 239000010959 steel Substances 0.000 claims description 10
- 238000009434 installation Methods 0.000 claims description 9
- 230000032258 transport Effects 0.000 claims description 5
- 238000010586 diagram Methods 0.000 description 6
- 238000000034 method Methods 0.000 description 5
- 238000005516 engineering process Methods 0.000 description 2
- 239000000428 dust Substances 0.000 description 1
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E01—CONSTRUCTION OF ROADS, RAILWAYS, OR BRIDGES
- E01D—CONSTRUCTION OF BRIDGES, ELEVATED ROADWAYS OR VIADUCTS; ASSEMBLY OF BRIDGES
- E01D21/00—Methods or apparatus specially adapted for erecting or assembling bridges
Landscapes
- Engineering & Computer Science (AREA)
- Architecture (AREA)
- Civil Engineering (AREA)
- Structural Engineering (AREA)
- Bridges Or Land Bridges (AREA)
Abstract
本发明属于桥梁施工工程领域,具体涉及一种基于斜拉架桥机的预制桥墩和预制主梁一体化装配施工方法,使用斜拉架桥机进行预制桥墩、预制帽梁与预制主梁施工:工厂准备构件、施工现场拼装固定架桥机与施工现场架设桥梁。通过滑车将预制桥墩节段、预制帽梁和预制主梁运输就位,首先完成架桥机前端预制桥墩节段的拼装和预制帽梁的拼装,然后将架桥机前端支承锚固在帽梁顶部,完成预制主梁的运输和架设,最终完成预制主梁和预制桥墩的一体化架设。本发明易于安装、施工简便,且架桥机与的桥梁有可靠的连接,解决了复杂山区环境下预制高墩桥梁建设中预制桥墩节段和预制主梁运输和吊装难的技术问题,能够加快桥梁建设速度,具有显著的经济效益。
The invention belongs to the field of bridge construction engineering, and in particular relates to a construction method for the integrated assembly of prefabricated piers and prefabricated main beams based on a cable-stayed bridge erecting machine. The factory prepares the components, assembles and fixes the bridge erecting machine on the construction site, and erects the bridge on the construction site. The prefabricated pier segment, prefabricated cap beam and prefabricated main girder are transported into place by the pulley, firstly, the assembly of the prefabricated pier segment and the prefabricated cap girder at the front end of the bridge erection machine are completed, and then the front end of the bridge erection machine is supported and anchored on the top of the cap girder , complete the transportation and erection of the prefabricated main girder, and finally complete the integrated erection of the prefabricated main girder and the prefabricated piers. The invention is easy to install, simple to construct, and has reliable connection between the bridge erecting machine and the bridge, solves the technical problem of difficult transportation and hoisting of prefabricated pier segments and prefabricated main beams in the construction of prefabricated high-pier bridges in complex mountainous environment, and can speed up The speed of bridge construction has significant economic benefits.
Description
技术领域technical field
本发明属于桥梁施工工程领域,具体涉及一种基于斜拉架桥机的预制桥墩和预制主梁一体化装配施工方法,还涉及斜拉架桥机。本发明适用于预制桥墩和预制主梁一体化建造施工。The invention belongs to the field of bridge construction engineering, in particular to an integrated assembly construction method of a prefabricated bridge pier and a prefabricated main beam based on a cable-stayed bridge erector, and also relates to a cable-stayed bridge erector. The invention is suitable for the integrated construction of prefabricated piers and prefabricated main beams.
背景技术Background technique
在当今社会快速发展的背景下,交通的制约会造成巨大的经济损失。因此,在城市路网关键节点进行桥梁改造遇到的问题不再是桥梁本身,而是如何减小对交通的影响。桥梁快速建造技术应运而生,较传统的桥梁施工方式具有构件工厂加工质量耐久性好、施工安全风险小、扬尘及噪声污染小、施工速度提高、对交通影响小等众多优势。In the context of the rapid development of today's society, traffic restrictions will cause huge economic losses. Therefore, the problem encountered in bridge reconstruction at key nodes of the urban road network is no longer the bridge itself, but how to reduce the impact on traffic. The rapid bridge construction technology has emerged as the times require. Compared with the traditional bridge construction method, it has many advantages such as good quality and durability of component factory processing, low construction safety risk, low dust and noise pollution, increased construction speed, and small impact on traffic.
目前已有的采用桥梁预制拼装技术拼装桥墩的工程,多为中低墩,拼装节段较少,而且建造地点多为施工场地较开阔的地区,不需要考虑运输、吊装施工机械的限制;而在山区这样的复杂地形条件下,建设的桥梁桥墩较高,而大型运输、吊装能力强的设备又难以进入施工地点。基于以上问题,需要提供一种基于斜拉架桥机的预制桥墩和预制主梁一体化装配施工方法。At present, the existing projects using bridge prefabricated assembly technology to assemble bridge piers are mostly medium and low piers with fewer assembly segments, and most of the construction sites are in open areas of the construction site, so there is no need to consider the limitations of transportation and hoisting construction machinery; Under complex terrain conditions such as mountainous areas, the piers of the bridges to be constructed are relatively high, and it is difficult for large-scale transportation and hoisting equipment to enter the construction site. Based on the above problems, it is necessary to provide a construction method for the integrated assembly of prefabricated piers and prefabricated main beams based on a cable-stayed bridge erector.
发明内容SUMMARY OF THE INVENTION
本发明的目的在于提供一种基于斜拉架桥机的预制桥墩和预制主梁一体化装配施工方法,该装配施工方法能够实现山区复杂环境下预制高墩桥梁的快速装配化建造施工;本发明的另一目的在于提供一种斜拉架桥机。The purpose of the present invention is to provide an integrated assembly construction method of prefabricated piers and prefabricated main beams based on a cable-stayed bridge erector, which can realize the rapid assembly construction of prefabricated high-pier bridges in a complex environment in mountainous areas; the present invention Another object of the invention is to provide a cable-stayed bridge erecting machine.
本发明实现上述目的提供的技术方案如下:一种基于斜拉架桥机的预制桥墩和预制主梁一体化装配施工方法;其特征在于按下述步骤使用斜拉架桥机进行预制桥墩、预制帽梁与预制主梁施工:工厂准备构件、施工现场拼装固定架桥机与施工现场架设桥梁;具体为:The technical solutions provided by the present invention to achieve the above objects are as follows: an integrated assembly and construction method for prefabricated bridge piers and prefabricated main beams based on a cable-stayed bridge erection machine; Construction of hat beam and prefabricated main beam: factory prepares components, assembles and fixes bridge erecting machine on construction site, and erects bridge on construction site; the details are:
步骤1、工厂准备构件;
1.1准备斜拉架桥机构件:主桁架、索塔、斜拉索、高强钢棒、螺栓、A滑车、B滑车、C滑车、D滑车、主提升机构、上工字钢、下工字钢;四台滑车各自配套有主提升机构;1.1 Prepare the components of the cable-stayed bridge structure: main truss, cable tower, stay cable, high-strength steel rod, bolt, A block, B block, C block, D block, main lifting mechanism, upper I-beam, lower I-beam ; Each of the four pulleys is equipped with a main lifting mechanism;
1.2准备桥梁构件:预制桥墩节段、预制帽梁与预制主梁。1.2 Prepare bridge components: prefabricated pier segments, prefabricated cap beams and prefabricated main beams.
步骤2、施工现场拼装固定架桥机;
沿已建好的桥梁节段横向在桥梁纵向的前、后两端分别搭设下工字钢,在下工字钢上面拼装主桁架、并将后锚点和索塔支点通过高强钢棒与螺栓固定在已建好的桥梁节段上;而后在主桁架上面安装四组上工字钢,各组上工字钢均与主桁架滑动连接、可沿主桁架纵向移动,在主桁架上面安装索塔,用斜拉索将索塔与主桁架固定连接;各自配套有主提升机构的A滑车、B滑车、C滑车与D滑车从前端起依次安装于四组上工字钢上面,并且,A滑车、B滑车位于索塔前方,C滑车、D滑车位于索塔后方;四个滑车即可以纵向滑动、也可以在上工字钢上横向滑动。施工第一跨时,可斜拉架桥机安装固定在路基上进行施工,不再赘述。The lower I-beams are erected at the front and rear ends of the longitudinal direction of the bridge along the horizontal direction of the built bridge segment, the main truss is assembled on the lower I-beam, and the rear anchor point and the fulcrum of the cable tower are fixed by high-strength steel rods and bolts On the bridge segment that has been built; then four groups of upper I-beams are installed on the main truss, and each group of upper I-beams is slidably connected to the main truss and can move longitudinally along the main truss, and the cable tower is installed on the main truss. , the cable tower is fixedly connected with the main truss by the stay cable; the A pulley, B pulley, C pulley and D pulley, which are respectively equipped with the main lifting mechanism, are installed on the four sets of upper I-beams in sequence from the front end, and the A pulley , B pulley is located in front of the cable tower, C pulley and D pulley are located behind the cable tower; the four pulleys can slide longitudinally or laterally on the upper I-beam. When constructing the first span, the cable-stayed bridge erection machine can be installed and fixed on the roadbed for construction, which is not repeated here.
步骤3、施工现场架设桥梁;
3.1预制桥墩节段拼装:采用运梁车将预制桥墩节段运送至梁前端,B滑车通过主桁架移动至梁前端,下放主提升机构吊起预制桥墩节段后,向前移动至桥墩位置,下放预制桥墩节段进行拼装施工,重复此步骤完成桥墩其它节段施工。3.1 Assembly of prefabricated pier segments: the beam transporter is used to transport the prefabricated pier segments to the front end of the beam, the B pulley is moved to the front end of the beam through the main truss, and the main lifting mechanism is lowered to lift the prefabricated pier segment, and then move forward to the pier position, Lower the prefabricated pier segments for assembly construction, and repeat this step to complete the construction of other segments of the pier.
3.2预制帽梁安装施工:待桥墩节段完成施工后再吊装预制帽梁,预制帽梁与步骤3.1预制桥墩节段拼装的施工方法相同;重复以上步骤直至完成桥梁所有下部结构的施工后,放下前支点支承锚固在预制帽梁上,为预制主梁施工做准备。3.2 Installation and construction of prefabricated cap beams: The prefabricated cap beams are hoisted after the construction of the pier segments is completed. The prefabricated cap beams are assembled in the same way as in step 3.1; the above steps are repeated until the construction of all the substructures of the bridge is completed, and then the prefabricated cap beams are put down. The front fulcrum support is anchored on the prefabricated cap beam to prepare for the construction of the prefabricated main beam.
3.3主梁安装施工:运梁车将预制主梁运送至吊装位置,首先通过C滑车与D滑车将预制主梁吊起,缓慢向前移动,待预制主梁前端送至索塔另一侧后,B滑车起吊,C滑车暂时退出工作,空转至D滑车附近重新起吊,D滑车退出工作;此时预制主梁由B滑车与C滑车共同吊起继续前移,C滑车移动至索塔时,A滑车接替B滑车,B滑车空转至索塔处接替C滑车,C滑车退出工作,由A滑车与B滑车吊装预制主梁至设计位置后落梁;保证吊装位置准确。3.3 Main beam installation and construction: The beam transporter transports the prefabricated main beam to the hoisting position. First, the prefabricated main beam is hoisted by the C pulley and the D pulley, and moves forward slowly until the front end of the prefabricated main beam is sent to the other side of the cable tower. , B pulley lifts, C pulley temporarily quits work, idling to the vicinity of D pulley to lift again, D pulley pulls out of work; at this time, the prefabricated main beam is jointly lifted by B pulley and C pulley and continues to move forward, when C pulley moves to the cable tower, The A pulley takes over the B pulley, the B pulley idles to the cable tower to take over the C pulley, the C pulley quits work, and the A pulley and the B pulley hoist the prefabricated main beam to the design position and then drop the beam; ensure the hoisting position is accurate.
完成本跨的预制主梁和预制桥墩的一体化施工后,将架桥机向前移动至下一跨并重复步骤3,逐跨完成整座全预制装配桥梁的建造施工。After completing the integrated construction of the prefabricated main girder and prefabricated piers of this span, move the bridge erection machine forward to the next span and repeat
一种斜拉架桥机,包括主桁架、索塔、斜拉索和配套有主提升机构的滑车,其特征在于:还包括下工字钢与上工字钢;滑车为四套;在路基或已建好的桥梁节段纵向的前、后两端,沿桥梁横向设有下工字钢,下工字钢上面安装主桁架,主桁架上面分散安装四组上工字钢,上工字钢与主桁架滑动连接、可沿主桁架纵向移动,主桁架上面、第二组与第三组上工字钢之间安装索塔,斜拉索将索塔与主桁架固定连接;后锚点和索塔支点通过高强钢棒与螺栓固定在已建好的桥梁节段上,索塔前后的四组上工字钢上面分别安装滑车。A cable-stayed bridge erecting machine, comprising a main truss, a cable tower, a cable-stayed cable and a pulley equipped with a main lifting mechanism, is characterized in that: it also includes a lower I-beam and an upper I-beam; the pulley is four sets; Or at the longitudinal front and rear ends of the built bridge segment, there are lower I-beams along the transverse direction of the bridge, the main trusses are installed on the lower I-beams, and four groups of upper I-beams and upper I-beams are installed scattered on the main trusses. The steel is slidingly connected with the main truss and can move longitudinally along the main truss. A cable tower is installed on the main truss and between the upper I-beams of the second group and the third group, and the cable tower is fixedly connected with the main truss by stay cables; And the fulcrum of the cable tower is fixed on the built bridge segment by high-strength steel rods and bolts, and the pulleys are respectively installed on the four sets of upper I-beams before and after the cable tower.
本文前端是指架设桥梁的前进方向。The front end of this article refers to the forward direction of building the bridge.
本发明通过滑车将预制桥墩节段、预制帽梁和预制主梁运输就位,首先完成架桥机前端预制桥墩节段的拼装和预制帽梁的拼装,然后将架桥机前端支承锚固在帽梁顶部,完成预制主梁的运输和架设,最终完成预制主梁和预制桥墩的一体化架设。The present invention transports the prefabricated bridge pier segments, the prefabricated cap beams and the prefabricated main beams in place by means of a pulley, firstly completes the assembly of the prefabricated bridge pier segments and the prefabricated cap beams at the front end of the bridge erecting machine, and then anchors the front end support of the bridge erecting machine to the cap. On the top of the beam, complete the transportation and erection of the prefabricated main beam, and finally complete the integrated erection of the prefabricated main beam and the prefabricated pier.
现有技术使用架桥机仅是完成预制主梁的施工,本发明实现了预制桥墩、预制帽梁与预制主梁都使用斜拉架桥机进行施工。本发明易于安装、施工简便,且架桥机与的桥梁有可靠的连接,解决了复杂山区环境下高墩桥梁建设中预制桥墩节段和预制主梁运输和吊装难的技术问题,能够加快桥梁建设速度,具有显著的经济效益。In the prior art, the bridge erection machine is only used to complete the construction of the prefabricated main beam, and the present invention realizes that the prefabricated bridge pier, the prefabricated cap beam and the prefabricated main beam are all constructed by the cable-stayed bridge erection machine. The invention is easy to install, simple to construct, and the bridge erection machine is reliably connected to the bridge, which solves the technical problem of difficult transportation and hoisting of prefabricated pier segments and prefabricated main beams in the construction of high-pier bridges in complex mountainous environments, and can speed up the bridge construction process. The construction speed has significant economic benefits.
附图说明Description of drawings
图1为本发明的轴侧图;Fig. 1 is the isometric view of the present invention;
图2为本发明的立面示意图;2 is a schematic elevational view of the present invention;
图3为图1的侧面图;Fig. 3 is the side view of Fig. 1;
图4为预制桥墩起吊图;Figure 4 is the lifting diagram of the prefabricated pier;
图5为预制桥墩就位拼装图;Fig. 5 is the assembly drawing of the prefabricated pier in place;
图6为D滑车、C滑车起吊预制梁图;Fig. 6 is the drawing of D block and C block lifting the prefabricated beam;
图7为D滑车、B滑车起吊预制梁图;Fig. 7 is the drawing of lifting the prefabricated beam by the D pulley and the B pulley;
图8为C滑车、B滑车起吊预制梁图;Figure 8 is a diagram of a prefabricated beam lifted by a C block and a B block;
图9为预制梁前移图;Fig. 9 is the forward movement diagram of the prefabricated beam;
图10为C滑车、A滑车起吊预制梁图;Figure 10 is a drawing of the prefabricated beams lifted by the C block and the A block;
图11为B滑车、A滑车起吊预制梁图;Figure 11 is a diagram showing the lifting of the prefabricated beam by the B pulley and the A pulley;
图12为预制梁前移就位图;Figure 12 is a diagram of the prefabricated beam moving forward;
图13为预制梁安装图。Figure 13 is the installation diagram of the prefabricated beam.
图中:1—预制桥墩,2—预制帽梁,3—预制主梁,4—高强钢棒,5—螺栓,6—架桥机主桁架,7—索塔,8—斜拉索,9—A滑车,10—B滑车,11—C滑车 12—D滑车,13—后锚点,14—索塔支点,15—前支点,16—上工字钢,17—下工字钢,18—主提升钩 ,19—预制桥墩节段,20—已建好的桥梁节段。In the picture: 1—prefabricated pier, 2—prefabricated cap beam, 3—prefabricated main girder, 4—high-strength steel rod, 5—bolt, 6—main truss of bridge erecting machine, 7—cable tower, 8—stayed cable, 9 -A block, 10—B block, 11—C block, 12—D block, 13—rear anchor point, 14—tower fulcrum, 15—front fulcrum, 16—upper I-beam, 17—lower I-beam, 18 - main lifting hook, 19 - prefabricated pier segment, 20 - completed bridge segment.
具体实施方式Detailed ways
方法实施例;基于斜拉架桥机的预制桥墩和预制主梁一体化装配施工方法;本实施例以40m简支预制T梁(即预制主梁)施工过程为实例,预制桥墩节段高2.0m,T梁梁高2.5m。按下述步骤进行:Method embodiment; an integrated assembly construction method for prefabricated piers and prefabricated main beams based on a cable-stayed bridge erecting machine; this embodiment takes the construction process of a 40m simply supported prefabricated T beam (ie, a prefabricated main beam) as an example, and the segmental height of the prefabricated piers is 2.0 m, T beam beam height 2.5m. Proceed as follows:
步骤1、工厂准备构件;
1.1准备斜拉架桥机构件:主桁架6、索塔7、斜拉索8、高强钢棒4、螺栓5、A滑车9、B滑车10、C滑车11、D滑车12、主提升机构18、上工字钢16、下工字钢17;四台滑车各自配套有主提升机构,四台滑车型号相同;1.1 Prepare the components of the cable-stayed bridge structure:
1.2准备桥梁构件:预制桥墩节段19、预制帽梁2与预制T梁3,以及其它安装工具。1.2 Prepare bridge components: prefabricated
步骤2、施工现场拼装固定架桥机;
参见图1至图4;沿已建好的桥梁节段20横向在桥梁纵向的前、后两端分别搭设下工字钢17,在下工字钢上面拼装主桁架6、并将后锚点13和索塔支点14通过高强钢棒4与螺栓5固定在已建好的预制T梁3上;高强钢棒4与螺栓5使架桥机与已建好的预制T梁3实现可靠连接;而后在主桁架6上面安装四组上工字钢16,各组上工字钢16均与主桁架6滑动连接、可沿主桁架6纵向移动,在主桁架6上面、第二组与第三组上工字钢16之间安装索塔7,索塔7距梁前端5m,用斜拉索8将索塔7与主桁架6固定连接;将各自配套有主提升机构18的A滑车9、B滑车10、C滑车11与D滑车12从梁前端起依次安装于四组上工字钢上面,A滑车、B滑车位于索塔前方,C滑车、D滑车位于索塔后方;安装了滑车的上工字钢16沿主桁架6纵向滑动,这样四个滑车即可以随着上工字钢16沿主桁架6纵向滑动、也可以在上工字钢16上横向滑动;下工字钢17略大于桥宽,保证横向有足够的施工空间。Referring to Figures 1 to 4; along the built
步骤3、施工现场架设桥梁;
3.1预制桥墩节段拼装:参见图4与图5;首先采用运梁车将预制桥墩节段19运送至梁前端,B滑车10通过主桁架6移动至梁前端,下放主提升机构18吊起预制桥墩节段19后,向前移动至桥墩1设计位置,下放预制桥墩节段19进行拼装施工,重复此步骤完成其它预制桥墩节段施工。3.1 Assembly of prefabricated pier segments: refer to Figures 4 and 5; first, the
3.2预制帽梁安装施工:待预制桥墩节段完成施工后再吊装预制帽梁2,预制帽梁2与步骤3.1预制桥墩节段拼装的施工方法相同;重复以上步骤直至完成桥梁所有下部结构的施工后,放下前支点15,支承锚固在预制帽梁2上,为主梁施工做准备;此时斜拉架桥机受力体系发生改变,由原来的拉索为主要受力杆件转化为主桁架为主要受力杆件。后锚点13、索塔支点14与前支点15将架桥机支承在预制主梁3上。3.2 Prefabricated cap girder installation and construction: After the prefabricated pier segment is completed, the
3.3主梁安装施工:因为索塔7固定在主桁架6上,滑车不能实现在整个主桁架6范围内纵向自由移动。主梁安装施工的程序为:运梁车将预制主梁3运送至吊装位置,参见图6、图7与图8;首先通过C滑车11与D滑车12将预制主梁3吊起,缓慢向前移动,待预制主梁3前端送至索塔另一侧后,B滑车10起吊,C滑车11暂时退出工作,C滑车11空转至D滑车12附近重新起吊,D滑车12退出工作;参见图9、图10与图11;此时预制主梁3由B滑车10与C滑车11共同吊起继续前移,C滑车11移动至靠近索塔7时,A滑车9接替B滑车10,B滑车10暂时退出工作,B滑车空转至靠近索塔7位置处接替C滑车11,C滑车11退出工作,参见图12与图13;由A滑车9与B滑车10吊装预制主梁3至设计位置后落梁就位安装;即四台滑车交替工作完成预制主梁的施工。3.3 Installation and construction of the main beam: Because the
完成该跨的预制主梁3和预制桥墩1的一体化施工后,将架桥机向前移动至下一跨并重复步骤3,后续施工预制主梁3吊装时可通过下工字钢17进行横向移动,逐跨完成整座全预制装配桥梁的建造施工。After completing the integrated construction of the prefabricated
架桥机实施例;如图1、图2与图3所示:本发明提供的一种斜拉架桥机,包括主桁架6、索塔7、斜拉索8和配套有主提升机构的滑车,还包括下工字钢17与上工字钢16;滑车为四套;在已建好的桥梁节段20纵向的前、后两端,沿桥梁横向设有下工字钢17,下工字钢上面安装主桁架6, 主桁架6上面分散安装四组上工字钢16,上工字钢16与主桁架7滑动连接、可沿主桁架6纵向移动,主桁架6上面、第二组与第三组上工字钢16之间安装索塔7,斜拉索8将索塔7与主桁架6固定连接;后锚点13和索塔支点14通过高强钢棒4与螺栓5固定在已建好的桥梁节段20上,索塔7前后的四组上工字钢16上面分别安装滑车,各个滑车与其相应的上工字钢16横向滑动连接。第一组上工字钢上面安装A滑车9,第二组上工字钢上面安装B滑车10, 第三组上工字钢上面安装C滑车11,第四组上工字钢上面安装D滑车12。Example of bridge erecting machine; as shown in Figure 1, Figure 2 and Figure 3: a cable-stayed bridge erecting machine provided by the present invention includes a
主桁架6下面设有后锚点13、索塔支点14与前支点15,架桥机通过后锚点13与索塔支点14支承在已建好的桥梁节段20上、且通过前支点15支承在前端的预制帽梁2上。The
Claims (4)
Priority Applications (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911053352.2A CN110820572A (en) | 2019-10-31 | 2019-10-31 | Integrated assembly construction method of prefabricated piers and main beams based on cable-stayed bridge erectors |
Applications Claiming Priority (1)
Application Number | Priority Date | Filing Date | Title |
---|---|---|---|
CN201911053352.2A CN110820572A (en) | 2019-10-31 | 2019-10-31 | Integrated assembly construction method of prefabricated piers and main beams based on cable-stayed bridge erectors |
Publications (1)
Publication Number | Publication Date |
---|---|
CN110820572A true CN110820572A (en) | 2020-02-21 |
Family
ID=69551780
Family Applications (1)
Application Number | Title | Priority Date | Filing Date |
---|---|---|---|
CN201911053352.2A Withdrawn CN110820572A (en) | 2019-10-31 | 2019-10-31 | Integrated assembly construction method of prefabricated piers and main beams based on cable-stayed bridge erectors |
Country Status (1)
Country | Link |
---|---|
CN (1) | CN110820572A (en) |
Cited By (5)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111472277A (en) * | 2020-03-31 | 2020-07-31 | 石家庄铁道大学 | Assembled pier transporting and erecting integrated machine and assembled pier transporting and erecting method based on same |
CN111472274A (en) * | 2020-03-18 | 2020-07-31 | 王文洋 | Device for adjusting folding line shape of segmental prefabricated assembled bridge |
CN112853998A (en) * | 2021-02-08 | 2021-05-28 | 中交第二航务工程局有限公司 | Integrated assembling bridge girder erection machine suitable for medium and small spans and construction method thereof |
CN114592433A (en) * | 2022-03-07 | 2022-06-07 | 中铁广州工程局集团有限公司 | Segmental beam dragging and sliding device and method for passing pier and storing beam |
CN115478486A (en) * | 2022-11-03 | 2022-12-16 | 四川交通职业技术学院 | Erecting method of pier-beam integrated construction bridge girder erection machine |
Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3733627A1 (en) * | 1987-10-05 | 1989-04-13 | Baresel Ag C | Method and apparatus for the sectional construction of prestressed-concrete bridges independently of terrain |
JPH0941327A (en) * | 1995-08-01 | 1997-02-10 | Ohbayashi Corp | Erection method of pc bridge and erection girder employed therefor |
JP2007262796A (en) * | 2006-03-29 | 2007-10-11 | Oriental Construction Co Ltd | Diagonal member erection structure of diagonal suspension frame and its diagonal member erection method |
CN204753395U (en) * | 2015-06-17 | 2015-11-11 | 中铁十五局集团第六工程有限公司 | Supporting device for rear supporting leg of bridge girder erection machine |
CN106320181A (en) * | 2016-09-14 | 2017-01-11 | 中交第航务工程局有限公司 | Construction method for installing precast beam slabs by adopting bridge girder erection machine |
CN108677742A (en) * | 2018-08-02 | 2018-10-19 | 中铁工程机械研究设计院有限公司 | The moving cantilever type Bridge Erector of full precast pier, cushion cap and beam body prefabricated construction |
CN208328717U (en) * | 2018-06-15 | 2019-01-04 | 河南省黄河防爆起重机有限公司 | A kind of U-shaped beam bridge formation machine |
CN109208478A (en) * | 2017-06-30 | 2019-01-15 | 中交第二航务工程局有限公司 | A kind of prefabricated assembled bridge integration rapid constructing method |
CN109252452A (en) * | 2018-11-23 | 2019-01-22 | 腾达建设集团股份有限公司 | A kind of Bridge Erector |
CN110093863A (en) * | 2019-05-31 | 2019-08-06 | 浙江省交通规划设计研究院有限公司 | A kind of double face integration Bridge Erector being not provided with front leg strut |
CN110344334A (en) * | 2019-07-31 | 2019-10-18 | 河南省交通规划设计研究院股份有限公司 | Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector |
-
2019
- 2019-10-31 CN CN201911053352.2A patent/CN110820572A/en not_active Withdrawn
Patent Citations (11)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
DE3733627A1 (en) * | 1987-10-05 | 1989-04-13 | Baresel Ag C | Method and apparatus for the sectional construction of prestressed-concrete bridges independently of terrain |
JPH0941327A (en) * | 1995-08-01 | 1997-02-10 | Ohbayashi Corp | Erection method of pc bridge and erection girder employed therefor |
JP2007262796A (en) * | 2006-03-29 | 2007-10-11 | Oriental Construction Co Ltd | Diagonal member erection structure of diagonal suspension frame and its diagonal member erection method |
CN204753395U (en) * | 2015-06-17 | 2015-11-11 | 中铁十五局集团第六工程有限公司 | Supporting device for rear supporting leg of bridge girder erection machine |
CN106320181A (en) * | 2016-09-14 | 2017-01-11 | 中交第航务工程局有限公司 | Construction method for installing precast beam slabs by adopting bridge girder erection machine |
CN109208478A (en) * | 2017-06-30 | 2019-01-15 | 中交第二航务工程局有限公司 | A kind of prefabricated assembled bridge integration rapid constructing method |
CN208328717U (en) * | 2018-06-15 | 2019-01-04 | 河南省黄河防爆起重机有限公司 | A kind of U-shaped beam bridge formation machine |
CN108677742A (en) * | 2018-08-02 | 2018-10-19 | 中铁工程机械研究设计院有限公司 | The moving cantilever type Bridge Erector of full precast pier, cushion cap and beam body prefabricated construction |
CN109252452A (en) * | 2018-11-23 | 2019-01-22 | 腾达建设集团股份有限公司 | A kind of Bridge Erector |
CN110093863A (en) * | 2019-05-31 | 2019-08-06 | 浙江省交通规划设计研究院有限公司 | A kind of double face integration Bridge Erector being not provided with front leg strut |
CN110344334A (en) * | 2019-07-31 | 2019-10-18 | 河南省交通规划设计研究院股份有限公司 | Steel reinforced concrete combined bridge construction method is done using two bridgings of dorsal funciculus formula Bridge Erector |
Cited By (6)
Publication number | Priority date | Publication date | Assignee | Title |
---|---|---|---|---|
CN111472274A (en) * | 2020-03-18 | 2020-07-31 | 王文洋 | Device for adjusting folding line shape of segmental prefabricated assembled bridge |
CN111472277A (en) * | 2020-03-31 | 2020-07-31 | 石家庄铁道大学 | Assembled pier transporting and erecting integrated machine and assembled pier transporting and erecting method based on same |
CN112853998A (en) * | 2021-02-08 | 2021-05-28 | 中交第二航务工程局有限公司 | Integrated assembling bridge girder erection machine suitable for medium and small spans and construction method thereof |
CN114592433A (en) * | 2022-03-07 | 2022-06-07 | 中铁广州工程局集团有限公司 | Segmental beam dragging and sliding device and method for passing pier and storing beam |
CN114592433B (en) * | 2022-03-07 | 2024-03-08 | 中铁广州工程局集团有限公司 | Segmental beam dragging and sliding device and pier-passing beam storage method |
CN115478486A (en) * | 2022-11-03 | 2022-12-16 | 四川交通职业技术学院 | Erecting method of pier-beam integrated construction bridge girder erection machine |
Similar Documents
Publication | Publication Date | Title |
---|---|---|
CN110820572A (en) | Integrated assembly construction method of prefabricated piers and main beams based on cable-stayed bridge erectors | |
CN102121234B (en) | Quick construction method of two-tower five-span steel truss girder cable-stayed bridge | |
CN102352604B (en) | Truss sheet unit of steel truss girder, steel truss girder structure and mounting method thereof | |
CN105648924B (en) | The construction method of multispan freely-supported steel truss girder bridge | |
CN103243658B (en) | The spelling method of cable stayed bridge dragging suspension basket | |
CN109778718A (en) | Construction method for long-span continuous steel box girder main span pure cantilever assembly mid-span closure | |
CN107338963A (en) | A kind of super-span truss string structure construction method for hanging outside the venue | |
CN101139821A (en) | Method and system for erecting steel trusses by stay cable auxiliary complete cantilever | |
CN104762882B (en) | Bridge subsection hanging apparatus and hanging method | |
CN201106155Y (en) | Inclined guy cable auxiliary full cantaliver crane trussed steel beam device | |
CN109098099A (en) | Continuous truss flexible arch bridge rapid constructing method | |
CN114263114A (en) | Construction system and construction method of large-section steel box girder | |
CN105484168B (en) | Rotary hoisting equipment for stiffening beam of suspension bridge and erecting method of stiffening beam | |
CN110172922B (en) | Construction method of environment-friendly downlink self-propelled steel trestle structure | |
CN114032791A (en) | A construction method for integral jacking of large-span steel truss bridges | |
CN113944114A (en) | Dismantling construction method for large-span prestressed concrete cable-stayed bridge | |
Yu et al. | Design and construction of the Tahya Misr cable-stayed bridge in Cairo, Egypt | |
CN102587280B (en) | Main tower area steel truss girder erection method of base support auxiliary frame beam crane and base support | |
Gongyi et al. | The innovations of Yangsigang Yangtze river bridge | |
CN209338005U (en) | A kind of mobile height leg gantry crane of erecting beam construction | |
CN105507160A (en) | Method of operation platform for movable-type bailey beams for construction of cast-in-place box beams | |
CN111945572B (en) | Multi-connected arch bridge erecting machine and multi-connected arch bridge erecting method | |
CN209873587U (en) | A four-point support jacking system for simply supported steel truss beams | |
CN115961549A (en) | Rear-feeding beam type erection construction method for large-tonnage whole-section steel beam of cable-stayed bridge | |
CN113944115A (en) | Full-automatic integrated bridge dismantling machine for dismantling concrete main beam of large-span cable-stayed bridge |
Legal Events
Date | Code | Title | Description |
---|---|---|---|
PB01 | Publication | ||
PB01 | Publication | ||
SE01 | Entry into force of request for substantive examination | ||
SE01 | Entry into force of request for substantive examination | ||
WW01 | Invention patent application withdrawn after publication |
Application publication date: 20200221 |
|
WW01 | Invention patent application withdrawn after publication |