CN110782326A - One-key bid adjustment method and terminal based on engineering bid - Google Patents

One-key bid adjustment method and terminal based on engineering bid Download PDF

Info

Publication number
CN110782326A
CN110782326A CN201911076657.5A CN201911076657A CN110782326A CN 110782326 A CN110782326 A CN 110782326A CN 201911076657 A CN201911076657 A CN 201911076657A CN 110782326 A CN110782326 A CN 110782326A
Authority
CN
China
Prior art keywords
price
adjustable
cost
lowest
adjustment
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911076657.5A
Other languages
Chinese (zh)
Inventor
曾开发
张钟元
梁燕玲
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Fujian Chenxi Information Technology Co Ltd
Original Assignee
Fujian Chenxi Information Technology Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Fujian Chenxi Information Technology Co Ltd filed Critical Fujian Chenxi Information Technology Co Ltd
Priority to CN201911076657.5A priority Critical patent/CN110782326A/en
Publication of CN110782326A publication Critical patent/CN110782326A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/06Buying, selling or leasing transactions
    • G06Q30/08Auctions
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q30/00Commerce
    • G06Q30/02Marketing; Price estimation or determination; Fundraising
    • G06Q30/0283Price estimation or determination
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/08Construction

Abstract

The invention discloses a one-key bid adjustment method and a one-key bid adjustment terminal based on engineering bidding, which are used for acquiring target construction cost, adjustment parameters, adjustable items and the lowest downward floating rate of unit price of materials, calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching reasonable lowest values, wherein the adjustable items comprise a plurality of adjustable elements; fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value; randomly obtaining adjustable elements to carry out random price adjustment until the real-time manufacturing cost is equal to the target manufacturing cost; the invention can conveniently and quickly adjust the price of the project to achieve the project bid price required by the user and ensure the rationality and difference of the adjusted scheme.

Description

One-key bid adjustment method and terminal based on engineering bid
Technical Field
The invention relates to the technical field of engineering bidding, in particular to a one-key bid adjustment method and a one-key bid adjustment terminal based on engineering bidding.
Background
The construction project bid means a transaction form which exchanges building products as commodities, and the transaction form is designed by a unique seller, asks a plurality of buyers to compete through secret quotations, and the seller selects a winner from the buyers and makes a transaction agreement with the winner, and then realizes bid according to the agreement.
In the process of bidding for the construction project, the bidding unit should prepare the bidding document according to the specification of the bidding document. Along with the increase of the bidding units and the general bidding requirements based on the bidding documents, the engineering quotation of the bidding units needs to meet the bidding price requirements on the whole and the prices of the bidding units on all items tend to be reasonable, and the conventional manual adjustment mode has low efficiency and is easy to make mistakes.
Disclosure of Invention
The technical problem to be solved by the invention is as follows: a one-key bid adjustment method and a one-key bid adjustment terminal based on project bidding are provided, so that price adjustment can be conveniently and quickly carried out on projects.
In order to solve the technical problems, the invention adopts the technical scheme that:
the one-key bid adjustment method based on engineering bidding comprises the following steps:
s1, obtaining a target construction cost, an adjusting parameter, an adjustable item and a lowest floating rate of unit price of materials, and calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching a reasonable lowest value, wherein the adjustable item comprises a plurality of adjustable elements;
s2, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value;
and S3, randomly acquiring adjustable elements to perform random price adjustment until the real-time manufacturing cost is equal to the target manufacturing cost.
In order to solve the technical problem, the invention adopts another technical scheme as follows:
the one-key bid-tuning terminal based on engineering bid comprises a memory, a processor and a computer program stored on the memory and capable of running on the processor, wherein the processor executes the computer program to realize the following steps:
s1, obtaining a target construction cost, an adjusting parameter, an adjustable item and a lowest floating rate of unit price of materials, and calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching a reasonable lowest value, wherein the adjustable item comprises a plurality of adjustable elements;
s2, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value;
and S3, randomly acquiring adjustable elements to perform random price adjustment until the real-time manufacturing cost is equal to the target manufacturing cost.
The invention has the beneficial effects that: the one-key bid adjustment method and the terminal based on engineering bidding acquire the target cost, adjustment parameters, adjustable items and the lowest float rate of unit price of materials set by a user, calculate to obtain the lowest cost and the lowest price of all adjustable elements reaching reasonable lowest values, perform fitting indentation according to the current price in the adjustment parameters and the lowest price, then randomly acquire the adjustable elements and perform random price adjustment to ensure that the adjusted cost is basically consistent with the target cost of the user, namely, the invention can conveniently and quickly adjust the price of the engineering to achieve the engineering bidding quotation required by the user and simultaneously ensure the reasonability and difference of the adjusted scheme.
Drawings
FIG. 1 is a flow chart of a one-click bidding method based on engineering bidding according to an embodiment of the present invention;
FIG. 2 is a schematic diagram of a conversion interface between a measure price and a control price according to an embodiment of the present invention;
FIG. 3 is a schematic diagram of cost locking for non-adjustable items according to an embodiment of the present invention;
FIG. 4 is a schematic diagram of a setup interface for project pricing according to an embodiment of the present invention;
fig. 5 is a schematic structural diagram of a one-touch bid adjustment terminal based on engineering bid according to an embodiment of the present invention.
Description of reference numerals:
1. one-key bid adjusting terminal based on project bidding; 2. a processor; 3. a memory.
Detailed Description
In order to explain technical contents, achieved objects, and effects of the present invention in detail, the following description is made with reference to the accompanying drawings in combination with the embodiments.
Referring to fig. 1 to 4, a one-touch bid adjustment method based on project bidding includes the steps of:
s1, obtaining a target construction cost, an adjusting parameter, an adjustable item and a lowest floating rate of unit price of materials, and calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching a reasonable lowest value, wherein the adjustable item comprises a plurality of adjustable elements;
s2, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value;
and S3, randomly acquiring adjustable elements to perform random price adjustment until the real-time manufacturing cost is equal to the target manufacturing cost.
From the above description, the beneficial effects of the present invention are: the method comprises the steps of obtaining target construction cost, adjustment parameters, adjustable items and the lowest downward floating rate of unit price of materials set by a user, calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching reasonable lowest values, fitting and retracting according to the current price and the lowest price in the adjustment parameters, then randomly obtaining the adjustable elements, and performing random price adjustment to enable the adjusted construction cost to be basically consistent with the target construction cost of the user.
Further, the step S1 is specifically:
acquiring target manufacturing cost, adjustment parameters, adjustable items and lowest downward floating rate of unit price of materials, and if the adjustable items comprise enterprise management fees and profits, preferentially adjusting the rates of the enterprise management fees and the profits until a reasonable minimum value is reached;
acquiring other adjustable elements except the enterprise management fee and the profit in the adjustable items, arranging the adjustable elements in a price descending manner, and descending the adjustable elements according to the lowest descending rate of the unit price of the material in sequence until the adjustable elements reach a reasonable lowest value;
and taking the price of all the adjustable elements when reaching the reasonable minimum value as the minimum price of each adjustable element, and obtaining the minimum cost according to the engineering quantity and the minimum price of each adjustable element.
From the above description, the reasonable minimum value is the engineering cost obtained by comprehensively considering factors such as construction organization design, quality, construction period, past construction experience of contractors, adoption of new construction technology and the like, and the adjustable elements are floated down by considering the reasonable minimum value and the lowest floating rate set by the user, so as to ensure the rationality of the obtained minimum value.
Further, the step S2 is specifically:
s21, taking the current prices of all adjustable elements in the adjustment parameters as a first group of data, taking the lowest prices of all adjustable elements as a second group of data, generating a first proportion according to the fitting of the first group of data and the second group of data, and floating the lowest prices according to the first proportion to obtain a third group of data;
s22, judging whether the real-time construction cost after floating is within a preset difference value with the target construction cost, if so, stopping fitting, otherwise, taking out two groups of data closest to the target construction cost from all the data to perform fitting, generate proportion and float according to the proportion;
and S23, circularly executing the step S22 until the real-time construction cost after the floating and the target construction cost are within a preset difference value.
From the above description, it can be seen that the fitting indentation method is adopted to quickly and accurately approach the target manufacturing cost.
Further, the step S1 is followed by the step of:
if the lowest cost is larger than the target cost, generating and displaying price adjustment failure prompt information, wherein the price adjustment failure prompt information comprises price adjustment failure information, an adjustable cost range of the current project and whether the lowest cost is applied or manual price adjustment is selected;
the step S3 specifically includes:
s31, judging whether the real-time construction cost is the same as the target construction cost, if so, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, otherwise, judging whether the adjustable elements capable of being continuously adjusted exist, if not, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, and if so, randomly obtaining an adjustable element from all the adjustable elements capable of being continuously adjusted and carrying out random price adjustment;
s32, judging whether the adjusted adjustable element and the corresponding price meet the project cost limit condition, if yes, saving the adjustment and calculating to obtain the real-time cost after the adjustment, otherwise, abandoning the adjustment and marking the adjustable element as unadjustable;
s33, repeating the step S31 and the step S32 until the real-time construction cost is the same as the target construction cost or the adjustable element which can be continuously adjusted does not exist.
It can be known from the above description that the difference price completion is realized by randomly selecting adjustable elements and randomly adjusting prices, so that the finally adjusted real-time cost can be consistent with the target cost as much as possible, and the adjusted bidding scheme has certain difference.
Further, when the manufacturing cost of the adjustment parameter is consistent with the target manufacturing cost in step S1, the current price ratio of all the adjustable elements in the adjustment parameter is then randomly oscillated to positive and negative two accuracies, and then a value is randomly selected to replace the current price.
As can be seen from the above description, a random oscillation method is adopted to ensure that the adjusted bidding schemes are random.
Referring to fig. 5, the one-click bidding terminal based on engineering bid includes a memory, a processor and a computer program stored in the memory and executable on the processor, wherein the processor implements the following steps when executing the computer program:
s1, obtaining a target construction cost, an adjusting parameter, an adjustable item and a lowest floating rate of unit price of materials, and calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching a reasonable lowest value, wherein the adjustable item comprises a plurality of adjustable elements;
s2, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value;
and S3, randomly acquiring adjustable elements to perform random price adjustment until the real-time manufacturing cost is equal to the target manufacturing cost.
From the above description, the beneficial effects of the present invention are: the method comprises the steps of obtaining target construction cost, adjustment parameters, adjustable items and the lowest downward floating rate of unit price of materials set by a user, calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching reasonable lowest values, fitting and retracting according to the current price and the lowest price in the adjustment parameters, then randomly obtaining the adjustable elements, and performing random price adjustment to enable the adjusted construction cost to be basically consistent with the target construction cost of the user.
Further, when the processor executes the step S1 in the computer program, the following steps are specifically implemented:
acquiring target manufacturing cost, adjustment parameters, adjustable items and lowest downward floating rate of unit price of materials, and if the adjustable items comprise enterprise management fees and profits, preferentially adjusting the rates of the enterprise management fees and the profits until a reasonable minimum value is reached;
acquiring other adjustable elements except the enterprise management fee and the profit in the adjustable items, arranging the adjustable elements in a price descending manner, and descending the adjustable elements according to the lowest descending rate of the unit price of the material in sequence until the adjustable elements reach a reasonable lowest value;
and taking the price of all the adjustable elements when reaching the reasonable minimum value as the minimum price of each adjustable element, and obtaining the minimum cost according to the engineering quantity and the minimum price of each adjustable element.
From the above description, the reasonable minimum value is the engineering cost obtained by comprehensively considering factors such as construction organization design, quality, construction period, past construction experience of contractors, adoption of new construction technology and the like, and the adjustable elements are floated down by considering the reasonable minimum value and the lowest floating rate set by the user, so as to ensure the rationality of the obtained minimum value.
Further, when the processor executes the step S2 in the computer program, the following steps are specifically implemented:
s21, taking the current prices of all adjustable elements in the adjustment parameters as a first group of data, taking the lowest prices of all adjustable elements as a second group of data, generating a first proportion according to the fitting of the first group of data and the second group of data, and floating the lowest prices according to the first proportion to obtain a third group of data;
s22, judging whether the real-time construction cost after floating is within a preset difference value with the target construction cost, if so, stopping fitting, otherwise, taking out two groups of data closest to the target construction cost from all the data to perform fitting, generate proportion and float according to the proportion;
and S23, circularly executing the step S22 until the real-time construction cost after the floating and the target construction cost are within a preset difference value.
From the above description, it can be seen that the fitting indentation method is adopted to quickly and accurately approach the target manufacturing cost.
Further, after the processor executes the step S1 in the computer program, the following steps are also implemented:
if the lowest cost is larger than the target cost, generating and displaying price adjustment failure prompt information, wherein the price adjustment failure prompt information comprises price adjustment failure information, an adjustable cost range of the current project and whether the lowest cost is applied or manual price adjustment is selected;
when the processor executes the step S3 in the computer program, the following steps are specifically implemented:
s31, judging whether the real-time construction cost is the same as the target construction cost, if so, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, otherwise, judging whether the adjustable elements capable of being continuously adjusted exist, if not, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, and if so, randomly obtaining an adjustable element from all the adjustable elements capable of being continuously adjusted and carrying out random price adjustment;
s32, judging whether the adjusted adjustable element and the corresponding price meet the project cost limit condition, if yes, saving the adjustment and calculating to obtain the real-time cost after the adjustment, otherwise, abandoning the adjustment and marking the adjustable element as unadjustable;
s33, repeating the step S31 and the step S32 until the real-time construction cost is the same as the target construction cost or the adjustable element which can be continuously adjusted does not exist.
It can be known from the above description that the difference price completion is realized by randomly selecting adjustable elements and randomly adjusting prices, so that the finally adjusted real-time cost can be consistent with the target cost as much as possible, and the adjusted bidding scheme has certain difference.
Further, when the processor executes the step S1 in the computer program, if the manufacturing cost of the adjustment parameter is consistent with the target manufacturing cost, the processor randomly selects a value to replace the current price after randomly oscillating the current price x ratio of all the adjustable elements in the adjustment parameter to positive and negative two accuracies.
As can be seen from the above description, a random oscillation method is adopted to ensure that the adjusted bidding schemes are random.
Referring to fig. 1 to 4, a first embodiment of the present invention is:
the one-key bid adjustment method based on engineering bidding comprises the following steps:
s1, obtaining a target cost, an adjusting parameter, an adjustable item and the lowest downward floating rate of the unit price of the material, and calculating to obtain the lowest cost and the lowest price of all adjustable elements reaching a reasonable lowest value, wherein the adjustable item comprises a plurality of adjustable elements;
in this embodiment, the following are specific: acquiring target manufacturing cost, adjustment parameters, adjustable items and the lowest downward floating rate of the unit price of the material, if the adjustable items comprise enterprise management fees and profits, preferentially adjusting the rates of the enterprise management fees and the profits until the rates reach reasonable minimum values, as shown in fig. 4, the target manufacturing cost of a user is 16808976 yuan, the adjustable items comprise the material, the main material, equipment, the enterprise management fees and the profits, and the lowest downward floating rate of the unit price of the material is 15%;
acquiring other adjustable elements except enterprise management fees and profits in the adjustable items, arranging the adjustable elements in a price descending manner, and carrying out downward floating on the adjustable elements in sequence according to the lowest downward floating rate of unit price of the material until the adjustable elements reach a reasonable minimum value, wherein the adjustable elements are water, bulk cement 42.5 and the like in the graph as shown in figure 4;
taking the price of all adjustable elements reaching the reasonable minimum value as the minimum price of each adjustable element, and obtaining the minimum cost according to the engineering quantity and the minimum price of each adjustable element;
after step S1, if the lowest cost is greater than the target cost, generating and displaying a price adjustment failure prompt message, wherein the price adjustment failure prompt message includes price adjustment failure information, an adjustable cost range of the current project, and whether to apply the lowest cost or select manual price adjustment;
s2, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value;
in this embodiment, the following are specific:
s21, taking the current prices of all adjustable elements in the adjustment parameters as a first group of data, taking the lowest prices of all adjustable elements as a second group of data, generating a first proportion according to the fitting of the first group of data and the second group of data, and floating the lowest prices according to the first proportion to obtain a third group of data;
s22, judging whether the real-time construction cost after floating is within a preset difference value with the target construction cost, if so, stopping fitting, otherwise, taking out two groups of data closest to the target construction cost from all the data to perform fitting, generate proportion and float according to the proportion;
s23, circularly executing the step S22 until the real-time construction cost after floating and the target construction cost are within a preset difference value;
s3, randomly obtaining adjustable elements to adjust the random price until the real-time cost is equal to the target cost;
in this embodiment, the following are specific:
s31, judging whether the real-time construction cost is the same as the target construction cost, if so, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, otherwise, judging whether an adjustable element capable of being continuously adjusted exists, if not, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, and if so, randomly obtaining an adjustable element from all adjustable elements capable of being continuously adjusted and carrying out random price adjustment;
it should be noted that, during the first stage of uniform floating-down and the second stage of uniform floating-up, there may be some cases where some adjustable elements are the same as the original values of the initial adjustment, i.e. belong to the elements that have not been adjusted in terms of value, for the following reasons: the first stage of floating is influenced by elements, so that the first material can float completely, one quota is reasonable and lowest price, and no floating space exists when other materials of the quota float; while in the second stage, some elements are floated to the original value. Therefore, in the difference compensation stage, the adjustable elements which are not adjusted and the adjustable elements which are adjusted but can be adjusted are filtered out for random adjustment, then the adjustable elements which are not adjusted are subjected to preferential random adjustment, and then the adjustable elements which are adjusted but can be adjusted are subjected to random selection adjustment, so that the reasonability and the difference of the whole bidding scheme are ensured.
S32, judging whether the adjusted adjustable element and the corresponding price meet the project cost limit condition, if yes, saving the adjustment and calculating to obtain the real-time cost after the adjustment, otherwise, abandoning the adjustment and marking the adjustable element as unadjustable;
and S33, repeatedly executing the step S31 and the step S32 until the real-time manufacturing cost is the same as the target manufacturing cost or no adjustable element which can be continuously adjusted exists.
That is, step S1 is first floated to the lowest cost, step S2 is then floated to approach the target cost, and finally step S3 is used to complete the difference price.
In this embodiment, if the manufacturing cost of the adjustment parameter is consistent with the target manufacturing cost in step S1, the current price ratio of all the adjustable elements in the adjustment parameter is then randomly oscillated to positive and negative two accuracies, and then a value is randomly selected to replace the current price. Such as: the current price of the adjustable element is 1.00, the ratio is 1.1, the obtained value is 1.00 x 1.1-1.10, the plus and minus precision is oscillated, namely, plus or minus 0.01 is added to obtain three values of 1.09,1.10 and 1.11, and one of the three values is randomly selected to replace 1.00.
In this embodiment, as shown in fig. 2, the adjusted control price data is set aside, the data of the original "volume price column" in the project is the bid control price, the bidder adjusts the target price on the basis of the bid control price, and after obtaining the target price, the bidder compares the target price with the bid control price conveniently.
In this embodiment, as shown in fig. 3, according to the bidding document requirement, locking is performed for the non-adjustable part of the fee during the adjustment process. As shown in fig. 3, the variable FBFXHJ-SBHJ + DJCSHJ in the calculation formula in the row named safe civilization construction cost is converted into a numerical value by back calculation, so that the cost is fixed, and the back calculation mode is as follows: the control price amount is divided by the rate and multiplied by 100 to obtain the value, namely 100 × 118356/2.27 in fig. 3 is 5213920.7.
In this embodiment, the target cost includes not only the direct input of the user, but also the calculation and application after the input of the K value in the calculator, wherein the K value of each bidding unit is determined by the bidding document request randomly drawn by the electronic trading platform or randomly drawn at the bidding site.
In addition, since the user adjusts the price in the project bidding process, the price for each element does not exceed the original value in principle, that is, the price does not exceed the original value in either the floating in step S2 or the random adjustment in step S3.
Referring to fig. 5, a second embodiment of the present invention is:
the one-click bidding terminal 1 based on engineering bid comprises a memory 3, a processor 2 and a computer program which is stored on the memory 3 and can run on the processor 2, wherein the processor 2 realizes the steps of the first embodiment when executing the computer program.
In summary, the one-key bid adjustment method and terminal based on engineering bid provided by the invention can obtain the target cost, the adjustment parameter, the adjustable item and the lowest downward floating rate of the unit price of the material set by the user, the adjustable elements are floated down in consideration of a reasonable minimum value and a minimum floating rate set by a user, so as to calculate the lowest cost and the lowest price of all adjustable elements reaching reasonable lowest value, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters, adjustable elements are randomly selected and random price adjustment is carried out, so as to realize price difference compensation, thereby leading the finally adjusted real-time manufacturing cost to be consistent with the target manufacturing cost as much as possible, the invention can conveniently and quickly adjust the price of the project to achieve the project bid price required by the user, and can ensure the reasonability and difference of the adjusted bid scheme to the maximum extent.
The above description is only an embodiment of the present invention, and not intended to limit the scope of the present invention, and all equivalent changes made by using the contents of the present specification and the drawings, or applied directly or indirectly to the related technical fields, are included in the scope of the present invention.

Claims (10)

1. The one-key bid adjustment method based on engineering bidding is characterized by comprising the following steps of:
s1, obtaining a target construction cost, an adjusting parameter, an adjustable item and a lowest floating rate of unit price of materials, and calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching a reasonable lowest value, wherein the adjustable item comprises a plurality of adjustable elements;
s2, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value;
and S3, randomly acquiring adjustable elements to perform random price adjustment until the real-time manufacturing cost is equal to the target manufacturing cost.
2. The one-touch bid tuning method based on project bid according to claim 1, wherein the step S1 is specifically as follows:
acquiring target manufacturing cost, adjustment parameters, adjustable items and lowest downward floating rate of unit price of materials, and if the adjustable items comprise enterprise management fees and profits, preferentially adjusting the rates of the enterprise management fees and the profits until a reasonable minimum value is reached;
acquiring other adjustable elements except the enterprise management fee and the profit in the adjustable items, arranging the adjustable elements in a price descending manner, and descending the adjustable elements according to the lowest descending rate of the unit price of the material in sequence until the adjustable elements reach a reasonable lowest value;
and taking the price of all the adjustable elements when reaching the reasonable minimum value as the minimum price of each adjustable element, and obtaining the minimum cost according to the engineering quantity and the minimum price of each adjustable element.
3. The one-touch bid tuning method based on project bid according to claim 1, wherein the step S2 is specifically as follows:
s21, taking the current prices of all adjustable elements in the adjustment parameters as a first group of data, taking the lowest prices of all adjustable elements as a second group of data, generating a first proportion according to the fitting of the first group of data and the second group of data, and floating the lowest prices according to the first proportion to obtain a third group of data;
s22, judging whether the real-time construction cost after floating is within a preset difference value with the target construction cost, if so, stopping fitting, otherwise, taking out two groups of data closest to the target construction cost from all the data to perform fitting, generate proportion and float according to the proportion;
and S23, circularly executing the step S22 until the real-time construction cost after the floating and the target construction cost are within a preset difference value.
4. The project bid-based one-touch bidding method according to claim 1, wherein the step S1 is followed by the further steps of:
if the lowest cost is larger than the target cost, generating and displaying price adjustment failure prompt information, wherein the price adjustment failure prompt information comprises price adjustment failure information, an adjustable cost range of the current project and whether the lowest cost is applied or manual price adjustment is selected;
the step S3 specifically includes:
s31, judging whether the real-time construction cost is the same as the target construction cost, if so, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, otherwise, judging whether the adjustable elements capable of being continuously adjusted exist, if not, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, and if so, randomly obtaining an adjustable element from all the adjustable elements capable of being continuously adjusted and carrying out random price adjustment;
s32, judging whether the adjusted adjustable element and the corresponding price meet the project cost limit condition, if yes, saving the adjustment and calculating to obtain the real-time cost after the adjustment, otherwise, abandoning the adjustment and marking the adjustable element as unadjustable;
s33, repeating the step S31 and the step S32 until the real-time construction cost is the same as the target construction cost or the adjustable element which can be continuously adjusted does not exist.
5. The one-touch bid tuning method according to any one of claims 1 to 4, wherein if the manufacturing cost of the tuning parameters is consistent with the target manufacturing cost in step S1, the current price ratio of all the tunable elements in the tuning parameters is then randomly oscillated to positive and negative two degrees of accuracy, and then a numerical value is randomly selected to replace the current price.
6. A one-key bid-tuning terminal based on engineering bid comprises a memory, a processor and a computer program stored on the memory and capable of running on the processor, and is characterized in that the processor executes the computer program to realize the following steps:
s1, obtaining a target construction cost, an adjusting parameter, an adjustable item and a lowest floating rate of unit price of materials, and calculating to obtain the lowest construction cost and the lowest price of all adjustable elements reaching a reasonable lowest value, wherein the adjustable item comprises a plurality of adjustable elements;
s2, fitting and retracting are carried out according to the current price and the lowest price in the adjusting parameters until the fitted real-time cost and the target cost are within a preset difference value;
and S3, randomly acquiring adjustable elements to perform random price adjustment until the real-time manufacturing cost is equal to the target manufacturing cost.
7. The project bid-based one-touch tender terminal of claim 6, wherein the processor implements the following steps when executing the step S1 in the computer program:
acquiring target manufacturing cost, adjustment parameters, adjustable items and lowest downward floating rate of unit price of materials, and if the adjustable items comprise enterprise management fees and profits, preferentially adjusting the rates of the enterprise management fees and the profits until a reasonable minimum value is reached;
acquiring other adjustable elements except the enterprise management fee and the profit in the adjustable items, arranging the adjustable elements in a price descending manner, and descending the adjustable elements according to the lowest descending rate of the unit price of the material in sequence until the adjustable elements reach a reasonable lowest value;
and taking the price of all the adjustable elements when reaching the reasonable minimum value as the minimum price of each adjustable element, and obtaining the minimum cost according to the engineering quantity and the minimum price of each adjustable element.
8. The project bid-based one-touch tender terminal of claim 6, wherein the processor implements the following steps when executing the step S2 in the computer program:
s21, taking the current prices of all adjustable elements in the adjustment parameters as a first group of data, taking the lowest prices of all adjustable elements as a second group of data, generating a first proportion according to the fitting of the first group of data and the second group of data, and floating the lowest prices according to the first proportion to obtain a third group of data;
s22, judging whether the real-time construction cost after floating is within a preset difference value with the target construction cost, if so, stopping fitting, otherwise, taking out two groups of data closest to the target construction cost from all the data to perform fitting, generate proportion and float according to the proportion;
and S23, circularly executing the step S22 until the real-time construction cost after the floating and the target construction cost are within a preset difference value.
9. The project bid-based one-touch tender terminal of claim 6, wherein after the processor executes the step S1 in the computer program, the following steps are further implemented:
if the lowest cost is larger than the target cost, generating and displaying price adjustment failure prompt information, wherein the price adjustment failure prompt information comprises price adjustment failure information, an adjustable cost range of the current project and whether the lowest cost is applied or manual price adjustment is selected;
when the processor executes the step S3 in the computer program, the following steps are specifically implemented:
s31, judging whether the real-time construction cost is the same as the target construction cost, if so, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, otherwise, judging whether the adjustable elements capable of being continuously adjusted exist, if not, storing the adjustment scheme of the real-time construction cost finally obtained in the step S2, and if so, randomly obtaining an adjustable element from all the adjustable elements capable of being continuously adjusted and carrying out random price adjustment;
s32, judging whether the adjusted adjustable element and the corresponding price meet the project cost limit condition, if yes, saving the adjustment and calculating to obtain the real-time cost after the adjustment, otherwise, abandoning the adjustment and marking the adjustable element as unadjustable;
s33, repeating the step S31 and the step S32 until the real-time construction cost is the same as the target construction cost or the adjustable element which can be continuously adjusted does not exist.
10. The project bid-based one-touch bidding terminal according to any one of claims 6 to 9, wherein when executing the step S1 in the computer program, if the manufacturing cost of the tuning parameter is consistent with the target manufacturing cost, the processor randomly selects a value to replace the current price after randomly oscillating the current price ratio of all tunable elements in the tuning parameter to plus or minus two accuracies.
CN201911076657.5A 2019-11-06 2019-11-06 One-key bid adjustment method and terminal based on engineering bid Pending CN110782326A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911076657.5A CN110782326A (en) 2019-11-06 2019-11-06 One-key bid adjustment method and terminal based on engineering bid

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911076657.5A CN110782326A (en) 2019-11-06 2019-11-06 One-key bid adjustment method and terminal based on engineering bid

Publications (1)

Publication Number Publication Date
CN110782326A true CN110782326A (en) 2020-02-11

Family

ID=69389839

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911076657.5A Pending CN110782326A (en) 2019-11-06 2019-11-06 One-key bid adjustment method and terminal based on engineering bid

Country Status (1)

Country Link
CN (1) CN110782326A (en)

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111553558A (en) * 2020-03-30 2020-08-18 宁波市城展建设工程有限公司 Building cost budgeting method, device and storage medium thereof
CN111598731A (en) * 2020-03-27 2020-08-28 广联达科技股份有限公司 Intelligent adjustment system and method for man-machine price difference in engineering settlement
CN112698776A (en) * 2021-03-24 2021-04-23 杭州品茗安控信息技术股份有限公司 Engineering data adjusting method and related device
CN112767040A (en) * 2021-01-26 2021-05-07 广联达科技股份有限公司 Method and device for generating project pricing file, computer equipment and storage medium

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111598731A (en) * 2020-03-27 2020-08-28 广联达科技股份有限公司 Intelligent adjustment system and method for man-machine price difference in engineering settlement
CN111553558A (en) * 2020-03-30 2020-08-18 宁波市城展建设工程有限公司 Building cost budgeting method, device and storage medium thereof
CN112767040A (en) * 2021-01-26 2021-05-07 广联达科技股份有限公司 Method and device for generating project pricing file, computer equipment and storage medium
CN112698776A (en) * 2021-03-24 2021-04-23 杭州品茗安控信息技术股份有限公司 Engineering data adjusting method and related device

Similar Documents

Publication Publication Date Title
CN110782326A (en) One-key bid adjustment method and terminal based on engineering bid
Holmberg Unique supply function equilibrium with capacity constraints
EP1662435A2 (en) Method and apparatus for conducting a dynamic exchange
KR102094137B1 (en) Method for relaying electric power trading
Cole et al. Fast-converging tatonnement algorithms for one-time and ongoing market problems
WO2001053929A1 (en) Method and system for partial quantity evaluated rank bidding in online auctions
Mason Network externalities and the Coase conjecture
US8521630B2 (en) Curve engine
Madani et al. Minimizing opportunity costs of paradoxically rejected block orders in European day-ahead electricity markets
CN109858934A (en) Pricing method, device and computer readable storage medium
Karaca et al. Game theoretic analysis of electricity market auction mechanisms
CN115063063A (en) Distribution method, device, equipment and storage medium of purchase order
JP2006195848A (en) Method of analyzing determinant for contract price in electric power transaction market and computer program for analysis
US20070219836A1 (en) Shipping planning system
Anderson et al. Price instability in multi-unit auctions
Carmona et al. The self-financing equation in high frequency markets
Zheng et al. Reactive production with preprocessing restriction in supply chains with forecast updates
CN111415232A (en) Bidding cloud platform and using method thereof
Lopomo et al. Optimal procurement with quality concerns
CN113807961A (en) Multi-microgrid energy transaction method and system based on alliance chain
Schumpeter et al. Imperfect competition
Kameshwaran et al. Design of progressive auctions for procurement based on Lagrangian relaxation
Ahunbay et al. Solving Large-Scale Electricity Market Pricing Problems in Polynomial Time
JP2006092044A (en) Method, device and program for displaying bid and order for electricity transaction
Ye et al. Analysis On Manufacturing Logistics Network Equilibrium Under the VMI Inventory Management Mode

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
WD01 Invention patent application deemed withdrawn after publication
WD01 Invention patent application deemed withdrawn after publication

Application publication date: 20200211