CN110778160A - Assembled clean operating room - Google Patents

Assembled clean operating room Download PDF

Info

Publication number
CN110778160A
CN110778160A CN201911140883.5A CN201911140883A CN110778160A CN 110778160 A CN110778160 A CN 110778160A CN 201911140883 A CN201911140883 A CN 201911140883A CN 110778160 A CN110778160 A CN 110778160A
Authority
CN
China
Prior art keywords
keel
assemblies
assembly
operating room
positioning
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201911140883.5A
Other languages
Chinese (zh)
Inventor
王刚玉
彭俊杰
张明亮
彭康杨
叶左权
曲兵
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
SHENZHEN HUAJIAN CONSTRUCTION GROUP CO Ltd
Original Assignee
SHENZHEN HUAJIAN CONSTRUCTION GROUP CO Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by SHENZHEN HUAJIAN CONSTRUCTION GROUP CO Ltd filed Critical SHENZHEN HUAJIAN CONSTRUCTION GROUP CO Ltd
Priority to CN201911140883.5A priority Critical patent/CN110778160A/en
Publication of CN110778160A publication Critical patent/CN110778160A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04HBUILDINGS OR LIKE STRUCTURES FOR PARTICULAR PURPOSES; SWIMMING OR SPLASH BATHS OR POOLS; MASTS; FENCING; TENTS OR CANOPIES, IN GENERAL
    • E04H3/00Buildings or groups of buildings for public or similar purposes; Institutions, e.g. infirmaries or prisons
    • E04H3/08Hospitals, infirmaries, or the like; Schools; Prisons

Abstract

The invention discloses an assembled clean operating room, which comprises a keel assembly, a wall corner connecting assembly, a wall panel and a top plate, wherein the keel assembly is arranged on the wall corner connecting assembly; the ground keel assembly is fixedly arranged on the ground; the wall corner connecting assemblies are arranged on the floor keel assemblies, the wall panel is connected between every two adjacent wall corner connecting assemblies, and the wall panel is fixed on the floor keel assemblies through the wall corner connecting assemblies; the roof sets up in a plurality of the top of shingle nail, and with a plurality of corner coupling assembling links to each other. According to the assembled clean operating room provided by the embodiment of the invention, each component can be produced in a modularized manner and can be directly assembled on site.

Description

Assembled clean operating room
Technical Field
The invention relates to the field of architectural decoration, in particular to an assembled clean operating room.
Background
At present in the clean operating room construction of hospital, generally adopt prefabricated combination formula steel sheet operating room, the wall body adopts high bearing square steel tube frame structure as fossil fragments, dalle back pastes the gypsum board, dalle face spouts antibacterial coating, and construct at the engineering scene, and relate to processes such as multiple professional welding, cutting, tailor and paste and spraying, the construction of every specialty needs corresponding professional, construction procedure is many, the technology is complicated, the period is long, the expense is high, the operation energy consumption is high, so, make construction cost high, and the efficiency of construction is low, be unfavorable for the development of enterprise.
Disclosure of Invention
The present invention is directed to solving, at least to some extent, one of the technical problems in the related art. Therefore, the invention aims to provide an assembled clean operating room.
In order to achieve the purpose, the assembled clean operating room comprises a ground keel component, a wall corner connecting component, a wall panel and a top plate;
the ground keel assembly is fixedly arranged on the ground;
the wall corner connecting assemblies are arranged on the floor keel assemblies, the wall panel is connected between every two adjacent wall corner connecting assemblies, and the wall panel is fixed on the floor keel assemblies through the wall corner connecting assemblies;
the roof sets up in a plurality of the top of shingle nail, and with a plurality of corner coupling assembling links to each other.
According to the assembled clean operating room provided by the embodiment of the invention, each component can be produced in a modularized manner and can be directly assembled on site.
In addition, the assembled clean operating room according to the above embodiment of the present invention may further have the following additional technical features:
according to one embodiment of the invention, the floor keel assembly comprises a keel frame and a plurality of locking fixing pieces;
the keel frame is connected with the plurality of wall panels and the plurality of corner connecting components;
the locking fixing pieces are connected with the keel frame and used for fixing the keel frame on the ground.
According to one embodiment of the invention, the keel frame comprises a plurality of first keel members and a plurality of second keel members;
the first keel pieces are of strip-shaped structures, and the wall panels are connected with the first keel pieces through a plurality of transverse positioning connecting assemblies;
the plurality of second keel pieces are of circular arc structures, two ends of each second keel piece are connected with the corresponding first keel piece, and the corner connecting assembly is connected with the second keel pieces.
According to an embodiment of the invention, the corner connecting assembly comprises a first connecting beam and a second connecting beam, the first connecting beam is of an L-shaped structure, two ends of the first connecting beam are respectively connected with the first connecting beam of the adjacent corner connecting assembly, the upper end of the second connecting beam is vertically connected with the middle part of the first connecting beam, and the lower end of the second connecting beam is connected with the second keel piece;
two sides of the wall panel are fixedly connected with two adjacent second connecting beams through a plurality of vertical positioning connecting assemblies and first fixing pieces penetrating through the vertical positioning connecting assemblies, and the upper end of the wall panel is fixedly connected with the first connecting beams through a plurality of transverse positioning connecting assemblies and second fixing pieces penetrating through the transverse positioning assemblies;
the roof sets up in a plurality of between the first tie-beam to through a plurality of horizontal positioning coupling assembling and wear to locate a plurality of third mounting in the horizontal positioning assembly with first tie-beam links to each other.
According to an embodiment of the present invention, the transverse positioning connecting assembly and the vertical positioning connecting assembly each include a first U-shaped seat, a second U-shaped seat, and a positioning member, and the positioning member is adapted to be clamped between the first U-shaped seat and the second U-shaped seat.
According to one embodiment of the invention, the shingle includes a plurality of first panels connected by a plurality of the vertical positioning connection assemblies;
the roof includes a plurality of second plate bodies, a plurality of second plate bodies are through a plurality of horizontal positioning coupling assembling links to each other.
According to one embodiment of the invention, the hanging plate and the supporting component are further included, the supporting component comprises a first supporting rod, an adjusting frame and a second supporting rod, the upper end of the first supporting rod is connected with the hanging plate, the lower end of the first supporting rod is in threaded connection with the adjusting frame, the upper end of the second supporting rod is connected with the adjusting frame, and the lower end of the second supporting rod is connected with the transverse connecting component on the top plate.
According to one embodiment of the invention, the lower surface of the hanging plate is provided with a plurality of hanging assemblies, and the lower ends of the hanging assemblies extend to the lower part of the top plate.
According to an embodiment of the present invention, the first connecting beam and the second connecting beam are both arc-shaped structures.
Drawings
FIG. 1 is a schematic structural diagram of an embodiment of the present invention;
FIG. 2 is a schematic view of a connection structure of a wall panel and a corner connecting assembly according to an embodiment of the present invention;
FIG. 3 is an enlarged partial schematic view at A in FIG. 2;
figure 4 is a schematic structural view of a floor keel assembly according to an embodiment of the invention;
fig. 5 is a schematic structural diagram of a first board body according to an embodiment of the present invention;
FIG. 6 is a schematic structural diagram of a horizontal positioning connection assembly and a vertical positioning connection assembly according to an embodiment of the present invention;
FIG. 7 is a schematic structural diagram of a hanger assembly according to an embodiment of the present invention.
Reference numerals:
a floor keel assembly 10;
a keel frame 11;
a first keel member 111;
a second keel member 112;
a locking fixture 12;
corner connecting assemblies 20;
a first connecting beam 21;
a second connection beam 22;
a wall panel 30;
a first plate body 31;
a recess 311;
a first fixing member 312;
a second fixing member 313;
a top plate 40;
a lateral positioning attachment assembly 50;
a first U-shaped seat 51;
a second U-shaped seat 52;
a positioning member 53;
a hanging plate 60;
a support assembly 70;
a hanger assembly 80.
The implementation, functional features and advantages of the objects of the present invention will be further explained with reference to the accompanying drawings.
Detailed Description
Reference will now be made in detail to embodiments of the present invention, examples of which are illustrated in the accompanying drawings, wherein like or similar reference numerals refer to the same or similar elements or elements having the same or similar function throughout. The embodiments described below with reference to the drawings are illustrative and intended to be illustrative of the invention and are not to be construed as limiting the invention.
In the description of the present invention, it is to be understood that the terms "center", "longitudinal", "lateral", "length", "width", "thickness", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", "top", "bottom", "inner", "outer", "clockwise", "counterclockwise", and the like, indicate orientations and positional relationships based on those shown in the drawings, and are used only for convenience of description and simplicity of description, and do not indicate or imply that the device or element being referred to must have a particular orientation, be constructed and operated in a particular orientation, and thus, should not be considered as limiting the present invention.
Furthermore, the terms "first", "second" and "first" are used for descriptive purposes only and are not to be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, a feature defined as "first" or "second" may explicitly or implicitly include one or more of that feature. In the description of the present invention, "a plurality" means two or more unless specifically defined otherwise.
In the present invention, unless otherwise expressly specified or limited, the terms "mounted," "connected," "secured," and the like are to be construed broadly and can, for example, be fixedly connected, detachably connected, or integrally connected; can be mechanically or electrically connected; they may be connected directly or indirectly through intervening media, or they may be interconnected between two elements. The specific meanings of the above terms in the present invention can be understood by those skilled in the art according to specific situations.
Referring to fig. 1 to 7, an embodiment of the present invention provides an assembled clean operating room, including a floor keel assembly 10, a corner connecting assembly 20, a wall panel 30 and a ceiling panel 40;
specifically, the ground keel assembly 10 is fixedly installed on the ground, that is, the ground keel assembly 10 is equivalent to a building foundation, and plays a role in bearing and supporting the whole operating room.
The corner connecting assemblies 20 are arranged on the ground keel assembly 10, a wall panel 30 is connected between every two adjacent corner connecting assemblies 20, and the wall panel 30 is fixed on the ground keel assembly 10 through the corner connecting assemblies 20. That is, a plurality of corner connecting assemblies 20 are arranged on the floor joist assembly 10 at intervals, and a wall panel 30 is arranged between two adjacent corner connecting assemblies 20, so that the plurality of corner connecting assemblies 20 and the plurality of wall panels 30 enclose to form a building main structure, so as to define the space of an operating room, and the plurality of wall panels 30 are fixed on the floor joist assembly 10 through the plurality of corner connecting assemblies 20, therefore, the installation and fixation of the plurality of wall panels 30 are more convenient, and further, the working efficiency of constructors can be improved.
The top plate 40 is disposed above the plurality of wall panels 30 and connected to the plurality of corner connecting members 20, so that the space in the operating room can be sealed by the top plate 40 and a dust-proof effect can be achieved.
According to the assembled clean operating room provided by the embodiment of the invention, each component can be produced in a modularized manner and can be directly assembled on site.
Advantageously, in one embodiment of the present invention, the floor keel assembly 10 comprises a keel frame 11 and a plurality of locking fixtures 12;
the keel frame 11 is connected with a plurality of wall panels 30 and a plurality of corner connecting components 20;
a plurality of locking fixtures 12 are connected to the keel frame 11 for fixing the keel frame 11 to the ground.
Preferably, expansion bolts can be used for the plurality of locking fixtures 12, so that the keel frame 11 can be stably and firmly fixed on the ground by using the expansion bolts, and accordingly, the keel frame 11 can be firmly installed on the plurality of wall panels 30 and the corner connecting assemblies 20, thereby improving the stability of the whole operating room.
Advantageously, in another embodiment of the invention, the keel frame 11 comprises a plurality of first keel members 111 and a plurality of second keel members 112;
the first keel members 111 are of strip-shaped structures, and the wall panels 30 are connected with the first keel members 111 through the transverse positioning connecting assemblies 50;
the second keel members 112 are circular arc-shaped structures, two ends of each second keel member are connected with the first keel member 111, and the corner connecting assembly 20 is connected with the second keel members 112.
That is, the keel frame 11 has a substantially square structure, wherein the second keel frame 11 is disposed at a corner position and connected to the first keel member 111, so that the corner connecting assembly 20 can be installed at the corner position through the second keel member 112, and the wall panel 30 can be installed through the first keel member 111, so as to form a wall structure, thereby defining a space in the operating room in cooperation with the corner connecting assembly 20.
Advantageously, in another embodiment of the present invention, the corner connecting assembly 20 includes a first connecting beam 21 and a second connecting beam 22, the first connecting beam 21 is of an L-shaped structure, two ends of the first connecting beam 21 are respectively connected to the first connecting beam 21 of the adjacent corner connecting assembly 20, the upper end of the second connecting beam 22 is vertically connected to the middle of the first connecting beam 21, and the lower end of the second connecting beam is connected to the second keel 112;
two sides of the shingle 30 are fixedly connected with two adjacent second connecting beams 22 through a plurality of vertical positioning connecting assemblies and first fixing pieces 312 arranged in the vertical positioning connecting assemblies in a penetrating way, and the upper end of the shingle 30 is fixedly connected with two first connecting beams through a plurality of transverse positioning connecting assemblies 50 and second fixing pieces arranged in the transverse positioning assemblies in a penetrating way;
the top plate 40 is disposed between the first connecting beams 21 and connected to the first connecting beams 21 through the plurality of transverse positioning connecting assemblies 50 and the third fixing members penetrating through the plurality of transverse positioning assemblies.
That is, the first connection beam 21 includes two mutually perpendicular beam bodies, one end of the two beam bodies is perpendicularly connected with the upper end of the second connection beam 22, the other end of the two beam bodies is connected with one beam body of the first connection beam 21 of the other adjacent corner connection component 20, thus, the two adjacent second connection beams 22 and the two adjacent first connection beams 21 form an installation space, the wall panel 30 is installed in the space, and the two sides of the wall panel 30 are fixedly connected with the two adjacent second connection beams 22 through the vertical positioning connection component, the upper end of the wall panel 30 is fixedly connected with the two connected first connection beams 21 through the transverse positioning connection component 50, and the wall panel 30 can be positioned and installed through the transverse positioning connection component 50 and the vertical positioning connection component, so as to be fixed on the floor joist component 10. In addition, an installation space is formed between the connected first connection beams 21, and the top plate 40 is installed in the space through the transverse positioning connection assembly 50, so that the top plate 40 can be positioned and installed through the transverse positioning connection assembly 50 to prevent dust in the operating room space.
Preferably, the first fixing member 312, the second fixing member 313 and the third fixing member may all adopt fastening screws, which not only has good fixing effect, but also is easy to operate.
Advantageously, in some embodiments of the present invention, the transverse positioning connecting assembly 50 and the vertical positioning connecting assembly each include a first U-shaped seat 51, a second U-shaped seat 52, and a positioning member 53, and the positioning member 53 is adapted to be clamped between the first U-shaped seat 51 and the second U-shaped seat 52.
That is, when the first U-shaped seat 51 and the second U-shaped seat 52 are respectively sleeved on the positioning member 53, the first U-shaped seat 51 and the second U-shaped seat 52 are just opposite to each other, so that the positioning of the first U-shaped seat 51 and the second U-shaped seat 52 can be realized, when the wall panel 30 is connected through the transverse positioning connection assembly 50, the first U-shaped seat 51 can be arranged in the groove 311 on the first keel member 111 and the first connection beam 21 in advance, the second U-shaped seat 52 can be arranged in the groove 311 on the outer wall of the wall panel 30, then the positioning member 53 can be arranged in the first U-shaped seat 51, so that when the wall panel 30 is installed, the positioning installation of the wall panel 30 and the corresponding first keel member 111 and the first connection beam 21 can be conveniently realized only by clamping the second U-shaped seat 52 outside the corresponding positioning member 53, and similarly, the top plate 40 can be conveniently positioned and installed with the first connection beam in the same way, so, can be quick fix a position the installation to shingle nail 30 and roof 40, of course, all set up threaded hole on the horizontal positioning coupling assembling 50 of connecting shingle nail 30 and first tie-beam 21 and the horizontal positioning coupling assembling 50 of connecting roof 40 and first tie-beam 21 to cooperate second mounting 313 and third mounting to lock shingle nail 30, roof 40 and first tie-beam 21 fixedly. And when connecting shingle nail 30 through vertical positioning coupling assembling, then can set up first U type seat 51 in recess 311 on second tie-beam 22 in advance, set up second U type seat 52 in recess 311 on shingle nail 30 outer wall, then, establish setting element 53 in first U type seat 51, so, when the installation wall, only need make second U type seat 52 card establish outside corresponding setting element 53, the installation of realization shingle nail 30 and corresponding second tie-beam 22 that can be very convenient, of course, set up threaded hole on the vertical positioning coupling assembling of connecting shingle nail 30 and second tie-beam 22, so that cooperate first mounting 312 to lock wallboard nail 30 and second tie-beam 22 fixedly. From this, horizontal positioning coupling assembling 50 and vertical positioning coupling assembling adopt this kind of structure, make the location installation between shingle nail 30 and roof 40 and keel subassembly 10 and corner coupling assembling 20 very convenient to be favorable to the constructor to be under construction.
Advantageously, in some embodiments of the invention, the wall panel 30 comprises a plurality of first panels 31, the plurality of first panels 31 being connected by a plurality of vertical positioning connection assemblies;
the top plate 40 includes a plurality of second panels connected by a plurality of transverse positioning and connection assemblies 50.
That is to say, shingle 30 and roof 40 are formed by a plurality of plate body concatenations, it is specific, shingle 30 is formed by a plurality of first plate bodies 31 through the concatenation of vertical positioning coupling assembling, and roof 40 has a plurality of second plate bodies to form through the concatenation of a plurality of transverse positioning coupling assembling 50, so, can be with further miniaturization and modularization of shingle 30 and roof 40, on the one hand, be convenient for production and processing and the transportation of shingle 30 and roof 40, thereby can reduce cost, on the other hand, the constructor's of also being convenient for construction, thereby can improve the efficiency of construction, shorten construction cycle.
It should be noted that the splicing manner between the first boards 31 and the splicing manner between the second boards are the same as the positioning connection manner between the wall panel 30 and the third connection, and therefore, further description thereof is omitted in this embodiment.
Advantageously, in other embodiments of the present invention, the hanging plate 60 and the supporting assembly 70 are further included, and the supporting assembly 70 includes a first supporting rod, an adjusting frame and a second supporting rod, the first supporting rod is connected to the hanging plate 60 at the upper end, the lower end is connected to the adjusting frame by screw threads, the second supporting rod is connected to the adjusting frame at the upper end, and the lower end is connected to the transverse connecting assembly on the top plate 40.
Preferably, a plurality of hanger units 80 are provided on the lower surface of the hanging plate 60, and the lower ends of the plurality of hanger units 80 extend below the top plate 40.
In this way, on one hand, a hanging plate 60 is supported on the top of the top plate 40 by a plurality of support assemblies 70, so that required components, such as an exhaust pipe and the like, can be properly installed in the space between the top plate 40 and the hanging plate 60, and the hanging plate 60 can play a role of dust prevention; on the other hand, the hanging component 80 arranged at the bottom of the hanging plate 60 can be used for hanging the required medical supplies so as to be used in the operation process.
Advantageously, in further embodiments of the present invention, the first connecting beam 21 and the second connecting beam 22 are both circular arc structures.
That is to say, corner coupling assembling 20 is circular arc structure, so, even make between two adjacent shingles 30 be the arc transition, also be the arc transition between shingle 30 and the roof 40, so, just there is not reentrant corner position between two adjacent shingles 30 and between shingle 30 and the roof 40, then, on the one hand, the junction between two adjacent shingles 30 and between shingle 30 and the roof 40 is difficult to accumulate the dust, on the other hand, this junction also easily washs, is favorable to improving the cleanliness factor in the operating room, also is convenient for medical personnel's subsequent cleaning work.
In the description herein, references to the description of the term "one embodiment," "some embodiments," "an example," "a specific example," or "some examples," etc., mean that a particular feature, structure, material, or characteristic described in connection with the embodiment or example is included in at least one embodiment or example of the invention. In this specification, the schematic representations of the terms used above do not necessarily refer to the same embodiment or example. Furthermore, the particular features, structures, materials, or characteristics described may be combined in any suitable manner in any one or more embodiments or examples.
Although embodiments of the present invention have been shown and described above, it is understood that the above embodiments are exemplary and should not be construed as limiting the present invention, and that variations, modifications, substitutions and alterations can be made in the above embodiments by those of ordinary skill in the art without departing from the principle and spirit of the present invention.

Claims (9)

1. An assembled clean operating room is characterized by comprising a keel assembly, a corner connecting assembly, a wall panel and a top plate;
the ground keel assembly is fixedly arranged on the ground;
the wall corner connecting assemblies are arranged on the floor keel assemblies, the wall panel is connected between every two adjacent wall corner connecting assemblies, and the wall panel is fixed on the floor keel assemblies through the wall corner connecting assemblies;
the roof sets up in a plurality of the top of shingle nail, and with a plurality of corner coupling assembling links to each other.
2. The assembled clean operating room of claim 1, wherein the floor keel assembly comprises a keel frame and a plurality of locking fixtures;
the keel frame is connected with the plurality of wall panels and the plurality of corner connecting components;
the locking fixing pieces are connected with the keel frame and used for fixing the keel frame on the ground.
3. The assembled clean operating room of claim 2, wherein the keel frame comprises a plurality of first keel members and a plurality of second keel members;
the first keel pieces are of strip-shaped structures, and the wall panels are connected with the first keel pieces through a plurality of transverse positioning connecting assemblies;
the plurality of second keel pieces are of circular arc structures, two ends of each second keel piece are connected with the corresponding first keel piece, and the corner connecting assembly is connected with the second keel pieces.
4. The assembly type clean operating room as claimed in claim 3, wherein the corner connecting assembly comprises a first connecting beam and a second connecting beam, the first connecting beam is of an L-shaped structure, two ends of the first connecting beam are respectively connected with the first connecting beam of the adjacent corner connecting assembly, the upper end of the second connecting beam is vertically connected with the middle part of the first connecting beam, and the lower end of the second connecting beam is connected with the second keel member;
two sides of the wall panel are fixedly connected with two adjacent second connecting beams through a plurality of vertical positioning connecting assemblies and first fixing pieces penetrating through the vertical positioning connecting assemblies, and the upper end of the wall panel is fixedly connected with the first connecting beams through a plurality of transverse positioning connecting assemblies and second fixing pieces penetrating through the transverse positioning assemblies;
the roof sets up in a plurality of between the first tie-beam to through a plurality of horizontal positioning coupling assembling and wear to locate a plurality of third mounting in the horizontal positioning assembly with first tie-beam links to each other.
5. The assembled clean operating room of claim 4, wherein the transverse positioning connecting assembly and the vertical positioning connecting assembly each comprise a first U-shaped seat, a second U-shaped seat and a positioning member, and the positioning member is adapted to be clamped between the first U-shaped seat and the second U-shaped seat.
6. The assembled clean operating room of claim 5, wherein the shingle comprises a plurality of first panels connected by a plurality of the vertical positioning connection assemblies;
the roof includes a plurality of second plate bodies, a plurality of second plate bodies are through a plurality of horizontal positioning coupling assembling links to each other.
7. The assembled clean operating room of claim 5, further comprising a hanging plate and a supporting component, wherein the supporting component comprises a first supporting rod, an adjusting frame and a second supporting rod, the upper end of the first supporting rod is connected with the hanging plate, the lower end of the first supporting rod is in threaded connection with the adjusting frame, the upper end of the second supporting rod is connected with the adjusting frame, and the lower end of the second supporting rod is connected with the transverse connecting component on the top plate.
8. The assembled clean operating room of claim 7, wherein the lower surface of the hanging plate is provided with a plurality of hanging components, and the lower ends of the plurality of hanging components extend to below the top plate.
9. The assembled clean operating room of claim 4, wherein the first and second connecting beams are both arc-shaped structures.
CN201911140883.5A 2019-11-20 2019-11-20 Assembled clean operating room Pending CN110778160A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911140883.5A CN110778160A (en) 2019-11-20 2019-11-20 Assembled clean operating room

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911140883.5A CN110778160A (en) 2019-11-20 2019-11-20 Assembled clean operating room

Publications (1)

Publication Number Publication Date
CN110778160A true CN110778160A (en) 2020-02-11

Family

ID=69391871

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911140883.5A Pending CN110778160A (en) 2019-11-20 2019-11-20 Assembled clean operating room

Country Status (1)

Country Link
CN (1) CN110778160A (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114352075A (en) * 2021-12-14 2022-04-15 惠瑞净化科技(江苏)有限公司 Installation method and structure of large-space lithium battery clean room
CN114352075B (en) * 2021-12-14 2024-04-26 惠瑞净化科技(江苏)有限公司 Installation method and structure of large-space lithium battery clean room

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN114352075A (en) * 2021-12-14 2022-04-15 惠瑞净化科技(江苏)有限公司 Installation method and structure of large-space lithium battery clean room
CN114352075B (en) * 2021-12-14 2024-04-26 惠瑞净化科技(江苏)有限公司 Installation method and structure of large-space lithium battery clean room

Similar Documents

Publication Publication Date Title
KR20170142582A (en) A curtain wall external pannel construction structure and construction method thereof
CN108086571B (en) Edge-closing drop-stage suspended ceiling
WO2012081994A1 (en) Interlocking structure with associated modular building assembly system
CN211776163U (en) Assembled clean operating room
JP7350167B2 (en) Modular factory building
CN110778160A (en) Assembled clean operating room
CN211774828U (en) Multifunctional light steel keel and partition wall
CN110258798B (en) Mounting method of assembled column base connection node
RU2448224C2 (en) Cleat for facing plate fastening
CN112376742A (en) Assembled partition wall fossil fragments frame and partition wall
CN110872876A (en) Built-in world fossil fragments connecting piece and wall body thereof
CN111075056A (en) Multifunctional light steel keel and partition wall
CN214461687U (en) Indoor sound absorption ceiling structure
CN211774599U (en) Assembled circular arc wall corner connecting structure
CN219508915U (en) Assembled sound insulation partition plate of fast-assembling connection
JP5979038B2 (en) Fixing structure of fixing bracket and wall material
CN218970337U (en) Plug-in type connecting piece of fast-assembling composite wallboard and fast-assembling wall body
CN213019098U (en) Lamp mounting structure of decorative curtain wall
CN218406211U (en) Assembled kitchen wall connecting piece of making level
CN110872884B (en) Assembly type wall with built-in top and bottom keel connecting piece
CN214532510U (en) Mounting structure of assembled wall body and door frame
CN220035839U (en) T-shaped aluminum alloy component curtain wall convenient to install
CN215889027U (en) Assembled wall system with wallboard capable of being installed transversely and vertically in two directions
CN214144252U (en) Assembled partition wall fossil fragments frame and partition wall
CN216380395U (en) Assembled keel structure capable of quickly leveling and quickly installing wall decoration plates

Legal Events