CN110766798A - Tunnel monitoring measurement result visualization method based on laser scanning data - Google Patents

Tunnel monitoring measurement result visualization method based on laser scanning data Download PDF

Info

Publication number
CN110766798A
CN110766798A CN201911208332.8A CN201911208332A CN110766798A CN 110766798 A CN110766798 A CN 110766798A CN 201911208332 A CN201911208332 A CN 201911208332A CN 110766798 A CN110766798 A CN 110766798A
Authority
CN
China
Prior art keywords
tunnel
section
point cloud
full
visual
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201911208332.8A
Other languages
Chinese (zh)
Other versions
CN110766798B (en
Inventor
仇峰涛
杨永强
刘丹
李勇
杜雷
陈和
王凯
王浩
王蓉
董瑞
李崎
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
China Railway First Engineering Group Co Ltd
Intelligent Technology Branch of China Railway First Engineering Group Co Ltd
Original Assignee
China Railway First Engineering Group Co Ltd
Intelligent Technology Branch of China Railway First Engineering Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by China Railway First Engineering Group Co Ltd, Intelligent Technology Branch of China Railway First Engineering Group Co Ltd filed Critical China Railway First Engineering Group Co Ltd
Priority to CN201911208332.8A priority Critical patent/CN110766798B/en
Publication of CN110766798A publication Critical patent/CN110766798A/en
Application granted granted Critical
Publication of CN110766798B publication Critical patent/CN110766798B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06TIMAGE DATA PROCESSING OR GENERATION, IN GENERAL
    • G06T17/00Three dimensional [3D] modelling, e.g. data description of 3D objects
    • G06T17/10Constructive solid geometry [CSG] using solid primitives, e.g. cylinders, cubes
    • GPHYSICS
    • G01MEASURING; TESTING
    • G01CMEASURING DISTANCES, LEVELS OR BEARINGS; SURVEYING; NAVIGATION; GYROSCOPIC INSTRUMENTS; PHOTOGRAMMETRY OR VIDEOGRAMMETRY
    • G01C7/00Tracing profiles
    • G01C7/06Tracing profiles of cavities, e.g. tunnels
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06FELECTRIC DIGITAL DATA PROCESSING
    • G06F16/00Information retrieval; Database structures therefor; File system structures therefor
    • G06F16/20Information retrieval; Database structures therefor; File system structures therefor of structured data, e.g. relational data
    • G06F16/26Visual data mining; Browsing structured data

Abstract

The invention discloses a method for visualizing a tunnel monitoring measurement result based on laser scanning data, which comprises the following steps: firstly, acquiring a three-dimensional point cloud outline of a tunnel; secondly, index storage of point cloud unit files; thirdly, visualizing the point cloud unit file; fourthly, acquiring full-section resolving parameters; fifthly, resolving the full section of the tunnel and establishing a visual full section database; sixthly, generating a tunnel roaming video; and seventhly, visualizing the monitoring and measuring result of the tunnel full-section data. According to the method, the point cloud unit file index storage is established, the rapid and smooth browsing of the large-scale tunnel is guaranteed, the full section of the tunnel is resolved by obtaining full section resolving parameters, a visual full section database is established, the diameter convergence, the slab staggering, the staggered joint and the three-dimensional displacement are displayed on a BIM (building information modeling) model of a tunnel segment, deformation monitoring and construction conditions in the tunnel are integrated into the tunnel, illumination and manual modeling are not needed, the video definition is high, and the visual guidance, acceptance and monitoring of the tunnel full section data monitoring and measuring result are achieved.

Description

Tunnel monitoring measurement result visualization method based on laser scanning data
Technical Field
The invention belongs to the technical field of visualization of tunnel monitoring measurement results, and particularly relates to a method for visualizing tunnel monitoring measurement results based on laser scanning data.
Background
The subway shield tunnel needs to provide monitoring and measuring data in both the construction period and the operation period so as to guide the tunnel construction and carry out safety protection. At present, for monitoring, deformation detection and the like in the fields of large civil engineering and the like, there are modes based on manual detection, based on stereoscopic vision detection, based on laser scanning detection and the like. The manual detection can obtain a high-precision result by means of a high-precision measuring instrument, such as a level gauge, a total station and the like, but has the defects of low efficiency, high labor intensity and the like, and the automatic data processing and report generation of the result have certain complexity; based on stereoscopic vision detection, after left and right images of a region to be detected are acquired through a binocular camera, contour, position and depth information of an object to be detected is acquired through threshold segmentation, feature point detection, extraction, stereoscopic matching and the like. The laser scanning technology can obtain a large amount of coordinate point cloud, laser reflectivity and other information of the object surface, quickly reconstruct the object outline, generate a gray image of the object and the like, has the advantages of high speed, high precision, small influence of weather change, strong robustness and the like, and is gradually applied to the field of large-scale engineering, such as subway tunnel detection and the like. At present, the tunnel is detected based on laser scanning, usually, algorithm processing analysis is directly carried out on point clouds, but the integration level of software and hardware for laser data processing is not high, the display of results is not visual enough, and simplicity and usability cannot be achieved.
Disclosure of Invention
The technical problem to be solved by the present invention is to provide a method for visualizing a measurement result of tunnel monitoring based on laser scanning data, the rapid and smooth browsing of the large-scale tunnel is ensured by establishing the point cloud unit file index storage, the full-section calculation parameters are obtained to calculate the full-section of the tunnel and establish a visual full-section database, diameter convergence, slab staggering, seam staggering and three-dimensional displacement are displayed on a BIM model of the tunnel segment, the display is visual, the tunnel deformation monitoring and construction working condition monitoring system can be integrated into a tunnel, has the effects of visualization, high definition, authenticity, high efficiency and the like, does not need illumination, manual modeling and comprehensive monitoring range, is high in video definition, realizes the visualization guidance, acceptance and monitoring of tunnel full-section data monitoring and measuring results, and is convenient to popularize and use.
In order to solve the technical problems, the invention adopts the technical scheme that: a tunnel monitoring measurement result visualization method based on laser scanning data is characterized by comprising the following steps:
step one, acquiring a tunnel three-dimensional point cloud outline: erecting a laser scanner on a movable carrier, setting the moving speed of the movable carrier, presetting the scanning resolution and sampling frequency of the laser scanner, covering the inner wall of a tunnel and moving and acquiring cross-section point clouds with laser reflectivity on the inner wall of the tunnel along the mileage direction of the tunnel by using a 2D cross-section spiral scanning mode of the laser scanner, wherein the scanning point coordinate of each cross-section point cloud takes the center of the laser scanner as the center of a circle, and simultaneously combining the ring number information corresponding to a tunnel lining segment with the scanning point coordinate of the cross-section point cloud so as to obtain the three-dimensional point cloud profile of the tunnel;
step two, point cloud unit file index storage: partitioning the obtained tunnel three-dimensional point cloud contour original points, establishing point cloud unit files, establishing unique point cloud unit file index identifications for the point cloud unit files, and adopting an Aliskian object storage service interface standard to orderly store, share and backup the tunnel three-dimensional point cloud contour original points;
step three, point cloud unit file visualization: resampling and thinning the point cloud unit file, exporting the point cloud unit file into an AutoCAD graphic file, and visualizing the point cloud unit file in a slicing mode;
step four, acquiring full-section resolving parameters: constructing a gray matrix corresponding to the point cloud unit file after rarefaction according to reflection intensity information corresponding to the point cloud unit file after rarefaction, generating a corresponding initial image, and manually marking a circular seam ring number and an assembling block seam position so as to obtain a full-section resolving parameter corresponding to each scanning section, wherein the full-section resolving parameter comprises mileage information, a design diameter, a partitioning angle, operation time, an operation sequence and a shield interval name;
step five, resolving the full section of the tunnel and establishing a visual full section database: performing steady estimation on the point cloud scanning points of the cross section, eliminating rough difference points, and acquiring the coordinates of the cross section scanning points and the diameter of the cross section by using the center of the cross section of the tunnel as the center of a circle through circle center fitting and diameter convergence processing; independently fitting arcs according to the diameter of the section and the blocking angle, then obtaining slab staggering and seam staggering in the corresponding section, extracting clearance convergence deformation data, and performing limit detection and full-section calculation;
storing results of the full-section calculation in a mode of staging and block indexing, generating a dwg file of a section graph or an xls report of the full-section calculation graph, drawing a diameter convergence curve and a single-ring duration change curve according to a tunnel mileage or ring number sequence, displaying the diameter convergence, staggered platform and staggered seam and three-dimensional displacement on a BIM (building information modeling) model of a tunnel segment, performing visual display, and establishing a visual full-section database;
step six, generating a tunnel roaming video, wherein the process is as follows:
601, calculating a theoretical value of the number of section point cloud scanning lines on a ring of fixed length of a tunnel lining segment in a visual full-section database according to the moving speed of a moving carrier and the sampling frequency of a laser scanner, comparing the theoretical value of the number of the section point cloud scanning lines with the number of actual section point cloud scanning lines of a ring of tunnel lining segments corresponding to the visual full-section database, and interpolating the number of the section point cloud scanning lines with uneven number of the actual section point cloud scanning lines of the ring of tunnel lining segments in the visual full-section database to obtain each section point cloud scanning line with even distribution in the tunnel mileage direction;
step 602, performing circle center orthographic projection on the reflection intensity of the cross-section point cloud according to the reflection intensity information of the corresponding cross-section point cloud to obtain the gray value of each scanning point in the cross-section point cloud;
603, constructing an image gray matrix according to gray information corresponding to each section point cloud scanning line on each ring of tunnel lining segment, and adding a geographical label to generate an orthophotograph of each ring of the tunnel lining segment;
step 604, selecting a visual angle, setting a visual field angle FOV and a closest visual distance and a farthest visual distance corresponding to different positions of the tunnel by taking human eyes as the visual angle, taking a projection plane corresponding to the farthest visual distance as a perspective projection plane of the perspective projection, and performing the perspective projection according to a formula
Figure BDA0002297440480000031
To obtainCalculating the coordinate value rho of the ith section point cloud scanning line coordinate in the perspective range of the tunnel on the perspective projection planeiWherein r isiScanning line coordinates of point cloud of ith section in the perspective range of the tunnel, wherein l is a viewing angle point and a perspective projectionFixed distance of shadow plane, /)iThe distance between the viewing angle point and the section of the ith section point cloud scanning line in the perspective range of the tunnel;
gradually transitioning from the nearest visible distance to the farthest visible distance in the perspective range of the tunnel, carrying out perspective projection on each section point cloud scanning line in the perspective range of the tunnel, and corresponding coordinates and gray scale information of each section point cloud scanning line in the perspective projection plane in the perspective range of the tunnel one by one to generate a frame of perspective projection image;
605, repeatedly circulating 604, and generating a frame-by-frame perspective projection image of a tunnel lining segment interval corresponding to the visual full-section database along the direction of the mileage of the tunnel;
606, setting the number of frames of the perspective projection images output per second, and continuously outputting the perspective projection images frame by frame according to a time sequence to generate a roaming video of a visual full-section database corresponding to a tunnel lining segment interval along the tunnel mileage direction and simulating the human eye visual angle;
step seven, visualization of monitoring and measuring results of the tunnel full-section data: establishing a shield remote monitoring center, synchronizing a visual full-section database to a cloud server through REST API, and realizing long-term recording and inquiring of visual monitoring measurement results of the whole process of tunnel shield segments; the roaming video with the geographic labels is uploaded to a cloud server and published as a network map service, and a shield remote monitoring center carries out remote access to realize visual guidance, acceptance and monitoring of tunnel full-section data monitoring and measuring results.
The method for visualizing the tunnel monitoring measurement result based on the laser scanning data is characterized by comprising the following steps of: and step seven, uploading the roaming video with the geographic tag to a cloud server through a seven-cow cloud video streaming media module.
The method for visualizing the tunnel monitoring measurement result based on the laser scanning data is characterized by comprising the following steps of: and in the first step, the laser scanner is a three-dimensional laser scanner Faro or a Z + F9012 three-dimensional laser scanner.
The method for visualizing the tunnel monitoring measurement result based on the laser scanning data is characterized by comprising the following steps of: in the third step, the point cloud unit file is resampled and thinned at intervals in a thinning mode of 1024 points/line and 5-10 lines/second.
The method for visualizing the tunnel monitoring measurement result based on the laser scanning data is characterized by comprising the following steps of: in step 604, the view angle is any three-dimensional view angle of 360 degrees, and a frame of perspective projection image with any three-dimensional view angle of 360 degrees is generated; in step 606, the perspective projection images frame by frame are continuously output according to the time sequence, and a 360-degree arbitrary three-dimensional view roaming video simulating the human eye view along the tunnel mileage direction is generated.
The method for visualizing the tunnel monitoring measurement result based on the laser scanning data is characterized by comprising the following steps of: the moving speed of the moving carrier in the first step is 3 km/h-10 km/h; the scanning resolution of the laser scanner is 3-5; the sampling frequency of the laser scanner is 50 Hz-200 Hz; in step 606, outputting 25-35 frames per second of perspective projection images is set.
The method for visualizing the tunnel monitoring measurement result based on the laser scanning data is characterized by comprising the following steps of: in step 603, the geographic labels comprise tunnel lining segment ring numbers, mileage, deformation, disease range and facility equipment; the disease range comprises point diseases, linear diseases and surface diseases; before generating a frame of perspective projection image in step 604, vectorization processing needs to be performed on the generated orthographic projection image of each ring of the tunnel lining segment to generate a tunnel image thematic map.
Compared with the prior art, the invention has the following advantages:
1. according to the method, a 2D section spiral scanning mode of a laser scanner is utilized, the section point cloud with laser reflectivity on the inner wall of the tunnel is covered and movably collected along the mileage direction of the tunnel, the ring number information corresponding to the tunnel lining segment is combined with the scanning point coordinates of the section point cloud, so that the three-dimensional point cloud profile of the tunnel is obtained, illumination and manual modeling are not needed, and the quick and smooth browsing of a large-scale tunnel is ensured by establishing point cloud unit file index storage, so that the method is convenient to popularize and use.
2. According to the method, the full-section calculation parameters are obtained, the full-section calculation of the tunnel is carried out, a visual full-section database is established, diameter convergence, slab staggering, seam staggering and three-dimensional displacement are displayed on a BIM (building information modeling) model of the tunnel segment, the display is visual, and when a laser scanner is installed, the instrument center of the laser scanner cannot be guaranteed to be located at the center of the tunnel section, so that data of the scanning point coordinates of each collected point cloud of the section point with the instrument center of the laser scanner as the center of a circle needs to be converted into the coordinates of the scanning point with the center of the tunnel section as the center of a circle, and the correction of; acquiring the reflection intensity information of the corresponding cross-section point cloud according to the laser reflectivity of each cross-section point cloud, performing circle center orthographic projection on the reflection intensity of the cross-section point cloud to generate an orthographic image of each ring of the tunnel lining segment, gradually transitioning from the nearest visible distance to the farthest visible distance in the perspective range of the tunnel, perspective projection is carried out on each section point cloud scanning line in the perspective range of the tunnel, coordinates and gray information of each section point cloud scanning line in the perspective projection plane in the tunnel are in one-to-one correspondence, a frame of perspective projection image and a static sequence image are generated and displayed rapidly and continuously, so that a motion false image is formed, by setting the number of image frames moving every second, the roaming video can be generated, the space perspective image of an object can be vividly displayed, and the method is visual, clear, real, high in efficiency, reliable and stable and good in using effect.
3. The method has simple steps, and the visual full-section database is synchronized to the cloud server through the REST API, so that the visual monitoring measurement result of the whole process of recording and inquiring the tunnel shield segment for a long time is realized; the roaming video with the geographic labels is uploaded to a cloud server and published as a network map service, and a shield remote monitoring center carries out remote access to realize visual guidance, acceptance and monitoring of tunnel full-section data monitoring and measuring results, so that the method is convenient to popularize and use.
In conclusion, the invention ensures the quick and smooth browsing of the large-scale tunnel by establishing the point cloud unit file index storage, solves the full section of the tunnel by acquiring the full section solution parameters and establishes the visual full section database, displays the diameter convergence, slab staggering, seam staggering and three-dimensional displacement on the BIM model of the tunnel segment, displays the diameter convergence, slab staggering and seam staggering, displays the diameter convergence, the slab staggering and the three-dimensional displacement on the BIM model of the tunnel segment, has visual display, can integrate the deformation monitoring and the construction working condition in the tunnel into the tunnel, has the effects of visualization, high definition, authenticity, high efficiency and the like, does not need illumination, does not need manual modeling, has high video definition, has comprehensive monitoring range, realizes the visual guidance, acceptance and monitoring of the monitoring and measuring result of the.
The technical solution of the present invention is further described in detail by the accompanying drawings and embodiments.
Drawings
FIG. 1 is a block diagram of a process flow of the method of the present invention.
FIG. 2 is a schematic diagram of a visual gray scale of a point cloud unit file according to the present invention.
FIG. 3 is a schematic diagram of a scanned cross-section of the present invention for manually marking the ring number of the circular seam and the joint of the assembly block.
FIG. 4 is a schematic diagram of the calculation of slab staggering and slab staggering in the full-section solution of the tunnel.
FIG. 5 is a gray scale schematic view of an orthophotomap of a tunnel lining segment interval according to the present invention.
FIG. 6 is a schematic view of a frame of perspective projection image according to the present invention.
Detailed Description
As shown in fig. 1, the method for visualizing the measurement result of tunnel monitoring based on the laser scanning data of the present invention includes the following steps:
step one, acquiring a tunnel three-dimensional point cloud outline: erecting a laser scanner on a movable carrier, setting the moving speed of the movable carrier, presetting the scanning resolution and sampling frequency of the laser scanner, covering the inner wall of a tunnel and moving and acquiring cross-section point clouds with laser reflectivity on the inner wall of the tunnel along the mileage direction of the tunnel by using a 2D cross-section spiral scanning mode of the laser scanner, wherein the scanning point coordinate of each cross-section point cloud takes the center of the laser scanner as the center of a circle, and simultaneously combining the ring number information corresponding to a tunnel lining segment with the scanning point coordinate of the cross-section point cloud so as to obtain the three-dimensional point cloud profile of the tunnel;
in this embodiment, the laser scanner in the first step is a three-dimensional laser scanner Faro or a Z + F9012 three-dimensional laser scanner.
In the embodiment, the moving speed of the moving carrier in the first step is 3 km/h-10 km/h; the scanning resolution of the laser scanner is 3-5; the sampling frequency of the laser scanner is 50 Hz-200 Hz; in step 606, outputting 25-35 frames per second of perspective projection images is set.
The method includes the steps that a 2D section spiral scanning mode of a laser scanner is utilized, section point clouds with laser reflectivity on the inner wall of a tunnel are covered and collected in a moving mode along the mileage direction of the tunnel, ring number information corresponding to tunnel lining segments is combined with scanning point coordinates of the section point clouds, accordingly, a three-dimensional point cloud profile of the tunnel is obtained, illumination is not needed, manual modeling is not needed, and quick and smooth browsing of a large-scale tunnel is guaranteed by establishing point cloud unit file index storage.
Step two, point cloud unit file index storage: partitioning the obtained tunnel three-dimensional point cloud contour original points, establishing point cloud unit files, establishing unique point cloud unit file index identifications for the point cloud unit files, and adopting an Aliskian object storage service interface standard to orderly store, share and backup the tunnel three-dimensional point cloud contour original points;
when the method is actually used, the original points of the obtained tunnel three-dimensional point cloud profile are partitioned, a point cloud unit file is established, and a unique GUID point cloud unit file index identification is established for the point cloud unit file.
Step three, point cloud unit file visualization: resampling and thinning the point cloud unit file, exporting the point cloud unit file into an AutoCAD graphic file, and visualizing the point cloud unit file in a slicing mode;
as shown in fig. 2, in the present embodiment, in the third step, the point cloud unit file is resampled and thinned at intervals in a thinning mode of 1024 points/line and 5-10 lines/second, resampled and thinned to be exported as an AutoCAD graphic file, and the point cloud unit file is sliced and visualized.
Step four, acquiring full-section resolving parameters: constructing a gray matrix corresponding to the point cloud unit file after rarefaction according to reflection intensity information corresponding to the point cloud unit file after rarefaction, generating a corresponding initial image, and manually marking a circular seam ring number and an assembling block seam position so as to obtain a full-section resolving parameter corresponding to each scanning section, wherein the full-section resolving parameter comprises mileage information, a design diameter, a partitioning angle, operation time, an operation sequence and a shield interval name, and is shown in FIG. 3;
step five, resolving the full section of the tunnel and establishing a visual full section database: performing steady estimation on the point cloud scanning points of the cross section, eliminating rough difference points, and acquiring the coordinates of the cross section scanning points and the diameter of the cross section by using the center of the cross section of the tunnel as the center of a circle through circle center fitting and diameter convergence processing; separately fitting arcs according to the diameter of the section and the blocking angle, then obtaining staggered platforms and staggered joints in the corresponding section, extracting clearance convergence deformation data as shown in figure 4, and performing limit detection and full-section calculation;
storing results of the full-section calculation in a mode of staging and block indexing, generating a dwg file of a section graph or an xls report of the full-section calculation graph, drawing a diameter convergence curve and a single-ring duration change curve according to a tunnel mileage or ring number sequence, displaying the diameter convergence, staggered platform and staggered seam and three-dimensional displacement on a BIM (building information modeling) model of a tunnel segment, performing visual display, and establishing a visual full-section database;
it should be noted that, by acquiring full-section calculation parameters, a full-section calculation and visual full-section database is established for the tunnel, diameter convergence, slab staggering, seam staggering and three-dimensional displacement are displayed on a BIM model of a tunnel segment, the display is visual, and when a laser scanner is installed, the instrument center of the laser scanner cannot be ensured to be located at the center of the tunnel section, so that data of scanning point coordinates of each collected point cloud of the section point with the instrument center of the laser scanner as the center of a circle needs to be converted into section scanning point coordinates with the center of the tunnel section as the center of a circle, and the correction of an image is realized; according to the laser reflectivity of each cross-section point cloud, the reflection intensity information of the corresponding cross-section point cloud is obtained, circle center orthographic projection is carried out on the reflection intensity of the cross-section point cloud, an orthographic image of each ring of a tunnel lining segment is generated, the nearest visible distance in the perspective range of the tunnel is gradually transited to the farthest visible distance, perspective projection is carried out on each cross-section point cloud scanning line in the perspective range of the tunnel, the coordinate and the gray scale information of each cross-section point cloud scanning line in the perspective projection plane in the perspective range of the tunnel are in one-to-one correspondence, a perspective projection image is generated, a static sequence image is displayed rapidly and continuously, the motion false image is formed, and by setting the number of image frames moving every second, a roaming video can be generated, the space perspective image of an object is vividly displayed, and the method is visual, clear, real.
Step six, generating a tunnel roaming video, wherein the process is as follows:
601, calculating a theoretical value of the number of section point cloud scanning lines on a ring of fixed length of a tunnel lining segment in a visual full-section database according to the moving speed of a moving carrier and the sampling frequency of a laser scanner, comparing the theoretical value of the number of the section point cloud scanning lines with the number of actual section point cloud scanning lines of a ring of tunnel lining segments corresponding to the visual full-section database, and interpolating the number of the section point cloud scanning lines with uneven number of the actual section point cloud scanning lines of the ring of tunnel lining segments in the visual full-section database to obtain each section point cloud scanning line with even distribution in the tunnel mileage direction;
step 602, performing circle center orthographic projection on the reflection intensity of the cross-section point cloud according to the reflection intensity information of the corresponding cross-section point cloud to obtain the gray value of each scanning point in the cross-section point cloud;
603, constructing an image gray matrix according to gray information corresponding to each section point cloud scanning line on each ring of tunnel lining segment, adding a geographic label, and generating an ortho-image map of each ring of the tunnel lining segment, wherein as shown in fig. 5, the ortho-image map of each ring of the tunnel lining segment is in a GeoTIFF format, so that a tunnel scene is displayed more visually, and the real status of a tunnel wall with a measurable function is obtained;
in this embodiment, the geographic labels in step 603 include tunnel lining segment ring number, mileage, deformation, disease range, and facility equipment; the disease range comprises point diseases, linear diseases and surface diseases; before generating a frame of perspective projection image in step 604, vectorization processing needs to be performed on the generated orthographic projection image of each ring of the tunnel lining segment to generate a tunnel image thematic map.
The point diseases are formed by illuminating lamps, distribution boxes and fire-fighting faucets in tunnels; the linear diseases are formed by cables, pipelines, cracks and escape safety platforms in the tunnel; the planar diseases are formed by water leakage in the tunnel, concrete defects and carbon fiber reinforcement, the forward projection image in the GeoTIFF format is generated into an image pyramid through a MapControl component of ArcEngine, the size of image data is reduced, details are not lost, and vectorization processing is carried out to generate a tunnel image thematic image.
Step 604, selecting a visual angle, setting a visual field angle FOV and a closest visual distance and a farthest visual distance corresponding to different positions of the tunnel by taking human eyes as the visual angle, taking a projection plane corresponding to the farthest visual distance as a perspective projection plane of the perspective projection, and performing the perspective projection according to a formula
Figure BDA0002297440480000101
To obtain
Figure BDA0002297440480000102
Calculating the coordinate value rho of the ith section point cloud scanning line coordinate in the perspective range of the tunnel on the perspective projection planeiWherein r isiThe point cloud scanning line coordinate of the ith section in the perspective range of the tunnel, wherein l is the fixed distance between a viewing angle point and a perspective projection planeiThe distance between the viewing angle point and the section of the ith section point cloud scanning line in the perspective range of the tunnel;
gradually transitioning from the nearest visible distance to the farthest visible distance in the perspective range of the tunnel, performing perspective projection on each section point cloud scanning line in the perspective range of the tunnel, and corresponding coordinates and gray scale information of each section point cloud scanning line in the perspective projection plane in the perspective range of the tunnel one by one to generate a frame of perspective projection image, as shown in fig. 6;
605, repeatedly circulating 604, and generating a frame-by-frame perspective projection image of a tunnel lining segment interval corresponding to the visual full-section database along the direction of the mileage of the tunnel;
606, setting the number of frames of the perspective projection images output per second, and continuously outputting the perspective projection images frame by frame according to a time sequence to generate a roaming video of a visual full-section database corresponding to a tunnel lining segment interval along the tunnel mileage direction and simulating the human eye visual angle;
in this embodiment, in step 604, the view angle is any three-dimensional view angle of 360 degrees, and a frame of perspective projection image of any three-dimensional view angle of 360 degrees is generated; in step 606, the perspective projection images frame by frame are continuously output according to the time sequence, and a 360-degree arbitrary three-dimensional view roaming video simulating the human eye view along the tunnel mileage direction is generated.
Step seven, visualization of monitoring and measuring results of the tunnel full-section data: establishing a shield remote monitoring center, synchronizing a visual full-section database to a cloud server through REST API, and realizing long-term recording and inquiring of visual monitoring measurement results of the whole process of tunnel shield segments; the roaming video with the geographic labels is uploaded to a cloud server and published as a network map service, and a shield remote monitoring center carries out remote access to realize visual guidance, acceptance and monitoring of tunnel full-section data monitoring and measuring results.
In this embodiment, the roaming video with the geographic tag in the seventh step is uploaded to the cloud server through the heptacow cloud video streaming media module.
When the invention is used, the result of the full-section calculation is stored in a staged and blocked indexing mode, a dwg file of a section graph or an xls report of the full-section calculation graph is generated, a diameter convergence curve and a single-ring time-duration change curve are drawn according to a tunnel mileage or ring number sequence, a risk source and a process record of a stroke in the monitoring process can be conveniently checked and recorded at any time by a first-line worker, a technician, a monitoring personnel and an owner, the effective field condition monitoring and tunnel protection cannot be realized on the video monitoring of the tunnel at present, a large amount of manpower and time are consumed by adopting a manual modeling mode, the invention directly generates a roaming video from laser point cloud, the manpower investment of 'segment modeling and blocked mapping' in the traditional modeling method is greatly reduced, the tunnel can more intuitively reflect the current situation, and the labor intensity of field monitoring can be greatly reduced, the operation cost is saved, the method is suitable for various complex actual environments, the monitoring range is comprehensive, and the visual guidance, acceptance inspection and monitoring of the tunnel full-section data monitoring and measuring result are realized.
The above description is only a preferred embodiment of the present invention, and is not intended to limit the present invention, and all simple modifications, changes and equivalent structural changes made to the above embodiment according to the technical spirit of the present invention still fall within the protection scope of the technical solution of the present invention.

Claims (7)

1. A tunnel monitoring measurement result visualization method based on laser scanning data is characterized by comprising the following steps:
step one, acquiring a tunnel three-dimensional point cloud outline: erecting a laser scanner on a movable carrier, setting the moving speed of the movable carrier, presetting the scanning resolution and sampling frequency of the laser scanner, covering the inner wall of a tunnel and moving and acquiring cross-section point clouds with laser reflectivity on the inner wall of the tunnel along the mileage direction of the tunnel by using a 2D cross-section spiral scanning mode of the laser scanner, wherein the scanning point coordinate of each cross-section point cloud takes the center of the laser scanner as the center of a circle, and simultaneously combining the ring number information corresponding to a tunnel lining segment with the scanning point coordinate of the cross-section point cloud so as to obtain the three-dimensional point cloud profile of the tunnel;
step two, point cloud unit file index storage: partitioning the obtained tunnel three-dimensional point cloud contour original points, establishing point cloud unit files, establishing unique point cloud unit file index identifications for the point cloud unit files, and orderly storing, sharing and backing up the tunnel three-dimensional point cloud contour original points by adopting an Aliskian object storage service interface standard;
step three, point cloud unit file visualization: resampling and thinning the point cloud unit file, exporting the point cloud unit file into an AutoCAD graphic file, and visualizing the point cloud unit file in a slicing mode;
step four, acquiring full-section resolving parameters: constructing a gray matrix corresponding to the point cloud unit file after rarefaction according to reflection intensity information corresponding to the point cloud unit file after rarefaction, generating a corresponding initial image, and manually marking a circular seam ring number and an assembling block seam position so as to obtain a full-section resolving parameter corresponding to each scanning section, wherein the full-section resolving parameter comprises mileage information, a design diameter, a partitioning angle, operation time, an operation sequence and a shield interval name;
step five, resolving the full section of the tunnel and establishing a visual full section database: performing steady estimation on the point cloud scanning points of the cross section, eliminating rough difference points, and acquiring the coordinates of the cross section scanning points and the diameter of the cross section by using the center of the cross section of the tunnel as the center of a circle through circle center fitting and diameter convergence processing; independently fitting arcs according to the diameter of the section and the blocking angle, then obtaining slab staggering and seam staggering in the corresponding section, extracting clearance convergence deformation data, and performing limit detection and full-section calculation;
storing results of the full-section calculation in a mode of staging and block indexing, generating a dwg file of a section graph or an xls report of the full-section calculation graph, drawing a diameter convergence curve and a single-ring duration change curve according to a tunnel mileage or ring number sequence, displaying the diameter convergence, staggered platform and staggered seam and three-dimensional displacement on a BIM (building information modeling) model of a tunnel segment, performing visual display, and establishing a visual full-section database;
step six, generating a tunnel roaming video, wherein the process is as follows:
601, calculating a theoretical value of the number of section point cloud scanning lines on a ring of fixed length of a tunnel lining segment in a visual full-section database according to the moving speed of a moving carrier and the sampling frequency of a laser scanner, comparing the theoretical value of the number of the section point cloud scanning lines with the number of actual section point cloud scanning lines of a ring of tunnel lining segments corresponding to the visual full-section database, and interpolating the number of the section point cloud scanning lines with uneven number of the actual section point cloud scanning lines of the ring of tunnel lining segments in the visual full-section database to obtain each section point cloud scanning line with even distribution in the tunnel mileage direction;
step 602, performing circle center orthographic projection on the reflection intensity of the cross-section point cloud according to the reflection intensity information of the corresponding cross-section point cloud to obtain the gray value of each scanning point in the cross-section point cloud;
603, constructing an image gray matrix according to gray information corresponding to each section point cloud scanning line on each ring of tunnel lining segment, and adding a geographical label to generate an orthophotograph of each ring of the tunnel lining segment;
step 604, selecting a visual angle, setting a visual field angle FOV and a closest visual distance and a farthest visual distance corresponding to different positions of the tunnel by taking human eyes as the visual angle, taking a projection plane corresponding to the farthest visual distance as a perspective projection plane of the perspective projection, and performing the perspective projection according to a formula
Figure FDA0002297440470000021
To obtain
Figure FDA0002297440470000022
Calculating the coordinate value rho of the ith section point cloud scanning line coordinate in the perspective range of the tunnel on the perspective projection planeiWherein r isiThe point cloud scanning line coordinate of the ith section in the perspective range of the tunnel, wherein l is the fixed distance between a viewing angle point and a perspective projection planeiThe distance between the viewing angle point and the section of the ith section point cloud scanning line in the perspective range of the tunnel;
gradually transitioning from the nearest visible distance to the farthest visible distance in the perspective range of the tunnel, carrying out perspective projection on each section point cloud scanning line in the perspective range of the tunnel, and corresponding coordinates and gray scale information of each section point cloud scanning line in the perspective projection plane in the perspective range of the tunnel one by one to generate a frame of perspective projection image;
605, repeatedly circulating 604, and generating a frame-by-frame perspective projection image of a tunnel lining segment interval corresponding to the visual full-section database along the direction of the mileage of the tunnel;
606, setting the number of frames of the perspective projection images output per second, and continuously outputting the perspective projection images frame by frame according to a time sequence to generate a roaming video of a visual full-section database corresponding to a tunnel lining segment interval along the tunnel mileage direction and simulating the human eye visual angle;
step seven, visualization of monitoring and measuring results of the tunnel full-section data: establishing a shield remote monitoring center, synchronizing a visual full-section database to a cloud server through REST API, and realizing long-term recording and inquiring of visual monitoring measurement results of the whole process of tunnel shield segments; the roaming video with the geographic labels is uploaded to a cloud server and published as a network map service, and a shield remote monitoring center carries out remote access to realize visual guidance, acceptance and monitoring of tunnel full-section data monitoring and measuring results.
2. The method for visualizing the measurement result of tunnel monitoring based on the laser scanning data as claimed in claim 1, wherein: and step seven, uploading the roaming video with the geographic tag to a cloud server through a seven-cow cloud video streaming media module.
3. The method for visualizing the measurement result of tunnel monitoring based on the laser scanning data as claimed in claim 1, wherein: and in the first step, the laser scanner is a three-dimensional laser scanner Faro or a Z + F9012 three-dimensional laser scanner.
4. The method for visualizing the measurement result of tunnel monitoring based on the laser scanning data as claimed in claim 1, wherein: in the third step, the point cloud unit file is resampled and thinned at intervals in a thinning mode of 1024 points/line and 5-10 lines/second.
5. The method for visualizing the measurement result of tunnel monitoring based on the laser scanning data as claimed in claim 1, wherein: in step 604, the view angle is any three-dimensional view angle of 360 degrees, and a frame of perspective projection image with any three-dimensional view angle of 360 degrees is generated; in step 606, the perspective projection images frame by frame are continuously output according to the time sequence, and a 360-degree arbitrary three-dimensional view roaming video simulating the human eye view along the tunnel mileage direction is generated.
6. The method for visualizing the measurement result of tunnel monitoring based on the laser scanning data as claimed in claim 1, wherein: the moving speed of the moving carrier in the first step is 3 km/h-10 km/h; the scanning resolution of the laser scanner is 3-5; the sampling frequency of the laser scanner is 50 Hz-200 Hz; in step 606, outputting 25-35 frames per second of perspective projection images is set.
7. The method for visualizing the measurement result of tunnel monitoring based on the laser scanning data as claimed in claim 1, wherein: in step 603, the geographic labels comprise tunnel lining segment ring numbers, mileage, deformation, disease range and facility equipment; the disease range comprises point diseases, linear diseases and surface diseases; before generating a frame of perspective projection image in step 604, vectorization processing needs to be performed on the generated orthographic projection image of each ring of the tunnel lining segment to generate a tunnel image thematic map.
CN201911208332.8A 2019-11-30 2019-11-30 Tunnel monitoring measurement result visualization method based on laser scanning data Active CN110766798B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201911208332.8A CN110766798B (en) 2019-11-30 2019-11-30 Tunnel monitoring measurement result visualization method based on laser scanning data

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201911208332.8A CN110766798B (en) 2019-11-30 2019-11-30 Tunnel monitoring measurement result visualization method based on laser scanning data

Publications (2)

Publication Number Publication Date
CN110766798A true CN110766798A (en) 2020-02-07
CN110766798B CN110766798B (en) 2023-02-14

Family

ID=69340513

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201911208332.8A Active CN110766798B (en) 2019-11-30 2019-11-30 Tunnel monitoring measurement result visualization method based on laser scanning data

Country Status (1)

Country Link
CN (1) CN110766798B (en)

Cited By (18)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111336990A (en) * 2020-03-27 2020-06-26 南京航空航天大学 Tunnel section convergence rapid analysis method and device
CN111402171A (en) * 2020-03-24 2020-07-10 上海勃发空间信息技术有限公司 Point cloud projection correction method based on tunnel general section
CN111456738A (en) * 2020-03-06 2020-07-28 中国十七冶集团有限公司 Tunnel excavation method based on step method
CN111663783A (en) * 2020-07-16 2020-09-15 广州城建职业学院 Assembly type building concrete pouring device based on BIM
CN111811420A (en) * 2020-07-16 2020-10-23 山东大学 Tunnel three-dimensional contour integral absolute deformation monitoring method and system
CN112197743A (en) * 2020-10-10 2021-01-08 北京工商大学 Subway tunnel contour-envelope shortest distance analysis method
CN112988079A (en) * 2021-05-07 2021-06-18 成都奥伦达科技有限公司 Management method and system for ultra-mass point clouds
CN113091639A (en) * 2021-04-01 2021-07-09 浙江华东测绘与工程安全技术有限公司 Shield tunnel segment dislocation extraction method
CN113420962A (en) * 2021-05-31 2021-09-21 中铁工程服务有限公司 Scanning detection method and device for shield subway tunnel segment and storage medium
CN113601505A (en) * 2021-08-05 2021-11-05 中铁工程装备集团有限公司 Intelligent control method and system for multifunctional installation trolley
CN113742505A (en) * 2021-08-30 2021-12-03 武汉数趣信息科技有限公司 Mass synthetic aperture radar interferometric measurement (InSAR) data online visualization method
CN113837996A (en) * 2021-08-17 2021-12-24 北京工商大学 Subway tunnel defect automatic detection method supporting manual verification
CN114046747A (en) * 2021-06-03 2022-02-15 北京工业大学 Intelligent shield tunnel inter-ring dislocation analysis method based on moving point cloud data
CN114370828A (en) * 2021-12-28 2022-04-19 中国铁路设计集团有限公司 Shield tunnel diameter convergence and radial slab staggering detection method based on laser scanning
CN114676474A (en) * 2022-02-16 2022-06-28 中铁建华南建设有限公司 Shield tunnel segment completion model construction method and device and computer equipment
WO2022254635A1 (en) * 2021-06-02 2022-12-08 日本電信電話株式会社 Analysis device, analysis method, and program
CN115930800A (en) * 2023-02-21 2023-04-07 西南石油大学 Tunnel face displacement field monitoring method based on three-dimensional laser point cloud
CN117274467A (en) * 2023-11-23 2023-12-22 长江水利委员会长江科学院 Dam safety monitoring multi-physical field cloud image online visualization method and system

Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010024212A1 (en) * 2008-08-29 2010-03-04 三菱電機株式会社 Bird's-eye image forming device, bird's-eye image forming method, and bird's-eye image forming program
CN102564393A (en) * 2011-12-28 2012-07-11 北京工业大学 Method for monitoring and measuring full section of tunnel through three-dimensional laser
CN109459439A (en) * 2018-12-06 2019-03-12 东南大学 A kind of Tunnel Lining Cracks detection method based on mobile three-dimensional laser scanning technique
CN110132157A (en) * 2019-05-30 2019-08-16 华中科技大学 A kind of metro safety distal end automatic monitoring and analysis system and method

Patent Citations (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2010024212A1 (en) * 2008-08-29 2010-03-04 三菱電機株式会社 Bird's-eye image forming device, bird's-eye image forming method, and bird's-eye image forming program
CN102564393A (en) * 2011-12-28 2012-07-11 北京工业大学 Method for monitoring and measuring full section of tunnel through three-dimensional laser
CN109459439A (en) * 2018-12-06 2019-03-12 东南大学 A kind of Tunnel Lining Cracks detection method based on mobile three-dimensional laser scanning technique
CN110132157A (en) * 2019-05-30 2019-08-16 华中科技大学 A kind of metro safety distal end automatic monitoring and analysis system and method

Non-Patent Citations (1)

* Cited by examiner, † Cited by third party
Title
潘国荣等: "三维激光扫描在地铁隧道变形监测中的开发应用", 《东华理工大学学报(自然科学版)》 *

Cited By (22)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN111456738A (en) * 2020-03-06 2020-07-28 中国十七冶集团有限公司 Tunnel excavation method based on step method
CN111402171A (en) * 2020-03-24 2020-07-10 上海勃发空间信息技术有限公司 Point cloud projection correction method based on tunnel general section
CN111336990A (en) * 2020-03-27 2020-06-26 南京航空航天大学 Tunnel section convergence rapid analysis method and device
CN111663783A (en) * 2020-07-16 2020-09-15 广州城建职业学院 Assembly type building concrete pouring device based on BIM
CN111811420A (en) * 2020-07-16 2020-10-23 山东大学 Tunnel three-dimensional contour integral absolute deformation monitoring method and system
CN112197743A (en) * 2020-10-10 2021-01-08 北京工商大学 Subway tunnel contour-envelope shortest distance analysis method
CN113091639A (en) * 2021-04-01 2021-07-09 浙江华东测绘与工程安全技术有限公司 Shield tunnel segment dislocation extraction method
CN112988079B (en) * 2021-05-07 2021-11-26 成都奥伦达科技有限公司 Management method and system for ultra-mass point clouds
CN112988079A (en) * 2021-05-07 2021-06-18 成都奥伦达科技有限公司 Management method and system for ultra-mass point clouds
CN113420962A (en) * 2021-05-31 2021-09-21 中铁工程服务有限公司 Scanning detection method and device for shield subway tunnel segment and storage medium
WO2022254635A1 (en) * 2021-06-02 2022-12-08 日本電信電話株式会社 Analysis device, analysis method, and program
CN114046747A (en) * 2021-06-03 2022-02-15 北京工业大学 Intelligent shield tunnel inter-ring dislocation analysis method based on moving point cloud data
CN113601505A (en) * 2021-08-05 2021-11-05 中铁工程装备集团有限公司 Intelligent control method and system for multifunctional installation trolley
CN113837996A (en) * 2021-08-17 2021-12-24 北京工商大学 Subway tunnel defect automatic detection method supporting manual verification
CN113837996B (en) * 2021-08-17 2023-09-29 北京工商大学 Automatic subway tunnel defect detection method supporting manual verification
CN113742505A (en) * 2021-08-30 2021-12-03 武汉数趣信息科技有限公司 Mass synthetic aperture radar interferometric measurement (InSAR) data online visualization method
CN114370828A (en) * 2021-12-28 2022-04-19 中国铁路设计集团有限公司 Shield tunnel diameter convergence and radial slab staggering detection method based on laser scanning
CN114676474A (en) * 2022-02-16 2022-06-28 中铁建华南建设有限公司 Shield tunnel segment completion model construction method and device and computer equipment
CN115930800A (en) * 2023-02-21 2023-04-07 西南石油大学 Tunnel face displacement field monitoring method based on three-dimensional laser point cloud
CN115930800B (en) * 2023-02-21 2023-05-05 西南石油大学 Tunnel face displacement field monitoring method based on three-dimensional laser point cloud
CN117274467A (en) * 2023-11-23 2023-12-22 长江水利委员会长江科学院 Dam safety monitoring multi-physical field cloud image online visualization method and system
CN117274467B (en) * 2023-11-23 2024-01-30 长江水利委员会长江科学院 Dam safety monitoring multi-physical field cloud image online visualization method and system

Also Published As

Publication number Publication date
CN110766798B (en) 2023-02-14

Similar Documents

Publication Publication Date Title
CN110766798B (en) Tunnel monitoring measurement result visualization method based on laser scanning data
CN109598714B (en) Tunnel super-underexcavation detection method based on image three-dimensional reconstruction and grid curved surface
CN111597666B (en) Method for applying BIM to transformer substation construction process
CN112254637B (en) Tunnel excavation surface scanning device and detection method based on multiple fusion data
García-Luna et al. Structure from Motion photogrammetry to characterize underground rock masses: Experiences from two real tunnels
EP2913796B1 (en) Method of generating panorama views on a mobile mapping system
CN104330074B (en) Intelligent surveying and mapping platform and realizing method thereof
CN111895911B (en) Method for monitoring hidden danger of ground collapse of shallow sand layer
CN109242966B (en) 3D panoramic model modeling method based on laser point cloud data
CN109826248B (en) Method for applying three-dimensional laser scanner to foundation pit deformation monitoring
CN109493420A (en) A kind of power plant's three-dimensional visualization methods of exhibiting based on Unity3D
CN111899332A (en) Overhead transmission line three-dimensional design method based on oblique photogrammetry technology
Grussenmeyer et al. Accurate documentation in cultural heritage by merging TLS and high-resolution photogrammetric data
CN104933223A (en) Power transmission line channel digital surveying method
CN108957507A (en) Fuel gas pipeline leakage method of disposal based on augmented reality
Oliveira et al. 3D modelling of laser scanned and photogrammetric data for digital documentation: the Mosteiro da Batalha case study
CN105023270A (en) Proactive 3D stereoscopic panorama visual sensor for monitoring underground infrastructure structure
CN102495879A (en) Industrial overhead pipeline measurement method based on ground LIDAR (Light Detection And Ranging)
CN110942516B (en) Tunnel roaming video generation method based on laser scanning data
Gaich et al. Digital rock mass characterization 2017–Where are we now? What comes next?
CN116030208A (en) Method and system for building scene of virtual simulation power transmission line of real unmanned aerial vehicle
Peteler et al. Analyzing the evolution of deterioration patterns: A first step of an image-based approach for comparing multitemporal data sets
JP7409517B2 (en) Apparatus, method and program for converting coordinates of 3D point cloud
CN113838193A (en) Data processing method and device, computer equipment and storage medium
Gonçalves et al. Planar projection of mobile laser scanning data in tunnels

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant