CN110761295A - Prefabricated assembled concrete pipe props structure - Google Patents
Prefabricated assembled concrete pipe props structure Download PDFInfo
- Publication number
- CN110761295A CN110761295A CN201911029389.1A CN201911029389A CN110761295A CN 110761295 A CN110761295 A CN 110761295A CN 201911029389 A CN201911029389 A CN 201911029389A CN 110761295 A CN110761295 A CN 110761295A
- Authority
- CN
- China
- Prior art keywords
- concrete pipe
- pipe support
- precast
- concrete
- precast concrete
- Prior art date
- Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
- Pending
Links
Images
Classifications
-
- E—FIXED CONSTRUCTIONS
- E02—HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
- E02D—FOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
- E02D17/00—Excavations; Bordering of excavations; Making embankments
- E02D17/02—Foundation pits
- E02D17/04—Bordering surfacing or stiffening the sides of foundation pits
Landscapes
- Engineering & Computer Science (AREA)
- Mining & Mineral Resources (AREA)
- Life Sciences & Earth Sciences (AREA)
- General Life Sciences & Earth Sciences (AREA)
- Paleontology (AREA)
- Civil Engineering (AREA)
- General Engineering & Computer Science (AREA)
- Structural Engineering (AREA)
- Reinforcement Elements For Buildings (AREA)
Abstract
本发明属于基坑工程技术领域,具体涉及一种预制装配式混凝土管撑结构,包括两个围护结构以及混凝土管撑;所述混凝土管撑的一端与其中一个围护结构固定连接,另一端通过预加力装置支撑于另一个围护结构上;所述混凝土管撑包括若干段预制混凝土管,且相邻两段预制混凝土管之间可拆卸连接。本发明提供的预制装配式混凝土管撑结构中,混凝土管撑通过在工厂预制多段预制混凝土管,并运输至现场拼装完成后架设于基坑工程中,具有较大的刚度;且混凝土管撑的一端与围护结构固定,另一端通过预加力装置支撑于另一个围护结构上,可很快形成支撑力,快速而且长期控制基坑变形;此外,预制混凝土管还可以回收利用。
The invention belongs to the technical field of foundation pit engineering, in particular to a prefabricated concrete pipe support structure, comprising two enclosure structures and a concrete pipe support; one end of the concrete pipe support is fixedly connected to one of the enclosure structures, and the other end It is supported on another enclosure structure by a pre-stressing device; the concrete pipe support comprises several sections of precast concrete pipes, and two adjacent sections of precast concrete pipes are detachably connected. In the prefabricated prefabricated concrete tube support structure provided by the present invention, the concrete tube support is prefabricated in a factory with multiple sections of prefabricated concrete tubes, transported to the site and then erected in the foundation pit project after completion of assembly, so that the concrete tube support has greater rigidity; One end is fixed with the enclosure structure, and the other end is supported on the other enclosure structure through a pre-stressing device, which can quickly form a supporting force and control the deformation of the foundation pit quickly and for a long time; in addition, the precast concrete pipe can also be recycled.
Description
技术领域technical field
本发明属于基坑工程技术领域,具体涉及一种预制装配式混凝土管撑结构。The invention belongs to the technical field of foundation pit engineering, and in particular relates to a prefabricated assembled concrete pipe support structure.
背景技术Background technique
现浇钢筋混凝土支撑与钢支撑是基坑工程中常用的支撑结构,两种支撑结构各有其优缺点。现浇钢筋混凝土支撑具体刚度大、抗变形能力强、整体性好的优点,但需现场支模浇筑,施工时间较长,强度形成需要较长时间,不能快速控制基坑变形,不能回收利用,造成较大工程浪费。钢支撑为预制钢管,施工速度快,且可很快形成支撑力,且可回收利用,能快速控制基坑变形,但刚度较低,抗变形能力较差。因此,有必要设计一种预制装配式混凝土管撑结构,以克服上述问题。Cast-in-place reinforced concrete support and steel support are commonly used support structures in foundation pit engineering, and the two support structures have their own advantages and disadvantages. The cast-in-place reinforced concrete supports have the advantages of high specific rigidity, strong deformation resistance and good integrity, but it requires on-site formwork pouring, the construction time is long, the strength formation takes a long time, the deformation of the foundation pit cannot be quickly controlled, and it cannot be recycled. Cause a large project waste. The steel support is a prefabricated steel pipe, the construction speed is fast, the support force can be formed quickly, and it can be recycled and can quickly control the deformation of the foundation pit, but the rigidity is low and the deformation resistance is poor. Therefore, it is necessary to design a prefabricated concrete tube support structure to overcome the above problems.
发明内容SUMMARY OF THE INVENTION
为了克服上述现有技术存在的不足,本发明的目的是提供一种预制装配式混凝土管撑结构,具有较大的刚度,能够很快形成支撑力。In order to overcome the above-mentioned deficiencies in the prior art, the purpose of the present invention is to provide a prefabricated concrete tube support structure, which has a relatively high rigidity and can quickly form a supporting force.
为实现上述目的,本发明的技术方案为一种预制装配式混凝土管撑结构,包括两个围护结构以及混凝土管撑;所述混凝土管撑的一端与其中一个围护结构固定连接,另一端通过预加力装置支撑于另一个围护结构上;所述混凝土管撑包括若干段预制混凝土管,且相邻两段预制混凝土管之间可拆卸连接。In order to achieve the above purpose, the technical solution of the present invention is a prefabricated concrete pipe support structure, comprising two enclosure structures and a concrete pipe support; one end of the concrete pipe support is fixedly connected to one of the enclosure structures, and the other end is It is supported on another enclosure structure by a prestressing device; the concrete pipe support comprises several sections of precast concrete pipes, and two adjacent sections of precast concrete pipes are detachably connected.
进一步地,每段所述预制混凝土管的两端均设有端部钢板,相邻两段所述预制混凝土管上互相靠近的端部钢板通过螺栓连接。Further, both ends of each section of the precast concrete pipe are provided with end steel plates, and the end steel plates on the adjacent two sections of the precast concrete pipes are connected by bolts.
更进一步地,所述端部钢板具有边缘部,所述边缘部凸出所述预制混凝土管的外边缘,且所述边缘部上设有供所述螺栓通过的螺栓孔。Further, the end steel plate has an edge portion, the edge portion protrudes from the outer edge of the precast concrete pipe, and the edge portion is provided with a bolt hole for the bolt to pass through.
更进一步地,相邻两段所述预制混凝土管通过多个螺栓连接,且多个螺栓沿所述预制混凝土管的周向间隔布置。Furthermore, two adjacent sections of the precast concrete pipes are connected by a plurality of bolts, and the plurality of bolts are arranged at intervals along the circumference of the precast concrete pipes.
更进一步地,所述围护结构上预埋有预埋钢板,所述混凝土管撑通过端部钢板通过焊接与所述预埋钢板连接。Furthermore, a pre-embedded steel plate is pre-embedded on the enclosure structure, and the concrete pipe support is connected to the pre-embedded steel plate by welding through the end steel plate.
进一步地,每段预制混凝土管内均设有钢筋笼骨架,所述钢筋笼骨架包括多根主筋和多根箍筋,多根箍筋沿所述预制混凝土管的长度方向间隔设置,多根主筋沿所述箍筋的内圈分布并沿预制混凝土管的长度方向延伸,所述主筋与箍筋连接形成所述钢筋笼骨架。Further, each section of precast concrete pipe is provided with a steel cage skeleton, the steel cage skeleton includes a plurality of main bars and a plurality of stirrups, and the plurality of stirrups are arranged at intervals along the length direction of the precast concrete pipe, and the plurality of main bars are arranged along the length of the precast concrete pipe. The inner circle of the stirrups is distributed and extends along the length direction of the prefabricated concrete pipe, and the main bars are connected with the stirrups to form the steel cage skeleton.
进一步地,所述混凝土管撑的两端还设有防坠落钢索,所述防坠落钢索的一端与所述混凝土管撑固定,另一端与所述围护结构上位于所述混凝土管撑上方的位置固定连接。Further, both ends of the concrete tube support are also provided with anti-falling steel cables, one end of the anti-falling steel cables is fixed with the concrete tube support, and the other end is located on the concrete tube support with the enclosure structure. The upper position is fixed connection.
与现有技术相比,本发明具有以下有益效果:Compared with the prior art, the present invention has the following beneficial effects:
(1)本发明提供的预制装配式混凝土管撑结构中,混凝土管撑通过在工厂预制多段预制混凝土管,并运输至现场拼装完成后架设于基坑工程中,具有较大的刚度;且混凝土管撑的一端与围护结构固定,另一端通过预加力装置支撑于另一个围护结构上,可很快形成支撑力,快速而且长期控制基坑变形;(1) In the prefabricated concrete tube support structure provided by the present invention, the concrete tube support is prefabricated in a factory with multiple sections of prefabricated concrete tubes and transported to the site to be assembled and erected in the foundation pit project, which has greater rigidity; and the concrete One end of the pipe support is fixed with the enclosure structure, and the other end is supported on the other enclosure structure through the pre-stressing device, which can quickly form a supporting force and control the deformation of the foundation pit quickly and for a long time;
(2)本发明提供的预制装配式混凝土管撑结构可回收利用,且施工进度快,解决了传统现浇混凝土支撑与钢支撑一系列问题。(2) The prefabricated concrete tube support structure provided by the present invention can be recycled and the construction progress is fast, which solves a series of problems of traditional cast-in-place concrete support and steel support.
附图说明Description of drawings
为了更清楚地说明本发明实施例或现有技术中的技术方案,下面将对实施例或现有技术描述中所需要使用的附图作简单地介绍,显而易见地,下面描述中的附图仅仅是本发明的一些实施例,对于本领域普通技术人员来讲,在不付出创造性劳动的前提下,还可以根据这些附图获得其它的附图。In order to explain the embodiments of the present invention or the technical solutions in the prior art more clearly, the following briefly introduces the accompanying drawings that need to be used in the description of the embodiments or the prior art. Obviously, the accompanying drawings in the following description are only These are some embodiments of the present invention, and for those of ordinary skill in the art, other drawings can also be obtained from these drawings without creative effort.
图1为本发明实施例提供的预制装配式混凝土管撑结构的示意图;Fig. 1 is a schematic diagram of a prefabricated concrete pipe support structure provided by an embodiment of the present invention;
图2为本发明实施例提供的预制装配式混凝土管撑结构的示意图;2 is a schematic diagram of a prefabricated concrete tube support structure provided by an embodiment of the present invention;
图3为图2的C-C剖面图;Fig. 3 is the C-C sectional view of Fig. 2;
图4为图2的D-D剖面图;Fig. 4 is the D-D sectional view of Fig. 2;
图5为图1中A处的示意图;Fig. 5 is the schematic diagram at A place in Fig. 1;
图6为图1中B处的示意图;Fig. 6 is the schematic diagram at B in Fig. 1;
图中:1、混凝土管撑,2、围护结构,3、螺栓,4、混凝土结构,5、主筋,6、箍筋,7、端部钢板,8、预埋钢板,9、预加力装置,10、防坠落钢索。In the picture: 1. Concrete pipe support, 2. Enclosure structure, 3. Bolts, 4. Concrete structure, 5. Main reinforcement, 6. Stirrup, 7. End steel plate, 8. Pre-embedded steel plate, 9. Pre-stressing device, 10, anti-fall steel cable.
具体实施方式Detailed ways
下面将结合本发明实施例中的附图,对本发明实施例中的技术方案进行清楚、完整地描述,显然,所描述的实施例仅仅是本发明一部分实施例,而不是全部的实施例。基于本发明中的实施例,本领域普通技术人员在没有做出创造性劳动前提下所获得的所有其它实施例,都属于本发明保护的范围。The technical solutions in the embodiments of the present invention will be clearly and completely described below with reference to the accompanying drawings in the embodiments of the present invention. Obviously, the described embodiments are only a part of the embodiments of the present invention, but not all of the embodiments. Based on the embodiments of the present invention, all other embodiments obtained by those of ordinary skill in the art without creative efforts shall fall within the protection scope of the present invention.
在本发明的描述中,需要理解的是,术语“中心”、“上”、“下”、“前”、“后”、“左”、“右”、“竖直”、“水平”、“顶”、“底”、“内”、“外”等指示的方位或位置关系为基于附图所示的方位或位置关系,仅是为了便于描述本发明和简化描述,而不是指示或暗示所指的装置或元件必须具有特定的方位、以特定的方位构造和操作,因此不能理解为对本发明的限制。In the description of the present invention, it should be understood that the terms "center", "upper", "lower", "front", "rear", "left", "right", "vertical", "horizontal", The orientation or positional relationship indicated by "top", "bottom", "inner", "outer", etc. is based on the orientation or positional relationship shown in the drawings, and is only for the convenience of describing the present invention and simplifying the description, rather than indicating or implying The device or element referred to must have a particular orientation, be constructed and operate in a particular orientation, and therefore should not be construed as limiting the invention.
术语“第一”、“第二”仅用于描述目的,而不能理解为指示或暗示相对重要性或者隐含指明所指示的技术特征的数量。由此,限定有“第一”、“第二”的特征可以明示或者隐含地包括一个或者更多个该特征;在本发明的描述中,除非另有说明,“多个”的含义是两个或两个以上。The terms "first" and "second" are only used for descriptive purposes, and should not be construed as indicating or implying relative importance or implicitly indicating the number of technical features indicated. Thus, the features defined with "first" and "second" may expressly or implicitly include one or more of the features; in the description of the present invention, unless otherwise specified, the meaning of "multiple" is two or more.
如图1-图6所示,本发明实施例提供一种预制装配式混凝土管撑结构,包括两个围护结构2以及混凝土管撑1;所述混凝土管撑1的一端与其中一个围护结构2固定连接,另一端通过预加力装置9支撑于另一个围护结构2上;所述混凝土管撑1包括若干段预制混凝土管,且相邻两段预制混凝土管之间可拆卸连接。本发明提供的预制装配式混凝土管撑结构中,混凝土管撑1通过在工厂预制多段预制混凝土管,并运输至现场拼装完成后架设于基坑工程中,具有较大的刚度;且混凝土管撑1的一端与围护结构2固定,另一端通过预加力装置9支撑于另一个围护结构2上,可很快形成支撑力,快速而且长期控制基坑变形;此外,由于相邻两段预制混凝土管之间是可拆卸连接的,因此,施工进度快,且预制混凝土管还可回收再利用。As shown in FIGS. 1-6 , an embodiment of the present invention provides a prefabricated concrete pipe support structure, including two
进一步地,每段所述预制混凝土管的两端均设有端部钢板7,相邻两段所述预制混凝土管上互相靠近的端部钢板7通过螺栓3连接。优化地,所述端部钢板7具有边缘部,所述边缘部凸出所述预制混凝土管的外边缘,且所述边缘部上设有供所述螺栓3通过的螺栓3孔。如图2和图4所示,每段预制混凝土管两端的端部钢板7的外边缘凸出预制混凝土管的外边缘的部分为边缘部,该边缘部上设有螺栓3孔,拼装时,通过螺栓3穿过螺栓3孔将相邻两段的预制混凝土管的端部钢板7实现预制混凝土管在施工现场的组装成型,可以有效地加快施工进度;而在拆卸时,通过将螺栓3穿从螺栓3孔中取出,便可实现混凝土管撑1自身的拆卸,同时拆卸的混凝土管撑1还可以回收利用。Further, both ends of each section of the precast concrete pipe are provided with end steel plates 7 , and the end steel plates 7 adjacent to each other on two adjacent sections of the precast concrete pipes are connected by bolts 3 . Preferably, the end steel plate 7 has an edge portion, the edge portion protrudes from the outer edge of the precast concrete pipe, and the edge portion is provided with a bolt 3 hole for the bolt 3 to pass through. As shown in Figures 2 and 4, the part where the outer edge of the end steel plates 7 at both ends of each precast concrete pipe protrudes from the outer edge of the precast concrete pipe is the edge part, and the edge part is provided with 3 holes for bolts. Through the bolts 3 passing through the holes of the bolts 3, the end steel plates 7 of the adjacent two sections of the precast concrete pipes can be assembled and formed at the construction site, which can effectively speed up the construction progress; The
更进一步地,相邻两段所述预制混凝土管通过多个螺栓3连接,且多个螺栓3沿所述预制混凝土管的周向间隔布置。如图4所示,多个螺栓3沿预制混凝土管的周向均匀布置,以实现预制混凝土管的连接接长,提高基坑施工的安全性。Further, two adjacent sections of the precast concrete pipes are connected by a plurality of bolts 3, and the plurality of bolts 3 are arranged at intervals along the circumference of the precast concrete pipes. As shown in FIG. 4 , a plurality of bolts 3 are evenly arranged along the circumference of the precast concrete pipe, so as to realize the connection and length of the precast concrete pipe and improve the safety of foundation pit construction.
更进一步地,所述围护结构2上预埋有预埋钢板8,所述混凝土管撑1通过端部钢板7通过焊接与所述预埋钢板8连接。如图6所示,通过预埋钢板8与靠近该围护结构2的预制混凝土管端部的端部钢板7的焊接,实现混凝土管撑1与围护结构2的连接。Furthermore, a pre-embedded steel plate 8 is pre-embedded on the
进一步地,每段预制混凝土管内均设有钢筋笼骨架,所述钢筋笼骨架包括多根主筋5和多根箍筋6,多根箍筋6沿所述预制混凝土管的长度方向间隔设置,多根主筋5沿所述箍筋6的内圈分布并沿预制混凝土管的长度方向延伸,所述主筋5与箍筋6连接形成所述钢筋笼骨架,如图3所示。本实施例中的主筋5和箍筋6的数量根据每段预制混凝土管的具体长度、直径以及强度要求来确定,钢筋笼骨架也可以采用其他形式。Further, each section of precast concrete pipe is provided with a steel cage skeleton, and the steel cage skeleton includes a plurality of main bars 5 and a plurality of stirrups 6, and the plurality of stirrups 6 are arranged at intervals along the length direction of the precast concrete pipe, and many The root main bars 5 are distributed along the inner circle of the stirrups 6 and extend along the length direction of the precast concrete pipe. The main bars 5 are connected with the stirrups 6 to form the steel cage skeleton, as shown in FIG. 3 . The quantity of the main bars 5 and the stirrups 6 in this embodiment is determined according to the specific length, diameter and strength requirements of each section of the precast concrete pipe, and the steel cage frame can also adopt other forms.
进一步地,所述混凝土管撑1的两端还设有防坠落钢索10,所述防坠落钢索10的一端与所述混凝土管撑1固定,另一端与所述围护结构2上位于所述混凝土管撑1上方的位置固定连接。如图5和图6所示,防坠落钢索10的一端缠绕固定于混凝土管撑1上,另一端与混凝土管撑1上方的围护结构2固定连接,进一步提高基坑施工的安全性。Further, both ends of the
本实施例中的预加力装置9可采用千斤顶的形式,将千斤顶置于混凝土管撑1的端部与围护结构2之间,且千斤顶的底座端和工作端分别抵靠在围护结构2和混凝土管撑1上,通过控制千斤顶的工作端的伸长,使混凝土管撑1的支撑于两侧的围护结构上形成支撑力,有效控制基坑变形,便于围护结构之间地下结构的施工。The
本发明的预制装配式混凝土管撑结构适用于基坑工程,如地下车站的施工,根据地下车站的深度,通常在基坑的深度方向上需要设置多道内支撑,采用明挖法施工时,第一道支撑可将混凝土管撑的两端浇筑于冠梁内,第二道及后续支撑均可按照本发明的预制装配式混凝土管撑结构进行架设;采用盖挖半逆作施工时,内支撑也可采用本发明的预制装配式混凝土管撑结构进行架设;采用本发明的预制装配式混凝土管撑结构具有较大的刚度,有效控制基坑变形,同时能够很快形成支撑力,加快施工进度。The prefabricated concrete tube support structure of the present invention is suitable for foundation pit engineering, such as the construction of an underground station. According to the depth of the underground station, usually multiple inner supports need to be arranged in the depth direction of the foundation pit. One support can cast both ends of the concrete tube support in the crown beam, and the second and subsequent supports can be erected according to the prefabricated concrete tube support structure of the present invention; The prefabricated concrete tube support structure of the present invention can also be used for erection; the prefabricated concrete tube support structure of the present invention has greater rigidity, effectively controls the deformation of the foundation pit, and at the same time can quickly form a supporting force and speed up the construction progress. .
以上所述仅为本发明的较佳实施例而已,并不用以限制本发明,凡在本发明的精神和原则之内,所作的任何修改、等同替换、改进等,均应包含在本发明的保护范围之内。The above descriptions are only preferred embodiments of the present invention, and are not intended to limit the present invention. Any modification, equivalent replacement, improvement, etc. made within the spirit and principle of the present invention shall be included in the scope of the present invention. within the scope of protection.
Claims (7)
Priority Applications (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201911029389.1A CN110761295A (en) | 2019-10-28 | 2019-10-28 | Prefabricated assembled concrete pipe props structure |
Applications Claiming Priority (1)
| Application Number | Priority Date | Filing Date | Title |
|---|---|---|---|
| CN201911029389.1A CN110761295A (en) | 2019-10-28 | 2019-10-28 | Prefabricated assembled concrete pipe props structure |
Publications (1)
| Publication Number | Publication Date |
|---|---|
| CN110761295A true CN110761295A (en) | 2020-02-07 |
Family
ID=69334356
Family Applications (1)
| Application Number | Title | Priority Date | Filing Date |
|---|---|---|---|
| CN201911029389.1A Pending CN110761295A (en) | 2019-10-28 | 2019-10-28 | Prefabricated assembled concrete pipe props structure |
Country Status (1)
| Country | Link |
|---|---|
| CN (1) | CN110761295A (en) |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112030988A (en) * | 2020-07-31 | 2020-12-04 | 中铁第四勘察设计院集团有限公司 | Assembled hollow steel tube concrete support system and construction method thereof |
| CN112030985A (en) * | 2020-07-31 | 2020-12-04 | 中铁第四勘察设计院集团有限公司 | Hollow steel pipe concrete support, prefabricated member, construction method and support system |
Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2012233349A (en) * | 2011-05-02 | 2012-11-29 | Toda Constr Co Ltd | Earth retaining method |
| CN206034458U (en) * | 2016-08-30 | 2017-03-22 | 中铁三局集团有限公司 | Structure of falling is prevented in steel shotcrete in SMW worker method stake envelope foundation ditch |
| CN107217675A (en) * | 2017-07-13 | 2017-09-29 | 中铁第四勘察设计院集团有限公司 | A kind of concrete-filled steel tubular hollow supporting construction suitable for Metro Deep Excavation |
| CN107964959A (en) * | 2017-12-05 | 2018-04-27 | 广州鑫桥建筑工程有限公司 | A kind of prefabricated assembled concrete support system |
| CN211368733U (en) * | 2019-10-28 | 2020-08-28 | 中铁第四勘察设计院集团有限公司 | Prefabricated assembled concrete pipe props structure |
-
2019
- 2019-10-28 CN CN201911029389.1A patent/CN110761295A/en active Pending
Patent Citations (5)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| JP2012233349A (en) * | 2011-05-02 | 2012-11-29 | Toda Constr Co Ltd | Earth retaining method |
| CN206034458U (en) * | 2016-08-30 | 2017-03-22 | 中铁三局集团有限公司 | Structure of falling is prevented in steel shotcrete in SMW worker method stake envelope foundation ditch |
| CN107217675A (en) * | 2017-07-13 | 2017-09-29 | 中铁第四勘察设计院集团有限公司 | A kind of concrete-filled steel tubular hollow supporting construction suitable for Metro Deep Excavation |
| CN107964959A (en) * | 2017-12-05 | 2018-04-27 | 广州鑫桥建筑工程有限公司 | A kind of prefabricated assembled concrete support system |
| CN211368733U (en) * | 2019-10-28 | 2020-08-28 | 中铁第四勘察设计院集团有限公司 | Prefabricated assembled concrete pipe props structure |
Cited By (2)
| Publication number | Priority date | Publication date | Assignee | Title |
|---|---|---|---|---|
| CN112030988A (en) * | 2020-07-31 | 2020-12-04 | 中铁第四勘察设计院集团有限公司 | Assembled hollow steel tube concrete support system and construction method thereof |
| CN112030985A (en) * | 2020-07-31 | 2020-12-04 | 中铁第四勘察设计院集团有限公司 | Hollow steel pipe concrete support, prefabricated member, construction method and support system |
Similar Documents
| Publication | Publication Date | Title |
|---|---|---|
| CN107989447A (en) | A kind of large-scale earthing concrete tank dome steel support structure and installation method | |
| CN103850363A (en) | Prefabricated through-hole assembled reinforced concrete shear wall and its construction method | |
| CN108457422A (en) | Precast prestressed beam, assembled composite frame structure and its installation method | |
| CN110878522A (en) | Construction system and construction method of beam under main tower | |
| CN207111119U (en) | A kind of Tunnel structure | |
| CN114439202A (en) | Thin-wall ultrahigh wall body double-side template operation platform and adjustable fixing system | |
| CN115680116A (en) | Assembled frame beam column connecting node and construction method thereof | |
| CN114164952A (en) | An assembled section steel column-section steel beam joint with inner and outer steel sleeves | |
| CN110761295A (en) | Prefabricated assembled concrete pipe props structure | |
| JP2750368B2 (en) | Construction method of reactor containment top slab | |
| CN205636516U (en) | Convertible template system of hollow concrete leaning tower | |
| CN108166629A (en) | A kind of detachable assembling type steel core concrete column-connected mode and its construction method | |
| CN210597882U (en) | Lattice type steel reinforced concrete combined column beam column node | |
| CN112227688A (en) | A stiffened plate-supported construction platform without outer frame and its method for residential buildings | |
| CN108797350B (en) | Tower column inner and outer stiff skeleton device and construction method thereof | |
| CN211368733U (en) | Prefabricated assembled concrete pipe props structure | |
| CN215563303U (en) | A support-free prefabricated concrete beam-column connection structure | |
| CN214785809U (en) | Stiffening plate bearing type outer frame-free construction platform for residential building | |
| CN215671420U (en) | Fixing device for vertically assembling annular steel ribs and steel pipes | |
| CN116517282A (en) | Hanging die construction method and construction device thereof | |
| CN2385010Y (en) | External mounted square steel tube concrete beam and column connecting node | |
| CN116290767A (en) | Construction process of self-supporting cast-in-situ reinforced concrete frame with assembled rib mould | |
| CN205153121U (en) | Buckling restrained brace and concrete beam column angle steel anchor connected node | |
| CN211973557U (en) | An exposed rigid column foot node | |
| CN209066611U (en) | Connecting structure of open caisson wall and floor system |
Legal Events
| Date | Code | Title | Description |
|---|---|---|---|
| PB01 | Publication | ||
| PB01 | Publication | ||
| SE01 | Entry into force of request for substantive examination | ||
| SE01 | Entry into force of request for substantive examination | ||
| RJ01 | Rejection of invention patent application after publication |
Application publication date: 20200207 |
|
| RJ01 | Rejection of invention patent application after publication |
