CN110705801A - Power grid accident economic loss estimation method and system based on fault loss electric quantity - Google Patents

Power grid accident economic loss estimation method and system based on fault loss electric quantity Download PDF

Info

Publication number
CN110705801A
CN110705801A CN201910959101.4A CN201910959101A CN110705801A CN 110705801 A CN110705801 A CN 110705801A CN 201910959101 A CN201910959101 A CN 201910959101A CN 110705801 A CN110705801 A CN 110705801A
Authority
CN
China
Prior art keywords
fault
fault line
electric quantity
loss
economic loss
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Pending
Application number
CN201910959101.4A
Other languages
Chinese (zh)
Inventor
张林峰
王蕾
李伦
张立柱
刘爱新
崔志国
赵长耀
李雅文
孙华杰
张同庆
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
State Grid Corp of China SGCC
TaiAn Power Supply Co of State Grid Shandong Electric Power Co Ltd
Original Assignee
State Grid Corp of China SGCC
TaiAn Power Supply Co of State Grid Shandong Electric Power Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by State Grid Corp of China SGCC, TaiAn Power Supply Co of State Grid Shandong Electric Power Co Ltd filed Critical State Grid Corp of China SGCC
Priority to CN201910959101.4A priority Critical patent/CN110705801A/en
Publication of CN110705801A publication Critical patent/CN110705801A/en
Pending legal-status Critical Current

Links

Images

Classifications

    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06316Sequencing of tasks or work
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/04Forecasting or optimisation specially adapted for administrative or management purposes, e.g. linear programming or "cutting stock problem"
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q10/00Administration; Management
    • G06Q10/06Resources, workflows, human or project management; Enterprise or organisation planning; Enterprise or organisation modelling
    • G06Q10/063Operations research, analysis or management
    • G06Q10/0631Resource planning, allocation, distributing or scheduling for enterprises or organisations
    • G06Q10/06312Adjustment or analysis of established resource schedule, e.g. resource or task levelling, or dynamic rescheduling
    • GPHYSICS
    • G06COMPUTING; CALCULATING OR COUNTING
    • G06QINFORMATION AND COMMUNICATION TECHNOLOGY [ICT] SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES; SYSTEMS OR METHODS SPECIALLY ADAPTED FOR ADMINISTRATIVE, COMMERCIAL, FINANCIAL, MANAGERIAL OR SUPERVISORY PURPOSES, NOT OTHERWISE PROVIDED FOR
    • G06Q50/00Systems or methods specially adapted for specific business sectors, e.g. utilities or tourism
    • G06Q50/06Electricity, gas or water supply
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y02TECHNOLOGIES OR APPLICATIONS FOR MITIGATION OR ADAPTATION AGAINST CLIMATE CHANGE
    • Y02EREDUCTION OF GREENHOUSE GAS [GHG] EMISSIONS, RELATED TO ENERGY GENERATION, TRANSMISSION OR DISTRIBUTION
    • Y02E40/00Technologies for an efficient electrical power generation, transmission or distribution
    • Y02E40/70Smart grids as climate change mitigation technology in the energy generation sector
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Landscapes

  • Business, Economics & Management (AREA)
  • Human Resources & Organizations (AREA)
  • Engineering & Computer Science (AREA)
  • Economics (AREA)
  • Strategic Management (AREA)
  • Entrepreneurship & Innovation (AREA)
  • Tourism & Hospitality (AREA)
  • Physics & Mathematics (AREA)
  • Theoretical Computer Science (AREA)
  • Marketing (AREA)
  • General Physics & Mathematics (AREA)
  • General Business, Economics & Management (AREA)
  • Quality & Reliability (AREA)
  • Development Economics (AREA)
  • Game Theory and Decision Science (AREA)
  • Operations Research (AREA)
  • Educational Administration (AREA)
  • Health & Medical Sciences (AREA)
  • Public Health (AREA)
  • Water Supply & Treatment (AREA)
  • General Health & Medical Sciences (AREA)
  • Primary Health Care (AREA)
  • Supply And Distribution Of Alternating Current (AREA)
  • Management, Administration, Business Operations System, And Electronic Commerce (AREA)

Abstract

The invention provides a power grid accident economic loss estimation method and system based on fault loss electric quantity, wherein the method comprises the following steps: s1, calculating the fault loss electric quantity of each fault line in the power grid accident; s2, acquiring the load type characteristic of each fault line; and S3, searching a ten-thousand-yuan production value electric quantity corresponding table according to the load type characteristics and the loss electric quantity of the fault line, and acquiring the economic loss of the fault line. According to the method and the system for estimating the economic loss of the power grid accident based on the fault loss electric quantity, provided by the invention, after a power device fails, the fault loss electric quantity to be faced by a power enterprise is obtained through integral calculation according to information provided by short-term load prediction, the economic loss caused to the society is estimated, the reasonable scheduling of the power generation capacity is realized on the basis of the estimation, the output requirement of a power plant in operation is predicted, an economic and reasonable emergency repair scheme is realized, the loss caused by the fault is reduced, and the stability of the power enterprise and the society is ensured.

Description

Power grid accident economic loss estimation method and system based on fault loss electric quantity
Technical Field
The invention belongs to the technical field of power systems, and particularly relates to a power grid accident economic loss estimation method and system based on fault loss electric quantity.
Background
The inability to store large quantities of electrical energy makes it necessary for the power system to maintain a balanced supply and demand at all times and to provide reliable and standardized electrical energy to various consumers as economically as possible to meet their load demands. Therefore, in order to ensure safe and economic operation of the power system, the change rule of the load and the future change trend must be mastered. In the operation, control and planning management of the power system, the load prediction determines the reasonable arrangement of power generation, transmission and distribution, which is an important component of the power system planning and one of the important factors for improving the economic benefit of power enterprises and promoting the national economic development. Accurate short-term load prediction is the key of a power generation and supply plan and power supply and demand balance of a power grid made by a power grid dispatching mechanism, and is beneficial to system operators to efficiently predict the production, transmission, distribution and consumption conditions of electric energy and make an economical and reasonable power generation scheme. At present, no scheme for effectively estimating economic loss caused by power grid accidents exists.
Therefore, it is very necessary to provide a method and a system for estimating economic loss of a power grid accident based on fault loss electric quantity to solve the above-mentioned drawbacks in the prior art.
Disclosure of Invention
Aiming at the defect that the prior art lacks a scheme for estimating the economic loss caused by the power grid accident, the invention provides a power grid accident economic loss estimation method and system based on fault loss electric quantity, so as to solve the technical problem.
In a first aspect, the invention provides a grid accident economic loss estimation method based on fault loss electric quantity, which comprises the following steps:
s1, calculating the fault loss electric quantity of each fault line in the power grid accident;
s2, acquiring the load type characteristic of each fault line;
and S3, searching a ten-thousand-yuan production value electric quantity corresponding table according to the load type characteristics and the loss electric quantity of the fault line, and acquiring the economic loss of the fault line.
Further, step S3 is followed by the following steps:
and S4, setting a power distribution first-aid repair sequence of the fault line according to the economic loss of the fault line. The power distribution first-aid repair sequence is set on the basis of the economic loss of the fault line, and the power generation capacity can be reasonably scheduled on the basis of the economic loss of the fault line.
Further, the step S4 specifically includes the following steps:
s41, acquiring the economic loss of each fault line;
and S42, setting a fault line emergency repair grade according to the economic loss value of each fault line, and then carrying out power distribution emergency repair on the fault line according to the fault line emergency repair grade. The fault line is graded according to economic loss, so that distribution and emergency repair are facilitated, resources are reasonably utilized, and economic loss is reduced to the maximum extent.
Further, the step S42 specifically includes the following steps:
s421, setting a rush-repair grade of the fault line according to the relation between the economic loss value of each fault line and a set threshold value;
when the economic loss value of the fault line exceeds a set threshold value; step S422 is entered;
when the economic loss value of the fault line does not exceed the set threshold value; proceeding to step S423;
s422, setting the fault line as a priority first-aid repair fault line, and setting the priority first-aid repair fault line to carry out power distribution first-aid repair according to the economic loss order; finishing;
and S423, setting the fault line as a secondary emergency repair fault line, and setting the secondary emergency repair fault line to perform power distribution emergency repair according to the distance sequence. Different rush-repair strategies are adopted for different rush-repair grade fault lines, so that power distribution rush-repair resources are conveniently and fully utilized, meanwhile, the economic loss is reduced, and the balance of rush-repair resource scheduling and economic loss is realized.
Further, the step S1 specifically includes the following steps:
s11, calculating the ultra-short term coincidence prediction curve of each fault line in the power grid accident;
s12, acquiring an actual power curve of each fault line;
and S13, taking the starting and stopping time of the power grid fault as a node, and carrying out integral calculation on the ultra-short term coincidence prediction curve and the actual power curve of the fault line to obtain the fault loss electric quantity of each fault line. The ultra-short term coincidence prediction curve of the fault line adopts the existing ultra-short term coincidence prediction, such as the ultra-short term load prediction of the power system based on the chaos theory, and is not described herein again.
Further, the step S3 specifically includes the following steps:
s31, acquiring a ten-thousand-yuan production value electric quantity corresponding table;
s32, searching a ten-thousand-yuan production value column corresponding to the load type characteristic of the fault line in the ten-thousand-yuan production value electric quantity corresponding table;
and S33, searching the ten-thousand-yuan economic loss of the fault line in the corresponding ten-thousand-yuan production value list according to the fault loss electric quantity of the fault line. The ten thousand yuan of output value electric quantity corresponding table is refined into more than 500 kinds of load type characteristics, and in each kind of conforming type characteristics, different electric quantities correspond to different output values.
In a second aspect, the present invention provides a grid accident economic loss estimation system based on fault loss electric quantity, including:
the fault line electric quantity loss calculation module is used for calculating the fault loss electric quantity of each fault line in the power grid accident;
the fault line load type characteristic acquisition module is used for acquiring the load type characteristic of each fault line;
and the fault line economic loss acquisition module is used for searching the ten-thousand-yuan production value electric quantity corresponding table according to the fault line load type characteristics and the loss electric quantity to acquire the economic loss of the fault line.
Further, still include:
the power distribution first-aid repair sequence setting module is used for setting the power distribution first-aid repair sequence of the fault line according to the economic loss of the fault line; the power distribution first-aid repair sequence setting module comprises:
the fault line economic loss acquisition unit is used for acquiring the economic loss of each fault line;
and the fault line emergency repair grade setting unit is used for setting the fault line emergency repair grade according to the economic loss value of each fault line and then carrying out power distribution emergency repair on the fault line according to the fault line emergency repair grade.
Further, the fault line power loss calculation module comprises:
the ultra-short term conformance preset curve calculation unit is used for calculating an ultra-short term conformance prediction curve of each fault line in the power grid accident;
the actual power curve acquiring unit is used for acquiring an actual power curve of each fault line;
and the fault loss electric quantity calculating unit is used for carrying out integral calculation on the ultra-short term coincidence prediction curve and the actual power curve of the fault line by taking the starting and stopping time of the power grid fault as a node to obtain the fault loss electric quantity of each fault line.
Further, the fault line economic loss acquisition module comprises:
the ten-thousand-yuan produced value electric quantity corresponding table acquiring unit is used for acquiring the ten-thousand-yuan produced value electric quantity corresponding table;
the ten-thousand-yuan production value column searching unit is used for searching a ten-thousand-yuan production value column corresponding to the load type characteristic of the fault line in the ten-thousand-yuan production value electric quantity corresponding table;
and the ten-thousand-yuan economic loss acquisition unit is used for searching the ten-thousand-yuan economic loss of the fault line in the corresponding ten-thousand-yuan economic loss list according to the fault loss electric quantity of the fault line.
The beneficial effect of the invention is that,
according to the method and the system for estimating the economic loss of the power grid accident based on the fault loss electric quantity, provided by the invention, after a power device fails, the fault loss electric quantity to be faced by a power enterprise is obtained through integral calculation according to information provided by short-term load prediction, the economic loss caused to the society is estimated, the reasonable scheduling of the power generation capacity is realized on the basis of the estimation, the output requirement of a power plant in operation is predicted, an economic and reasonable emergency repair scheme is realized, the loss caused by the fault is reduced, and the stability of the power enterprise and the society is ensured.
In addition, the invention has reliable design principle, simple structure and very wide application prospect.
Therefore, compared with the prior art, the invention has prominent substantive features and remarkable progress, and the beneficial effects of the implementation are also obvious.
Drawings
In order to more clearly illustrate the embodiments or technical solutions in the prior art of the present invention, the drawings used in the description of the embodiments or prior art will be briefly described below, and it is obvious for those skilled in the art that other drawings can be obtained based on these drawings without creative efforts.
FIG. 1 is a first schematic flow chart of the method of the present invention;
FIG. 2 is a second schematic flow chart of the method of the present invention;
FIG. 3 is a schematic diagram of the system of the present invention;
in the figure, 1-a fault line power loss calculation module; 1.1-ultra-short term conformity preset curve calculation unit; 1.2-actual power curve acquisition unit; 1.3-fault loss electric quantity calculating unit; 2-fault line load type characteristic obtaining module; 3-a fault line economic loss acquisition module; 3.1-ten thousand yuan of value electric quantity corresponding table acquisition unit; 3.2-ten thousand yuan produce value column searching unit; 3.3-ten thousand yuan of economic loss acquisition units; 4-power distribution first-aid repair sequence setting module; 4.1-a fault line economic loss acquisition unit; 4.2-failure line first-aid repair grade setting unit.
Detailed Description
In order to make those skilled in the art better understand the technical solution of the present invention, the technical solution in the embodiment of the present invention will be clearly and completely described below with reference to the drawings in the embodiment of the present invention, and it is obvious that the described embodiment is only a part of the embodiment of the present invention, and not all embodiments. All other embodiments, which can be derived by a person skilled in the art from the embodiments given herein without making any creative effort, shall fall within the protection scope of the present invention.
Example 1:
as shown in fig. 1, the present invention provides a grid accident economic loss estimation method based on fault loss electric quantity, which includes the following steps:
s1, calculating the fault loss electric quantity of each fault line in the power grid accident;
s2, acquiring the load type characteristic of each fault line;
s3, searching a ten-thousand-yuan production value electric quantity corresponding table according to the load type characteristics and the lost electric quantity of the fault line to obtain the economic loss of the fault line;
and S4, setting a power distribution first-aid repair sequence of the fault line according to the economic loss of the fault line.
Example 2:
as shown in fig. 2, the present invention provides a grid accident economic loss estimation method based on fault loss electric quantity, which includes the following steps:
s1, calculating the fault loss electric quantity of each fault line in the power grid accident; the method comprises the following specific steps:
s11, calculating the ultra-short term coincidence prediction curve of each fault line in the power grid accident;
s12, acquiring an actual power curve of each fault line;
s13, taking the starting and stopping time of the power grid fault as a node, and carrying out integral calculation on the ultra-short term coincidence prediction curve and the actual power curve of the fault line to obtain the fault loss electric quantity of each fault line;
s2, acquiring the load type characteristic of each fault line;
s3, searching a ten-thousand-yuan production value electric quantity corresponding table according to the load type characteristics and the lost electric quantity of the fault line to obtain the economic loss of the fault line; the method comprises the following specific steps:
s31, acquiring a ten-thousand-yuan production value electric quantity corresponding table;
s32, searching a ten-thousand-yuan production value column corresponding to the load type characteristic of the fault line in the ten-thousand-yuan production value electric quantity corresponding table;
s33, searching the ten-thousand-yuan economic loss of the fault line in the corresponding ten-thousand-yuan production value list according to the fault loss electric quantity of the fault line;
s4, setting a power distribution first-aid repair sequence of the fault line according to the economic loss of the fault line; the method comprises the following specific steps:
s41, acquiring the economic loss of each fault line;
s42, setting a fault line emergency repair grade according to the economic loss value of each fault line, and then carrying out power distribution emergency repair on the fault line according to the fault line emergency repair grade; the method comprises the following specific steps:
s421, setting a rush-repair grade of the fault line according to the relation between the economic loss value of each fault line and a set threshold value;
when the economic loss value of the fault line exceeds a set threshold value; step S422 is entered;
when the economic loss value of the fault line does not exceed the set threshold value; proceeding to step S423;
s422, setting the fault line as a priority first-aid repair fault line, and setting the priority first-aid repair fault line to carry out power distribution first-aid repair according to the economic loss order; finishing;
and S423, setting the fault line as a secondary emergency repair fault line, and setting the secondary emergency repair fault line to perform power distribution emergency repair according to the distance sequence.
Example 3:
as shown in fig. 3, the present invention provides a grid accident economic loss estimation system based on fault loss electric quantity, which includes:
the power loss calculation module 1 of the fault line is used for calculating the power loss of each fault line in the power grid accident; the fault line power loss calculation module 1 includes:
the ultra-short term conformance preset curve calculating unit 1.1 is used for calculating an ultra-short term conformance prediction curve of each fault line in the power grid accident;
an actual power curve obtaining unit 1.2, configured to obtain an actual power curve of each faulty line;
the fault loss electric quantity calculating unit 1.3 is used for carrying out integral calculation on the ultra-short term coincidence prediction curve and the actual power curve of the fault line by taking the starting and stopping time of the power grid fault as a node to obtain the fault loss electric quantity of each fault line;
the fault line load type characteristic acquisition module 2 is used for acquiring the load type characteristic of each fault line;
the fault line economic loss acquisition module 3 is used for searching the ten-thousand-yuan generation value electric quantity corresponding table according to the fault line load type characteristics and the lost electric quantity to acquire the economic loss of the fault line; the faulty line economic loss acquisition module 3 includes:
a ten thousand yuan of output value electric quantity corresponding table obtaining unit 3.1 for obtaining the ten thousand yuan of output value electric quantity corresponding table;
the ten-thousand-yuan production value column searching unit 3.2 is used for searching a ten-thousand-yuan production value column corresponding to the load type characteristic of the fault line in the ten-thousand-yuan production value electric quantity corresponding table;
the ten-thousand-yuan economic loss acquisition unit 3.3 is used for searching the ten-thousand-yuan economic loss of the fault line in the corresponding ten-thousand-yuan economic loss column according to the fault loss electric quantity of the fault line;
the power distribution first-aid repair sequence setting module 4 is used for setting the power distribution first-aid repair sequence of the fault line according to the economic loss of the fault line; the power distribution first-aid repair sequence setting module 4 comprises:
the fault line economic loss acquisition unit 4.1 is used for acquiring the economic loss of each fault line;
and the faulty line emergency repair grade setting unit 4.2 is used for setting the faulty line emergency repair grade according to the economic loss value of each faulty line and then carrying out power distribution emergency repair on the faulty line according to the faulty line emergency repair grade.
Although the present invention has been described in detail by referring to the drawings in connection with the preferred embodiments, the present invention is not limited thereto. Various equivalent modifications or substitutions can be made on the embodiments of the present invention by those skilled in the art without departing from the spirit and scope of the present invention, and these modifications or substitutions are within the scope of the present invention/any person skilled in the art can easily conceive of the changes or substitutions within the technical scope of the present invention. Therefore, the protection scope of the present invention shall be subject to the protection scope of the appended claims.

Claims (10)

1. A power grid accident economic loss estimation method based on fault loss electric quantity is characterized by comprising the following steps:
s1, calculating the fault loss electric quantity of each fault line in the power grid accident;
s2, acquiring the load type characteristic of each fault line;
and S3, searching a ten-thousand-yuan production value electric quantity corresponding table according to the load type characteristics and the loss electric quantity of the fault line, and acquiring the economic loss of the fault line.
2. The grid accident economic loss estimation method based on fault loss electric quantity according to claim 1, characterized in that the step S3 is followed by the following steps:
and S4, setting a power distribution first-aid repair sequence of the fault line according to the economic loss of the fault line.
3. The grid accident economic loss estimation method based on fault loss electric quantity according to claim 2, wherein the step S4 is as follows:
s41, acquiring the economic loss of each fault line;
and S42, setting a fault line emergency repair grade according to the economic loss value of each fault line, and then carrying out power distribution emergency repair on the fault line according to the fault line emergency repair grade.
4. The grid accident economic loss estimation method based on fault loss electric quantity according to claim 3, wherein the step S42 includes the following steps:
s421, setting a rush-repair grade of the fault line according to the relation between the economic loss value of each fault line and a set threshold value;
when the economic loss value of the fault line exceeds a set threshold value; step S422 is entered;
when the economic loss value of the fault line does not exceed the set threshold value; proceeding to step S423;
s422, setting the fault line as a priority first-aid repair fault line, and setting the priority first-aid repair fault line to carry out power distribution first-aid repair according to the economic loss order; finishing;
and S423, setting the fault line as a secondary emergency repair fault line, and setting the secondary emergency repair fault line to perform power distribution emergency repair according to the distance sequence.
5. The grid accident economic loss estimation method based on fault loss electric quantity according to claim 1, wherein the step S1 is as follows:
s11, calculating the ultra-short term coincidence prediction curve of each fault line in the power grid accident;
s12, acquiring an actual power curve of each fault line;
and S13, taking the starting and stopping time of the power grid fault as a node, and carrying out integral calculation on the ultra-short term coincidence prediction curve and the actual power curve of the fault line to obtain the fault loss electric quantity of each fault line.
6. The grid accident economic loss estimation method based on fault loss electric quantity according to claim 1, wherein the step S3 is as follows:
s31, acquiring a ten-thousand-yuan production value electric quantity corresponding table;
s32, searching a ten-thousand-yuan production value column corresponding to the load type characteristic of the fault line in the ten-thousand-yuan production value electric quantity corresponding table;
and S33, searching the ten-thousand-yuan economic loss of the fault line in the corresponding ten-thousand-yuan production value list according to the fault loss electric quantity of the fault line.
7. A grid accident economic loss estimation system based on fault loss electric quantity is characterized by comprising:
the power loss calculation module (1) of the fault line is used for calculating the fault power loss of each fault line in the power grid accident;
the fault line load type characteristic acquisition module (2) is used for acquiring the load type characteristic of each fault line;
and the fault line economic loss acquisition module (3) is used for searching the ten-thousand-yuan generation value electric quantity corresponding table according to the fault line load type characteristics and the lost electric quantity to acquire the economic loss of the fault line.
8. A grid fault economic loss estimation system based on fault loss power as claimed in claim 7 further comprising:
the power distribution first-aid repair sequence setting module (4) is used for setting the power distribution first-aid repair sequence of the fault line according to the economic loss of the fault line; the power distribution first-aid repair sequence setting module (4) comprises:
a faulty line economic loss acquisition unit (4.1) for acquiring the economic loss of each faulty line;
and the fault line emergency repair grade setting unit (4.2) is used for setting the fault line emergency repair grade according to the economic loss value of each fault line and then carrying out power distribution emergency repair on the fault line according to the fault line emergency repair grade.
9. The grid accident economic loss estimation system based on fault loss power according to claim 7, characterized in that the fault line power loss calculation module (1) comprises:
the ultra-short term conformance preset curve calculation unit (1.1) is used for calculating an ultra-short term conformance prediction curve of each fault line in the power grid accident;
an actual power curve acquisition unit (1.2) for acquiring an actual power curve of each faulty line;
and the fault loss electric quantity calculating unit (1.3) is used for carrying out integral calculation on the ultra-short term coincidence prediction curve and the actual power curve of the fault line by taking the starting and stopping time of the power grid fault as a node to obtain the fault loss electric quantity of each fault line.
10. The grid accident economic loss estimation system based on fault loss electric quantity according to claim 7, characterized in that the fault line economic loss acquisition module (3) comprises:
a ten-thousand-yuan produced value electric quantity corresponding table obtaining unit (3.1) for obtaining the ten-thousand-yuan produced value electric quantity corresponding table;
the ten-thousand-yuan production value column searching unit (3.2) is used for searching a ten-thousand-yuan production value column corresponding to the load type characteristic of the fault line in the ten-thousand-yuan production value electric quantity corresponding table;
and the ten-thousand-yuan economic loss acquisition unit (3.3) is used for searching the ten-thousand-yuan economic loss of the fault line in the corresponding ten-thousand-yuan economic loss column according to the fault loss electric quantity of the fault line.
CN201910959101.4A 2019-10-10 2019-10-10 Power grid accident economic loss estimation method and system based on fault loss electric quantity Pending CN110705801A (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910959101.4A CN110705801A (en) 2019-10-10 2019-10-10 Power grid accident economic loss estimation method and system based on fault loss electric quantity

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910959101.4A CN110705801A (en) 2019-10-10 2019-10-10 Power grid accident economic loss estimation method and system based on fault loss electric quantity

Publications (1)

Publication Number Publication Date
CN110705801A true CN110705801A (en) 2020-01-17

Family

ID=69199001

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910959101.4A Pending CN110705801A (en) 2019-10-10 2019-10-10 Power grid accident economic loss estimation method and system based on fault loss electric quantity

Country Status (1)

Country Link
CN (1) CN110705801A (en)

Cited By (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115935114A (en) * 2022-11-29 2023-04-07 光大环境科技(中国)有限公司 Method for calculating power loss electric quantity of power grid fault in wind power plant

Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1188952A (en) * 1997-08-18 1998-07-29 北京供电公司 Wireless automatic alarming device for 10KV over high voltage distribution line failure
JP2013114418A (en) * 2011-11-28 2013-06-10 Ntt Facilities Inc Risk evaluation system, method of the same and program of the same
CN105762793A (en) * 2016-03-16 2016-07-13 国网江苏省电力公司电力科学研究院 Distribution network fault power failure loss assessment method considering distributed new energy
CN106127347A (en) * 2016-06-27 2016-11-16 华南理工大学 Consider the regional power grid accident load loss predictor method of voltage character of load
JP2017103862A (en) * 2015-11-30 2017-06-08 株式会社東芝 Power estimating apparatus, power estimating method, and power estimating program
CN106845678A (en) * 2016-12-19 2017-06-13 国家电网公司 A kind of power communication spare part resource the whole network integration dynamic adaptation method and device
CN107516170A (en) * 2017-08-30 2017-12-26 东北大学 A kind of difference self-healing control method based on probability of equipment failure and power networks risk
CN107766988A (en) * 2017-11-03 2018-03-06 国网湖南省电力公司 Disaster prevention emergency electricity optimization collocation method and device in a kind of urban area
CN107947174A (en) * 2017-12-26 2018-04-20 国网浙江省电力公司电力科学研究院 A kind of electric power compensation computational methods under urgent need response
CN109038546A (en) * 2018-07-10 2018-12-18 中国电力科学研究院有限公司 A kind of AC-DC hybrid power grid load restoration method and system based on VSC-HVDC system
CN109146124A (en) * 2018-06-27 2019-01-04 国家电网有限公司 A kind of distribution terminal transformation decision-making technique based on time-varying crash rate
CN110208019A (en) * 2019-05-14 2019-09-06 北京博华信智科技股份有限公司 A kind of dynamic equipment condition monitoring dynamic threshold method for early warning

Patent Citations (12)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN1188952A (en) * 1997-08-18 1998-07-29 北京供电公司 Wireless automatic alarming device for 10KV over high voltage distribution line failure
JP2013114418A (en) * 2011-11-28 2013-06-10 Ntt Facilities Inc Risk evaluation system, method of the same and program of the same
JP2017103862A (en) * 2015-11-30 2017-06-08 株式会社東芝 Power estimating apparatus, power estimating method, and power estimating program
CN105762793A (en) * 2016-03-16 2016-07-13 国网江苏省电力公司电力科学研究院 Distribution network fault power failure loss assessment method considering distributed new energy
CN106127347A (en) * 2016-06-27 2016-11-16 华南理工大学 Consider the regional power grid accident load loss predictor method of voltage character of load
CN106845678A (en) * 2016-12-19 2017-06-13 国家电网公司 A kind of power communication spare part resource the whole network integration dynamic adaptation method and device
CN107516170A (en) * 2017-08-30 2017-12-26 东北大学 A kind of difference self-healing control method based on probability of equipment failure and power networks risk
CN107766988A (en) * 2017-11-03 2018-03-06 国网湖南省电力公司 Disaster prevention emergency electricity optimization collocation method and device in a kind of urban area
CN107947174A (en) * 2017-12-26 2018-04-20 国网浙江省电力公司电力科学研究院 A kind of electric power compensation computational methods under urgent need response
CN109146124A (en) * 2018-06-27 2019-01-04 国家电网有限公司 A kind of distribution terminal transformation decision-making technique based on time-varying crash rate
CN109038546A (en) * 2018-07-10 2018-12-18 中国电力科学研究院有限公司 A kind of AC-DC hybrid power grid load restoration method and system based on VSC-HVDC system
CN110208019A (en) * 2019-05-14 2019-09-06 北京博华信智科技股份有限公司 A kind of dynamic equipment condition monitoring dynamic threshold method for early warning

Non-Patent Citations (4)

* Cited by examiner, † Cited by third party
Title
曲朝阳等: "电网企业信息运维故障诊断模型的研究与应用", 《电测与仪表》 *
李福禄等: "电力线损实时监测技术及其应用实例", 《电力需求侧管理》 *
莫汉•木纳辛格等: "《电力系统可靠度和计划的经济性 理论和实例分析》", 28 February 1987, 水利电力出版社 *
袁修广等: "计及故障停电经济损失的配电网风险评估", 《电力系统及其自动化学报》 *

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN115935114A (en) * 2022-11-29 2023-04-07 光大环境科技(中国)有限公司 Method for calculating power loss electric quantity of power grid fault in wind power plant
CN115935114B (en) * 2022-11-29 2023-10-03 光大环境科技(中国)有限公司 Method for calculating power grid fault loss electric quantity in wind power plant

Similar Documents

Publication Publication Date Title
Li et al. A distributed transmission-distribution-coupled static voltage stability assessment method considering distributed generation
Shu et al. Analysis and recommendations for the adaptability of China's power system security and stability relevant standards
WO2022105944A1 (en) A method for calculating optimal load capacity of 10 kv feeder taking into account impact of different load structures and reliabilities
CN112104005B (en) Power grid dispatching method and system considering new energy prediction uncertainty
CN108599379B (en) Power monitoring system for micro-grid group
WO2022242020A1 (en) Method and system for optimizing direct current transmission limit within planning period
CN105720575A (en) Partition optimization method for power system operation reserves of considering interval support and section constraints
Estebsari et al. IoT-enabled real-time management of smart grids with demand response aggregators
CN109586272A (en) A kind of generation method and system of power grid continuous operation emulation section
CN110705801A (en) Power grid accident economic loss estimation method and system based on fault loss electric quantity
CN104809543A (en) Power grid operation mode generating method based on monthly power transmission and distribution equipment maintenance plan
Vempere et al. Methodology for investment evaluation in electricity generation modules according to the requirements of the European Union
WO2023086017A2 (en) Method and apparatus for determining state of phovoltaic power station, device, and readable storage medium
CN113673792B (en) Method, system, equipment and storage medium for making power failure maintenance plan
Liu et al. An optimization method of maintenance strategy for power equipment
Momoh et al. Voltage stability enhancement using Phasor Measurement Unit (PMU) technology
Li et al. Fast Frequency Response Reserve Planning for Power Systems Considering Homogeneous Extreme Risks
CN111859585B (en) Transmission and distribution cooperative equipment bearing capacity calculation method and system
Ahangar et al. Negative effects of cyber network (control, monitoring, and protection) on reliability of smart grids based on DG penetration
Cai et al. Study on reliability assessment of distribution networks containing distributed power supplies
Zhou et al. Demand side response participation in reserve configuration optimization based on decomposition and coordination
Nassaj et al. A dynamic voltage control scheme by employing cooperative game theory
Tuinema et al. Network redundancy versus generation reserve in combined onshore-offshore transmission networks
CN111191948A (en) Power grid operation state evaluation method and system for multi-provincial union intra-day connecting line
Guoyong et al. Rationality evaluation of schedule power flow data for large power grid

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
RJ01 Rejection of invention patent application after publication
RJ01 Rejection of invention patent application after publication

Application publication date: 20200117