WO2022242020A1 - Method and system for optimizing direct current transmission limit within planning period - Google Patents

Method and system for optimizing direct current transmission limit within planning period Download PDF

Info

Publication number
WO2022242020A1
WO2022242020A1 PCT/CN2021/123951 CN2021123951W WO2022242020A1 WO 2022242020 A1 WO2022242020 A1 WO 2022242020A1 CN 2021123951 W CN2021123951 W CN 2021123951W WO 2022242020 A1 WO2022242020 A1 WO 2022242020A1
Authority
WO
WIPO (PCT)
Prior art keywords
power
cost
risk
planning
operating conditions
Prior art date
Application number
PCT/CN2021/123951
Other languages
French (fr)
Chinese (zh)
Inventor
张红丽
刘福锁
李威
余思聪
倪禛霖
王玉
薛峰
李兆伟
吴雪莲
郜建良
雷杰
Original Assignee
南瑞集团有限公司
国电南瑞科技股份有限公司
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by 南瑞集团有限公司, 国电南瑞科技股份有限公司 filed Critical 南瑞集团有限公司
Publication of WO2022242020A1 publication Critical patent/WO2022242020A1/en

Links

Images

Classifications

    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J3/00Circuit arrangements for ac mains or ac distribution networks
    • H02J3/36Arrangements for transfer of electric power between ac networks via a high-tension dc link
    • HELECTRICITY
    • H02GENERATION; CONVERSION OR DISTRIBUTION OF ELECTRIC POWER
    • H02JCIRCUIT ARRANGEMENTS OR SYSTEMS FOR SUPPLYING OR DISTRIBUTING ELECTRIC POWER; SYSTEMS FOR STORING ELECTRIC ENERGY
    • H02J2203/00Indexing scheme relating to details of circuit arrangements for AC mains or AC distribution networks
    • H02J2203/20Simulating, e g planning, reliability check, modelling or computer assisted design [CAD]
    • YGENERAL TAGGING OF NEW TECHNOLOGICAL DEVELOPMENTS; GENERAL TAGGING OF CROSS-SECTIONAL TECHNOLOGIES SPANNING OVER SEVERAL SECTIONS OF THE IPC; TECHNICAL SUBJECTS COVERED BY FORMER USPC CROSS-REFERENCE ART COLLECTIONS [XRACs] AND DIGESTS
    • Y04INFORMATION OR COMMUNICATION TECHNOLOGIES HAVING AN IMPACT ON OTHER TECHNOLOGY AREAS
    • Y04SSYSTEMS INTEGRATING TECHNOLOGIES RELATED TO POWER NETWORK OPERATION, COMMUNICATION OR INFORMATION TECHNOLOGIES FOR IMPROVING THE ELECTRICAL POWER GENERATION, TRANSMISSION, DISTRIBUTION, MANAGEMENT OR USAGE, i.e. SMART GRIDS
    • Y04S10/00Systems supporting electrical power generation, transmission or distribution
    • Y04S10/50Systems or methods supporting the power network operation or management, involving a certain degree of interaction with the load-side end user applications

Definitions

  • the invention relates to a method and system for optimizing DC transmission limits within a planning period, and belongs to the technical field of power grid planning.
  • the present invention provides a DC transmission limit optimization method and system within a planning period, which solves the problems disclosed in the background technology.
  • a method for optimizing DC transmission limits within a planning cycle comprising:
  • the annual operating risk cost is calculated according to the cost of power abandonment, the cost of purchased power, the cost of backup, and the emergency control cost of the sending power grid under the failure of the second-level safety standard;
  • the DC maximum transmittable power corresponding to the minimum total cost of risk is used to construct the DC transmission limit sequence within the planning period.
  • typical operating conditions include Fengda, Fengxiao, Fengpingda, Kuda, Kuxiao and Kupingda;
  • typical operating conditions include Fengda, Fengxiao, Fengpingda, Kuda, Kuxiao, Kupingda, new energy Dafa and new energy Xiaofa.
  • the formula for calculating the electricity abandonment cost is:
  • C discard is the cost of electricity discarding
  • j and ⁇ j are the operating conditions and the probability of operating conditions in which the power arranged by DC is greater than the maximum transmittable power of DC, respectively, is the maximum transmittable power of DC
  • k is the unit cost of curtailment
  • P j is the DC power arranged in operating condition j.
  • C risk is the operation risk cost
  • C discard is the power abandonment cost
  • ⁇ i , ⁇ t are the operating condition i probability and the corresponding disturbance probability respectively
  • C ec , C re , C pur are the emergency control cost, backup cost and The cost of purchased electricity.
  • the specific process is as follows:
  • a DC transmission limit optimization system within a planning period comprising:
  • Operating condition acquisition module acquire the typical operating conditions of the sending power grid every year within the planning period;
  • Transmittable power module According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
  • Abandonment cost module According to the annual DC maximum transmittable power, calculate the electricity abandonment cost caused by the failure of DC to send out full power, and adjust all operating conditions;
  • Operational risk cost module based on the adjusted operating conditions, calculate the annual operational risk cost based on the cost of power abandonment, cost of purchased power, backup cost, and emergency control cost of the sending power grid under the second-level safety standard failure;
  • Total risk cost module Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
  • Limit sequence module use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the DC transmission limit sequence within the planning period.
  • a computer-readable storage medium storing one or more programs, the one or more programs including instructions that, when executed by a computing device, cause the computing device to perform a DC transmission limit optimization method within a planning period.
  • a computing device comprising one or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and configured to be executed by the one or more Executed by a plurality of processors, the one or more programs include instructions for executing the method for optimizing the DC transmission limit within the planning period.
  • the present invention analyzes each year within the planning cycle to obtain the maximum transmittable power of direct current per year, the loss of abandoned power caused by the inability to send out full power of direct current, emergency control costs, outsourced power costs, and backup costs Calculate the unified monetization to form the operation risk cost, combine multiple sets of risk threshold sequences randomly generated, calculate the total risk cost under each risk threshold sequence, and use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the planning cycle
  • the internal DC transmission limit sequence through reasonable planning of DC transmission limits, realizes the seamless connection from planning to operation, and can guide power system planners to fully consider the operation risks after DC is put into operation, so that the coordinated development of power supply-grid-DC load can be achieved.
  • Fig. 1 is the flowchart of the method of the present invention.
  • a DC transmission limit optimization method within a planning cycle includes the following steps:
  • Step 1 Obtain the typical operating conditions of the sending power grid every year within the planning period;
  • Step 2 calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
  • Step 3 according to the annual DC maximum transmittable power, calculate the cost of electricity curtailment caused by the failure of DC to send out full power, and adjust all operating conditions;
  • Step 4 based on the adjusted operating conditions, calculate the annual operating risk cost based on the cost of power abandonment, cost of purchased power, backup cost, and emergency control cost of the sending power grid under the failure of the second-level safety standard;
  • Step 5 Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
  • Step 6 Use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the DC transmission limit sequence within the planning period.
  • the above method is based on "decoupling-aggregation”. Firstly, decoupling analysis is carried out every year in the planning cycle to obtain the maximum DC transmittable power per year, the loss of power curtailment caused by the inability to send DC at full power, emergency control costs, and outsourced power costs. , the reserve cost is uniformly monetized to form the operational risk cost, and then combined with multiple groups of randomly generated risk threshold sequences, the total risk cost under each risk threshold sequence is aggregated and calculated, and finally the annual DC maximum possible cost corresponding to the minimum total risk cost is used. Transmission power, constructing the DC transmission limit sequence within the planning period.
  • the probability corresponding to the operating conditions, as well as the disturbance and the disturbance probability corresponding to the production operating conditions will also be obtained accordingly.
  • the typical operating conditions include Fengda, Fengxiao, Fengpingda, Kuda, Kuxiao and Kupingda; if the sending grid is a grid with new energy ( Generally, it includes a large amount of new energy transmission), and on the basis of the above-mentioned typical operating conditions, it also includes new energy large and new energy small.
  • the probability corresponding to the operating condition can be expressed as the number of hours of the operating condition in a year divided by 8760h; the disturbance is the first-level safety standard failure and the second-level safety standard stipulated in the "GB 38755-2019 Power System Safety and Stability Guidelines".
  • N-1 faults in the disturbance probability can be set to 0.01 times/km
  • N-2 faults can be set to 0.002 times/km
  • DC unipolar faults can be set to 1.6 times/year
  • DC bipolar faults can be set to 0.1 times/km Article. Year.
  • the annual DC maximum transmittable power can be calculated, and the specific process is as follows:
  • the DC transmission power is not limited
  • the transient overvoltage shall be checked according to not exceeding the busbar voltage protection setting value of the converter station 1.3p.u./500ms, and the steady-state voltage shall be checked according to not exceeding 550kV/half an hour; Verify that the voltage of the new energy collection busbar does not exceed the new energy grid-related standards;
  • the transient overvoltage and steady-state overvoltage of the converter station/DC near-area AC busbar/new energy collection busbar exceed the protection setting value, that is, there is a DC fault that does not meet the requirements
  • reduce the DC power in this working condition until the transient overvoltage and steady-state overvoltage of the converter station/DC near-area AC busbar/new energy collection busbar are within the standard after the DC disturbance.
  • the DC power in this working condition is the maximum DC transmission power P DC voltage subject to voltage stability constraints;
  • the highest frequency shall be checked according to the action setting value of 50.8Hz/500ms for the high-cycle cutting machine, and the lowest frequency shall not exceed the action setting value of 49Hz for low-cycle load shedding; when there is new energy in the DC near area, it shall also be checked
  • the frequency of nuclear new energy does not exceed the new energy network-related standards; for DC with simultaneous transmission and reception, the frequency response characteristics after the failure of DC commutation at the same transmission and reception should also be checked;
  • C discard is the cost of electricity discarding
  • j and ⁇ j are the operating conditions and the probability of operating conditions in which the power arranged by DC is greater than the maximum transmittable power of DC, respectively, is the maximum transmittable power of DC
  • k is the unit cost of power abandonment, which can be determined by referring to the unit grid price of power sources.
  • the unit cost of power abandonment of hydropower is 227.7 yuan/MWh
  • P j is the DC power arranged in operating condition j.
  • Adjust all operating conditions according to the annual DC maximum transmittable power When adjusting all operating conditions, for operating conditions where the DC power is greater than the DC maximum transmittable power, adjust the DC power to the maximum transmittable power, and reduce the supporting power supply first contribute.
  • C risk is the operation risk cost
  • ⁇ i , ⁇ t are the probability of operating condition i and the corresponding disturbance probability, respectively
  • C ec , C re , and C pur are the emergency control cost, backup cost and purchased electricity cost, respectively.
  • the above-mentioned random generation of risk threshold sequences in multiple sets of planning cycles calculates the total risk cost of each set of risk threshold sequences from the start year to the end year of the planning cycle.
  • the specific process is as follows:
  • the above method considers risks such as safety and adequacy in operation and monetizes them, and considers the risk cost in operation and the economics of DC power transmission as a whole, avoiding the problems caused by single consideration of operation or planning.
  • the DC transmission power is not coordinated with the power supply and the grid, resulting in insufficient DC carrying capacity of the grid; through reasonable planning of the DC transmission limit, the seamless connection between planning and operation can be realized, and it can guide power system planners to fully consider the operation after DC is put into operation Risks make the power supply-grid-DC load coordinated development.
  • a DC transmission limit optimization system within a planning cycle characterized in that: comprising,
  • Operating condition acquisition module acquire the typical operating conditions of the sending power grid every year within the planning period;
  • Transmittable power module According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
  • Abandonment cost module According to the annual DC maximum transmittable power, calculate the electricity abandonment cost caused by the failure of DC to send out full power, and adjust all operating conditions;
  • Operational risk cost module based on the adjusted operating conditions, calculate the annual operational risk cost based on the cost of power abandonment, cost of purchased power, backup cost, and emergency control cost of the sending power grid under the second-level safety standard failure;
  • Total risk cost module Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
  • Limit sequence module use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the DC transmission limit sequence within the planning period.
  • a computer-readable storage medium storing one or more programs, the one or more programs including instructions that, when executed by a computing device, cause the computing device to perform a DC transmission limit optimization method within a planning period.
  • a computing device comprising one or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and configured to be executed by the one or more Executed by a plurality of processors, the one or more programs include instructions for executing the method for optimizing the DC transmission limit within the planning period.
  • the embodiments of the present application may be provided as methods, systems, or computer program products. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) having computer-usable program code embodied therein.
  • computer-usable storage media including but not limited to disk storage, CD-ROM, optical storage, etc.
  • These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing apparatus to operate in a specific manner, such that the instructions stored in the computer-readable memory produce an article of manufacture comprising instruction means, the instructions
  • the device realizes the function specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.

Landscapes

  • Engineering & Computer Science (AREA)
  • Power Engineering (AREA)
  • Supply And Distribution Of Alternating Current (AREA)

Abstract

Disclosed in the present invention are a method and system for optimizing a direct current transmission limit within a planning period. The method of the present invention comprises: performing annual analysis within the planning period; obtaining annual maximum direct current transmittable power; performing unified monetization on abandoned power loss caused by incapability of transmitting direct current at full power, emergency control cost, outsourcing power cost and standby cost to form operation risk cost; calculating total risk cost under each group of risk threshold sequence in combination with multiple groups of risk threshold sequences which are randomly generated; constructing a direct current transmission limit sequence within the planning period by employing the annual maximum direct current transmittable power corresponding to the minimum total risk cost; and reasonably planning a direct current transmission limit, so as to realize seamless connection from planning to operation. Power system planning personnel can be guided to fully consider operation risks after direct current commissioning, thereby realizing power supply-power grid-direct current load collaborative development.

Description

一种规划周期内直流传输极限优化方法及系统A method and system for optimizing DC transmission limits within a planning period 技术领域technical field
本发明涉及一种规划周期内直流传输极限优化方法及系统,属于电网规划技术领域。The invention relates to a method and system for optimizing DC transmission limits within a planning period, and belongs to the technical field of power grid planning.
背景技术Background technique
大力开发可再生能源已成为我国能源发展的重要战略共识,然而,由于规划、管理、技术等方面的原因,我国可再生能源的“弃水弃光弃风”问题十分突出。以四川电网为例,随着四川投产的三回特高压直流线路形成了四川电网“强直弱交”的电力结构特征,外送通道建设和水电装机投产规模不匹配、外送需求和省外接纳具体情况不匹配均可造成弃水,合理的规划建设特高压直流是缓解弃水问题以及全国能源优化配置的重要举措。Vigorously developing renewable energy has become an important strategic consensus for my country's energy development. However, due to planning, management, and technical reasons, the problem of "abandoning water, light, and wind" in my country's renewable energy is very prominent. Taking Sichuan Power Grid as an example, with the three-circuit UHV DC line put into operation in Sichuan, the power structure characteristics of Sichuan Power Grid have been formed. The mismatch of specific conditions can lead to water abandonment. Reasonable planning and construction of UHV DC is an important measure to alleviate the problem of water abandonment and optimize the allocation of energy in the country.
传统交直流电网结构优化研究重点考虑一次系统加强对送受电需求和能力的影响,提出直流落点方式及交流网架构建方法,实现供电的经济性、可靠性,在规划方案制定时主要考虑电力电量平衡、N-1约束及经济性,不考虑小概率的极端工况。电网的运行情况主要取决于电网规划以及电力设计水平,由于特高压交流电网建设滞后,“强直弱交”结构的长期存在,现有运行极限计及了极端工况N-2故障后的稳定约束,导致了我国交直流电网运行存在较大的安全稳定风险。在直流投产的过渡期通常达不到规划设计的额定容量,在直流实际运行中过于依赖二次系统弥补规划带来的电网结构不足。Traditional AC/DC power grid structure optimization research focuses on the impact of primary system strengthening on the demand and capacity of power transmission and reception, and proposes the way of DC drop point and the construction method of AC grid structure to realize the economy and reliability of power supply, and mainly considers power when formulating the planning scheme. Power balance, N-1 constraint and economy, do not consider extreme working conditions with small probability. The operation of the power grid mainly depends on the power grid planning and power design level. Due to the lag in the construction of the UHV AC power grid and the long-term existence of the "strong straight and weak AC" structure, the existing operating limits have taken into account the stability constraints after the extreme working condition N-2 fault , leading to greater security and stability risks in the operation of AC and DC power grids in my country. During the transitional period of DC commissioning, the planned and designed rated capacity is usually not reached, and in the actual operation of DC, it relies too much on the secondary system to make up for the lack of grid structure caused by planning.
新版《电力系统安全稳定导则》(GB38755-2019)明确要求,在电网规划阶段要统筹考虑稳定控制等二次系统,计算远景系统的稳定性能,使得电力系统发生稳定破坏时,能够有预定的措施以防止事故范围扩大,减少事故损失;同 时规定了电力系统的二次设备(包括继电保护装置、安全自动装置、自动化设备、通信设备等)的参数设定及耐受能力应与一次设备相适应因此。因此,在直流的规划设计阶段,亟需考虑运行风险的直流传输极限优化方法。The new version of "Guidelines for Power System Safety and Stability" (GB38755-2019) clearly requires that secondary systems such as stability control should be considered in the planning stage of the power grid, and the stability performance of the long-term system should be calculated so that when the stability of the power system is damaged, there can be predetermined Measures to prevent the scope of accidents from expanding and reduce accident losses; at the same time, it is stipulated that the parameter setting and tolerance of secondary equipment (including relay protection devices, safety automatic devices, automation equipment, communication equipment, etc.) of the power system should be the same as those of primary equipment Adapt accordingly. Therefore, in the planning and design stage of DC, there is an urgent need for a DC transmission limit optimization method that considers operational risks.
发明内容Contents of the invention
本发明提供了一种规划周期内直流传输极限优化方法及系统,解决了背景技术中披露的问题。The present invention provides a DC transmission limit optimization method and system within a planning period, which solves the problems disclosed in the background technology.
为了解决上述技术问题,本发明所采用的技术方案是:In order to solve the problems of the technologies described above, the technical solution adopted in the present invention is:
一种规划周期内直流传输极限优化方法,包括,A method for optimizing DC transmission limits within a planning cycle, comprising:
获取规划周期内每年送端电网典型的运行工况;Obtain the typical operating conditions of the sending power grid every year within the planning period;
根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率;According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
根据每年直流最大可传输功率,统计因直流不能满功率送出而导致的弃电代价,调整所有运行工况;According to the annual DC maximum transmittable power, calculate the cost of power abandonment caused by the failure of DC to send out full power, and adjust all operating conditions;
基于调整后的运行工况,根据弃电代价、外购电成本、备用成本以及第二级安全标准故障下送端电网的紧急控制代价,计算每年的运行风险代价;Based on the adjusted operating conditions, the annual operating risk cost is calculated according to the cost of power abandonment, the cost of purchased power, the cost of backup, and the emergency control cost of the sending power grid under the failure of the second-level safety standard;
随机生成多组规划周期内的风险阈值序列,根据运行风险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本;Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost under each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列。The DC maximum transmittable power corresponding to the minimum total cost of risk is used to construct the DC transmission limit sequence within the planning period.
若送端电网为没有新能源送出的电网,典型的运行工况包括丰大、丰小、丰平大、枯大、枯小和枯平大;If the power grid at the sending end is a power grid without new energy transmission, typical operating conditions include Fengda, Fengxiao, Fengpingda, Kuda, Kuxiao and Kupingda;
若送端电网为有新能源送出的电网,典型的运行工况包括丰大、丰小、丰 平大、枯大、枯小、枯平大、新能源大发和新能源小发。If the power grid at the sending end is a power grid with new energy sent, typical operating conditions include Fengda, Fengxiao, Fengpingda, Kuda, Kuxiao, Kupingda, new energy Dafa and new energy Xiaofa.
根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率,具体过程为,According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints. The specific process is as follows:
计算所有运行工况下直流有效短路比,获取受直流有效短路比约束的直流最大传输功率;Calculate the DC effective short-circuit ratio under all operating conditions to obtain the maximum DC transmission power constrained by the DC effective short-circuit ratio;
计算所有运行工况下发生交流故障后直流近区交流断面输电功率,获取受交流通道电力组织约束的直流最大传输功率;Calculate the transmission power of the DC near-area AC section after the AC fault occurs under all operating conditions, and obtain the maximum DC transmission power constrained by the power organization of the AC channel;
计算直流扰动冲击下换流站及直流近区交流母线暂态过电压和稳态过电压受限情况,获取受电压稳定约束的直流最大传输功率;Calculate the transient overvoltage and steady overvoltage limitation of the converter station and the AC bus in the DC vicinity under the impact of DC disturbance, and obtain the maximum DC transmission power subject to voltage stability constraints;
计算直流扰动冲击下系统频率受限情况,获取受频率稳定约束的直流最大可传输功率;Calculate the frequency limitation of the system under the impact of DC disturbance, and obtain the maximum transmittable power of DC subject to the frequency stability constraint;
计算同时受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率。Calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization, voltage stability and frequency stability.
弃电代价的计算公式为,The formula for calculating the electricity abandonment cost is:
Figure PCTCN2021123951-appb-000001
Figure PCTCN2021123951-appb-000001
其中,C discard为弃电代价,j、λ j分别为直流安排的功率大于直流最大可传输功率的运行工况及运行工况概率,
Figure PCTCN2021123951-appb-000002
为直流最大可传输功率,k为弃电的单位代价,P j为运行工况j中安排的直流功率。
Among them, C discard is the cost of electricity discarding, j and λ j are the operating conditions and the probability of operating conditions in which the power arranged by DC is greater than the maximum transmittable power of DC, respectively,
Figure PCTCN2021123951-appb-000002
is the maximum transmittable power of DC, k is the unit cost of curtailment, and P j is the DC power arranged in operating condition j.
调整所有运行工况时,对于直流安排的功率大于直流最大可传输功率的运行工况,将直流功率调整至最大可传输功率,优先减少配套电源出力。When adjusting all operating conditions, for operating conditions where the power of the DC arrangement is greater than the maximum transmittable power of the DC, adjust the DC power to the maximum transmittable power, and give priority to reducing the output of the supporting power supply.
计算运行风险代价的公式为,The formula for calculating the running risk cost is,
Figure PCTCN2021123951-appb-000003
Figure PCTCN2021123951-appb-000003
其中,C risk为运行风险代价,C discard为弃电代价,λ i、ω t分别为运行工况i概率及对应扰动概率,C ec、C re、C pur分别为紧急控制代价、备用成本和外购电成本。 Among them, C risk is the operation risk cost, C discard is the power abandonment cost, λ i , ω t are the operating condition i probability and the corresponding disturbance probability respectively, C ec , C re , C pur are the emergency control cost, backup cost and The cost of purchased electricity.
随机生成多组规划周期内的风险阈值序列,根据运行风险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本,具体过程为,Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost. The specific process is as follows:
随机生成多组规划周期内的风险阈值序列;其中,各组风险阈值序列的起始年和终点年分别与规划周期的起始年和终点年一致,各组风险阈值序列均包含规划周期各年的风险阈值;Randomly generate multiple sets of risk threshold sequences in the planning cycle; the start year and end year of each set of risk threshold sequences are consistent with the start year and end year of the planning cycle, and each set of risk threshold sequences includes the risk threshold;
针对每组风险阈值序列,对运行风险代价超过相应风险阈值的年份,进行规划措施优化选择,计算风险阈值序列下的风险总成本;其中,风险总成本为规划周期内每年的运行风险代价和规划措施成本累加。For each set of risk threshold series, optimize the selection of planning measures for the year in which the operating risk cost exceeds the corresponding risk threshold, and calculate the total risk cost under the risk threshold sequence; where the total risk cost is the annual operating risk cost and planning Measures add up in cost.
一种规划周期内直流传输极限优化系统,包括,A DC transmission limit optimization system within a planning period, comprising:
工况获取模块:获取规划周期内每年送端电网典型的运行工况;Operating condition acquisition module: acquire the typical operating conditions of the sending power grid every year within the planning period;
可传输功率模块:根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率;Transmittable power module: According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
弃电代价模块:根据每年直流最大可传输功率,统计因直流不能满功率送出而导致的弃电代价,调整所有运行工况;Abandonment cost module: According to the annual DC maximum transmittable power, calculate the electricity abandonment cost caused by the failure of DC to send out full power, and adjust all operating conditions;
运行风险代价模块:基于调整后的运行工况,根据弃电代价、外购电成本、备用成本以及第二级安全标准故障下送端电网的紧急控制代价,计算每年的运行风险代价;Operational risk cost module: based on the adjusted operating conditions, calculate the annual operational risk cost based on the cost of power abandonment, cost of purchased power, backup cost, and emergency control cost of the sending power grid under the second-level safety standard failure;
风险总成本模块:随机生成多组规划周期内的风险阈值序列,根据运行风 险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本;Total risk cost module: Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
极限序列模块:采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列。Limit sequence module: use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the DC transmission limit sequence within the planning period.
一种存储一个或多个程序的计算机可读存储介质,所述一个或多个程序包括指令,所述指令当由计算设备执行时,使得所述计算设备执行规划周期内直流传输极限优化方法。A computer-readable storage medium storing one or more programs, the one or more programs including instructions that, when executed by a computing device, cause the computing device to perform a DC transmission limit optimization method within a planning period.
一种计算设备,包括一个或多个处理器、一个或多个存储器以及一个或多个程序,其中一个或多个程序存储在所述一个或多个存储器中并被配置为由所述一个或多个处理器执行,所述一个或多个程序包括用于执行规划周期内直流传输极限优化方法的指令。A computing device comprising one or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and configured to be executed by the one or more Executed by a plurality of processors, the one or more programs include instructions for executing the method for optimizing the DC transmission limit within the planning period.
本发明所达到的有益效果:本发明对规划周期内每年进行分析,获取每年直流最大可传输功率,将直流不能满功率送出导致的弃电损失、以及紧急控制代价、外购电成本、备用成本计统一货币化,形成运行风险代价,结合随机生成的多组风险阈值序列,计算每组风险阈值序列下的风险总成本,采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列,通过合理规划直流传输极限,实现规划到运行的无缝衔接,能够指导电力系统规划人员充分考虑直流投运后的运行风险,使得电源-电网-直流负荷协同发展。Beneficial effects achieved by the present invention: the present invention analyzes each year within the planning cycle to obtain the maximum transmittable power of direct current per year, the loss of abandoned power caused by the inability to send out full power of direct current, emergency control costs, outsourced power costs, and backup costs Calculate the unified monetization to form the operation risk cost, combine multiple sets of risk threshold sequences randomly generated, calculate the total risk cost under each risk threshold sequence, and use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the planning cycle The internal DC transmission limit sequence, through reasonable planning of DC transmission limits, realizes the seamless connection from planning to operation, and can guide power system planners to fully consider the operation risks after DC is put into operation, so that the coordinated development of power supply-grid-DC load can be achieved.
附图说明Description of drawings
图1为本发明方法的流程图。Fig. 1 is the flowchart of the method of the present invention.
具体实施方式Detailed ways
下面结合附图对本发明作进一步描述。以下实施例仅用于更加清楚地说明 本发明的技术方案,而不能以此来限制本发明的保护范围。The present invention will be further described below in conjunction with the accompanying drawings. The following examples are only used to more clearly illustrate the technical solutions of the present invention, but cannot limit the protection scope of the present invention with this.
如图1所示,一种规划周期内直流传输极限优化方法,包括以下步骤:As shown in Figure 1, a DC transmission limit optimization method within a planning cycle includes the following steps:
步骤1,获取规划周期内每年送端电网典型的运行工况;Step 1. Obtain the typical operating conditions of the sending power grid every year within the planning period;
步骤2,根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率;Step 2, according to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
步骤3,根据每年直流最大可传输功率,统计因直流不能满功率送出而导致的弃电代价,调整所有运行工况;Step 3, according to the annual DC maximum transmittable power, calculate the cost of electricity curtailment caused by the failure of DC to send out full power, and adjust all operating conditions;
步骤4,基于调整后的运行工况,根据弃电代价、外购电成本、备用成本以及第二级安全标准故障下送端电网的紧急控制代价,计算每年的运行风险代价;Step 4, based on the adjusted operating conditions, calculate the annual operating risk cost based on the cost of power abandonment, cost of purchased power, backup cost, and emergency control cost of the sending power grid under the failure of the second-level safety standard;
步骤5,随机生成多组规划周期内的风险阈值序列,根据运行风险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本;Step 5: Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
步骤6,采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列。Step 6: Use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the DC transmission limit sequence within the planning period.
上述方法基于“解耦-聚合”,先对规划周期内每年进行解耦分析,获取每年直流最大可传输功率,将直流不能满功率送出导致的弃电损失、以及紧急控制代价、外购电成本、备用成本计统一货币化,形成运行风险代价,然后结合随机生成的多组风险阈值序列,聚合计算每组风险阈值序列下的风险总成本,最后采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列。The above method is based on "decoupling-aggregation". Firstly, decoupling analysis is carried out every year in the planning cycle to obtain the maximum DC transmittable power per year, the loss of power curtailment caused by the inability to send DC at full power, emergency control costs, and outsourced power costs. , the reserve cost is uniformly monetized to form the operational risk cost, and then combined with multiple groups of randomly generated risk threshold sequences, the total risk cost under each risk threshold sequence is aggregated and calculated, and finally the annual DC maximum possible cost corresponding to the minimum total risk cost is used. Transmission power, constructing the DC transmission limit sequence within the planning period.
在获取运行工况时,还会相应的获取运行工况对应的概率,以及生产运行工况相应的扰动和扰动概率。When acquiring the operating conditions, the probability corresponding to the operating conditions, as well as the disturbance and the disturbance probability corresponding to the production operating conditions will also be obtained accordingly.
若送端电网为没有新能源送出的电网,典型的运行工况包括丰大、丰小、 丰平大、枯大、枯小和枯平大;若送端电网为有新能源送出的电网(一般包含大量新能源送出),在上述典型运行工况的基础上,还包括新能源大发和新能源小发。If the sending grid is a grid without new energy, the typical operating conditions include Fengda, Fengxiao, Fengpingda, Kuda, Kuxiao and Kupingda; if the sending grid is a grid with new energy ( Generally, it includes a large amount of new energy transmission), and on the basis of the above-mentioned typical operating conditions, it also includes new energy large and new energy small.
运行工况对应的概率可以表示为运行工况一年中出现的小时数除以8760h;扰动为《GB 38755-2019电力系统安全稳定导则》规定的第一级安全标准故障和第二级安全标准故障,扰动概率中N-1故障可取为0.01次/km,N-2故障可取为0.002次/km,直流单极故障可取为1.6次/条.年,直流双极故障可取为0.1次/条.年。The probability corresponding to the operating condition can be expressed as the number of hours of the operating condition in a year divided by 8760h; the disturbance is the first-level safety standard failure and the second-level safety standard stipulated in the "GB 38755-2019 Power System Safety and Stability Guidelines". For standard faults, N-1 faults in the disturbance probability can be set to 0.01 times/km, N-2 faults can be set to 0.002 times/km, DC unipolar faults can be set to 1.6 times/year, and DC bipolar faults can be set to 0.1 times/km Article. Year.
基于获得运行工况,可计算出每年直流最大可传输功率,具体过程如下:Based on the obtained operating conditions, the annual DC maximum transmittable power can be calculated, and the specific process is as follows:
21)计算所有运行工况下直流有效短路比,获取受直流有效短路比约束的直流最大传输功率;21) Calculate the DC effective short-circuit ratio under all operating conditions, and obtain the maximum DC transmission power constrained by the DC effective short-circuit ratio;
当所有运行工况下直流有效短路比均大于2,则直流传输功率不受限;When the DC effective short-circuit ratio is greater than 2 under all operating conditions, the DC transmission power is not limited;
当存在直流有效短路比小于2的工况时,降低该工况中直流功率,重新计算直流有效短路比,当直流有效短路比刚好等于2时,所对应的直流功率为受短路比约束的直流最大传输功率P DC ESCRWhen there is a working condition where the DC effective short-circuit ratio is less than 2, reduce the DC power in this working condition and recalculate the DC effective short-circuit ratio. When the DC effective short-circuit ratio is just equal to 2, the corresponding DC power is the DC power constrained by the short-circuit ratio Maximum transmission power P DC ESCR ;
22)计算所有运行工况下发生交流故障后直流近区交流断面输电功率,获取受交流通道电力组织约束的直流最大传输功率;22) Calculate the transmission power of the DC near-area AC section after the AC fault occurs under all operating conditions, and obtain the maximum DC transmission power constrained by the power organization of the AC channel;
由于直流需要通过交流断面汇集网内已投产电源,通常情况下需要校核直流近区交流N-1、N-2故障后系统的热稳定、暂态稳定、动态稳定的情况,当近区交流N-1、N-2故障后存在线路过热稳/系统暂态失稳/系统动态失稳,降低交流断面输电功率,直到交流N-1、N-2故障后系统稳定。Since the DC needs to collect the power supply in the network through the AC section, it is usually necessary to check the thermal stability, transient stability, and dynamic stability of the system after the DC near-area AC N-1 and N-2 faults, when the near-area AC After N-1 and N-2 faults, if there is line overheating stability/system transient instability/system dynamic instability, reduce the transmission power of the AC section until the system is stable after AC N-1 and N-2 faults.
当直流近区所有汇集的交流断面最大输电功率P DC AC小于直流额定功率时, 受交流通道电力组织约束的直流最大传输功率即为P DC ACWhen the maximum transmission power P DC AC of all the AC sections in the DC near area is less than the DC rated power, the maximum transmission power of the DC subject to the power organization of the AC channel is P DC AC ;
23)计算直流扰动(含换相失败、闭锁、再启动)冲击下换流站及直流近区交流母线暂态过电压和稳态过电压受限情况,获取受电压稳定约束的直流最大传输功率;23) Calculate the transient overvoltage and steady-state overvoltage limitation of the converter station and the DC near-area AC busbar under the impact of DC disturbance (including commutation failure, lockout, and restart), and obtain the maximum DC transmission power constrained by voltage stability ;
一般而言,暂态过电压按照不超过换流站母线电压保护定值1.3p.u./500ms校核,稳态电压按照不超过550kV/半小时校核;当直流近区存在新能源的,还应校核新能源汇集母线电压不超过新能源涉网标准;Generally speaking, the transient overvoltage shall be checked according to not exceeding the busbar voltage protection setting value of the converter station 1.3p.u./500ms, and the steady-state voltage shall be checked according to not exceeding 550kV/half an hour; Verify that the voltage of the new energy collection busbar does not exceed the new energy grid-related standards;
当发生直流扰动(含换相失败、闭锁、再启动)后换流站/直流近区交流母线/新能源汇集母线暂态过电压和稳态过电压超过保护定值,即存在不满足直流故障后暂态或稳态过电压的工况,降低该工况中直流功率,直到直流扰动后换流站/直流近区交流母线/新能源汇集母线暂态过电压和稳态过电压均在标准范围内,则该工况中直流功率即为受电压稳定约束的直流最大传输功率P DC voltageWhen the DC disturbance (including commutation failure, blocking, and restart) occurs, the transient overvoltage and steady-state overvoltage of the converter station/DC near-area AC busbar/new energy collection busbar exceed the protection setting value, that is, there is a DC fault that does not meet the requirements In the post-transient or steady-state overvoltage working condition, reduce the DC power in this working condition until the transient overvoltage and steady-state overvoltage of the converter station/DC near-area AC busbar/new energy collection busbar are within the standard after the DC disturbance. Within the range, the DC power in this working condition is the maximum DC transmission power P DC voltage subject to voltage stability constraints;
24)计算直流扰动(含换相失败、闭锁、再启动)冲击下系统频率受限情况,获取受频率稳定约束的直流最大可传输功率;24) Calculate the frequency limitation of the system under the impact of DC disturbance (including commutation failure, blocking, and restart), and obtain the maximum transmittable power of DC subject to frequency stability constraints;
一般而言,最高频率按照不超过高周切机动作定值50.8Hz/500ms校核,最低频率不超过低周减载动作定值49Hz校核;当直流近区存在新能源的,还应校核新能源频率不超过新能源涉网标准;对于存在同送同受的直流,还应校核同送同受直流换相失败后频率响应特性;Generally speaking, the highest frequency shall be checked according to the action setting value of 50.8Hz/500ms for the high-cycle cutting machine, and the lowest frequency shall not exceed the action setting value of 49Hz for low-cycle load shedding; when there is new energy in the DC near area, it shall also be checked The frequency of nuclear new energy does not exceed the new energy network-related standards; for DC with simultaneous transmission and reception, the frequency response characteristics after the failure of DC commutation at the same transmission and reception should also be checked;
计算直流扰动(含换相失败、闭锁、再启动)冲击下系统频率,对于不满足直流故障后最高频率或最低频率的工况,降低该工况中直流功率,直到该工况发生直流扰动后频率在标准范围内,则该工况中直流功率即为受频率约束的直流最大传输功率P DC frequencyCalculate the system frequency under the impact of DC disturbance (including commutation failure, lockout, and restart). For the working condition that does not meet the highest frequency or the lowest frequency after the DC fault, reduce the DC power in this working condition until the DC disturbance occurs in this working condition If the frequency is within the standard range, the DC power in this working condition is the maximum DC transmission power P DC frequency constrained by the frequency ;
25)计算同时受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率,即P DC max=min(P DC ESCR,P DC AC,P DC voltage,P DC frequency) 25) Calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization, voltage stability and frequency stability, that is, P DC max = min(P DC ESCR ,P DC AC ,P DC voltage ,P DC frequency )
根据每年直流最大可传输功率,统计因直流不能满功率送出而导致的弃电代价,具体公式如下:According to the maximum transmittable power of DC each year, the power abandonment cost caused by the inability to send DC at full power is calculated. The specific formula is as follows:
Figure PCTCN2021123951-appb-000004
Figure PCTCN2021123951-appb-000004
其中,C discard为弃电代价,j、λ j分别为直流安排的功率大于直流最大可传输功率的运行工况及运行工况概率,
Figure PCTCN2021123951-appb-000005
为直流最大可传输功率,k为弃电的单位代价,可参考电源的单位上网电价制定,如水电的弃电单位代价为227.7元/MWh,P j为运行工况j中安排的直流功率。
Among them, C discard is the cost of electricity discarding, j and λ j are the operating conditions and the probability of operating conditions in which the power arranged by DC is greater than the maximum transmittable power of DC, respectively,
Figure PCTCN2021123951-appb-000005
is the maximum transmittable power of DC, and k is the unit cost of power abandonment, which can be determined by referring to the unit grid price of power sources. For example, the unit cost of power abandonment of hydropower is 227.7 yuan/MWh, and P j is the DC power arranged in operating condition j.
根据每年直流最大可传输功率调整所有运行工况:调整所有运行工况时,对于直流安排的功率大于直流最大可传输功率的运行工况,将直流功率调整至最大可传输功率,优先减少配套电源出力。Adjust all operating conditions according to the annual DC maximum transmittable power: When adjusting all operating conditions, for operating conditions where the DC power is greater than the DC maximum transmittable power, adjust the DC power to the maximum transmittable power, and reduce the supporting power supply first contribute.
基于调整后的运行工况,计算每年的运行风险代价,具体公式为:Based on the adjusted operating conditions, the annual operating risk cost is calculated, and the specific formula is:
Figure PCTCN2021123951-appb-000006
Figure PCTCN2021123951-appb-000006
其中,C risk为运行风险代价,λ i、ω t分别为运行工况i概率及对应扰动概率,C ec、C re、C pur分别为紧急控制代价、备用成本和外购电成本。 Among them, C risk is the operation risk cost, λ i , ω t are the probability of operating condition i and the corresponding disturbance probability, respectively, C ec , C re , and C pur are the emergency control cost, backup cost and purchased electricity cost, respectively.
上述随机生成多组规划周期内的风险阈值序列,根据运行风险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本,具体过程为:The above-mentioned random generation of risk threshold sequences in multiple sets of planning cycles, according to the operating risk cost, calculates the total risk cost of each set of risk threshold sequences from the start year to the end year of the planning cycle. The specific process is as follows:
51)随机生成多组规划周期内的风险阈值序列;其中,各组风险阈值序列的起始年和终点年分别与规划周期的起始年和终点年一致,各组风险阈值序列 均包含规划周期各年的风险阈值;51) Randomly generate multiple sets of risk threshold sequences within the planning cycle; wherein, the start year and end year of each set of risk threshold sequences are consistent with the start year and end year of the planning cycle, and each set of risk threshold sequences includes the planning cycle Risk thresholds for each year;
52)针对每组风险阈值序列,对运行风险代价超过相应风险阈值的年份,进行规划措施优化选择,直到运行风险代价降低至风险阈值以内,并将规划措施计入后续年份,刷新后续年份工况和扰动,计算风险阈值序列下的风险总成本;其中,风险总成本为规划周期内每年的运行风险代价和规划措施成本累加,若没有进行规划措施优化选择,则规划措施成本为0;规划措施包含新建储能、抽蓄、SVG、线路、主变。52) For each set of risk threshold series, optimize the selection of planning measures for the year in which the operating risk cost exceeds the corresponding risk threshold, until the operating risk cost is reduced to within the risk threshold, and include the planning measures in subsequent years to refresh the working conditions of subsequent years and disturbance, calculate the total cost of risk under the risk threshold sequence; among them, the total cost of risk is the accumulation of the annual operation risk cost and the cost of planning measures in the planning cycle. If no optimization selection of planning measures is made, the cost of planning measures is 0; Including new energy storage, pumped storage, SVG, lines, main transformer.
上述方法在直流的规划设计阶段,通过考虑运行中安全性及充裕性等风险并进行货币化,将运行中的风险代价与直流送电的经济性统筹考虑,避免了单一考虑运行或规划造成的直流传输功率与电源、网架不协调,导致网架承载直流能力不足等;通过合理规划直流传输极限,实现规划到运行的无缝衔接,能够指导电力系统规划人员充分考虑直流投运后的运行风险,使得电源-电网-直流负荷协同发展。In the planning and design stage of DC, the above method considers risks such as safety and adequacy in operation and monetizes them, and considers the risk cost in operation and the economics of DC power transmission as a whole, avoiding the problems caused by single consideration of operation or planning. The DC transmission power is not coordinated with the power supply and the grid, resulting in insufficient DC carrying capacity of the grid; through reasonable planning of the DC transmission limit, the seamless connection between planning and operation can be realized, and it can guide power system planners to fully consider the operation after DC is put into operation Risks make the power supply-grid-DC load coordinated development.
一种规划周期内直流传输极限优化系统,其特征在于:包括,A DC transmission limit optimization system within a planning cycle, characterized in that: comprising,
工况获取模块:获取规划周期内每年送端电网典型的运行工况;Operating condition acquisition module: acquire the typical operating conditions of the sending power grid every year within the planning period;
可传输功率模块:根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率;Transmittable power module: According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
弃电代价模块:根据每年直流最大可传输功率,统计因直流不能满功率送出而导致的弃电代价,调整所有运行工况;Abandonment cost module: According to the annual DC maximum transmittable power, calculate the electricity abandonment cost caused by the failure of DC to send out full power, and adjust all operating conditions;
运行风险代价模块:基于调整后的运行工况,根据弃电代价、外购电成本、备用成本以及第二级安全标准故障下送端电网的紧急控制代价,计算每年的运行风险代价;Operational risk cost module: based on the adjusted operating conditions, calculate the annual operational risk cost based on the cost of power abandonment, cost of purchased power, backup cost, and emergency control cost of the sending power grid under the second-level safety standard failure;
风险总成本模块:随机生成多组规划周期内的风险阈值序列,根据运行风险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本;Total risk cost module: Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
极限序列模块:采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列。Limit sequence module: use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the DC transmission limit sequence within the planning period.
一种存储一个或多个程序的计算机可读存储介质,所述一个或多个程序包括指令,所述指令当由计算设备执行时,使得所述计算设备执行规划周期内直流传输极限优化方法。A computer-readable storage medium storing one or more programs, the one or more programs including instructions that, when executed by a computing device, cause the computing device to perform a DC transmission limit optimization method within a planning period.
一种计算设备,包括一个或多个处理器、一个或多个存储器以及一个或多个程序,其中一个或多个程序存储在所述一个或多个存储器中并被配置为由所述一个或多个处理器执行,所述一个或多个程序包括用于执行规划周期内直流传输极限优化方法的指令。A computing device comprising one or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and configured to be executed by the one or more Executed by a plurality of processors, the one or more programs include instructions for executing the method for optimizing the DC transmission limit within the planning period.
本领域内的技术人员应明白,本申请的实施例可提供为方法、系统、或计算机程序产品。因此,本申请可采用完全硬件实施例、完全软件实施例、或结合软件和硬件方面的实施例的形式。而且,本申请可采用在一个或多个其中包含有计算机可用程序代码的计算机可用存储介质(包括但不限于磁盘存储器、CD-ROM、光学存储器等)上实施的计算机程序产品的形式。Those skilled in the art should understand that the embodiments of the present application may be provided as methods, systems, or computer program products. Accordingly, the present application may take the form of an entirely hardware embodiment, an entirely software embodiment, or an embodiment combining software and hardware aspects. Furthermore, the present application may take the form of a computer program product embodied on one or more computer-usable storage media (including but not limited to disk storage, CD-ROM, optical storage, etc.) having computer-usable program code embodied therein.
本申请是参照根据本申请实施例的方法、设备(系统)、和计算机程序产品的流程图和/或方框图来描述的。应理解可由计算机程序指令实现流程图和/或方框图中的每一流程和/或方框、以及流程图和/或方框图中的流程和/或方框的结合。可提供这些计算机程序指令到通用计算机、专用计算机、嵌入式处理机或其他可编程数据处理设备的处理器以产生一个机器,使得通过计算机或其他可编程数据处理设备的处理器执行的指令产生用于实现在流程图一个流 程或多个流程和/或方框图一个方框或多个方框中指定的功能的装置。The present application is described with reference to flowcharts and/or block diagrams of methods, apparatus (systems), and computer program products according to embodiments of the present application. It should be understood that each procedure and/or block in the flowchart and/or block diagram, and a combination of procedures and/or blocks in the flowchart and/or block diagram can be realized by computer program instructions. These computer program instructions may be provided to a general purpose computer, special purpose computer, embedded processor, or processor of other programmable data processing equipment to produce a machine such that the instructions executed by the processor of the computer or other programmable data processing equipment produce a An apparatus for realizing the functions specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.
这些计算机程序指令也可存储在能引导计算机或其他可编程数据处理设备以特定方式工作的计算机可读存储器中,使得存储在该计算机可读存储器中的指令产生包括指令装置的制造品,该指令装置实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能。These computer program instructions may also be stored in a computer-readable memory capable of directing a computer or other programmable data processing apparatus to operate in a specific manner, such that the instructions stored in the computer-readable memory produce an article of manufacture comprising instruction means, the instructions The device realizes the function specified in one or more procedures of the flowchart and/or one or more blocks of the block diagram.
这些计算机程序指令也可装载到计算机或其他可编程数据处理设备上,使得在计算机或其他可编程设备上执行一系列操作步骤以产生计算机实现的处理,从而在计算机或其他可编程设备上执行的指令提供用于实现在流程图一个流程或多个流程和/或方框图一个方框或多个方框中指定的功能的步骤。These computer program instructions can also be loaded onto a computer or other programmable data processing device, causing a series of operational steps to be performed on the computer or other programmable device to produce a computer-implemented process, thereby The instructions provide steps for implementing the functions specified in the flow chart or blocks of the flowchart and/or the block or blocks of the block diagrams.
以上仅为本发明的实施例而已,并不用于限制本发明,凡在本发明的精神和原则之内,所做的任何修改、等同替换、改进等,均包含在申请待批的本发明的权利要求范围之内。The above are only embodiments of the present invention, and are not intended to limit the present invention. Any modifications, equivalent replacements, improvements, etc. made within the spirit and principles of the present invention are included in the pending application of the present invention. within the scope of the claims.

Claims (10)

  1. 一种规划周期内直流传输极限优化方法,其特征在于:包括,A DC transmission limit optimization method within a planning cycle, characterized in that: comprising,
    获取规划周期内每年送端电网典型的运行工况;Obtain the typical operating conditions of the sending power grid every year within the planning period;
    根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率;According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
    根据每年直流最大可传输功率,统计因直流不能满功率送出而导致的弃电代价,调整所有运行工况;According to the annual DC maximum transmittable power, calculate the cost of power abandonment caused by the failure of DC to send out full power, and adjust all operating conditions;
    基于调整后的运行工况,根据弃电代价、外购电成本、备用成本以及第二级安全标准故障下送端电网的紧急控制代价,计算每年的运行风险代价;Based on the adjusted operating conditions, the annual operating risk cost is calculated according to the cost of power abandonment, the cost of purchased power, the cost of backup, and the emergency control cost of the sending power grid under the failure of the second-level safety standard;
    随机生成多组规划周期内的风险阈值序列,根据运行风险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本;Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost under each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
    采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列。The DC maximum transmittable power corresponding to the minimum total cost of risk is used to construct the DC transmission limit sequence within the planning period.
  2. 根据权利要求1所述的一种规划周期内直流传输极限优化方法,其特征在于:若送端电网为没有新能源送出的电网,典型的运行工况包括丰大、丰小、丰平大、枯大、枯小和枯平大;A DC transmission limit optimization method within a planning period according to claim 1, characterized in that: if the power grid at the sending end is a power grid without new energy transmission, the typical operating conditions include Feng Da, Feng Xiao, Feng Ping Da, Kuda, Kuxiao and Kupingda;
    若送端电网为有新能源送出的电网,典型的运行工况包括丰大、丰小、丰平大、枯大、枯小、枯平大、新能源大发和新能源小发。If the power grid at the sending end is a power grid with new energy sent, typical operating conditions include Fengda, Fengxiao, Fengpingda, Kuda, Kuxiao, Kupingda, new energy Dafa and new energy Xiaofa.
  3. 根据权利要求1所述的一种规划周期内直流传输极限优化方法,其特征在于:根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率,具体过程为,A method for optimizing DC transmission limits within a planning cycle according to claim 1, characterized in that: according to the operating conditions, the calculation is limited by the DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints. The maximum transmittable power of DC, the specific process is,
    计算所有运行工况下直流有效短路比,获取受直流有效短路比约束的直流 最大传输功率;Calculate the DC effective short-circuit ratio under all operating conditions to obtain the maximum DC transmission power constrained by the DC effective short-circuit ratio;
    计算所有运行工况下发生交流故障后直流近区交流断面输电功率,获取受交流通道电力组织约束的直流最大传输功率;Calculate the transmission power of the DC near-area AC section after the AC fault occurs under all operating conditions, and obtain the maximum DC transmission power constrained by the power organization of the AC channel;
    计算直流扰动冲击下换流站及直流近区交流母线暂态过电压和稳态过电压受限情况,获取受电压稳定约束的直流最大传输功率;Calculate the transient overvoltage and steady overvoltage limitation of the converter station and the AC bus in the DC vicinity under the impact of DC disturbance, and obtain the maximum DC transmission power subject to voltage stability constraints;
    计算直流扰动冲击下系统频率受限情况,获取受频率稳定约束的直流最大可传输功率;Calculate the frequency limitation of the system under the impact of DC disturbance, and obtain the maximum transmittable power of DC subject to the frequency stability constraint;
    计算同时受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率。Calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization, voltage stability and frequency stability.
  4. 根据权利要求1所述的一种规划周期内直流传输极限优化方法,其特征在于:弃电代价的计算公式为,A DC transmission limit optimization method within a planning period according to claim 1, characterized in that: the calculation formula of power abandonment cost is:
    Figure PCTCN2021123951-appb-100001
    Figure PCTCN2021123951-appb-100001
    其中,C discard为弃电代价,j、λ j分别为直流安排的功率大于直流最大可传输功率的运行工况及运行工况概率,
    Figure PCTCN2021123951-appb-100002
    为直流最大可传输功率,k为弃电的单位代价,P j为运行工况j中安排的直流功率。
    Among them, C discard is the cost of electricity discarding, j and λ j are the operating conditions and the probability of operating conditions in which the power arranged by DC is greater than the maximum transmittable power of DC, respectively,
    Figure PCTCN2021123951-appb-100002
    is the maximum transmittable power of DC, k is the unit cost of curtailment, and P j is the DC power arranged in operating condition j.
  5. 根据权利要求4所述的一种规划周期内直流传输极限优化方法,其特征在于:调整所有运行工况时,对于直流安排的功率大于直流最大可传输功率的运行工况,将直流功率调整至最大可传输功率,优先减少配套电源出力。A method for optimizing DC transmission limits within a planning period according to claim 4, characterized in that: when adjusting all operating conditions, for operating conditions in which the power of the DC arrangement is greater than the maximum transmittable power of the DC, the DC power is adjusted to The maximum transmittable power, prioritizing the reduction of supporting power supply output.
  6. 根据权利要求1所述的一种规划周期内直流传输极限优化方法,其特征在于:计算运行风险代价的公式为,A method for optimizing DC transmission limits within a planning period according to claim 1, wherein the formula for calculating the operating risk cost is:
    Figure PCTCN2021123951-appb-100003
    Figure PCTCN2021123951-appb-100003
    其中,C risk为运行风险代价,C discard为弃电代价,λ i、ω t分别为运行工况i概率及对应扰动概率,C ec、C re、C pur分别为紧急控制代价、备用成本和外购电成本。 Among them, C risk is the operation risk cost, C discard is the power abandonment cost, λ i , ω t are the operating condition i probability and the corresponding disturbance probability respectively, C ec , C re , C pur are the emergency control cost, backup cost and The cost of purchased electricity.
  7. 根据权利要求1所述的一种规划周期内直流传输极限优化方法,其特征在于:随机生成多组规划周期内的风险阈值序列,根据运行风险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本,具体过程为,A method for optimizing DC transmission limits within a planning period according to claim 1, characterized in that multiple sets of risk threshold sequences within the planning period are randomly generated, and according to the operating risk cost, each set of risk threshold sequences is calculated starting from the planning period The total cost of risk from the beginning year to the end year, the specific process is,
    随机生成多组规划周期内的风险阈值序列;其中,各组风险阈值序列的起始年和终点年分别与规划周期的起始年和终点年一致,各组风险阈值序列均包含规划周期各年的风险阈值;Randomly generate multiple sets of risk threshold sequences in the planning cycle; the start year and end year of each set of risk threshold sequences are consistent with the start year and end year of the planning cycle, and each set of risk threshold sequences includes the risk threshold;
    针对每组风险阈值序列,对运行风险代价超过相应风险阈值的年份,进行规划措施优化选择,计算风险阈值序列下的风险总成本;其中,风险总成本为规划周期内每年的运行风险代价和规划措施成本累加。For each set of risk threshold series, optimize the selection of planning measures for the year in which the operating risk cost exceeds the corresponding risk threshold, and calculate the total risk cost under the risk threshold sequence; where the total risk cost is the annual operating risk cost and planning Measures add up in cost.
  8. 一种规划周期内直流传输极限优化系统,其特征在于:包括,A DC transmission limit optimization system within a planning cycle, characterized in that: comprising,
    工况获取模块:获取规划周期内每年送端电网典型的运行工况;Operating condition acquisition module: acquire the typical operating conditions of the sending power grid every year within the planning period;
    可传输功率模块:根据运行工况,计算受直流有效短路比约束、交流通道电力组织约束、电压稳定约束和频率稳定约束的每年直流最大可传输功率;Transmittable power module: According to the operating conditions, calculate the annual DC maximum transmittable power subject to the constraints of DC effective short-circuit ratio, AC channel power organization constraints, voltage stability constraints, and frequency stability constraints;
    弃电代价模块:根据每年直流最大可传输功率,统计因直流不能满功率送出而导致的弃电代价,调整所有运行工况;Abandonment cost module: According to the annual DC maximum transmittable power, calculate the electricity abandonment cost caused by the failure of DC to send out full power, and adjust all operating conditions;
    运行风险代价模块:基于调整后的运行工况,根据弃电代价、外购电成本、备用成本以及第二级安全标准故障下送端电网的紧急控制代价,计算每年的运行风险代价;Operational risk cost module: based on the adjusted operating conditions, calculate the annual operational risk cost based on the cost of power abandonment, cost of purchased power, backup cost, and emergency control cost of the sending power grid under the second-level safety standard failure;
    风险总成本模块:随机生成多组规划周期内的风险阈值序列,根据运行风 险代价,计算每组风险阈值序列下从规划周期起始年到终点年的风险总成本;Total risk cost module: Randomly generate multiple groups of risk threshold sequences in the planning cycle, and calculate the total risk cost of each group of risk threshold sequences from the start year to the end year of the planning cycle according to the operating risk cost;
    极限序列模块:采用风险总成本最小时对应的每年直流最大可传输功率,构建规划周期内直流传输极限序列。Limit sequence module: use the annual DC maximum transmittable power corresponding to the minimum total risk cost to construct the DC transmission limit sequence within the planning period.
  9. 一种存储一个或多个程序的计算机可读存储介质,其特征在于:所述一个或多个程序包括指令,所述指令当由计算设备执行时,使得所述计算设备执行根据权利要求1至7所述的方法中的任一方法。A computer-readable storage medium storing one or more programs, wherein the one or more programs comprise instructions which, when executed by a computing device, cause the computing device to perform the Any one of the methods described in 7.
  10. 一种计算设备,其特征在于,包括:A computing device, comprising:
    一个或多个处理器、一个或多个存储器以及一个或多个程序,其中一个或多个程序存储在所述一个或多个存储器中并被配置为由所述一个或多个处理器执行,所述一个或多个程序包括用于执行根据权利要求1至7所述的方法中的任一方法的指令。one or more processors, one or more memories, and one or more programs, wherein the one or more programs are stored in the one or more memories and configured to be executed by the one or more processors, The one or more programs include instructions for performing any of the methods according to claims 1-7.
PCT/CN2021/123951 2021-05-20 2021-10-15 Method and system for optimizing direct current transmission limit within planning period WO2022242020A1 (en)

Applications Claiming Priority (2)

Application Number Priority Date Filing Date Title
CN202110549858.3A CN113300396B (en) 2021-05-20 2021-05-20 Method and system for optimizing direct current transmission limit in planning period
CN202110549858.3 2021-05-20

Publications (1)

Publication Number Publication Date
WO2022242020A1 true WO2022242020A1 (en) 2022-11-24

Family

ID=77322969

Family Applications (1)

Application Number Title Priority Date Filing Date
PCT/CN2021/123951 WO2022242020A1 (en) 2021-05-20 2021-10-15 Method and system for optimizing direct current transmission limit within planning period

Country Status (2)

Country Link
CN (1) CN113300396B (en)
WO (1) WO2022242020A1 (en)

Families Citing this family (5)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN113300396B (en) * 2021-05-20 2022-07-08 南瑞集团有限公司 Method and system for optimizing direct current transmission limit in planning period
CN113890080A (en) * 2021-08-26 2022-01-04 国家电网公司西南分部 Method for optimizing direct current transmission limit in planning period considering operation risk
CN113890077A (en) * 2021-08-26 2022-01-04 国家电网公司西南分部 Method for evaluating direct current bearing capacity in operation
CN114024331B (en) * 2021-08-26 2022-10-21 国家电网公司西南分部 Planning operation measure optimization method for improving direct current bearing capacity
CN113595153B (en) * 2021-09-29 2022-02-25 中国电力科学研究院有限公司 Output power optimization method and device of new energy cluster

Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN106972634A (en) * 2017-05-16 2017-07-21 成都课迪科技有限公司 A kind of automatic monitoring method of direct-current grid
US20180129768A1 (en) * 2013-06-26 2018-05-10 International Business Machines Corporation Method, Computer Program and System Providing Real-Time Power Grid Hypothesis Testing and Contingency Planning
CN108418255A (en) * 2018-03-01 2018-08-17 中国电力科学研究院有限公司 A kind of extra-high voltage direct-current suitable for the new energy containing high permeability sends Electric power network planning method and system outside
CN110649652A (en) * 2019-09-12 2020-01-03 国电南瑞科技股份有限公司 New energy sending-out system phase modulator configuration method and device based on risk quantitative evaluation
CN112491043A (en) * 2020-11-23 2021-03-12 国网经济技术研究院有限公司 New energy enrichment power grid power supply planning method and system
CN112686514A (en) * 2020-12-23 2021-04-20 华北电力大学 Comprehensive planning method for direct-current power distribution network
CN113300396A (en) * 2021-05-20 2021-08-24 南瑞集团有限公司 Method and system for optimizing direct current transmission limit in planning period

Family Cites Families (1)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112766634A (en) * 2020-12-23 2021-05-07 国电南瑞科技股份有限公司 Coordination optimization method and system for meeting all-time clean power supply of regional power grid

Patent Citations (7)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
US20180129768A1 (en) * 2013-06-26 2018-05-10 International Business Machines Corporation Method, Computer Program and System Providing Real-Time Power Grid Hypothesis Testing and Contingency Planning
CN106972634A (en) * 2017-05-16 2017-07-21 成都课迪科技有限公司 A kind of automatic monitoring method of direct-current grid
CN108418255A (en) * 2018-03-01 2018-08-17 中国电力科学研究院有限公司 A kind of extra-high voltage direct-current suitable for the new energy containing high permeability sends Electric power network planning method and system outside
CN110649652A (en) * 2019-09-12 2020-01-03 国电南瑞科技股份有限公司 New energy sending-out system phase modulator configuration method and device based on risk quantitative evaluation
CN112491043A (en) * 2020-11-23 2021-03-12 国网经济技术研究院有限公司 New energy enrichment power grid power supply planning method and system
CN112686514A (en) * 2020-12-23 2021-04-20 华北电力大学 Comprehensive planning method for direct-current power distribution network
CN113300396A (en) * 2021-05-20 2021-08-24 南瑞集团有限公司 Method and system for optimizing direct current transmission limit in planning period

Also Published As

Publication number Publication date
CN113300396A (en) 2021-08-24
CN113300396B (en) 2022-07-08

Similar Documents

Publication Publication Date Title
WO2022242020A1 (en) Method and system for optimizing direct current transmission limit within planning period
CN103078326B (en) Optimization method for improving safety and stability of grid frequency
CN107730076B (en) Method for analyzing comprehensive utilization efficiency of regional distribution network equipment
CN105356494B (en) The reliability calculation method of multiterminal VSC-HVDC grid-connected systems
CN106599341B (en) Method for generating stability control strategy table containing flexible direct current power transmission system
CN111541280A (en) Power grid wind power maximum permeability evaluation method considering static voltage stability constraint
Zhang et al. A short-term optimal scheduling model for wind-solar-hydro-thermal complementary generation system considering dynamic frequency response
CN117117918A (en) Source network load storage optimization operation method and device
CN111313466A (en) Sending-end power grid AGC optimization regulation and control method and system based on wind power priority regulation
CN116565842A (en) Power distribution network toughness assessment method, system and equipment based on multi-source collaborative strategy
Wang et al. Analysis of renewable energy consumption and economy considering the joint optimal allocation of “renewable energy+ energy storage+ synchronous condenser”
CN113315140A (en) Offshore wind power reactive compensation coordination control method
Cai et al. Multistage Coordinated Control Risk Dispatch Considering the Uncertainty of Source-Network
Zhang et al. Resilience Oriented Planning for Multi-energy Microgrids in an Urban Area
Leng et al. Research on Security Check Method of Multi-Area Interconnected Power System Suitable for Operation of Electricity Spot Market
CN113890080A (en) Method for optimizing direct current transmission limit in planning period considering operation risk
CN112653148B (en) Method and system for checking power transmission capacity of extra-high voltage alternating current-direct current combined sending-out system considering wind power access
CN117410991B (en) Power balancing method, system, equipment and storage medium for distributed resources
CN117057659B (en) Regional power grid electricity-carbon joint risk assessment method
Yajun et al. The reliability evaluation of the power system containing wind farm using the improved state space partition method
Li et al. Transmission Paths Capacity Optimization for Wind Farm Based on Optimal Power Flow
Lu et al. Comprehensive Evaluation of Grid Adaptability Considering Rolling Access of Cascade Power Stations
Deng et al. Coordinated expansion planning of AC network and synchronous condenser for receiving-end grids with multi-infeed UHVDC links
Zhou et al. The method of energy storage location and capacity determination in extreme environments
Sun et al. Simulation Analysis of Power System Stochastic Production with High Proportion of Offshore Wind Power

Legal Events

Date Code Title Description
121 Ep: the epo has been informed by wipo that ep was designated in this application

Ref document number: 21940466

Country of ref document: EP

Kind code of ref document: A1

NENP Non-entry into the national phase

Ref country code: DE

122 Ep: pct application non-entry in european phase

Ref document number: 21940466

Country of ref document: EP

Kind code of ref document: A1