CN110700238A - Newly-built enclosure structure for existing basement extension and construction method thereof - Google Patents

Newly-built enclosure structure for existing basement extension and construction method thereof Download PDF

Info

Publication number
CN110700238A
CN110700238A CN201910948722.2A CN201910948722A CN110700238A CN 110700238 A CN110700238 A CN 110700238A CN 201910948722 A CN201910948722 A CN 201910948722A CN 110700238 A CN110700238 A CN 110700238A
Authority
CN
China
Prior art keywords
existing
newly
built
enclosure
underground continuous
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Granted
Application number
CN201910948722.2A
Other languages
Chinese (zh)
Other versions
CN110700238B (en
Inventor
徐磊
朱毅敏
王彬楠
张文军
张佳
张雨超
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Shanghai Construction No 1 Group Co Ltd
Original Assignee
Shanghai Construction No 1 Group Co Ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Shanghai Construction No 1 Group Co Ltd filed Critical Shanghai Construction No 1 Group Co Ltd
Priority to CN201910948722.2A priority Critical patent/CN110700238B/en
Publication of CN110700238A publication Critical patent/CN110700238A/en
Application granted granted Critical
Publication of CN110700238B publication Critical patent/CN110700238B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Images

Classifications

    • EFIXED CONSTRUCTIONS
    • E02HYDRAULIC ENGINEERING; FOUNDATIONS; SOIL SHIFTING
    • E02DFOUNDATIONS; EXCAVATIONS; EMBANKMENTS; UNDERGROUND OR UNDERWATER STRUCTURES
    • E02D5/00Bulkheads, piles, or other structural elements specially adapted to foundation engineering
    • E02D5/18Bulkheads or similar walls made solely of concrete in situ
    • E02D5/187Bulkheads or similar walls made solely of concrete in situ the bulkheads or walls being made continuously, e.g. excavating and constructing bulkheads or walls in the same process, without joints
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G23/00Working measures on existing buildings
    • E04G23/02Repairing, e.g. filling cracks; Restoring; Altering; Enlarging
    • E04G23/0266Enlarging

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Structural Engineering (AREA)
  • Civil Engineering (AREA)
  • Mining & Mineral Resources (AREA)
  • General Life Sciences & Earth Sciences (AREA)
  • Paleontology (AREA)
  • Life Sciences & Earth Sciences (AREA)
  • General Engineering & Computer Science (AREA)
  • Chemical & Material Sciences (AREA)
  • Chemical Kinetics & Catalysis (AREA)
  • Electrochemistry (AREA)
  • Mechanical Engineering (AREA)
  • Underground Structures, Protecting, Testing And Restoring Foundations (AREA)

Abstract

The invention discloses a newly-built enclosure structure for expanding an existing basement and a construction method thereof. The invention can ensure the structural stability and safety of the existing building to be expanded and the adjacent existing buildings, and reduce the potential safety hazard. The invention is suitable for the expansion of basements of existing buildings which are close to the existing buildings, adjacent to water and adjacent to mountains.

Description

Newly-built enclosure structure for existing basement extension and construction method thereof
Technical Field
The invention relates to the technical field of constructional engineering, in particular to a newly-built enclosure structure for the extension of an existing basement and a construction method thereof.
Background
In the technical field of construction engineering, along with the development of urban modernization, the contradictions and problems of urban land resource and space development are increasingly prominent, and the utilization of underground space is continuously three-dimensional. The problems of congestion of underground spaces, such as parking difficulty in traffic hub stations, large-scale venues, commercial buildings and residential districts, are increasingly prominent, and the sustainable development of cities is seriously influenced. Therefore, the reasonable development and utilization of the underground space of the existing buildings in the city is one of the effective ways for solving the contradiction between the land resources and the space development of the city at present. The development of the underground space of the existing building comprises the steps of reserving the existing building to increase the underground space and dismantling the existing building to develop the underground space. When underground space development is carried out on an existing basement, an enclosure structure of the existing basement needs to be expanded. The extension enclosure structure in the prior art is generally arranged on the periphery of an existing enclosure structure, the spacing distance between the extension enclosure structure and the existing enclosure structure is large, the area of an existing basement can be enlarged in the transverse direction, and when some existing buildings are adjacent and close to each other, contradiction exists between the safety of the existing buildings and the safety of the adjacent existing buildings when the extension enclosure structure is constructed on the periphery of the existing enclosure structure. In addition, because the spacing distance between the extension building envelope and the existing building envelope is larger, soil around the existing building envelope loosens to cause the existing building envelope to lack extrusion force, thereby influencing the structural stability of the existing building. In addition, when the existing building constructed by adjacent water and adjacent mountains is involved, when the enclosure structure is expanded outside the adjacent water surface or the adjacent mountains of the existing enclosure structure, on one hand, construction is inconvenient, and on the other hand, after construction, because the expanded enclosure structure is closer to the water or the adjacent mountains, potential safety hazards can be caused to the structural safety of the existing building body. Therefore, how to reduce the safety and the structural stability of the existing building and the adjacent buildings in the construction of the basement extension envelope structure becomes a technical problem which needs to be solved in the field.
Disclosure of Invention
The invention aims to solve the technical problem of providing a newly-built enclosure structure for the extension of an existing basement and a construction method thereof, so as to solve the problems of the safety and the structural stability of an existing building and adjacent buildings to be built.
In order to solve the technical problem, the invention provides a construction method of a newly-built enclosure structure for the extension of an existing basement, wherein a newly-built underground continuous wall is constructed on the inner side of an existing enclosure pile through an existing engineering pile area, and the newly-built underground continuous wall is the newly-built enclosure structure.
Further, the construction method of the newly-built enclosure structure of the existing basement extension provided by the invention comprises the following steps of:
setting out and positioning at the position of the underground continuous wall to be built in the existing engineering pile area, and driving a steel sleeve to rotate downwards to cut a soil body borehole to a preset depth in the setting-out and positioning area by adopting a full rotary drilling machine;
when a steel sleeve of a full slewing drilling machine meets an existing engineering pile in the process of drilling a wall body by rotary cutting, separating the existing engineering pile from a soil body, putting a wedge-shaped hammer between the steel sleeve and the existing engineering pile, cutting the existing engineering pile into an existing engineering pile section by the wedge-shaped hammer along with the rotation of a copper sleeve, and pulling out the existing engineering pile section by section;
and (3) clearing the pay-off positioning area and soil in the drill hole by using a trenching machine to form a groove, arranging guide wall templates on two sides of the groove, pouring concrete to form guide walls, hoisting a reinforcement cage in the groove between the guide walls, and pouring concrete to form the newly-built underground continuous wall.
Further, the construction method of the newly-built enclosure structure of the existing basement extension provided by the invention is characterized in that the inner side of at least one surface of the existing enclosure pile penetrates through the newly-built underground continuous wall of the corresponding construction surface of the existing engineering pile area, the outer side of the rest surface of the existing enclosure pile is tightly attached to the newly-built underground continuous wall of the corresponding construction surface of the existing enclosure pile, and all the newly-built underground continuous walls are connected to form the newly-built enclosure pile.
Further, the construction method of the newly-built enclosure structure of the existing basement extension, provided by the invention, comprises the following steps of:
and (3) paying off and positioning at the position of the underground continuous wall to be built, excavating soil to a preset depth by adopting a trenching machine in a paying off and positioning area to form a groove, arranging guide wall templates on two sides of the groove to pour concrete to form guide walls, hoisting a reinforcement cage in the groove between the guide walls and pouring the concrete to form the newly-built underground continuous wall.
Further, the construction method of the newly-built enclosure structure of the existing basement extension, provided by the invention, is a method for constructing the newly-built underground continuous wall clinging to the corresponding surface of the existing enclosure pile, and means that a small gap exists between the newly-built underground continuous wall and the existing enclosure pile, and the size of the gap is subject to the condition that the soil body between the newly-built underground continuous wall and the existing enclosure pile is loosened and extruded by the newly-built underground continuous wall so that the existing enclosure pile is not loosened.
Furthermore, the construction method of the newly-built enclosure structure for the extension of the existing basement provided by the invention is used for constructing the newly-built underground continuous wall by penetrating the area of the existing engineering piles between the inner side of the existing enclosure pile and the outer wall of the existing basement.
Further, the construction method of the newly-built enclosure structure of the existing basement extension is used for constructing the water stop piles on the periphery of the newly-built underground continuous wall.
In order to solve the technical problem, the invention also provides a newly-built enclosure structure for the extension of the existing basement, which comprises a newly-built underground continuous wall passing through the area of the existing engineering piles at the inner side of the existing enclosure piles, wherein the newly-built underground continuous wall is the newly-built enclosure pile.
Furthermore, the newly-built enclosure structure for the extension of the existing basement, provided by the invention, is characterized in that the inner side of at least one surface of the existing enclosure pile penetrates through the newly-built underground continuous wall of the corresponding construction surface of the existing engineering pile area, the newly-built underground continuous wall of the corresponding construction surface of the existing enclosure pile is closely attached to the outer side of the rest surface of the existing enclosure pile, and the newly-built underground continuous walls are connected to form the newly-built enclosure pile.
Furthermore, the newly-built enclosure structure for the extension of the existing basement is characterized in that a newly-built underground continuous wall penetrating through the area of the existing engineering piles at the inner side of the existing enclosure pile is positioned between the existing enclosure pile and the outer wall of the existing basement.
Compared with the prior art, the newly-built enclosure structure for expanding the existing basement and the construction method thereof provided by the invention have the advantages that the newly-built underground continuous wall is constructed in the area where the existing engineering piles penetrate through the inner sides of the existing enclosure piles to serve as the newly-built enclosure structure, when the existing buildings are adjacent to each other, the newly-built underground continuous wall can be expanded to serve as the newly-built enclosure structure for expanding the existing basement, and the newly-built underground continuous wall is constructed in the area where the existing engineering piles penetrate through the inner sides of the existing enclosure piles to not cross the adjacent existing buildings, so that the safety and the structure of the adjacent existing buildings are not influenced. When the existing building built by the adjacent water and the adjacent mountain is involved, the newly-built underground continuous wall is constructed on the surface of the adjacent water and the adjacent mountain by penetrating the existing engineering pile area at the inner side of the existing fender pile, and a newly-built fender structure is not constructed in the direction close to the mountain edge or the water edge, so that the structural stability and the safety of the existing building to be expanded can be ensured, and the potential safety hazard is reduced. The invention is suitable for the expansion of basements of existing buildings which are close to the existing buildings, adjacent to water and adjacent to mountains.
Drawings
Fig. 1 to fig. 2 are schematic top view structural diagrams of a new enclosure construction process of an existing basement extension according to an embodiment of the present invention;
FIG. 3 is a schematic view of an embodiment of the present invention illustrating a full rotary drill for drilling holes and clearing obstacles;
FIG. 4 is a schematic diagram of a cut-out structure of an existing construction pile according to an embodiment of the present invention;
FIG. 5 is a flow chart of an embodiment of the present invention for constructing a newly constructed underground diaphragm wall through an existing piling area;
fig. 6 is a flow chart of a method of constructing a newly constructed underground diaphragm wall outside and in close proximity to existing fender piles according to an embodiment of the present invention.
Shown in the figure: 101. the method comprises the following steps of existing fender piles, 102, existing engineering piles, 103, existing basement outer walls, 200, newly-built underground continuous walls, 201, drilling holes, 202, grooves, 300, a full-slewing drilling machine, 301, steel sleeves, 302, hoisting lines, 303, wedge-shaped hammers, 401, terraces, 402 and soil bodies.
Detailed Description
The invention is described in detail below with reference to the attached drawing figures:
referring to fig. 2, an embodiment of the present invention provides a method for constructing a newly-built enclosure structure for expanding an existing basement, wherein a newly-built underground continuous wall 200 is constructed on the inner side of an existing fender pile 101 through an area of an existing engineering pile 102, and the newly-built underground continuous wall 200 is the newly-built enclosure structure.
Referring to fig. 5, in the method for constructing a newly-built enclosure structure for expanding an existing basement according to the embodiment of the present invention, the method for constructing a newly-built underground continuous wall 200 through an area of an existing engineering pile 102 includes:
step 501, please refer to fig. 1 and fig. 3, pay off and position the underground continuous wall to be built in the area of the existing engineering pile 102, and drive the steel casing 301 to rotate downwards to cut the soil drilling hole 201 to a predetermined depth in the pay-off and position area by using the full slewing drilling machine 300.
Step 502, please refer to fig. 1 and 4, when the steel casing 301 of the full slewing drilling machine 300 encounters the existing engineering pile 102 in the process of rotationally cutting the wall borehole 201, the existing engineering pile 102 is separated from the soil body 402, a wedge-shaped hammer 303 is placed between the steel casing 301 and the existing engineering pile 102, the wedge-shaped hammer 303 rotates along with the copper casing 301 to cut off or twist off the existing engineering pile 102 to form an existing engineering pile section, and the existing engineering pile section is pulled out section by section. Wherein the wedge hammer 303 may also be referred to as a drill steel, a clamping bar, and an inverted triangular hammer. Where steel casing 301 has a diameter greater than the diameter of existing engineered pile 102. The existing engineering pile section can be pulled out by a crane. After the hole 201 is cleared, firstly, the cement soil is backfilled to a certain depth, and then the steel sleeve 301 is pulled out while the cement soil is backfilled, wherein the bottom of the steel sleeve 301 is always kept below the cement soil. The cement soil is reserved on the steel sleeve 301 by a certain amount, so that the condition that the amount is insufficient when the steel sleeve is pulled out is avoided, and the cement soil is a mixture of cement and soil.
Step 503, please refer to fig. 1, a trenching machine is used to remove the line-laying positioning area and the soil body in the drill hole 201 to form a trench 202, guide wall templates are arranged at two sides of the trench 202 to pour concrete to form guide walls, and a reinforcement cage is hung in the trench 202 between the guide walls and concrete is poured to form the newly-built underground continuous wall 200. The trenching machine in step 503 is a dual-wheel trenching machine that has dual functions of trenching and clearing obstacles. In this step 503, before forming the groove 202, a gantry column may be disposed along the line-releasing positioning area to ensure the accuracy of the construction position of the guide wall.
In the embodiment of the invention, the method for constructing and newly building the underground continuous wall 200 through the area of the existing engineering piles 102 is to pass through the area of the existing engineering piles 102 and carry out pile pulling treatment on the existing engineering piles 102 with obstacles, thereby constructing and newly building the underground continuous wall 200. The method utilizes the effective area of the existing basement of the existing building to be constructed, and avoids the influence on the structural performance and the safety performance of the adjacent existing building caused by crossing the adjacent existing building. And the influence of the newly-built underground continuous wall 200 on the structural performance and the safety performance of the existing building to be built due to the proximity of the adjacent mountains, the adjacent water and other areas is avoided.
In the embodiment of the invention, the method for constructing and newly building the underground continuous wall 200 through the area of the existing engineering pile 102 adopts the full slewing drilling machine 300, and can utilize the steel sleeve 301 for retaining soil when drilling downwards through the steel sleeve 301, so that hole collapse is prevented, and the influence on the surrounding environment is reduced. Removing the obstacles and digging to form the groove 202 by means of a two-wheel slot milling machine reduces the risk of tilting or cracking the surrounding structure building, thereby reducing the impact on the surrounding environment.
Referring to fig. 1 and fig. 2, in the method for constructing a newly-built enclosure structure for expanding an existing basement according to the embodiment of the present invention, a newly-built underground continuous wall 200 of a corresponding surface is constructed on the inner side of at least one surface of an existing fender post 101 through an area of an existing engineering post 102, and a newly-built underground continuous wall 200 of a corresponding surface is constructed on the outer side of the remaining surface of the existing fender post 101 and in close contact with the existing fender post 101, so that all the newly-built underground continuous walls 200 are connected to form a newly-built fender post. The embodiment of the invention includes, but is not limited to, constructing the newly-built underground continuous wall 200 of the corresponding surface through the existing engineering pile 102 area at the inner side of the south surface of the existing fender pile 101, and constructing the newly-built underground continuous wall 200 of the corresponding surface by clinging the existing fender pile 101 at the east surface, the north surface and the west surface of the existing fender pile 101. Specifically, the construction of the newly-built underground continuous wall 200 through the existing construction pile 102 areas in several planes of the existing fender post 101 requires the construction design according to the geographical location environment of the existing building.
Referring to fig. 6, the method for constructing a newly-built enclosure structure for expanding an existing basement according to the embodiment of the present invention includes the following steps:
step 601, paying off and positioning at the position of the underground continuous wall to be built, and excavating soil to a preset depth by adopting a trenching machine in a paying off and positioning area to form a groove 202. The trenching machine in this step 601 is a backhoe excavator.
Step 602, arranging guide wall templates on two sides of the groove 202 and pouring concrete to form guide walls, hoisting a reinforcement cage into the groove 202 between the guide walls and pouring concrete to form the newly-built underground continuous wall 200.
The method for constructing the newly-built underground continuous wall 200 of the corresponding surface by clinging to the existing fender post 101 means that a small gap exists between the newly-built underground continuous wall 200 and the existing fender post 101, and the size of the gap is determined by the fact that the soil body between the newly-built underground continuous wall 200 and the existing fender post 101 is loosened and extruded by the newly-built underground continuous wall 200, so that the existing fender post 101 is not loosened. The construction is closely attached, and the structural stability and the safety of the existing building can be ensured.
In the embodiment of the invention, when the newly-built underground continuous wall 200 is constructed outside the existing fender post 101 and clings to the existing fender post 101, because no obstacle of the existing engineering post 102 blocks the newly-built underground continuous wall, a back-hoe excavator can be adopted to directly form the groove 202, and the construction difficulty is reduced.
Referring to fig. 1 to 2, in the method for constructing a newly-built enclosure structure for enlarging an existing basement according to the embodiment of the present invention, a newly-built underground continuous wall 200 is constructed between the inner side of an existing fender post 101 and an existing basement exterior wall 103 through an area of an existing engineering post 102. The embodiment of the invention is suitable for a two-wall separation structure of an existing basement, wherein the two walls respectively refer to an existing fender post 101 and an existing basement outer wall 103. The horizontal force is transmitted and supported by adopting a support plate changing belt between the existing fender post 101 and the existing basement outer wall 103. At this time, when the underground diaphragm wall 200 is newly constructed, the area of the bracing plate changing zone needs to be cleared. A crane can be used for cooperating with the grab bucket to remove obstacles such as soil, concrete, engineering pile sections and the like.
The construction method of the newly-built enclosure structure of the existing basement extension provided by the embodiment of the invention is to construct the water stop piles at the periphery of the newly-built underground continuous wall 200.
Referring to fig. 1, the embodiment of the present invention further provides a newly-built enclosure structure for the extension of an existing basement, which includes a newly-built underground continuous wall 200 passing through the area of the existing engineering piles 102 at the inner side of the existing enclosure piles 101, wherein the newly-built underground continuous wall 200 is the newly-built enclosure pile.
Referring to fig. 1, in the newly-built enclosure structure for expanding an existing basement according to the embodiment of the present invention, a newly-built underground continuous wall 200 of a corresponding surface is constructed on the inner side of at least one surface of an existing enclosure pile 101 through an area of an existing engineering pile 102, and a newly-built underground continuous wall 200 of a corresponding surface is constructed on the outer side of the remaining surface of an existing enclosure pile 101 and in close contact with an existing enclosure pile 101, and all the newly-built underground continuous walls 200 are connected to form a newly-built enclosure pile.
Referring to fig. 1, in the newly-built enclosure structure for the extension of the existing basement according to the embodiment of the present invention, a newly-built underground continuous wall 200 passing through the area of the existing engineering piles 102 at the inner side of the existing enclosure piles 101 is located between the existing enclosure piles 101 and the outer wall 103 of the existing basement.
According to the newly-built enclosure structure for the extension of the existing basement and the construction method thereof provided by the embodiment of the invention, the newly-built underground continuous wall 200 is constructed in the area where the existing guard post 101 penetrates through the existing engineering post 102 as the newly-built enclosure structure, when the existing buildings are adjacent and close to each other, the newly-built underground continuous wall 200 can be constructed for the extension of the existing basement as the newly-built enclosure structure, and the newly-built underground continuous wall 200 is constructed in the area where the existing guard post 101 penetrates through the existing engineering post 102 at the inner side of the existing guard post 101 and cannot cross over the adjacent existing buildings, so that the safety and the structure of the adjacent existing buildings cannot be influenced. When the existing building built by the adjacent water and the adjacent mountain is involved, the newly-built underground continuous wall 200 is constructed on the surface of the adjacent water and the adjacent mountain by penetrating the area of the existing engineering pile 102 at the inner side of the existing fender pile 101, and a newly-built enclosure structure is not constructed in the direction close to the mountain edge or the water edge, so that the structural stability and the safety of the existing building to be expanded can be ensured, and the potential safety hazard is reduced. The embodiment of the invention is suitable for the expansion of basements of existing buildings which are close to the existing buildings, adjacent to water and adjacent to mountains.
The east, south, west and north faces of the existing fender post 101 of the present embodiment are in the same orientation as shown in the drawings.
The present invention is not limited to the above-described embodiments, and any variations and modifications thereof by those skilled in the art are intended to fall within the scope of the appended claims.

Claims (10)

1. A construction method of a newly-built enclosure structure of an existing basement extension is characterized in that a newly-built underground continuous wall is constructed on the inner side of an existing enclosure pile through an existing engineering pile area, and the newly-built underground continuous wall is the newly-built enclosure structure.
2. The method of constructing a new building envelope of an existing basement extension according to claim 1, wherein the method of constructing a new underground diaphragm wall through an existing piling area comprises:
setting out and positioning at the position of the underground continuous wall to be built in the existing engineering pile area, and driving a steel sleeve to rotate downwards to cut a soil body borehole to a preset depth in the setting-out and positioning area by adopting a full rotary drilling machine;
when a steel sleeve of a full slewing drilling machine meets an existing engineering pile in the process of drilling a wall body by rotary cutting, separating the existing engineering pile from a soil body, putting a wedge-shaped hammer between the steel sleeve and the existing engineering pile, cutting the existing engineering pile into an existing engineering pile section by the wedge-shaped hammer along with the rotation of a copper sleeve, and pulling out the existing engineering pile section by section;
and (3) clearing the pay-off positioning area and soil in the drill hole by using a trenching machine to form a groove, arranging guide wall templates on two sides of the groove, pouring concrete to form guide walls, hoisting a reinforcement cage in the groove between the guide walls, and pouring concrete to form the newly-built underground continuous wall.
3. The method as claimed in claim 1, wherein the newly constructed underground continuous wall of the corresponding side is constructed on the inner side of at least one side of the existing fender post through the existing construction post area, and the newly constructed underground continuous wall of the corresponding side is constructed on the outer side of the remaining side of the existing fender post and closely attached to the existing fender post, and all the newly constructed underground continuous walls are connected to form the newly constructed fender post.
4. The method of constructing a new enclosure for an existing basement according to claim 1, wherein the method of constructing a new underground diaphragm wall on the outside of the remaining face of the existing fender post and abutting the corresponding face of the existing fender post comprises:
and (3) paying off and positioning at the position of the underground continuous wall to be built, excavating soil to a preset depth by adopting a trenching machine in a paying off and positioning area to form a groove, arranging guide wall templates on two sides of the groove to pour concrete to form guide walls, hoisting a reinforcement cage in the groove between the guide walls and pouring the concrete to form the newly-built underground continuous wall.
5. The method of claim 1, wherein the method of constructing the new underground diaphragm wall closely attached to the corresponding surface of the existing fender post means that a small gap exists between the new underground diaphragm wall and the existing fender post, and the size of the gap is determined by the fact that the soil between the new underground diaphragm wall and the existing fender post is loosened and pressed by the new underground diaphragm wall.
6. The method of claim 1, wherein a new underground diaphragm wall is constructed between the inner side of the existing fender post and the outer wall of the existing basement through the area of the existing construction post.
7. A construction method of a newly built enclosure of an existing basement extension according to claim 1, characterized in that the water stop piles are constructed at the periphery of the newly built underground diaphragm wall.
8. A newly-built enclosure structure for the extension of an existing basement is characterized by comprising a newly-built underground continuous wall which penetrates through an existing engineering pile area on the inner side of an existing enclosure pile, wherein the newly-built underground continuous wall is the newly-built enclosure pile.
9. A new enclosure of an existing basement according to claim 8 wherein a new underground continuous wall of a corresponding side is constructed in the area of the existing construction piles through the inside of at least one side of the existing enclosure piles, and a new underground continuous wall of a corresponding side is constructed in the area of the existing enclosure piles outside the remaining side of the existing enclosure piles and abutting the existing enclosure piles, all of said new underground continuous walls being connected to form the new enclosure piles.
10. A newly-built enclosure for an existing basement extension of claim 8, wherein a newly-built underground continuous wall passing through the area of the existing construction pile inside the existing enclosure is located between the existing enclosure pile and the outer wall of the existing basement.
CN201910948722.2A 2019-10-08 2019-10-08 Newly-built enclosure structure for expanding existing basement and construction method thereof Active CN110700238B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910948722.2A CN110700238B (en) 2019-10-08 2019-10-08 Newly-built enclosure structure for expanding existing basement and construction method thereof

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910948722.2A CN110700238B (en) 2019-10-08 2019-10-08 Newly-built enclosure structure for expanding existing basement and construction method thereof

Publications (2)

Publication Number Publication Date
CN110700238A true CN110700238A (en) 2020-01-17
CN110700238B CN110700238B (en) 2024-05-28

Family

ID=69198270

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910948722.2A Active CN110700238B (en) 2019-10-08 2019-10-08 Newly-built enclosure structure for expanding existing basement and construction method thereof

Country Status (1)

Country Link
CN (1) CN110700238B (en)

Cited By (2)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096109A (en) * 2020-08-27 2020-12-18 中国二十冶集团有限公司 Construction method for newly built building reserved beside building
CN117057101A (en) * 2023-07-18 2023-11-14 山东建筑大学 Method and system for evaluating upper layer-adding construction safety of existing underground structure

Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004048703A1 (en) * 2002-11-22 2004-06-10 De Waal Technology & Consultancy B.V. Method for supporting an object, in particular an existing object
CN209040138U (en) * 2018-08-23 2019-06-28 广州市住宅建设发展有限公司 A kind of grooving foundation structure before construction of diaphragm wall
CN211256952U (en) * 2019-10-08 2020-08-14 上海建工一建集团有限公司 Newly-built enclosure structure of existing basement extension

Patent Citations (3)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
WO2004048703A1 (en) * 2002-11-22 2004-06-10 De Waal Technology & Consultancy B.V. Method for supporting an object, in particular an existing object
CN209040138U (en) * 2018-08-23 2019-06-28 广州市住宅建设发展有限公司 A kind of grooving foundation structure before construction of diaphragm wall
CN211256952U (en) * 2019-10-08 2020-08-14 上海建工一建集团有限公司 Newly-built enclosure structure of existing basement extension

Non-Patent Citations (2)

* Cited by examiner, † Cited by third party
Title
李强;: "旧基桩上新建房屋的基础处理", 建设科技, no. 11, pages 80 - 81 *
范庆国;: "上海外滩通道综合改造工程关键施工技术", 建筑施工, vol. 32, no. 11, pages 1097 - 1101 *

Cited By (4)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
CN112096109A (en) * 2020-08-27 2020-12-18 中国二十冶集团有限公司 Construction method for newly built building reserved beside building
CN112096109B (en) * 2020-08-27 2022-02-25 中国二十冶集团有限公司 Construction method for newly built building reserved beside building
CN117057101A (en) * 2023-07-18 2023-11-14 山东建筑大学 Method and system for evaluating upper layer-adding construction safety of existing underground structure
CN117057101B (en) * 2023-07-18 2024-04-19 山东建筑大学 Method and system for evaluating upper layer-adding construction safety of existing underground structure

Also Published As

Publication number Publication date
CN110700238B (en) 2024-05-28

Similar Documents

Publication Publication Date Title
EP2732101B1 (en) Diaphragm wall apparatus and methods
KR20100115019A (en) Panel joint for construction for underground diaphragm well and underground diaphragm well constructing method using the same
CN105155516B (en) The method of construction drill bored concrete pile before making an overall screening underground obstacle
WO2022227725A1 (en) Trench forming construction method
CN110700238B (en) Newly-built enclosure structure for expanding existing basement and construction method thereof
CN111236387B (en) Construction method for connecting newly-built sewage pipe with existing sewage pipe
KR101381325B1 (en) The non-open cut tunnel construction method using the multistage small diameter steel pipe
JP7094423B2 (en) Underground wall pile structure with expanded bottom
CN211256952U (en) Newly-built enclosure structure of existing basement extension
CN101725147A (en) Construction process of first-inserting last-jetting type steel churning pile enclosing structure under low net space
CN111042104A (en) Method for constructing diaphragm wall at existing underground structure
JP2004052398A (en) Construction method of underground structure
JP4485006B2 (en) Construction method for underground structures
KR102325623B1 (en) Construction method of retaining wall
JP3948655B2 (en) Construction method of retaining wall and underground structure
JP4303512B2 (en) Construction method of large section tunnel
CN106759377A (en) The construction method of recyclable building enclosure
CN112031021A (en) Construction method of cylindrical self-sinking underground space structure
KR20210002947A (en) Two-side semicircle arch type leading pipe and structure of non-excavation type tunnel using thereof and method of constructing thereof
JP2004218378A (en) Removing method for existing pile
JP2607966B2 (en) Expanded connecting wall construction method
CN113026688B (en) System for expanding piles to form wall by using foundation rocks at bottom of concrete guide wall foundation
CN114657998B (en) Subway station deep foundation pit retaining structure and construction method thereof
KR102608601B1 (en) Sheet non excavation method for drilling a tunnel having a file reinforcing structure
KR102048831B1 (en) Non-excavation type tunnel structure using steel pipe loof and leading pipe and method of constructing thereof

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant