CN110593561B CN201910990903.1A CN201910990903A CN110593561B CN 110593561 B CN110593561 B CN 110593561B CN 201910990903 A CN201910990903 A CN 201910990903A CN 110593561 B CN110593561 B CN 110593561B
Authority
CN
China
Prior art keywords
square tube
clamping
clamping part
connecting end
tube body
Prior art date
Legal status (The legal status is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the status listed.)
Active
Application number
CN201910990903.1A
Other languages
Chinese (zh)
Other versions
CN110593561A (en
Inventor
钱卫东
姜磊
庞娇
Current Assignee (The listed assignees may be inaccurate. Google has not performed a legal analysis and makes no representation or warranty as to the accuracy of the list.)
Tianjin Dongxin New Material Technology Co ltd
Original Assignee
Tianjin Dongxin New Material Technology Co ltd
Priority date (The priority date is an assumption and is not a legal conclusion. Google has not performed a legal analysis and makes no representation as to the accuracy of the date listed.)
Filing date
Publication date
Application filed by Tianjin Dongxin New Material Technology Co ltd filed Critical Tianjin Dongxin New Material Technology Co ltd
Priority to CN201910990903.1A priority Critical patent/CN110593561B/en
Publication of CN110593561A publication Critical patent/CN110593561A/en
Application granted granted Critical
Publication of CN110593561B publication Critical patent/CN110593561B/en
Active legal-status Critical Current
Anticipated expiration legal-status Critical

Links

Classifications

    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/001Corner fastening or connecting means for forming or stiffening elements
    • EFIXED CONSTRUCTIONS
    • E04BUILDING
    • E04GSCAFFOLDING; FORMS; SHUTTERING; BUILDING IMPLEMENTS OR AIDS, OR THEIR USE; HANDLING BUILDING MATERIALS ON THE SITE; REPAIRING, BREAKING-UP OR OTHER WORK ON EXISTING BUILDINGS
    • E04G17/00Connecting or other auxiliary members for forms, falsework structures, or shutterings
    • E04G17/06Tying means; Spacers ; Devices for extracting or inserting wall ties
    • E04G17/065Tying means, the tensional elements of which are threaded to enable their fastening or tensioning
    • E04G17/0655Tying means, the tensional elements of which are threaded to enable their fastening or tensioning the element consisting of several parts
    • E04G17/0657Tying means, the tensional elements of which are threaded to enable their fastening or tensioning the element consisting of several parts fully recoverable

Landscapes

  • Engineering & Computer Science (AREA)
  • Architecture (AREA)
  • Mechanical Engineering (AREA)
  • Civil Engineering (AREA)
  • Structural Engineering (AREA)
  • Joining Of Building Structures In Genera (AREA)
  • Mutual Connection Of Rods And Tubes (AREA)

Abstract

The invention discloses a screw type clamp for a steel frame template, which comprises a connecting square tube, and a first clamping mechanism and a second clamping mechanism which are oppositely arranged at two ends of the connecting square tube; the connecting square tube comprises a connecting square tube body, one end of the connecting square tube body is fixedly provided with a fastening mechanism, and three groups of connecting holes are formed in the opposite tube wall of the other end of the connecting square tube body at equal intervals; the first clamping mechanism comprises a square tubular first connecting end, a first mounting hole and a first clamping part, the inner side of the first clamping part is inwards bent into an arc shape, and the tail end of the arc shape inwards protrudes to form a first flange; the second clamping mechanism comprises a square tube-shaped second connecting end, a second mounting hole and a second clamping part, the inner side of the second clamping part is inwards bent to be arc-shaped, and the tail end of the arc-shaped part inwards protrudes to form a second flange. The invention has high universality, and can realize the fixed connection of the traditional aluminum alloy frame and the novel steel frame through two mounting modes.

Description

Screw fixture for steel frame template
Technical Field
The invention belongs to the technical field of building template quick-release systems, and particularly relates to a screw type clamp for a steel frame template.
Background
The building form is a temporary supporting structure, which is manufactured according to the design requirement, so that the concrete structure and the components are formed according to the specified position and geometric dimension, the correct position of the concrete structure and the components is kept, and the self weight of the building form and the external load acted on the building form are borne.
The building template structure for the construction of the cast-in-place concrete structural engineering mainly comprises a panel, a supporting structure and connecting fittings. The panel is a bearing plate directly contacted with the newly poured concrete; the supporting structure is a temporary structure for supporting the panel, the concrete and the construction load, so that the building template structure is firmly combined, and deformation and damage are avoided; the connection fitting is a fitting that connects the panel to the support structure as a unit.
In the traditional aluminum alloy template, the connecting fittings commonly used between aluminum alloy frames are pin-type clamps, however, the pin-type clamps are easy to loosen due to vibration and the like in the construction process, and the tightness is poor, so that the frame connecting clamps with novel structures and stronger universality are required to be developed.
Disclosure of Invention
The invention aims to provide a screw type clamp for a steel frame template, which has good tightness and strong universality.
In order to achieve the above purpose, the present invention provides the following technical solutions: the screw type clamp for the steel frame template comprises a connecting square pipe, and a first clamping mechanism and a second clamping mechanism which are oppositely arranged at two ends of the connecting square pipe; the connecting square tube comprises a connecting square tube body, one end of the connecting square tube body is fixedly provided with a fastening mechanism, and three groups of connecting holes are formed in the opposite tube wall of the other end of the connecting square tube body at equal intervals; the first clamping mechanism comprises a square pipe-shaped first connecting end, the first connecting end can be sleeved outside the connecting square pipe body, a group of first mounting holes matched with the connecting holes are formed in the pipe wall opposite to the first connecting end, a first clamping part is fixedly arranged at the bottom of the first connecting end, the inner side of the first clamping part is inwards bent to be arc-shaped, and the tail end of the arc-shaped part inwards protrudes to form a first flange; the second clamping mechanism comprises a square tube-shaped second connecting end, the second connecting end can be sleeved outside the connecting square tube body, the length of the second connecting end is larger than that of the first connecting end, a group of second mounting holes matched with the connecting holes are formed in the opposite tube wall close to the outer end of the second connecting end, second clamping portions are fixedly arranged at positions, corresponding to the second mounting holes, of the bottoms of the second connecting ends, the inner sides of the second clamping portions are inwards bent to be arc-shaped, and the tail ends of the arc-shaped portions inwards protrude to form second flanges.
Preferably, a first clamping block is arranged in the middle of the outer side of the first clamping part, and a second clamping block is arranged in the middle of the outer side of the second clamping part.
Preferably, edges of the first clamping block and the second clamping block are of a sawtooth-shaped structure.
Preferably, the fastening mechanism comprises a fastening screw fixedly arranged at one end of the connecting square tube body, and a corresponding fastening nut is arranged on the fastening screw.
Preferably, a reinforcing rib is arranged at the joint of the first connecting end and the first clamping part; the joint of the second connecting end and the second clamping part is provided with a reinforcing rib.
Preferably, the fastening screw is welded on the inner wall of one end of the connecting square tube body.
Compared with the prior art, the invention has the beneficial effects that: (1) According to the invention, firstly, the connecting square tube, the first clamping mechanism and the second clamping mechanism are respectively pre-fixed through screws, then, after the relative positions of the clamp and the frame are adjusted to clamp the frame, the side face is further fastened through the fastening screw rod and the fastening nut to complete the fixed connection process, so that the tightness is good, and meanwhile, the disassembly is also convenient; (2) The invention has two mounting modes, can realize the fixed connection of the traditional aluminum alloy frame and the novel steel frame at the same time, and has high universality.
Drawings
FIG. 1 is a schematic diagram of an exploded construction of the present invention;
FIG. 2 is a schematic view of the structure of the present invention in a use state;
fig. 3 is a schematic structural view of another use state of the present invention.
In the figure: 1. the square tube body is connected; 2. a connection hole; 3. fastening a screw; 4. a first connection end; 5. a first mounting hole; 6. a first clamping part; 7. a first flange; 8. a first clamping block; 9. a second connection end; 10. a second mounting hole; 11. a second clamping part; 12. a second clamping block; 13. a second flange; 14. and fastening the screw cap.
Detailed Description
A preferred embodiment of the present invention will be described with reference to the accompanying drawings, in which technical solutions of the preferred embodiment of the present invention are clearly and completely described.
Referring to fig. 1, the present invention includes a connecting square tube, and a first clamping mechanism and a second clamping mechanism which are oppositely installed at two ends of the connecting square tube.
The connecting square tube comprises a connecting square tube body 1, a fastening mechanism is fixedly arranged at one end of the connecting square tube body 1, and three groups of connecting holes 2 are formed in the opposite tube wall of the other end of the connecting square tube body 1 at equal intervals.
The first clamping mechanism comprises a square pipe-shaped first connecting end 4, the first connecting end 4 can be sleeved outside the connecting square pipe body 1, a group of first mounting holes 5 matched with the connecting holes 2 are formed in the opposite pipe walls of the first connecting end 4, a first clamping part 6 is fixedly arranged at the bottom of the first connecting end 4, the inner side of the first clamping part 6 is inwards bent to be arc-shaped, and the tail end of the arc-shaped tail end inwards protrudes to form a first flange 7.
The second clamping mechanism comprises a square tube-shaped second connecting end 9, the second connecting end 9 can be sleeved outside the connecting square tube body 1, the length of the second connecting end 9 is greater than that of the first connecting end 4, a group of second mounting holes 10 matched with the connecting holes 2 are formed in the opposite tube wall close to the outer end of the second connecting end 4, a second clamping part 11 is fixedly arranged at the bottom of the second connecting end 9 and in a position corresponding to the second mounting holes 10, the inner side of the second clamping part 11 is inwards bent into an arc, and the tail end of the arc inwards protrudes to form a second flange 13.
In this embodiment, a first clamping block 8 is disposed in the middle of the outer side of the first clamping portion 6, and a second clamping block 12 is disposed in the middle of the outer side of the second clamping portion 11; the edges of the first clamping block 8 and the second clamping block 12 are of a saw-tooth structure.
In this embodiment, the fastening mechanism includes a fastening screw 3 fixedly disposed at one end of the square tube body 1, and a corresponding fastening nut 14 is disposed on the fastening screw 3.
In this embodiment, a reinforcing rib is disposed at the connection position between the first connection end 4 and the first clamping portion 6; the joint of the second connecting end 9 and the second clamping part 11 is provided with a reinforcing rib.
In this embodiment, the fastening screw 3 is welded to an inner wall of one end of the square pipe body 1.
Referring to fig. 2, the installation method of the present invention comprises: the first connecting end 4 and the second connecting end 9 are respectively sleeved on the connecting square pipe body 1 for pre-fixing; then install this fixture on a set of steel frame that sets up relatively, first flange 7 and second flange 13 block respectively in the draw-in groove of steel frame both sides, adjust fixture makes first chucking portion 6 and second chucking portion 11 fix the steel frame chucking, then fix through the internal rotation screw in first mounting hole 5, second mounting hole 10 and connecting hole 2, the rethread fastening screw 3 and fastening nut 14 carry out further fastening from the side, accomplish fixed connection process.
Referring to fig. 3, another application method of the present invention is that the present invention can be used for a conventional aluminum alloy frame, and is different from the above-mentioned installation method in that the first connection end 4 and the second connection end 9 are reversely sleeved on the connection square tube body 1, that is, the first clamping block 8 and the second clamping block 12 of the clamping apparatus are installed oppositely, the first clamping portion 6 and the second clamping portion 11 cooperate with the serrated rough surfaces at the edges of the first clamping block 8 and the second clamping block 12 to clamp the aluminum alloy frame, and the fastening manner is the same as the above-mentioned method.
According to the invention, firstly, the connecting square tube, the first clamping mechanism and the second clamping mechanism are respectively pre-fixed through screws, then, after the relative positions of the clamp and the frame are adjusted to clamp the frame, the side face is further fastened through the fastening screw rod and the fastening nut to complete the fixed connection process, so that the tightness is good, and meanwhile, the disassembly is also convenient; the invention has two mounting modes, can realize the fixed connection of the traditional aluminum alloy frame and the novel steel frame at the same time, and has high universality.
Although embodiments of the present invention have been shown and described, it will be understood by those skilled in the art that various changes, modifications, substitutions and alterations can be made therein without departing from the principles and spirit of the invention, the scope of which is defined in the appended claims and their equivalents.

Claims (3)

1. The utility model provides a screw fixture for steel frame template which characterized in that: the device comprises a connecting square tube, a first clamping mechanism and a second clamping mechanism which are oppositely arranged at two ends of the connecting square tube;
The connecting square tube comprises a connecting square tube body (1), one end of the connecting square tube body (1) is fixedly provided with a fastening mechanism, and three groups of connecting holes (2) are formed in the opposite tube wall of the other end of the connecting square tube body (1) at equal intervals;
The first clamping mechanism comprises a square pipe-shaped first connecting end (4), the first connecting end (4) can be sleeved outside the connecting square pipe body (1), a group of first mounting holes (5) matched with the connecting holes (2) are formed in the opposite pipe walls of the first connecting end (4), a first clamping part (6) is fixedly arranged at the bottom of the first connecting end (4), the inner side of the first clamping part (6) is inwards bent into an arc shape, and the tail end of the arc shape inwards protrudes to form a first flange (7);
The second clamping mechanism comprises a square tube-shaped second connecting end (9), the second connecting end (9) can be sleeved outside the connecting square tube body (1), the length of the second connecting end (9) is larger than that of the first connecting end (4), a group of second mounting holes (10) matched with the connecting holes (2) are formed in the opposite tube wall close to the outer end of the second connecting end (9), a second clamping part (11) is fixedly arranged at the position, corresponding to the second mounting holes (10), of the bottom of the second connecting end (9), the inner side of the second clamping part (11) is inwards bent into an arc shape, and the tail end of the arc shape inwards protrudes to form a second flange (13);
The middle part of the outer side of the first clamping part (6) is provided with a first clamping block (8), and the middle part of the outer side of the second clamping part (11) is provided with a second clamping block (12);
The edges of the first clamping block (8) and the second clamping block (12) are of a saw-tooth structure;
The fastening mechanism comprises a fastening screw rod (3) fixedly arranged at one end of the square pipe connecting body (1), and a corresponding fastening nut (14) is arranged on the fastening screw rod (3).
2. The screw-type clamp for steel frame templates according to claim 1, wherein: the connection part of the first connecting end (4) and the first clamping part (6) is provided with a reinforcing rib; the joint of the second connecting end (9) and the second clamping part (11) is provided with a reinforcing rib.
3. The screw-type clamp for steel frame templates according to claim 1, wherein: the fastening screw (3) is welded on the inner wall of one end of the connecting square tube body (1).
CN201910990903.1A 2019-10-18 2019-10-18 Screw fixture for steel frame template Active CN110593561B (en)

Priority Applications (1)

Application Number Priority Date Filing Date Title
CN201910990903.1A CN110593561B (en) 2019-10-18 2019-10-18 Screw fixture for steel frame template

Applications Claiming Priority (1)

Application Number Priority Date Filing Date Title
CN201910990903.1A CN110593561B (en) 2019-10-18 2019-10-18 Screw fixture for steel frame template

Publications (2)

Publication Number Publication Date
CN110593561A CN110593561A (en) 2019-12-20
CN110593561B true CN110593561B (en) 2024-05-10

Family

ID=68850763

Family Applications (1)

Application Number Title Priority Date Filing Date
CN201910990903.1A Active CN110593561B (en) 2019-10-18 2019-10-18 Screw fixture for steel frame template

Country Status (1)

Country Link
CN (1) CN110593561B (en)

Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3020742U (en) * 1995-07-18 1996-02-06 義晴 内橋 Formwork clamp
JP2004360391A (en) * 2003-06-06 2004-12-24 Teruaki Nishioka Connecting tool set, structure, and metallic pipe connecting method
JP2008128297A (en) * 2006-11-17 2008-06-05 Osaka Rasenkan Kogyo Kk Clamp for flange type pipe joint
CN102031865A (en) * 2010-12-03 2011-04-27 蓟县新兴模板技术服务部 Steel frame template and assembly method thereof
US8496421B1 (en) * 2010-11-09 2013-07-30 Christopher C. Burton Ferrule lock nuts
CN108166757A (en) * 2018-03-14 2018-06-15 沭阳县福阳木业制品厂 A kind of bindiny mechanism of building template
KR20180065043A (en) * 2016-12-06 2018-06-18 주식회사 정우비엔씨 Reinforced Connection device and method
CN208137431U (en) * 2017-11-09 2018-11-23 天津市东文模架施工技术有限公司 A kind of building template connector
CN211229531U (en) * 2019-10-18 2020-08-11 天津市东鑫新材料科技有限公司 Screw type fixture for steel frame template

Patent Citations (9)

* Cited by examiner, † Cited by third party
Publication number Priority date Publication date Assignee Title
JP3020742U (en) * 1995-07-18 1996-02-06 義晴 内橋 Formwork clamp
JP2004360391A (en) * 2003-06-06 2004-12-24 Teruaki Nishioka Connecting tool set, structure, and metallic pipe connecting method
JP2008128297A (en) * 2006-11-17 2008-06-05 Osaka Rasenkan Kogyo Kk Clamp for flange type pipe joint
US8496421B1 (en) * 2010-11-09 2013-07-30 Christopher C. Burton Ferrule lock nuts
CN102031865A (en) * 2010-12-03 2011-04-27 蓟县新兴模板技术服务部 Steel frame template and assembly method thereof
KR20180065043A (en) * 2016-12-06 2018-06-18 주식회사 정우비엔씨 Reinforced Connection device and method
CN208137431U (en) * 2017-11-09 2018-11-23 天津市东文模架施工技术有限公司 A kind of building template connector
CN108166757A (en) * 2018-03-14 2018-06-15 沭阳县福阳木业制品厂 A kind of bindiny mechanism of building template
CN211229531U (en) * 2019-10-18 2020-08-11 天津市东鑫新材料科技有限公司 Screw type fixture for steel frame template

Also Published As

Publication number Publication date
CN110593561A (en) 2019-12-20

Similar Documents

Publication Publication Date Title
CN213927506U (en) Connecting and locking device for building template
CN110593561B (en) Screw fixture for steel frame template
CN211229531U (en) Screw type fixture for steel frame template
CN218292765U (en) Cross steel column and circular steel tube fixing clamp assembly
CN110593562B (en) Steel frame shaping building template system
CN206815540U (en) A kind of positioner for concrete structure built-in fitting
CN113482155A (en) Assembly type building node connection structure
CN204646890U (en) Photovoltaic bracket multipurpose connects pipe box
CN219471512U (en) Wall connecting device for scaffold
CN219637823U (en) Expansion joint department stagnant water copper reinforcement instrument
CN219175464U (en) Steel connection structure with multimode connection function
CN217680207U (en) Ultrahigh aluminum square tube mounting connecting piece
WO2022247376A1 (en) Easy-to-fold assembled photovoltaic support and use method
CN219569575U (en) Adjustable anchor ear structure for reinforcing vertical member template
CN218323203U (en) Steel pipe concrete connection structure for building
CN211548796U (en) Stagnant water bolt assembly
CN204001742U (en) A kind of combination type heat insulating template fastener
CN216810312U (en) Thin-wall steel beam connecting structure
CN219060844U (en) Cutting-free outer frame wall connecting piece for full concrete outer wall
CN220828027U (en) Wall-penetrating wall connecting piece
CN217128628U (en) Assembled wallboard installed part
CN210738064U (en) A outrigger attachment device for tall and big space
CN218643875U (en) Pull rod for building outer frame
CN218933834U (en) Tool type supporting structure for post-pouring belt
CN215881509U (en) 90-degree bolt tightening device

Legal Events

Date Code Title Description
PB01 Publication
PB01 Publication
SE01 Entry into force of request for substantive examination
SE01 Entry into force of request for substantive examination
GR01 Patent grant
GR01 Patent grant